Plaxis 2d 2024.3 2d 1 Tutorial
Plaxis 2d 2024.3 2d 1 Tutorial
3
Tutorial Manual
Introduction.......................................................................
1 Settlement of a circular footing on sand...................................................11
1.1 Introduction........................................................................................................................ 11
1.2 Geometry.......................................................................................................................... 12
1.3 Case A: Rigid footing....................................................................................................... 12
1.3.1 Create a new project...........................................................................................13
1.3.2 Define the soil stratigraphy................................................................................ 15
1.3.3 Create and assign material data sets................................................................ 16
1.3.4 Define the footing...............................................................................................21
1.3.5 Generate the mesh............................................................................................ 22
1.3.6 Define and perform the calculation.................................................................. 24
1.4 Case B: Flexible footing..................................................................................................33
1.4.1 Modify the geometry.......................................................................................... 33
1.4.2 Add material properties for the footing............................................................ 35
1.4.3 Generate the mesh............................................................................................ 36
1.4.4 Calculations........................................................................................................36
1.4.5 View the calculation results.............................................................................. 38
1.4.6 Generate a load-displacement curve................................................................39
2 Drained and undrained stability of an embankment.................................43
2.1 Introduction...................................................................................................................... 43
2.2 Create new project.........................................................................................................44
2.3 Define the soil stratigraphy............................................................................................44
2.4 Create and assign material data sets............................................................................45
2.5 Create the embankment.................................................................................................46
2.6 Generate the mesh......................................................................................................... 46
2.7 Define and perform the calculation............................................................................... 47
2.7.1 Initial phase: Initial conditions............................................................................ 47
2.7.2 Phase 1: Embankment construction on drained subsoil................................... 47
2.7.3 Phase 2: Embankment construction on undrained subsoil.............................. 48
2.7.4 Calculate............................................................................................................ 48
2.8 Results............................................................................................................................. 49
2.9 Safety analysis................................................................................................................50
2.9.1 Evaluation of safety analysis results................................................................. 52
3 Submerged construction of an excavation............................................. 55
3.1 Introduction...................................................................................................................... 55
3.2 Create new project......................................................................................................... 56
3.3 Define the soil stratigraphy............................................................................................ 57
3.4 Create and assign material data sets............................................................................ 57
3.5 Define the structural elements.......................................................................................59
3.5.1 To define the diaphragm wall:........................................................................... 59
3.5.2 To define the interfaces:...................................................................................60
3.5.3 To define the excavation levels:........................................................................61
3.5.4 To define the strut:........................................................................................... 62
3.5.5 To define the distributed load:......................................................................... 63
3.6 Generate the mesh......................................................................................................... 64
3.7 Define and perform the calculation............................................................................... 64
3.7.1 Initial phase......................................................................................................... 65
3.7.2 Phase 1: External load....................................................................................... 65
3.7.3 Phase 2: First excavation stage........................................................................ 66
3.7.4 Phase 3: Installation of a strut.......................................................................... 67
3.7.5 Phase 4: Second (submerged) excavation stage............................................. 67
3.7.6 Phase 5: Third excavation stage.......................................................................68
3.7.7 Execute the calculation......................................................................................69
3.8 View the calculation results........................................................................................... 70
3.8.1 Displacements and stresses.............................................................................. 70
3.8.2 Shear forces and bending moments................................................................. 71
4 Stabilisation of a rock slope.................................................................. 75
4.1 Introduction...................................................................................................................... 75
4.2 Create a new project...................................................................................................... 76
4.3 Create and assign material data sets............................................................................ 76
4.3.1 Define the rock mass stratigraphy.....................................................................77
4.4 Define the structural elements.......................................................................................78
4.4.1 Define the fault...................................................................................................78
4.4.2 Define the excavation of the road cut..............................................................79
4.4.3 Define the cables.............................................................................................. 80
4.4.4 Define the retaining wall and backfill............................................................... 81
4.5 Generate the mesh......................................................................................................... 82
4.6 Define and perform the calculation............................................................................... 83
4.6.1 Initial phase: Initial conditions............................................................................84
4.6.2 Phase 1: First excavation stage........................................................................ 84
4.6.3 Phase 2: Installation of the first two rows of cables........................................85
4.6.4 Phase 3: Second excavation stage.................................................................. 86
4.6.5 Phase 4: Installation of the third cable.............................................................86
4.6.6 Phase 5: Construction of the retaining wall..................................................... 87
4.6.7 Phase 6: Backfilling........................................................................................... 87
4.6.8 Phase 7 and Phase 8: Safety analysis............................................................. 88
4.7 Calculate..........................................................................................................................89
4.8 Results............................................................................................................................. 89
4.8.1 Evaluation of results...........................................................................................89
4.8.2 Evaluation of safety analysis results.................................................................91
5 Settlements due to tunnel construction [GSE].........................................95
5.1 Introduction...................................................................................................................... 95
5.2 Create new project......................................................................................................... 96
5.3 Define the soil stratigraphy............................................................................................ 96
5.3.1 Create and assign material data sets................................................................ 97
5.4 Define the structural elements..................................................................................... 100
5.4.1 Define the tunnel.............................................................................................. 100
5.4.2 Define building................................................................................................. 103
5.5 Generate the mesh........................................................................................................104
5.6 Define and perform the calculation..............................................................................105
5.6.1 Initial phase....................................................................................................... 105
5.6.2 Phase 1: Building..............................................................................................106
5.6.3 Phase 2: TBM...................................................................................................106
5.6.4 Phase 3: TBM conicity.................................................................................... 106
5.6.5 Phase 4: Tail void grouting..............................................................................107
5.6.6 Phase 5: Lining installation.............................................................................. 107
5.6.7 Execute the calculation.................................................................................... 107
5.7 Results............................................................................................................................ 107
6 Excavation of an NATM tunnel [GSE]..................................................... 111
6.1 Introduction...................................................................................................................... 111
6.2 Create a new project..................................................................................................... 112
6.3 Define the soil stratigraphy........................................................................................... 112
6.4 Create and assign material data sets........................................................................... 113
6.5 Define the tunnel........................................................................................................... 116
| PLAXIS 2D 2024.3
6.6 Generate the mesh........................................................................................................ 118
6.7 Define and perform the calculation...............................................................................119
6.7.1 Initial phase........................................................................................................ 119
6.7.2 Phase 1: First tunnel excavation (deconfinement)...........................................120
6.7.3 Phase 2: First (temporary) lining..................................................................... 120
6.7.4 Phase 3: Second tunnel excavation (deconfinement)..................................... 121
6.7.5 Phase 4: Second (final) lining.......................................................................... 121
6.7.6 Execute the calculation.................................................................................... 122
6.8 Results............................................................................................................................122
7 Dry excavation using a tie back wall [ADV]........................................... 125
7.1 Introduction..................................................................................................................... 125
7.2 Create new project........................................................................................................ 126
7.3 Define the soil stratigraphy........................................................................................... 126
7.4 Create and assign material data sets........................................................................... 127
7.5 Define the structural elements...................................................................................... 128
7.5.1 To define the diaphragm wall and interfaces:..................................................129
7.5.2 Definition of excavation levels......................................................................... 130
7.5.3 Defining the ground anchor............................................................................. 130
7.5.4 Defintition of distributed load.......................................................................... 132
7.6 Generate the mesh........................................................................................................ 132
7.7 Define and perform the calculation.............................................................................. 133
7.7.1 Initial phase........................................................................................................ 133
7.7.2 Phase 1: Activation of wall and load................................................................ 134
7.7.3 Phase 2: First excavation................................................................................. 135
7.7.4 Phase 3: First anchor row................................................................................ 135
7.7.5 Phase 4: Second excavation............................................................................ 136
7.7.6 Phase 5: Second anchor row........................................................................... 136
7.7.7 Phase 6: Final excavation................................................................................. 137
7.7.8 Execute the calculation.....................................................................................139
7.8 Results............................................................................................................................ 139
8 Dry excavation using a tie back wall - ULS [ADV].................................. 143
8.1 Introduction.....................................................................................................................143
8.2 Define the geometry..................................................................................................... 143
8.3 Define and perform the calculation..............................................................................146
8.3.1 Changes to all phases...................................................................................... 146
8.3.2 Execute the calculation....................................................................................147
8.4 Results............................................................................................................................147
9 Construction of a road embankment [ADV]............................................151
9.1 Introduction......................................................................................................................151
9.2 Create new project........................................................................................................152
9.3 Define the soil stratigraphy...........................................................................................152
9.4 Create and assign material data sets...........................................................................153
9.5 Define the construction.................................................................................................155
9.5.1 Definiton of the embankment...........................................................................155
9.5.2 To define the drains.........................................................................................155
9.6 Generate the mesh........................................................................................................156
9.7 Define and perform the calculation.............................................................................. 157
9.7.1 Initial phase: Initial conditions........................................................................... 157
9.7.2 Consolidation analysis......................................................................................158
9.7.3 Safety analysis................................................................................................. 160
9.7.4 Calculate............................................................................................................ 161
9.8 Results............................................................................................................................162
9.8.1 Deformed mesh................................................................................................ 162
9.8.2 Incremental displacements..............................................................................163
9.8.3 Excess pore pressures.................................................................................... 163
9.8.4 Development of excess pore pressure........................................................... 164
Table of Contents |
9.8.5 Safety analysis results..................................................................................... 165
9.9 Using drains...................................................................................................................169
9.10 Updated mesh and updated water pressures analysis...............................................170
10 Excavation and dewatering [ADV]....................................................... 173
10.1 Introduction................................................................................................................... 173
10.2 Create and assign material data set........................................................................... 173
10.3 Define the structural elements.................................................................................... 173
10.4 Generate the mesh...................................................................................................... 174
10.5 Define and perform the calculation............................................................................ 175
10.5.1 Phase 6: Dewatering....................................................................................... 175
10.5.2 Execute the calculation.................................................................................. 175
10.6 Results.......................................................................................................................... 175
11 Cyclic vertical capacity and stiffness of circular underwater footing
[ADV].................................................................................................177
11.1 Introduction.................................................................................................................... 177
11.2 Create new project....................................................................................................... 178
11.3 Define the soil stratigraphy.......................................................................................... 178
11.4 Create and assign material data sets.......................................................................... 179
11.4.1 Material: Clay - total load................................................................................ 179
11.4.2 Material: Clay - cyclic load.............................................................................189
11.4.3 Material: Concrete...........................................................................................192
11.5 Define the structural elements.....................................................................................193
11.5.1 Define the concrete foundation.......................................................................193
11.5.2 Define the interfaces...................................................................................... 193
11.5.3 Define a vertical load......................................................................................195
11.6 Generate the mesh....................................................................................................... 195
11.7 Define and perform the calculation............................................................................. 195
11.7.1 Initial phase....................................................................................................... 196
11.7.2 Phase 1: Footing and interface activation.......................................................196
11.7.3 Phase 2: Cyclic Vertical Bearing capacity and stiffness................................ 196
11.7.4 Phase 3: Calculate vertical cyclic stiffness.................................................... 196
11.7.5 Execute the calculation....................................................................................197
11.8 Results........................................................................................................................... 197
12 Flow through an embankment [ULT]....................................................201
12.1 Introduction................................................................................................................... 201
12.2 Create new project..................................................................................................... 202
12.3 Define the soil stratigraphy........................................................................................ 202
12.4 Create and assign material data set.......................................................................... 203
12.5 Generate the mesh..................................................................................................... 203
12.6 Define and perform the calculation........................................................................... 204
12.6.1 Initial phase..................................................................................................... 205
12.6.2 Phase 1-Transient ground water flow analysis............................................. 206
12.6.3 Phase 2-Long term groundwater flow analysis............................................ 207
12.6.4 Execute the calculation................................................................................. 208
12.7 Results..........................................................................................................................208
13 Potato field moisture content [ULT]......................................................211
13.1 Introduction.................................................................................................................... 211
13.2 Create new project...................................................................................................... 212
13.3 Define the soil stratigraphy......................................................................................... 212
13.4 Create and assign material data sets......................................................................... 214
13.5 Generate the mesh...................................................................................................... 214
13.6 Define and perform the calculation............................................................................ 215
13.6.1 Initial phase......................................................................................................215
13.6.2 Transient phase.............................................................................................. 216
13.6.3 Execute the calculation.................................................................................. 219
| PLAXIS 2D 2024.3
13.7 Results.......................................................................................................................... 219
14 Stability of dam under rapid drawdown [ULT].......................................221
14.1 Introduction................................................................................................................... 221
14.2 Create new project......................................................................................................222
14.3 Define the soil stratigraphy........................................................................................ 222
14.4 Create and assign material data sets.........................................................................222
14.5 Define the dam............................................................................................................223
14.6 Generate the mesh..................................................................................................... 224
14.7 Define and perform the calculation............................................................................224
14.7.1 Initial phase: Dam construction & high reservoir........................................... 225
14.7.2 Phase 1: Rapid drawdown..............................................................................228
14.7.3 Phase 2: Slow drawdown.............................................................................. 232
14.7.4 Phase 3: Low level.........................................................................................234
14.7.5 Phase 4 to 7: Safety analysis........................................................................ 235
14.7.6 Execute the calculation.................................................................................. 235
14.8 Results......................................................................................................................... 236
15 Dynamics analysis of a generator on an elastic foundation [ULT]...........239
15.1 Introduction...................................................................................................................239
15.2 Create new project..................................................................................................... 240
15.3 Define the soil stratigraphy........................................................................................ 240
15.4 Create and assign material data sets......................................................................... 241
15.5 Define the structural elements.................................................................................... 241
15.6 Generate the mesh......................................................................................................242
15.7 Define and perform the calculation............................................................................243
15.7.1 Initial phase..................................................................................................... 243
15.7.2 Phase 1: Footing............................................................................................. 243
15.7.3 Phase 2: Start generator................................................................................244
15.7.4 Phase 3: Stop generator................................................................................246
15.7.5 Execute the calculation.................................................................................. 247
15.7.6 Additional calculation with damping.............................................................. 247
15.8 Results......................................................................................................................... 248
16 Pile driving [ULT]............................................................................... 251
16.1 Introduction................................................................................................................... 251
16.2 Create new project......................................................................................................252
16.3 Define the soil stratigraphy.........................................................................................252
16.4 Create and assign material data sets.........................................................................252
16.5 Define the structural elements................................................................................... 254
16.5.1 Define the pile.................................................................................................255
16.5.2 Define a load..................................................................................................255
16.6 Generate the mesh......................................................................................................257
16.7 Define and perform the calculation............................................................................258
16.7.1 Initial phase......................................................................................................258
16.7.2 Phase 1: Pile activation.................................................................................. 258
16.7.3 Phase 2: Pile driving...................................................................................... 259
16.7.4 Phase 3: Fading............................................................................................. 260
16.7.5 Execute the calculation.................................................................................. 260
16.8 Results.......................................................................................................................... 261
17 Free vibration and earthquake analysis of a building [ULT]....................263
17.1 Introduction................................................................................................................... 263
17.2 Create new project...................................................................................................... 264
17.3 Define the soil stratigraphy......................................................................................... 264
17.4 Create and assign material data sets......................................................................... 265
17.5 Define the structural elements....................................................................................268
17.5.1 Define the building.......................................................................................... 268
17.5.2 Define the loads............................................................................................. 270
Table of Contents |
17.5.3 Create interfaces on the boundary................................................................ 271
17.6 Generate the mesh...................................................................................................... 272
17.7 Define and perform the calculation.............................................................................272
17.7.1 Initial phase...................................................................................................... 272
17.7.2 Phase 1: Building............................................................................................. 273
17.7.3 Phase 2: Excitation..........................................................................................273
17.7.4 Phase 3: Free vibration...................................................................................273
17.7.5 Phase 4: Earthquake.......................................................................................274
17.7.6 Execute the calculation...................................................................................276
17.8 Results.......................................................................................................................... 276
18 Thermal expansion of a navigable lock [ULT].......................................279
18.1 Introduction...................................................................................................................279
18.2 Create new project..................................................................................................... 280
18.3 Define the soil stratigraphy........................................................................................ 280
18.4 Create and assign material data sets........................................................................ 280
18.5 Define the structural elements................................................................................... 282
18.6 Generate the mesh......................................................................................................283
18.7 Define and perform the calculation............................................................................284
18.7.1 Initial phase..................................................................................................... 284
18.7.2 Phase 1: Construction.................................................................................... 285
18.7.3 Phase 2: Heating............................................................................................ 287
18.7.4 Execute the calculation..................................................................................289
18.8 Results......................................................................................................................... 289
19 Freeze pipes in tunnel construction [ULT]........................................... 293
19.1 Introduction...................................................................................................................293
19.2 Create new project..................................................................................................... 294
19.3 Define the soil stratigraphy........................................................................................ 294
19.4 Create and assign material data sets.........................................................................295
19.5 Define the structural elements................................................................................... 297
19.5.1 Define freeze pipes........................................................................................ 297
19.5.2 Define freeze pipes boundary conditions..................................................... 297
19.5.3 Define model boundary conditions............................................................... 298
19.5.4 Assign model boundary conditions.............................................................. 298
19.5.5 Define the tunnel........................................................................................... 298
19.6 Generate the mesh......................................................................................................299
19.7 Define and perform the calculation............................................................................299
19.7.1 Initial phase......................................................................................................299
19.7.2 Phase 1: Transient calculation....................................................................... 300
19.7.3 Execute the calculation.................................................................................. 300
19.8 Results.......................................................................................................................... 301
| PLAXIS 2D 2024.3
ix
Introduction
PLAXIS 2D is a finite element package that has been developed specifically for the analysis of
deformation, stability and flow in geotechnical engineering projects. The simple graphical input
procedures enable a quick generation of complex finite element models, and the enhanced
output facilities provide a detailed presentation of computational results. The calculation itself is
fully automated and based on robust numerical procedures. This concept enables new users to
work with the package after only a few hours of training.
Though the various tutorials deal with a wide range of interesting practical applications, this
Tutorial Manual is intended to help new users become familiar with PLAXIS 2D. The tutorials and
the respective material data sets should therefore not be used as a basis for practical projects.
Users are expected to have a basic understanding of soil mechanics and should be able to work
in a Windows environment. It is strongly recommended that the tutorials are followed in the
order that they appear in the manual. Please note that minor differences in results maybe found,
depending on hardware and software configuration.
The Tutorial Manual does not provide theoretical background information on the finite element
method, nor does it explain the details of the various soil models available in the program. The
latter can be found in the Material Models Manual, as included in the full manual, and theoretical
background is given in the Scientific Manual. For detailed information on the available program
features, the user is referred to the Reference Manual. In addition to the full set of manuals, short
courses are organised on a regular basis at several places in the world to provide hands-on
experience and background information on the use of the program.
Tutorials available for different licencing levels:
Given PLAXIS 2D features and soil models are provided for separated licencing services, the
present tutorial manuals are available with previous installation of a specific licence level.
For more information about licencing levels please visit:General Information Manual, Reference
Manual and Material Models Manual).
As a summary, the tutorials available for each licence level can be identified with the following
conventions:
●
Tutorials with no identification - generally available for PLAXIS 2D licence.
●
[ADV] - tutorials for users with PLAXIS 2D Advanced licence.
●
[ULT] - tutorials for users with PLAXIS 2D Ultimate licence.
●
[GSE] - tutorials for users with Geotechnical SELECT subscription (previous Basic, Advanced
or Ultimate licence level required).
ix
x | Introduction | OpenTopic
x |
Settlement of a circular footing on
1
sand
1.1 Introduction
In this chapter a first application is considered, namely the settlement of a circular foundation
footing on sand. This is the first step in becoming familiar with the practical use of PLAXIS 2D.
The general procedures for the creation of a geometry model, the generation of a finite element
mesh, the execution of a finite element calculation and the evaluation of the output results are
described here in detail. The information provided in this chapter will be utilised in the later
tutorials. Therefore, it is important to complete this first tutorial before attempting any further
tutorial examples.
Objectives:
●
Starting a new project
●
Creating an axisymmetric model
●
Creating soil stratigraphy using the Borehole feature
●
Creating and assigning of material data sets for soil ( Mohr-Coulomb model )
●
Defining prescribed displacements
●
Creation of footing using the Plate feature
●
Creating and assigning material data sets for plates
●
Creating loads
11
●
Generating the mesh
●
Generating initial stresses using the K0 procedure
●
Defining a Plastic calculation
●
Activating and modifying the values of loads in calculation phases
●
Viewing the calculation results
●
Selecting points for curves
●
Creating a 'Load - displacement' curve
1.2 Geometry
A circular footing with a radius of 1.0 m is placed on a sand layer of 4.0m thickness as shown
in Figure 1–1 (p. 12). Under the sand layer there is a stiff rock layer that extends to a large
depth. The purpose of the exercise is to find the displacements and stresses in the soil caused
by the load applied to the footing. Calculations are performed for both rigid and flexible footings.
