0% found this document useful (0 votes)
5 views5 pages

CE1 Example

This document outlines the author's experience as a Structural Design Engineer on the construction of a 30-floor apartment building in NSW, detailing their responsibilities and challenges faced during the project. Key tasks included designing a complex suspended ground floor slab, managing structural works, and ensuring compliance with safety and design standards. The author highlights the professional growth and skills acquired throughout the project, including project management and effective communication with stakeholders.

Uploaded by

Irfan Iqbal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views5 pages

CE1 Example

This document outlines the author's experience as a Structural Design Engineer on the construction of a 30-floor apartment building in NSW, detailing their responsibilities and challenges faced during the project. Key tasks included designing a complex suspended ground floor slab, managing structural works, and ensuring compliance with safety and design standards. The author highlights the professional growth and skills acquired throughout the project, including project management and effective communication with stakeholders.

Uploaded by

Irfan Iqbal
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 5

CE1.

This career episode deals with my involvement in the construction of Building


XXX located at XXX (Address of Company) in NSW while working as Structural
Design Engineer (Designation) for XXX (Company Name). Our office was
commissioned by the head office to complete several complicated elements of the
structure. My role in this project was to complete the majority of the detailed
design of the complex suspended ground floor slab. I undertook this project in July
2009 and the construction is due to be completed in April 2012 (Duration of
Project).

(b) Background

CE1.2 (Introduction about the Company/ Organization)

“Company” was established in 19** by Architect, Mr. XXX. The company has
completed various architectural projects, designs and supervising construction
work all over the country especially in the capital city. “Company” was both the
owner and contractor of the XXX project. This project consisted of an apartment
building with 30 floors and 4 basement floors and the top apartment was planned
to be a duplex. The construction area was 12,000 m2 (Introduction about Project).

CE1.3 (Job Description)

The principal role and responsibilities that I carried on this project were:

 supervise all structural works and submission of related reports to the project
manager
 arrange supply of required amount of concrete, steel, formwork and other
materials
 monitoring changes to designs, assessing effects on cost, and measuring,
valuing and negotiating variations to designs
 analysing structural systems for both static and dynamic loads
 designing structures to ensure they do not collapse, bend, twist or vibrate in
undesirable ways
 assessing present and future travel flow patterns taking into account
population increase and needs change- work in accordance with standards
 interpret and use specifications, drawings, plans, construction methods,
procedures
 responsible for construction of the structures in accordance with contractual
and design requirements on site and work according to the standards

CE1.4 (Organogram/ Organizational Hierarchy)

The organizational structure for the engineering project at the time was as shown
below:

(c) Personal Engineering Activity

CE1.5

After being briefed on the project by the chief project engineer, my first task was
to break down the entire floor system into an ordered set of discrete designable
elements such as slabs, bands and transfer beams. Next I used the RAPT computer
program (Softwares Used) to carry out the detailed design of each of the forty or so
elements. This involved measuring the span, dimensions and loading on each
element and entering this data to model it in the program. My aim was to make the
models as accurate as practicable, while still allowing for the opportunity to
incorporate future changes.

CE1.6

After re-assessing the specified design criteria, I realised that the reinforcement
cover I had used did not satisfy fire resistance and durability requirements (Issue
faced). However because each design element was already set up as a computer
model, it was simple enough to change the covers and make the necessary design
modifications. To ensure the clarity of the design to others, I
documented (Documentation) and ordered the calculations and computer output in
a lever arch file, including summary pages and assumptions used.
CE1.7 (Designing Jobs/ Tasks)

Throughout the design process (Designing Component), it was my responsibility to


produce, order and maintain all the design documentation including
computations and reinforcement drawings. I arranged the calculations, numbering
approximately 1000 pages, based on the site grid system. The RAPT output for
each element designed was sorted in this system, with summary pages of input and
conclusions provided for each. I clearly outlined content pages and the design
concepts and philosophies at the front of the documentation, while also including
sections for superseded computations and verification documentation.

