GMP Contracts
GMP Contracts
If you would like to know more about the subjects covered in this publication or our services, please contact:
Tracy London, Partner +44(0)20 7006 4561 David Metzger, Partner +44 (0)20 7006 4240 Tim Steadman, Partner +44(0)20 7006 4012 To email one of the above, please use [email protected] Clifford Chance LLP, 10 Upper Bank Street, London, E14 5JJ, UK www.cliffordchance.com
UK-2116681-v2B
OFFICE
funders are persuaded by that argument. As mentioned above, real savings against the GMP are likely to be assisted by strict cost definition and control rather than by upside sharing alone. In addition, the GMP protection is to some extent illusory. In theory, a contractor who manages to expend cost-plus fee equal to the whole of the GMP while completing only 10% of the work remains liable to complete the remaining 90% for no further payment. But that would represent a significant bet by the employer/funders on the credit strength of the contractor, and recovery on any termination would probably be further limited by liability caps and limited bond values. In theory, payment should be based on vouchers or other evidence of actual cost. Most main contractors will in any event subcontract the bulk of the work, so that evidence will consist of subcontract invoices or payment records. Rights of retrospective cost auditing and spot checking should always be reserved, as well as approval/open book rights in relation to subcontracting. The Fee It is customary to pay the contractor a fee in addition to his costs (but normally subject in the aggregate to the GMP) in order to cover profit, head office overhead and risk. The fee is normally expressed as a percentage of cost. In some contracts the total amount of the fee is capped at a maximum cash value, or the percentage is reduced where the cost figure exceeds a certain threshold. It is advisable to list the items covered by the fee in order to avoid double counting between the fee and cost. In addition to gross profit and head office overheads (the latter meriting its own definition also), the fee might be stipulated to cover some of the financial risks absorbed by the contractor, such as tax increases and other changes in law and material price or currency fluctuation. In certain circumstances it may be appropriate to deny the contractor any fee on a given cost item or (more realistically) to pay a reduced fee. An analogy can be found in FIDIC where certain claim events entitle the contractor to cost without profit. The adjusted fee is likely to be paid in many circumstances where cost is payable without any corresponding increase in the GMP, or where no extra economic value is generated. Design The CPGMP approach is often symptomatic of a less than normal degree of design evolution prior to signing. Close attention to the design development provisions in the contract is therefore merited. Conclusion There are many other issues which must be examined in detail before negotiations are complete and a CPGMP contract is signed, including but not limited to contingencies, reserves, sectional GMP, definitions such as prime and design costs, cost estimates, insurance recoveries, and overall risk allocation (to which CPGMP lends an altered overall perspective). A clear and comprehensive CPGMP contract is an effective tool in construction contracting in certain circumstances, but must only be used where close and well informed analysis confirms it as the appropriate choice.
UK-2116681-v2B
-2-
OFFICE
This Client briefing does not necessarily deal with every important topic or cover every aspect of the topics with which it deals. It is not designed to provide legal or other advice. If you do not wish to receive further information from Clifford Chance about events or legal developments which we believe may be of interest to you, please either send an email to [email protected] or by post at Clifford Chance LLP, 10 Upper Bank Street, Canary Wharf, London E14 5JJ.
www.cliffordchance.com
Abu Dhabi Amsterdam Bangkok Barcelona Beijing Brussels Bucharest Dubai Dsseldorf Frankfurt Hong Kong Kyiv London Luxembourg Madrid Milan Moscow Munich New York Paris Prague Riyadh* Rome So Paulo Shanghai Singapore Tokyo Warsaw Washington, D.C. * Clifford Chance has a co-operation agreement with Al-Jadaan & Partners Law Firm in Riyadh and a 'best friends' relationship with AZB & Partners in India and with Lakatos, Kves & Partners in Hungary
UK-2116681-v2B
-3-
OFFICE