Aggregate Production Planning

Aggregate planning involves matching supply and demand over the medium term, usually 12 months in the future. The aim is to set output levels to account for fluctuating demands. Factors considered include inventory levels, outsourcing, overtime, hiring and firing of staff. The goal is to minimize total costs over the planning period while meeting demand and complying with company policies. Inputs for aggregate planning include available resources, demand forecasts, and costs of production alternatives and inventory holding.

Uploaded by

Piyush Bhardwaj
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
77 views2 pages

Aggregate Production Planning

Aggregate planning involves matching supply and demand over the medium term, usually 12 months in the future. The aim is to set output levels to account for fluctuating demands. Factors considered include inventory levels, outsourcing, overtime, hiring and firing of staff. The goal is to minimize total costs over the planning period while meeting demand and complying with company policies. Inputs for aggregate planning include available resources, demand forecasts, and costs of production alternatives and inventory holding.

Uploaded by

Piyush Bhardwaj
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Aggregate planning

From Wikipedia, the free encyclopedia

Aggregate planning is an operational activity that does an aggregate plan for the production process, in advance of 2 to 18 months, to give an idea to management as to what quantity of materials and other resources are to be procured and when, so that the total cost of operations of the organization is kept to the minimum over that period.. The quantity of outsourcing, subcontracting of items, overtime of labour, numbers to be hired and fired in each period and the amount of inventory to be held in stock and to be backlogged for each period are decided. All of these activities are done within the framework of the company ethics, policies, and long term commitment to the society, community and the country of operation. Aggregate planning has certain pre required inputs which are inevitable. They include:

Information about the resources and the facilities available. Demand forecast for the period for which the planning has to be done. Cost of various alternatives and resources. This includes cost of holding inventory, ordering cost, cost of production through various production alternatives like subcontracting, backordering and overtime.

Organizational policies regarding the usage of above alternatives.

"Aggregate Planning is concerned with matching supply and demand of output over the medium time range, up to approximately 12 months into the future. Term aggregate implies that the planning is done for a single overall measure of output or, at the most, a few aggregated product categories. The aim of aggregate planning is to set overall output levels in the near to medium future in the face of fluctuating or uncertain demands. Aggregate planning might seek to influence demand as well as supply."

[edit]Aggregate [edit]Level

Plan Strategies

plans

Use a constant workforce & produce similar quantities each time period Use inventories and backorders to absorb demand peaks & valleys

[edit]Chase

plans

Minimize finished good inventories by trying to keep pace with demand fluctuations Matches demand by varying either work force level or output rate

[edit]Hybrid

Strategies

Build-up inventory ahead of rising demand and use backorders to level extreme peaks Layoff or furlough workers during lulls Subcontract production or hire temporary workers to cover short-term peaks Reassign workers to preventive maintenance during lulls

[edit]Problems
Smoothing

related to Aggregate Planning

Smoothing refers to costs that result from changing production and workforce levels from one period to the next.

Bottleneck Problems

It is the inability of the system to respond to sudden changes in demand as a result of capacity restrictions.

Planning Horizon

The number of periods for which the demand is to be forecasted , and hence the number of periods for which workforce and inventory levels are to be determined, must be specified in advance.

Treatment of Demand Aggregate planning methodology requires the assumption that demand is known with certainty. This is simultaneously a weakness and a strength of the approach.