Feasibility Report Skid Mounted Unit
Feasibility Report Skid Mounted Unit
Feasibility Report Skid Mounted Unit
CLIENT: M/s:
CONSULTANTS ECO PARYAVARAN ENGINEERS AND CONSULTANTS PVT LTD H.O. : E - 207, INDUSTRIAL AREA, PHASE VIII B, MOHALI (PUNJAB) WORKS: E - 207, INDUSTRIAL AREA, PHASE VIII B, MOHALI (PUNJAB) Tel FAX: 0172 4616225, Mb.: +91-9814003103 EMAIL: [email protected], [email protected] WEBSITE: www.ecoparyavaran.org
Eco Paryavaran
2.
We will be providing the diffusers of Silicone Membrane. Although these diffusers have high initial cost, but these have very long life and very high oxygen transfer efficiency.
3.
We will be providing the high quality UV stabilized SAFF & Tube Settler media from Munter's, Germany thus preventing algae formation.
4.
Our emphasis has always been on quality so that the system provided should have the least recurring maintenance costs.
5.
We have our own in house Govt. approved state of the art water analysis laboratory approved by MOEF, NABL & control Board under the supervision of Punjab Pollution highly qualified
professionals at Mohali. This enables us to check the stage wise performance parameters of the plant as well as helps in proper monitoring of the complete system.
Eco Paryavaran
6.
We will also be providing the exhaustive OEM manuals along with testing procedures to help your operating staff to work in a more professional manner.
1. INTRODUCTION
M/s .. requires a package type skid mounted ready to use sewage treatment plant of capacity 10 m3/day to treat the domestic sewage. The Sewage water will be generated from Toilets, Bathrooms, Canteens and floor washings etc. The sewage water requires treatment in order to meet the standard norms set by the PCB. This proposal shall consider various aspects covering the parameters of sewage water (both quality and quantity), The Scheme & process of treatment, process units involved in the treatment, their specification with commercial terms & conditions.
4. TREATMENT SCHEME
The STP is of modular construction and the treatment process will consists of four stages.
Eco Paryavaran
Stage 1: Primary Treatment Screen Chamber, Oil & Grease chamber, Sewage collection tank. Stage 2: Secondary or biological treatment SAFF Reactor, Secondary Tube Settler Stage 3: Tertiary treatment Filter Feed tank, Pressure sand Filter, Activated carbon Filter & Hypo dosing system/ UV system (Optional). Stage 4: Sludge Treatment Sludge Drying Beds/ Filter press
Eco Paryavaran
sludge will be pumped to filter press for mechanical dewatering. The dried sludge will be dried & used as organic manure. The Clarifier water collected from the collection launder of the tube settler is then passed to the Filter Feed tank TERTIARY TREATMENT The clarified water is collected into the Filter Feed tank. It is necessary to pass the effluent further through tertiary treatment comprises of filtration with pressure sand filter for removal of suspended solids & Activated carbon filter for removal of trace organic matter, color & odor. Then this treated water will discharge to irrigation/plantation.
PRIMARY TREATMENT
BAR SCREEN 1. Application- Screening of floatable matter MOC- MSEP, Size of spacing 10 mm, Make- ECO 1 No.
3.
Eco Paryavaran
MOC MS with FRP Lining Internally Make: ECO SAFF MEDIA Sp Surface Area-102 m2/m3 MOC- PVC UV Stabilized, Make: Cooldeck / Munters Germany AERATION GRID FOR SAFF REACTOR 6. Application - For providing air SAFF reactor Accessories- Complete with piping & valves MOC MSEP ,Make-ECO AIR DIFFUSERS 7. Application - For providing air in SAFF reactor Type: Tubular Fine membrane MOC Silicon, Make- Rehaue / OTT / Eqt. AIR BLOWER WITH ACCESSORIES Application - Supply of air for mixing Capacity- 50 m3/hr MOC CI, Pressure - 0.40 kg/cm2 , Blower make- Everest / Beta Motor make- Crompton/ Kirloskar/ABB/Marathon Accessories- MS base plate, safety valves, suction filter, silencer, NRV, PRV, ant vibration pad, V belt, Belt guard, Drive and driven pulleys SECONDARY TUBE SETTLER WITH MEDIA Application - For settling of sludge SECONDARY TUBE SETTLER TANK 9. Capacity- Suitable to handle 10 KLD MOC MS with FRP Lining Internally Make: ECO TUBE SETTLER MEDIA Length 750 mm MOC- PVC UV Stabilized, Make: Cooldeck / Munters Germany SLUDGE RECIRCULATION PUMP 12. Application- To Recycle sludge to SAFF Reactor Type- Centrifugal, Monoblock, horizontal , Self priming Capacity: 1 m3/hr,Head- 10 m, MOC CI, Make Kirloskar/Johnson 2 Nos (1 W + 1 S). 1 No. 1 Lot. 1 Lot
8.
