NCHRP RPT 574
NCHRP RPT 574
NCHRP RPT 574
REPORT 574 Guidance for Cost Estimation and Management for Highway Projects During Planning, Programming, and Preconstruction
MEMBERS
Michael W. Behrens, Executive Director, Texas DOT, Austin Allen D. Biehler, Secretary, Pennsylvania DOT, Harrisburg John D. Bowe, Regional President, APL Americas, Oakland, CA Larry L. Brown, Sr., Executive Director, Mississippi DOT, Jackson Deborah H. Butler, Vice President, Customer Service, Norfolk Southern Corporation and Subsidiaries, Atlanta, GA Anne P. Canby, President, Surface Transportation Policy Project, Washington, DC Douglas G. Duncan, President and CEO, FedEx Freight, Memphis, TN Nicholas J. Garber, Henry L. Kinnier Professor, Department of Civil Engineering, University of Virginia, Charlottesville Angela Gittens, Vice President, Airport Business Services, HNTB Corporation, Miami, FL Genevieve Giuliano, Professor and Senior Associate Dean of Research and Technology, School of Policy, Planning, and Development, and Director, METRANS National Center for Metropolitan Transportation Research, University of Southern California, Los Angeles Susan Hanson, Landry University Professor of Geography, Graduate School of Geography, Clark University, Worcester, MA James R. Hertwig, President, CSX Intermodal, Jacksonville, FL Gloria J. Jeff, General Manager, City of Los Angeles DOT, Los Angeles, CA Adib K. Kanafani, Cahill Professor of Civil Engineering, University of California, Berkeley Harold E. Linnenkohl, Commissioner, Georgia DOT, Atlanta Sue McNeil, Professor, Department of Civil and Environmental Engineering, University of Delaware, Newark Debra L. Miller, Secretary, Kansas DOT, Topeka Michael R. Morris, Director of Transportation, North Central Texas Council of Governments, Arlington Carol A. Murray, Commissioner, New Hampshire DOT, Concord John R. Njord, Executive Director, Utah DOT, Salt Lake City Pete K. Rahn, Director, Missouri DOT, Jefferson City Sandra Rosenbloom, Professor of Planning, University of Arizona, Tucson Henry Gerard Schwartz, Jr., Senior Professor, Washington University, St. Louis, MO Michael S. Townes, President and CEO, Hampton Roads Transit, Hampton, VA C. Michael Walton, Ernest H. Cockrell Centennial Chair in Engineering, University of Texas, Austin
EX OFFICIO MEMBERS
Thad Allen (Adm., U.S. Coast Guard), Commandant, U.S. Coast Guard, Washington, DC Thomas J. Barrett (Vice Adm., U.S. Coast Guard, ret.), Pipeline and Hazardous Materials Safety Administrator, U.S.DOT Marion C. Blakey, Federal Aviation Administrator, U.S.DOT Joseph H. Boardman, Federal Railroad Administrator, U.S.DOT John Bobo, Deputy Administrator, Research and Innovative Technology Administration, U.S.DOT Rebecca M. Brewster, President and COO, American Transportation Research Institute, Smyrna, GA George Bugliarello, Chancellor, Polytechnic University of New York, Brooklyn, and Foreign Secretary, National Academy of Engineering, Washington, DC J. Richard Capka, Federal Highway Administrator, U.S.DOT Sean T. Connaughton, Maritime Administrator, U.S.DOT Edward R. Hamberger, President and CEO, Association of American Railroads, Washington, DC John H. Hill, Federal Motor Carrier Safety Administrator, U.S.DOT John C. Horsley, Executive Director, American Association of State Highway and Transportation Officials, Washington, DC J. Edward Johnson, Director, Applied Science Directorate, National Aeronautics and Space Administration, John C. Stennis Space Center, MS William W. Millar, President, American Public Transportation Association, Washington, DC Nicole R. Nason, National Highway Traffic Safety Administrator, U.S.DOT Jeffrey N. Shane, Under Secretary for Policy, U.S.DOT James S. Simpson, Federal Transit Administrator, U.S.DOT Carl A. Strock (Lt. Gen., U.S. Army), Chief of Engineers and Commanding General, U.S. Army Corps of Engineers, Washington, DC
Keith Molenaar
UNIVERSITY OF COLORADO
Boulder, CO
Cliff Schexnayder
DEL E. WEB SCHOOL OF CONSTRUCTION ARIZONA STATE UNIVERSITY
Tempe, AZ
Subject Areas
Research sponsored by the American Association of State Highway and Transportation Officials in cooperation with the Federal Highway Administration
COPYRIGHT PERMISSION
Authors herein are responsible for the authenticity of their materials and for obtaining written permissions from publishers or persons who own the copyright to any previously published or copyrighted material used herein. Cooperative Research Programs (CRP) grants permission to reproduce material in this publication for classroom and not-for-prot purposes. Permission is given with the understanding that none of the material will be used to imply TRB, AASHTO, FAA, FHWA, FMCSA, FTA, or Transit Development Corporation endorsement of a particular product, method, or practice. It is expected that those reproducing the material in this document for educational and not-for-prot uses will give appropriate acknowledgment of the source of any reprinted or reproduced material. For other uses of the material, request permission from CRP.
NOTICE
The project that is the subject of this report was a part of the National Cooperative Highway Research Program conducted by the Transportation Research Board with the approval of the Governing Board of the National Research Council. Such approval reects the Governing Boards judgment that the program concerned is of national importance and appropriate with respect to both the purposes and resources of the National Research Council. The members of the technical committee selected to monitor this project and to review this report were chosen for recognized scholarly competence and with due consideration for the balance of disciplines appropriate to the project. The opinions and conclusions expressed or implied are those of the research agency that performed the research, and, while they have been accepted as appropriate by the technical committee, they are not necessarily those of the Transportation Research Board, the National Research Council, the American Association of State Highway and Transportation Officials, or the Federal Highway Administration, U.S. Department of Transportation. Each report is reviewed and accepted for publication by the technical committee according to procedures established and monitored by the Transportation Research Board Executive Committee and the Governing Board of the National Research Council. The Transportation Research Board of the National Academies, the National Research Council, the Federal Highway Administration, the American Association of State Highway and Transportation Officials, and the individual states participating in the National Cooperative Highway Research Program do not endorse products or manufacturers. Trade or manufacturers names appear herein solely because they are considered essential to the object of this report.
