Technical Note 2: Facility Layout
Technical Note 2: Facility Layout
Technical Note 2
Facility Layout
OBJECTIVES
Layout Planning
Assembly Line balancing
Service Layout
Facility Layout
Defined
Facility layout can be defined as the process by which the placement of departments, workgroups within departments, workstations, machines, and stockholding points within a facility are determined This process requires the following inputs:
Specification of objectives of the system in terms of output and flexibility Estimation of product or service demand on the system Processing requirements in terms of number of operations and amount of flow between departments and work centers Space requirements for the elements in the layout Space availability within the facility itself
Process Layout (also called job-shop or functional layout) Product Layout (also called flow-shop layout) Group Technology (Cellular) Layout
Fixed-Position Layout
Given
The flow (number of moves) to and from all departments The cost of moving from one department to another The existing or planned physical layout of the plant The best locations for each department, where best means maximizing flow, which minimizing costs
Determine
"Compare two departments at a time and exchange them if it reduces the total cost of the layout."
It does not guarantee an optimal solution CRAFT assumes the existence of variable path material handling equipment such as forklift trucks
Planning
Can be impractical to obtain Does not account for the qualitative factors that may be crucial to the placement decision
Accounts for the importance of having each department located next to every other department Is also guided by trial and error
Switching
5
6
A
E I O U X
Absolutely necessary
Especially important Important Ordinary closeness OK Unimportant Undesirable
16
8 4 2 0 80
10
Note here that the (1) Credit Dept. and (2) Toy Dept. are given a high rating of 6.
5 U 100 -A 400 1,6 X 300 1 Note here that X 100 the 1 Toy Dept. (2)
and the (5) 100 Candy Dept. are given a high rating of 6.
11
1 I 2
E 4
U
5
A Note here again, Depts. (1) and (2) are linked together, and Depts. (2) and (5) are linked together by multiple lines or required transactions.
The number of lines here represent paths required to be taken in transactions between the departments. The more lines, the more the interaction between departments.
12
2 3
20 ft
1
50 ft
4 Note in the Final Layout that Depts. (1) and (5) are not both placed directly next to Dept. (2).
Initial Layout
Ignoring space and building constraints
Final Layout
Adjusted by square footage and building size
13
Station 1
Station 2
Station 3
Minutes 6 7 3 per Unit Answer: The cycle time of the line is always determined by the work station taking the longest time. In this problem, the cycle time of the line is 7 minutes. There is also going to be idle time at the other two work stations.
14
Youve just been assigned the job a setting up an electric fan assembly line with the following tasks:
Time (Mins) 2 1 3.25 1.2 0.5 1 1 1.4 Description Assemble frame Mount switch Assemble motor housing Mount motor housing in frame Attach blade Assemble and attach safety grill Attach cord Test Predecessors None A None A, C D E B F, G
Task A B C D E F G H
15
A, C
A B G
E, G
H C D E
16
C 3.25
D 1.2
E .5
Answer: Task C is the cycle time of the line and therefore, the maximum rate of production.
Cycle Time
Determine
18
Question: Suppose we want to assemble 100 fans per day. What would our cycle time have to be?