The geometry of the finite element model for these two situations is similar. The rock layer is not
included in the model; instead, an appropriate boundary condition is applied at the bottom of
the sand layer. To enable any possible mechanism in the sand and to avoid any influence of the
outer boundary, the model as shown in Figure 1–1 (p. 12) is extended in horizontal direction to
a total radius of 5.0 m.
2.0 m
Load
Footing
y
Sand 4.0 m
The Quick start dialog box appears in which you can create a new project or select an
existing one.
The Project properties window appears with three tabsheets: Project, Model and Cloud
services .
Note: For the different licencing tiers the Project properties window will vary from
three tabsheets to four tabsheets with the addition of Constants alongwith Project,
Model and Cloud services.
Note:
The first step in every analysis is to set the basic parameters of the finite element
model. This is done in the Project properties window. These settings include the
description of the problem, the type of model, the basic type of elements, the basic
units and the size of the drawing area.
To enter the appropriate settings for the footing calculation follow the steps below.
3 In the Project tabsheet, enter Lesson 1 in the Title box and type Settlement of a
circular footing in the Comments box.
4 Click the Next button at the bottom or click the Model tab.
The project is created with the given properties. The Project properties window closes and the
Soil mode view will be shown, where the soil stratigraphy can be defined.
Note: The project properties can be changed later. You can access the Project
properties window by selecting the corresponding option from the File menu.
1
Click the Create borehole button in the side (vertical) toolbar to start defining the soil
stratigraphy.
2 Click at x = 0 in the drawing area to locate the borehole.
The Modify soil layers window will appear as shown in Figure 1–5 (p. 16) .
3 Add a soil layer by clicking the Add button in the Modify soil layers window.
4 Set the top boundary of the soil layer at y = 4 and keep the bottom boundary at y = 0 m.
By default the Head value (groundwater head) in the borehole column is set to 0 m.
Mechanical
Young's modulus E'ref 3 2
13 · 10 kN/m
Poisson's ratio ν 0.3 -
Cohesion c'ref 1 2
kN/m
Friction angle φ' 30 °
Dilatancy angle ψ 0 °
To create a material set for the sand layer, follow these steps:
1
Open the Material sets window by clicking the Materials button in the Modify soil
layers window or in the side toolbar.
The Material sets window pops up as shown in Figure 1–6 (p. 18).
A new window will appear with the tabsheets: General, Mechanical, Groundwater,
Interfaces and Initial.
3 In the Material set box of the General tabsheet, write Sand in the Identification box.
The default material model (Mohr-Coulomb) and drainage type (Drained) are valid for this
example.
4 Enter the proper values in the General properties box (Figure 1–7 (p. 19)) according to
the material properties listed in Table 1 (p. 17). Keep parameters that are not mentioned
in the table at their default values.
Note:
a. As displayed in Figure 1–7 (p. 19) a Feedback side panel is included in the
Material window. This panel prevents the definition of an invalid material data
set. To display the list of detailed messages please select Show full feedback.
Three types of messages are possible:
● Errors: the parameter value or combination of parameter values must be
changed, otherwise the material set could be invalid and calculation of the
project will be blocked.
● Warnings: the parameter value seems to deviate from a recommended
parameter value or parameter range. Generally the material set will not
be considered invalid and calculating the project will not be blocked. The
chosen parameter could however cause unexpected results.
● Hints: the entered parameter can be defined under certain circumstances or
options.
b. The Feedback side panel is displayed at the moment of defining materials and
structures. For the sake of simplicity, this panel will only be shown in some
tutorial examples..
5 Click the Next button or click the Mechanical tab to proceed with the input of model
parameters.
Figure 1–8: Mechanical tabsheet of the Soil window - Soil and interfaces set type
6 Enter the model parameters of Table 1 (p. 17) in the corresponding edit boxes of the
Mechanical tabsheet (Figure 1–8 (p. 20)) and keep the other parameters as their default
values. A detailed description of different soil models and their corresponding parameters
can be found in the Material Models Manual.
Note: To understand why a particular soil model has been chosen, see Appendix B
of the Material Models Manual.
7 The soil material is drained, the geometry model does not include interfaces and the
default thermal and initial conditions are valid for this case, therefore the remaining
tabsheets can be skipped. Click OK to confirm the input of the current material data set.
Now the created data set will appear in the tree view of the Material sets window.
8 Drag the set Sand from the Material sets window (select it and hold down the left mouse
button while moving) to the graph of the soil column on the left hand side of the Modify
soil layers window and drop it there (release the left mouse button).
9 Click OK in the Material sets window to close the database.
Tip:
Visibility of a grid in the drawing area can simplify the definition of geometry. The grid
provides a matrix on the screen that can be used as reference. It may also be used
for snapping to regular points during the creation of the geometry. The grid can be
activated by clicking the corresponding button under the drawing area. To define the
size of the grid cell and the snapping options:
Click the Snapping options button in the bottom toolbar. The Snapping window
pops up where the size of the grid cells and the snapping interval can be specified. The
spacing of snapping points can be further divided into smaller intervals by the Number
of snap intervals value. Use the default values in this tutorial.
1 Click the Structures tab to proceed with the input of structural elements in the Structures
mode .
2
Click the Create prescribed displacement button in the side toolbar.
3
Select the Create line displacement option in the expanded menu.
4 In the drawing area move the cursor to point (0 4) and click the left mouse button.
2
Click the Generate mesh button in the side toolbar.
The Mesh options window pops up as shown in Figure 1–10 (p. 23). The Medium option
is by default selected as element distribution.
A new window is opened displaying the generated mesh as shown in Figure 1–11 (p. 23).
Note that the mesh is automatically refined under the footing.
Note:
● By default, the Element distribution is set to Medium. The Element distribution
setting can be changed in the Mesh options window. In addition, options are
available to refine the mesh globally or locally (for more information see the
Reference Manual).
● The finite element mesh has to be regenerated if the geometry is modified.
● The automatically generated mesh may not be perfectly suitable for the intended
calculation. Therefore it is recommended that the user inspects the mesh and
makes refinements if necessary.
1 Click the Staged construction tab to proceed with the definition of calculation phases. The
Flow conditions mode may be skipped.
When a new project has been defined, a first calculation phase named ' Initial phase', is
automatically created and selected in the Phases explorer as shown in Figure 1–12 (p.
24):
All structural elements and loads that are present in the geometry are initially automatically
switched off, only the soil volumes are initially active.
2
Click the Edit phase button or double-click the phase in the Phases explorer.
In this tutorial lesson the properties of the Initial phase will be described. Below an overview
is given of the options to be defined even though the default values of the parameters are
used.
The other default options in the Phases window will be used as well in this tutorial.
The Phases window is displayed in Figure 1–13 (p. 25).
4 In the Model explorer expand the Model conditions subtree as shown in Figure 1–14 (p.
26).
For deformation problems two types of boundary conditions exist: Prescribed displacement
and prescribed forces (loads). In principle, all boundaries must have one boundary condition
in each direction. That is to say, when no explicit boundary condition is given to a certain
boundary (a free boundary), the natural condition applies, which is a prescribed force equal
to zero and a free displacement.
To avoid the situation where the displacements of the geometry are undetermined,
some points of the geometry must have prescribed displacements. The simplest form
of a prescribed displacement is a fixity (zero displacement), but non-zero prescribed
displacements may also be given.
5 Expand the Deformations subtree.
Note that the box is checked by default. By default, a full fixity is generated at the
base of the geometry, whereas roller supports are assigned to the vertical boundaries
(BoundaryXMin and BoundaryXMax are normally fixed, BoundaryYMin is fully fixed and
BoundaryYMax is free).
6 Expand the Water subtree.
1
Click the Add phase button in the Phases explorer.
The current phase starts from the Initial phase, which contains the initial stress state. The
default options and values assigned are valid for this phase as shown in Figure 1–16 (p.
28).
5 In the drawing area right-click the prescribed displacement and select the Activate option in
the appearing menu as shown in Figure 1–17 (p. 29).
Tip: Calculation phases may be added, inserted or deleted using the Add, Insert and
Delete buttons in the Phases explorer or in the Phases window.
1
Click the Calculate button to start the calculation process. Ignore the warning that no
nodes and stress points have been selected for curves.
During the execution of a calculation, a window appears which gives information about the
progress of the actual calculation phase as shown in Figure 1–18 (p. 30) .
The information, which is continuously updated, shows the calculation progress, the current
step number, the global error in the current iteration and the number of plastic points in
the current calculation step. It will take a few seconds to perform the calculation. When a
calculation ends, the window is closed and focus is returned to the main window.
The phase list in the Phases explorer is updated. A successfully calculated phase is
indicated by a check mark inside a green circle .
2
Save the project by clicking the Save button before viewing results.
Once the calculation has been completed, the results can be displayed in the Output program.
2 From the Reached values subtree look for the Force-Y which is an important value of the
current application. This value represents the total reaction force corresponding to the
applied prescribed vertical displacement, which corresponds to the total force under 1.0
radian of the footing (note that the analysis is axisymmetric). In order to obtain the total
footing force, the value of Force-Y should be multiplied by 2π (this gives a value of about
588 kN).
4
Click the View calculation results button in the side toolbar.
As a result, the Output program is started, showing the deformed mesh at the end of the
selected calculation phase as shown in Figure 1–19 (p. 31):
The deformed mesh is scaled to ensure that the deformations are visible.
5 Select the menu Deformations > Total displacements > |u|.
The plot shows the colour shadings of the total displacements. The colour distribution is
displayed in the legend at the right hand side of the plot.
Tip: The legend can be toggled on and off by clicking the corresponding option in
the View menu.
6 The total displacement distribution can be displayed in contours by clicking the Contour
lines button in the toolbar.
The plot shows contour lines of the total displacements, which are labelled. An index is
presented with the displacement values corresponding to the labels.
7
Click the Arrows button .
The plot shows the effective principal stresses at the stress points of each soil element
with an indication of their direction and their relative magnitude as shown in Figure 1–20 (p.
32):
A new window is opened in which a table is presented, showing the values of the principal
stresses and other stress measures in each stress point of all elements.
Tip:
● In addition to the total displacements, the Deformations menu allows for the
presentation of Incremental displacements. The incremental displacements are
the displacements that occurred within one calculation step (in this case the final
step). Incremental displacements may be helpful in visualising an eventual failure
mechanism.
● The plots of stresses and displacements may be combined with geometrical features,
as available in the Geometry menu.
Mechanical
Isotropic - Yes -
Axial stiffness EA1 5 · 10
6 kN/m
Click OK.
The new data set now appears in the tree view of the Material sets window.
7 Drag the set called Footing to the drawing area and drop it on the footing. Note that the
shape of the cursor changes to indicate that it is valid to drop the material set.
Tip: If the Material sets window is displayed over the footing and hides it, click on
its header and drag it to another position.
2
Click the Generate mesh button in the side toolbar. For the Element distribution
parameter, use the option Medium (default).
3
Click the View mesh button to view the mesh.
4 Click the Close tab to close the Output program.
1.4.4 Calculations
2 Leave the initial phase as it is. The initial phase is the same as in the previous case.
3 Double-click the following phase (Phase_1) and enter an appropriate name for the phase ID.
Keep the Calculation type as Plastic and keep the Loading type as Staged construction.
4 Close the Phases window.
The calculation definition is now complete. Before starting the calculation it is advisable to
select nodes or stress points for a later generation of load-displacement curves or stress
and strain diagrams. To do this, follow these steps:
8 Click the Select points for curves button in the side toolbar.
As a result, all the nodes and stress points are displayed in the model in the Output
program. The points can be selected either by directly clicking on them or by using the
options available in the Select points window.
9 In the Select points window enter (0.0 4.0) for the coordinates of the point of interest and
click Search closest.
The nodes and stress points located near that specific location are listed.
10 Select the node at exactly (0.0 4.0) by checking the box in front of it. The selected node
is indicated by Node 4* in the model when the Selection labels option is selected in the
Mesh menu.
Tip: Instead of selecting nodes or stress points for curves before starting the
calculation, points can also be selected after the calculation when viewing the
output results. However, the curves will be less accurate since only the results
of the saved calculation steps will be considered. To select the desired nodes by
clicking on them, it may be convenient to use the Zoom in option on the toolbar
to zoom into the area of interest.
11 Click the Update button on the top left to return to the Input program.
12 Check if both calculation phases are marked for calculation by a blue arrow . If this is
not the case click the symbol of the calculation phase or right-click and select Mark for
calculation from the pop-up menu.
13 Click the Calculate button to start the calculation.
14
Click the Save button to save the project after the calculation has finished.
Note: Multiple (sub-)windows may be opened at the same time in the Output program.
All windows appear in the list of the Window menu. PLAXIS 2D follows the Windows
standard for the presentation of sub-windows (Cascade, Tile, Minimize, Maximize,
etc).
The Curve generation window pops up as shown in Figure 1–26 (p. 40).
Tip:
You can re-enter the Settings window (in the case of a mistake, a desired regeneration
or modification) by:
● Double-click the curve in the legend of the chart OR
● Select the menu Format > Settings.
The properties of the chart can be modified in the Chart tab sheet whereas the
properties curve can be modified in the corresponding tab sheet.
2.1 Introduction
In this chapter the construction of an embankment on clay is simulated. The clay will first be
considered a drained material and then an undrained material. For both cases the factor of
safety will be determined. This would for instance give an indication of both the long term and
short term stability of the embankment.
Objectives
●
Modelling Drained and Undrained soil behaviour.
●
Changing material sets during the calculation.
●
Calculating a factor of safety.
Geometry
Figure 2–1 (p. 44) shows the layout of an embankment . The embankment is 4 m high and the
crest of the embankment has a width of 2.0 m. The groundwater level is just below surface, but
to simplify the problem it will be defined at ground level.
43
14 m 8m 2m 12 m 14 m
y
4m
6m
1 Start the Input program and select Start a new project from the Quick start dialog box.
2 In the Project tabsheet of the Project properties window, enter an appropriate title.
3 In the Model tabsheet keep the default options for Model (Plane strain), and Elements (15-
Noded).
4 Set the model dimensions to: xmin = 0 m, xmax = 50 m, ymin = -6 m and ymax = 4 m.
5 Keep the default values for units, constants and the general parameters and click OK to
close the Project properties window.
The Modify soil layers window pops up as shown in Figure 2–2 (p. 45).
2 Add a single soil layer from Top = 0 to Bottom = -6.
3 Keep the Head for this borehole to 0. Hence, the groundwater level coincides with ground
level.
Mechanical
Secant stiffness in standard drained ref 3 2
E50 15·10 5,600 kN/m
triaxial test
Tangent stiffness for primary ref 3 2
Eoed 15·10 5,000 kN/m
oedometer loading
ref 3 3 2
Unloading / reloading stiffness Eur 45·10 20·10 kN/m
Cohesion c'ref 3 10 2
kN/m
Friction angle φ' 30 25 °
Initial
K0-determination - Automatic Automatic -
Overconsolidation ratio OCR 1.0 1.2 -
1
Select the Show materials button so that the Materials sets window shows up.
2 Using the New button define the two material sets as defined in the Table 3 (p. 45) .
3 In order to create the undrained material set for the clay layer select the drained material
in the Material sets window and click the Copy button to duplicate the material set. In the
copied material set, change the name and set the Drainage type to Undrained (A).
4 Assign the material set representing the drained clay to the subsoil.
1 Go to Structures mode .
2 From the tools side bar select the Create soil polygon option and then from the small
popup button menu that appears select the Create soil polygon option again.
3 Now draw a polygon starting from (x y) = (14 0) continuing to (22 4), (24 4) and finally (36
0).
4 Now assign the embankment material to the polygon. This can either be done by opening
the Material sets window and then drag and drop the material set onto the polygon, or by
selecting the polygon and then in the Selection explorer set the Material option of the soil
polygon to the embankment material.
2
Click the Generate mesh button to generate the mesh.
In the new phase the Calculation Type > Plastic analysis and the Loading type > Staged
construction are used as a default.
2 Right-click on the embankment and from the popup menu select the Activate option to
activate the soil representing the embankment. The model of phase 1 is shown in Figure 2–5
(p. 48).
1 In the Phase explorer select the Initial phase and then create a new phase using the Add
phase button .
Because the initial phase was the selected phase the newly created phase 2 will start from
the initial phase. In case by mistake phase 2 starts from phase 1, this can be changed by
double-clicking on Phase 2 in the Selection explorer so that the Phases window opens. In
the General section now set the option Start from phase to the initial phase and close the
Phases window again.
2 Now the soil behaviour of the subsoil must be changed to undrained by assigning the
undrained material set to the subsoil. There are several ways to do this:
●
From the navigation side bar select the Show materials button . From the Material
sets window that opens drag and drop the material set for undrained clay on the subsoil.
●
Right-click on the subsoil and from the popup menu(s) that open consecutively select the
options Soil ( ) > Soil ( ) > Set material and finally assign the material representing
the undrained subsoil .
●
Select the subsoil and in the Selection explorer change the Material under the Soil
object for the material representing the undrained subsoil.
3 Finally, activate the embankment. The model for phase 2 is shown in Figure 2–6 (p. 48).
2.7.4 Calculate
Before starting the calculation it's recommended to choose some nodes or stress points to later
evaluate the results in for instance load-displacement or stress-strain curves. In this project we
will select a point halfway the left hand side slope to later evaluate the factor of safety.
3 Click the Update button on the top left to close the Output program and store the selected
point.
4 Click the Calculate button to start the calculation.
2.8 Results
1 After the calculation ended, select the first phase and click the View calculations results
button .
The Output program now opens showing the deformed mesh after the construction of the
embankment on the drained subsoil.
2 From the Displayed step drop-down list at the top choose to see the results for Phase 2.
Now the deformed mesh after construction of the embankment on undrained subsoil is
shown.
Figure 2–7 (p. 49) shows the deformed mesh for both phases. In case of the drained
subsoil the embankment settles everywhere, but in case of the undrained subsoil the
embankment settles in the middle but heaves near the toes. This makes perfect sense: the
subsoil is now undrained and because of that there can be no volume change. Hence, if the
subsoil settles in the middle due to the weight of the embankment it must heave somewhere
else, typically just next to the embankment.
Figure 2–7: Deformed mesh after phase 1 (top) and phase 2 (bottom)
It can also be seen that in case of the undrained subsoil the embankment seems to widen
leading to a larger settlement at the top of the embankment. This is not immediately obvious
and it will be discussed in more detail after performing a factor of safety analysis.
3 From the Stresses menu select the option Pore pressures and then p excess . This will show
the excess pore pressures due to the undrained loading of the subsoil. By default the pore
pressures are shown as iso-shadings but with the buttons and from the horizontal
button bar at the top it is possible to see the principal directions of the pore pressures, either
for all or a reduced number of stress points.
2.8 Results | 49
Figure 2–8 (p. 50) shows that excess pore pressures have developed due to the
construction of the embankment. The highest excess pore pressures are of course directly
underneath the embankment, but also on either side of the toes of the embankment some
excess pore pressures occur.
Where S represents the shear strength. The ratio of the true strength to the computed minimum
strength required for equilibrium (hence, the mobilized strength) is the safety factor that is
conventionally used in soil mechanics. For soil models using the standard Coulomb failure
condition, the safety factor is obtained as:
Where c and φ are the input strength parameters and σn is the actual normal stress component.
The parameters cr and φr are reduced strength parameters that are just large enough to maintain
equilibrium. The principle described above is the basis of the method of Safety that can be used
in PLAXIS 2D to calculate a global safety factor. In this approach the cohesion and the tangent of
the friction angle are reduced in the same proportion:
The reduction of strength parameters is controlled by a multiplier called ΣMsf that is increased
step-by-step until failure occurs. The safety factor is then defined as the value of ΣMsf at
failure, provided that at failure a more or less constant value is obtained for a number of
successive load steps with ongoing deformations.
Note:
Note that for a Safety phase the option Use pressures from the previous phase
in the Pore pressure calculation type drop-down menu is automatically selected
and grayed out indicating that this option cannot be changed. A Safety calculation
always uses the same pore pressures as the phase for which the safety factor has to be
calculated.
