0% found this document useful (0 votes)
4 views47 pages

Module-3 Formwork - 2

The document provides a comprehensive overview of formwork in construction, detailing its definition, types, requirements, and materials used. It covers specific applications for walls, floors, columns, and stairs, along with guidelines for design and removal. Additionally, it addresses potential failures and the importance of proper support and supervision during the construction process.

Uploaded by

Ankit Patel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views47 pages

Module-3 Formwork - 2

The document provides a comprehensive overview of formwork in construction, detailing its definition, types, requirements, and materials used. It covers specific applications for walls, floors, columns, and stairs, along with guidelines for design and removal. Additionally, it addresses potential failures and the importance of proper support and supervision during the construction process.

Uploaded by

Ankit Patel
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 47

1

Formwork
Advance construction Technology 01-04-2020
2 Formwork
 Introduction
 Form work for RCC walls
 Formwork for floors
 Formwork for columns
 Formwork for stairs
 Centering
 Slip formwork
 Failure of formwork
 Design features for formwork

Advance construction Technology 01-04-2020


3 Introduction
 “Formwork is a temporary structure which is removed after
the concrete gains sufficient strength should be such that
able to withstand the normal loads of construction without
impairing the properties of concrete.”
 As the fresh or wet concrete is in the plastic state, it required
temporary supports for casting it into different sizes and
shapes till it gains sufficient strength.
 These temporary supports, such as timber and steel forms
and moulds are known as form work or shuttering.

Advance construction Technology 01-04-2020


4 Use of Formwork in different structure
 Wall
 Column
 Beam
 Slab
 Stairs
 Chimney
 Water tank
 Cooling tower
 Etc...

Advance construction Technology 01-04-2020


5 Requirements of Form work
 Be able to sustain loads during construction (Structural
Design) concrete weight and pressure, live load of
equipment's (e.g. vibrators), personal etc.
 Free from leaks (leaks in form works is major reason of
honey combs.)
 Should be true in shape (least in adversely affect the
flatness, etc. of the concrete surface).
 Should be clean (least it discolour the concrete surface).

Advance construction Technology 01-04-2020


6 Qualities of Formwork
 It should be water tight.
 It should be strong.
 It can be reusable.
 Its contact surface should be uniform.
 It should be according to the size of member.

Advance construction Technology 01-04-2020


7 Requirement of good formwork
 Easy removal
 Economic
 Strength
 Rigidity
 Less leakage
 Smooth surface
 Light weight
 Quality
 Supports

Advance construction Technology 01-04-2020


8 Materials for formwork
 The selection of materials suitable for formwork should be based on the
price, safety during construction, and the quality required in the finished
product. Approval of formwork materials by the engineer/architect, if
required by the contract documents, should be based on how the
quality of materials affects the quality of finished work. Where the
concrete surface appearance is critical, the engineer/architect should
give special notice and make provision for preconstruction mockups.

 Timber formwork
 Steel formwork
 Plywood formwork
 Aluminum sheet formwork
 Fiberglass sheet formwork

Advance construction Technology 01-04-2020


9 Timber formwork

Advance construction Technology 01-04-2020


10 Steel formwork

Advance construction Technology 01-04-2020


11 Plywood Formwork

Advance construction Technology 01-04-2020


12 Aluminum sheet formwork

Advance construction Technology 01-04-2020


13 Fiberglass Sheet Formwork

Advance construction Technology 01-04-2020


14 Formwork for R.C.C walls

 Material/instrument required:
 Boarding –sheet
 Studs
 Braces
 Wedges
 M.S tie bars
 Sole plate
 Stakes
 Etc..

Advance construction Technology 01-04-2020


15 Boarding –sheet

Advance construction Technology 01-04-2020


16 Studs

Advance construction Technology 01-04-2020


17 Braces

Advance construction Technology 01-04-2020


18 Wedges

Advance construction Technology 01-04-2020


19 Stakes

Advance construction Technology 01-04-2020


20 Tie bars

Advance construction Technology 01-04-2020


• The sheet are supported by vertical
Formwork for RCC Wall
21 studs and horizontal wales.
• The tie are provided to maintain the
distance between the sheet and to
resist the bursting action of concrete.
• The small pieces of timber known as
spacer may be used and they are to be
removed as the concrete reaches that
level.
• The wire ties and bolts may be also
provided.
• Bolts are provided with grease so as to
make their removal easy after 2 or 3 days
of pouring concrete.

