Civil Works in Power Plants
Civil Works in Power Plants
Civil Works in Power Plants
03-08-2012
CONTENTS
Bidding
Technical Specifications Preparation Of Bid
Water Systems
Miscellaneous buildings Soil Profiles in India
Soil Investigation
Design Aid:
Softwares IS Codes
Station capacity: Determines the quantum of coal to be handled by coal handling plant and the capacity of coal unloading system, crushers, coal conveying system, etc. Coal source and quality: Quality of the coal determines the specification of coal handling equipment apart from the quantity of coal to be handled. Coal transportation mode: Depends on the location of power plants with respect to coal mines/sources and other site conditions. Topography and geometry: Layout of coal handling system varies with topography, geometry of the area, coal storage requirements as well as wind direction. No. of transfer points may also vary with topography and geometry of the area.
Boiler area Foundations for boilers, bunkers, elevator supporting structure Foundation of dewatering & re-filling pumps drainage arrangements provision of passage way for maintenance of equipment
Transformer Yard
Foundations for transformers including soak pits, fire barrier wall, rail foundations including rails, foundations for other equipment and structures in the transformer yard, oil drainage arrangements, oil collection and separation pits, trenches and duct banks, paving of the transformer yard including drainage arrangement for the yard, fencing around the yard with gate for movement of equipment etc.
SOIL INVESTIGATION
Purpose: To obtain information on the physical properties of soil and rock around a site to design earthworks and foundations Soil Samples
IN SITU TESTS
Standard penetration 2131: 1981
test:
IS
In-situ dynamic penetration test Bore hole dia. of 100-150 mm and length 650 mm Diving head 63.5 Kg and height 75 cm
Corrections
Overburden Dilatancy if the stratum consists of fine sand and silt below water table
Cone penetration test IS 4968 Method: consists of pushing an instrumented cone, with the tip facing down, into the ground at a controlled rate Provides soil cohesiveness data and bearing capacity CPTu - Piezocone Penetrometer. measures the groundwater pressure as the probe is advanced SCPTu Seismic Piezocone Penetrometer. probe is equipped with either geophones or accelerometers to detect shear waves and/or pressure waves produced by a source at the surface.
LABORATORY TESTING
Atterberg limit
FOUNDATIONS
Shallow Foundations
Spread Foundation
The bottom part is made wider to reduce the pressure Used in residential buildings Design based on weight Not suitable for heavy structures
Mat-Slab Foundation
The load is distributed to the entire building area Thick mats required for heavy structures
Slab-on-grade foundation
Concrete slab, to be used as foundation, is made using a mold Leaves no space between ground and structure Can lead to large heat losses, exposes to flood damage due to low elevation
Deep Foundations
Driven Piles
Made of wood, concrete or steel Pole shaped members driven into soil using large weights Column rest on pile caps supported by Group of piles Monopile foundation consists of a single large member supporting all the weight
Drilled Piles
Under reamed piles have a enlarged base and are used in firm soils Auger cast piles are formed by drilling through the ground using a flight auger and then pouring concrete Rotary bored piling can be dry bored or wet bored. Pile is encased in a temporary casing which is removed after the required depth is reached.
CHIMNEY CONSTRUCTION
A chimney is a structure for venting hot flue gases or smoke from the boiler into the atmosphere at sufficient heights The stack in coal fired power plants can be tall in the range of 200 to 300 M The stack has an outer RCC shell and a steel inner lining (Flue) for the flue gas path The outer shell provides the strength and the inner lining protects the concrete layer from corrosive flue gases Connection of multiple units to a single shell will have multiple inner flue gas liners
Methods
Slip form method - In this method the form work for the concrete literally slips up cm by cm to produce an integrated concrete column. Continuous pouring of concrete ensures a joint free construction Jump form method - form work jumps up to the next layer after the bottom layer is cast. This is suitable for stacks, which have lining - like refractory lining in the inside of the shell. The concrete is not continuous
Covered in IS 875 part 1. Unit weight are specified for all the materials to be used in construction Weights of parts and components, fuels miscellaneous are also covered
Wind causes a random time-dependent load, which can be seen as a mean plus a fluctuating component. IS 875 part 3 specifies the wind loads Design Wind Speed (Vz)
Vz = Vb k1 k2 k3 k4
Vz = design wind speed at any height z in m/s, Vb = wind velocity at any height at any specified location k1 = probability factor (risk coefficient) k2 = terrain roughness and height factor k3 = topography factor k4 = importance factor for the cyclonic region
The factor k1 is based on statistical concepts, which take account of the degree of reliability required, and period of time in years during which there will be exposure to wind, that is, life of the structure.
Selection of terrain categories shall be made with due regard to the effect of obstructions which constitute the ground surface roughness.
Category 1 Exposed open terrain with a few or no obstructions and in which the average height of any object surrounding the structure is less than 1.5 m Category 2 Open terrain with wellscattered obstructions having height generally between 1.5 and 10 m Category 3 Terrain with numerous closely spaced obstructions having the size of building-structures up to 10 m in height with or without a few isolated tall structures Category 4 Terrain with numerous large high closely spaced obstructions
the speeds given in the basic wind speed map are often exceeded during the cyclones. Structures of postcyclone importance 1.30 Industrial structures 1.15 All other structures 1.00 The highest value may be used only for structures of postcyclone importance such as cyclone shelters, hospitals, school and community buildings, communication towers, power-plant structures, and water tanks
pz = wind pressure in N/m2 at height z, and Vz = design wind speed in m/s at height z.
Kd :
For circular or near circular forms this factor may be taken as 1.0. For buildings, solid signs, open signs, lattice frameworks, and
trussed towers (triangular, square, rectangular) a factor of 0.90 may be used on the design wind pressure.