Operating Procedures
Operating Procedures
FOR
NORTHERN REGION
(as mandated by the Indian Electricity Grid Code)
REV-00
(SEPTEMBER, 2000)
CONTENTS
ANNEXE
1
CHAPTER – 1
GENERAL
1.1 OVERVIEW
1.2.1 The Section 6.0 of the IEGC covers the operational aspects for the
regional grids and clause 6.1(d) of the code specifies the requirement to
prepare the set of detailed internal operating procedure for each regional
grid to be developed and maintained by respective RLDC, in consultation
with the regional constituents. This document viz. “Operating Procedures
for Northern Region” has been prepared in line with the above
requirements and consists of the following chapters:
Chapter – 1 : General
Chapter – 2 : Network Security & System Operation
Chapter – 3 : Demand Estimation & Control
Chapter – 4 : Outage Planning
Chapter – 5 : Bilateral Agreements
Chapter – 6 : Scheduling & Despatch
Chapter – 7 : Grid Disturbances & Revival
Chapter – 8 : Event Information & Reports
Chapter – 9 : Settlement System
ii) Considering that demand estimation & control is under the purview of the
State Load Despatch Centres (SLDCs), chapter 3 describes briefly the
SLDC’s interface with NRLDC with respect to demand estimation &
control.
iii) Chapter 4 contains the procedure to be followed for outage planning &
availing the same, handling unforeseen outages and deferment of
planned shutdowns.
1.2.3 This document does not cover the procedure to be followed in case power
supply has be regulated to any utility on account of non-payment of dues.
2
The same would be implemented by NRLDC in line with the directives
issued by CERC from time to time.
1.2.4 The details indicated in this document are intended to serve only as a
guideline for efficient system operation and are not exhaustive. In
particular, these procedures do not cover the tools required for efficient
and effective system operation and analysis viz. Communication Systems,
Supervisory Control & Data Acquisition Systems (SCADA), Energy
Management Systems (EMS), and other recording and control equipment.
It is expected that these requirements would be provided by all concerned
to enable efficient system operation. Further, these procedures are to be
read in conjunction with the various clauses as given in Indian Electricity
Grid Code (IEGC) and are without prejudice to the NRLDC’ s power to
give directions and exercises supervision and control as stated under
Sections 55(3) and 55(6) of the amended Electricity Supply Act, 1948.
1.2.5 This document would come in force with immediate effect. It would also
be reviewed annually or earlier in case significant changes taking place in
the system warrant a review.
*****
3
CHAPTER-2
2.1 OVERVIEW:
This chapter describes the actions required on the part of the system
operator to keep the network secured at all times against contingencies. It
also describes the actions required to maintain system parameters close to
nominal values in day-to-day operation.
2.2.1 Background
The system planner generally designs & provides a power system, which
complies with the various transmission security standards and associated
criteria mentioned in section 3.5 of the IEGC. Nevertheless, certain
assumptions are made while planning and designing the system, which may
not be satisfied in actual operation. These deviations could be classified as:
The second category of events, are those outside the operator’s control such
as extreme weather conditions either affecting the reliability of transmission
system (e.g. thunderstorm, cyclones) or resulting in uneven demand growth
(e.g. widespread drought in certain pockets of the system). There could also
be departures from planned generation pattern due to various conditions.
These would fall under the category of crisis management and tackled as
such.
(iii) The substation operators must ensure the above condition even
when any lightly loaded line is opened to control overvoltage. Such
opening of lines is generally superimposed over other line outages
on account of faults created by adverse weather conditions
resulting in reduced security of the system.
(v). In order to damp out the low frequency oscillations in the system,
the power system stabilizers on the generating units would be
tuned as per the programme drawn out by the Central
Transmission Utility (CTU), in consultation with the constituents.
(vii). In line with section 6.2(e) to 6.2(g) of the IEGC, the generating
units should be on free governor operation.
5
2.2.3 Defence Mechanisms For The System
ii) Each regional constituent shall provide adequate and reliable communication
facility with NRLDC as well as internally and with other constituents in order
6
to ensure exchange of data / information necessary to maintain reliability and
security of the grid.
One of the main assumptions of the power system planner is that the system
parameters viz. frequency, voltage remain close to nominal values. This
section lists the measures to be adopted by the system operators at SLDCs /
ISGS / substations for frequency and voltage control.
All the regional constituents would make all possible efforts to ensure the
maintenance of grid frequency within the normal band i.e. 49.0 to 50.5
Hz.This would be ensured by adhering to the following steps:
i) Each SLDC shall regulate the load / own generation under its control
so that it may not draw more than its net drawal schedule during low
frequency conditions and less than its drawal schedule during high
frequency conditions.
ii) Each of the Inter State Generating Station (ISGS) shall maintain
generation such that it may not generate less than its generation
schedule during low frequency conditions and more than its
generation schedule during high frequency conditions
iii) In case any state constituent is likely to face power shortage situation
despite requisitioning its full entitlement from ISGS, then it shall
endeavour to enter into a bilateral agreement with the other state
constituents having a power surplus and vice-versa. In any case,
during low frequency conditions no state would carry out
overdrawals.
While the grid frequency is higher than 50.5 Hz, the MW generation at no
generating station (irrespective of type and ownership) shall be increased.
Provided that when the frequency has risen from a previous lower level to
50.5 Hz. or higher, and due to normal governor action, the MW output of a
7
generating unit has fallen to a level requiring oil support or which results in
unstable operation of the unit, then the MW output may be increased to the
lowest level,
- at which oil support is not required, and
- at which the unit can operate in a stable and safe manner.
Similarly, no generating unit shall be synchronised with the grid while the
grid frequency is above 50.5 Hz. or higher, except with the specific
concurrence of NRLDC and in case of nuclear units, which may have to be
re-synchronised to prevent poisoning out of the reactor. NRLDC would
separately issue frequency linked despatch guidelines to be followed by
each power station.
NRLDC would observe the drawal pattern of the SLDC’s control area &
attention would also be drawn to wilful overdrawals resulting in low
frequency operation. All SLDCs are expected to suo moto curb such
overdrawals and abide by NRLDC’s instructions in this matter. In case of
any violation, NRLDC would take such action as it may deem fit including
physical regulation.
Constituents would ensure that the generating units synchronised with the
grid are operated on free governor mode of operation and with necessary
primary and secondary control in line with sections 6.2 (e), 6.2 (f), 6.2 (g),
and 6.2 (h) of IEGC.
As defined in the IEGC section 6.2 (g), the operating range of the voltage at
various voltage levels of grid is as follows:
Voltage in KV (rms)
8
The maximum and minimum values in the above table are the outer limits
and all the constituents would endeavour to maintain the voltage level well
within the above limits.
All generating units shall keep their Automatic Voltage Regulators (AVRs) in
operation and Power System Stabilisers (PSS) in AVRs shall be tuned in line
with clause 6.2 (j) of IEGC
The constituent states shall take action in regard to VAR exchange with the
grid looking at the topology and voltage profile of the exchange point. In
general the beneficiaries shall endeavour to minimise the VAR drawal at
interchange point when the voltage at that point is below nominal value and
shall not return VARs when the voltage is above the nominal value. In fact
the beneficiaries are expected to provide local VAR compensation so that
they do not draw any VARs from the grid during low voltage conditions and
do not inject any VARs to the grid during high voltage conditions.
