Storage Type Hydropower Project
If you pump casually, you will pump forever. Pump hard to begin with and keep it up until you get that water flowing. Then a great deal will happen.
WATER FOR LIFE AND CIVILIZATION
Water for life
Water has been the key to the civilization ever since the start of the human development. Ancient Egyptyian civilization was also known as the gift of nile. Mesopotamian civilisation and the indus valley civilization in the east were on the river side.
Water for agriculture..agriculture for food...food for life
Water for power
Power hungry photos
Power demand in worlds data
Power Situation in Nepal
Nepal rely heavily on traditional source of energy. Fuel wood = 68% Bio mass = 13% Fossil fuel = 18% Hydropower = 1% Sources of energy in Nepal
Fuel wood
Bio mass Fossil Fuel hydropower
Solution to power?
Water Power
Hydrological Status of Nepal
Total annual average run-off from the nation's 600 perennial rivers :over 200 billion cu.m Around 20,000 litres of water per person per day Average annual precipitation is approximately 1700mm. 80% in monsoon season june to september.
Hydropower potential
Nepal's storage potential is estimated at 88 billion cu.m. Theoretical power potential is approximately 83,000 MW( Dr. Hari Man Shrestha) More recent estimation:52000 MW (IOE Theseus) Economically feasible potential : 43,000 MW Power harnessed: 718MW
LOAD FORCAST
Projects in Nepal
Project Name Hewa Khola Lower Piluwa Gamgad small hydropower project
Power Capacity(kW) 4455 kW 990 kW 400 kW
Remarks completed completed completed
Dhalkebar-Muzaffarpur double circuit transmission line
400 kV
Cross-border interconnection between Nepal and India. Necessary ground works are now in place for taking off the implementation. Expected to be in operation by 2014
Rasuwagadhi HydroelectricProject 111MW
Middle Bhotekoshi Hydroelectric Project
102MW
Upper Sanjen Hydroelectric Project
14.8 MW
Sanjen Hydroelectric Project
42.5 MW
Upper Modi Hydropower Project Upper Trishuli Hydropower Project Hetaunda-Bharatpur Transmission Line
47 MW 60 MW 220 kV
NEA and K-Water(S.Korea) with 20% NEA share ownership
Bhotekoshi Hydropower Project
Kulekhani-3 Hydroelectric Project Chameliya Hydrolectric Project
9 MW
14 MW 30 MW Completion date September 13,2014 tunnel breakthrough on 12th May, 2012 Overall progress of civil works is 75%
Upper Trishuli 3A
60 MW
Construction of major works of the Project is to commence only after the issuance of Work Order by the Consultant.
The Khimti Dhalkebar Double Circuit Transmission line Project
220 kV
95 % work completed the completion of the project is hampered due to obstructions created by local residents regarding the right of way issue Work is underway Almost complete and expected to be commissioned soon Substantial Progress Substantial Progress Substantial Progress Substantial Progress
Hetauda- Bharatpur Bardghat ransmission line
220 kV 132 kV 132 kV 132 kV 132 kV 132 kV
Syangja substation
Dumre-Damauli-Marsyangdi 132kV ransmission line
Singati-Lamosangu 132kV ransmission line
Kabeli 132 kV transmission line
Chapali 132 kV substation
Pathlaiya 132 kV substation
132 kV
132 kV 132 kV
Substantial Progress
Substantial Progress Substantial Progress
Matatirtha 132 kV substation extension
Second circuit stringing of Butwal Kohalpur- Mahendranagar 132 kV ransmission line
Second circuit stringing of Hetauda 132 kV Kulekhani-II - Siuchatar 132 kV transmission line
Substantial Progress
Hetauda Dhalkebar Duhabi 400 kV transmission line project
400 kV
Cross border power exchange with India
Upper Tamakoshi Hydro Power Company Limited (UTKHPL)
456 MW
NEA with 41% stake A Project Of National Pride Construction Works ongoing at full swing
Tanahu Hydropower Project
140 MW
The detailed engineering study of the project is in the final stage of completion. Construction could begin by mid 2013
Upper Trishuli 3B Hydroelectric Project
37 MW
Under development
We need power.....
