Specifications Concrete Deck/Thin Set Tile Overlayment
Specifications Concrete Deck/Thin Set Tile Overlayment
Specifications Concrete Deck/Thin Set Tile Overlayment
PART 1 – GENERAL
A. Drawings and general provisions of the Contract, including General and Supplementary
Conditions and Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
B. Related Sections: The following Sections contain requirements that relate to this Section:
A. General: Provide a waterproofing system that prevents the passage of liquid water under
hydrostatic pressure and complies with physical requirements as demonstrated by testing
performed by an independent testing agency of manufacturer’s current waterproofing
formulations and system design.
1.4 SUBMITTALS
A. Submit Product Data for each type of waterproofing specified, including manufacturer’s
printed instructions for evaluating, preparing, and treating the substrate, technical data,
and tested physical and performance properties.
B. Project Data - Submit Shop Drawings showing locations and extent of waterproofing,
including details for substrate joints and cracks, sheet flashing, penetrations, and other
termination conditions.
C. Samples – Submit representative samples of the following for approval:
C. Field Sample: Apply waterproofing system field sample to 100 sq./ft. (9.3 sq./m.) of deck or
wall to demonstrate surface preparation, joint and crack treatment, thickness, texture, and
standard of workmanship.
1. Notify Architect one week in advance of the dates and times when field sample will be
prepared.
2. If Architect determines that field sample, does not meet requirements: reapply
waterproofing until field sample is approved.
3. Retain and maintain approved field sample during construction in an undisturbed
condition as a standard for judging the completed waterproofing. An undamaged field
sample may become part of the completed Work.
C. Remove and replace material that cannot be applied within its stated shelf life.
B. Perform work only when existing and for-cast weather conditions are within manufacturer’s
recommendations for the material and application method used.
C. Minimum clearance of 24 inches is required for application of product. For areas with less
than 24-inch clearance, the product may be applied by hand using ECOLINE-R.
E. All plumbing, electrical, mechanical and structural items to be under or passing through the
waterproof membrane shall be positively secured in their proper positions and
appropriately protected prior to membrane application.
F. Waterproof membrane shall be installed before placement of reinforcing steel. When not
possible, all exposed reinforcing steel shall be masked by General Contractor prior to
membrane application.
1.8 WARRANTY
A. General Warranty: The special warranty specified in this Article shall not deprive the
Owner of other rights the Owner may have under other provisions of the Contract
Documents, and shall be in addition to, and run concurrent with, other warranties made by
the Contractor under requirements of the Contract Documents.
PART 2 – PRODUCTS
2.1 MANUFACTURERS
A. Fluid applied waterproofing system – ECOLINE-S: a single course, high build, polymer
modified, asphalt emulsion. Waterborne and spray applied at ambient temperatures. A
nominal thickness of 80 dry mils (60 mil minimum), unless specified otherwise. Non-toxic
and odorless. ECOLINE-R has similar properties with greater viscosity and is roller or
brush applied. Manufactured by EPRO Services, Inc.
A. Sheet Flashing: 60-mil reinforced modified asphalt sheet good with double-sided adhesive.
C. Joint Detailing Sealant Mastic: ECOLINE-T, a high viscosity polymer modified water based
asphalt material.
3.1 EXAMINATION
A. Examine substrates, areas, and conditions under which waterproofing systems will be
applied, with Installer present, for compliance with requirements. Do not proceed with
installation until unsatisfactory conditions have been corrected.
B. Mask off adjoining surfaces not receiving waterproofing to prevent spillage or over spray
affecting other construction.
C. Close off deck drains and other deck penetrations to prevent spillage and migration of
waterproofing fluids.
D. Remove grease, oil, form release agents, paints, and other penetrating contaminants from
concrete.
E. Remove fins, ridges, and other projections and fill honeycomb, aggregate pockets, grout
joints, tie holes, and other voids with ECOLINE-T, hydraulic cement, or rapid-set grout.
B. Apply two coats of ECOLINE-T (30 mil each) and embed a joint reinforcing strip in
preparation coat and apply a second coat over embedded joint reinforcing strip ensuring
its complete saturation and covering. (See drawing B).
1. Terminations should be treated 6 inches on each side for both vertical and horizontal.
2. Penetrations should be treated in a 6inch radius around penetration and 3 inches onto
penetrating object.
B. Less than 1/16 in. - Apply two coats of ECOLINE-T waterproofing, 6 inches on each side of
joint or crack and embed a joint reinforcing strip in preparation coat and apply a second
coat over embedded joint reinforcing strip ensuring to complete saturation and covering.
C. Greater then 1/16 in. – Rout joint or crack, install backer-rod and sealant to bring flush to
surface. Apply a coat of ECOLINE-T to joint or crack, 6 in. on each side, embed a joint
reinforcement strip and apply a second coat, where indicated or required according to
waterproofing manufacturer’s recommendations.
(See drawings C & D)
A. Install ECOSHIELD-P protection course with fabric side up and overlapped seams over
nominally cured membrane no later than recommended by manufacturer and before
starting subsequent construction operations.
B. Secure ECOSHIELD-P protection course seams with ECOLINE-R and attach to adhesive
strips (sheet flashing that does not penetrate waterproofing) as recommended by
manufacturer.
B. Test areas are to be patched over with ECOLINE-S to an 80-mil minimum dry thickness,
extending a minimum of one-inch (1”) beyond the test perimeter.
B. Clean spillage and soiling from adjacent construction using cleaning agents and
procedures recommended by manufacturer of affected construction.