Expenses Till Date
Expenses Till Date
Circle-- Hyderabad Period Date 29-May-11 29-May-11 30-May-11 30-May-11 30-May-11 31-May-11 Tour Report : O & M Handover of Kotepalli Site Period Date From----------------------- To---------------Starting Time
Cluster location---------------------
Mobile No.--7893601327
From Station KPHB JBS Karimnagar Kotepalli Karimnagar JBS JBS Karimnagar Kotepalli Karimnagar JBS KPHB
To Station
Return Time
Kilometers
Hotel Exps.
DA
Amount
400
300
300
2820
From Station
Return Time
1-Jun-11 KPHB 2-Jun-11 MGBS 2-Jun-11 adilabad 2-Jun-11 Talamadugu Site 2-Jun-11 Adilabad 3-Jun-11 MGBS PIU Commissioning and Site clearance of Talamadugu Site Tour Report : Period From----------------------- To---------------Date Starting From Station Time 6-Jun-11 KPHB 6-Jun-11 MGBS 7-Jun-11 Anantapur 7-Jun-11 Karnool 8-Jun-11 MGBS Tour Report : Gooty road Issue Clearance with Site Owner Period From----------------------- To---------------Date Starting From Station Time 11-Jun-11 KPHB JBS 12-Jun-11 JBS Karimnagar 13-Jun-11 Karimnagar JBS 13-Jun-11 JBS KPHB Tour Report : DCM Signatory on Upgradation Sites Period From----------------------- To---------------Date Starting From Station Time 17-Jun-11 KPHB 17-Jun-11 Ongole Tour Report : Pinapaka Site Closure Signatory Period From----------------------- To---------------Date Starting From Station Time 18-Jun-11 KPHB 20-May-11 Kotepalli Tour Report : Kotepalli Site Visit along With Cluster Manager Mr.Venkatesh.B Period From----------------------- To---------------Date Starting From Station Time 16-Jun-11 KPHB 16-Jun-11 Indus warehouse Tour Report : Materail Reconcillation at INDUS Warehouse Period From----------------------- To---------------Date Starting From Station Time 23-Jun-11 KPHB 23-Jun-11 Indus warehouse Tour Report : Materail Reconcillation And Unloading PIU of Talamaudgu Site at INDUS Warehouse
Kilometers
Hotel Exps.
DA
Amount
400
300
2085
Return Time
Kilometers
Hotel Exps.
DA
800
450
Total Amount 90 650 300 DD Commissioning charges and Luch for Site Owner and Indus 1200 750 Team 80 Amount
3570
To Station
Return Time
Kilometers
DA
Amount
300
1760
Return Time
Kilometers
DA 150
Amount
1600
Return Time
DA 150
Amount
5100
Return Time
Hotel Exps.
DA 150
Amount
500
Return Time
Hotel Exps.
DA 150
Amount 2500
3060
Checked by:
Signature___________ Name_________________
Passed By:
Signature_________________________ Name____________________________
Local 29-May-11 18-Jun-11 1-Jun-11 6-Jun-11 13-Jun-11 17-Jun-11 16-Jun-11 23-Jun-11 170 0 200 170 210 0 0 0 750
Out 1050 4200 1185 1400 850 1050 350 410 10495
Other 900 0 0 750 0 0 0 2500 4150 2820 5100 2085 3570 1760 1600 500 3060 20495
Engineer Mobile Data card Courier Printouts & Xerox & scan Photos Stamp
Sr.No 1 2 3 4
Discription Ariyalur Site visit BB, SMPS Installation Cables purchase Vendor payment