2 Nos (1 W + 1 S).
Eco Paryavaran
TERTIARY TREATMENT FILTER FEED PUMP Application- To feed the treated Sewage to Pressure sand filter / backwashing Type- Centrifugal, Monoblock, horizontal , Self priming, Capacity: -1 m3/hr, Head- 25 m, MOC CI Make Kirloskar PRESSURE SAND FILTER 14. Application for Removal of fine suspended solids Size Suitable to Handle 10 KL Flow Media- under bed with graded silica sand MOC FRP, Make Aquanomics/Eqt ACTIVATED CARBON FILTER Application - Removal of fine suspended solids, Color & Odor Size - Suitable to Handle 10 KL Flow Media- under bed with graded silica sand & Activated carbon, MOC FRP Make Aquanomics/Eqt HYPO DOSING SYSTEM DOSING TANK Application - Storage of Chlorine Dosing Solution Type- Vertical Capacity-100 Ltr MOC HDPE Make-Sintex DOSING PUMP Application - To dose the hypo chloride solution Type- Electronic, Diaphragm Capacity-0-6 Lph Pump Make: Edose/ Aquanomics /Equivalent INTERCONNECTING PIPING, FITTING & VALVES 17. MOC: MS / PVC / Equivalent Make: Tata / Zenith 18. a. MECHANICAL SLUDGE DEWATERING SYSTEM SLUDGE FEED PUMP Application- To feed the sludge to Filter press 1 No. 1 Lot 1 No.
13.
2 Nos (1 W + 1 S).
15.
1 No.
16.
1 Lot.
Eco Paryavaran
Capacity-1 m3/hr Head- 40 m MOC CI, Make : Roto / Eqt. COARSE AIR DIFFUSERS FOR SLUDGE HOLDING TANK b. Application - For providing air to Sludge collection Tank MOC EPDM / Silicon, Type: Coarse Dia: 150 mm Make-Welcome / Cooldek POLYELECTROLYTE SOLUTION TANK Location: Near Sludge collection tank Application -Storage of Polyelectrolyte c. MOC- HDPE /PVC Capacity-100 Liters Accessories -Puddle pipe with flange, valves, pipes and fittings Make: Syntax / Equivalent FILTER PRESS Type: Recessed, MOC of plate: PP No of plates: 12 d. No. of chambers: 11,Closing device: Hydraulic Drive: 1.0 HP, 3 Phase, Kirloskar / Crompton Size of chambers: 300 mm x 300 mm Make: Welcome / Eqt. UV System (Optional) 19. Capacity: 1 m3 / Hr MOC: SS Make: Philips Holland / Good Life 1 No. 1 No. 1 No. 1 Lot.
7. ELECTRICAL WORKS
S.NO DESCRIPTION
CONTROL PANEL i. Control panel will be fabricated in 14 SWG/ 16 SWG CRCA sheet with non- compartment, dust & vermin proof, machine mounted Make of Switchgears - Siemens / L & T ii. CABLING
Eco Paryavaran
Electrical cabling shall be provided from control panel to various units of sewage treatment plant Size of cable- As per the capacity of the motors / drives MOC: Copper / Al unarmored Make: CCI / Polycab / Equivalent
8. DETAIL OF INSTRUMENTATION
S.NO DESCRIPTION Pressure Gauges I.
Location - Delivery line of Blowers Type - Bourdon / Diaphragm Range- 0 to 4 Kg/ cm2 Make - Wika / H guru / Equivalent
Qty.
1 Lot
2 Sets
9.
SCOPE OF WORK
S. No. 1. 2. 3. 4. 5. Description Supply of Mechanical Equipments as per detail above Supply of Electrical Items as per detail above Supply of piping, valves and other accessories as per detail above Supply of Instrumentation items Supply of fabricated items.
Eco Paryavaran
6. 7. 8. 9.
Operators training Supply of operation and maintenance manuals Erection, Testing & Commissioning Supply of Civil drawings & supervision over civil works.
10.
S. No. 1. 2. 3. 4. 5. 6. 7.
Note: Please note that adjustment in dimensions in the above designed units is sometimes needed due to site constraints keeping in view the overall requirements of area and volume.
11.
SCHEDULE OF EXCLUSION
Our supplies will be restricted to the items included in the above details. For your ready reference a list of exclusions from our supply is given below: 1. All types of civil works
10
Eco Paryavaran
2. 3. 4. 5. 6.
All type of piping and valves up to inlet and beyond outlet of the STP. Earthing, Area lighting and cable trays All type of Puddle pipes required for civil tanks Supply of power to MCC Panel at STP with cabling & earthing. Tools, tackles, man power, storage facility for the safety of the equipment and other utilities during erection and commissioning.
7.
All supplies, working and services not specifically mentioned as forming part of our offer.
8.
11
Eco Paryavaran
12