The resulting plot shown in Figure 2–10 (p. 52) gives a good impression of the failure
mechanisms. The magnitude of the displacement increments is not relevant. From the results it
can be seen that the slope on the left side of the embankment fails with a classical slip surface .
By choosing phase 4 from the drop down list at the toolbar the failure mechanism for the
embankment constructed on undrained subsoil can be evaluated. The failure mechanism is no
longer limited to just the embankment, but is in fact mostly a failure of the subsoil underneath
the embankment. This also explains the widening of the embankment at the base as was
observed earlier: the soil underneath the embankment fails and moves horizontally away from
the center of the embankment shown in Figure 2–11 (p. 53).
The safety factor can be obtained from the Calculation info option of the Project menu. The
Multipliers tabsheet of the Calculation information window represents the actual values of
the load multipliers. The value of ΣMsf represents the safety factor, provided that this value is
indeed more or less constant during the previous few steps.
The best way to evaluate the safety factor, however, is to plot a curve in which the parameter
ΣMsf is plotted against the displacements of a certain node. Although the displacements are not
relevant, they indicate whether or not a failure mechanism has developed.
In order to evaluate the safety factors for the three situations in this way, follow these steps:
1. Click the Curves manager button in the toolbar.
2. Click New in the Charts tabsheet.
3. In the Curve generation window, use from the dropdown list the previously selected Node
for the x-axis. Select Deformations > Total displacements > |u|.
4. For the y-axis, select Project > Multipliers > ΣMsf. The Safety phases are considered in
the chart.
5. Press OK to close the window and generate the chart.
6. Right-click on the chart and select the Settings option in the appearing menu. The Settings
window pops up.
7. In the tabsheet corresponding to the curve click the Phases button.
8. In the Select phases window select only Phase 3 as shown in Figure 2–12 (p. 53):
13. Click Apply to update the chart according to the changes made and click OK to close the
Settings window.
14. The plot is shown as follows in Figure 41:
The maximum displacements plotted are not relevant. It can be seen that for both curves a
more or less constant value of ΣMsf is obtained. Hovering the mouse cursor over a point on the
curves, a box shows up with the exact value of ΣMsf as well as the calculation phase. With the
latter it can be determined that the upper curve with a factor of safety of 1.8 is Phase 3, hence
the embankment on drained soil. Similarly the lower curve with a factor of safety of 1.4 is Phase
4, the embankment on undrained soil.
3.1 Introduction
This tutorial illustrates the use of PLAXIS 2D for the analysis of submerged construction of
an excavation. Most of the program features that were used in Tutorial 1 will be utilised here
again. In addition, some new features will be used, such as the use of interfaces and anchor
elements, the generation of water pressures and the use of multiple calculation phases. The new
features will be described in full detail, whereas the features that were treated in Tutorial 1 will
be described in less detail. Therefore it is suggested that Tutorial 1 should be completed before
attempting this exercise.
Objectives
●
Modelling soil-structure interaction using the Interface feature.
●
Advanced soil models (Soft Soil model and Hardening Soil model).
●
Undrained (A) drainage type.
●
Defining Fixed-end-anchor.
●
Creating and assigning material data sets for anchors.
●
Simulation of excavation (cluster de-activation).
Geometry
This tutorial concerns the construction of an excavation close to a river. The submerged
excavation is carried out in order to construct a tunnel by the installation of prefabricated tunnel
55
segments which are 'floated' into the excavation and 'sunk' onto the excavation bottom. The
excavation is 30 m wide and the final depth is 20 m. It extends in longitudinal direction for
a large distance, so that a plane strain model is applicable. The sides of the excavation are
supported by 30 m long diaphragm walls, which are braced by horizontal struts at an interval
of 5 m. Along the excavation a surface load is taken into account. The load is applied from 2 m
2
from the diaphragm wall up to 7 m from the wall and has a magnitude of 5 kN/m /m.
The upper 20 m of the subsoil consists of soft soil layers, which are modelled as a single
homogeneous clay layer. Underneath this clay layer there is a stiffer sand layer, which extends
to a large depth and 30 m of the sand layer are considered in the model which is shown in Figure
3–1 (p. 56).
43 m 5m 2m 30 m 2m 5m 43 m
5 kN/m2/m 5 kN/m2/m
Strut
1m
19 m to be excavated
Clay
10 m
Sand
Diaphragm wall
20 m
Since the geometry is symmetric, only one half (the left side) is considered in the analysis.
The excavation process is simulated in three separate excavation stages. The diaphragm wall
is modelled by means of a plate, such as used for the footing in the previous tutorial. The
interaction between the wall and the soil is modelled at both sides by means of interfaces. The
interfaces allow for the specification of a reduced wall friction compared to the friction in the
soil. The strut is modelled as a spring element for which the normal stiffness is a required input
parameter.
3 In the Project tabsheet of the Project properties window, enter an appropriate title.
4 In the Model tabsheet keep the default options for Model (Plane strain}, and Elements (15-
Node).
5 Set the model Contour to xmin = 0 m, xmax = 65 m, ymin = -30 m and ymax = 20 m.
6 Keep the default values for units and constants and click OK.
1
Click the Create borehole button and create a borehole at x = 0.
Next the material data sets are defined and assigned to the soil layers, see 3.4 Create and
assign material data sets (p. 57).
Table 4: Material properties of the sand and clay layer and the interfaces
Mechanical
Secant stiffness in standard drained ref 3 3 2
triaxial test E50 4 · 10 40 · 10 kN/m
ref 3 3 2
Unloading / reloading stiffness Eur 12 · 10 120 · 10 kN/m
Groundwater
Data set - Standard Standard -
Soil type - Coarse Coarse -
Use defaults - None None -
Interfaces
Srength determination - Manual Manual -
Interface reduction factor Rinter 0.5 0.67 -
Initial
K0 determination - Automatic Automatic -
1
Click the Materials button in the Modify soil layers window.
The Material sets window pops up, where the Soil and interfaces option is selected by
default as the Set type.
2 Click the New button in the Material sets window to create a new data set.
3 For the clay layer, enter Clay for the Identification and select Hardening Soil as the Soil
model. Set the Drainage type to Undrained (A).
4 Enter the properties of the clay layer, as listed in Table 4 (p. 57), in the General,
Mechanical and Flow parameters tabsheets.
5 Click the Interfaces tab. Select the Manual option in the Strength drop-down menu. Enter
a value of 0.5 for the parameter Rinter.
This parameter relates the strength of the soil to the strength in the interfaces, according
to the equations: and where:
, see Table 4 (p. 57)
Hence, using the entered Rinter-value gives a reduced interface friction (wall frictions)
and interface cohesion (adhesion) compared to the friction angle and the cohesion in the
adjacent soil.
Note:
● When the Rigid option is selected in the Strength drop-down, the interface has
the same strength properties as the soil (Rinter = 1.0).
● Note that a value of Rinter < 1.0 , reduces the strength as well as the stiffness
of the interface (for more info see the corresponding section in the Reference
Manual.
● Instead of accepting the default data sets of interfaces, data sets can directly
be assigned to interfaces in the Model explorer by selecting Interfaces >
Interface_#_# > Material mode.
Mechanical
Isotropic - Yes -
1
Click the Create structure button in the side toolbar.
2
In the expanded menu select the Create plate option as shown in Figure 3–2 (p. 60).
6 Drag the Diaphragm wall data set to the wall in the geometry and drop it as soon as the
cursor indicates that dropping is possible.
7 Click OK to close the Material sets window.
Note: In general, only one point can exist at a certain coordinate and only one
line can exist between two points. Coinciding points or lines will automatically be
reduced to single points or lines. More information is available in the Reference
Manual
Note:
● In order to identify interfaces at either side of a geometry line, a positive sign (
) or negative sign ( ) is added. This sign has no physical relevance or influence
on the results.
● A Virtual thickness factor can be defined for interfaces. This is a purely
numerical value, which can be used to optimise the numerical performance of
the interface. To define it, select the interface in the drawing area and specify
the value to the Virtual thickness factor parameter in the Selection explorer.
Non-experienced users are advised not to change the default value. For more
information about interface properties see the Reference Manual - Chapter 5 -
Advanced Geometric Modelling options.
Mechanical
Out-of-plane spacing Lspacing 5 m
Axial stiffness EA 2 · 10
6 kN
1
Click the Create structure button in the side toolbar and select the Create fixed-end
anchor in the expanded menu.
2 Move the cursor to (50 19) and click the left mouse button. A fixed-end anchor is added,
being represented by a rotated T with a fixed size.
3
Click the Show materials button in the side toolbar. Set the Set type parameter in
the Material sets window to Anchors and click the New button. Enter Strut as an
Identification of the data set and enter the properties as given in Table 6 (p. 62). Click
OK to close the data set.
4 Click OK to close the Material sets.
5 Make sure that the fixed-end anchor is selected in the drawing area.
6 In the Selection explorer assign the material data set to the strut by selecting the
corresponding option in the Material drop-down menu.
The anchor is oriented in the model according to the Directionx and Directiony parameters in
the Selection explorer . The default orientation is valid in this tutorial.
Note: The Equivalent length is the real distance between the connection point and
the fixed end point. For an excavation problem that is typically half the width of the
excavation as the axis of symmetry in the middle of the excavation is considered
fixed.
2
Click the Generate mesh button in the side toolbar. For the Element distribution
parameter, use the option Medium (default).
3
Click the View mesh button to view the mesh as shown in Figure 3–6 (p. 64).
The default settings are valid for this phase. In the model the full geometry is active except
for the wall, interfaces, strut and load.
2 Click the Select multiple objects button in the side toolbar. In the appearing menu select
Select line > Select plates as shown in Figure 3–7 (p. 65).
When the wall is unselected it can be seen that wall is now visible in the color that is
specified in the material dataset.
5 Right-click the distributed load to activate it and select the Activate option from the
appearing menu.
The load has been defined in the Structures mode as -5 kN/m/m. The value can be checked
in the Selection explorer.
6 Make sure all the interfaces in the model are active.
A new calculation phase appears in the Phases explorer. Note that the program
automatically presumes that the current phase should start from the previous one and that
the same objects are active.
2 The default settings are valid for this phase. In the Staged construction mode all the
structure elements except the fixed-end anchor are active.
3 In the drawing area right-click the top right cluster and select the Deactivate option in the
appearing menu.
The model for the first excavation phase is shown in Figure 3–9 (p. 67):
Note: Note that in PLAXIS 2D the pore pressures are not automatically deactivated
when deactivating a soil cluster. Hence, in this case, the water remains in the
excavated area and a submerged excavation is simulated.
1
Click the Add phase button to add a new phase.
2 Deactivate the third cluster from the top on the right hand side of the mesh.
The model for the phase is shown in Figure 3–11 (p. 69):
1
Click the Select points for curves button in the side toolbar.
The connectivity plot is displayed in the Output program and the Select points window is
activated.
2 Select some nodes on the wall at points where large deflections can be expected (e.g. 50
10). The nodes located near that specific location are listed. Select the convenient one by
checking the box in front of it in the list.
3 Click on the Update tab at the top left to save the selected points, close the Output program
and go back to the Input program.
4
Click the Calculate button to calculate the project.
During a Staged construction calculation phase, a multiplier called ΣMstage is increased from
0.0 to 1.0. This parameter is displayed in the calculation info window. As soon as ΣMstage has
reached the value 1.0, the construction stage is completed and the calculation phase is finished.
If a Staged construction calculation finishes while ΣMstage is smaller than 1.0, the program will
give a warning message. The most likely reason for not finishing a construction stage is that
a failure mechanism has occurred, but there can be other causes as well. See the Reference
Manual for more information about Staged construction.
2
Click the View calculation results button on the toolbar.
As a result, the Output program is started, showing the deformed mesh (scaled up) as
shown in Figure 3–12 (p. 70) at the end of the selected calculation phase, with an
indication of the maximum displacement:
Note:
In the Output program, the display of the loads, fixities and prescribed
displacements applied in the model can be toggled on/off by clicking the
corresponding options in the Geometry menu.
The plot shows colour shadings of the displacement increments, which indicates the
formation of a mechanism of soil movement behind the wall.
The plot shows the displacement increments of all nodes as arrows. The length of the
arrows indicates the relative magnitude.
5 Select the menu Stresses > Principal effective stresses > Effective principal stresses.
The plot in Figure 3–13 (p. 71) shows the effective principal stresses at the three middle
stress points of each soil element with an indication of their direction and their relative
magnitude. Note that the Center principal stresses button is selected in the toolbar. The
orientation of the principal stresses indicates a large passive zone under the bottom of the
excavation and a small passive zone behind the strut.
The bending moment in the wall is displayed in Figure 55 with an indication of the maximum
moment:
Note: The Window menu may be used to switch between the window with the
forces in the wall and the stresses in the full geometry. This menu may also be
used to Tile or Cascade the two windows, which is a common option in a Windows
environment.
4 Select the first window (showing the effective stresses in the full geometry) from the
Window menu. Double-click the strut.
75
top is 12 m. The geometry of the rock slope, along with the fault and reinforcements, is shown in
Figure 4–1 (p. 76).
1
Select the Show materials button and the Material sets window will pop up.
2 Click the New button in the Material sets window to create the data set as shown in the
Table 7 (p. 76).
Mechanical
Young's modulus Erm 6 2
1 · 10 kN/m
Poisson's ratio ν 0.25 -
Uni-axial compressive strength 3 2
intact rock 25 · 10 kN/m
Tensile strength - 30 2
kN/m
Dilatancy angle ψmax 10 °
Dilatancy parameter 50 2
kN/m
3 Select the created polygon and assign the Material to the soil polygon as shown in Figure 4–
2 (p. 77).
1 Click the Structures tab to proceed with the input of structural elements in the Structures
mode.
3
Click the Create soil polygon button in the side toolbar and select the Create soil
polygon option.
4 Create the rock mass either in the command line or by clicking on points at coordinates:
(0 -13) (0 15) (20 15) (23.5 13) (27 10.5) (29 8.5) (32 6) (35 4) (37
2.5) (40 0) (42.5 -1) (45 -2) (45 -13)
Mechanical
Normal stiffness 6 3
1·10 kN/m
Shear stiffness 3 3
100·10 kN/m
Strength method - Peak
Cohesion 8 2
kN/m
Friction angle 20 o
Dilatancy angle 0 o
1
In the Structures mode, click the Create line button and select the Create discontinuity
option .
2 Draw the discontinuity through the points (8 15) and (42 -13).
3 Select the discontinuity, then in the Selection explorer click on Material. This will display a
drop-down list.
4
Click the Add button to create and assign a new material set for the discontinuity as
shown in Figure 4–4 (p. 79).
5 Define the material data set for the discontinuity based on the properties listed in Table 8 (p.
78).
1
Define the slope face of the road cut by drawing a line passing through points (20 15) and
(25 0).
2 Define the bottom of excavation (roadway) by drawing a line through points (25 0) and (40
0).
3
Define the upper 9 m of excavation by drawing a horizontal line from (23 6) to the point
where it intersects with the initial slope surface at (32 6).
Mechanical
Cable bolt spacing 3 m
Cross section type - Predefined -
Predefined cross section type - Solid circular beam -
Diameter 0.0254 m
Stiffness 6 2
98.6·10 kN/m
Compressive yield strength 0 kN
Shear stiffness 6 2
15·10 kN/m
Strength distribution - Uniform -
Cohesive strength - 800 kN/m
1 In the side tool bar click on the Create line button and then select the Create cable option
.
2 Draw a line from (21.5 10.5) to (11.5 7) to create the first row of cables.
3 Repeat step 2 to define the middle and bottom rows of the cables using the coordinates
given in Table 9 (p. 80).
Mechanical
Young's modulus 6 2
27·10 kN/m
Poisson's ratio 0.15 -
Cohesion 500 2
kN/m
Friction angle 35 o
Dilatancy angle 5 o
Mechanical
Young's modulus 3 2
100·10 kN/m
Cohesion 5 2
kN/m
Friction angle 45 o
Dilatancy angle 15 o
To define the geometry of the retaining wall and backfill, follow these steps:
1
Click on the Create line button and then select the Create line option .
2 Draw the retaining wall by defining lines through the points (25.5 0), (25.5 3) then (25.5 3),
(26.5 3) and (26.5 3), (26.5 0).
3 Define the backfill by drawing a line from (25.5 3) at the retaining wall to the sloping face of
the rock cut at (24 3).
4 Create the separate materials for the retaining wall and the backfill in the Material sets >
Soil and interfaces using the parameters listed in Table 11 (p. 81) and Table 12 (p. 81).
These materials will be assigned later in the Staged construction mode.
Note:
In areas where large stress concentrations or large deformation gradients are expected,
it is desirable to have a more accurate (finer) finite element mesh, whereas other parts
of the geometry might not require a fine mesh. Such a situation often occurs when the
geometry model includes edges or corners or structural objects. Local refinement is
based on a local coarseness factor that can be specified for each geometry entity.
3 Activate the discontinuity by selecting it in the Model explorer. All other structural
components (cables) should remain deactivated.
4 In the Phases explorer, double-click the initial phase and for Calculation type select the
Gravity loading option. The other default parameters for the initial phase remain the same.
5 Click OK to close the Phases window.
Note: The water conditions are not considered in this tutorial example, therefore the
pore pressure calculation options are neglected.
The model for the Phase 1 is shown in Figure 4–8 (p. 85) below:
2 Select the third cable and activate it in the Selection explorer by clicking on the checkbox in
front of the Cables.
3 In the Selection explorer, click the checkbox for Adjust prestress and assign a pre-stress
force of 200 kN.
The model configuration for Phase 4 is shown in Figure 4–11 (p. 87).
The model configuration for Phase 6 is shown in Figure 4–13 (p. 88) below:
4 In the Phases window, Phase 3 is automatically selected from the Start from phase drop-
down menu.
5
In the Calculation type box, select Safety .
6 In the Deformation control parameters section select the Reset displacements to zero
option in order to exclude the existing deformations from the previous calculations.
7 In the Numerical control parameters section deselect the Use default iter parameters
option, and in the Max steps box input 180. The safety calculation is now defined for Phase
3.
8 Follow the same steps as mentioned above to create a new calculation phase that analyses
the stability of the final phase after the construction of the retaining wall and the backfill
(Phase 6).
The phases after defining the safety calculations are displayed in Figure 4–14 (p. 89).
4.7 Calculate
Before initiating the calculation, it is recommended to select some nodes in order to generate the
plots to determine the factor of safety at a later stage. To do this, follow these steps.
1
Click on the Select points for curves button in the side toolbar.
2 Select the characteristic point (23 6) for curves and click on Update.
3
Click on the Calculate button to compute the project.
4
Once the calculation is completed, save the project by clicking on the Save button .
4.8 Results
For this tutorial, the results for the excavation phases and the safety analysis are evaluated.
Figure 4–15 (p. 90) shows the deformed mesh for the Phase 3.
4.7 Calculate | 89
Figure 4–15: The deformed mesh after the second excavation stage
2 To inspect the resulting axial force in the cables, in the toolbar from the Displayed step
button drop-down menu, go to Phase 6. Click on the Drag a window to select structures
button in the side toolbar and drag the mouse to define a rectangle encompassing all
the cables. Select the Cable option in the appearing window, as shown in Figure 4–16 (p.
90).
4 From the Forces menu, select the option to view the shear force developed in the
grouted segments as displayed in Figure 4–17 (p. 91).
Figure 4–19 (p. 92) and Figure 4–20 (p. 92) shows the contour plots and arrows of
the incremental displacement from the safety calculations for both Phases 3 and 6. The
magnitude of the displacement increments is not relevant, but it indicates whether or not
a failure mechanism has developed. In Figure 4–19 (p. 92), the rock slope tends to
7 In the Curve generation window, select the pre-calculation Node from the dropdown list
for the x-axis. Select Deformations > Total displacements > |u|.
8 For the y-axis, select Project > Multipliers > ΣMsf.
10 Right-click on the chart and select the Settings option in the appearing menu. The Settings
window pops up.
11 In the tabsheet corresponding to the node curve, click the Phases button.
12 In the Select phases window make sure only the safety calculation Phases are selected.
14 In the Settings window change the titles and colour of the curves in the corresponding
tabsheet.
15 Click Apply to update the chart according to the changes made and click OK to close the
Settings window. The plot is shown in Figure 4–21 (p. 93).