FOREWORD
By Ronald D. McCready
Staff Officer Transportation Research Board
This guidebook presents approaches to cost estimation and management to overcome the root causes of cost escalation and to support the development of consistent and accurate project estimates through all phases of the development process, from long-range planning, through priority programming, and through project design.
The problem of cost escalation has become a major concern in virtually every field of capital project development. Within the transportation sector, cost escalation has attracted attention at the federal, state, regional, and local government levels for highways, transit, and other modes. State departments of transportation (DOTs), transit agencies, and other government entities responsible for delivering transportation projects historically have experienced increases in project cost estimates from the time that a project is rst proposed or programmed until the time that it is completed. Recent studies have shown that this has been a worldwide problem, particularly for large projects. Cost estimate increases that occur after a project is rst identied in a plan but before the project is designed create a substantial disruption in priority programs, because other projects have to be delayed or removed in order to accommodate higher cost estimates. The challenges of accurate cost estimation and management of costs are faced by almost every state DOT, transit agency, and metropolitan planning organization (MPO) in the country as projects evolve from concept in the long-range planning process, are prioritized within programs, and are subject to detailed development prior to construction. Cost estimates increasing over the course of project development may be caused by any number of factors, such as an inadequate project scope at the time of planning or programming, insufficient information on the extent of utility relocation requirements, insufficient knowledge of right-of-way costs and locations, required environmental mitigation costs to avoid certain impacts, traffic control requirements, and work-hour restrictions. As is often the case with very large and complex projects, the project scope and concept may not be fully understood until well after a substantial commitment has been made to its construction. In addition, the project scope often expands as more internal and external stakeholders provide input on what elements should be included. Sometimes, if the cost of an item is not known, it is not included in early project cost estimates. In other instances, items such as right-of-way or construction engineering may be included with only tentative or supercial information to support their estimated costs. Initial cost estimates may be prepared by an agency other than the agency responsible for project delivery; this can result in different understandings of project requirements and vastly different estimates. There is sometimes speculation that, to secure funding for projects, items may be purposefully excluded from initial project scopes and costs with the intention of adding them later. Questions about
honesty or competence can threaten the credibility of the planning and programming process and that of the transportation agency and create increased frustration by professional staffs, policy makers, elected officials, and the general public. Both the Federal Highway Administration and the Federal Transit Administration have initiated major efforts to overcome this problem in federally aided projects. In recent years, states, transit agencies, and local public works agencies have studied the problem and attempted to nd causes and solutions to improve the procedures, with varying degrees of success. There is a need for research into all aspects of cost estimation management and cost estimation procedures aimed at addressing consistency and accuracy throughout the entire project development process, from long-range planning, through priority programming, up to preconstruction engineering and design. The objective of this project was to develop a guidebook on highway cost estimation and management practice aimed at achieving greater consistency and accuracy between long-range transportation planning, priority programming, and preconstruction cost estimates. The guidebook provides strategies, methods, and tools to develop, track, and document more realistic cost estimates during each phase of the process. Under NCHRP Project 8-49, Guidance on Cost Estimation and Management for Highway Projects During Planning, Programming, and Preconstruction, a research team led by Texas Transportation Institute carried out a comprehensive investigation into current and effective practices for cost estimation and management during the various planning and project development phases prior to construction. The project resulted in a practical guidebook designed to provide users with the most appropriate practices to develop and manage realistic cost estimates throughout the project development process. The guidebook should be of significant use to managers, practitioners, and decision makers interested in development and management of realistic and accurate cost estimates for transportation projects from the earliest stages of planning through nal project design. The guidance provided is intended to provide methods and tools that will reduce unintended or unanticipated escalation of costs as transportation projects proceed through the development process.
