Decision Maths
Critical Path Analysis
Problem
Every morning you have three pieces of
bread (A,B and C) under the grill. The grill will take two pieces of bread at a time and will take 30 seconds to toast one side of the bread. How long will it take to toast all three pieces of bread?
Solution
You could follow the Or you could follow a more
schedule below.
efficient plan.
Time
Toast one side of A & B Toast other side of A & B Toast one side of C Toast the other side of C Total Time 30s 30s 30s 30s Total Time 120s Toast one side of A and B Toast one side of C and other of A Toast other side of B and C
Time
30s
30s
30s 90s
Critical Path Analysis
This was a trivial example of how time can be
saved by careful planning. We can apply similar thinking to larger problems involving construction and maintenance. Critical Path Analysis enables us to plan and monitor complex projects, so that they are approached and carried out as efficiently as possible.
Critical Path Analysis
Imagine you have a project to do which
involves doing lots of different activities, some of which cannot be started until others have been completed. For example the stages involved in recording and promoting a compact disc are shown in the table below
Critical Path Analysis
Activity A B C D E F G H I J Tape the performance Design the cover Book adverts in press Tape to CD Produce Cover Packing Promotion Copies to radio Dispatch to shops Played on radio Adverts in press Duration 10 9 3 2 2 1 1 3 2 1 A B D,E D,E F G C,H,I Preceding Activities
Critical Path Analysis
Given the conditions previously shown, what
is the shortest possible time the project can be completed in. We will assume that tasks can be carried out simultaneously whenever the conditions allow it. The first stage is construct a Precedence Network.
Precedence Network
Draw a start node
Duration A B C D E 10 9 3 2 2 A B Prec Act F G H I J Duration 1 1 3 2 1 Prec Act D,E D,E F G C,H,I
From the start node
add the activities that can be done immediately.
A(10) B(9)
1
C(3)
Precedence Network
Activity D needs A to
Duration A B C D 10 9 3 2 A Prec Act F G H I Duration 1 1 3 2 Prec Act D,E D,E F G
have been done immediately before it. Add a node to A. Have D coming from that node.
2 A(10) B(9)
C,H,I
D(2)
1
C(3)
Precedence Network
We can do a similar
Duration A B C D E 10 9 3 2 2 A B Prec Act F G H I J Duration 1 1 3 2 1 Prec Act D,E D,E F G C,H,I
thing with activity E
2 A(10) B(9)
D(2)
1
C(3)
E(2)
Precedence Network
Activities F and G have both
Duration A B C D E 10 9 3 2 2 A B Prec Act F G H I J Duration 1 1 3 2 1 Prec Act D,E D,E F G C,H,I
of D and E as their immediately preceding activities. Bring D and E into a single node. F and G emerge from that node. D(2)
2 A(10) B(9) 4
F(1)
1
C(3)
E(2)
G(1)
Precedence Network
Add nodes to the end of
Duration A B C D E 10 9 3 2 2 A B Prec Act F G H I J Duration 1 1 3 2 1 Prec Act D,E D,E F G C,H,I
activities F and G. Activity H must follow F. Activity I must follow G.
2 A(10) B(9)
D(2)
4
F(1)
H(3)
1
C(3)
E(2)
G(1) 6
I(2)
Precedence Network
J must follow C,H and I,
Duration A B C D E 10 9 3 2 2 A B Prec Act F G H I J Duration 1 1 3 2 1 Prec Act D,E D,E F G C,H,I
so bring all of those in to one node. J can now be added and the network is complete.
2 A(10) B(9)
D(2)
4
F(1)
H(3) J(1)
7
G(1) 6
1
C(3)
E(2)
I(2)
Critical Path Analysis
More Complicated Examples
The example we
have just looked through was a reasonably easy one. Consider the example to the right, it will give us more to think about.
