Lecture 6-Project Delivery Methods
Lecture 6-Project Delivery Methods
Schedule
February 8
February 10/15- Project Delivery February 17- No class February 22- Midterm Review February 24- Midterm
In the industry the term Pre-Construction Services is utilized when defining the first five stages of the project life cycle. Pre-Construction Services
1.
Project Conception
2.
3. 4. 5.
Project Delivery
Design Construction Documents Bidding/Negotiating/Procurement
This is where the industry and owners are beginning to see an opportunity to increase the success of the project by the integration of design and construction throughout these stages of the project life cycle.
2. Project Delivery
Project Delivery is the process by which all of the procedures and components of designing and building a project are organized and put together in an agreement that results in a completed project. The Owners approach to organizing the project team that will manage the entire design and construction process. Project Delivery is the contractual relationships between the owner, architect/engineer (A/E), contractor(s), and the management services utilized to design and construct a project.
Contract Types
In addition to choosing a delivery system for a project, the owner must decide what type of contract to use. A contract is simply an agreement between two or more entities in which they agree to provide a specific task in exchange for something in return. The contract type basically is the format on how the owner pays for the services of the contractor.
The Traditional Delivery Method- Design-Bid-Build Design-Negotiate-Build The Construction Management Delivery Methods The Design/Build Delivery Method Contract types
Lump Sum or Fixed Price Unit Price Cost Plus Fee Cost Plus with a GMP
The magnitude, form, function and complexity of the project. Time is of the essence. Sequencing of the project. Establishing the project timeline. Fast-tracking utilizing multiple contractors or contracts to condense the project timeline. Cost /Budget/ Other Financial Challenges
Design-Build
The Design-Bid-Build method is most common. The Owner first contracts with a Design Professional who provides the design. The basis of this delivery method is that design is completed prior to bidding/pricing and construction. Competitive bidding is a a method of determining the least cost for accomplishing the scope of work defined by the bid documents. Once the design is complete, the Owner contracts with the Builder who provides the most responsive competitive bid for construction.
Owner
Architect/Engineer
General Contractor
Design Consultants
Subcontractors
Craft Workers
Suppliers/Vendors
Traditional Method
Well defined relationships, procedures and rules of conduct have been worked out and understood. A known quantity. Lots of experience in this method by all parties. The risk of cost increases depends to a large extent on the accuracy and completeness of the work scope and contract documents. The actual construction price of the project is not known until all bids are received. No collaboration from the contractor. Normally design-bid-build with a specific timeframe. This does not allow for fast tracking the project. This process is inherently adversarial. Price is based on a specific scope of work. If the documents are poor or scope of work is undefined then the potential for change orders is extreme. This can lead to contract problems and litigation.
Design-Negotiate-Build
Same structure as Design-Bid-Build usually the design is complete before negotiations. The contractor may be selected on other factors than low price including qualifications, expertise, reputation and timeline. This negotiating process allows both parties to work together on issues including design, product selection, project phasing, optimum constructability, scheduling and budgeting. Cost is not usually the primary consideration for selection but the firms history of successfully completing complex projects on time which will usually mean an ultimate savings of money and time with collaboration and working together.
Design-Negotiate-Build Limitations
The lowest cost may not be obtained due to the absence of competition and inflated prices. Negotiated contracts are rarely used for publicly funded projects because laws are requiring competitive bidding to protect the publics interest. In this method the final price may be negotiated on partial information. Modifications to design documents after the price is negotiated may lead to cost increases or the project scope may be reduced. These modifications are sometimes referred to as scope creep. By negotiating agreement, the owner becomes financially committed to the project without knowing the total cost. More known's by selecting a contractor.
Construction Management
As Owner Agent
As GC
Allows construction input during PreConstruction. The Owner pays the contractors directly, the CM acts as the Owners agent.
Allows construction input during PreConstruction Can be called CM/GC. Usually proposes a guaranteed maximum price (GMP) on a scope of work. Sometimes called atrisk construction management.
Contractors
Subcontractors/Vendors
Good communications among owner, designer and CM firm is established early in the project. Usually involve multiple contracts or fast-tacking or complex projects that require intense professional management. Knowledge of construction, systems costs and scheduling is utilized during the design phase. Good opportunities for cost savings and value engineering by having construction expertise involved early. The Owner receives the cost benefit of the competition among the subcontractor and supplier bids. Good communication leads to a less difficult change process. This delivery system requires the project team to share responsibilities where trust, proper ethics and a cooperative environment is a must. Its important you have a strong CM/Design Team the advantages of this method can turn to the disadvantages fast.