CONTENTS
1 3
3 3 3 4 4 5 5 6 6
7
7 7 10 11
Chapter 2 Agency Cost Estimation Practice and Cost Estimation Management Processes
Transportation Development Phases Cost Estimation Practice and Cost Estimation Management Overview Cost Estimation Practice and Cost Estimation Management Steps Summary
13
13 13 15 16 16 16 16 17 17 17 17 17 17
19
19 19 19 21 21
22
22
24 25 25 26 26 27 27 27 27 28 29 29 29 30 30 30 31 31 32 32 33 33 33 34 34 34 35 35 36 36 37 37 37 38
Methodology 5.1 Strategy: Management 5.1.1 Budget Control 5.1.2 Communication 5.1.3 Consistency 5.1.4 Recognition of Project Complexity 5.1.5 Risk Analysis 5.2 Strategy: Scope and Schedule 5.2.1 Buffers 5.2.2 Communication 5.2.3 Computer Software 5.3 Strategy: Off-Prism Issues 5.3.1 Communication 5.3.2 Identifying Off-Prism Issues 5.4 Strategy: Risk 5.4.1 Identication of Risk 5.4.2 Right-of-Way 5.4.3 Risk Analysis 5.5 Strategy: Delivery and Procurement 5.5.1 Delivery and Procurement Method 5.6 Strategy: Document Quality 5.6.1 Computer Software 5.6.2 Document Estimate Basis and Assumptions 5.6.3 Identifying Off-Prism Issues 5.7 Strategy: Estimate Quality 5.7.1 Computer Software 5.7.2 Conceptual Estimation 5.7.3 Estimate ReviewExternal 5.7.4 Estimate ReviewInternal 5.7.5 Project Scoping 5.7.6 Right-of-Way 5.8 Strategy: Integrity 5.8.1 Computer Software 5.9 Summary
39
39 41 41 41 43 44 44 45 45 46 46 46 47 48
48 49 49 50 50 51 51 52 52 52 53 53 54 54 55 55 55 56 56 57 57 58 58 58 60 60 60 61 61 62 62 63 63 63 63 64 65 65 66 66 66 67 67
6.3
6.4
6.5 6.6
6.7
6.8
6.9
6.2.5 Identication of Changes 6.2.6 Constructability 6.2.7 Value Engineering Strategy: Off-Prism Issues 6.3.1 Communication 6.3.2 Right-of-Way 6.3.3 Public Involvement 6.3.4 Estimate ReviewInternal 6.3.5 Identifying Off-Prism Issues Strategy: Risk 6.4.1 Communication 6.4.2 Identication of Risk 6.4.3 Right-of-Way 6.4.4 Risk Analysis 6.4.5 Delivery and Procurement Method Strategy: Delivery and Procurement 6.5.1 Delivery and Procurement Method Strategy: Document Quality 6.6.1 Computer Software 6.6.2 Constructability 6.6.3 Estimate/Document Review Strategy: Estimate Quality 6.7.1 Computer Software 6.7.2 Consistency 6.7.3 Creation of Project Baseline 6.7.4 Gated Process 6.7.5 Right-of-Way 6.7.6 Communication 6.7.7 Design Estimation 6.7.8 Document Estimate Basis and Assumptions 6.7.9 Estimate ReviewExternal 6.7.10 Estimate ReviewInternal 6.7.11 Project Scoping Strategy: Integrity 6.8.1 Communication 6.8.2 Computer Software 6.8.3 Design to Mandated Budget 6.8.4 Consistency 6.8.5 Estimate ReviewExternal 6.8.6 Estimate ReviewInternal 6.8.7 Validate Costs 6.8.8 Verify Scope Completeness Summary
69
69 69 69 70 71 73
73 73 74 74 75 75 76 76 77 77 77 78 78 79 79 79 80 80 81 81 81 82 82 83 83 83 84 84 85 85 86 86 86 87 87
7.2
7.3
7.4
7.5
7.6
7.7
7.8
7.9
7.1.4 Estimate ReviewInternal 7.1.5 Gated Process 7.1.6 Identication of Changes 7.1.7 Plans, Specications, and Estimates (PS&E) Strategy: Scope and Schedule 7.2.1 Buffers 7.2.2 Communication 7.2.3 Estimate ReviewExternal 7.2.4 Estimate ReviewInternal 7.2.5 Identication of Changes 7.2.6 Value Engineering Strategy: Off-Prism Issues 7.3.1 Communication 7.3.2 Right-of-Way 7.3.3 Risk Analysis Strategy: Risk 7.4.1 Communication 7.4.2 Identication of Risk 7.4.3 Risk Analysis Strategy: Delivery and Procurement 7.5.1 Off-Prism Issues 7.5.2 Constructability Strategy: Document Quality 7.6.1 Computer Software 7.6.2 Estimate/Document Review 7.6.3 Document Estimate Basis and Assumptions Strategy: Estimate Quality 7.7.1 Estimate ReviewExternal 7.7.2 Estimate ReviewInternal 7.7.3 Consistency 7.7.4 Plans, Specications, and Estimates (PS&E) Strategy: Integrity 7.8.1 Estimate ReviewExternal 7.8.2 Estimate ReviewInternal Summary
88
88 88 89 89 90 90 90 91 91 91 92 92 92 92 93
Chapter 8 Implementation
Introduction Step 1: Implementation of StrategiesOrganizational Change Establish Steering Committee Conduct Agencywide Workshop Step 2: Implementation of MethodsProgrammatic Change Assess Current Practices Develop Policies and Procedures Develop Education and Training Step 3: Implementation of ToolsProject Change Assess Current Practices Test New Tools Develop Agency-Specic Tools Step 4: Integrating the SystemA Strategic Plan Implement the Long-Term Strategic Plan Summary
94
94 94 94 95 95
SUMMARY
Guidance for Cost Estimation and Management for Highway Projects During Planning, Programming, and Preconstruction
State highway agencies face a major challenge in controlling project budgets over the time span between project initiation and the completion of construction. Project cost increases, as reected by budget overruns during the course of project development, are caused by factors that have been identied through a large number of studies and research projects. These factors, the root causes behind estimation problems, differ with project development phase and project complexity. This Guidebook presents cost estimation management and cost estimation practice approaches to address the root causes of cost escalation and to support the development of consistent and accurate project estimates. These approaches are aligned with project development phases and project complexity. The Guidebook provides appropriate strategies, methods, and tools to develop, track, and document realistic cost estimates during each phase of project development.
A Strategic Approach
Agencies will have to do more than simply institute changes in estimation practices if they are to achieve consistent and accurate estimates. Project cost estimation management and cost estimation practice should be viewed as interdependent processes that span the entire project development process. An analysis of estimation literature and exhaustive data provided by state highway agencies led to the development of eight global strategies to address state highway agency estimation problems. These strategies focus on the critical causal factors behind project cost escalation and support the objective of consistent and accurate estimation:
Management strategyManage the estimation process and costs through all stages of project development; Scope and schedule strategyFormulate denitive processes for controlling project scope and schedule changes; Off-prism strategyUse proactive methods for engaging external participants and assessing the macroenvironmental conditions that can inuence project costs; Risk strategyIdentify risks, quantify their impact on cost, and take actions to mitigate the impact of risks as the project scope is developed; Delivery and procurement strategyApply appropriate delivery methods to better manage cost because project delivery inuences both project risk and cost; Document quality strategyPromote cost estimate accuracy and consistency through improved project documents; Estimate quality strategyUse qualied personnel and uniform approaches to achieve improved estimate consistency and accuracy; and Integrity strategyEnsure that checks and balances are in place to maintain estimate accuracy and to minimize the impact of outside pressures that can cause optimistic biases in estimates.