In order to improve the overall voltage profile, the generators shall run in a
manner so as to have counter balancing action corresponding to low / high
supergrid voltage and to bring it towards the nominal value. In order to
achieve the same, all generators shall generate reactive power during low
voltage conditions and absorb reactive power during high voltage
conditions as per the capability limits of the respective generating units. The
On-Load Tap Changers (OLTCs) on the generator transformers wherever
available, should also be used to achieve this. Off load tap changers would
also be used to take care of seasonal variations in the voltage profile.
i) In the event of high voltage (e.g., 400kV bus voltages going above
410kV), the following specific steps would be taken by the
respective grid substations / generating station at their own, unless
specifically mentioned by NRLDC otherwise;
9
! The bus reactors be switched in
! The manually switchable capacitor banks be taken out
! The switchable line/ tertiary reactors be taken in
! Operate synchronous condensers for VAR absorption
! Operate hydro generators / gas turbines as synchronous
condenser for VAR absorption wherever possible
! Opening of the lightly loaded lines in consultation with
NRLDC, keeping in view the security of the balance
network.
ii) In the event of low voltage, (e.g., 400kV bus voltages going down
below 390kV), the following specific steps would be taken by the
respective grid substations / generating station at their own, unless
specifically mentioned by NRLDC otherwise;
All the state constituents shall identify the radial feeders in their areas which
have significant reactive drawals and which can be disconnected in order to
improve the voltage conditions in the event of voltage dropping to low levels.
The details of all such feeders shall be kept handy in the respective control
rooms and standing instruction would remain with the operating personnel to
obtain the requisite relief in the hour of crisis by disconnecting such feeders.
In case the state constituents do not take the requisite measures and the
voltage drops down to critically low levels (say 360kV and below at 400kV
bus), then NRLDC may resort to regulatory measures by opening of lines
including those, feeding radial loads in the areas of defaulting constituents.
While taking such action, NRLDC would duly consider that the same does
not result in affecting ISGS generation.
In the event of persistent high voltage conditions when all other reactive
control measures as mentioned earlier have been exhausted, selected lines
10
shall be opened for voltage control measures. The opening of lines and
reviving them back in such an event would be carried out as per the
instructions issued by NRLDC in real time and as per the standing
instructions issued from time to time. While taking such action, NRLDC
would duly consider that the same does not result in affecting ISGS
generation.
The control rooms of all SLDCs, power plants, grid substations as well as
any other control centres of regional constituents shall be manned round
the clock by qualified and adequately trained manpower who would remain
vigilant and cooperative at all the times so as to maintain the system safety
and security and operate it in a most optimum manner.
******
11
CHAPTER – 3
3.1 OVERVIEW
3.2.1 The SLDCs would forecast demand (MW peak & energy in MWh) on an
annual, quarterly, monthly, weekly and ultimately on daily basis, which
would be used in the day-ahead scheduling. Each SLDC is expected to
maintain a historical database for the purpose and be equipped with the
state-of-the-art tools such as Energy Management System (EMS) for
demand forecasting. Ideally, the forecasts should be on hourly basis
(8760, 720 & 168 values respectively in the annual, monthly and weekly
forecasts) rather than mentioning only the peak MW and energy
requirements for the period.
3.2.2 The annual, quarterly and monthly demand forecasts would be used in
the outage plan prepared by REB Secreteriat in consultation with all the
constituents.
3.2.3 Attention would also be paid by SLDCs in demand forecasting for special
days such as important festivals and National Holidays having different
crests and troughs in the daily load-curve as compared to normal days.
3.2.4 The above demand estimation covers only active power. It is also
important that, the reactive power requirements are also forecasted right
from substation level by each SLDC. The reactive power planning
exercise and programme for installation of reactive compensation
equipments should take care of these requirements also.
12
3.3 DEMAND CONTROL
3.3.1 As stated earlier, primarily the need for demand control would arise on
account of the following conditions.
3.3.2 As already mentioned in section 7.4.5 of the IEGC, the SLDCs / STUs
would regularly carryout the necessary exercises regarding short-term
and long-term demand estimation for their respective states to enable
them to plan in advance as to how they would meet their consumers load
without overdrawing from the grid. Further, a tight control on the drawals
from the grid is not mandated and the deviations from the schedule would
be priced appropriately. However, the following deviations from the
schedule & other violations would have to be controlled by the SLDCs.
3.3.3 Demand control would have to be exercised under these conditions by the
SLDCs, which could be done by either of the following methods or a
combination thereof.
13
3.3.5 Each SLDC would also identify feeders drawing heavy quantum of
reactive power and disconnect the same under low voltage conditions. As
already mentioned in Sec.2.3.2.3 of Chapter-2, necessary metering
arrangements for identifying such feeders would be provided by the
SLDCs.
3.4.1 In the event of load crash in the system due to weather disturbance or
other reasons, the situation would be controlled by the SLDCs/ ISGS by
the following methods:
*****
14
CHAPTER-4
OUTAGE PLANNING
4.1 OVERVIEW
The earlier chapters have dwelt on the network security, reliability and
demand estimation. The next logical step is outage planning of generating
units, transmission lines and ICTs subject to the above constraints. This
would have to be done in line with section 6.7 of the IEGC. As already
mentioned earlier, the list of important elements of the Northern Regional
Grid is enclosed at Annex-I. Outage planning would be done centrally only
in respect of these lines, ICTs and generating units, allowing sufficient
discretion to the SEBs / STUs in respect of other lines and units, unless
otherwise decided by NREB Secreteriat. Outages in the system have an
effect on the network security and have to be planned carefully. Power
system studies would have to be done by the NREB and NRLDC for the
outage planning (up to monthly review) and for day-to-day operations
respectively, to assess the effect of outages on the grid security. Further,
outage plan finalised would also have commercial implications for each
SEB / STU / ISGS after the implementation of ABT in the region, the
same would have to be done meticulously.
(i) Constituents will forward to NREB Secretariat the required data for
planning for the next financial year, by 30th November.
(ii) NREB Secretariat will issue the draft outage programme to all the
regional constituents and NRLDC by 31st December.
(iii) The mutually agreed final outage plan shall be intimated by NREB
Secretariat to all regional constituents and NRLDC for
implementation latest by 31st January.
(I). In the months just preceding to each quarter i.e. during the second
fortnight of March, June, September and December the outage
plans for the balance part of the financial year shall be reviewed in
15
joint meetings to be attended by all regional constituents and
NRLDC and co-ordinated by NREB secretariat. The revisions in the
outage plans if any on the basis of above quarterly meetings shall
be issued by NREB Secretariat to all concerned before the end of
the respective months i.e. by 31st March, 30th June, 30th
September and 31st December respectively.
