Risk Analysis
Risk Analysis
htm
lightning,
basic
insulation
lightning
level,
1. Introduction
Typically, more than 2,000 thunderstorms are active throughout the world at a given moment, producing in the order of 100 lightning flashes per second (Hileman, 1999). Lightning activity in South
142
East Asia, especially in Malaysia, ranks as one of the highest in the world. Tenaga Nasional Berhad Research (TNBR) Malaysia has recorded as high as 320 kA lightning impulse current in Malaysia using their lightning detection network system (LDNS) (TNBR, 2008). Substations can be considered as the most crucial parts in power systems. This is because it consists of such an expensive equipment that is the power transformer which is the essential part to the system to operate as a feeder check point either as stepping up or stepping down the incoming line voltage. There are many studies describing how one could model the substation for transient analysis studies (IEEE Modelling and Analysis of System Transient WG, 1996, IEEE Power Engineering Society, 1999, IEEE Power Engineering Society, 1996, IEC, 1993, Hileman, 1999). The equivalent circuit of the substation is basically modelled by a group of important input parameters to represent the elements inside the substation. Usually for transient analysis studies, parts of transmission line properties must also be included in the overall simulation model such as the transmission line connected to the substation entrance with a few span, phase conductor and transmission line tower because the substation is normally regarded having a perfect shielding and the voltage stresses penetrating inside the substation only via the lines (Savic and Stojkovic, 1994).
2. Simulation modelling
The case studies include four cases of investigation concerning the influence of arrester presence in the system. The lightning current was injected at the top of the last tower before entering the substation while voltage level at selected points are observed as the voltage propagate to the substation. Below are the lists of mentioned case studies: 1. With both arresters (SA1 and SA2) are installed 2. Only SA1 is installed 3. Only SA2 is installed 4. Without both arresters The voltage level at four crucial points had been monitored, that are E1 at the substation entrance, E2 at the first surge arrester to protect the capacitive voltage transformer, CVT, E3 at the second surge arrester and finally at the power transformer, E4. Two main locations or points will be observed which are the E2 and E4, where there are transformers located at these points. Figure 1 depicts the substation system modelled for case studies.
Figure 1: Substation model for case studies
143
Table 1:
Model Lightning Strike Overhead Line
Substation Equipments
Table 2:
Capacitor CCVT CISOa CT CB CISOc CBb CB CTx
Table 2 describes the comparison of capacitor value between TNB calculation approach and IEEE recommendation base on 115 kV US substation system model. For this work, TNB calculation approach of capacitor values was adapted to model the system as it more or less agreed with the value recommended by IEEE WG 3.4.11 (1992) and for the actual analysis. The distance between each substation equipments are as below: Tsub1 =3.0 m Tsub2 =3.5 m Tsub3 =3.5 m Tsub4 =3.0 m Tsub5 = 4.0 m Tsub6 = 4.5 m Tsub7 = 3.0 m Tsub8 = 3.0 m Tsub9 = 14.5 m Tsub10 = 3.0 m Tsub11 = 3.0 m Tsub12 = 5.0 m
144
145
Table 3 describes the summary of our case study which the worst case was when there was no arrester installed, since 35 kA of lightning current level had already caused the transformer at point E4 to breakdown. For assessing the best arrester placement, it really depends on the asset to be protected in the substation. If there is only power transformer available to be protected, then the best option is to have the SA2 installed as close as possible to the transformer to ensure the voltage level at the power
146
transformer within the safety margin in the presence of unpredicted very high transient current level injection.
Table 3:
Case Study Case i. Case ii. Case iii. Case iv.
4.2. Case comparison at selected current, I The purpose of this analysis is to observe the difference of voltages level at points E1, E2, E3 and E4 at selected lightning current. For current of 40 kA, the comparison of the voltages values can be seen in Table 4 while Tables 5 and 6 show the results for the lightning current at 80 kA and 120 kA respectively.
Table 4: Voltage values at lightning current of 40 kA
E1 759 759 759 759 E2 216 223 306 657 E3 204 284 220 688 E4 208 291 225 692
In the case of no surge arresters installed at substation (vandalism or failed to operate), this current has already caused the transformer damage due to the maximum voltage level that exceeded the suggested BIL of 550 kV.