Advance construction Technology 01-04-2020


 The bracing may be provided at the
22
horizontal distance of about 2 m and
they are supported at ground level by
stakes.
 If the wall is high the formwork is to be
supported on either side by guy wires
instead of bracing.
 The reinforcement should be properly
placed in position before laying of
concrete.
 The formwork should be cleaned and
washed with water before laying
concrete in it.
 If the height of wall is 3 m or more, the
wall is prepared in vertical lifts of about 1
m height.

Advance construction Technology 01-04-2020


Important facts:  The formwork for floor should be designed for the
weight of concrete plus some additional load to the
23 extent of about 30% to provided for labor, material,
equipment etc..
 The post should be provided with diagonal braces.
 It is possible to use steel forms for slab, the other
components being of wood.
 The vertical supports should be firmly supported at the
bottom.
 The formwork for floor should be given necessary
slope as required and the whole surface should be
thoroughly cleaned.
 The box for beam formwork is generally prepared at
ground level and hoisted and placed in position.
 When secondary beams are to rest on the main
beams, suitable opening at the correct position are
provided in main beam to receive the formwork of
secondary beams.
Advance construction Technology 01-04-2020
24 Formwork for RCC column

Advance construction Technology 01-04-2020


 Column box consist of two ends and two
25 Formwork for column side.
 Ends side is fixed with wedges and sides
are with yokes.
 The height of each panel is equal to the
story height minus the slab thickness and
floor sheeting.
 Yokes are equally spaced on both the
sides and ends. It can project at both the
ends by about 25cm.
 A hole is usually provided at the bottom
of formwork to remove debris.
 Formwork components for any column
are required to be designed properly
resist high pressure resulting from quick
filling of the concrete.

Advance construction Technology 01-04-2020


26 Formwork for stair

Advance construction Technology 01-04-2020


27 Formwork of stair

Advance construction Technology 01-04-2020


 Timber plank or steel plat for the waist slab
are placed on cross joist, which are
28 Formwork for stair supported on stringer joist.
 The cross joist of 5 cm x 10 cm placed below
planking .
 Stringer joist of size 7.5 cm x 10 cm provide
bottom ends of the stair as per slope of the
stair.
 Vertical side planks or steel plates are
provided on both the side of the bottom
plank with slop.
 The steel reinforcement is then fixed in the
position as per structure design.
 The horizontal riser planks 4 to 5 cm thick
and width equal to height of riser and
length equal to width of stair are fixed with
side plank with help of nails.
 The stiffener joist is placed along the middle
of the riser plank for extra support.
 Concreting is done in the formwork starting
from bottom to top.
Advance construction Technology 01-04-2020
29 Removal of formwork

 The operation of removing the formwork is known as the stripping


 The forms which can be conveniently reused are known as panel forms
 The form which cannot be reused because of their non standard shape are
known as stationary forms.
 Sequence for removing formwork:
1. Shutter forming vertical faces of wall beam and column side.
2. Shuttering forming soffit to slab should be removed next.
3. Shuttering forming soffit of beam girder or other heavily loaded shuttering
should be removed in the end.