Activity Duration A B C D E 1 2 4 4 3
IPA
A A,B D
Complicated Example 1
Draw a start node
From the start node add
Activity A B C D E
Duration 1 2 4 4 3
IPA
the activities that can be done immediately. Connect nodes to the ends of these activities.
2 A(1) 1 B(2)
A A,B D
Complicated Example 1
Activity C follows A.
D must follow both A
Activity A B C D E
Duration 1 2 4 4 3
IPA
and B. Where should D go?
A A,B D
C(4) 2 A(1) 1 B(2)
Complicated Example 1
You must add in a
dummy activity. This will have a duration of 0. Now to progress from node (3) you will have to have completed A and B. C(4)
2 A(1) 1 B(2) (0)
Activity A B C D E
Duration 1 2 4 4 3
IPA
A A,B D
Why does the dummy go from node (2) to
(3)? Activity C needs to follow A but has no need to follow B. If the dummy went the other way then it would be impossible to place activity C.
Complicated Example 1
Activity D can now be
attached to node (3). Now place a node at the end of D. Activity E can be assigned.
C(4) 2 A(1) 1 B(2) (0) D(4) E(3)
Activity A B C D E 5
Duration 1 2 4 4 3
IPA
A A,B D
Complicated Example 2
This starts in a similar way and
we can assign A and B to node 1. Both C and D must follow A and B, Where does the dummy go? The dummy is set from (3) to (2) because E comes from B and does not follow A.
Activity A B C D E
Duration 1 2 4 4 3
IPA
A,B A,B B
2 A(1)
(0)
1 B(2)
Complicated Example 2
C and D can now be
added to node (2). E can be added to node (3). They all join the final node (4).
C(4) 2 A(1) 1 B(2) (0) D(4) E(3)
Activity A B C D E
Duration 1 2 4 4 3
IPA
A,B A,B B
Complicated Example 3
Activities A and B are
simple. C and E are also simple as they follow A and B respectively. Two dummies are required to a new node (4). D is attached and all meet at (5)
2 A(1) (0)
Activity A B C D E
Duration 1 2 4 4 3
IPA
A A,B B
C(4)
4 (0)
D(4)
5 E(3)
1
B(2) 3
Precedence Network
Below is a precedence Network for a real life construction
project. The times on the arc represent days. What is the quickest time that the project can be completed in? 170 days. 10
3
F(16) B(25) A(10) C(10) D(16) H(18) K(16) O(11) N(34)
I(32)
J(32)
M(31)
G(12)
P(25)
11
T(24) V(21)
14
Q(48) R(16) S(14)
5
E(9)
13
U(50)
L(21)
12
Precedence Network
Due to a resource problem activity H is delayed by 10 days.
What effect will this have on the whole project? The entire project is delayed by 3 days.
10 3
F(16) B(25) A(10) C(10) D(16) H(18) K(16) O(11) N(34)
I(32)
J(32)
M(31)
G(12)
P(25)
11
T(24) V(21)
14
Q(48) R(16) S(14)
5
E(9)
13
U(50)
L(21)
12
Precedence Network
The supervisor in charge of activity I wants to use overtime to
reduce the completion time. How would you respond to this request? No there is plenty of spare time for the activity to be completed.
10 3
F(16) B(25) A(10) C(10) D(16) H(18) K(16) O(11) N(34)
I(32)
J(32)
M(31)
G(12)
P(25)
11
T(24) V(21)
14
Q(48) R(16) S(14)
5
E(9)
13
U(50)
L(21)
12
Precedence Network
Money is available to reduce the time of activity B or Q. Where
would you advise that the money is spent and why? Activity B It can reduce the overall completion time of the project.
10 3
F(16) B(25) A(10) C(10) D(16) H(18) K(16) O(11) N(34)
I(32)
J(32)
M(31)
G(12)
P(25)
11
T(24) V(21)
14
Q(48) R(16) S(14)
5
E(9)
13
U(50)
L(21)
12