Page No.1 2012 / PCDO For The Month of April 2012

1) Progress was reported on various AFTC, BPAC, and signalling works including the ABU-PAB AFTC work where foundations have been cast and track crossings completed. 2) Budget expenditure and personnel details were provided with staff nominations for training. Store items status and pending indents were enclosed. 3) Assistance was requested from headquarters to reconstruct the leaking office building of the Dy. CSTE/Proj/MS office or relocate it to a convenient location.

Uploaded by

Vinu Varshith
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
43 views10 pages

Page No.1 2012 / PCDO For The Month of April 2012

1) Progress was reported on various AFTC, BPAC, and signalling works including the ABU-PAB AFTC work where foundations have been cast and track crossings completed. 2) Budget expenditure and personnel details were provided with staff nominations for training. Store items status and pending indents were enclosed. 3) Assistance was requested from headquarters to reconstruct the leaking office building of the Dy. CSTE/Proj/MS office or relocate it to a convenient location.

Uploaded by

Vinu Varshith
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 10

Page No.

1 2012 / PCDO for the month of April 2012


I.

/HIGH LIGHTS

1. ABU-PAB AFTC work: (7 Km)

ABU 4.5 Km

AVD 2.5 Km

PAB

S. Nature of Work N o

Section: ABU-AVD

Section: AVD-PAB Remarks Status Completed Completed Window and Completed door work pending Completed Completed Completed Under Progress Completed 1500 Mtrs to Completed be done Not started Completed Not started Completed Remarks Completed ---

Status 1 Casting of Completed foundations 2 Track crossings Completed 3 Construction of 3 Completed AFTC huts 4 Installation of Pending tuning boxes 5 Wiring of signals Pending 6 Location wiring Pending 7 Indoor works in Pending AFTC huts 8 Provision of special Completed earth 9 Trenching work 3000 Mtrs done 1 Glued joints Pending 0 1 OHE structure Pending

1 bond shifting

Page No. 2 SIGNALLING PLAN FOR ABU-AVE AFTC AUTO SECTION, YET TO BE RECEIVED FROM CSTE/P/MAS. 2. . b) OHE Mast shifting PENDING WORKS FOR AVD-PAB a) .Tunning Units to track lead connection

3.

/PROVISION OF LED SIGNALS a) Provision of LED SIGNALS in MAS division was completed. b) As - made drawing sent for approval on 08/09/2011. c) As made negative checking work in progress.

4.

/TPWS WORK:

All the 81 sleeping mode motor coaches are under observation. Frequent footplate is being carried out to monitor the performance of TPWS system. 5. - /VPY-ABU AFTC WORK:

Earlier Tender Discharged on 21/02/2012, Directions required for retendering. 6. - /ENR-GPD AFTC WORK: Tender under process at Project Office.

Page No.3 7. . - /CGL-AJJ BPAC WORK : (62.96 RKm)

AJJ

14.37Km

TMLP

13.97Km CJ

12.78Km WJ

10.35K

PALR CGL 14.98Km

S.N o 1 2. 3

Section PALR-TMLP CGL-PALR TMLP-AJJ

Remarks BPAC commissioned on 06/03/2012. BPAC energized on 14/03/2012 and under observation Work Completed and kept under observation. Awaiting for sanction from CSTE/MAS for commissioning

CGL-PALR section, CSTE sanction has been obtained). AJJ Sigg.plan & TC yet to be received from CSTE/P/MAS. SWR of AJJ yet to be received from CSTE/P/MAS. Page No.4

II

/BUDGET:

Expenditure statement enclosed as Annexure-A.

III

. /PERSONNEL:

a. Scale check of staff strength enclosed as Annexure-B1. b. Staff/ Officers nominated for training.: Sl.N o. 1 Name(S/Shri) K.Girishkuma r Designatio n Tech/GrI/Si g Course Name Pre-Promotional course Training Centre IRISET/SC

I. Phase from 09/01/2012 to 24/02/2012 - completed II Phase started from 12/03/2012 c. Position of vacancies in Group-C cadre enclosed as Annexure-B2. IV. /STORES:

Enclosed as Annexure-C1 to Annexure-C5 a. Stock position of vital items, viz. Cables, relays, Point Machines, power supply equipments, etc. b. List of pending indents on Stores Dept. and S&T Workshops. c. List of pending Purchase orders. d. List of materials received from Trade and Railway Workshops. e. Scrap disposal.

Page No.5 V. 2012 /PROGRESS OF SIGNALLING WORKS FOR THE MONTH OF APRIL- 2012 Enclosed as Annexure-D.

VI. /COMPLIANCE REPORT FOR INSPECTION NOTES OF HQRS.OFFICERS NIL VII. / /STATUS REG. HANDING OVER OF STATIONS/ SECTIONS TO DIVISION: No pending case /POSITION OF PENDING SANCTIONS TO ESTIMATES: NIL

VIII.

IX. - / /ACTION PLAN FOR DRAWAL OF COMPLETION REPORT/POSITION OF COMPLETION REPORT No Source Work Name of the Remarks Target for of Code Work completio financ n Report. e 1 DF4 330069 MAS,PGT,TPJ CR already drawn sent to ---on calling on signals Accounts for vetting. 2 CAP 160080 GPD-SPE ONE Final books adjustment has May 2012 IBS to be made in Account office. AJJ-RRI 3 DRF 330122 Awaiting PCR from Engg and May 2012. (North-West Electrical Departments
Cabin)

4 5

Capital 160085 DRF 330099

ICHCHIPUTTUR IBS in AJJ-TRT MAS on B route (KBT-TO)

DRF

330098

MAS on A route

Awaiting PCR from Engg. May 2012. and Electrical Departments. Final contract bill will be June 2012. passed in November 2011. Final books adjustment has to be made in Accounts office. Final contract payment June 2012. already over. Final Books adjustment has to be made in Accounts office.

DRF

330103

ENR-GPD-RRI

Final contract bill will be June 2012. passed in September 2011. Final books adjustment has to be made in Accounts office.

Page No.6 X. REPORT: - / /AUDIT PARAS / INSPECTION

2011- Inspection Report- Part I Non-Personal and Personalduring October 2011 Report to be replied. XI.
1)

/ASSISTANCE REQUIRED FROM HQ: Presently Dy. CSTE/Proj/MS office is working in very old temporary building which was constructed for more than 30 years. In the present monsoon it has been observed that the entire building is leaking. The repairs works were carried out with the help of the Division during the year 2005.

With all the being very old building it is not sustaining the repairs. Lot of files and drawings are kept in the rooms that are too badly leaking. In view of the above it is suggested that the entire office building may be reconstructed or got shifted to convenient location, so that day to day office work is not hampered. This will also boost up the morale of the staff working in the office. It is requested that one Gr.I OS may be posted to this unit to head the Ministerial staff
2)

XII: / / SYSTEM IMPROVEMENT/ INNOVATIONS DONE. - NIL