0% found this document useful (0 votes)
154 views53 pages

Project Scheduling: Prof. DR Amir Azam Khan

Engineering management
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
154 views53 pages

Project Scheduling: Prof. DR Amir Azam Khan

Engineering management
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 53

Project Scheduling

Prof. Dr Amir Azam Khan


Department of Mechanical and Manufacturing Engineering
Universiti Malaysia Sarawak
Chapter 8 Scheduling, PERT, Critical Path Analysis 2
INTRODUCTION
Schedule converts action plan into operating
time table
Basis for monitoring and controlling project
Scheduling more important in projects than
in production, because unique nature
Sometimes customer specified/approved
requirement-e.g: JKR projects
Based on Work Breakdown Structure (WBS)
Chapter 8 Scheduling, PERT, Critical Path Analysis 3
NETWORK TECHNIQUES
PERT
CPM
-Program Evaluation and
Review Technique
- developed by the US
Navy with Booz
Hamilton Lockheed
- on the Polaris
Missile/Submarine
program 1958
Critical Path Method
Developed by El Dupont
for Chemical Plant
Shutdown Project- about
same time as PERT
Both use same calculations, almost similar
Main difference is probabilistic and deterministic in time estimation
Gantt Chart also used in scheduling
Chapter 8 Scheduling, PERT, Critical Path Analysis 4
Graphical portrayal of activities and events
Shows dependency relationships between
tasks/activities in a project
Clearly shows tasks that must precede
(precedence) or follow (succeeding) other tasks
in a logical manner
Clear representation of plan a powerful tool
for planning and controlling project
NETWORK
Chapter 8 Scheduling, PERT, Critical Path Analysis 5
Example of Simple Network
Survey
Chapter 8 Scheduling, PERT, Critical Path Analysis 6
Example of Network
More Complex

Scheduling, PERT, Critical Path Analysis 7
DEFINITION OF TERMS IN A NETWORK
Activity : any portion of project (task) which is required
by the project, use resources and consumes
time may involve labor, paper work,
contractual negotiations, machinery operations
Activity on Arrow (AOA) shown as arrow,
Activity on Node (AON), shown as node
Event : beginning or ending points of one or more
activities, instantaneous point in time, also
called nodes

Network : Combination of all project activities and the events
ACTIVITY
PRECEEDING
SUCCESSOR
EVENT
Chapter 8 Scheduling, PERT, Critical Path Analysis 8
Emphasis on Logic in Network Construction
Construction of network should be based on logical or
technical dependencies among activities
Example - before start of activity Approve Drawing
the activity Prepare Drawing must be completed
Common error build network on the basis of time
logic (a feeling for proper sequence ) see example
below

WRONG !!!
CORRECT
Chapter 8 Scheduling, PERT, Critical Path Analysis 9
Example 1- A simple network
Consider the list of four activities for making a simple product:
Activity Description Immediate
predecessors

A Buy Plastic Body -

B Design Component -

C Make Component B

D Assemble product A,C
Immediate predecessors for a particular activity are the activities
that, when completed, enable the start of the activity in question.
Chapter 8 Scheduling, PERT, Critical Path Analysis 10

Sequence of activities
Can start work on activities A and B anytime, since
neither of these activities depend upon the
completion of prior activities.
Activity C cannot be started until activity B has been
completed
Activity D cannot be started until both activities A
and C have been completed.
The graphical representation (next slide) is referred to
as the PERT/CPM network
Chapter 8 Scheduling, PERT, Critical Path Analysis 11
Network of Four Activities
1 3 4
2
A
B
C
D
Arcs indicate project activities
Nodes correspond to the beginning
and ending of activities
Chapter 8 Scheduling, PERT, Critical Path Analysis 12
Example 2
Develop the network for a project with following activities and
immediate predecessors:

Activity Immediate
predecessors
A -

B -

C B

D A, C

E C

F C

G D,E,F
Try to do for the first five (A,B,C,D,E) activities
Chapter 8 Scheduling, PERT, Critical Path Analysis 13
Network of first five activities
1 3 4
2
A
B
C
D
5
E
We need to introduce
a dummy activity
Chapter 8 Scheduling, PERT, Critical Path Analysis 14
Note how the network correctly identifies D, E, and F as the
immediate predecessors for activity G.