In Phase 7 which represents the second excavation stage has a lower factor of safety of
about 1.33. It indicates that the rock slope along the discontinuity is unstable. However, in
5.1 Introduction
In this tutorial the construction of a shield tunnel in medium soft soil and the influence on a
pile foundation is considered. A shield tunnel is constructed by excavating soil at the front of a
tunnel boring machine (TBM) and installing a tunnel lining behind it. In this procedure the soil
is generally over-excavated, which means that the cross sectional area occupied by the final
tunnel lining is always less than the excavated soil area. Although measures are taken to fill up
this gap, one cannot avoid stress re-distributions and deformations in the soil as a result of the
tunnel construction process. To avoid damage to existing buildings or foundations on the soil
above, it is necessary to predict these effects and to take proper measures. Such an analysis
can be performed by means of the finite element method. This tutorial shows an example of
such an analysis.
Objectives
●
Modelling of the tunnel boring process
●
Modelling undrained behaviour using the Undrained (B) option
Geometry
The tunnel considered in this tutorial has a diameter of 5 m and is located at an average depth of
17 m. The geometry of the tunnel is shown in Figure 5–1 (p. 96) .
95
5m 10 m 20 m
+3 m
y
0m
x
Piles
Clay
-10 m
Sand
-12 m
Deep clay
-17 m
Deep sand
-30 m
Figure 5–1: Geometry of the tunnel project with an indication of the soil layers
1 Start the Input program and select Start a new project from the Quick start dialog box.
2 In the Project tabsheet of the Project properties window, enter an appropriate title.
3 In the Model tabsheet keep the default options for Model (Plane strain), and Elements (15-
Noded).
4 Set the model Contour to xmin = 0 m, xmax = 35 m, ymin = -30 m and ymax = 3 m.
5 Keep the default values for units and constants and press OK to close the Project properties
window.
1
Click the Create borehole button and create a borehole at x = 0.
Figure 5–2: The soil stratigraphy in the Modify soil layers window
2 Create the soil stratigraphy as shown in Figure 5–2 (p. 97).
The data sets of the two lower soil layers include appropriate parameters for the tunnel
interfaces. In the other data sets the interface properties just remain at their default values. Enter
four data sets with the properties as listed in Table 13 (p. 98) and Table 14 (p. 98) , then
assign them to the corresponding clusters in the geometry model.
The layers have the following properties:
Mechanical
Young's modulus at reference level E' ref 3 3 2
3.4 · 10 9.0 · 10 kN/m
Poisson's ratio ν(nu) 0.33 0.33 -
Groundwater
Data set - Standard Standard -
Soil type - Coarse Coarse -
Use defaults - None None -
Interfaces
Strength determination - Rigid Manual -
Interface reduction factor Rinter 1.0 0.7 -
Initial
K0 determination - Manual Manual -
Mechanical
Secant stiffness in standard drained ref 3 3 2
triaxial test E50 25 · 10 42 · 10 kN/m
ref 3 3 2
Unloading / reloading stiffness Eur 75 · 10 126 · 10 kN/m
Cohesion c'ref 0 0 2
kN/m
Friction angle φ' 31 35 °
Dilatancy angle ψ 1 5 °
Groundwater
Classification type - Standard Standard -
Soil class - Coarse Coarse -
Use defaults - None None -
Permeability in horizontal direction kx 1.0 0.5 m/day
Interfaces
Strength determination - Rigid Manual -
Interface reduction factor Rinter 1.0 0.7 -
Initial
K0 determination - Automatic Automatic -
Pre-overburden pressure POP 0.0 0.0 -
Over-consolidation ratio OCR 1.0 1.0 -
1
In the Structures mode click the Create tunnel button in the side toolbar and click at (0
-17) in the drawing area.
The Tunnel designer window pops up displaying the General tabsheet of the Cross
section mode .
2 Select the Circular option in the Shape type drop-down menu.
3 Select the Define right half option in the Whole or half tunnel drop-down menu.
4 In the Offset to begin point group set Axis 2 to -2.5. No change is required for the
orientation axes.
A segment is automatically created. A new box is shown under the segment list where the
properties of the segment can be defined.
6 In the Segment box set Radius to 2.5 m.
Note: In the tunnel as considered here, the segments do not have a specific
meaning as the tunnel lining is homogeneous and the tunnel will be constructed at
once. In general, the meaning of segments becomes significant when:
● It is desired to excavate or construct the tunnel (lining) in different stages.
● Different tunnel segments have different lining properties.
● One would consider hinge connections in the lining (hinges can be added after
the design of the tunnel, in the general drawing area).
● The tunnel shape is composed of arcs with different radii (for example NATM
tunnels).
8 Right-click on the segment in the display area and select the menu Create > Create plate
option in the appearing menu.
9 In Tunnel Designer go to the Material property in the Selection explorer and click the plus
button to create a new material dataset. Specify the material parameters for the TBM
according to the Table 15 (p. 101):
Mechanical
Isotropic - Yes Yes Yes -
Axial 6 6 10
EA1 63 · 10 14 · 10 1 · 10 kN/m
stiffness
Bending 3 3 10 2
EI 472.5 · 10 143 · 10 1 · 10 kNm /m
stiffness
Poisson's
ν(nu) 0 0.15 0 -
ratio
Note: A tunnel lining consists of curved plates (shells). The lining properties can
be specified in the material database for plates. Similarly, a tunnel interface is
nothing more than a curved interface.
10 Right-click the segment in the display area and select the Create negative interface option
in the appearing menu.
11 Right-click the segment in the display area and select the Create line contraction option
in the appearing menu. In the polycurve properties specify a value of 0.5% for Cref. The
tunnel model is shown in Figure 5–4 (p. 103) .
Note:
● A Cref value of 0.5% corresponds to a volume loss of 0.5% of the tunnel
volume. The actual strain that is applied to the line is half the applied
contraction. Hence, the resulting liner contraction is 0.25%.
● The entered value of contraction is not always fully applied, depending on the
stiffness of the surrounding clusters and objects.
1
From the side bar, select Create line > Create plate and draw a plate from (5 3) to (15 3),
representing the building.
2 Create a material set for the building according to Table 15 (p. 101) and assign it to the
plate. Do not forget to also create the material set for the tunnel lining.
3 From the side bar, select Create line > Create embedded beam and draw two piles from
(5 3) to (5 -11) and from (15 3) to (15 -11).
Mechanical
Pile spacing Lspacing 3.0 m
Cross section type - Predefined -
Predefined cross
- Solid circular beam -
section type
Diameter - 0.25 m
Stiffness E 6 2
10 · 10 kN/m
Axial skin resistance Linear -
2
Click the Generate mesh button in the side toolbar. For the Element distribution
parameter, use the option Medium (default).
3
Click the View mesh button to view the mesh as shown in Figure 5–5 (p. 105) .
Tip:
With the Default fixities used, a plate that extends to a geometry boundary that is
fixed in at least one direction obtains fixed rotations, whereas a plate that extends to
a free boundary obtains a free rotation. To view the fixities in the Output program go
to menu bar at the top click on Geometry > Fixities.
1
Click the Add phase button to create a new phase.
2 In the Phases window rename the Phase ID as Building.
3 In the Deformation control parameters subtree select the Ignore undr. behaviour (A,B)
option. The default values of the remaining parameters are valid for this phase.
4 In the drawing area activate the plate of the building and the foundation piles.
Note:
● The contraction represents the effects of the cone shape of the TBM (cutter head
has larger diameter than the tail).
● The contraction of the tunnel lining by itself does not introduce forces in the tunnel
lining. Eventual changes in lining forces as a result of the contraction procedure are
due to stress redistributions in the surrounding soil or to changing external forces.
1
Click the Add phase button to create a new phase.
2 In the Staged construction mode deactivate the TBM (plates, negative interfaces and
contraction).
3 Multi-select the clusters inside the tunnel. In the Selection explorer activate
WaterConditions.
4 In the Condition drop-down menu select the User-defined option and set p ref to -230 kN/
2
m . The pressure distribution in the tunnel is constant.
4 Since the plates now represent the final lining of the tunnel, assign the Lining material set to
the plate elements.
5.7 Results
After the calculation, select the last calculation phase and click the View calculation results
button. The Output program is started, showing the deformed meshes at the end of the
calculation phases which is shown in Figure 5–6 (p. 108):
As a result of the second calculation phase (removing soil and water out of the tunnel) there is
some settlement of the soil surface and the tunnel lining shows some deformation. In this phase
the axial force in the lining is the maximum axial force that will be reached. The lining forces
can be viewed by double- clicking the lining and selecting force related options from the Force
-3
menu. The plots of the axial forces and bending moment are scaled by factors of 5·10 and 0.2
respectively which is shown in Figure 5–7 (p. 108).
Figure 5–7: Axial forces and Bending moments in the lining after the second phase
Figure 5–8: Effective principal stresses after the construction of the tunnel (Phase 2 TBM)
To display the tilt of the structure at the end of lining installation phase:
1. Click the Distance measurement button in the side toolbar.
2. Click the node located at the left corner of the structure (5 3).
3. Click the node located at the right corner of the structure (15 3).
The Distance measurements information window is displayed in Figure 5–9 (p. 110), where
the resulting tilt of the structure is shown.
111
28 m 8m 7m 7m 50 m
(-7 35)
Top layer 5m
(-14 30)
6m
(-22 24)
(-50 24)
Clay - Siltstone
13 m
(-50 11)
y
Clay - Limestone
11 m
x
(-50 0)
1 Start the Input program and select Start a new project from the Quick start dialog box.
2 In the Project tabsheet of the Project properties window, enter an appropriate title.
3 In the Model tabsheet make sure that Model is set to Plane strain and that Elements is set
to 15-Noded.
4 Define the limits for the soil contour as xmin = -50 m, xmax = 50 m, ymin = 0 m and ymax = 35
m.
1
Click the Create borehole button and create the first borehole at x = -22 m.
2 In the Modify soil layers window create three soil layers.
a. Layer number 1: both Top and Bottom lie in 24, which means that layer 1 has a depth
equal to zero in Borehole_1.
b. Layer number 2: lies from Top = 24 to Bottom = 11.
c. Layer number 3: lies from Top = 11 to Bottom = 0.
3 At the bottom of the Modify soil layers window click on the Boreholes button.
8 In Borehole_3:
a. Layer number 1: lies from Top = 35 to Bottom = 30, which means that layer 1 has a non-
zero thickness in of Borehole_3.
b. Layer number 2: lies from Top = 30 to Bottom = 11.
c. Layer number 3: lies from Top = 11 to Bottom = 0.
9 In all the boreholes the water level is located at y = 0 m.
10 Specify the soil layer distribution as shown in Figure 6–2 (p. 113).
Mechanical
Secant stiffness in standard drained ref 3 2
triaxial test E50 40·10 kN/m
ref 3 2
Unloading / reloading stiffness Eur 120·10 kN/m
Cohesion c'ref 10 2
kN/m
Friction angle φ' 30 °
Interfaces
Strength determination - Rigid -
Interface reduction factor Rinter 1.0 -
Clay- Clay-
Parameter Name Unit
silt stone limestone
General
Soil model - Hoek-Brown Hoek-Brown -
Type of material behaviour - Drained Drained -
Mechanical
Young's modulus Erm 6 6 2
1.0·10 2.5·10 kN/m
Poisson's ratio ν (nu) 0.25 0.25 -
Interfaces
Strength determination - Manual Rigid -
Interface reduction factor Rinter 0.5 1.0 -
1 Create soil material data sets according to Table 17 (p. 114) and assign them to the
corresponding layer Figure 6–2 (p. 113). Then assign the values for the soft rock layers as
per Table 18 (p. 114), find the analysis for various strength parameters from the emerging
window as shown in Figure 6–3 (p. 115).
2 Close the Modify soil layers window and proceed to the Structures mode to define the
structural elements.
4
Click the Add section button in the side toolbar. In the tunnel Selection Explorer.
6
Click the Add section button to add a new arc segment.
7
Click the Add section button to add a new arc segment.
8
Click the Extend to symmetry axis option to complete the right half of the tunnel.
A new arc segment is automatically added closing the half of the tunnel.
9
Click the Symmetric close button to complete the tunnel. Four new arc segment are
automatically added closing the tunnel.
10 Click on the Subsections tab.
11
Click the Add button to add a new subsection.
Note:
● The current subsection will be used to separate the top heading (upper
excavation cluster) from the invert (lower excavation cluster).
● While creating the new subsection some warnings and/or errors will be
displayed. For this tutorial, ignore them and continue with the instructions.
With the created subsection selected, in the Selection Explorer do the following:
16 Multi-select the polycurves in the display area, right click and in the appearing menu select
Create > Create Plate.
17 The various segments in the tunnel cross section can be seen in Figure 6–4 (p. 117).
18 Press Ctrl + M to open the Material sets window. Create a new material dataset for the
created plates according to Table 19 (p. 117).
Mechanical
Isotropic - True -
Bending stiffness EI 3 2
20·10 kNm /m
Poisson's ratio ν 0.15 -
19 Multi-select the created plates and in the Selection explorer, assign the material Lining to
the selected plates.
20 Create negative interfaces to the lines defining the shape of the tunnel (not the excavation
levels or subsection).
The final tunnel view in the Tunnel designer window is shown in Figure 6–5 (p. 118):
stresses. Instead Gravity loading will be used. This option is available in the General
subtree of the Phases window.
3 Water will not be considered in this example. The general phreatic level should remain at the
model base.
All the plates and interfaces around the full tunnel are active.
3 Select the lower deactivated cluster. In the Selection explorer set Deconfinement to 100 %.
4 The model for phase 4 can be seen in Figure 6–10 (p. 121).
6.8 Results
After the calculation, select the last calculation phase and click the View calculation results
button. The Output program is started, showing the deformed mesh at the end of the calculation
phases as shown in Figure 6–11 (p. 122):
Figure 6–11: The deformed mesh at the end of the final calculation phase
7.1 Introduction
This example involves the dry construction of an excavation. The excavation is supported by
concrete diaphragm walls. The walls are tied back by prestressed ground anchors.
PLAXIS 2D allows for detailed modelling of this type of problem. It is demonstrated in this
example how ground anchors are modelled and how prestressing is applied to the anchors.
Moreover, the dry excavation involves a groundwater flow calculation to generate the new water
pressure distribution. This aspect of the analysis is explained in detail.
Objectives
●
Modelling ground anchors.
●
Generating pore pressures with a groundwater flow calculation.
●
Displaying the contact stresses and resulting forces in the model.
●
Scaling the displayed results.
Geometry
The excavation is 20 m wide and 10 m deep. 16 m long concrete diaphragm walls of 0.35 m
thickness are used to retain the surrounding soil. Two rows of ground anchors are used at
each wall to support the walls. The anchors have a total length of 14.5 m and an inclination of
2
33.7°(2:3). On the left side of the excavation a surface load of 10 kN/m is taken into account.
125
The relevant part of the soil consists of three distinct layers. From the ground surface to a depth
of 3 m there is a fill of relatively loose fine sandy soil. Underneath the fill, down to a minimum
depth of 15 m, there is a more or less homogeneous layer consisting of dense well-graded sand.
This layer is particularly suitable for the installation of the ground anchors. The underlying layer
consists of loam and lies to a large depth. 15 m of this layer is considered in the model as shown
in Figure 7–1 (p. 126).
10 m 2m 20 m
10kN/m2
Silt 3m
4m
Ground anchor
Sand
3m
5m
2 In the Project tabsheet of the Project properties window, enter an appropriate title.
3 In the Model tabsheet keep the default options for Model (Plane strain), and Elements (15-
Node).
4 Set the model Contour to xmin = 0 m, xmax = 100 m, ymin = 0 m, ymax = 30 m.
5 Keep the default values for units and the constants and press OK to close the Project
properties window.
1
Click the Create borehole button and create a borehole at x = 0.
Mechanical
Secant stiffness in standard drained ref 3 3 3 2
triaxial test E50 20 · 10 30 · 10 12 · 10 kN/m
ref 3 3 3 2
Unloading / reloading stiffness Eur 60 · 10 90 · 10 36 · 10 kN/m
Groundwater
Classification type - USDA USDA USDA -
Van Van Van
SWCC fitting method - -
Genuchten Genuchten Genuchten
Soil class - Silt Sand Loam -
< 2μm - 6.0 4.0 20.0 %
2μm - 50μm - 87.0 4.0 40.0 %
50μm - 2mm - 7.0 92.0 40.0 %
From From From
Flow parameters - Use defaults - -
data set data set data set
Permeability in horizontal direction kx 0.5996 7.128 0.2497 m/day
Interfaces
Strength determination - Manual Manual Rigid -
Interface reduction factor Rinter 0.65 0.70 1.0 -
Consider gap closure - Yes yes yes
Initial
K0 determination - Automatic Automatic Automatic -
1 Define three data sets for soil and interfaces with the parameters given in Table 20 (p.
127).
2 Assign the material data sets to the corresponding soil layers (Figure 7–2 (p. 127)).
Mechanical
Isotropic - True -
Bending stiffness EI 3 2
120 · 10 kNm /m
Poisson's ratio ν (nu) 0.15 -
1 In the Structures mode, model the diaphragm walls as plates passing through (40 30) - (40
14) and (60 30) - (60 14).
2 Multi-select the plates in the model.
The view will change displaying a drop-down menu and a plus button next to it as shown in
Figure 7–3 (p. 129):
1 Define the second excavation phase by drawing a line through (40 23) and (60 23).
2 Define the third excavation phase by drawing a line through (40 20) and (60 20).
Axial stiffness EA 3 kN
500 · 10
Out-of-plane spacing Lspacing 2.5 m
Unit weight γ 0 3
kN/m
Mechanical
Pile spacing Lspacing 2.5 m
Beam type - Predefined -
Predefined beam type - Solid circular beam -
Diameter D 0.3 m
Stiffness E 6 2
7.07 · 10 kN/m
Distribution Linear -
1
Define the node-to-node anchors according to Table 22 (p. 130).
2 Create an Anchor material data set according to the parameters specified in Table 23 (p.
130).
3 Multi-select the anchors in the drawing area. Assign the material data set by selecting the
corresponding option in the Material drop-down menu in the Selection explorer.
4 Define the grout body using the Embedded beam button according to Table 24 (p.
130).
5 Create the Grout material data set according to the parameters specified in Table 25 (p.
131) and assign it to the grout body.
6 Set the Behaviour of the embedded beam to Grout body as shown in Figure 7–4 (p.
132).
Note that a group is created composed of the elements of the top ground anchors.
9 Click on Group_1 in the Model explorer and type a new name (e.g GroundAnchor_Top).
10 Follow the same steps to create a group and to rename the bottom ground anchors.
Although the precise stress state and interaction with the soil cannot be modelled with this 2D
model, it is possible in this way to estimate the stress distribution, the deformations and the
stability of the structure on a global level, assuming that the grout body does not slip relative to
the soil. With this model it is certainly not possible to evaluate the pullout force of the ground
anchor.
2
Click the Generate mesh button in the side toolbar. Use the default option for the
Element distribution parameter (Medium).
3
Click the View mesh button to view the mesh as shown in Figure 7–5 (p. 133).
2 Initially, all structural components and loads are inactive. Hence, make sure that the
plates, the node-to-node anchors, the embedded beam rows and the surface loads are
deactivated.
3 In the Phases explorer double-click the initial phase. The default parameters for the initial
phase will be used. The Phreatic option is selected as Pore pressure calculation type.
Note that when the pore pressures are generated by phreatic level, the full geometry of the
defined phreatic level is used to generate the pore pressures.
4 Click OK to close the Phases window.
The active elements in the project are indicated by a green check mark.
3 Activate the distributed load.
4 After selecting the line load assign a value of -10 to qy,start,ref in the Selection explorer
shown in Figure 7–7 (p. 134):
The model for the first excavation phase is shown in Figure 7–9 (p. 135):
4 In the Selection explorer set the Adjust prestress parameter to True and assign a pre-
stress force of 500 kN.
The model for the phase 3 in the Staged construction mode is shown in Figure 7–10 (p. 136):
The model for the phase 4 in the Staged construction mode is displayed in Figure 7–11 (p.
136):
4 In the Selection explorer set the Adjust prestress parameter to True and assign a pre-
stress force of 1000 kN.
The model for the phase 5 in the Staged construction mode is displayed in Figure 7–12 (p.
137):
7
Click the Create water level button in the side toolbar and draw a new phreatic level.
Start at (0 23) and draw the phreatic level through (40 20), (60 20) and end in (100 23).