Advance construction Technology 01-04-2020


Structural member Period of time
30
Sides of Walls, Columns and Vertical faces of 1 to 2 days
beam
Slabs (props left under) 3 days

Beam soffits (props left under) 7 days

Removal of Props of Slabs:

i) Slabs spanning up to 4.5m 7 days

ii) Slabs spanning over 4.5m 14 days

Removal of props for beams and arches

i) Span up to 6m 14 days

ii) Span over 6m 21 days

Advance construction Technology 01-04-2020


31 Centering
 Centering is the temporary structure required to support brick, stone or
concrete work of arch, dome etc.. During its construction till it has gained
sufficient strength.
 Timber centering is most common in arch construction as it is easy in
installation and removal and also economic.
 The centering choice depends upon several factor:
 Shape of arch
 Span of opening
 Thickness of soffit
 Material used in arch construction

Advance construction Technology 01-04-2020


32 centering
 The usual centering for arch construction consists of a thick wooden plank
with horizontal bottom and the upper surface is made to match with the
shape of intrados of the arch which is known as turning piece.
 Its width is normally 10 cm. and is supported on vertical timber posts called
props, with wooden wedges to tighten or loosen centering.
 If the width of soffit is wider than 10 cm two ribs suitably spaced and shaped
at the top may be used. These ribs are connected by 4*2 cm wooden
sections called laggings. The ribs are supported by wedges and posts at both
the ends as shown.

Advance construction Technology 01-04-2020


33

Advance construction Technology 01-04-2020


34 Centering for Big Arches
• For construction of big arches centering will be invariably required.
Features:
 The design of centering should be such that the combined cost of labor
and material works out to be the minimum.
 The centering should be so prepared that maximum quantity of material
of centering may be recovered.it means that the centering should be
have a greater salvage value.
 The centering should be of sufficient strength and rigidity.it will then be
possible to keep such centering in line, level and shape during
construction.
 The centering should be so arranged so that it can be removed easily
after work is completed without causing any damage to arch.

Advance construction and Equipments 01-04-2020


35 Types of centering

 Timber truss centering


 Trestle centering
 Steel truss centering

Advance construction Technology 01-04-2020


36 Timber truss centering

 This type of centering timber truss of suitable shape and design are used;
 condition under which it is useful:
 When arch is provided in deep valley or gorge.
 When the support for centering are to rest in deep water.
 When the passage for traffic is required during the construction of arch.

Advance construction Technology 01-04-2020


Trestle centering
37

• The term trestle centering is used to mean that the arch is supported by
vertical posts resting on ground

Single tier Two tier

Advance construction Technology 01-04-2020


38 Trestle centering

Inclined of post Combined trestle centering

Advance construction Technology 01-04-2020


39 Steel truss centering

 When it is impossible or uneconomical to use trestle type centering.


 When depth of water is more
 When arches are to be constructed in river subjected to frequent heavy
floods.

Advance construction Technology 01-04-2020


40
Slip form work

Advance construction Technology 01-04-2020


41 Slip formwork
 The slip formwork proves to be economical for vertical structures, which are
in the form of concrete shafts.
 Hence they are widely used for piers, chimneys, towers missile launching
bases, water reservoirs, silos, revolving restaurants, etc.
 The essential parts of slip forms are :
1. Sheathing
2. Wales or ribs
3. Yokes
4. Working platform
5. Suspended scaffolding
6. Lifting devices

Advance construction Technology 01-04-2020


42 Falsework

Advance construction Technology 01-04-2020


43 False work
 False work consists of a temporary structures used in construction to support
spanning or arched structures in order to hold the component in place until
its construction is sufficiently advanced to support itself.
 False work also includes temporary support structures for formwork used to
mould concrete form a desired shape and scaffolding to give workers
access to the structure being constructed.
 These are stabilized for lateral loads using series of timber or cable braces.

Advance construction Technology 01-04-2020


44 False work

 Construction of false work in bridges consists of :


 Timber or concrete foundation pads
 Timber corbles
 Sand jacks and wedges
 Steel sill beams
 Timber or round hollow steel posts
 Steel cap beams
 Timber or steel stringer beams and timber joists

Advance construction Technology 01-04-2020


45 Failure of formwork

 Striping operation is carried out carefully.


 Shoring is not properly supported.
 Forms are continuously supported and, supports are uniformly beard.
 Work should be carried under strict supervision.
 Wedging of post to counter-balance load must be carried out with
extreme care.

Advance construction Technology 01-04-2020


46
Failure of formwork

Advance construction Technology 01-04-2020


47

Advance construction Technology 01-04-2020

You might also like