In this Guidebook, these eight strategies are linked to over 30 recommended methods for implementing the strategies and to over 90 tools for executing specific methods.
Keys to Success
Disciplined cost estimation management and cost estimation practice should be applied in the context of the eight global strategies. This research has determined that 10 key principles 5 cost estimation management principles and 5 cost estimation practice principlesmust be focused on to ensure creation of consistent and accurate estimates. Each individual principle by itself can help improve cost estimation management and cost estimation practice. However, maximum improvement of these two processes will only occur if the 10 key principles are incorporated into the agencys business practices throughout the organization. The key principles, in prioritized order, are as follows. Cost estimation management: 1. Make estimation a priority by allocating time and staff resources. 2. Set a project baseline cost estimate during programming or early in preliminary design, and manage to this estimate throughout project development. 3. Create cost containment mechanisms for timely decision making that indicate when projects deviate from the baseline. 4. Create estimate transparency with disciplined communication of the uncertainty and importance of an estimate. 5. Protect estimators from internal and external pressures to provide low cost estimates. Cost estimation practice: 1. Complete every step in the estimation process during all phases of project development. 2. Document estimate basis, assumptions, and back-up calculations thoroughly. 3. Identify project risks and uncertainties early, and use these explicitly identified risks to establish appropriate contingencies. 4. Anticipate external cost inuences and incorporate them into the estimate. 5. Perform estimate reviews to conrm that the estimate is accurate and fully reects project scope.
Challenges
Implementing new concepts involves facing the challenges that accompany change. State highway agencies must consider several challenges when deploying this Guidebook:
Challenging the status quo and creating a cultural change requires leadership and mentoring to ensure that all steps in the cost estimation management and cost estimation processes are performed. Developing a systems perspective requires organizational perspective and vision to integrate cost estimation management and cost estimation practice throughout the project development process. Dedicating sufcient time to changing agency attitudes toward estimation and incorporating the strategies, methods, and tools from this Guidebook into current state highway agency practices is difcult when resources are scarce. Dedicating sufcient human resources to cost estimation practice and cost estimation management beyond the resources that have previously been allocated to estimation processes. Meeting these challenges will ultimately require a commitment by the agencys senior management to direct and support change. The benet of this commitment will be manifested in projects that are consistently within budget and on schedule and that fulll their purpose as dened by their scope. This benet will also improve program management by allowing for better allocation of funds to projects to meet the needs of the ultimate customer, the public.
CHAPTER 1
Introduction
Background
Project cost escalation is a major challenge for state highway agencies. Over the time span between the initiation of a project and the completion of construction, many factors inuence a projects nal costs. This time span is normally several years, but for highly complex and technologically challenging projects the time span can easily exceed a decade. Over that period, numerous changes to the project scope and schedule will occur. Many factors that inuence project costs are undened during the early stages of project development, such as knowledge about right-of-way cost and alignment, environmental mitigation requirements, trafc control requirements, or work-hour restrictions. Moreover, there are process-related factors that can drive project cost increases, such as unforeseen engineering complexities and constructability issues, changes in economic and market conditions, changes in regulatory requirements, local governmental and stakeholder pressures, and a transformation of community expectations. All of these and other cost escalation factors create distinct challenges related to the development of project estimates and effective cost estimation management. These challenges are
Difculty in describing scope solutions for all issues early
struction complexities of such projects are overshadowed by economic, societal, and political challenges. Within the transportation community, project cost escalation has attracted management, political, and stakeholder attention at federal, state, regional, and local levels. News reports of project cost escalation cause the public to lose condence in the ability of transportation agencies to effectively perform their responsibilities. Additionally, state highway agency management must deal with the disruption that project cost increases cause in priority programs (the disruption occurs when other projects have to be delayed or removed in order to accommodate higher project costs). As projects move from concept to construction, cost escalation is faced by every state highway agency, transit agency, and metropolitan planning organization (MPO) in the country. Although project cost escalation is usually caused by lack of project scope control and factors external to the state highway agency, it results in cost estimation practice and cost estimation management approaches that do not promote consistency and accuracy of cost estimates across the project development process.
in project development, Difculty in evaluating the quality and completeness of early cost estimates, Difculty in identifying major areas of variability and uncertainty in project scope and costs, and Difculty in tracking the cost impact of design development that occurs between major cost estimates.