8 In the Model explorer expand the User water levels subtree. Click on UserWaterLevel_1
and type LoweredWaterLevel to rename the water level created in the Flow conditions
mode as shown in Figure 7–13 (p. 138).
The model and the defined water levels are displayed in Figure 7–15 (p. 139):
Note: Note that for Groundwater flow (steady or transient) the intersection points of the
water level with the active model boundaries are important. The program calculates flow
boundary conditions in terms of a groundwater head corresponding to the water level.
The 'internal' part of the water level is not used and will be replaced by the phreatic
level resulting from the groundwater flow calculation. Hence, the water level tool is just a
convenient tool to create boundary conditions for a flow calculation.
7.8 Results
The deformed meshes at the end of calculation phase 2 to phase 6 are shown in Figure 7–16 (p.
139), Figure 7–17 (p. 140), Figure 7–18 (p. 140), Figure 7–19 (p. 140) and Figure 7–20 (p.
140):
Figure 7–21 (p. 141) shows the effective principal stresses in the final situation. The passive
stress state beneath the bottom of the excavation is clearly visible. It can also be seen that there
are stress concentrations around the grout anchors.
Figure 7–22 (p. 141) shows the bending moments in the diaphragm walls in the final state. The
two dips in the line of moments are caused by the anchor forces.
Figure 7–22: Bending moments in the diaphragm walls in the final stage
The anchor force can be viewed by double-clicking the anchor. When doing this for the results
of the third and the fifth calculation phase, it can be checked that the anchor force is indeed
equal to the specified pre-stress force in the calculation phase they are activated. In the
following phases this value might change due to the changes in the model.
8.1 Introduction
In this tutorial an Ultimate Limit State (ULS) calculation will be defined and performed for the
dry excavation using a tie back wall (7 Dry excavation using a tie back wall [ADV] (p. 125)).
The same geometry model will be used. The Design approaches feature is introduced in this
example. This feature allows for the use of partial factors for loads and model parameters after a
serviceability calculation has already been performed.
Objective
●
Using Design approaches
1 Open the project created in 7 Dry excavation using a tie back wall [ADV] (p. 125) and save
it under a different name.
2 Select the menu Soil > Design approaches or Structures > Design approaches.
143
The corresponding window is displayed .
3 Click the Add button.
7 Assign a value of 1.25 to Effective strength (c' and phi') as shown in Figure 8–2 (p. 145).
8 Click the Materials... button. The Material sets window pops up.
9 Open the Loam material data set. Note that the view has changed. In the current view it is
possible to assign factors to different soil parameters, as well as to see the effect of these
factors on the soil parameters.
10 Click the Mechanical tab. In the Mechanical tabsheet select the Label > Effective
strength (c' and phi') [MaterialFactorLabel_2] from the drop down list for c'ref and φ'
respectively. The new values will be updated for the strength parameters as shown in
Figure 8–3 (p. 146).
11 Repeat the step for the remaining soil data sets.
Note:
Note that a partial factor for φ' and ψ applies to the tangent of φ' and ψ respectively.
5 In the General subtree of the Phases window select the defined design approach in the
corresponding drop-down menu.
7 Select the Variable unfavourable option in the LoadFactorLabel drop-down menu of the
static component of the load.
8.4 Results
The results obtained for the design approach phases can be evaluated in Output. Figure 8–5 (p.
148) displays the ΣMstage - |u| plot for the node located at (40.0 27.0).
If the ULS calculations have successfully finished, the model complies with the corresponding
design approach. If there are doubts about this due to excessive deformations, an additional
Safety calculation may be considered using the same design approach, which should then
result in a stable ΣMsf value larger than 1.0. Note that if partial factors have been used it is not
necessary that ΣMsf also includes a safety margin. Hence, in this case ΣMsf just larger that 1.0 is
enough.
Figure 8–6 (p. 149) displays the ΣMsf - |u| plot for the Safety calculations of the Phase 6 and
the corresponding ULS phase (Phase 12). It can be concluded that the situation complies with
the design requirements.
9.1 Introduction
The construction of an embankment on soft soil with a high groundwater level leads to an
increase in pore pressure. As a result of this undrained behaviour, the effective stress remains
low and intermediate consolidation periods have to be adopted in order to construct the
embankment safely. During consolidation the excess pore pressures dissipate so that the soil
can obtain the necessary shear strength to continue the construction process.
This tutorial concerns the construction of a road embankment in which the mechanism
described above is analysed in detail. In the analysis three new calculation options are
introduced, namely a consolidation analysis, an updated mesh analysis and the calculation of a
safety factor by means of a safety analysis (strength reduction).
Objectives
●
Consolidation analysis
●
Modelling drains
●
Change of permeability during consolidation
●
Safety analysis (strength reduction)
●
Updated mesh analysis (large deformations)
Geometry
151
The embankment is 16 m wide and 4 m high. The slopes have an inclination of 1:3. The
problem is symmetric, so only one half is modelled (in this case the right half is chosen). The
embankment itself is composed of loose sandy soil. The subsoil consists of 6 m of soft soil.
The upper 3 m is peat and the lower 3 m is clay. The phreatic level is located 1 m below the
original ground surface. Under the soft soil layers there is a dense sand layer of which 4 m are
considered in the model which is shown in Figure 9–1 (p. 152).
12 m 16 m 12 m
Road embankment 4m
Peat 3m
Clay 3m
Dense sand
3 In the Project tabsheet of the Project properties window, enter an appropriate title.
4 In the Model tabsheet make sure that Model is set to Plane strain and that Elements is set
to 15-Noded.
5 Set the model Contour to xmin = 0 m, xmax = 60 m, ymin = -10 m and ymax = 4 m.
1
Click the Create borehole button and create a borehole at x = 0.
The Modify soil layers window pops up as shown in Figure 9–2 (p. 153).
3 The water level is located at y = -1 m. In the borehole column specify a value of -1 to Head.
Table 26: Material properties of the sand and clay layer and the interfaces
Embank-
Parameter Name Sand Peat Clay Unit
ment
General
Hardening Hardening
Soil model - Soft soil Soft soil -
soil soil
Undrained Undrained
Drainage type - Drained Drained -
(A) (A)
Unsaturated unit 3
γunsat 16 17 8 15 kN/m
weight
Mechanical
Modified compression index * - - 0.15 0.05 -
λ
Groundwater
Classification type - USDA USDA USDA USDA -
Van Van Van Van
SWCC fitting method - -
GenuchtenGenuchtenGenuchtenGenuchten
Loamy
Soil class - Sand Clay Clay -
sand
< 2μm - 6.0 4.0 70.0 70.0 %
2μm - 50μm - 11.0 4.0 13.0 13.0 %
50μm - 2mm - 83.0 92.0 17.0 17.0 %
From From From
Use defaults - None -
data set data set data set
Horizontal permeability kx 3.499 7.128 0.1 0.04752 m/day
Interfaces
Strength determination - Rigid Rigid Rigid Rigid -
Interface reduction factor Rinter 1 1 1 1 -
Initial
K0 determination - Automatic Automatic Automatic Automatic -
Note: The initial void ratio (einit) and the change in permeability (ck) should be defined to
enable the modelling of a change in the permeability in a consolidation analysis due to
compression of the soil. This option is recommended when using advanced models.
3 Select and right click the created polygon and assign the Embankment data set to the soil
polygon as shown in Figure 9–3 (p. 155).
Figure 9–3: Assignment of a material dataset to a soil cluster in the drawing area
4
To define the embankment construction level click the Cut polygon button in the side
toolbar and define a cutting line by clicking on (0 2) and (14 2).
Note:
The modelling of drains in a plane strain model actually involves the use of an equivalent
(lateral) permeability in the surrounding soil based on the drain pattern. The latter has
1
been omitted in this simplified example. More information can be in found in literature .
2
Click the Generate mesh button in the side toolbar. For the Element distribution
parameter, use the option Medium (default).
3
Click the View mesh button to view the mesh as shown in Figure 9–6 (p. 157).
The initial water pressures are fully hydrostatic and based on a general phreatic level located at
y = -1 m. Note that a phreatic level is automatically created at y = -1 m, according to the value
specified for Head in the borehole. In addition to the phreatic level, attention must be paid to the
boundary conditions for the consolidation analysis that will be performed during the calculation
process. Without giving any additional input, all boundaries except for the bottom boundary are
draining so that water can freely flow out of these boundaries and excess pore pressures can
dissipate. In the current situation, however, the left vertical boundary must be closed because
this is a line of symmetry, so horizontal flow should not occur. The remaining boundaries are
open because the excess pore pressures can be dissipated through these boundaries. In order
to define the appropriate consolidation boundary conditions, follow these steps:
1 Go to the Staged construction mode and in the Model explorer expand the Model
conditions subtree shown in Figure 9–8 (p. 158).
2 Expand the GroundwaterFlow subtree and set BoundaryXMin to Closed and
BoundaryYMin to Open.
Consolidate for a predefined period, including the effects of changes to the active
geometry (Staged construction).
Consolidate until all excess pore pressures in the geometry have reduced to a
predefined minimum value (Minimum excess pore pressure).
Consolidate until a specified degree of saturation is reached (Degree of
consolidation).
The first two possibilities will be used in this exercise. To define the calculation phases, follow
these steps:
1
Click the Add phase button to create a new phase and double-click.
2 In the Phases window go to the General subtree and from the Calculation type drop-down
menu select the Consolidation option .
3
Make sure that for the Loading type the Staged construction option is selected .
5 In the Staged construction mode activate the first part of the embankment. The model for
phase 1 is shown in Figure 9–9 (p. 159).
1
Click the Add phase button to create a new phase.
2 In the Phases window go to the General subtree and from the Calculation type drop-down
menu select the Consolidation option .
3
For the Loading type make sure that the Staged construction option is selected.
4 Enter a Time interval of 30 days. The default values of the remaining parameters will be
used.
5 In the Staged construction mode activate the second part of the embankment. The model
for phase 3 is shown in Figure 9–10 (p. 159).
1
Click the Add phase button to create a new phase.
2 In the Phases window go to the General subtree and from the Calculation type drop-down
menu select the Consolidation option .
3
In the Loading type drop-down menu select the Minimum excess pore pressure option
2
and accept the default value of 1 kN/m for the minimum pressure. The default values of the
remaining parameters will be used.
2
Add a new calculation phase.
3 Double-click on the new phase to open the Phases window.
4 In the Phases window the selected phase is automatically selected in the Start from phase
drop-down menu.
5
In the General subtree, select Safety as calculation type.
6
The Incremental multipliers option is already selected in the Loading input box. The first
increment of the multiplier that controls the strength reduction process, Msf, is set to 0.1.
7 In order to exclude existing deformations from the resulting failure mechanism, select the
Reset displacements to zero option in the Deformation control parameters subtree.
9.7.4 Calculate
Before starting the calculation it is suggested that you select nodes or stress points for a later
generation of load-displacement curves or stress and strain diagrams. To do this, follow the
steps given below.
1
Click the Select points for curves button in the side toolbar.
2 As the first point, select the toe of the embankment at (20 0).
3 The second point will be used to plot the development (and decay) of excess pore
pressures. To this end, a point somewhere in the middle of the soft soil layers at the left
side of the model is needed, hence underneath the middle of the embankment. Select for
instance a precalculation point at (0 -3).
4 Click the update option.
5
Click the Calculate button to calculate the project.
During a consolidation analysis the development of time can be viewed in the upper part of the
calculation info window as shown in Figure 9–12 (p. 162).
In addition to the multipliers, a parameter Pexcess,max occurs, which indicates the current
maximum excess pore pressure. This parameter is of interest in the case of a Minimum excess
pore pressure consolidation analysis, where all pore pressures are specified to reduce below a
predefined value.
9.8 Results
2
Select the menu View > Arrows option in the menu or click the corresponding button in
the toolbar to display the results arrows.
On evaluating the total displacement increments, it can be seen that a failure mechanism is
developing shown in Figure 9–14 (p. 163):
1 Press Ctrl + 7 to display the developed excess pore pressures (see Appendix C of the
for more shortcuts). They can also be displayed by selecting the menu StressesPore
pressuresPexcess.
2
Click the Center principal directions button . The principal directions of excess pressures
are displayed at the center of each soil element. The results are displayed in Figure 9–15 (p.
163).
It is clear that the highest excess pore pressure occurs under the embankment centre.
4 Click the Contour lines button in the toolbar to display the results as contours.
5 To show the labels of the contour lines on the soil profile click on the Draw scanline button
(or the corresponding option in the View menu). Then on the geometry make a line by
clicking on an initial point and dragging on the contours to be identified (Figure 9–15 (p.
163)).
By exploring the different phases, it can be seen that the settlement of the original soil
surface and the embankment increases considerably during the Phase 4. This is due to the
dissipation of the excess pore pressures (= consolidation), which causes further settlement
of the soil. Figure 9–15 (p. 163) shows the remaining excess pore pressure distribution
2
after consolidation. Check that the maximum value is below 1.0 kN/m .
2
Figure 9–16: Excess pore pressure contours after consolidation to Pexcess < 1.0 kN/m
1
In the Curves manager create a new curve by clicking the button .
2 For the x-axis, select the Project option from the drop-down menu and select Time in the
tree.
3 For the y-axis select the point in the middle of the soft soil layers (defined as second pre-
calculation point) from the drop-down menu. In the tree select Stresses > Pore pressure >
pexcess.
4 Select the Invert sign option for the y-axis.
5 Click OK.
7 In the Show box click the Phases button. By default all phases are selected to show in the
curve. For the clarity of the curve, hide the Safety phases (phases 5 - 8).
8 Click OK to close the Curve settings window.
A curve similar to the following one should appear as shown in Figure 9–17 (p. 165):
The figure clearly shows the four calculation phases. During the construction phases the
excess pore pressure increases with a small increase in time while during the consolidation
periods the excess pore pressure decreases with time. In fact, consolidation already occurs
during construction of the embankment, as this involves a small time interval. From the
curve it can be seen that more than 50 days are needed to reach full consolidation.
Save the chart before closing the Output program.
1
Select one of these phases and click the View calculation results button .
2 Select the menu Deformations > Incremental displacements > |Δu|.
3
Change the presentation from Arrows to Shadings . The resulting plots shown in Figure
9–18 (p. 166) gives a good impression of the failure mechanisms. The magnitude of the
displacement increments is not relevant.
3 In the Curve generation window, select the embankment toe (Point A) for the x-axis. Select
Deformations > Total displacements > |u|.
4 For the y-axis, select Project > Multipliers > ΣMsf. The Safety phases are considered in
the chart.
5 Right-click on the chart and select the Settings option in the appearing menu. The Settings
window pops up.
6 In the tabsheet corresponding to the curve click the Phases button.
7 In the Select phases window select Phase 5 shown in Figure 9–19 (p. 167):
9 In the Settings window change the titles of the curve in the corresponding tabsheet.
10 Click the Add curve button and select the From current project... option in the appearing
menu. Define curves for phases 6, 7 and 8 by following the described steps.
11 In the Settings window click the Chart tab to open the corresponding tabsheet.
13 Set the scaling of the x-axis to Manual and set the value of Maximum to 1 as shown in
Figure 9–20 (p. 168):
17 The legend can be relocated in the chart by dragging it. The plot is shown in Figure 9–21
(p. 169):
1 After the calculation is finished, save the project, then select the last phase and click the
View calculation results button . The Output window now shows the deformed mesh
after the drained construction of the final part of the embankment. In order to compare the
effect of the drains, the excess pore pressure dissipation in the second point can be used.
2
Click the Curves manager button to open the Curves manager.
3 In the Chart tabsheet double-click Chart 1 (pexcess of the second point at (0 -3) versus
time). The chart is displayed. Close the Curves manager.
4 Double-click the curve in the legend at the right of the chart. The Settings window pops
up.
7 In the chart a new curve is added and a new tabsheet corresponding to it is opened in the
Settings window. Click the Phases button. From the displayed window select the Initial
phase and the last four phases (drains) and click OK.
8 In the Settings window change the titles of the curves in the corresponding tabsheets.
10 Click Apply to preview the generated curve and click OK to close the Settings window.
The chart gives a clear view of the effect of drains in the time required for the excess pore
pressures to dissipate as shown in Figure 9–22 (p. 170):
Tip:
Instead of adding a new curve, the existing curve can be regenerated using the
corresponding button in the Curves settings window.
3 Define the new phase in the same way as Phase 1. In the Deformation control parameters
subtree check the Updated mesh and Updated water pressures options.
4 Define the other 3 phases in the same way.
1. When the calculation has finished, compare the settlements for the two different calculation
methods.
5 In the Curve generation window select time for the x-axis and select the vertical
displacement (uy) of the point in the middle of the soft soil layers at (0 -3) for the y-axis.
6 In this curve the results for Initial phase and phases from 1 to 4 will be considered.
8 In this curve the results for Initial phase and phases from 13 to 16 will be considered. The
resulting chart is shown in Figure 9–23 (p. 171).
1 Open the project defined in the tutorial 7 Dry excavation using a tie back wall [ADV] (p. 125).
2 Save the project under a different name (e.g. 'Flow around a sheet pile wall').
173
1
In the Structures mode click the Create hydraulic conditions button in the side toolbar.
2
Select the Create well option in the appearing menu.
3 Draw the first well by clicking on (42 20) and (42 17).
4 Draw the second well by clicking on (58 20) and (58 17).
2 Select the cluster and two wells as shown in the Figure 10–1 (p. 174) . In Selection
Explorer specify a Coarseness factor of 0.25.
Figure 10–1: Indication of the local refinement of the mesh in the model
3
Click the Generate mesh button to generate the mesh. Use the default option for the
Element distribution parameter (Medium).
4
Click the View mesh button to view the mesh as shown in Figure 10–2 (p. 174).
2 In the Selection explorer the behaviour of the wells is by default set to Extraction.
3 3
Set the discharge value to 1.5m /day/m.
4 Set the hmin value to 17m. This means that water will be extracted as long as the
groundwater head at the wall location is at least 17m.
Figure 10–3 (p. 175) shows the parameters assigned to the wells in the Selection explorer.
1
Click the Calculate button to calculate the project.
2
Save the project after the calculation has finished.
10.6 Results
To display the flow field:
1. Select the Phase 6 in the drop down menu.
2. Click the menu Stresses > Groundwater flow > |q|.
A scaled representation of the results (scale factor = 5.0 ) is shown in Figure 10–4 (p. 176):
11.1 Introduction
This tutorial illustrates how to calculate the vertical bearing capacity and vertical stiffness of a
circular stiff underwater footing (e.g. one of the footings of a jacket structure) exposed to cyclic
loading during a storm. The storm is idealised by a distribution of load parcels with different
magnitude. The cyclic accumulation tool is used to obtain soil parameters for the UDCAM-S
model . The example considers a circular concrete footing with a radius of 11 m, placed on an
over-consolidated clay layer.
The procedure for establishing non-linear stress-strain relationships and calculating load-
displacement curves of a foundation under a cyclic vertical load component is presented. The
analysis of the circular footing is performed with a 2D axisymmetric model. The soil profile
consists of clay with an overconsolidation ratio, OCR, of 4, submerged unit weight of 10 kN/
3
m and an earth pressure coefficient, K0 of 1. The (static) undrained shear strength from
C
anisotropically consolidated triaxial compression tests has a constant value with a depth of su
= 130 kPa. The maximum shear modulus, Gmax, of the clay is 67275 kPa. The cyclic behaviour
177
2
of the soil is based on contour diagrams for Drammen clay (Andersen, Kleven & Heien, 1988 )
assuming that the behaviour is representative of the actual clay.
Objectives
●
Obtain the UDCAM-S model input parameters by running the cyclic accumulation procedure,
determining the stress-strain curves and optimising the material model parameters.
●
Calculate the total cyclic vertical bearing capacity.
●
Calculate the vertical stiffness accounting for cyclic loading for both the total and the cyclic
component.
Geometry
The soil properties and footing geometry are shown in Figure 11–1 (p. 178) .
1m
D = 22 m
1 Start the Input program and select Start a new project from the Quick select dialog box.
2 In the Project tabsheet of the Project properties window, enter an appropriate title.
2 Andersen, K.H., Kleven, A., Heien, .D. (1988). Cyclic soil data for design of gravity structures.
Journal of Geotechnical Engineering, 517–539.
1
Click the Create borehole button and create a borehole at x = 0.
3 For simplicity, water is not taken into account in this example. The groundwater table is
therefore set below the bottom of the model, and the soil weight is based on the effective
(underwater) weight.