WHY HYDROPOWER?
Energy sources
Traditional Energy
Wood, animal dung, agricultural-waste etc.
Commercial Energy
Fossil Fuel, Electricity etc. Alternate Energy sources Bio-gas, Solar panel, Wind etc.
Features of Hydropower
Clean and renewable Energy Cheap Energy Easy to control High efficiency
A green energy
Our Capabilities in Hydropower Design for 100MW
Design, Engineering. construction 100% Engineering, construction Roads & Bridges 100% Gates, stop logs and trash racks 100% Penstock pipes and manifolds 100% Draft Tubes and embedded parts 100% Micro, Mini Turbine 100% Tubular steel poles and accessories, towers 100% Substations 100% Distribution/ Power Transformers 100% ACSR Conductors, Power Cables 100% Generators upto 100MW (By 2010) 100%
By Er.Gyendra Lal Pradhan
Hydropower wonders then and now
Hoover Dam
First great achievement was in the form of Hoover dam constructed across the Colorado river in Black canyon of Arizona Constructed between 1931 and 1936 was the largest structure to be built then with still untested construction techniques Concrete thick arch structure 726.4 ft. high 1244 ft. long 660ft. Thick at base and 45 ft. at top Storage capacity 30,500,000 acre feet Power generation 2.8 million kilowatts
Three Gorges Dam
Largest hydropower project of the world spans the Yangtze River by the town of Sandouping, located in Yiling District, Yichang, Hubei province, China Completedc in 2006 Capacity of 22500 MW
WHY HAS THERE BEEN SUCH DIFFERENCE?
Geological factors Availability of Tenchnolgy Research Sound political and policy making
Constraints in Nepal
Geological difficulty Technological complications Young geology Low capital investments/ poor economy Political instability
Status of current powerplants in Nepal
Dificulties and Problems
Before we even initiate
Geological And Environmental
Seasonal Power Production Variations Sedimentation Transportation
Political
Decade-long conflict between the government and Maoists Obstruction in the construction of new hydroelectric power plants No proper policy to attract private sectors Butans 20 year hydro-power master plan Failure of our tenth five year plan
Political
If we have a look at the periodic development:
Plan Period Achieved
Capacity MW Target
Success (%)
Till 1991 8th Plan (1992/1997) 9th Plan (1997/02) 10th Plan (2002/07) Interim Plan (2007/10)
239.33 3.2 261 41.63 82
293 314 105
89.07% 13.26% 78.09%
Technical
No proper manpower and brain drain Lack of test labs and modern equipment Proficient construction company Reliance on foreign consultancies
Ongoing Projects
Contractor confliction Political instability Petroleum price inflation Corruption Technical
Post Project
Siltation Power grid Power theft Timely maintenance Technical
MONEY
What is money?
Money is the basic need that fulfills all the other basic needs.
Money is paper, but not really.
Money is the mode of financial transactions.
Money in the project
Infrastructure Development
Transportation of goods and construction materials
Construction of engineering structures Payment Operation and Maintenance cost
Economy and Hydropower
Apart from being a source of energy, hydropower is an important asset for our economical development.
Our overall economy is considerably affected both directly and indirectly by electricity generation ,which makes the role of hydropower very significant. Economy ,its strength and stability determines the favorability to extract maximum energy from our resources and create an investment friendly environment.
Financial Problems in Hydropower
Lack of budget
Imbalance in budget prioritization
Role of broker companies
Corruption
P.P.A.(Power Purchase Agreement)
Agreement done between government authority and private companies. PPA is done under the Single Buyer Model.
In SBM, private ownership in electricity generation only.
Electricity Act doesnt officially recommend such a system but it is prevalent as a situational default. With the introduction of Wholesale Competition Market, single buyer concept will be dissolved.
Our Project
What are we doing?
Project 1
Project Selection Site selection Site survey/collection of data Hydrological study Geological studies
Project 2
Environmental Assessment Design of hydraulic structure -River training work -Dam and intake -Penstock pipe -Surge tank -Settling basin -Turbine -Powerhouse -Headrace/Tailrace -Access road Economic analysis Project review and presentation