(ii). Monthly review of the outage plan for the current month and the
consecutive month would be done in the Operation Co-ordination
Committee (OCC) of NREB meeting, generally held in the first
week of every month. NREB Secretariat would issue the outage
plan so frozen in this meeting, to all constituents and NRLDC within
next two working days.
4.3.1 NRLDC would review on daily basis the outage schedule for the next two
days and in case of any contingency or conditions described in Sec.6.7.4
(g) of the IEGC, defer any planned outage as deemed fit clearly stating
the reasons thereof. The revised dates in such cases would be finalised in
consultation with the constituent.
4.3.2 For a transmission element the outage of which shall affect more than one
constituent, the information about the approval or deferment shall be
communicated by NRLDC to all such constituents so that they may
remain informed about the said outage
4.3.3 In respect of important elements of the grid, a final code would have to be
obtained from NRLDC before taking the said element for maintenance. All
preparatory works for maintenance must be done well in advance before
availing the code so as to avoid any idling time. Similarly, a code would
have to be obtained from NRLDC before reviving the element after shut
down.
4.3.4 The code issued by NRLDC for opening / revival of the circuit signifies
such approval only from the system point of view notwithstanding
anything contained in respect of safety measures and other switching
operations to be carried out locally. The related line / substation personnel
would be responsible for ensuring all safety precautions to be followed
16
while opening / closing of any element to avoid any threat to operating
personnel and equipment.
4.3.5 During the period of shutdown, the constituent(s) shall keep NRLDC
apprised regarding the status of work and the likely time of return of the
shut down. All efforts shall be made by the constituents for timely return
of shutdowns and delays if any shall immediately be reported to NRLDC
along with the reasons and likely time of return of shut down.
*****
17
CHAPTER-5
BILATERAL AGREEMENTS
5.1 OVERVIEW
5.2.1 NRLDC would require information in respect of bilateral exchanges for the
following:
5.2.2 The bilateral agreement must include the following minimum information.
(i) The date & time of commencement of the agreement and duration
for which it shall remain in force.
(ii) MW exchange (ceiling value) for each 15 minutes time block and
MWH for the entire day (ceiling value).
(iii) The delivery / take-off point for the purpose of accounting for
transmission losses.
18
(vi) Details of information that shall be exchanged with NRLDC in
respect of day-ahead scheduling and revisions thereof.
5.3.2 In case the figures given by the two constituents for any day is at variance
with each other, NRLDC would accord the following treatment for working
out the net drawal schedules.
(iii) If both the constituents indicate a different quantum then the lower
of the two values would be taken.
*****
19
CHAPTER-6
6.1 OVERVIEW
With the de centralised market mechanism being adopted for the country,
the power system under each SLDC constitutes a notional control area.
The states would have full operational autonomy and their SLDCs shall
have the total responsibility for scheduling and despatch of their own
generation (including generation of their captive licensees), regulating the
demand of their customers, scheduling of their drawals from ISGS,
arranging any bilateral exchanges and regulating their net drawal from the
regional grid. Section 7.4 of the IEGC indicates in detail the demarcation
of responsibilities for the purpose of scheduling and despatch. This
chapter illustrates the procedure for scheduling with the treatment to be
accorded for special situations.
6.2 GENERAL
6.2.1 For the purpose of scheduling each day would be divided into 96 blocks of
15 minutes duration each and for each block NRLDC would intimate each
SLDC the drawal schedule and to each ISGS the generation schedule in
advance and as outlined in Section 6.3 below.
6.2.2 The net drawal schedule of any state would be the sum of the ex-power
plant schedules from different ISGS and any bilateral exchange agreed
with other constituent state in Northern or any other region less estimated
transmission losses. The states would be required to maintain their actual
drawal from the grid close to such ‘net drawal schedule’ by regulating their
own generation and / or consumer’s load.
6.2.3 The generation schedule to each ISGS shall be the sum of the
requisitions made by each of the beneficiaries, restricted to their
entitlements and subject to the maximum and minimum value criteria or
any other technical constraint as indicated by NRLDC.
20
6.2.4 The states shall endeavor to maintain their drawals in such a manner that
they do not overdraw from the grid whenever the frequency is below the
normal value and do not underdraw whenever the frequency is above the
normal value. Similarly, each ISGS shall also endeavor to maintain their
generation in such a manner that they do not generate above schedule
during the period when frequency is above the normal value and do not
generate below schedule, whenever the frequency falls below normal
value.
6.2.5 The format of the generation schedule for all the ISGS and drawal
schedules for all the states shall be as per Annexe-II.
6.2.6 The generation scheduling for the stations under Bhakra Beas
Management Board (BBMB) would be co-ordinated & finalised well before
1500 hrs by BBMB in accordance with the requirements of the beneficiary
states viz. Punjab, Haryana, Rajasthan and Himachal Pradesh and
subject to the irrigation and hydrology constraints. The schedules so
finalised for each BBMB station would be communicated to NRLDC by
1500 hrs every day.
6.2.7 NREB Secretariat would ensure that any change in the allocations from
each ISGS is finalised and informed to all concerned at least a month in
advance so that trading of such capacity is facilitated. This is in line with
the spirit of clause 5.1.3 of the ABT order of the CERC.
6.3.1 By 1000 hrs everyday each ISGS shall advise NRLDC the station-wise
ex-power plant MW and MWh capabilities foreseen for the next day i.e.
between 0000 to 2400 hrs of the following day, at 15 minutes interval.
6.3.2 The above information shall be compiled by NRLDC and the MW and
MWh entitlements available to each state during the following day at 15
minutes interval shall be intimated by NRLDC to states by 1100 hrs.
6.3.3 After receipt of the information in regard to the availability from different
ISGS, all the states shall review such availability vis-à-vis their foreseen
demand and their own generating capability, including the bilateral
exchanges if any. By 1500 hrs the SLDCs would advise NRLDC their
requisition in each of the ISGS alongwith the bilateral exchanges they
intend to have with the other state / states and the estimates of demand /
availability in their own states. BBMB would also advise NRLDC of the
generation schedule finalised for its stations in consultation with its
partner states by 1500 hours. While indicating their station-wise
requisitions SLDCs must ensure that the step increase is not more than
1% of the previous requisition. SLDCs, while finalising their requisition
from ISGS, shall also consider estimated losses that would be deducted
from their ex-power plant schedules in ISGS & BBMB stations.
6.3.4 By 1700 hrs NRLDC shall convey to each ISGS the generation schedule
i.e., ex-power plant despatch schedule and to each state the net drawal
21
schedule i.e. the schedule at the periphery of the state (after deducting
the apportioned estimated transmission losses).
6.3.5 The SLDC/ ISGS may inform the modifications/ changes to be made if
any in the above schedule to NRLDC by 2200 hrs.
6.3.6 On receipt of such information and after consulting with the concerned
constituents if required, the NRLDC shall issue the final generation /
drawal schedule to each ISGS/SLDC by 2300 hrs.
