The key takeaways are that a P&ID is a basic engineering document used to show process requirements, equipment, piping, instrumentation, and their relationships. It is used for various engineering and operational activities.

A P&ID, or Piping & Instrument Diagram, is a diagram that shows the piping, instrumentation, and process flow in a process plant. It indicates process requirements, equipment, piping components, instrumentation, and their logical relationships. From a P&ID, one can obtain information about equipment outlines and internals, piping line numbers, sizes, materials, and configurations, and instrumentation tag numbers and functions.

The main components that should be included on a P&ID are process equipment, all piping for normal and abnormal operations, instrumentation for controlling and monitoring the process, safety devices, and other details like battery limits and responsibility changes.

P&ID Piping & Instrument Diagram

What is P&ID

Basic Engineering document Indicating -Process Requirement -Equipment in the Plant -Piping and Piping Component -Instrument and Logic Relations

What should be indicated on P&ID? Process requirement

- PFD : all line and flow, every item


- not on PFD : relieving system, pump minimum flow, compressor anti surge flow, isolation system - item for maintenance, operation, pre-commissioning, commissioning, start-up

What should be indicated on P&ID? Equipment - all equipment with exact number and components : all nozzles, manholes, internals - type of connection to piping - equipment item number, service name, major specification

What should be indicated on P&ID? Piping

- all lines for normal operation, startup, shutdown, emergency, special operation, and maintenance - all piping components (valves etc.) and notes on them (CSO, CSC, TSO)

- line information : line no., size, fluid symbol, piping service class, insulation
- configuration requirement : No Pockets, Free Draining

What should be indicated on P&ID? Instrumentation - instrumentation for controlling, monitoring, emergency shutdown, sequence control, interlock, automatic start/stop - field instrument - control and shutdown valves with their type, size, failure status - pressure relief valves with their set pressure and size - kind of signal : pneumatic, electric, hydraulic, capillary tubing, softlink

What should be indicated on P&ID? Other - battery limit between client and contractor - area battery limit - change of responsibility between Piping and Instrument, Contractor and Vendor

- extent of packaged equipment supply


- breaks of line information : line number, piping service class, insulation

What information can you get?

For Equipment Outline/Internals For Piping Line No./Size/Material/Insulation/Line Configuration/Piping Component Type For Instrument Tag No./Function/Control Method

P&ID is used for

Detail Engineering of each disciplines Piping layout/Material Purchase Instrument Logic/DCS Plan, etc Planning of Construction/Commissioning/Plant Operation/Maintenance

How to Develop/Finalize
Process Verification Proj.Spec Discipline Comments

P&ID IFA

Company Comments
HAZOP SIL Study, etc. Field Change Feedback P&ID IFC P&ID As Built

Detail Design Feedback Vendor Data Input

P&ID IFH

P&ID Symbols

P&ID Symbols

P&ID Symbols

P&ID Symbols

P&ID Practices

Control valve loop

1
PC H 005 L PY 005 I/P

PT 005

PV 005

FC 4 300# 4

LT/FT Cascade Control

LT 105

DISP

LI 105

H L

SP FC 102 FT 102 FV 102 6-PL-10042-AA11-N 300# FE 102 FC 4 300# 4 6-PL-10042-AA11-N

Split range control(1)


PY 2xa 001A PC H 001 L PY 2x(a-50) 001B PY 001D I/P

CV OPENING

100 0

PV 001B 8-PG-10043-AA11-N PT 001 FC/TSO 4 300# 6-PG-10043-BA21-N


P

0 100 PIC OUTPUT

I/P PY 001C PV 001A 6 6-PG-10042-BA21-N

FC 4 300# 4

Split range control(2)


1

2x(50-a)

PY 001A

a
PC AH 001 AL

PY 2x(a-50) 001B
CV OPENING

100 0

I/P PY 001C PV 001A 2 FC 1 1-1/2 2-PG-10102-AA11-N

PT 001

I/P PY 001D PV 001B 3 FC 1-1/2 2

0 100 PIC OUTPUT

3-PG-10101-AA11-N

Place equipment and its components Connect main piping Complete control valve loop Place other instrument and connect signals Indicate safety devices incl. alarm Place piping components (Valve/Fitting) as required Check detail and add items required incl. vent/drain connection