Project Management 0
Project Management 0
Sri Sarathi
Institute of Engineering & Technology
Gantt chart /& Mail stone chart CPM PERT & Probabilistic Activity Times
Project Crashing and Time-Cost Trade-off Describe how CPM / PERT have developed and merged together to provide a useful technique for managing projects.
What is Project?
Definition:
Application:
Project Characteristics
General purpose
High labor skills required
Project Elements
Objective of Project Management Scope (Limitations / Boundary) Contract requirements Schedules Resources (Physical) Personnel (Psychological) Control Risk and problem analysis
EXAMPLES OF PROJECTS
Examples of Projects
Building construction
Examples of Projects
New! Improved!
9 Nude Sandalfoot Medium to Tall (B)
No nonsense
Examples of Projects
Examples of Projects
Examples of Projects
Building construction New product introduction Training seminar Research project S/W development Planning concert, football games, or basketball tournaments
Project Scope
Scope statement
Statement of work
Good motivators Stand up to exert when necessary Support team members Encourage new ideas
Project Team
made up of individuals from various areas and departments within a company
Matrix Organization
a team structure with members from functional areas, depending on skills required
Mechanism of Planning
Identify tasks and subtasks -- deliverables Lowest element stand alone work package
Identify tasks relationship Identify possible risks Estimate work packages (people, time, etc.) Create initial schedule Iterate plan (Procedure) Document
Allocate resources
To complete project within elapsed time To ensure optimum utilization of available resources without delay To complete a project with a minimum of capital investment.
Scheduling
Scheduling
Controlling
PROJECT PLANNING
Project Planning
Establishing objectives Defining project Creating work breakdown structure (WBS) Determining resources Forming organization
Lists the WHAT of a Project Begins with Finished Project Consists of Tree Chart, with Each Branch Listing the WHATs at that Level
Then List Each Task that Must Be Completed to Accomplish the WHAT
Start at top, progressively break work down into work packages Roll up the packages for bottom up estimating Packages give clear work assignments
Splits work into manageable, logical packages Make sure packages can be tested for completeness
- Criteria
- Visit Locations
10
- Closing
Project Organization
Project Organization
Often temporary structure Uses specialists from entire company Headed by project manager Coordinates activities Monitors schedule & costs Eng. Eng. Permanent Mkt. Acct. structure called matrix organization
Mgr.
PROJECT SCHEDULING
Project Scheduling
Sequencing activities Identifying precedence relationships Determining activity times & costs Estimating material & worker requirements Determining critical activities
PROJECT CONTROL
Project Control
Periodical check list concerned with: Time management Cost management Quality management Performance management
a standard procedure for numerically measuring a projects progress, forecasting its completion date and cost and measuring schedule and budget variation
GANTT CHART
Gantt Chart
Gantt Chart was developed by
Henry Laurence Gantt (1861-1919) was a mechanical engineer and management consultant who is most famous for developing the Gantt chart in the 1910s. These Gantt charts were employed on major infrastructure projects including the Hoover Dam and Interstate highway system. He refined production control and cost control techniques.
Month 4
10
Lay foundation
Order and receive materials Build house Select paint Select carpet Finish work
3 Month
- Criteria
- Visit Locations
TASK 1-criteria 2-visit loc. 3-affordability 4-mortgage co 5-mortg lock 6-type of hse 7-real est agent 8-look for hse 9-offer, P&S 10-closing
PREDECESSOR 3 1 3 4 1 2, 6 7 5, 8 9
10
- Closing
CPM by DuPont for chemical plants In 1957 suitable for Civil & Mechanical Projects PERT by U.S. Navy for Polaris missile in 1958 consulting with M/s Booz, Allen & Hamilton
Consider precedence relationships & interdependencies Each uses a different estimate of activity times
Identify activities Determine sequence Create network Determine activity times Find critical path
Earliest & Latest start times Earliest & Latest finish times Slack or Float
Completion date? On schedule? Within budget? Probability of completing by ...? (Duration) Critical activities? Enough resources available? How can the project be finished early at the least cost?
Constructing Networks
An arrow leads from tail to head directionally A node is represented by a circle or any mathematical symbol
Node Arrow
Nodes
Task is Represented by Node as the Completion of an Activity Arrows Represent the Sequential Linkages Between Activities For Example, Node 1 is Begin, Node 2 is Complete Task 1, Node 3 is Complete Task 2
1 2 3
Task is Represented by an Arrow Bounded on Either End by a Node (Event) Each Event is Identified by a Number The Activity is Designated by the Leading Event Number and the Following Event Number - i.e. Activity 1 - 2
1 2
Represented by Dashed Arrows Show Sequential Relationships Among Tasks, but Take No time or Resources
2
Dummy Activity 2-3 indicates that both Activities 1-2 and 2-3 must be Completed before beginning Activity 3-4
4 3
Network Terms
Project: Obtain a college degree - B. Tech.