Dummy activities is used to identify precedence relationships
correctly and to eliminate possible confusion of two or more
activities having the same starting and ending nodes

Dummy activities have no resources (time, labor, machinery, etc)
purpose is to PRESERVE LOGIC of the network
Network of Seven Activities
1 3 4
2
A
B
C
D
5
E
7
6
F
G
dummy
Chapter 8 Scheduling, PERT, Critical Path Analysis 15
EXAMPLES OF THE USE OF DUMMYACTIVITY
Dummy

RIGHT

1

1

2

Activity c not
required for e

a

b

c

d

e

a

b

c

d

e

WRONG
!!!

RIGHT



Network concurrent activities

1

2

1

2

3

a

WRONG!!!
a

b

b

WRONG !
RIGHT
Chapter 8 Scheduling, PERT, Critical Path Analysis 16
1
1
2
2
3
3
4
a d
b e
c f
a d
b
e
f c
WRONG!!! RIGHT!!!

a precedes d.
a and b precede e,
b and c precede f (a does not precede f)
Chapter 8 Scheduling, PERT, Critical Path Analysis 17
Scheduling with activity time
Activity Immediate Completion
predecessors Time (week)
A - 5
B - 6
C A 4
D A 3
E A 1
F E 4
G D,F 14
H B,C 12
I G,H 2
Total 51
This information indicates that the total time required to complete
activities is 51 weeks. However, we can see from the network that several
of the activities can be conducted simultaneously (A and B, for example).
Network
Chapter 8 Scheduling, PERT, Critical Path Analysis 18
1
3
4
2
5
7
6
D 3 weeks

Chapter 8 Scheduling, PERT, Critical Path Analysis 19
Earliest start & earliest finish time

We are interested in the longest path through the
network, i.e., the critical path.

Starting at the networks origin (node 1) and using a
starting time of 0, we compute an earliest start (ES) and
earliest finish (EF) time for each activity in the network.

The expression EF = ES + t can be used to find the
earliest finish time for a given activity.
For example, for activity A, ES = 0 and t = 5; thus the
earliest finish time for activity A is
EF = 0 + 5 = 5
Chapter 8 Scheduling, PERT, Critical Path Analysis 20
Arc with ES & EF time
1
2
Activity
ES = earliest start time
EF = earliest finish time
t = expected activity
time
Chapter 8 Scheduling, PERT, Critical Path Analysis 21
Network with ES & EF time
1
3
4
2
5
7
6
D[5,8]
3
Earliest start time rule:
The earliest start time for an activity leaving a particular node is equal to
the largest of the earliest finish times for all activities entering the node.
Chapter 8 Scheduling, PERT, Critical Path Analysis 22

To find the critical path we need a backward pass calculation.

Starting at the completion point (node 7) and using a latest
finish time (LF) of 26 for activity I, we trace back through the
network computing a latest start (LS) and latest finish time
for each activity

The expression LS = LF t can be used to calculate latest start
time for each activity. For example, for activity I, LF = 26 and t
= 2, thus the latest start time for activity I is
LS = 26 2 = 24
Latest start & latest finish time
Chapter 8 Scheduling, PERT, Critical Path Analysis 23
Activity, duration, ES, EF, LS, LF
2
3
Activity
ES = earliest start time
EF = earliest finish time
LF = latest finish time
LS = latest start time
Chapter 8 Scheduling, PERT, Critical Path Analysis 24
Network with LS & LF time
1
3
4
2
5
7
6
D[5,8]
3[7,10]
Latest finish time rule:
The latest finish time for an activity entering a particular node is equal to
the smallest of the latest start times for all activities leaving the node.
Chapter 8 Scheduling, PERT, Critical Path Analysis 25
Slack or Free Time or Float
Slack is the length of time an activity can be delayed without affecting the
completion date for the entire project.
For example, slack for C = 3 weeks, i.e Activity C can be delayed up to 3
weeks
(start anywhere between weeks 5 and 8).

