Operations Management Practice Questions (Que) Final
Operations Management Practice Questions (Que) Final
2. Which of the following statements best describes the Master Production Schedule (MPS)?
A. It is a long-term strategic sales plan that forecasts future demand.
B. It defines what products to produce, when to produce them, and in what quantity.
C. It replaces the need for Material Requirements Planning (MRP).
D. It focuses solely on marketing and customer engagement.
Week 1 2 3 4 5
Orders 15 8 12 18 9
Forecast 10 12 10 20 15
Questions:
a. Complete the following table by filling in the MPS (Master Production Schedule) and
PAB (Projected Available Balance) for each week.
c. Explain why a batch was scheduled or not scheduled in each week, referring to the
safety stock condition.
• Customer Orders:
• 50 conference tables due in Week 2
• 100 conference tables due in Week 5
• Scheduled Receipts (SR):
• Tops: 60 units arriving in Week 1 and Week 3
• Legs: 100 units arriving in Week 1
• Lead Times (LT):
• Table Assembly: 1 weeks
• Top Panel: 1 week
• Table Legs: 1 week
• Initial Inventory:
• Tables: 10 units
• Tops: 20 units
• Legs: 100 units
Please finish the MRP tables for all items (Conference Table, Top Panel, Table Legs) under lot
for lot policy.