Table 5: Voltage values at lightning current of 80 kA
E1 1321 1321 1321 1321 E2 228 239 408 1222 E3 220 397 240 1278 E4 231 407 245 1282
While in Table 5, case 1 and 2 are still in safe condition at lightning current of 80 kA. This shows that SA1 is very important for helping discharging the lightning voltage at the entrance of the substation and protect the equipments in the substation section. Failure in operation of SA1 will cause a significant effect in terms of voltage level up at point E2 (if the current goes high), as demonstrated in the next result.
Table 6: Voltage values at lightning current of 120 kA
E1 1794 1794 1794 1794 E2 235 256 498 1741 E3 226 452 261 1818 E4 241 471 274 1821
Result in Table 6 shows the voltages level at lightning current of 120 kA. Whilst the voltage level on case 1 and 2 are below the BIL value, the voltage at point E2 increases as the lightning current
147
increases to 120 kA, even though they are not exceeding the BIL value of the transformer. For case 4, the equipments especially the transformers were already damaged by overvoltage caused by the lightning impulse. 4.3 Result comparison for case 4 Figure 7 shows the I-V characteristic for case 4. The graph is clearly shown that without SA1 and SA2, low lightning current can already caused damage to the transformers and the value is around 25 to 35 kA for all points. Therefore, the utility should be concerned and aware of the surge arresters installation, which is used to protect the transformers in the substation section. More care and cautions are needed to avoid the damage and vandalisms which may affect the performance of transformers and other equipments in the substation section.
Figure 7: I-V characteristics graph for case 4
I-V characteristic 220 200 180 Lightning C urre I (kA nt, ) 160 140 120 100 80 60 40 20 0 0 300 600 900 1200 1500 1800 2100 2400 2700 3000 Voltages, E max (kV) E 1max E 2max E 3max E 4max
5. Conclusion
The modelling concept and parameter selection to model a substation were presented for the simulations of substation performance in order to investigate the failure probability of crucial component in the substation. The validation of the result was earlier compared with previous work done by Savic and Stojkovic to make sure the model was valid. The results showed that the default arrangement of TNB substation (Case 1) was well protected, but the cost for implementation of such arrangement is high. The placement of arrester is crucially needed in order to optimize the substation performance in term of its reliability and cost effective. The arrester is best suited for optimized performance if it is installed near to the crucial point compared to the substation entrance. In this case, it is very important to have this surge arrester as close as possible to the equipment to be protected.
148
References
[1] [2] [3] [4] [5] [6] [7] Hileman, A. R., 1999. Insulation coordination for power system. 1st ed, Marcel Dekker Inc., New York. ISBN: 0824799577 TNBR, 2008. Lightning Detection Network System Database. IEEE Modeling and Analysis of System Transient WG, 1996. Modeling guidelines for fast front transients. IEEE Transactions on Power Delivery, vol. 11, pp 493-506. IEEE Power Engineering Society, 1999. IEEE Standard 1313.2-1999: Guide for the application of the insulation coordination. IEEE Power Engineering Society, 1996. IEEE Standard 998-1996: Guide for direct lightning stroke shielding of substation. IEC, 1993. Insulation coordination Part 1: Definition, principle and rules. IEC 71-1: International Standard. Savic, M and Z. Stojkovic, 1994. High voltage substation equivalent circuits in the lightning performance estimation. IEE Proc. Generation Transmission Distribution, vol 141(2). pp 99105. CIGRE (1991). Guide to procedures for estimating the lightning performance of transmission lines. CIGRE Brochure 63. Woodford, D, 1998. PSCAD/EMTDC: Getting started manual, Version 3. Manitoba HVDC Research Centre Inc., Canada. IEEE WG 3.4.11, 1992. Modeling of Metal Oxide Surge Arresters. IEEE Transaction on Power Delivery, vol. 7, pp.393-398. Martinez, L. A and F. Castro-Aranda, 2004. Modeling overhead transmission lines for line arrester studies. IEEE Power Engineering Society General Meeting, 6-10 June 2004, Colorado, USA. pp: 1125- 1130 Goudarzi, A and H. Mohseni, 2004. Evaluation of mathematical models of metal oxide surge arrester for energy absorption study. 39th International Universities Power Engineering Conference, Bristol, UK. pp: 211-214
[12]