ES
5
LS
8
EF
9
LF-EF = 12 9 =3
LS-ES = 8 5 = 3
LF-ES-t = 12-5-4 = 3
LF
12
2
3
Chapter 8 Scheduling, PERT, Critical Path Analysis 26
Activity schedule for our example
Activity Earliest
start (ES)
Latest
start (LS)
Earliest
finish (EF)
Latest
finish (LF)
Slack
(LS-ES)
Critical
path
A 0 0 5 5 0 Yes
B 0 6 6 12 6
C 5 8 9 12 3
D 5 7 8 10 2
E 5 5 6 6 0 Yes
F 6 6 10 10 0 Yes
G 10 10 24 24 0 Yes
H 9 12 21 24 3
I 24 24 26 26 0 Yes
Chapter 8 Scheduling, PERT, Critical Path Analysis 27
IMPORTANT QUESTIONS
What is the total time to complete the project?
26 weeks if the individual activities are completed on schedule.

What are the scheduled start and completion times for each activity?
ES, EF, LS, LF are given for each activity.

What activities are critical and must be completed as scheduled in order
to keep the project on time?
Critical path activities: A, E, F, G, and I.

How long can non-critical activities be delayed before they cause a delay
in the projects completion time
Slack time available for all activities are given.
Chapter 8 Scheduling, PERT, Critical Path Analysis 28
Importance of Float (Slack) and Critical Path
1. Slack or Float shows how much allowance each activity has, i.e how
long it can be delayed without affecting completion date of project

2. Critical path is a sequence of activities from start to finish with zero
slack. Critical activities are activities on the critical path.

3. Critical path identifies the minimum time to complete project

4. If any activity on the critical path is shortened or extended, project
time will be shortened or extended accordingly
Chapter 8 Scheduling, PERT, Critical Path Analysis 29
5. So, a lot of effort should be put in trying to control activities along
this path, so that project can meet due date. If any activity is
lengthened, be aware that project will not meet deadline and some
action needs to be taken.

6. If you can spend resources to speed up some activity, do so only for
critical activities.

7. Dont waste resources on non-critical activity, it will not shorten the
project time.

8. If resources can be saved by lengthening some activities, do so for
non-critical activities, up to limit of float.

9. Total Float belongs to the path

Importance of Float (Slack) and Critical Path (cont)
Chapter 8 Scheduling, PERT, Critical Path Analysis 30
PERT For Dealing With Uncertainty
So far, times can be estimated with relative certainty, confidence

For many situations this is not possible, e.g Research, development,
new products and projects etc.

Use 3 time estimates
m= most likely time estimate, mode.
a = optimistic time estimate,
b = pessimistic time estimate, and

Expected Value (TE) = (a + 4m + b) /6
Variance (V) = ( ( b a) / 6 )
2

Std Deviation () = SQRT (V)

Chapter 8 Scheduling, PERT, Critical Path Analysis 31
Precedences And Project Activity Times
Immediate Optimistic Most Likely Pessimistic EXP Var S.Dev
Activity Predecessor Time Time Time TE V o

a - 10 22 22 20 4 2
b - 20 20 20 20 0 0
c - 4 10 16 10 4 2
d a 2 14 32 15 25 5
e b,c 8 8 20 10 4 2
f b,c 8 14 20 14 4 2
g b,c 4 4 4 4 0 0
h c 2 12 16 11 5.4 2.32
I g,h 6 16 38 18 28.4 5.33
j d,e 2 8 14 8 4 2