4 In the borehole column specify a value of -50.00 for Head.
1 Choose Soil and interfaces as the Set type and click the New button.
2 On the General tab enter the values according to Table 27 (p. 180).
Instead of entering the model parameters in this tab sheet, we will run the cyclic accumulation
and optimisation tool. This procedure consists of three steps.
Click the Mechanical tab and click the Cyclic accumulation and optimisation tool option in the
side window as shown in Figure 11–3 (p. 180).
The three steps of the cyclic accumulation and optimisation procedure are represented by the
three modes (Cyclic accumulation, Stress-strain curves and Parameter optimisation) in the
window.
Table 28: Composition of cyclic vertical load for a 6-hour design storm
11 Cyclic vertical capacity and stiffness of circular underwater footing [ADV] | 181
# Load ratio N cycles
7 0.75 10
8 0.89 3
9 1.0 1
1 Select an appropriate contour diagram from Select contour diagram data in the Cyclic
accumulation tab. In this case, select Drammen clay, OCR = 4.
3
Note: For more information about contour diagrams, see Andersen (2015) and
Reference Manual, Cyclic accumulation and optimisation tool.
2 The load ratios and number of cycles from the storm composition can be entered in the
empty table. The storm composition is given in Table 28 (p. 181) (Jostad, Torgersrud,
4
Engin & Hofstede, 2015) as the cyclic vertical load normalized with respect to the maximum
cyclic vertical load (Load ratio) and the number of cycles (N cycles). It is here assumed that
the cyclic shear stress history in the soil is proportional to the maximum cyclic vertical load
of the footing. The table should be entered such that the smallest load ratio is at the top and
the highest load ratio is at the bottom.
Note: The design storm is a load history that is transformed into parcels of constant
cyclic load. Each parcel corresponds to a number of cycles at a constant amplitude
determined from the time record of the load component. See Reference Manual,
Cyclic accumulation and optimisation tool, for more information.
When you've entered the load parcels in the table, the Load ratio vs N cycles graph will
show a graphic representation of the data. For the data given here and the logarithmic scale
turned on, the resulting graph is shown in Figure 11–5 (p. 183).
3 Andersen, K.H. (2015). Cyclic soil parameters for offshore foundation design, volume The
3rd ISSMGE McClelland Lecture of Frontiers in Offshore Geotechnics III. Meyer (Ed). Taylor &
Francis Group, London, ISFOG 2015. ISBN 978-1-138-02848-7.
4 Jostad, H.P., Torgersrud, Ø., Engin, H.K., Hofstede, H. (2015). A fe procedure for calculation
of fixity of jack-up foundations with skirts using cyclic strain contour diagrams. City University
London, UK.
The selected contour diagram is plotted together with the shear stress history for a scaling
factor where the soil fails (here defined at 15% shear strain) at the last cycle (Figure 11–6
(p. 183)) and the loci of end-points of the stress history for different scaling factors. The
calculated equivalent number of cycles corresponds to the value on the x-axis at the last
point of the locus of end-points and is equal to 6.001.
2 For the Neq determination, keep the default option From cyclic accumulation. The calculated
equivalent number of cycles is adopted from the previous tab.
3 Keep the Soil behaviour as Anisotropic, and the Scaling factor, DSS and Scaling factor, TX
as 1.
11 Cyclic vertical capacity and stiffness of circular underwater footing [ADV] | 183
Note:
● Cyclic strength can be scaled based on available soil specific cyclic strength.
● If the plasticity index and/or water content of the soil is different from Drammen
clay, the cyclic strength can be scaled by applying a scaling factor different from
5
1 (see Andersen, 2015 for details).
4 Set the cyclic to average shear stress ratio for DSS, triaxial compression and triaxial
extension, describing the inclination of the stress path, to appropriate values. In this
example, the following input values are selected to obtain strain compatibility at failure, i.e.
the same cyclic and average shear strain for the different stress paths at failure.
5 Select the load type as, Total load for this first material.
DSS and triaxial contour diagrams are plotted together with stress paths described by
the cyclic to average ratios (Figure 11–7 (p. 185)). Notice that the shear stresses are
normalised with respect to the static undrained shear strength in compression. The
extracted stress-strain curves are plotted below the contour diagrams.
6 Click Calculate to produce the corresponding normalised stress-strain curves below the
contour diagrams. See Figure 11–7 (p. 185) for the outcome.
5 Andersen, K.H. (2015). Cyclic soil parameters for offshore foundation design, volume The
3rd ISSMGE McClelland Lecture of Frontiers in Offshore GeotechnicsIII. Meyer (Ed). Taylor &
Francis Group, London, ISFOG 2015. ISBN978-1-138-02848-7.
11 Cyclic vertical capacity and stiffness of circular underwater footing [ADV] | 185
Min Max Optimised
Parameter Name Unit
value value value
Ratio of the cyclic compression
C C
shear strength over the undrained τ / Su 1.14 1.16 1.152 -
static compression shear strength
Ratio of the cyclic DSS shear
DSS C
strength over the undrained static τ / Su 0.89 0.91 0.9051 -
compression shear strength
Ratio of the cyclic extension shear
E C
strength over the undrained static τ / Su 0.62 0.64 0.6208 -
compression shear strength
Reference degraded shear strength
C
at failure in the triaxial compression τ ref - - 149.7 -
test
Reference depth yref - - 0.000 m
Increase of degraded shear strength kN/
C
at failure in the triaxial compression τ inc - - 0.000 2
test with depth m /m
2 C
Enter the parameters of the clay in the Static properties. Set su ref to 130.0 and K0
determination to Manual and set K0 to 1.0.
3 Propose minimum and maximum values for the parameters listed in Table 29 (p. 185).
4 Click Calculate to obtain optimised parameters (Figure 11–8 (p. 187) and column
Optimised value of Table 29 (p. 185)).
After a few seconds, the optimal values are shown in the corresponding column in the
Parameter ranges table. Based on these values, the optimised parameters are calculated
and listed in the right-hand side of the table as shown in Figure 11–8 (p. 187)
11 Cyclic vertical capacity and stiffness of circular underwater footing [ADV] | 187
The resulting stress-strain curves from test simulations with the UDCAM-S model using
the optimised parameters are shown together with the target points from the contour
diagrams.
5 When the calculation has finished, save the application state of the Cyclic accumulation
and optimisation tool. The saved data will be used when creating another material. To save
the application state, press the Save button at the top of the window. Save the state
under the file name optimised_total.json.
6 Copy the optimised material parameters: Press the Copy parameters button and go back
to the Soil-UDCAM-S window describing the material.
7
Click the Paste material button .
The values in the Mechanical tab are replaced with the new values as shown in Figure 11–9
(p. 188) .
10 Assign the Clay - total load material set to the soil layer in the borehole.
11 Cyclic vertical capacity and stiffness of circular underwater footing [ADV] | 189
Min Max Optimised
Parameter Name Unit
value value value
Ratio of the degraded shear strength
at failure in the direct simple shear DSS C
τ /τ - - 0.7181 -
test to the degraded shear strength
in the triaxial compression test
Like for the first material, also here the parameters will be determined using the Cyclic
accumulation and optimisation tool.
4 Click the Cyclic accumulation and optimisation tool button on the Mechanical tab to open
the tool.
5
Click the Open file button and choose the application state optimised_total.json
that was saved after optimisation of the first material.
The optimised parameters are shown in the Figure 11–11 (p. 192) and are also listed in the
column 'Optimised value' in Table 30 (p. 189).
11 Cyclic vertical capacity and stiffness of circular underwater footing [ADV] | 191
Figure 11–11: Optimised parameters for cyclic load
13 Save the application state under the file name optimised_cyclic.json.
14 Copy the optimised material parameters: Click the Copy parameters button and go back to
the Soil-UDCAM-S window.
15
Click the Paste material button .
The values in the Mechanical tab are replaced with the new values.
16 Click OK to close the created material.
1 Choose Soil and interfaces as the Set type and click the New button.
2 Enter Concrete footing for the Identification and select Linear elastic as the Soil model.
Note: Do not yet assign the Concrete footing material to the polygon.
1 Click Create interface to create the upper part from (11.0, -1.0) to (11.0, 0.0), Figure 11–13 (p.
194).
2 Click Create interface to create the lower part (between foundation and soil) from (11.0, -1.5)
to (11.0, -1.0), Figure 11–13 (p. 194).
3 The upper part interface (between the foundation and the soil) is modeled with a reduced
strength of 30%.
a. Make a copy of the Clay - total load material and name it Clay - total load -
interface .
b. Reduce the interface strength by setting Rinter to 0.3 as shown in Figure 11–12 (p. 194)
and
1 Define a distributed load by selecting Create line load and click (0.0, 0.0) and (11.0, 0.0).
2
Click the Generate mesh button in the side toolbar. For the Element distribution
parameter, use the option Medium (default).
3
Click the View mesh button to view the mesh as shown in Figure 11–14 (p. 195).
3 Activate the footing by assigning the Concrete footing material to the corresponding
polygon.
4 Activate the interfaces as well.
1
Click the Add phase button to create a new phase.
2 Phase 2 starts from Phase 1.
3 In the Phases window go to the Deformation control parameters subtree and select the
Reset displacements to zero option and Reset small strain.
4 In the Phases window go to the Numerical control parameters and in Max number of steps
stored set 500 steps.
5 Activate the line load.
1
Click the Add phase button to create a new phase.
3 Go to the Deformation control parameters subtree and select the Reset displacements to
zero option and Reset small strain.
4 In the Phases window goto the Numerical control parameters and in Max number of steps
stored set 500 steps and close the Phases window.
5 Replace the soil material with the Clay - cyclic load.
6 Assign the material Clay - cyclic load - interface material to the upper part of the interface.
The material mode of the lower part of the interface remains From adjacent soil.
7 Make sure the line is activated.
1
Click the Select points for curves button in the side toolbar.
The connectivity plot is displayed in the Output program and the Select points window is
activated.
2 Select a pre-calc node on the footing (0.0, 0.0). Close the Select points window.
3 Click on the Update tab to close the Output program and go back to the Input program.
4
Click the Calculate button to calculate the project.
5 Once the calculation is finished, go to the Output program and click on the Select points for
curves button and chose a post-calc node on the footing (0.0, 0.0).
11.8 Results
Total load cyclic vertical bearing capacity
2
Applied vertical stress (load): qy = -1000kN/m
2
Failure at: qy = 720kN/m (Figure 11–15 (p. 198))
2 2
Total vertical bearing capacity: Vcap = qy · Area = 720 kN/m · π · (11m) = 273.7MN
where:
● qphase.start is the load value at the start of the phase (or actually the load value at the
end of the previous phase).
● qphase.end is the desired load value at the end of the current phase, i.e. the defined
value in the Staged Construction settings.
Since for this tutorial qphase.start =0 then qactive=ΣMstage x qphase.end
Procedure:
1. From the Output program go to Curves manager and obtain the ΣMstage-
displacement curve.
2. Click on the icon. Copy the |u| vs ΣMstage values for all steps and paste them
on the spreadsheet. Ensure that the values and their units pasted are consistent with
PLAXIS output.
3. Multiply each value of the ΣMstage column with the value of qphase.end. For this
example, qphase.end is equal to the defined vertical load of 1000KN.
4. Graph |u| vs qy.
For comparison, the static vertical bearing capacity (using the static undrained shear strength)
is found to be 228.1MN. The reason for the larger vertical bearing capacity is that the shear
Figure 11–16: Total displacement vs vertical bearing capacity curve for cyclic load
Vertical stiffness
The vertical stiffness (accounting for cyclic loading) is calculated as ky = Fy / uy for both the
total and the cyclic component. The total vertical displacement includes accumulated vertical
11 Cyclic vertical capacity and stiffness of circular underwater footing [ADV] | 199
displacements during the storm. Load versus stiffness is shown in the following Figure 11–17 (p.
200):
Tip: To construct the vertical load vs vertical stiffness graph, use the values of the load
displacement curve (|u| vs qy) and operate Fy for each step, take into account:
● Fy = qy x Areafooting.
● For this example, uy is equal to |u|.
Figure 11–17: Vertical load versus stiffness for total and cyclic load components
201
2m 6m 2m 10 m 3m
3m
5m
3m y
1m
x
1 Start the Input program and select Start a new project from the Quick select dialog box.
2 In the Project tabsheet of the Project properties window, enter an appropriate title.
3 In the Model tabsheet keep the default options for Model (Plane strain), and Elements (15-
Node).
4 Set the model dimensions to: xmin = 0 m, xmax = 23 m, ymin = 0 m and ymax = 6 m
5 Keep the default values for units, constants and the general parameters and click OK.
1
Click the Create borehole button and create a borehole at x = 2.
Mechanical
Young's modulus E'ref 3 2
10·10 kN/m
Poisson's ratio ν 0.3 -
Groundwater
Classification type - Standard -
Soil class - Medium fine -
Flow parameters - Use defaults - From data set -
Horizontal permeability kx 0.02272 m/day
1
Define the soil material according to the table above and assign the material dataset to
the cluster. Skip the Interfaces and Initial tabsheets as these parameters are not relevant.
2 After assigning the material to the soil cluster close the Modify soil layers window.
5
Click the View mesh button to view the mesh as shown in Figure 12–3 (p. 204).
Note: Note that the 'internal' part of the global water level will be replaced by the result
of the groundwater flow calculation.
2 In the General subtree select the Flow only option as the Calculation type.
3 The default values of the remaining parameters are valid for this phase. Click OK to close
the Phases window.
4 In the Model explorer expand the Model conditions subtree.
5 In the Model conditions expand the GroundwaterFlow subtree. The default boundary
conditions are relevant for the initial phase. Confirm that only the bottom boundary is closed.
The expanded groundwater flow boundary conditions is shown in Figure 12–5 (p. 205).
Figure 12–5: The groundwater flow boundary conditions for the initial phase
6 In the Model explorer expand the Groundwater flow BCs subtree. The boundary conditions
at the extremities of the model are automatically created by the program and listed under the
GWFlowBaseBC.
3 In the General subtree select the Transient groundwater flow option as pore pressure
calculation type.
4 Set the Time interval to 1 day.
5 In the Numerical control parameters subtree set the Max number of steps stored
parameter to 50. The default values of the remaining parameters will be used.
6 Click OK to close the Phases window.
7
Click the Select multiple objects button in the side toolbar.
8
Click Select lines > Select water boundaries.
13 Select the Time dependent option in the Time dependency drop-down menu.
15
Click the Add button to add a new head function.
16 In the Flow functions window select the Harmonic option in the Signal drop-down menu.
Set the amplitude to 1 m, the phase angle to 0° and the period to 1 day.
3 In the General subtree select the Initial phase in the Start from phase drop-down menu.
4 Select the Transient groundwater flow option as Pore pressure calculation type.
6 In the Numerical control parameters subtree set the Max number of steps stored
parameter to 50. The default values of the remaining parameters will be used.
7 Click OK to close the Phases window.
10
Click the Add button to add a new head function.
11 In the Flow functions window select the Harmonic option in the Signal drop-down menu.
Set the amplitude to 1 m, the phase angle to 0° and the period to 10 day as shown in Figure
12–8 (p. 208).
1
In the Staged construction mode click the Select point for curves button in the side
toolbar.
4
Click the Calculate button to calculate the project.
5
Save the project after the calculation has finished.
12.7 Results
In the Output program the Create animation tool can be used to animate the results displayed in
the Output program. To create the animation follow these steps:
1. Click the menu Stresses > Pore pressures > Groundwater head.
2. Select the menu File > Create animation. The corresponding window pops up.
3. Define the name of the animation file and the location where it will be stored. By default the
program names it according to the project and stores it in the project folder. In the same way
animations can be created to compare the development of pore pressures or flow field.
Figure 12–11: Active pore pressure variation in the cross section in Phase 2
211
0.75m 1.25m 15m 15m
Precipitation Precipitation
0.75m
0.50m
Loam
0.75m
Sand
1 Start the Input program and select Start a new project from the Quick select dialog box.
2 In the Project tabsheet of the Project properties window, enter an appropriate title.
3 In the Model tabsheet keep the default options for Model (Plane strain), and Elements (15-
Node).
4 Set the model dimensions to: xmin = 0 m, xmax = 15 m, ymin = 0 m and ymax = 5 m.
5 Keep the default values for units, constants and the general parameters and press OK.
1
Click the Snapping options button in the bottom toolbar and snapping window appears
as shown in Figure 13–2 (p. 213).
6 In the first borehole set Top = 3.75 and Bottom = 3 for the uppermost soil layer. Set Bottom
= 0 for the lowest soil layer.
7 In the second borehole set Top = 5 and Bottom = 3 for the uppermost soil layer. Set Bottom
= 0 for the lowest soil layer.
8 For both boreholes the Head is located at y = 4.25.
Figure 13–3 (p. 213) shows the soil stratigraphy defined in the Modify soil layers window.
Mechanical
Stiffness E' ref 3 3 2
1·10 10·10 kN/m
Poisson's ratio ν 0.3 0.3 -
Groundwater
Classification type Type Staring Staring -
Van Van
SWCC fitting method - -
Genuchten Genuchten
Subsoil/Topsoil - Topsoil Subsoil -
Clayey Loamy
Soil class - -
loam (B9) sand (O2)
Flow parameters - Use defaults - From data set From data set -
Permeability in horizontal direction kx 0.01538 0.1270 m/day
1
Create the material data sets according to Table 33 (p. 214).
2 Assign the material data set to the corresponding clusters in the model.
2 Multi-select the line segments composing the upper boundary of the model as shown in
Figure 13–4 (p. 215).
4
Click the Generate mesh button to generate the mesh. Use the default option for the
Element distribution parameter (Medium).
5
Click the View mesh button to view the mesh which is shown in Figure 13–5 (p. 215).
8 Expand the Water subtree. The borehole water level is assigned to GlobalWaterLevel.
Tip: Note that the conditions explicitly assigned to groundwater flow boundaries
are taken into account. In this tutorial the specified Head will be considered for
the bottom boundary of the model, NOT the Closed condition specified in the
GroundwaterFlow subtree under the Model conditions.
ID Time [days] 3
Δ Discharge [m /day/m]
1 0 0
2 1 0.01
3 2 0.03
4 3 0
5 4 -0.02
6 5 0
7 6 0.01
8 7 0.01
9 8 0
1
Click the Add phase button to create a new phase.
2 In General subtree of the Phases window select the Transient groundwater flow as Pore
pressure calculation type.
3 Set the Time interval to 15 days.
4 In the Numerical control parameters subtree set the Max number of steps stored to 250.
The default values of the remaining parameters will be used.
5 Click OK to close the Phases window.
6 To define the precipitation data a discharge function should be defined. In the Model
explorer expand the Attributes library subtree.
7 Right-click on Flow functions and select the Edit option in the appearing menu. The Flow
functions window pops up.
8 In the Discharge functions tabsheet add a new function.
9 Specify a name for the function and select the Table option in the Signal drop-down menu.
10 Click the Add row button to introduce a new row in the table. Complete the data using the
values given in Table 34 (p. 216).
Figure 13–7 (p. 218) shows the defined function for precipitation.
12 In the Model explorer under Model conditions expand the Precipitation subtree and
activate it. The default values for discharge (q) and condition parameters (ψmin = -1.0 m
and ψmax = 0.1m) are valid.
13 For the precipitation select the Time dependent option in the corresponding drop-down
menu and assign the defined function.
14 In the Model explorer set DischargeFunction_1 under Discharge function as shown in
Figure 13–8 (p. 219).
13.7 Results
The calculation was focused on the time-dependent saturation of the potato field.
To view the results:
The Legend settings window pops up. Define the settings as shown in Figure 13–9 (p.
220).
3
Figure 13–10 (p. 220) shows the spatial distribution of the saturation for the last time step.
4 Create an animation of the transient phase for a better visualisation of the results.
5 It is also interesting to create a vertical cross section at x = 4 m and draw cross section
curves for pore pressure and saturation.
14.1 Introduction
This example concerns the stability of a reservoir dam under conditions of drawdown. Fast
reduction of the reservoir level may lead to instability of the dam due to high pore water
pressures that remain inside the dam. To analyse such a situation using the finite element
method, a fully coupled flow-deformation analysis is required. Time-dependent pore pressure
is coupled with deformations development and used in a stability analysis. This example
demonstrates how coupled analysis and stability analysis can interactively be performed in
PLAXIS 2D.
Objectives
●
Defining time-dependent hydraulic conditions (Flow functions).
●
Defining transient flow conditions using water levels.