Guidebook Concepts
This Guidebook presents a strategic approach for achieving accurate project cost estimates based on strategies, methods, and tools for project cost estimation practice and cost estimation management that are linked to (1) planning and the project development process and (2) project complexity. A strategy is a plan of action intended on accomplishing a specic goal. Strategies typically address a specic problem and are formulated to address a problems root cause. For example, a strategy might be risk. The risk strategy for controlling cost seeks to identify risks, quantify the impact of a risk on cost, and take actions to mitigate that impact. This strategy would likely address a root cause of cost escalation such as
Industry Problem
Managing large capital construction projects requires the coordination of a multitude of human, organizational, and technical resources. Quite often, the engineering and con-
scope changes caused by external and internal stakeholders providing input during project development. The strategy is implemented through a method. A method is a means or manner of procedure, especially a regular and systematic way of accomplishing something. The method must support the strategy. A method for the described risk strategy might be a formal or structured risk analysis. This method is typically applied when preparing early project estimates, as the scope is being dened and detailed. One purpose of this method is to narrow the range of scope uncertainty. A method is then implemented using a tool. A tool is something used in the performance of an operation. In this case, the operation is the method. A newly used tool for the risk analysis method is estimation ranges. At the core of this tool are risk identication, risk assessment, and the communication of uncertainty. This tool makes use of probabilities and simulation to produce a probabilistic range of project costs rather than a single-point estimate. Project estimates are made at various points in time during project development for a variety of reasons. An estimation method and tool must fit the information available at the time the estimate is developed. Thus, certain types of estimates apply to specic project development phases. For example, the risk analysis method is used when projectspecic estimates are prepared during the early phases of project development. State highway agencies deal with a variety of project types; thus, the Guidebook considers strategies, methods, and tools in terms of their application to small or straightforward projects, rehabilitation projects, major reconstruction projects, major new construction projects, and special situations such as when a state highway agency uses an innovative contracting method and does not prepare a complete set of plans and specications. Project complexity is also important because it may determine when, and to what extent, a specic method and tool should be used. As an example, the risk analysis method is typically used to expose areas associated with large, complex projects that have signicant uncertainties associated with construction methods. The hierarchical decomposition of strategies, methods, and tools is illustrated in Figure 1.1. Methods are used to implement strategies. As shown, more than one method may be used to implement a particular strategy. One or more tools can be used to implement a method. The use of specic strategies,
Strategy 1 Strategy 2
methods, and tools changes with project development phases and different levels of project complexity.
Guidebook Development
This Guidebook was developed under NCHRP Project 8-49, Procedures for Cost Estimation and Management for Highway Projects during Planning, Programming, and Preconstruction. Approaches for addressing the transportation community problem of accurately estimating and managing project cost are proposed based on this research. The research was conducted in two phases. The rst phase focused on a state-of-practice review of cost estimation practice and cost estimation management processes. The current state of estimation practice was characterized by an extensive review of the literature supported by interviews of transportation agencies. Major factors causing project cost escalation were identied during this rst phase of the research. Over 23 state highway agencies provided input on the practices they use during different project development phases. A critical review of these practices formed the basis for identifying viable and successful approaches to cost estimation practice and cost estimation management. Based on this literature and interview work, eight strategies were identied to address the root causes of project cost escalation. These eight strategies were then linked to over 30 implementation methods. From the discussion with state highway agencies, over 90 tool applications were identied to support the 30 methods. These strategies, methods, and tools align with planning, programming, and preconstruction. This strategic approach, including the methods and tools, was reviewed and approved by the NCHRP 8-49 panel. Based on the state-of-practice data from the state highway agencies, the second phase of the research developed this Guidebook. The Guidebook, with a focus on addressing cost escalation through the use of strategies, methods, and tools, was prepared in draft form. It was then critically reviewed by 10 state highway agencies. These state highway agencies provided a critique of the Guidebooks content, structure, layout, and user friendliness. The NCHRP 8-49 panel reviewed and commented on this nal version of this Guidebook.
Guidebook Organization
The Guidebook has nine chapters, including the introduction. The background information and fundamental concepts concerning the content of the Guidebook are developed in Chapters 2, 3, and 4. Chapter 2, Agency Cost Estimation Practice and Cost Estimation Management Processes, demonstrates how cost estimation practice and cost estimation management are linked to planning and the project development process. The key information exchanged between different development phases is presented in a ow chart format.
Method 1
Method 2
Method 3
Tool 1
Tool 2
Tool 3
Tool 4
This ow chart is critical to understanding that achievement of accurate estimates requires a systematic approach. Further, the purposes of cost estimates prepared during different project phases are also discussed because estimates at specic points in planning and project development are critical to making sound nancial decisions. Chapter 3, Factors and Strategies, identies and categorizes 18 cost escalation factors that have been found to repeatedly cause cost overruns on state highway agency projects. Eight strategies are then introduced that address these cost escalation factors. If these strategies are systematically implemented as suggested in the Guidebook, state highway agencies will reduce project-specic cost increases and subsequent increases in capital program budgets. Chapter 4, Guidebook Framework, presents a consistent approach used to describe the strategies, methods, and tools as applied during planning and the project development process. Chapters 5, 6, and 7Guide for Planning Phase, Guide for Programming and Preliminary Design Phase, and Guide for Final Design Phase, respectively, focus on the application of the fundamental concepts presented in Chapters 2, 3, and 4. These chapters provide guidance on cost estimation practice and cost estimation management process implementation during each phase. Guidance is provided with a specic focus on the dominant cost escalation factors that most often occur during a specic project phase and the strategies that are effective in addressing these cost escalation factors. Specic methods employed to implement strategies are identied in terms of key information relevant to applying the method. Tools are linked to methods and strategies through an extensive appendixAppendix Awhich provides support for implementation of the methods described in Chapters 5, 6, and 7. Appendix A provides information concerning tools, including examples and illustrations of all tools. New concepts and innovative ideas require a planned approach to facilitate their implementation into practice. Chapter 8, Implementation, covers key implementation thrust areas and steps in the implementation process that must be considered when introducing changes to current cost estimation practice and cost estimation management within a transportation agency. Finally, Chapter 9 summarizes the main features of the Guidebook and the challenges users may encounter when striving to improve agency cost estimation practice and cost estimation management. This chapter also provides 10 key principles that will lead to successful application of the strategies, methods, and tools presented in this Guidebook.
cic details on cost estimation practice or cost estimation management. However, the Guidebook does provide the necessary knowledge and information for state highway agencies to create how to approaches that t within their own agency processes and culture. The Guidebook is designed to provide information to various users in a number of ways. Guidebook information is categorized as having an implementation thrust or topic focus. Several examples are provided. The user is encouraged to use a strategic approach, but there are other ways to use the methods and tools presented in the Guidebook.