6.3.7 The following specific points would be taken into consideration while
preparing the schedules:
(ii) After receipt of the requisitions from different states, while finalising
the generation schedule for ISGS, if it is found by NRLDC that such
schedules are not operationally reasonable particularly in terms of
ramping up / ramping down rates and ratio between minimum and
maximum generation levels, then NRLDC shall moderate the
schedule to the required extent under intimation to the concerned
constituents. The ramping up/ ramping down rates in respect of
different categories of stations would be based on the technical
data as substantiated by the generating stations and as mutually
agreed by the constituents. As regards the technical minimum, it
would have to be decided mutually between the beneficiaries and
the ISGS with subsequent information to NRLDC.
6.4.1 In case of forced outage of a unit, NRLDC will revise the schedules on the
basis of revised declared capability. The revised schedule will become
effective from the 4th time block, counting the time block in which the
revision is advised by the generator to be the first one.
6.4.3 In case of any grid disturbance, the scheduled generation of all the
generating stations and scheduled drawal of all the beneficiaries shall be
22
deemed to have been revised to be equal to their actual
generation/drawal for all the time blocks affected by the grid disturbance.
The exact duration of such grid disturbance would be declared by NRLDC
on the basis of mutually agreed guidelines.
6.4.6 If, at any point of time, RLDC observes that there is need for revision of
the schedules in the interest of better system operation, it may do so on
its own and in such cases, the revised schedules shall become effective
from the 4th time block, counting the time block in which the revised
schedule is issued by RLDC to be the first one.
6.4.7 On completion of the operating day i.e. after 2400 hrs, the final schedule
as implemented shall be issued by NRLDC after incorporating all before
the fact changes during the day of operation.
6.4.8 Various steps involved in the scheduling and the final schedule issued by
RLDC shall be open to all the constituents for any checking/verification for
a period of 20 days. In case any mistake/omission is detected, NRLDC
shall forthwith make a complete check and rectify the same.
Based on the above information, NRLDC would work out the requisitions
from each ISGS considering the merit order of energy charges in respect
23
of ISGS stations after translating the above MW values to ex-power plant
(considering an estimated level of transmission losses). This is without
prejudice to the procedure given for treatment of bilateral exchanges in
Chapter 5.
(i) In respect of hydro power stations where the MWh generation for
the day is fixed depending on the water inflows, MWh entitlement
of each beneficiary is fixed for the day. In case the beneficiaries
are allowed full freedom to requisition on 15-minute time block
basis restricted to their MWh entitlement for the day, it may result
in an ISGS schedule not practicable for the generator to follow
(part load or high cavitations zone operation on sustained basis). It
is therefore proposed that each SLDC submits its proposed total
requirement from the grid, for the next day to NRLDC by 1000
hours (format E at Annex-II). An interim schedule would be worked
out by adding this forecasted requirement for each state with a
weightage corresponding to percentage entitlement of the state in
that ISGS. This interim schedule would be rounded off to the
nearest feasible MW for the ISGS station to get the final schedule
of the ISGS. With this procedure, the generation schedule would
adequately reflect the weightage accorded to:
24
In line with section 5.7.3 of the CERC’s orders on ABT, each ISGS could
negotiate the terms with any beneficiary for such un-requisitioned power
on day-to-day basis. A copy of all such agreements would be made
available to NRLDC and NREB Secreteriat. These agreements would get
first priority in allocation of un-requisitioned surpluses.
6.6.1 With the implementation of ABT, the generation schedules and drawal
schedules would have a bearing on the energy charge payments to ISGS
and Unscheduled Interchange. Therefore, the timely and accurate
exchange of information in regard to schedule is of paramount
importance. This aspect gains extra importance particularly in view of the
CERC order on ABT dated 04.01.2000 wherein under schedule 1.0, para
xvi it is stated that “Generation schedule and drawal schedules
issued/revised by RLDC shall become effective from designated time
block irrespective of communication success”. In order to avoid any
adverse effect commercially on the ISGS / SLDCs, the need for a reliable
and fast communication arrangement for exchange of information in
respect of scheduling cannot be overemphasized. The arrangement
described below shall be followed to meet such an objective.
6.6.4 For this purpose NRLDC would have a dedicated INTERNET connection
on a leased circuit. In order to have fast access on the network, all the
25
constituents should also endeavour to have fast/dedicated connectivity on
INTERNET.
6.6.5 The ISGS and states shall upload the information to NRLDC site in regard
to scheduling at the agreed time and download the generation schedules
and drawal schedule from NRLDC site at the designated times.
6.6.7 NRLDC shall incorporate the required changes and the information in
regard to revision of schedule shall be flashed to the constituent
telephonically or e-mail / fax / coded message and accordingly the
constituents can download the revised schedule from NRLDC site.
6.6.10 At the end of the day the final schedule as implemented after
incorporating all ‘before the fact changes’ during the day of operation shall
be made available by NRLDC on the network and accordingly can be
downloaded by the constituents.
6.6.11 The conventional voice / fax arrangement would act as back-up in case of
failure of PC -to- PC communication link through INTERNET.
*****
26
CHAPTER -7
7.1 OVERVIEW:
7.3.1 The recovery of the system shall be carried out as mentioned in the
companion document ‘Black Start Procedures for Northern Region’
prepared by NRLDC in consultation with constituents and amended from
time to time.
vii) All generating units would be on free governor operation and the
excitation controlled to maintain proper voltage profile.
7.4.1 After a category ‘A’ or ‘B’ disturbance, the system would be deemed to
have been normalised if
ii) 80% of the total loss of generation at ISGS stations, during the
incident, has been revived.
7.4.2 After a category-C disturbance, the system would be deemed to have been
normalised if,
iii) At least one unit at the affected power station has been
synchronised (subject to a maximum of three hours of receipt of
start-up power)
29
In case of disturbance or any other contingency in the Northern Region or any
other neighbouring region, NRLDC shall permit exchange of such power with
the neighbouring region on Unscheduled Interchange (UI) basis, needed to
meet the essential load, start-up-power, railway traction and other such
emergent requirements for the duration of such contingencies.
*****
30
CHAPTER-8
8.1 OVERVIEW
8.2.1 Any tripping of an element falling under the list of “Important elements of
Regional Grid”, whether manual or automatic, shall be intimated by the
control centre of the constituent to NRLDC in a reasonable time say within
ten (10) minutes of the occurrence of the event. Along with the tripping
intimation, the reason for tripping (to the extent determined) and the likely
time of restoration shall also be intimated. Such intimation can be on
telephone or fax or e-mail.
8.2.2 Any operation planned to be carried out by a constituent which may have
an impact on the regional grid, or on any of the “Important Element of
Northern Regional Grid”, shall be reported by the constituent to NRLDC in
advance.
8.2.4 The intimation and the exact time of revival of an element falling under the
category of “Important Elements of Northern Regional Grid” whether
revived after a tripping or after a prolonged outage shall be intimated to
NRLDC immediately.
32
In line with the Clause 6.2(m) of the IEGC, all state constituents have to
provide automatic under-frequency load shedding in their respective
systems as per plans approved by NREB to arrest frequency decline that
could result in collapse / disintegration of the grid. In order to check and
ascertain their operation as per approved plans, the details of all such
tripping in their areas shall be intimated by each SLDC to NRLDC,
whenever required by the latter.
