Guide trough
Fixed point
Cable reserve
Support structure
Guide trough
Support structure
Fixed point
Moving end
Moving end
max. 3mm Guide trough with glide bar Guide trough without glide bar
b E-Chain has to be free movable along the entire travel length. Other obstacles or crane parts must not disturb operation area! wrong!
h b
6
z = 2000 3 x5 L-profile Level the support structure y5 x5 wrong! Center line Crane rail = reference Level the L-profile Crane rail and support structure have to be aligned. wrong! wrong! right wrong!
x5 Crane rail
8
Center line
Check support strukture before trough installation. Necessary reworks to be corrected before next installation step.
Ba
No gap = wear on chain links. E-Chain is blocked. 2 +1mm Ba +4 Ba + 4 = L L L /2 Spacer tool Big gap = wear on chain links and cross bar.
+2
2 +1mm
10
E-Chain Pre-Assembly
Check part no. on E-Chain, before assembly. For example: 5050C- 4040C- Series Chain s number 5050C.30.300.0 5050C 30 300 0
Series Number Width Radius of chain Colour
E-Chain assembly Lay the fixed point (part 3) into the trough and assemble part 2 until you reach the mounting end.
part 3
part 2
12
E-Chain Pre-Assembly
Make sure that fixed point position is according to igus drawings, relative to the travel stroke. Lay thee preassembled E-Chain into the guiding tough.
Fixed point
Red flag
Fixed point
Moving end
14
wrong!
Alternative instalation: Open the crossbars, lay the cables in the E-Chain and close it.
Check the interior separation of E-Chain. All seperators plumb and tight? right wrong!
16
Attach E-Chain
Leave a spare cable loop for cable adjustment at fixed point and moving end.
Make shure that fixed point is at correct position and fix it with allan screws (DIN 912 / EN ISO 7462).
wrong!
18
Adjust Cables
Correct cable adjustment
wrong!
wrong!
wrong!
20
Move the E-Chain slow and carefull to both end positions and check cable arrangement. Doublecheck after a few test cycles.