Chapter 8 Scheduling, PERT, Critical Path Analysis 32
The complete network

2

6

1

3

7

4

5

a
(20,4)

d
(15,25)

e
(10,4)

f
(14,4)

j
(8,4)

i
(18,28.4)

g
(4,0)

h
(11,5.4)

c
(10,4)

b
(20,0)
Chapter 8 Scheduling, PERT, Critical Path Analysis 33
The complete Network (Critical Time)
2
6
1 3
7
4
5
b
(20,0)
d
(15,25)
e
(10,4)
f
(14,4)
j
(8,4)
i
(18,28.4)
g
(4,0)
h
(11,5.4)
c
(10,4)
CRIT. TIME = 43
EF=20 35
43
24
10
20
a
(20,4)
Chapter 8 Scheduling, PERT, Critical Path Analysis 34
Critical Path Analysis (PERT)
Activity LS ES Slacks Critical ?
a 0 0 0 Yes

b 1 0 1
c 4 0 4
d 20 20 0 Yes
e 25 20 5
f 29 20 9
g 21 20 1
h 14 10 4
i 25 24 1
j 35 35 0 Yes
Chapter 8 Scheduling, PERT, Critical Path Analysis 35
Assume, PM promised to complete the project in the fifty days.
What are the chances of meeting that deadline?
Calculate Z (Factor of Variance), where D = Deadline, S = Scheduled
Time including variance

Z = (D-S) / \V

Example,
D = 50; S(Scheduled time) = 20+15+8 =43; V =
(4+25+4) =33
Z = (50 43) / 5.745
= 1.22 standard deviations.

The probability value of Z = 1.22, is 0.888






Chapter 8 Scheduling, PERT, Critical Path Analysis 36
What deadline are you 95% sure of meeting


Z value associated with 0.95 is 1.645


D = S + 5.745 (1.645)
= 43 + 9.45
= 52.45 days


Thus, there is a 95 percent chance of finishing the
project by 52.45 days.
Chapter 8 Scheduling, PERT, Critical Path Analysis 37
Comparison Between CPM and PERT
CPM PERT
1 Uses network, calculate float or slack,
identify critical path and activities,
guides to monitor and controlling
project

Same as CPM
2 Uses one value of activity time Requires 3 estimates of activity time
Calculates mean and variance of time
3 Used where times can be estimated
with confidence, familiar activities
Used where times cannot be estimated
with confidence.
Unfamiliar or new activities
4 Minimizing cost is more important Meeting time target or estimating
percent completion is more important
5 Example: construction projects,
building one off machines, ships, etc
Example: Involving new activities or
products, research and development
etc
Example Question
Chapter 8 Scheduling, PERT, Critical Path Analysis 38
Question: The following table gives important parameters about
different activities to be carried out in a project. Please develop the
network, show the Earliest and Latest start as well as Earliest and
Latest finish, locate the Critical Path and decide upon Critical and Non
Critical Activities. What is the total Project Time?
Activity Prerequisite Time (weeks)
A - 5
B - 6
C A 4
D A 3
E A 2
F E 6
G D 15
H B, C 18
I F, G, H 4
Chapter 8 Scheduling, PERT, Critical Path Analysis 39
BENEFITS OF CPM / PERT NETWORK
Consistent framework for planning, scheduling,
monitoring, and controlling project.

Shows interdependence of all tasks, work packages, and
work units.

Helps proper communications between departments and
functions.

Determines expected project completion date.

Identifies so-called critical activities, which can delay the
project completion time.


Chapter 8 Scheduling, PERT, Critical Path Analysis 40
Identified activities with slacks that can be delayed for
specified periods without penalty, or from which
resources may be temporarily borrowed

Determines the dates on which tasks may be started or
must be started if the project is to stay in schedule.

Shows which tasks must be coordinated to avoid resource
or timing conflicts.

