Environment: Unit Testing / User Manual
Environment: Unit Testing / User Manual
UNIT TESTING SCENARIO SCENARIO NUMBER DESCRIPTION : BPML QM03 - 14 : CONTROL PLAN
PREPARED & TESTED BY NAME SIGNATURE DATE TEAM Approved by : J.SIVA : : 23.12.2008 : QM : Kabir R (PwC)
Page 1 of 16
Testing: Unit Testing / User Manual
1. Transaction Code/ Path Enter the menu path of the transaction code, which is going to be tested by the user. Menu Path T.Code Logistics - Quality Management Quality Planning Inspection Planning Inspection Plan - Create QP01
1. Type QP01 and enter (This is fast path) Note : For making the change in already created inspection plan , select QP02 and follow the procedure of QP01, To display inspection plan select QP03. also you can use the further T codes such as QP60,61,06,07 etc as per requirements.
Page 2 of 16
Testing: Unit Testing / User Manual
4. Click on Operations
Usage : Select usage 5 by drill down (5 means for Goods receipt, 3 Universal Use for Manual inspection lot creation., 4 is for Plant maintenance for service orders such as repairing of equipments /Maintenance items / external gauge calibration) 2. Status : Keep always 4 (Released general) 3. Dynamic Mod Level / Modification rule Select by drill down This is plant specific. Refer Sampling plan Process Manual (BPML QM03-13) 4. Click on Operations
1.
Page 3 of 16
Testing: Unit Testing / User Manual
4 2 1. Type QM01 in Control key column 2. Type Inspection stage description such as Receipt Inspection , Inward Inspection , M/c. Shop Final Inspection, Engine testing Insp. etc in Description column 3. Select the line 4. Go to Inspection Characteristics. (Note : Select control key as per specific module e.g. PM01 for Maintenance select from drill down)
Page 4 of 16
Testing: Unit Testing / User Manual
Drill down here to select Sampling Procedure and enter. (This is plant specific and user) specific.
All required columns will gets filled up after enter. ( Whatever columns are filled in MIC will only gets filled-up here.) MIC may be Qualitative or Quantitative. You can overwrite the parameters in this screen.
Testing: Unit Testing / User Manual
1. Click on Quantitative or Qualitative as per the inspection characteristics. 2. Type the Short text of Inspection Characteristic 3. Select the line and enter 4. For Quantitative Characteristics following screen will display
Testing: Unit Testing / User Manual
1. Select Type (Mandatory), Sample, Result confirmation as per our requirement. 2. Tick to select.
Note: a) Destructive Insp : After activation of this field From every lot a fixed quantity will come for sample usage stage, we have remove this and correct the used quantity and remaining qty to be added to Unrestricted stock manually. b) Additive Sample : Field activates for extra samples for inspection. c) Summ. Recording: Only one result recording Average value. d) Single Result :- For every sample required recording e) Required Char. :-Result Recording is mandatory f) Optional Char :- Result recording is optional. g) Defect Recording:- To record the defect This is mandatory.
Page 7 of 16
Testing: Unit Testing / User Manual
If you required addition sample to be inspected for this characteristics then only activate by click at Tick mark, otherwise close the screen X.
Page 8 of 16
Testing: Unit Testing / User Manual
1. Enter values Decimal places, Target, Lower, Upper limit. 2. Scroll down or Enter (if you know) for Unit of measurement and Enter.
Page 9 of 16
Testing: Unit Testing / User Manual
1. Put cat type 9 or drill down and select 9 ( for defect catalog type) 2. Drill down and select the required defect code group or selected set.
Page 10 of 16
Testing: Unit Testing / User Manual
2 1
1. 2. 3. 4.
Select Qualitative Type Short text Inspection characteristic Select line Enter
Page 11 of 16
Testing: Unit Testing / User Manual
Testing: Unit Testing / User Manual
Page 13 of 16
Testing: Unit Testing / User Manual
Put 9 as Cat Type for defect and a) Tick in S box if You want to select selected set and select selected set thru drill down. b) Select code group thru drill down Enter
Select sampling procedure form drill down as per your requirement and Enter
Page 14 of 16
Testing: Unit Testing / User Manual
SAVE
Page 15 of 16
Testing: Unit Testing / User Manual
Click tick
Inspection plan group No. will get display here. It means Inspection plan is successfully created.
Page 16 of 16