Answer:
Required Cycle Time, C = Production time per period Required output per period
19
Answer:
Theoretical Min. Number of Workstations, N t Sum of task times (T) Cycle time (C)
Nt =
20
Assign tasks to station 1, then 2, etc. in sequence. Keep assigning to a workstation ensuring that precedence is maintained and total work is less than or equal to the cycle time. Use the following rules to select tasks for assignment. Primary: Assign tasks in order of the largest number of following tasks Secondary (tie-breaking): Assign tasks in order of the longest operating time
21
2 A
1 B
1 G
1.4 H F 1
C 3.25
D 1.2
E .5
Task A C D B E F G H
Followers 6 4 3 2 2 1 1 0
Station 1
Station 2
Station 3
22
2 A
1 B
1 G
1.4 H F 1
C 3.25
D 1.2
E .5
Task A C D B E F G H
Followers 6 4 3 2 2 1 1 0
Station 1 A (4.2-2=2.2)
Station 2
Station 3
23
2 A
1 B
1 G
1.4 H F 1
C 3.25
D 1.2
E .5
Task A C D B E F G H
Followers 6 4 3 2 2 1 1 0
Station 2
Station 3
24
2 A
1 B
1 G
1.4 H F 1
C 3.25
D 1.2
E .5
Task A C D B E F G H
Followers 6 4 3 2 2 1 1 0
Station 2
Station 3
25
2 A
1 B
1 G
1.4 H F 1
C 3.25
D 1.2
E .5
Task A C D B E F G H
Followers 6 4 3 2 2 1 1 0
Station 2 C (4.2-3.25)=.95
Station 3
26
2 A
1 B
1 G
1.4 H F 1
C 3.25
D 1.2
E .5
Task A C D B E F G H
Followers 6 4 3 2 2 1 1 0
Station 2 C (4.2-3.25)=.95
Station 3
Idle = .95
27
2 A
1 B
1 G
1.4 H F 1
C 3.25
D 1.2
E .5
Task A C D B E F G H
Followers 6 4 3 2 2 1 1 0
Station 2 C (4.2-3.25)=.95
Station 3 D (4.2-1.2)=3
Idle = .95
28
2 A
1 B
1 G
1.4 H F 1
C 3.25
D 1.2
E .5
Task A C D B E F G H
Followers 6 4 3 2 2 1 1 0
Station 2 C (4.2-3.25)=.95
Idle = .95
29
2 A
1 B
1 G
1.4 H F 1
C 3.25
D 1.2
E .5
Task A C D B E F G H
Followers 6 4 3 2 2 1 1 0
Station 2 C (4.2-3.25)=.95
Idle = .95
30
2 A
1 B
1 G
1.4 H F 1
C 3.25
D 1.2
E .5
Task A C D B E F G H
Followers 6 4 3 2 2 1 1 0
Station 2 C (4.2-3.25)=.95
Idle = .95
31
32
33
34
Answer: Arranging materials and equipment concentrically around the production point in their order of use.
35
36
Question Bowl
Which of the following are distinguishing features of CRAFT? a. It is an optimization methodology b. Does not require any assumptions about the layout or inter-relationships of departments c. Can handle over 50 departments d. All of the above e. None of the above
Answer: e. None of the above (It is a heuristic program, does not guarantee an optimal solution, requires layout assumptions and can handle up to 40 departments.)
37
Question Bowl
Which of the following is a process that involves developing a relationship chart showing the degree of importance of having each department located adjacent to every other department? a. Systematic layout planning b. Assembly-line balancing
c.
d. e.
38
Question Bowl
If the production time per day is 1200 minutes and the required output per day is 500 units, which of
2.4 minutes
0.42 minutes
1200 units 500 units None of the above
39
Question Bowl
You have just finished determining the cycle time for an assembly line to be 5 minutes. The sum of all the tasks required on this assembly is is 60 minutes. Which of the following is the theoretical minimum number of workstations required to satisfy the workstation cycle time? a. 1 workstation b. 5 workstations Answer: c. 12 c. 12 workstations workstations d. 60 workstations (60/5=12) e. None of the above
40
Question Bowl
If the sum of the task times for an assembly line is 30 minutes, the actual number of workstations is 5, and the workstation cycle time is 10 minutes, what is the resulting efficiency of this assembly line? a. 0.00 b. 0.60 c. 1.00 d. 1.20 e. Can not be computed from the data above
41
Question Bowl
Which of the following are ways that we can accommodate a 20 second task in a 18
42
Question Bowl
Which of the following are ambient conditions that should be considered in layout design?
a.
b. c.
Noise level
Lighting Temperature
d.
e.
Scent
All of the above
43