Geometry
The dam to be considered is 30m high and the width is 172.5m at the base and 5m at the top.
The dam consists of a clay core with a well graded fill at both sides. The normal water level
behind the dam is 25m high. A situation is considered where the water level drops 20m. The
normal phreatic level at the right hand side of the dam is 10m below ground surface. The
geometry of the dam is shown in Figure 14–1 (p. 222).
221
50 m 77.5 m 5m 90 m 37.5 m
25 m
Core
30 m
y
Fill Fill
5m
x
Subsoil 30 m
120 m 20 m 120 m
1 Start the Input program and select Start a new project from the Quick start dialog box.
2 In the Project tabsheet of the Project properties window, enter an appropriate title.
3 Keep the default units and constants and set the model Contour to xmin = -130 m, xmax = 130
m, ymin = -30 m and ymax = 30 m.
1
Click the Create borehole button and create a borehole at x = 0.
Mechanical
Young's modulus E' ref 3 3 3 2
1.5·10 20·10 50·10 kN/m
Poisson's ratio ν 0.35 0.33 0.3 -
Cohesion c'ref - 5 1 2
kN/m
kN/
Young's modulus increment E'inc 300 - - 2
m /m
Groundwater
Classification type - Hypres Hypres Hypres -
Van Van Van
SWCC fitting method - -
Genuchten Genuchten Genuchten
Subsoil /Topsoil - Subsoil Subsoil Subsoil -
Soil class(standard) - Very fine Coarse Coarse -
Flow parameters - Use defaults None None None -
1
Open the Material sets window.
2 Create data sets under the Soil and interfaces set type according to the information given in
Table 35 (p. 222). Note that the Thermal, Interfaces and Initial tabsheets are not relevant
(no thermal properties, no interfaces or K0 procedure are used).
3 Assign the Subsoil material dataset to the soil layer in the borehole.
to-grid distance, select the Snapping options button below the drawing area. The Spacing
defines the distance between 2 grid points and the Intervals defines the amount of snap-to-
grid intervals between 2 grid points. In order to have a snap-to-grid distance of 0.5m we can set
either the Spacing to 0.5m and leave the Intervals to 1, or we can leave the Spacing at 1 m and
set the amount of Intervals to 2.
1
Click on the Polygon button to define a polygon through the points located at (-80 0),
(92.5 0), (2.5 30) and (-2.5 30).
2
Click again on the Polygon button , and this time select the Cut polygon button to
create the sub-clusters in the dam. Define two cutting lines from (-10 0) to (-2.5 30) and
from (10 0) to (2.5 30).
3 Assign the corresponding material datasets to the soil clusters.
2
Click the Generate mesh button in the side toolbar. For the Element distribution
parameter, use the option Fine.
3
Click the View mesh button to view the mesh which is shown in Figure 14–2 (p. 224).
5
Select the Calculation type > Gravity loading option .
6
Select the Pore pressure calculation type > Steady state groundwater flow option
7 In the Deformation control parameters subtree, uncheck the Ignore suction option.
The phases window after putting all the parameters is shown in Figure 14–3 (p. 225):
Figure 14–3: The Phases window
Note: Note that by default Undrained behaviour (A) and (B) are ignored for a
Gravity loading calculation type. The corresponding option is available in the
Deformation control parameters subtree in the Phases window
9
Define the water level corresponding to the level of water in the reservoir prior to the
drawdown. The water level consists of four points:
●
Starting at the very left side at a level of 25 m above the ground surface (-132 25);
●
Second point just inside the dam at a level of 25 m (-10 25);
●
Third point near the dam toe (93 -10);
●
Forth point just outside the right boundary at a level of 10 m below the ground surface
(132 -10).
Note: Straight lines can be defined by keeping the Shift key pressed while defining
the geometry.
Note that the global water level can also be specified in the Model Explorer by selecting
the corresponding option in the menu Model conditions > Water > GlobalWaterLevel >
UserWaterLevel_1.
11 In the Model explorer expand the Attributes library.
12 Expand the Water levels subtree. The levels created in the Flow conditions mode are
grouped under User water levels.
13 Expand the User water levels subtree.
The created water level can be seen named as UserWaterLevel_1. The location of the water
levels in Model explorer is shown in Figure 14–5 (p. 227)
Note that by default the boundary at the bottom of the model is set to Closed shown in
Figure 14–6 (p. 228). This is relevant for this example.
1
Click the Add phase button to create a new phase.
2 In the Phases explorer double-click the newly added phase.
7 In the Deformation control parameters subtree, make sure that the Reset displacements
to zero and Reset small strain options are selected.
8 Click OK to close the Phases window (see Figure 14–7 (p. 229)).
a. In the Model explorer go to the Attributes library and right-click the Flow functions
option. Select the Edit option in the appearing menu. The Flow functions window is
displayed.
b. In the Head functions tabsheet add a new function by clicking the corresponding button
. The new function is highlighted in the list and options to define the function are
displayed.
c. Specify a proper Name to the function for the rapid drawdown (e.g. Rapid).
d. From the Signal drop-down menu, select the Linear option .
e. Specify a time interval of 5 days.
f. As ΔHead assign a value of -20 m representing the amount of the head decrease.
A graph is displayed showing the defined function in Figure 14–9 (p. 231).
Figure 14–10 (p. 232) shows the selected water segment in Model explorer.
Note that the shadow under the water level segment in the upstream shoulder indicates the
variation of the water level during the phase.
2
Click the Add phase button to create a new phase.
3 In Phases explorer double-click the newly added phase. The Phases window is displayed.
4 In the General subtree specify the name of the phase (e.g. Slow drawdown). The High
reservoir phase is automatically selected for the Start from phase parameter.
7 Make sure that the Reset displacements to zero and Reset small strain options are
selected in the Deformation control parameters subtree. The Ignore suction option is
unchecked by default.
8 Click OK to close the Phases window.
9 Create a new duplicate of the high water level. The newly created water level will be used
as Global water level in the slow drawdown phase. Even though the water level in this
phase has the same geometry as the previously defined ones, the flow function for the
time dependency is different.
10 Rename the newly created water level as 'FullReservoir_Slow'.
11
Add a new flow function following the steps described for the previous phase.
a. Specify a proper name to the function for the slow drawdown (e.g. Slow).
b. From the Signal drop-down menu select the Linear option.
c. Specify a time interval of 50 days.
d. Assign a value of -20 m to ΔHead, representing the amount of the head decrease. A
graph is displayed showing the defined function.
e. Click OK to close the Flow functions window as shown in Figure 14–12 (p. 233).
Figure 14–12: The flow function for the slow drawdown case
12 In the Model Explorer > Attributes library > Water levels > User water levels right-click
on FullReservoir_Slow and select the Use as global water level option in the appearing
menu.
13 Expand the FullReservoir_Slow subtree. Select the water segment in the upstream
shoulder (left from the dam, at the reservoir side).
The segment selected in Model explorer is indicated by a red colour in the model.
14 Expand the subtree of the selected segment and for the TimeDependency parameter
select the Time dependent option.
Note that in the Model explorer under the Model conditions in the Water subtree the
GlobalWaterLevel gets assigned the new water level (FullReservoir_Slow).
2
Click the Add phase button to create a new phase.
3 In Phases explorer double-click the newly added phase.
9
Define the water level corresponding to the level of water in the reservoir after the
drawdown. The water level consists of four points:
●
Starting at the very left side at a level of 5 m above the ground the surface (-132 5);
●
Second point inside the dam at a level of 5 m (-60 5);
●
Third point at (93 -10);
●
Fourth point just outside the right boundary at a level of 10 m below the ground surface
(132 -10).
10 Rename the newly created water level as 'LowLevel_Steady'.
11 In the Model explorer > Model conditions > Water assign to the GlobalWaterLevel the
newly created water level (LowLevel_Steady).
Figure 14–13: Model for the low level case in the Flow conditions mode
All the defined water levels are shown in Figure 14–13 (p. 234).
2
Click the Add phase button to create a new phase. Proceed to the Phases window.
3
Set Calculation type to Safety .
4 In the Deformation control subtree, select Reset displacements to zero.
5 In the Deformation control parameters subtree, check the Ignore suction option for all the
safety analyses.
Note: Taking suction into account in a Safety phase gives a higher factor of safety,
hence ignoring suction in a Safety phase is more conservative. In the Safety
analysis of PLAXIS 2D, any unbalance due to changing from suction to no suction is
first solved before the factor of safety is determined. As a result, ΣMsf can decrease
in the first part of the calculation.
6 The final view of the phases explorer window is shown in Figure 14–14 (p. 235).
2
Select nodes located at the crest (-2.5 30) and at the toe of the dam (-80 0).
3
Click the Calculate button to calculate the project and ignore the warnings regarding the
influence of suction in the Safety analysis..
4
Save the project after the calculation has finished.
Figure 14–15: Pore pressure distribution, (pactive), for high reservoir level
●
The pore pressure distribution after rapid drawdown of the reservoir level is shown in Figure
14–16 (p. 236).
●
The pore pressure distribution after slow drawdown of the reservoir level is shown in Figure
14–17 (p. 236).
●
The steady-state situation with a low reservoir level is shown in Figure 14–18 (p. 237).
Note:
The phreatic level can be smoother with a high refinement of the mesh in the core.
When the change of pore pressure is taken into account in a deformation analysis, some
additional deformation of the dam will occur. These deformations and the effective stress
distribution can be viewed on the basis of the results of the first four calculation phases.
Here, attention is focused on the variation of the safety factor of the dam for the different
situations. Therefore, the development of ΣMsf is plotted for the phases 4 to 7 as a function of
the displacement of the dam crest point (-2.5 30.0), see Figure 14–19 (p. 237).
Rapid drawdown of a reservoir level can reduce the stability of a dam significantly. Fully coupled
flow-deformation and stability analysis can be performed with PLAXIS 2D to effectively analyse
such situations.
15.1 Introduction
Using PLAXIS 2D, it is possible to simulate dynamic soil-structure interaction. Here the influence
of a vibrating source on its surrounding soil is studied. Oscillations caused by the generator are
transmitted through the footing into the subsoil.
The physical damping due to the viscous effects is taken into consideration via the Rayleigh
damping. Also, due to axisymmetry 'geometric damping' can be significant in attenuating the
vibration.
The modelling of the boundaries is one of the key points. In order to avoid spurious wave
reflections at the model boundaries (which do not exist in reality), special conditions have to be
applied in order to absorb waves reaching the boundaries.
Objectives
●
Defining a Dynamic calculation
●
Defining dynamic loads
●
Defining dynamic boundary conditions (viscous)
●
Defining material damping by means of Rayleigh damping
Geometry
239
The vibrating source is a generator founded on a 0.2 m thick concrete footing of 1 m in diameter
as shown in Figure 15–1 (p. 240).
Generator
1m
Sandy clay
1 Start the Input program and select Start a new project from the Quick select dialog box.
2 In the Project tabsheet of the Project properties window, enter an appropriate title.
3 Due to the three dimensional nature of the problem, an axisymmetric model is used. In the
Model tabsheet select the Axisymmetric option for Model and keep the default option for
Elements (15-Noded).
4 Keep the default values for units and constants and set the model contour to xmin = 0 m, xmax
= 20 m, ymin = -10 m and ymax = 0 m.
Note: The model boundaries should be sufficiently far from the region of interest,
to avoid disturbances due to possible reflections. Although special measures
are adopted in order to avoid spurious reflections (viscous boundaries), there is
always a small influence and it is still a good habit to put boundaries far away. In
a dynamics analysis, model boundaries are generally taken further away than in a
static analysis.
1
Click the Create borehole button and create a borehole at x = 0.
2 Create a soil layer extending from ground surface (y = 0) to a depth of 10 m (y = -10).
3 Keep the Head in the borehole at 0 m. This means that the sub-soil is fully saturated.
Mechanical
Stiffness E' ref 3 2
50·10 kN/m
Poisson's ratio ν' 0.3 -
Initial
K0 determination - Automatic -
Note: When using Mohr-Coulomb or linear elastic models the wave velocities Vp and
Vs are calculated from the elastic parameters and the soil weight. Vp and Vscan also
be entered as input; the elastic parameters are then calculated automatically. See also
Elastic parameters and the Wave Velocity relationships in the Mechanical Tabsheet of
the Reference Manual.
Flexural rigidity EI 3 2
24·10 kNm /m
Poisson's ration ν 0 -
1
Create a plate extending from (0 0) to (0.5 0) to represent the footing.
2
Define a material data set for the footing according to the information given in Table 37
2
(p. 241). The footing is assumed to be elastic and has a weight of 5 kN/m .
3 Apply a distributed load on the footing to model the weight of the generator as well as the
vibrations that it produces. The actual value of the load will be defined later.
2
Click the Generate mesh button to generate the mesh. Use the default option for the
Element distribution parameter (Medium).
3
Click the View mesh button to view the mesh.
The resulting mesh is shown in Figure 15–3 (p. 243) . Note that the mesh is automatically
refined under the footing.
2 The initial phase has already been introduced. The default settings of the initial phase will be
used in this tutorial.
3 Activate the static component of the distributed load. In the Selection explorer set qy,start,ref
value to -8 kN/m/m. Do not activate the dynamic component of the load as shown in Figure
15–4 (p. 244).
1
Click the Add phase button to create a new phase.
2
In the General subtree in the Phases window, select the Dynamic option as calculation
type.
3 Set the Dynamic time interval parameter to 0.5 s.
4 In the Deformation control parameters subtree in the Phases window select the Reset
displacements to zero parameter. The default values of the remaining parameters will be
used for this calculation phase.
5 In the Model explorer expand the Attributes library subtree.
6 Right-click the Dynamic multipliers subtree and select the Edit option from the appearing
menu.
8
Click the Add button to introduce a multiplier for the loads.
9 Define a Harmonic signal with an Amplitude of 10, a Phase of 0° and a Frequency of 10
Hz and as shown in Figure 15–5 (p. 245):
Figure 15–6: Specification of the dynamic load component in the Selection explorer
12 Special boundary conditions have to be defined to account for the fact that in reality the
soil is a semi-infinite medium. Without these special boundary conditions the waves would
be reflected on the model boundaries, causing perturbations. To avoid these spurious
reflections, viscous boundaries are specified at Xmax and Ymin. The dynamic boundaries
can be specified in the Model explorer > Model conditions > Dynamics subtree as shown
in Figure 15–7 (p. 246).
3 In the General tabsheet Rayleigh damping parameter is displayed .Set the Input method to
SDOF Equivalent.
4 In order to introduce 5% of material damping, set the value of the ξ parameter to 5%
for both targets as ξ 1 and ξ 2 and set the frequency values to 1 and 10 for f 1 and f 2
respectively.
5 The values of α and β are automatically calculated by the program as shown in Figure 15–8
(p. 248).
7 Check whether the phases are properly defined (according to the information given before)
and start the calculation.
15.8 Results
The Curve generator feature is particularly useful for dynamics analysis. You can easily display
the actual loading versus time (input) and also displacements, velocities and accelerations of the
pre-selected points versus time. The evolution of the defined multipliers with time can be plotted
by assigning Dynamic time to the x-axis and uy to the y-axis.
Figure 15–9 (p. 249) shows the response of the pre-selected points at the surface of the
structure. It can be seen that even with no damping, the waves are dissipated which can be
attributed to the geometric damping.
It can be seen that the vibration is totally seized when some time is elapsed after the removal of
the force (at t = 0.5 s). Also, the displacement amplitudes are lower. Compare the curves without
and with damping.
Figure 15–11: Acceleration (|a|) in the soil at the end of phase 2 (with damping)
16.1 Introduction
Pile driving is a dynamic process that causes vibrations in the surrounding soil. Moreover,
excess pore pressures are generated due to the quick stress increase around the pile.
In this example focus is put on the irreversible deformations below the pile. In order to simulate
this process most realistically, the behaviour of the sand layer is modelled by means of the
Hardening Soil model with small-strain stiffness.
Geometry
This example involves driving a concrete pile through an 11 m thick clay layer into a sand layer.
The pile has a diameter of 0.4 m which is displayed in Figure 16–1 (p. 252).
251
Clay Pile Ø 0.4 m 11 m
Sand 7m
1 Start the Input program and select Start a new project from the Quick start dialog box.
2 In the Project tabsheet of the Project properties window, enter an appropriate title.
3 In the Model tabsheet select the Axisymmetry option for Model and keep the default option
for Elements (15-Noded).
4 Keep the default values for units and constants and set the model Contour to xmin = 0 m,
xmax = 30 m, ymin = 0 m and ymax = 18 m.
1
Click the Create borehole button and create a borehole at x = 0.
2 Create two soil layers extending from y = 18 to y = 7 and from y = 7 to y = 0.
Table 38: Material properties of the clay layer and the pile
Mechanical
Young's modulus (constant) E'ref 3 6 2
5.0·10 30·10 kN/m
Poisson's ratio ν 0.3 0.1 -
Cohesion c'ref - - - 2
kN/m
Interface
Strength determination Type Manual Rigid -
Interface reduction factor Rinter 0.5 1.0 -
Initial
K0 determination - Automatic Automatic -
Mechanical
Secant stiffness in standard drained ref 3 2
triaxial test E50 50·10 kN/m
ref 3 2
Unloading / reloading stiffness Eur 150·10 kN/m
Cohesion c'ref 0 2
kN/m
Friction angle φ' 31 °
Dilatancy angle ψ 0 °
Interface
Strength determination - Rigid -
Initial
K0 determination - Automatic -
Create the material data sets according to Table 38 (p. 253) and Table 39 (p. 253)
Pile
Interface
Clay
(0.2, 7.0)
(0.0, 7.0)
Extended interface
Sand
(0.2, 6.6)
1 Click the Structures tab to proceed with the input of structural elements in the Structures
mode .
2 Select the Create line feature in the side toolbar and draw a line from (0.2 6.6) to (0.2 18).
3
Assign a negative interface to the line to model the interaction of the pile with the
surrounding soil.
The pile is made of concrete, which is modelled by means of the linear elastic model
considering non-porous behaviour. In the beginning, the pile is not present, so initially the
clay properties are present in the area the represents the pile.
1
Define a distributed load by clicking on Create load > Create line load from the tool bar
and then on (0 18.0) and (0.2 18.0).
2 The load components will be defined in the Selection explorer. Note that the static
component of the load will not be used in this project. The program will neglect the static
components of the load if it (static load) is not activated.
3 Expand the Dynamic load subtree and specify a unit load in the gravity direction.
4
Click the Multiplier_y drop down menu and click on the appearing plus button .
The Multipliers window pops up and a new load multiplier is automatically added.
Tip:
Note that dynamic multipliers can be defined by right-clicking the Dynamic
multipliers subtree under Attributes library in the Model explorer.
Note that dynamic multipliers are attributes and as such it is possible to define them
in all the program's modes.
2
Click the Generate mesh button to generate the mesh. Use the default option for the
Element distribution parameter (Medium).
3
Click the View mesh button to view the mesh shown in Figure 16–5 (p. 257).
The resulting mesh is shown. Note that the mesh is automatically refined under the footing.
4 In the Staged construction mode assign the pile properties to the pile cluster.
5 Activate the interface in the Clay layer only. The model for the Phase 1 in the Staged
construction mode is displayed in Figure 16–6 (p. 258).
5 In the Staged construction mode activate the dynamic component of the distributed load.
The activated dynamic component of the load in Selection explorer is shown in Figure 16–7
(p. 259) .
The result of this phase is half a harmonic cycle of the external load. At the end of this phase,
the load is back to zero.
When looking at the output of the second calculation phase (t = 0.01 s, i.e. just after the stroke),
it can be seen that large excess pore pressures occur very locally around the pile tip. This
reduces the shear strength of the soil and contributes to the penetration of the pile into the
sand layer. The excess pore pressures remain also in the third phase since consolidation is not
considered.
Figure 16–10 (p. 262) shows the shear stresses in the interface elements at t = 0.01 s. The plot
shows that the maximum shear stress is reached all along the pile, which indicates that the soil
is sliding along the pile.
When looking at the deformed mesh of the last calculation phase (t = 0.2 s), it can also be seen
that the final settlement of the pile is about 9.5 mm. In order to see the whole dynamic process
it is suggested to use the option Create Animation to view a 'movie' of the deformed mesh in
time. You may notice that the first part of the animation is slower than the second part.
17.1 Introduction
This example demonstrates the natural frequency of a five-storey building when subjected to
free vibration and earthquake loading. The two calculations employ different dynamic boundary
conditions:
●
In the free vibration, the Viscous boundary conditions are considered. This option is suitable
for problems where the dynamic source is inside the mesh.
