HP Case
HP Case
HP Case
Dara Falahi : df2444 Lokesh Prabhu : lp2480 Golazin Tabib : gt2264 Latitia Zemiro : lz2303 April 5, 12
Inventory
Crisis
Brent
Cartier,
manager
for
special
projects
in
Materials
Department
of
HP
was
facing
several
problems
with
inventory
levels
for
the
DeskJet
printer
product
line
in
1990s.
Their
main
problem
was
to
satisfy
the
customer
requirements
by
holding
minimum
inventory
in
Europe.
Market
required
98%
product
availability
however
the
distribution
was
asking
for
minimum
inventory.
Uncertainties
in
delivery
of
incoming
material,
internal
processes
and
demand
were
also
other
problems
that
they
were
facing.
Despite
growing
inventory
levels
at
the
distribution
centers
in
Europe
and
Asia- Pacific,
the
organization
in
Europe
claimed
that
inventory
levels
should
be
raised
to
meet
customer
demands.
On
the
other
hand,
although
HPs
new
inkjet
printers
were
selling
well,
inventory
levels
worldwide
were
rising
as
sales
rose.
In
Europe,
high
product
variety
was
making
inventory
levels
very
high.
DeskJet
printers
were
manufactured
in
Vancouvers
facility
and
shipped
to
one
of
HPs
distribution
centers
(DC)
in
North
America,
Asia-Pacific
or
Europe,
which
in
1990
were
filled
with
DeskJet
stocks.
Management
later
decided
to
operate
each
of
these
DCs
with
a
make-to-stock
mode
in
order
to
provide
high
levels
of
availabilities
to
the
customers.
At
the
moment
the
Vancouver
facility
was
not
able
to
build
the
right
products
in
right
quantities
and
meet
the
demand
efficiently.
Some
of
the
issues
that
are
highlighted
in
the
case
as
causes
of
the
inventory
problems
are:
Uncertainty
about
how
to
set
the
correct
the
inventory
level
Different
localization
options
make
inventory
difficult
to
manage
Long
lead
time
to
difficulty
in
forecasting
High
safety
stock
Conflicting
goals
between
various
departments
on
setting
and
implementing
consistent
inventory
levels
Minimizing
inventory
levels
while
satisfying
customer
needs
in
terms
of
product
availability.
There is no coordination in channel members so HP must improve this deficiency through increased information flow DC localizations The bullwhip effect in the supply chain caused massive fluctuations in the inventory levels. Therefore, product differentiation (product postponement) can be done at later stages to decrease the effect of bullwhip.
Although there are some disadvantages such as Air freight cost, redesign cost and more staffing in order to come up with the optimal solution, but a combination of all above recommendations could save time, provide better communication and satisfy customers. One of the main causes, which was brought up by a Stanford student as the root of the problem, was the forecasting system. The demand oscillations and wide range of products due to localization often contributed to forecast errors. These inaccurate forecasts were the basis for safety stock calculation creating high inventory levels and backorders. DCs were not connected and divided in terms of inventory policies due to the lack of a scientific rule on this. The magnitude of demand uncertainty led to this Inventory/Services crisis because having such a changeable demand made the process much harder at the DCs that wanted to keep safety stocks to cover demand. Products took 4 to 5 weeks to reach DCs in Europe and Asia, representing long lead times that raised less capability to respond to orders. Other situation that contributed to this crisis was the make-to-stock system that due to all the inaccurate forecasts and to long lead times creates high levels of inventory in the DCs resulting in carrying costs. By using push system, HP has to calculate at great length its inventory levels avoiding stock-out and overstock. Because of competitive nature in printers industry, this problem had to be handled quickly. Cartier had short time for these tasks because preparation was needed to be done for Mondays meeting with Group Management on worldwide inventory levels for the DeskJet Printer product line.
The
forecasted
average
monthly
demand
is
taken
from
the
data.
Lead
Time:
For
the
US,
it
is
8
days,
and
for
Asia
and
Europe,
5
weeks.
Z
is
the
coefficient
associated
with
the
rate
of
service.
is
the
standard
deviation
of
demand
during
the
lead
time
Exhibit
1
:
Computations
of
the
safety
stock
required
for
the
different
regions
Please Note: The commas represent the dots. Currently, with the introduction of the Kanban system that has helped HP going towards a pull system in production, HP has reached a general level of 0.9 months of inventory. Therefore, after computations of the differences between current levels of inventory and theoretical values of safety stock, we see that for the US, they are maintaining a very high level of inventory compared to what they should have; but for Asia and Europe, they have less than what they should.
In the case, we understand that they are facing a lot of shortages in Europe and this is one of the reason for it. Therefore, it will be necessary to implement the system of target inventory levels to avoid such shortages and keep the brand name that customers like. However, when we compute these levels and have a look at the data (standard deviation and mean of demand), we notice that for many options, the standard deviation is higher than the mean. It implies that forecasts are really not accurate and that it will be difficult to implement such systems of safety stocks because to meet such uncertainties, we will need to maintain a level of inventory that will be very high and then very expensive. A second recommendation would concern the creation of a new plant in Asia. Why do we think this recommendation has some sense? We know that the current market in Europe and in the US is mature; therefore we know better how to predict demand and meet customers needs. But for the Asian part, it is still developing and all the behaviors are not fully understood. HP believes in a potential growth in Asia on the printer market. To reduce cycle times and respond to the demand, it will be necessary to have a closer plant than the one in Vancouver that has been serving the whole world up to now. Air shipments are very fast but expensive to the company and HP should find a way to decrease such costs. As we have a 1.25 month cycle time for Asia and Europe compared to a 0.27 months for the US, the only way to be operating efficiently and meet demand is to reduce cycle times. It will ease the replenishments of the different printers and also decrease the levels of safety stock needed, as the lead-time will decrease. In order see what the challenges are to implement our recommendation, We can think of different risks facing this recommendation. The first one resides in the forecasted demands. Any inventory management can be implemented if demand follows a normal distribution. At the same time, if the forecasts are not accurate, the model will not fit and anticipate future demands. If standard deviation is too large, it will imply a constant very high level of inventory in the distribution center to meet demand, but this will be very expensive to HP. As Brents goals are to meet demand while minimizing inventory, this will not be the best solution. Another point to mention is about the potential creation of a DC or plant in Asia. This project needs to be profitable, and therefore we need to compute NPV calculation to be sure that we can invest (Here the data are not available to develop such calculations). We know that currently, Canon is leading the Japanese market and this market is very competitive. We need to be sure that HP will not only have very small Asian market shares because in that case, it will not be profitable to HP to build this new plant. Currently, the Asian sales compared to the European or US are very low. Then, HP should either invest in advertising to make the name of HP get a real brand name, or focus on companies that already know their products and that have subsidiaries in Asia.