Evm
Evm
Some slides in this presentation were originally developed by Mr. Tom Rethard, and most have been further enhanced and modified by Mr. Mike ODell for use in the CSE Senior Design class.
Earned value can be compared to actual cost and budgeted cost to determine variance and predict future performance
3
Each task in the Work Breakdown Structure (WBS) is assigned a BCWP based on its individual cost.
Project BCWP is total of BCWP for all tasks required to complete the project
Cost (Person-Hours)
Planned Value: what your plan called for sending on the tasks planned to be completed by this date.
Earned Value: value (cost) of what you have accomplished to date, per the base plan.
Time (Date)
7
Cost (Person-Hours)
Over Budget
Behind Schedule
Time (Date)
8
Variance
Any schedule or cost deviation from a specific plan. Used within an organization to verify the budget and schedule for a project Frequently used as a key component of plan reviews and performance measurement
Variance
Must compare scheduling and budget variance at the same time
Schedule variance: deviations from work planned not a measure of changes in cost Cost variance: deviations from the budget not a measure of work scheduled vs. work completed
Example: applying more $$/people to a task may maintain the schedule, but it adds to cost schedule on track over budget on expenses (cost)
10
Performance Indices
Cost Performance Index
CPI = BCWP/ACWP
Analysis
CPI > 1.0 exceptional performance CPI < 1.0 poor performance Similar for SPI
11
On Day X:
PLANNED VALUE (BCWS) = 18 + 10 + 16 + 6 = 50 EARNED VALUE (BCWP) = 18 + 8 + 14 + 0 = 40 ACTUAL COST (ACWP) = 45 (from your project tracking)
Therefore:
Level of effort
Work that is not discernable in discrete, measurable tasks (e.g., project management, training)
13
Our approach
Others?
14
Example 2
Plans to spend 100K in each of first 4 weeks (baseline budget, per documented plan) Actuals, at end of week 4 show: 325K spent
BCWS = 400K (100K x 4) ACWP = 325K
15
17
Variance Projection
19
20
21
Summary
Cost, in the form of Earned Value or BCWP, can be used to analyze progress of a project Using Earned Value data to make critical project decisions must be based on careful analysis of data, variances and trends
22
Act. A B C D E F G H I j
Pred. A B B D E C F G
Dur. 3 1 4 4 5 2 3 4 2 3
Bud. Cost 600 200 800 700 500 200 500 400 600 300 4800
BCWS (Budgeted Cost of Work Scheduled) = % Scheduled completion X Total Budgeted Cost = 3167.7 BCWP (Budgeted Cost of Work Performed ) = % Actual Completed X Total Budgeted Cost = 2985 ACWP ( Actual Cost of Work Performed) = % Actual Completed X Actual Cost incurred till date of reporting = 3100 Cost Performance Indices (CPI) = BCWP/ACWP = 2985 / 3100 = 0.96 Schedule Performance Indices (SPI) = BCWP/BCWS = 2985 / 3167.7 = 0.94 Cost of Completion = Budgeted Cost / CPI = 4800 / 0.96 = 5000 Time of Completion= Scheduled Duration/SPI = 12/0.94 = 12.76 i.e. 13 days