*****
33
CHAPTER -9
SETTLEMENT SYSTEM
9.1 OVERVIEW
9.2.1 As per Chapter 7, Clause 7.4.14 of IEGC, CTU shall be allowed to install
Special Energy Meters on all interconnections between the regional
constituents and other identified points for recording of actual net
interchanges and average frequency on 15-minute time block basis and
MVARh drawals under low/high voltage conditions.
9.2.2 In the Northern Region, all such inter-utility exchange points have already
been identified and shall be equipped with Special Energy Meters in order
to record the values stated above.
9.2.3 All the constituents shall extend the necessary assistance in timely
collection of data from these meters. For this purpose, a Data Collection
Device (DCD) would be handed over generally to each sub-station where
special energy meters are installed by POWERGRID. The agency in
whose sub-station / power station these Special Energy Meters are
installed would be responsible for transferring the data from the meters to
DCD and thereafter from the DCD to a local Personal Computer (PC) to
be provided by the agency. The data would then be transferred from the
sub-station to NRLDC on Public Switched Telephone Network (PSTN) /
Internet. The above activities would be carried out on weekly basis and
shall be completed between 0030 - 0400 hrs every Monday, wherever
DCD & PC location is the same and between 0030-1000 hrs. in case PC
is located at an adjacent sub-station. However till the existing
infrastructure limitations are overcome, the data could be transmitted to
NRLDC latest by 1300 hrs.
9.3.2 As mentioned in Section 9.2.3 above, all the energy meter data would
reach NRLDC by 1000 hours every Monday. NRLDC would carry out
data validation and in case of any problem, request any sub-station to
send the data again. Each substation would therefore have the necessary
back up of data on floppies while carrying out the steps in 9.2.3 above.
9.3.3 Reactive energy transactions between SEB to SEB and from one SEB to
the ISTS points would also be worked out by NRLDC & communicated
to NREB Secretariat and all the constituents.
9.3.4 All computations carried out by NRLDC shall be open to all constituents
for checking / verification for a period of 20 days and mistakes/
omissions detected, if any, would be rectified.
9.4.2 All computations carried out by NREB Secreteriat shall be open to all
constituents for checking / verification for a period of 20 days and
mistakes / omissions detected, if any, would be rectified.
*****
35
LIST OF IMPORTANT ELEMENTS
(Please see the file “Imp_element_NR.xls”)
FORMATS FOR DAILY SCHEDULING
(please see files “SCH_OPEC_form.doc” & “Annex-II.xls”)
ANNEX - III
EVENT REPORT
(From Constituents to NRLDC)
(As per clause 6.9.6 (c) of IEGC)
2. Location:
5. Antecedent conditions:
6. Interruption of
Quantum Duration
Particulars
(MW) From To
Demand
Generation
1 Disturbance recorder
2 Event logger
4 Any other
1. The details of the Important Elements in Northern Region (ownership wise) is as follows
2. The list of other ISTS trasmission lines in Northern Region not included in the " Important
Elements of Northern Regional Grid" is detailed subsequent to D above (page 25 to 30).
3. The following points are specifically indicated in respect of lists indicated from A to D above
i) The line(s) in the above context means a grid element from bus-bar to bus-bar and
includes all equipments such as associated circuit breaker(s), line reactor(s),
isolator(s), CVT(s), CT(s) etc.
ii) Any 400 kV bus shutdown at substations needs the approval of NRLDC.
iii) Outage or the intention to take under outage, of any major component/ sub-system,
which would reduce security/ redundancy level of the above elements, shall be
precisely intimated to NRLDC along with the likely time and status regarding
revival.
iv) In respect of two main and transfer bus switching scheme at 400 kV substations,
NRLDC shall be informed whenever the 400 kV transfer breaker(s) at any
substation is utilized for switching any line/ICT.
4. The criteria adopted in drawing up the lists indicated at point 1 above is as follows :
i) HVDC Rihand-Dadri bipole, HVDC B/B stations & all 800 kV/ 400 kV lines in the Region.
ii) All 220 kV lines belonging to the Central Transmission Utility (CTU).
iii) All 220 kV lines emanating from Inter State Generating Station (ISGS).
iv) Important 220 kV & 132 kV lines from the territory of one state to another state.
v) Lines affecting system security or forming part of islanding scheme.
vi) Lines feeding loads of a strategic/sensitive nature.
vii) All ISGS and BBMB power stations (excluding Ganguwal & Kotla)
viii) All units of 100 MW and above capacity.
Annex -I
Page 3 of 30
400 kV UPPCL
1 Obra-Panki S/C 386.60 UPPCL UPPCL UPPCL POWERGRID
2 Obra-Sultanpur S/C 230.40 UPPCL UPPCL UPPCL POWERGRID
3 Obra-Anpara S/C 40.00 UPPCL UPPCL UPPCL POWERGRID
4 Anpara-A-Sarnath S/C 140.00 UPPCL UPPCL UPPCL
5 Anpara-B-Sarnath I D/C 159.00 UPPCL UPPCL UPPCL
6 Anpara-B-Sarnath II D/C 159.00 UPPCL UPPCL UPPCL
7 Sarnath-Azamgarh S/C 95.00 UPPCL UPPCL UPPCL
8 Sarnath-Mau S/C 106.00 UPPCL UPPCL UPPCL
9 Azamgarh-Sultanpur S/C 125.50 UPPCL UPPCL UPPCL
10 Sultanpur-Lucknow S/C 145.10 UPPCL UPPCL UPPCL POWERGRID
11 Panki-Muradnagar S/C 395.20 UPPCL UPPCL UPPCL POWERGRID
12 Moradabad-Rishikesh S/C 159.80 UPPCL UPPCL UPPCL POWERGRID
13 Muradnagar-Rishikesh S/C 182.75 UPPCL UPPCL UPPCL POWERGRID