●
For the earthquake loading, the Free-field and Compliant base boundary conditions are
considered. This option is preferred for earthquake analysis, where the dynamic input is
applied at the bottom of the model.
Objectives
●
Performing a Dynamic calculation
●
Defining dynamic boundary conditions (free-field, compliant base and viscous)
●
Defining earthquakes by means of dynamic multipliers
●
Modelling free vibration of structures
●
Modelling hysteretic behaviour by means of Hardening Soil model with small-strain stiffness
●
Evaluating the natural frequency from Fourier spectrum
Geometry
263
The building consists of 5 floors and a basement. It is 10 m wide and 17 m high including
basement. The total height from the ground level is 5 x 3 m = 15 m and the basement is 2 m
2
deep. A value of 5 kN/m is taken as the weight of the floors and the walls. The building is
constructed on a rather loose sand of 15 m depth underlain by a deep denser sand layer. In the
model, 25 m of the deep sand layer will be considered as shown in Figure 17–1 (p. 264).
15 m y
2m x
15 m
25 m
75 10 75
1 Start the Input program and select Start a new project from the Quick start dialog box.
2 In the Project tabsheet of the Project properties window, enter an appropriate title.
3 In the Model tabsheet keep the default options for Model (Plane strain) and Elements (15-
Noded).
4 Keep the default units and constants and set the model Contour to xmin = -80 m, xmax = 80
m, ymin = -40 m and ymax = 15 m.
1
Click the Create borehole button and create a borehole at x = 0.
Upper Lower
Parameter Name Unit
sand layer sand layer
General
Soil model - HS small HS small -
Drainage type - Drained Drained -
Mechanical
Secant stiffness in standard drained ref 3 3 2
triaxial test E50 20·10 30·10 kN/m
ref 3 3 2
Unloading / reloading stiffness Eur 95·10 110·10 kN/m
Cohesion c'ref 10 5 2
kN/m
Friction angle φ' 31 28 °
Dilatancy angle ψ 0 0 °
When subjected to cyclic shear loading, the Hardening Soil model with small-strain stiffness will
ref
show typical hysteretic behaviour. Starting from the small-strain shear stiffness, G0 , the actual
stiffness will decrease with increasing shear. The figures below display the Modulus reduction
curves, i.e. the decay of the shear modulus with strain. Figure 17–2 (p. 266) shows the secant
shear modulus and Figure 17–3 (p. 266) shows the tangent shear modulus.
Figure 17–3: Modulus reduction curve for the lower sand layer
In the Hardening Soil model with small-strain stiffness, the tangent shear modulus is bound by a
lower limit, Gur.
ref
Table 41: Gur values and ratio to G0
Figure 17–4 (p. 267) and Figure 17–5 (p. 268) show the damping ratio as a function of the
shear strain for the material used in the model. A more detailed description about the modulus
6
reduction curve to the damping curve can be found in the literature.
6 Brinkgreve, R.B.J., Kappert, M.H., Bonnier, P.G. (2007). Hysteretic damping in small-strain
stiffness model. In Proc. 10th Int. Conf. on Comp. Methods and Advances in Geomechanics.
Rhodes, Greece, 737-742.
Rayleigh β - -3 -3 -
8.0·10 8.0·10
Mechanical
Isotropic - Yes Yes -
Bending stiffness EI 3 3 2
67.5·10 160·10 kNm /m
Poisson's ratio ν 0 0 -
Axial stiffness EA 6 kN
2.5· 10
1
Use plates to create the vertical walls of the building from (-5 0) to (-5 15) and from (5
0) to (5 15).
2 Again with plates, now define the vertical walls of the basement from (-5 -2) to (-5 0) and
from (5 -2) to (5 0).
3 Define the basement and ground level of the building as plates from (-5 -2) to (5 -2) and
from (-5 0) to (5 0).
4 Define the floors by copying the basement floor 5 times. To do so, select the basement
floor and choose the Array button . Now specify that we want to copy it in y-direction, 6
copies (be aware: number of copies includes the original) and an intermediate distance of
3 m.
5
Define the material datasets for the structural elements in the building according to
Table 42 (p. 268).
6 Assign the Basement material dataset to the vertical plates (2) and the lowest horizontal
plate (all below ground level) in the model.
7 Assign the Building material dataset to the remaining plates in the model.
8
Use the Node-to-node anchor feature to define the column at the centre of the building
connecting consecutive floors, hence (0 -2) to (0 0), (0 0) to (0 3), (0 3) to (0 6), (0 6) to
(0 9), (0 9) to (0 12) and (0 12) to (0 15). Of course this can also be done by drawing one
column and use the Array function to copy the others.
9 Define the properties of the anchor according to Table 43 (p. 269) and assign the
material dataset to the anchors in the model.
10
Define an interface to model the interaction between soil and the building.
a. Define a line displacement at the bottom of the model, from (-80 -40) to (80 -40).
b. Set the x-component of the line displacement to Prescribed and assign a value of 1.0.
The y-component of the line displacement is Fixed. The default distribution (Uniform)
should be kept.
3 To define the dynamic multipliers for the line displacement:
Click the Create interfaces on the boundary button to automatically generate the interfaces
at the boundary of the model.
2 Reset the mesh refinement on the boundaries by changing the Coarseness factor on the
boundaries to 1.
3 Select both soil layers and set their Coarseness factor to 0.3.
4
Click the Generate mesh button to generate the mesh. Set the Element distribution to
Medium.
5
Click the View mesh button to view the mesh.
2 The initial phase has already been introduced. The default settings of the initial phase will be
used in this tutorial.
3 In the Staged construction mode check that the building and load are inactive.
4 The model for the initial phase is shown in Figure 17–9 (p. 273).
Note:
For a better visualisation of the results, animations of the free vibration and earthquake
can be created. If animations are to be created, it is advised to increase the number of
the saved steps by assigning a proper value to the Max steps saved parameter in the
Parameters tabsheet of the Phases window.
5 In the Deformation control parameters subtree, select the Reset displacement to zero.
6 In the Numerical control parameters subtree uncheck the Use default iter parameters
checkbox.
7 Set the Max steps to 1000.
8 Set the Time step determination to Manual and the Number of sub steps to 4 in order to
get a more detailed time-acceleration curve.
Note:
● The dynamic time interval is set to 20 seconds with a time interval of 0.005
seconds which gives 20/0.005=4000. So 4000 steps are required for the
calculation. Therefore, the Max steps is set to 1000 and the Number of sub
steps is set to 4. However, the automatic time stepping suggests smaller time
steps due to one or two relatively small elements, which requires a sensitivity
analysis for the time step size. For more information on time step for dynamic
calculations please visit Bentley communities.
● For more information on drift correction and input signal please visit Bentley
communities.
10 Expand the Dynamics subtree. Set the BoundaryXMin and BoundaryXMax to Free-field.
Set the BoundaryYMin to Compliant base as shown in Figure 17–12 (p. 275).
17.8 Results
Figure 17–13 (p. 276) shows the deformed structure at the end of the Phase 2 (application of
horizontal load).
Figure 17–14 (p. 277) shows the time history of displacements of the selected points A (0 15)
for the free vibration phase. It may be seen from the figure that the vibration slowly decays with
time due to damping in the soil and in the building.
In the Fourier tabsheet of the Curve generation window select the Power (spectrum) > Total
displacements > Ux and click OK to create the plot. The plot is shown in Figure 17–15 (p. 277).
From this figure it can be evaluated that the dominant building frequency is around 1 Hz.
18.1 Introduction
A navigable lock is temporarily 'empty' due to maintenance. After some time there is significant
increase of the air temperature, which causes thermal expansion of the inner side of the
lock, while the soil-side of the concrete block remains relatively cold. This leads to backward
bending of the wall and, consequently, to increased lateral stress in the soil behind the wall and
increased bending moments in the wall itself.
Objectives
This example demonstrates the use of the Thermal module to analyse this kind of situations.
●
Defining a thermal temperature function
●
Use of thermal expansion
●
Performing a fully coupled analysis for THM calculation
The geometry of the project is shown in Figure 18–1 (p. 280).
279
Excavation
5m
6m
10 m Concrete lock
12 m
16 m
Sand
50 m
2 In the Project tabsheet of the Project properties window, enter an appropriate title.
3 In the Model tabsheet, the default options for Model and Elements are used for this project.
Also the default options for the units are used in this tutorial.
4 Set the model Contour to xmin = 0 m, xmax = 25 m, ymin = -16 m and ymax = 0 m.
1
Click the Create borehole button and create a borehole at x = 0.
Mechanical
Young's modulus Eref - 6 2
25· 10 kN/m
Poisson's ratio ν - 0.15 -
Secant stiffness in standard drained ref 3 2
E50 40· 10 - kN/m
triaxial test
Tangent stiffness for primary ref 3 2
Eoed 40· 10 - kN/m
oedometer loading
ref 5 2
Unloading / reloading stiffness Eur 1.2· 10 - kN/m
Power for stress-level dependency
m 0.5 - -
of stiffness
ref 3 2
Shear modulus at very small strains G0 80· 10 - kN/m
Cohesion c'ref 2 - 2
kN/m
Friction angle φ' 32 - °
Dilatancy angle ψ 2 - °
Groundwater
Data set - USDA - -
Van
Model - - -
Genuchten
Soil - Type - Sand - -
Flow parameters - Use defaults - From data set - -
Thermal
Specific heat capacity cs 860 900 kJ/t/K
Interfaces
Strength determination - Rigid Manual -
Interface reduction factor Rinter 1.0 0.67 -
Initial
K0 determination - Automatic Automatic -
2
Click the Create soil polygon button in the side toolbar and select the Create soil
polygon option.
3 Define the lock in the drawing area by clicking on (0 -5), (5 -5), (5 0), (5.5 0), (6 -6), (0 -6)
and (0 -5).
Tip:
The Snapping options can be selected, and the Spacing can be set to 0.5 to easily
create the polygon.
8 Select the bottom boundary, in the Selection explorer set the Behaviour to Temperature.
9
Set the reference temperature, Tref to 283.4 K which is shown in Figure 18–2 (p. 283).
2 Select the polygon representing the concrete block, and in the Selection explorer set the
Coarseness factor to 0.25.
3
Click the Generate mesh button to generate the mesh. The default element distribution of
Medium is used for this example.
4
Click the View mesh button to view the mesh.
3 The default options for Calculation type and Pore pressure calculation type are used in this
example.
4 Select Earth gradient for the Thermal calculation type option and close the Phases
window.
5 In the Staged construction activate the ThermalFlow under the Model conditions subtree
and set the value for Tref to 283 K. The default values for href and Earth gradient are valid.
The Thermal flow parameters are shown in Figure 18–5 (p. 285) and the model for initial
phase is shown in Figure 18–6 (p. 285).
3 In the Phases window, enter an appropriate name for the phase ID and select Steady state
groundwater flow as Pore pressure calculation type.
4 Set the Steady state thermal flow for the Thermal calculation type.
5 Make sure that the Reset displacements to zero and Ignore suction options are selected.
9 In the Model explorer, activate all the Thermal flow boundary conditions.
10 In the Model explorer, activate the Model conditions > Climate condition.
11 2
Set the Air temperature to 283 K and the Surface transfer to 1 kW/m /K as shown in
Figure 18–8 (p. 287).
This will define the thermal conditions at the ground surface and the inside of the lock.
6 Make sure that the Reset displacements to zero and Reset small strain options are selected
in the Deformation control parameters subtree. The Ignore suction option is unchecked by
default.
7 A temperature function is defined for the Time dependency in Climate which is used for this
phase. Follow these steps to create a temperature function.
a. Right-click the Thermal functions option in the Attributes library in the Model explorer
and select Edit option in the appearing menu.
A graph is displayed in Figure 18–10 (p. 288) showing the defined function. Since the
time interval of the phase is 10 days, only a quarter of a temperature cycle is considered
in this phase, which means that after 10 days the temperature has increased by 15 K.
1
Click the Select points for curves button in the side toolbar and select some
characteristic points for curves (for example at the top of the excavation, (5.0, 0.0)).
2
Click the Calculate button to calculate the project, a warning regarding different stress
type used in the Fully coupled flow deformation analysis will appear. This warning appears
because the Fully coupled flow deformation analysis always calculates with suction while
the other calculation types by default do not calculate suction, and mixing phases with
and without suction may lead to unexpected results. However, since in this tutorial we are
dealing with sand the influence of suction will be very small and thus the warning can be
ignored.
3
After the calculation has finished, save the project by clicking the Save button .
18.8 Results
In the Phases explorer, select the Initial phase and click the View calculation results button on
the toolbar. In the Output program, select the menu Stresses > Heat flow > Temperature.
Figure 18–12 (p. 290) shows the initial temperature distribution, which is obtained from the
reference temperature at the ground surface and the earth gradient. This gives a temperature of
283.0 K at the ground surface and 283.4 at the bottom of the model.
Figure 18–13 (p. 290) shows the temperature distribution obtained from Phase_1 using a
steady-state thermal flow calculation. In fact, the temperatures at the top and bottom are equal
to the temperatures as defined in the Initial phase; however, since the temperature at the ground
surface is now defined in terms of Climate conditions (air temperature), this temperature is also
applied at the inner side of the lock and affects the temperature distribution in the ground.
The most interesting results are obtained in Phase_2 in which the air temperature in the Climate
condition increases gradually from 283 K to 298 K (defined by a quarter of a harmonic cycle
with an amplitude of 15K). Figure 18–14 (p. 291) shows the temperature at the ground surface
as a function of time.
As a result of the short increase in temperature at the inside of the concrete block, while the
outer side (soil side) remains 'cold', the wall will bend towards the soil. Figure 18–15 (p. 291)
shows the deformed mesh at the end of Phase_2.
As a result of this backward bending, the lateral stresses in the soil right behind the concrete
block will increase, tending towards a passive stress state.
Note:
● Note that the visualisation is different for Figure 18–16 (p. 292), because it displays
the stresses in the porous materials. This can be changed in View > Settings on the
tab Results (see the Reference Manual for more information).
● Note that Figure 18–16 (p. 292) shows the principal stresses for all stress points
whereas by default the principal stresses are only shown for the 3 center stress
points. This can be changed using the and buttons on the navigation bar.
19.1 Introduction
This tutorial illustrates change in coupling of groundwater flow and thermal flow as a result of
ground freezing. A tunnel is constructed with the use of freeze pipes. By first installing freeze
pipes in the soil, the soil freezes and becomes watertight so that tunnel construction can take
place. This method of construction requires a lot of energy for the cooling of the soil, so by
being able to model the cooling behaviour while groundwater flow is present an optimal freezing
system can be designed.
Objectives
●
Modelling soil freezing, coupling between thermal flow and groundwater flow
●
Modelling unfrozen water content.
●
Using the command line for structure definition.
Geometry
In this tutorial a tunnel with a radius of 3.0 m will be constructed in a 30 m deep soil layer. A
groundwater flow from left to right is present, influencing the thermal behaviour of the soil. First
the soil will be subjected to the low temperatures of the freeze pipes, and once the soil has
frozen sufficiently, tunnel construction can take place. The latter is not included in this tutorial.
293
Because groundwater flow causes an asymmetric temperature distribution, the whole geometry
needs to be modelled, where in previous examples only half of the geometry was sufficient. The
geometry of the project is shown in Figure 19–1 (p. 294).
15 m
30 m
45 m
Radius = 3.0 m
90 m
2 In the Project tabsheet of the Project properties window, enter an appropriate title.
3 In the Model tabsheet, the default options for Model and Elements are used for this project.
Also the default options for the units are used in this tutorial. Note that the unit of Mass is set
automatically to tonnes.
4 Set the model Contour to xmin = -45 m, xmax = 45 m, ymin = -30 m and ymax = 0 m.
5 In the Constants tabsheet, set Twater and Tref to 283 K, other constants keep their default
values. A description of constants can be found in the Reference Manual.
6 Click OK to close the Project properties window.
1
Click the Create borehole button and create a borehole at x = 0.
Mechanical
Young's modulus E' 3 2
ref 100· 10 kN/m
Poisson's ratio ν 0.3 -
Cohesion c'ref 0 2
kN/m
Friction angle φ' 37 °
Dilatancy angle ψ 0 °
Groundwater
Classification type - Standard -
Soil - class - Medium -
Flow parameters - Use defaults - None -
Horizontal permeability kx 1 m/day
Thermal
Specific heat capacity cs 860 kJ/t/K
-3 kW/
Thermal conductivity λs 4·10 m/K
Interfaces
Strength determination - Rigid -
2
Thermal resistance factor Rthermal 0 m K/
kW
Initial
K0 determination - Automatic -
To model the amount of (fluid) water available to flow through the soil at certain
temperatures, a curve for unfrozen water content needs to be determined by defining a
table with values for unfrozen water content at certain temperatures. The same curve can be
applied in other projects, hence the table can be saved and loaded into the soil properties of
other projects. For more information, refer to the Reference Manual.
3. Click the Thermal tab. Enter the values as given in Table 46 (p. 296) .
Table 46: Input for unfrozen water content curve for sand
1
Multi select the 12 lines representing the freeze pipes using the Select lines option from
the side toolbar.
2
Right click the selected lines and select Thermal flow BC to create the thermal flow
boundary conditions for the freeze pipes.
3 For the selected freeze pipes, in the Selection explorer expand the subtree for the
ThermalFlowBC.
4 The Behaviour is set to Convection, the Tfluid to 250 K and the Transfer coefficient to 1.0
2
kW/m /K.
1 To assign the thermal boundary conditions, please take the following instructions:
1 Click the Create tunnel button in the side toolbar and click on (0 -18) in the drawing area.
2 The option Circular is selected for Shape type. Note that the default option is Free.
4 Proceed to the Segments tab and set Radius to 3 m to the two multi selected segments.
5 Click on Generate to generate the defined tunnel in the model. Close the Tunnel designer
window.
2
Click the Generate mesh button to generate the mesh. The default element distribution of
Medium is used for this example.
3
Click the View mesh button to view the mesh.
3 In the Phases window select the Flow only option from the Calculation type drop-down
menu.
4 Choose the Earth gradient option for the Thermal calculation type.
5 In the Staged construction activate the ThermalFlow under the Model conditions subtree
and set the value for Tref to 283 K, href to 0 m and 0 K/m for the Earth gradient.
6 The model for initial phase is shown in Figure 19–4 (p. 300).
3 In the Phases window, enter an appropriate name for the phase ID (e.g. Transient
calculation).
4
Set Transient groundwater flow as the option for the Pore pressure calculation type.
5
Set Transient thermal flow as the option for the Thermal calculation type.
6 Set Time interval to 180 days and the Max number of steps stored to 100. This is to be able
to view intermediate time steps after the calculation.
7 In Staged construction mode, activate all the thermal boundary conditions by clicking the
check box for the Thermal flow BCs in the Model explorer.
8 In the Model explorer, activate the four groundwater flow boundary conditions
corresponding to the left, top, right and bottom boundary conditions in the Groundwater
flow BCs subtree.
19.8 Results
Interesting results from this calculation can be the point in time when there is no groundwater
flow in between two freezing pipes, groundwater flow over the whole model and temperature
distribution for both steady state and transient calculations.
To view the results in the Output program:
1
Click the View calculation results button on the toolbar.
2 Select the menu Stresses > Heat flow > Temperature.
3 Figure 19–5 (p. 301) shows the spatial distribution of the temperature for transient
calculation in the final step. Note that the element contours have been switched off to better
show that the temperature of the soil inside the tunnel is below freezing.
5
Select the menu View > Arrows or click the corresponding button in the toolbar to
display the results arrows.
In the Output program, it is possible to view the results for the intermediate saved steps. More
information is available in the Reference Manual. It is possible to view the progression of the
freezing of the tunnel.
Figure 19–6 (p. 302) shows the distribution of the of groundwater flow field for an intermediate
step for the transient calculation (around 38 days).
Figure 19–7 (p. 302) shows the groundwater flow field for the last time step for the transient
flow calculation. Here it is clearly noticeable that the entire tunnel area is frozen and no flow
occurs.
Figure 19–8 (p. 303) shows the change of temperature in time for the point in the middle of
the tunnel. It can be seen that the temperature drops quite fast until about 273 K when the pore
water starts to change from water to ice. During this process the temperature remains almost
constant and only until after all pore water has turned to ice (at t = 122 s) the ice temperature
drops further.