Shows which tasks may run in parallel to meet project
completion date


BENEFITS OF CPM / PERT NETWORK (cont.)
Chapter 8 Scheduling, PERT, Critical Path Analysis 41
Gantt Charts
Since 1917; Useful for showing work vs time in form of bar charts
e.g.
Can draw directly or from CPM/PERT network
Chapter 8 Scheduling, PERT, Critical Path Analysis 42
Modified PERT/CPM diagram from network

1
1
1
4
3
3
2
5
7
4
3
6
e
f
a d
b
c dummy
h
0 5 10 15 20 25
30
35 40 45
Legend

| Scheduled Start
| Scheduled Finish
Actual Progress
Unavailable
A Current Date
^ Milestone
Scheduled
+ Milestone
Achieved

Days
Chapter 8 Scheduling, PERT, Critical Path Analysis 43
Gantt Chart
Chapter 8 Scheduling, PERT, Critical Path Analysis 44
Chapter 8 Scheduling, PERT, Critical Path Analysis 45
Chapter 8 Scheduling, PERT, Critical Path Analysis 46
Gantt Charts and CPM/PERT Networks
Gantt Charts:

Even though a lot of info, easy to read and , understand to
monitor and follow progress.

Not very good for logical constraints

Should be used to COMPLEMENT networks, not replace

Chapter 8 Scheduling, PERT, Critical Path Analysis 47







RESOURCE ANALYSIS AND SCHEDULING
Ability to carry out projects depend on the availability
of resources

Analyze resource implication
-How requirements can be met and changes needed

Use resources efficiently

Use network to give information about time, resources
and cost
Chapter 8 Scheduling, PERT, Critical Path Analysis 48
Activities D, E, F, G and H require fitters.
Construct a bar chart with activities at their EST indicating
person required and total float.
0 5 10 15 20
H
G
F
E
D
4 4 4 4 4 4 4 4 4 4 4 4
2 2 2 2
2 2
2 2 2 2 2 2
2 2 2 2 2 2 2 2
Time
A
c
t
i
v
i
t
y

Add up across all activities to get the total number of men
required.
Chapter 8 Scheduling, PERT, Critical Path Analysis 49
Convert the bar chart to a histogram
Shows: i) Variation from week to week (fitters)
ii) Maximum number of person required (12) during
week 5-6
Examine resource implication.
0 5 10 15 20
1
2
3
4
5
6
7
8
9
10
11
12
13
14
T
o
t
a
l

n
u
m
b
e
r

o
f

m
a
n

r
e
q
u
i
r
e
d
Time
Resource analysis before scheduling
Chapter 8 Scheduling, PERT, Critical Path Analysis 50
Example
If only 8 fitters are available at any period during the projects:

New bar chart:
0 5 10 15 20
H
G
F
E
D
4 4 4 4 4 4 4 4 4 4 4 4
2 2 2 2
2 2
2 2 2 2 2 2
2 2 2 2 2 2 2 2
Time
A
c
t
i
v
i
t
y

Chapter 8 Scheduling, PERT, Critical Path Analysis 51
Additional Restriction no fitters available until the end of
week 5.

Revised Schedule:
0 5 10 15 20
H
G
F
E
D
4 4 4 4 4 4 4 4 4 4 4 4
2 2 2 2
2 2
2 2 2 2 2 2
2 2 2 2 2 2 2 2
Time
A
c
t
i
v
i
t
y

Chapter 8 Scheduling, PERT, Critical Path Analysis 52
Resource constraints relates to:
1. Variations in resource requirements
2. Resource availability

Smaller variations:
1. Easier control of the job
2. Better utilization of resources

Big variations:
1. Frequent moving of manpower
2. Require close control
3. Affect efficiency
Chapter 8 Scheduling, PERT, Critical Path Analysis 53
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18
T
o
t
a
l

n
u
m
b
e
r

o
f

m
a
n

r
e
q
u
i
r
e
d
Time
Histogram showing large resource variations

You might also like