Pc-I (Infrastructure-Proforma For Development Projects)
Pc-I (Infrastructure-Proforma For Development Projects)
Pc-I (Infrastructure-Proforma For Development Projects)
PC-1 FORM
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
(INFRASTRUCTURE SECTORS)
• Telecommunication
• Information Technology
2. Location
4. Plan provision
15. Certified that the project proposal has been prepared on the basis
of instructions provided by the Planning Commission for the
preparation of PC-I for Infrastructure sector projects.
Prepared by _______________________
Name, Designation & Phone #
Checked by _______________________
Name, Designation & Phone #
Approved by _______________________
Name, Designation & Phone #
3
Revised 2005
GOVERNMENT OF PAKISTAN
PLANNING COMMISSION
Instructions to Fill-in PC-I Proforma(Infrastructure Sectors)
2. Location
• Provide name of the district/province.
• Attach a map of the area, clearly indicating the
project location.
Information Technology
6
price (with custom duties and taxes shown separately) and
disposal of ash and effluents.
• Give a comprehensive, comparison of available technology and
rationale/criteria for selection of specified technology.
• Provide analysis of adopted technology with respect to existing
system.
• Indicate whether maintenance facilities are available. If not,
provide details/plans for maintenance facilities.
• For transmission and distribution system: Basis of design
voltage drop allowance system stability, reliability, operating
voltage, policy regarding reserves, design and material to be
used for supporting structure, average span length and
conductor size, type of spacing.
• Load flow studies for the year in which plant is proposed to be
commissioned and five years thereafter.
• For sub-stations and switching stations: Give location and
purpose of each station KVA voltage, type and structure,
number of circuits, type of transformers and major circuit
breakers.
• Load conditions of the existing facilities, in case of extention
facilities.
• In case of new projects, loading conditions of sub stations be
provided.
7
• Provide project areas characteristics in terms of population,
climate, geology, soil, irrigation, ground water, drainage and
agriculture (crops, yields etc.)
• For multipurpose projects, provide basis of allocation of
costs between different purposes.
• Engineering projects be supported by technical background
data and each distinct segment of the project be described
separately.
8
• Item-wise, year-wise actual expenditure and Physical
progress.
• Justification for revision of PC-I and variation in scope
of project if applicable.
• Item-wise comparison of revised cost with the approved
cost and give reasons for variation.
• Exchange rate used to work out FEC in the original and
revised PC-I’s.
8. Annual Operating Cost
Sources of financing
(a) Equity:
b) Debt
9
Indicate the local & foreign debt, interest rate, grace period
and repayment period for each loan separately. The loan
repayment schedule be also annexed.
• Financial analysis
• Economic analysis
10
• Employment analysis
• Sensitivity analysis
11
• The manpower requirements by skills during execution and
operation of the project be provided.
• The job description, qualification, experience, age and
salary of each post be provided.
15. Certificate
12