CE1.8 (Designing Parts, Issue n Solution)

I considered various design possibilities. In one particular possibility, due to the


height difference in the external ground level to the internal slab finished level, it
was required to provide retaining walls. Providing retaining walls was a cost
effective solution compared to importing fill to raise the external ground level. I
introduced concrete ramps and steps to the entrance. I undertook the concrete
design to satisfy Australian standards AS 3600 (important to mention standards
used). Whilst I was checking the drawings, I noticed that some area in the added
mezzanine floor was created as part of the structural system and redundant (Issue
faced during the project and solution). I was convinced that this area was necessary
for the structural framing and that in future, it had a potential to be used as extra
storage space. I performed design checks for the related structural elements for a
storage imposed load. This exercise avoided any anticipated potential risk.

CE1.9 (Job Tasks, Independent working, issue faced and solution)

It was also my task to draw up and update the reinforcement drawings. I


produced a sample markup which was checked by the chief project
engineer and the clients to ensure an acceptable format for the rest of the drawings.
After we issued this sample markup, the chief project engineer went on several
weeks holiday, which left me with the task of managing the timing and production
of the rest of these drawings, with minimal supervision from the department
manager. Using the original design computations as my basis, I drew up all the
detailed reinforcement plans. This approach allowed me to check and verify
the computations as I went, and update the drawings accordingly.

CE1.10 (Issue while performing tasks and solutions provided)

Altered drawings were revised and reissued as a next revision, in many cases with
copies of relevant calculations to show reasoning. During this time the rest of my
workload was light so, apart from one or two difficult areas, I took the chance to
push the drawings ahead and have the first revisions largely ready before time.
Whilst in the middle of this process, the client advised us that the pile capping
drawings needed to be issued earlier than anticipated, so I diverted more of my
time and resources to this task in order to get the drawings and documentation
ready by the deadline (Issue and solution). Key documentation met this deadline,
with supporting section drawings being delivered a few days later.

CE1.11 (Issue and Solution)

The client was concerned about the deflection under load of the suspended ground
floor slab. I discussed my computer model results with the client and demonstrated
that the design case deflections were acceptable. I also showed that changing the
design to provide less deflection would significantly increase construction costs.

CE1.12 (Issues faced and solutions provided)

Another engineer completed an independent verification of the ground floor


structure. I then went through and addressed all the issues raised, making changes
where necessary. The head office also reviewed and directed many queries to our
chief project engineer. I was then given the task of reviewing and addressing many
of these issues and providing responses. The reviewed design was provided to the
client who advised that the design brief had been met.

CE1.13 (Involvement in OHS, Planning, Approvals, Communication, etc.)

Apart from my design activities, my participation in this project involved health


and safety considerations, planning, obtaining approvals and communicating
effectively with stakeholders. By coincidence, a couple of months later I was on
holiday in this capital city and I used this opportunity to contact the head office and
organize a site visit with one of their engineers. At the time they were constructing
the basement and foundations, so not much of my design had been built yet.
However the experience was still very valuable to see the site and discuss my
designs with the site engineer to unearth any problems and methods he believed
things could have been done better.

(d) Summary

CE1.14 (outcomes/ professional benefits achieved: practical knowledge, project


management, management, analysis, design, communication skills, engineering,
building construction, appreciation and recognition)

This job was my first hands-on experience as a qualified Civil/ Structural Engineer
and I learnt so much about the practical application of the job. I learned many
things including how to read a project, leading workers, price analysis, purchasing,
communicating with people, designing, etc. I gained knowledge in the field of civil
engineering as well as knowledge in other related fields, e.g. project management,
etc. I gained great knowledge and skills in building and constructionduring my
time with “company” and I felt fortunate to be given the opportunity to lead this
kind of project. It was also a great honor for me to have the appreciation and
recognition of my manager on completion of the project.

You might also like