The CM/GC approach assumes one entity, manages all facets of the construction effort including preconstruction services. During pre-construction the contractor is a CM and converts to GC after the guaranteed maximum price is decided upon. The firm could subcontract, on a lump sum or cost plus basis, work that the Client feels is suitable for local hire such as specialty subcontracts (painting, insulation, HVAC, refractory, grading/paving and site development).
A single entity provides both design and construction of the project. The Design-Builder is obligated to meet the design criteria and performance requirements specified in the bidding documents. On a design/build project the contractor and designer work together to serve the Owner on cost, schedule and scope of work. Ability for fast track/phased construction.
Contractor Led (subcontract design or joint venture) Designer Led (subcontract construction or joint venture) A single firm with both capabilities internally
Design/Build
Why Design/Build?
Ability for fast track/phased construction. Higher quality projects. Reduction of claims and litigation against owners. Identification of costs early. Better relations and communication, more Contractor involvement throughout the process. The design-builder provides only the necessary documentation to build the project efficiently.
Scope development and the selection process. The need for new documents. The differentiation of design and construction. Legal and professional issues. Owner expertise. Public and federal procurement rules and policies. Insurance/Bonding/Indemnification/Limits of Liability.
The Design-Build Institute of America predicted that by 2005, 55% of private commercial projects will use design-build method. Not so but alternate delivery systems are becoming much more common in the industry.
The bidding process may change with each project delivery method but each one will select one of the below bid processes.
Negotiated Bidding
Trends
Traditional delivery leads to more problems regarding cost overruns and disputes. A large majority of large military projects are now design-build. Many public companies are going to CM/GC or GC/CM contracting. Design-Assist -new terminology Mechanical Exterior Cladding New Rules
Sole Source Responsibility Design Assist Design-Build-Maintain Capital Cost vs. Life Cycle Analysis
Contract Types
In addition to choosing a delivery system for a project, the owner must decide what type of contract to use. A contract is simply an agreement between two or more entities in which they agree to provide a specific task in exchange for something in return. The contract type basically is the format on how the owner pays for the services of the contractor.
Contract Types
Fixed price or lump sum- The contractor agrees to provide a specified amount of work (known as the scope of work) for a specific sum. Cost plus a fee- The contractor is reimbursed for their costs and receives a agreed upon fee. A GMP (guaranteed maximum price) may be added to the contract. The contractor may share in savings if provided in the contract. If the contract amount goes over the contractor is responsible for the overage. Time and Materials- Specific labor rates are agreed to and charged out based on the work accomplished. Materials are reimbursed with an appropriate mark-up. Unit Price or Rate- The owner and contractor agree on the price to be charged per unit for the major elements of the project.
Fixed Price/Lump Sum Based on a scope of services a lump sum or fixed amount decides the value of the contract. Cost Plus Fee Cost Plus is the accumulation of actual costs expended on the project plus an appropriate fee to cover overhead and profit for the contractor. Cost Plus Fee GMP The GMP (Guaranteed Maximum Price) sets a not to exceed price. If the accumulation of actual costs goes over the GMP the contractor pays. If it goes under the contractor may share in savings based on the contract.
Time and Materials Carpenter $50.00 per hour X 400 hours= Laborer $30.00 per hour X 100 hours= Backhoe $45.00 per hour X 100 hours= Lumber Invoice $1500 X .15% markup = Total Project
Time labor rates are based on an hourly rate per worker or piece of equipment used which includes all associated costs for providing labor and equipment. Overhead and profit is included in the labor and owned equipment rates. Material is invoiced cost plus a markup or fee.
Unit Price or Rate Gravel 5000 tons @ $10.00 per ton= $ 50,000 Asphalt 8000 tons @ $ 8.00 per ton= $ 64,000 Concrete Barriers 1500 CY @ $100.00 per CY= $150,000 Drain Pipe 1000 LF @ $ 10.00 per LF= $10,000 Total Price $274,000 Used primarily in Heavy/Civil/Highway construction. Unit prices include all associated costs for project. Overall scope is based on those target quantities agreed to by the Owner and Contractor. Any major change in quantities may require renegotiating unit prices. The unit rates include all overhead and profit for the project.
Types of Contracts
All Companies Industrial & Nonresidential Heavy & Highway Specialty Trades
Fixed Price
61%
56%
47%
74%
14%
5% 7% 2% 10% 1%
28%
7% 3% 55 0% 1%
1%
2% 6% 0% 43% 0%
4%
3% 13% 1% 5% 0%
The Traditional Delivery Method- Design-Bid-Build Design-Negotiate-Build The Construction Management Delivery Methods The Design/Build Delivery Method Contract types
Lump Sum or Fixed Price Unit Price Cost Plus Fee Cost Plus with a GMP