Implementation Thrust
Organization Level If cost escalation is a signicant problem for an agency, changes in agency policy that inuence how cost estimation practice and cost estimation management is performed may be necessary to improve the processes and provide more consistent and accurate estimates throughout project development. If this is the case, executive managers should review Chapters 2, 3, and 4 of the Guidebook. These chapters provide a basic structure and approach for developing agencywide policies that will lead to improved cost estimation practice and cost estimation management processes. Chapter 8 will provide assistance in implementing changes related to cost estimation practice and cost estimation management from an agencywide perspective. Program Level Program-level managers are often charged with implementing policy changes. If policy changes in cost estimation practice and cost estimation management are necessary, then these managers should read Chapter 2; Chapter 3; Chapter 4; the relevant Chapter 5, 6, and/or 7; and Chapter 8 on implementation issues. For example, planning directors can focus on Chapter 5, Guide for Planning Phase, while managers of engineering and environmental programs can focus on Chapter 6, Guide for Programming and Preliminary Design Phase. Project Level Project-level managers, engineers, and discipline leaders (the chiefs of sections such as design, right-of-way, and/or estimation) who are directly responsible for cost estimation practice and cost estimation management processes should read Chapter 3; Chapter 4; the relevant Chapters 5, 6, and/or 7; and Appendix A according to their area of expertise. Those leaders directly involved in estimation should read the same chapters and Appendix A. If the estimator has a specic area of expertisesuch as plans, specications, and estimates
Use of Guidebook
The intent of the Guidebook is to provide transportation agencies with guidance on preparing realistic estimates and managing project cost. The material contained in the following chapters does not provide how to procedures with spe-
(PS&E)then Chapter 7, Guide for Final Design Phase, should be studied in detail, including the relevant tools in Appendix A.
Topic Focus
Cost Escalation Problem If the user has a specic cost escalation problem to solve, the user should read Chapter 3. The user should determine which cost escalation factor is most closely aligned with the problem and then select a strategy or strategies that address the problem. Based on the development phase of interest, the user can determine methods to implement specic strategies covered in Chapters 5, 6, and/or 7. Estimation Tools If the user is interested in nding a specic type of tool, the user should review the list of tools at the beginning of Appen-
dix A. After nding a tool of interest, the user should study the description of the tool under the method that is relevant to the tool. If the user wants to determine where the tool is used, the user can locate the method and tool in the summary section of Chapters 5, 6, and 7.
Summary
Cost escalation, or estimate increases, over the course of project development constitute the major problem that is addressed by this Guidebook. As projects evolve from concept to detailed development prior to construction, this problem is faced by every state highway agency, transit agency, and MPO in the country. Estimation strategies, methods, and tools provide a structured approach for addressing the project cost escalation problem. This Guidebook was developed as part of NCHRP Project 8-49, Procedures for Cost Estimation and Management for Highway Projects during Planning, Programming, and Preconstruction.
CHAPTER 2
Final Design
Construction
Determine the lowest responsive bidder; initiate contract; mobilize; conduct inspection and materials testing; administer contract; control traffic; and construct bridge, pavement, and drainage.
identify projects. In this Guidebook, the project development process begins with the programming phase, in which specic projects are developed and prioritized for inclusion in shorterrange capital programs based on target letting dates for construction. The purpose of planning for both statewide areas and metropolitan areas is to identify the set of the most cost-effective projects and approaches that achieves the stated goals of the planning process. Federal law requires that state highway agencies develop a statewide transportation plan (STP) and that MPOs develop a regional transportation plan (RTP). The horizon year for these long-range plans is usually 25 years into the
future. While some states do identify major projects, or even unique minor projects, most STPs do not identify specic projects, but rather establish strategic directions for state investment in its transportation system. The RTP is very different from the STP. The RTP identies specic projects that are to be implemented over the next 25 years, usually dened in short-, medium-, and long-term implementation stages. Federal law also requires that the statewide and metropolitan plans be consistent and that plan development include the participation of both groups, along with many other stakeholders. A long-range plan is considered to be the output of the planning phase for purposes of this Guidebook.
Figure 2.1. Typical transportation need development phases for highway projects.
Estimate Type Cost Estimation Practice and Cost Estimation Management Purpose
Conceptual Estimation Estimate Potential Funds Needed and Prioritize Needs for Long-Range Plans Cost Estimation Management
Planning Scope [Concepts & Complexity] Planning (Projects) Cost Estimates Cost Estimation Practice Cost Estimates [Recycle Loop] Long-Range Plan
Design Estimation Estimate Baseline Cost for Projects and Program Projects Design Development/Project Conditions (as Design Progresses)
Programming
Priority Program
*
Project Scope [% Milestones & Complexity] Cost Estimation Practice Project Development Process Preliminary Design
Periodic Cost Estimates Design Estimation Estimate Funds for Projects in STIP Cost Estimation Management Changes (Scope/Cost/Time) Cost Estimate Updates for STIP
STIP
Cost Estimation Practice PS&E Estimate Construction Costs to Obligate Funds and Compare with Bid Engineers Estimate Bid Data
PS&E = plans, specifications, and estimates STIP = statewide transportation improvement plan
Figure 2.2. Agency-level ow chart for cost estimation practice and cost estimation management.