14 Mau-Azamgarh S/C 48.40 UPPCL UPPCL UPPCL
15 Azamgarh-Gorakhpur S/C 90.00 UPPCL UPPCL UPPCL
16 Unnao-Agra S/C 274.80 UPPCL UPPCL UPPCL POWERGRID
17 Unnao-Lucknow S/C 39.16 UPPCL UPPCL UPPCL POWERGRID
18 Unnao-Panki S/C 48.54 UPPCL UPPCL UPPCL POWERGRID
Annex -I
Page 4 of 30
220 kV PSEB
Annex -I
Page 7 of 30
400 kV in NR-1
1 Singrauli-Anpara S/C 25.057 POWERGRID NTPC UPPCL
2 Singrauli-Kanpur-I S/C 447.00 POWERGRID NTPC POWERGRID UPPCL
3 Singrauli-Kanpur-II S/C 424.15 POWERGRID NTPC POWERGRID UPPCL
4 Singrauli-Lucknow S/C 408.60 POWERGRID NTPC UPPCL
5 Singrauli-Rihand-I S/C 42.026 POWERGRID NTPC NTPC
6 Singrauli-Rihand-II S/C 43.95 POWERGRID NTPC NTPC
7 Singrauli-Vindhyachal S/C 3.34 POWERGRID NTPC POWERGRID WRLDC
8 Vindhyachal-Kanpur S/C 398.00 POWERGRID POWERGRID POWERGRID UPPCL
9 Kanpur-Ballabhgarh S/C 385.60 POWERGRID POWERGRID POWERGRID
10 Kanpur-Agra S/C 240.00 POWERGRID POWERGRID POWERGRID
11 Kanpur-Panki-I S/C 5.62 POWERGRID POWERGRID UPPCL
12 Kanpur-Panki-II S/C 5.70 POWERGRID POWERGRID UPPCL
13 Lucknow-Moradabad S/C 331.18 POWERGRID UPPCL UPPCL
14 Moradabad-Muradnagar S/C 133.00 POWERGRID UPPCL UPPCL
15 Dadri-Muradnagar S/C 33.10 POWERGRID NTPC UPPCL
16 Dadri-Panipat S/C 112.32 POWERGRID NTPC BBMB HVPNL
Annex -I
Page 11 of 30
400 kV in NR-2
1 Uri-Wagoora I D/C 93.00 POWERGRID NHPC POWERGRID PDD J&K
2 Uri-Wagoora II D/C 93.00 POWERGRID NHPC POWERGRID PDD J&K
Annex -I
Page 13 of 30
132 kV Others
Annex -I
Page 15 of 30
LIST OF OTHER ISTS ELEMENTS IN NORTHERN REGION NOT INCLUDED IN THE LIST OF
"IMPORTANT ELEMENTS OF REGIONAL GRID"
Line Agency at
Sl. Ckt. Confi- Other Agencies
Name of Line/ICT Length O&M by Remarks
No. guration End - 1 End - 2 Affected
(in km)
1 220 kV Ganguwal-Dhulkote I D/C 110.00 BBMB BBMB BBMB HVPNL
LIST OF OTHER ISTS ELEMENTS IN NORTHERN REGION NOT INCLUDED IN THE LIST OF
"IMPORTANT ELEMENTS OF REGIONAL GRID"
Line Agency at
Sl. Ckt. Confi- Other Agencies
Name of Line/ICT Length O&M by Remarks
No. guration End - 1 End - 2 Affected
(in km)
12 221 kV Dasuya-Jallandhar II S/C 57.00 PSEB PSEB PSEB
LIST OF OTHER ISTS ELEMENTS IN NORTHERN REGION NOT INCLUDED IN THE LIST OF
"IMPORTANT ELEMENTS OF REGIONAL GRID"
Line Agency at
Sl. Ckt. Confi- Other Agencies
Name of Line/ICT Length O&M by Remarks
No. guration End - 1 End - 2 Affected
(in km)
23 220 kV Bhiwani-Dadri IV D/C 38.00 BBMB BBMB BBMB HVPNL
LIST OF OTHER ISTS ELEMENTS IN NORTHERN REGION NOT INCLUDED IN THE LIST OF
"IMPORTANT ELEMENTS OF REGIONAL GRID"
Line Agency at
Sl. Ckt. Confi- Other Agencies
Name of Line/ICT Length O&M by Remarks
No. guration End - 1 End - 2 Affected
(in km)
34 220 kV Bhakra (R)-Mahilpur S/C 51.00 PSEB BBMB PSEB
66kV Mohali(PSEB)-Chandigarh
35 D/C UT Chandigarh PSEB Chandigarh
UTSec-39 - I
66kV Mohali(PSEB)-Chandigarh
36 D/C UT Chandigarh PSEB Chandigarh
UTSec-39 - II
66kV Mohali(PSEB)-Chandigarh
37 D/C UT Chandigarh PSEB Chandigarh
UTSec-52 - I
66kV Mohali(PSEB)-Chandigarh
38 D/C UT Chandigarh PSEB Chandigarh
UTSec-52 - II
66kV Pinjore(HVPN)-Ch'garh
39 D/C BBMB HVPNL Chandigarh
UTSec-28(BBMB)-I
66kV Pinjore(HVPN)-Ch'garh
40 D/C BBMB HVPNL Chandigarh
UTSec-28(BBMB)-II
66kV Dhulkote(BBMB)-Ch'garh UT
41 D/C BBMB BBMB Chandigarh
Sec-28(BBMB)-I
66kV Dhulkote(BBMB)-Ch'garh UT
42 D/C BBMB BBMB Chandigarh
Sec-28(BBMB)-II
43 33kV Kundli-Narela S/C HVPNL HVPNL DVB
LIST OF OTHER ISTS ELEMENTS IN NORTHERN REGION NOT INCLUDED IN THE LIST OF
"IMPORTANT ELEMENTS OF REGIONAL GRID"
Line Agency at
Sl. Ckt. Confi- Other Agencies
Name of Line/ICT Length O&M by Remarks
No. guration End - 1 End - 2 Affected
(in km)
45 132kV Narela -Bahadurgarh S/C HVPNL BBMB HVPNL
LIST OF OTHER ISTS ELEMENTS IN NORTHERN REGION NOT INCLUDED IN THE LIST OF
"IMPORTANT ELEMENTS OF REGIONAL GRID"
Line Agency at
Sl. Ckt. Confi- Other Agencies
Name of Line/ICT Length O&M by Remarks
No. guration End - 1 End - 2 Affected
(in km)
56 132kV Ropar-Pinjore - I D/C HVPNL PSEB HVPNL
LIST OF OTHER ISTS ELEMENTS IN NORTHERN REGION NOT INCLUDED IN THE LIST OF
"IMPORTANT ELEMENTS OF REGIONAL GRID"
Line Agency at
Sl. Ckt. Confi- Other Agencies
Name of Line/ICT Length O&M by Remarks
No. guration End - 1 End - 2 Affected
(in km)
67 66kV Bhakra-L-PACL S/C BBMB BBMB PACL
FORMAT-A
AVAILABILITY DECLARATION (Ex BUS) BY COAL FIRED / NUCLEAR ISGS
(TO BE SENT BY ISGS TO NRLDC BY 10:00 HRS)
MSG NO. ......... REVISION NO .......... DATE OF ISSUE : dd.mm.yy TIME OF ISSUE: hh : mm
( ii ) Units to go under planned shut down during next day ................ ..................... ............
................ ..................... ............
(iii) Units likely to return from planned shutdown ................ ..................... ............
during next day ................ ..................... ............
* The Ex-BUS MWH declared capability (DC) is a value which can be lower than the arithmetic sum of the capability declared
for different blocks due to fuel or any other technical constraints and should be stated by the station after taking into consideration
all such factors.
FORMAT-A , DECLARED CAPABILITY ( Ex-bus ) OF (Name of power station), FOR DATE: dd.mm.yy, REVISION NO .........., ( Page 1/ 1 )
ANNEX – II
SHEET 2 of 26
FORMAT-B
AVAILABILITY DECLARATION (Ex BUS) BY GAS FIRED / LIQUID FIRED ISGS
(TO BE SENT BY ISGS TO NRLDC BY 10:00 HRS)
( ii ) Units to go under planned shut down during next day ................ ..................... ............