Register
1
Event (Node)
Receive degree
2
Event (Node)
Activity Relationships
Activity Relationships
Activity Relationships
2
A
1
B A & B can occur concurrently
Activity Relationships
A must be done before C & D can begin A
2
C
1
B
Activity Relationships
2
A
D
C
1
B
4
E B & C must be done before E can begin
Activity Relationships
A must be done before C & D can begin A
2
C
1
B A & B can occur concurrently
4
E B & C must be done before E can begin
Dummy Activities
Every activity must have unique pair of beginning & ending events
2
2-3
2-3
3-4
2
2-3
4
Different activities; same designation
1
Correct
1-2
2
2-3 2-4
4
4-5
2
2-3
2
2-3: Dummy activity
1
B
o
A C
q
G
s
I
Network Example
Youre a project manager for Bechtel. Construct the network.
Activity A B C D E F G H Predecessors -A A B B C D E, F
B 1
2 C
B 1 A 2
6 H
C
4
C P M Technique - foretaste
Activity oriented technique Single Time estimation Designed for repetitive projects Not Statistically analyzed Demarcates critical activities Dummy activities are not necessary Employs words like arrow diagram, nodes and floats etc Suitable for industrial settings, plant maintenance, civil construction projects etc.
A B C D E F G
A B B D C F, E
1 6 3 2 3 4 1
A B C D E F G
1 6 3 2 3 4 1
Event ID
A B C D E F G
B.6 G.1 A.1 2-3 6 7 3 1 2 E.3 3-4 D.2 5 3-5 5-6 4-6 Different paths from network: 6-7 1-2-3-4-6-7 - 15 (Critical Path)
C.3
F.4
1-2-3-5-6-7 -
13
Begin at starting event & work forward EST = 0 for starting activities
Begin at ending event & work backward LFT = Maximum EFT for ending activities
LS 0 1 7 9 11 10 12
LF 1 7 10 11 14 14 15
Slack 0 0 0 2 3 0 0
Event oriented technique Three time estimation Use of dummy activities are required representing the proper sequence A probabilistic model with uncertainty in activity duration Analyzed statistically Employs words Network diagram, events and Slack etc
CPM - One Time Estimate per Activity PERT - Three Time Estimates per Activity
to = Optimistic Time Estimate tm = Most Likely Time Estimate tp = Pessimistic Time Estimate
Activity Mean Time Estimate = te Activity Variance Estimate = Sigmae te = (to + 4tm + tp)/6
Sigmae = (tp - to )/6
Can Use Central Limit Theorem to Estimate Project Time
Ff E2
t 2 L2
A
1
C
4
G
H
I
7
B
3
E F
a
10 9 1 1 1 5 8 1 6 6
m
12 11 3 8 7 10 13 7 10 10
b
14 13 11 9 13 15 18 19 20 14
te
12 11 4 7 7 10 13 8 11 10
Sigmae
2/3 2/3 5/3 4/3 6/3 5/3 5/3 9/3 7/3 4/3
A B C D E F G H I J
1-2 1-3 2-4 2-5 3-4 3-6 4-5 4-6 5-6 6-7
te =7 te =4 te =7
te =13
4
te =11
te =8
6 7
te =11
te =10
te =10
Begin at starting event & work forward EST = 0 for starting activities
te =12
ES=0
1
te =7
ES=18
4
ES=31
5
te =4
ES=11
te =13 te =8
te =11
ES=42
6
ES=52
7
te =11
te =7 te =10
te =10
Begin at ending event & work backward LFT = Maximum EFT for ending activities
tm
12 11 3 8 7 10 13 7 10 10
tp
14 13 11 9 13 15 18 19 20 14
te Sigmae EST
12 11 4 7 7 10 13 8 11 10 2/3 2/3 5/3 4/3 6/3 5/3 5/3 9/3 7/3 4/3 0 0 12 12 11 11 18 18 31 42
LST
2 0 14 24 11 32 18 34 31 42
EFT
12 11 16 19 18 21 31 26 42 52
LFT
14 11 18 31 18 42 31 42 42 52
1-2 1-3 2-4 2-5 3-4 3-6 4-5 4-6 5-6 6-7
10 9 1 1 1 5 8 1 6 6
t1-2=12 0|2|12|14
1
t1-3=11 0|0|11|11
t3-6=10 11|32|21|42
t6-7=10 42|42|52|52
PERT
Activity oriented technique. It has one time estimate. Designed for repetitive projects. Not statistically analyzed. It demarcates critical activities. It employs words like arrow diagram, node, floats etc. Dummy activities are not necessary. Suitable for industrial settings, plant maintenance, civil construction projects. A deterministic model with well known activities times based on past experience. Cost is not directly proportional to time and const is the controlling factor.
Event oriented technique. It has three time estimation. Suitable for non-repetitive projects. Analyzed statistically. It does not demarcated critical and non-critical activities. It employs words like network diagram, events Slack etc. Use of dummy activities are required representing the proper sequence. Suitable for defense projects and R & D etc. Where activities cannot be predicted. A probabilistic model with uncertainty in activities duration Cost varies directly with time and time is the controlling factor.
Benefits
of PERT/CPM
Useful at many stages of project management Mathematically simple Use graphical displays Give critical path & slack time Provide project documentation Useful in monitoring costs and time
Limitations of PERT/CPM
Clearly defined, independent, & stable activities Specified precedence relationships Activity times (PERT) follow beta distribution Subjective time estimates Over emphasis on critical path
Conclusion
Explained what a project is Summarized the CPM / PERT project activities and their time estimates Drew project networks Compared PERT & CPM Determined slack & critical path Computed project probabilities
Project Management
PERT/CPM
THE END