10
As depicted in Figure 2.2, cost estimates that are prepared to support these long-range plans have, as their fundamental purpose, to provide a gross estimate of the funds needed over the 25-year planning horizon. These cost estimates are also often used in benet-cost analysis for prioritizing dollars in longrange plans. Planning-phase cost estimates are most often developed using the conceptual estimation method with a costper-mile tool. During the planning phase, cost estimation management is focused primarily on updating planning dollar amounts and determining how these dollars are communicated to the public. The programming and preliminary design phase starts the project development process, as shown in Figure 2.2. In programming, federal law requires the transportation improvement program (TIP) for a metropolitan area to become part of the states transportation improvement program (STIP). It is thus very common for state highway agencies and MPOs to work closely on identifying the likely costs associated with candidate projects. Project cost estimates can have a signicant affect on the overall transportation program and, thus, on the ability of states and metropolitan areas to meet their transportation needs. Thus, estimates prepared during programming are critical in terms of setting a baseline cost, schedule, and scope for managing project development. The baseline cost sets the budget used to develop a 5- to 10-year authorized priority program, as shown in Figure 2.2. Authorization allows for preliminary design to begin, and it typically includes a target date for a construction letting. The rst 3 to 5 years of the priority program form the basis for the STIP. When preliminary design falls within this minimum 3-year period and federal funds are used, the preliminary design cost is included in the STIP. Right-of-way and construction costs will be added to the STIP later, as the STIP is updated regularly. In some cases, if the project needs to be let for construction within 3 years, the entire project cost covering preliminary design, right-of-way, and construction will be included in the STIP. Once preliminary design begins, this baseline cost estimate becomes the basis for cost estimation management. Preliminary design develops the project scope at ever increasing levels of detail, as shown in Figure 2.2 (e.g., the percentage milestones such as 15%, 30%, and 60%). At various times during preliminary design, project cost estimates are prepared to ensure that scope changes have not increased cost above the baseline and for management control of the budget. During preliminary design, design estimation approaches are based on both conceptual estimation and design estimation methods. When the project is within 3 to 4 years of the construction letting, an updated cost estimate is prepared so that current construction costs are reected in the STIP. This estimation is critical because the STIP is scally constrained, and costs for each project in the STIP must be closely monitored.
Cost estimation management is an important activity during preliminary design. Periodic estimation updates should be constantly compared with the project baseline estimate included in the authorized priority program. Further, to effectively manage overall project cost, changes in scope, in design development, and in project site or market conditions must be evaluated in relation to cost and time impact. Cost estimation management is a process for evaluating changes in scope or other issues that affect project cost. The nal design phase typically represents that point in the project development process when plans and specications are nearing completion. Prior to nal approval of the project design, PS&E is initiated, and the engineers estimate is prepared, as shown in Figure 2.2. The basic purpose of this estimate is to provide cost data for comparing bid prices with estimated costs. The estimate provides management with a reference for determining whether a project should be awarded for construction and whether, if a project is awarded, to obligate funds for construction. The engineers estimate is a detailed line-item estimate of project costs based on a schedule of work items and their corresponding quantities. The line items that make up this estimate are the same as those in the contract documents that serve as the basis for bidding the project. Cost estimation management at this phase focuses on comparing the engineers estimate with the current STIP estimate and the contractors bid.
Prepare estimate, including documentation of estimate assumptions, types of cost data, and adjustments to cost data; application of appropriate estimation techniques, parameters, and cost data consistent with level of scope definition; coverage of all known project elements; coverage of all known project conditions; and checking of key ratios to ensure that estimates are consistent with past experience.
Identify and quantify areas of uncertainty related to project knowns and unknowns, potential risks associated with these uncertainties, and appropriate level of contingency congruent with project risks.
Review estimate basis and assumptions, including methods used to develop estimate parameters (e.g., quantities) and associated costs; completeness of estimate relative to the project scope; application of cost data, including project-specific adjustments; reconciliation of current estimates with the baseline estimate (explain differences); and preparation of an estimation file that compiles information and data used to prepare the project estimate.
public. The types of information provided through databases and diverse entities also vary depending on the phase. Cost estimation management is described by a number of steps. Five steps and a general description of each step are provided in Table 2.3. Again, the descriptions are general and, therefore, applicable to the cost estimation management process across each development phase. Implementation of these steps varies by phase. Similar to the cost estimation practice steps, the cost estimation management steps and their descriptions could be shown in greater detail, but five steps are sufficient to provide guidance on cost estimation management. The required number of steps performed in each phase varies. The manner in which the steps are performed also varies depending on the development phase. These variations are reected in the strategies, methods, and tools that are implemented during each phase. Specic graphic depictions of the cost estimation practice and cost estimation management processes are presented and discussed in the introductory sections of the chapters that specically discuss each phase: Chapter 5, Guide for Plan-
ning Phase; Chapter 6, Guide for Programming and Preliminary Design Phase; and Chapter 7, Guide for Final Design Phase.
Summary
Cost estimates are created at various times during project development. There is a relationship and interaction between these phases and the cost estimation practice and cost estimation management processes. During the planning phase, cost projections are developed most often using the conceptual estimation method. Design estimation methods include parametric estimation as well as line-item estimation. Detailed estimates are developed based on the nal design. The appropriate estimation approach will vary with the projects scope denition, design development, and complexity. Chapter 3 identies cost escalation factors and the strategies that a state highway agency can implement in the context of its cost estimation and cost estimation management processes to overcome project cost escalation.
Communication approach is dependent upon the stakeholder who is receiving the information, but should consider mechanism for communicating the cost estimate for its intended purpose, level of uncertainty to be communicated in the estimate given the information upon which it is based, and mechanism to communicate estimate to external parties.
Identify any potential deviation from the existing estimate basis, including changes in project scope; changes due to design development; changes due to external conditions; the nature and description of the potential deviation; and whether the deviation impacts the project budget and/or schedule (potential increase or decrease).
Assess potential impact of change, including cost and time impact of the deviation and recommendation as to whether to modify the project scope, budget, and/or schedule due to change.
Document changes to the baseline estimate, including appropriate approval of the deviation; the new project scope, new budget, and/or new schedule; and notification of the change to project personnel.
13
CHAPTER 3
Before the strategies, methods, and tools are developed to address cost escalation problems, the causal factors that inuence and create changes in cost estimates must be delineated and explained. This chapter rst identies the causal factors and then presents the strategies to address specic problem areas.