................ ..................... ............
(iii) Units likely to return from planned shutdown ................ ..................... ............
during next day ................ ..................... ............
* The Ex-BUS MWH declared capability (DC) is a value which can be lower than the arithmetic sum of the capability declared
for different blocks due to fuel or any other technical constraints and should be stated by the station after taking into consideration
all such factors.
FORMAT-B , DECLARED CAPABILITY ( Ex-bus ) OF (Name of power station), FOR DATE: dd.mm.yy , EVISION NO........, ( Page 1 / 1 )
ANNEX – II
SHEET 3 of 26
FORMAT-C
AVAILABILITY DECLARATION (Ex BUS ) BY RESERVOIR BASED HYDRO ISGS
(TO BE SENT BY ISGS TO NRLDC BY 10:00 HRS)
MSG NO. ......... REVISION NO .......... DATE OF ISSUE : dd.mm.yy TIME OF ISSUE: hh : mm
( ii ) Units to go under planned shut down during next day ................ ..................... ............
................ ..................... ............
(iii) Units likely to return from planned shutdown ................ ..................... ............
during next day ................ ..................... ............
( iii ) Anticipated inflows for the next day ..................... cumacs / cusecs
GENERATION TIME
(MW) (hh : mm)
( iv ) Time duration for which maximum generation can be sustained ..................... ............
at a stretch
* The Ex-BUS MWH declared capability (DC) is a value which can be lower than the arithmetic sum of the capability declared
for different blocks due to fuel or any other technical constraints and should be stated by the station after taking into consideration
all such factors.
FORMAT-C , DECLARED CAPABILITY ( Ex-bus ) OF (Name of power station), FOR DATE: dd.mm.yy , EVISION NO........, ( Page 1 / 1 )
ANNEX – II
SHEET 4 of 26
FORMAT-D
AVAILABILITY DECLARATION (Ex BUS) BY RUN OFF THE RIVER HYDRO ISGS
(TO BE SENT BY ISGS TO NRLDC BY 10:00 HRS)
MSG NO. ......... REVISION NO .......... DATE OF ISSUE : dd.mm.yy TIME OF ISSUE: hh : mm
( ii ) Units to go under planned shut down during next day ................ ..................... ............
................ ..................... ............
(iii) Units likely to return from planned shutdown ................ ..................... ............
during next day ................ ..................... ............
( B ) INFLOWS STATUS
GENERATION TIME
(MW) (hh : mm)
( iii ) Time duration for which maximum generation can be sustained ..................... ............
at a stretch
* The Ex-BUS MWH declared capability (DC) is a value which can be lower than the arithmetic sum of the capability declared
for different blocks due to fuel or any other technical constraints and should be stated by the station after taking into consideration
all such factors.
FORMAT-D , DECLARED CAPABILITY ( Ex-bus ) OF (Name of power station), FOR DATE: dd.mm.yy , REVISION NO........, ( Page 1 / 1 )
ANNEX - II
SHEET 19 of 26
FORMAT- J
DRAWAL SCHEDULE FOR CONSTITUENT STATES
( TO BE ISSUED BY NRLDC TO CONSTITUENT STATES BY 1700 HRS )
FROM : SCE, NRLDC, NEW DELHI TO : ( Name of the constituent state )
DRAWAL SCHEDULE ( Ex STATE PERIPHERY ) FROM THE GRID FOR ( Name of constituent state ) FOR DATE: dd.mm.yy
hh : mm 1 2 3 4 5 6 7 8 9 10
1 00:00
2 00:15
3 00:30
4 00:45
5 01:00
6 01:15
7 01:30
8 01:45
9 02:00
10 02:15
11 02:30
12 02:45
13 03:00
14 03:15
15 03:30
16 03:45
17 04:00
18 04:15
19 04:30
20 04:45
21 05:00
22 05:15
23 05:30
24 05:45
25 06:00
26 06:15
27 06:30
28 06:45
29 07:00
30 07:15
31 07:30
32 07:45
33 08:00
34 08:15
35 08:30
36 08:45
37 09:00
38 09:15
39 09:30
40 09:45
41 10:00
42 10:15
43 10:30
44 10:45
NOTE: Net drawal schedule in respect of Bhakra, Dehar & Pong is as finalised by BBMB
FORMAT- J, DRAWAL SCHEDULE FOR ( Name of constituent state ), FOR DATE: dd.mm.yy, REVISION NO……, ( Page 1 / 8 )
ANNEX - II
SHEET 20 of 26
hh : mm 1 2 3 4 5 6 7 8 9 10
45 11:00
46 11:15
47 11:30
48 11:45
49 12:00
50 12:15
51 12:30
52 12:45
53 13:00
54 13:15
55 13:30
56 13:45
57 14:00
58 14:15
59 14:30
60 14:45
61 15:00
62 15:15
63 15:30
64 15:45
65 16:00
66 16:15
67 16:30
68 16:45
69 17:00
70 17:15
71 17:30
72 17:45
73 18:00
74 18:15
75 18:30
76 18:45
77 19:00
78 19:15
79 19:30
80 19:45
81 20:00
82 20:15
83 20:30
84 20:45
85 21:00
86 21:15
87 21:30
88 21:45
89 22:00
90 22:15
91 22:30
92 22:45
93 23:00
94 23:15
95 23:30
96 23:45
ENERGY IN MWH
NOTE: Net drawal schedule in respect of Bhakra, Dehar & Pong is as finalised by BBMB
FORMAT- J, DRAWAL SCHEDULE FOR ( Name of constituent state ), FOR DATE: dd.mm.yy, REVISION NO……, ( Page 2 / 8 )
ANNEX - II
SHEET 21 of 26
hh : mm 11 12 13 14 15 16 17 18 19 20
1 00:00
2 00:15
3 00:30
4 00:45
5 01:00
6 01:15
7 01:30
8 01:45
9 02:00
10 02:15
11 02:30
12 02:45
13 03:00
14 03:15
15 03:30
16 03:45
17 04:00
18 04:15
19 04:30
20 04:45
21 05:00
22 05:15
23 05:30
24 05:45
25 06:00
26 06:15
27 06:30
28 06:45
29 07:00
30 07:15
31 07:30
32 07:45
33 08:00
34 08:15
35 08:30
36 08:45
37 09:00
38 09:15
39 09:30
40 09:45
41 10:00
42 10:15
43 10:30
44 10:45
45 11:00
46 11:15
47 11:30
48 11:45
NOTE: Net drawal schedule in respect of Bhakra, Dehar & Pong is as finalised by BBMB
FORMAT- J, DRAWAL SCHEDULE FOR ( Name of constituent state ), FOR DATE: dd.mm.yy, REVISION NO……, ( Page 3 / 8 )
ANNEX - II
SHEET 22 of 26
hh : mm 11 12 13 14 15 16 17 18 19 20
49 12:00
50 12:15
51 12:30
52 12:45
53 13:00
54 13:15
55 13:30
56 13:45
57 14:00
58 14:15
59 14:30
60 14:45
61 15:00
62 15:15
63 15:30
64 15:45
65 16:00
66 16:15
67 16:30
68 16:45
69 17:00
70 17:15
71 17:30
72 17:45
73 18:00
74 18:15
75 18:30
76 18:45
77 19:00
78 19:15
79 19:30
80 19:45
81 20:00
82 20:15
83 20:30
84 20:45
85 21:00
86 21:15
87 21:30
88 21:45
89 22:00
90 22:15
91 22:30
92 22:45
93 23:00
94 23:15
95 23:30
96 23:45
ENERGY IN MWH
NOTE: Net drawal schedule in respect of Bhakra, Dehar & Pong is as finalised by BBMB
FORMAT- J, DRAWAL SCHEDULE FOR ( Name of constituent state ), FOR DATE: dd.mm.yy, REVISION NO……, ( Page 4 / 8 )
ANNEX - II
SHEET 23 of 26
BLOCK TIME PONG Ex-PP from Bilateral-1 Bilateral-2 Bilateral-3 Bilateral-4 Bilateral-5 Bilateral-6 Net Bilateral **
NO. POINT ISGS/JS * With….. With….. With….. With….. With….. With…..
( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW )
hh : mm 21 22 23 24 25 26 27 28 29
1 00:00
2 00:15
3 00:30
4 00:45
5 01:00
6 01:15
7 01:30
8 01:45
9 02:00
10 02:15
11 02:30
12 02:45
13 03:00
14 03:15
15 03:30
16 03:45
17 04:00
18 04:15
19 04:30
20 04:45
21 05:00
22 05:15
23 05:30
24 05:45
25 06:00
26 06:15
27 06:30
28 06:45
29 07:00
30 07:15
31 07:30
32 07:45
33 08:00
34 08:15
35 08:30
36 08:45
37 09:00
38 09:15
39 09:30
40 09:45
41 10:00
42 10:15
43 10:30
44 10:45
45 11:00
46 11:15
47 11:30
48 11:45
NOTE: Net drawal schedule in respect of Bhakra, Dehar & Pong is as finalised by BBMB
* Ex-POWER PLANT FROM ISGS / JS = {SUM OF DRAWAL SCHEDULE FROM ISGS / JS} = [SUM OF ENTITIES FROM (1) TO (21)]
** NET BILATERAL = {SUM OF BILATERAL-1 TO BILATERAL-6} = [SUM OF ENTITIES FROM (22) TO (28)]
FORMAT- J, DRAWAL SCHEDULE FOR ( Name of constituent state ), FOR DATE: dd.mm.yy, REVISION NO……, ( Page 5 / 8 )
ANNEX - II
SHEET 24 of 26
BLOCK TIME PONG Ex-PP from Bilateral-1 Bilateral-2 Bilateral-3 Bilateral-4 Bilateral-5 Bilateral-6 Net Bilateral **
NO. POINT ISGS/JS * With….. With….. With….. With….. With….. With…..
( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW ) ( MW )
hh : mm 21 22 23 24 25 26 27 28 29
49 12:00
50 12:15
51 12:30
52 12:45
53 13:00
54 13:15
55 13:30
56 13:45
57 14:00
58 14:15
59 14:30
60 14:45
61 15:00
62 15:15
63 15:30
64 15:45
65 16:00
66 16:15
67 16:30
68 16:45
69 17:00
70 17:15
71 17:30
72 17:45
73 18:00
74 18:15
75 18:30
76 18:45
77 19:00
78 19:15
79 19:30
80 19:45
81 20:00
82 20:15
83 20:30
84 20:45
85 21:00
86 21:15
87 21:30
88 21:45
89 22:00
90 22:15
91 22:30
92 22:45
93 23:00
94 23:15
95 23:30
96 23:45
ENERGY IN MWH
NOTE: Net drawal schedule in respect of Bhakra, Dehar & Pong is as finalised by BBMB
FORMAT- J, DRAWAL SCHEDULE FOR ( Name of constituent state ), FOR DATE: dd.mm.yy, REVISION NO……, ( Page 6 / 8 )
ANNEX - II
SHEET 25 of 26
hh : mm 30 31
1 00:00
2 00:15
3 00:30
4 00:45
5 01:00
6 01:15
7 01:30
8 01:45
9 02:00
10 02:15
11 02:30
12 02:45
13 03:00
14 03:15
15 03:30
16 03:45
17 04:00
18 04:15
19 04:30
20 04:45
21 05:00
22 05:15
23 05:30
24 05:45
25 06:00
26 06:15
27 06:30
28 06:45
29 07:00
30 07:15
31 07:30
32 07:45
33 08:00
34 08:15
35 08:30
36 08:45
37 09:00
38 09:15
39 09:30
40 09:45
41 10:00
42 10:15
43 10:30
44 10:45
45 11:00
46 11:15
47 11:30
48 11:45
NOTE: Net drawal schedule in respect of Bhakra, Dehar & Pong is as finalised by BBMB
*** NET DRAWAL SCHEDULE (Ex POWER PLANT) = { [Ex-PP DRAWAL SCHEDULE FROM ISGS / JS] + [NET BILATERAL] } = [(22) + (29)]
**** NET DRAWAL SCHEDULE (Ex-SEB PERIPHERY)= NET DRAWAL SCHEDULE (Ex POWER PLANT) - TRANSMISSION LOSSES (ESTIMATED)
FORMAT- J, DRAWAL SCHEDULE FOR ( Name of constituent state ), FOR DATE: dd.mm.yy, REVISION NO……, ( Page 7 / 8 )
ANNEX - II
SHEET 26 of 26
hh : mm 30 31
49 12:00
50 12:15
51 12:30
52 12:45
53 13:00
54 13:15
55 13:30
56 13:45
57 14:00
58 14:15
59 14:30
60 14:45
61 15:00
62 15:15
63 15:30
64 15:45
65 16:00
66 16:15
67 16:30
68 16:45
69 17:00
70 17:15
71 17:30
72 17:45
73 18:00
74 18:15
75 18:30
76 18:45
77 19:00
78 19:15
79 19:30
80 19:45
81 20:00
82 20:15
83 20:30
84 20:45
85 21:00
86 21:15
87 21:30
88 21:45
89 22:00
90 22:15
91 22:30
92 22:45
93 23:00
94 23:15
95 23:30
96 23:45
ENERGY MWH
NOTE: Net drawal schedule in respect of Bhakra, Dehar & Pong is as finalised by BBMB
*** NET DRAWAL SCHEDULE (Ex POWER PLANT) = { [Ex-PP DRAWAL SCHEDULE FROM ISGS / JS] + [NET BILATERAL] } = [(22) + (29)]
**** NET DRAWAL SCHEDULE (Ex-SEB PERIPHERY)= NET DRAWAL SCHEDULE (Ex POWER PLANT) - TRANSMISSION LOSSES (ESTIMATED)
FORMAT- J, DRAWAL SCHEDULE FOR ( Name of constituent state ), FOR DATE: dd.mm.yy, REVISION NO……, ( Page 8 / 8 )