When risk is shifted to a party that is unable to control it, project cost will likely increase. The decision regarding which project delivery approach (e.g., design-bid-build, design-build, or build-operate-transfer) and procurement methodology (e.g., low bid, best value, or qualications-based selection) affects the transfer of project risks. In addition to the question of risk allocation, lack of experience with a delivery method or procurement approach can also lead to underestimation of project costs. (Harbuck, 2004; New Jersey DOT, 1999; Parsons Brinckerhoff Quade & Douglas, Inc., 2002; SAIC, 2002; Weiss, 2000) Project schedule changes, particularly extensions, caused by budget constraints, timing of fund allocations, environmental impacts, or design challenges can result in unanticipated increases in project overhead and/or ination. Additional project overhead costs can be incurred by both the state highway agency and the consultants, designers, and contractors. Project schedule changes can be viewed in terms of the time value of money. There are two primary components to the issue: (1) the ination rate and (2) the timing of the expenditures. Many state highway agencies have a xed annual or bi-annual budget, and project schedules must often be adjusted to ensure that project funding is available as needed for all projects. Estimators frequently do not know what expenditure timing adjustments will be made by management or caused by external circumstances. (Committee for Review, 2003; Booz Allen & Hamilton, Inc., and DRI/McGraw-Hill, 1995; Callahan, 1998; Hufschmidt and Gerin, 1970; U.S. General Accounting Ofce, 1999a; Semple et al., 1994; Touran and Bolster, 1994) Engineering and construction complexities caused by the projects location or purpose can make early design work very challenging and lead to internal coordination errors between project components. Internal coordination errors can include conicts or problems between the various disciplines involved in the planning and design of a project. Constructability problems that need to be addressed may also be encountered as the project develops. If these issues are not addressed, cost
3. Project Schedule Changes 4. Engineering and Construction Complexities 5. Scope Changes 6. Scope Creep 7. Poor Estimation 8. Inconsistent Application of Contingencies 9. Faulty Execution 10. Ambiguous Contract Provisions 11. Contract Document Conflicts External 1. Local Concerns and Requirements 2. Effects of Inflation 3. Scope Changes 4. Scope Creep 5. Market Conditions 6. Unforeseen Events 7. Unforeseen Conditions
* Note: these factors are numbered for reference only. The numbering does not indicate a level of influence.
increases are likely to occur. (Committee for Review, 2003; Booz Allen & Hamilton, Inc., and DRI/McGraw-Hill, 1995; Callahan, 1998; Hufschmidt and Gerin, 1970; U.S. General Accounting Ofce, 1999a; Touran and Bolster, 1994; U.S. General Accounting Ofce, 2003; U.S. General Accounting Ofce, 1997; U.S. General Accounting Ofce, 2002) Scope changes, which should be controllable by the state highway agency, but which still happen, can lead to project cost escalation. Such changes may include additions to or deletions from the project scope. Examples of this phenomenon are the addition of a lane to the project scope or increasing the project right-of-way. (Committee for Review, 2003; Booz Allen & Hamilton, Inc., and DRI/McGraw-Hill, 1995; Callahan, 1998; Chang, 2002; Harbuck, 2004; Hufschmidt and Gerin, 1970; Mackie and Preston, 1998; U.S. General Accounting Ofce, 1999a; Merrow et al., 1981; Merrow, 1986; Merrow, 1988; Semple et al., 1994; Touran and Bolster, 1994) Scope creep is the tendency for the accumulation of many minor scope changes to increase project cost. While individual scope changes have only minimal cost effects, the accumulation of these minor changes, which are often not essential to the intended function of the facility, can result in a signicant cost increase over time. Projects seem to often grow naturally as the project progresses from inception through development to construction. These changes can often be attributed on highway projects to the changing needs or environmental compliance in the area being served. (Akinci and Fischer, 1998; Committee for Review, 2003; Booz Allen & Hamilton, Inc., and DRI/McGraw-Hill, 1995; Callahan, 1998; Chang 2002, Harbuck, 2004; Hufschmidt and Gerin, 1970; Mackie and Preston, 1998; U.S. General Accounting
Ofce, 1999a; Merrow et al., 1981; Merrow, 1986; Merrow, 1988; Semple et al., 1994; Touran and Bolster, 1994) Poor estimation can also lead to underestimation, which subsequently translates into increases in project cost as errors and omissions are exposed. Estimation documentation must be in a form that can be understood, checked, veried, and corrected. The foundation of a good estimate is the formats, procedures, and processes used to arrive at the cost. Poor estimation includes general errors and omissions relating to plan details and project quantities as well as general inadequacies and poor performance in planning and estimation procedures and techniques. Errors can be made not only in the volume of material and services needed for project completion but also in the costs of acquiring such resources. (Arditi et al., 1985; Booz Allen & Hamilton, Inc., and DRI/McGraw-Hill, 1995; Carr, 1989; Chang, 2002; Harbuck, 2004; Hufschmidt and Gerin, 1970; Merrow et al., 1981; Merrow, 1986; Merrow, 1988; Pickrell, 1990; Pickrell, 1992) Inconsistent application of contingencies causes confusion as to exactly what is included in the line items of an estimate and what is covered by contingency amounts. Contingency funds are typically meant to cover a variety of possible events and problems that are not specically identied or to account for a lack of project denition during the preparation of planning estimates. Misuse and failure to dene what costs contingency amounts cover can lead to estimation problems. In many cases, it is assumed that contingency amounts can be used to cover added scope, and planners seem to forget that the purpose of the contingency amount in the estimate is lack of design denition. State highway agencies run into problems when the contingency amounts are applied inappropriately. During project execution, contingency funds are often inappropriately used to cover project overruns, instead of being applied to and available for their intended purpose. (Noor and Tichacek, 2004; Ripley, 2004; AACE International, 1997) Faulty execution by the state highway agency in managing a project is one factor that can lead to project cost overruns. This factor can include the inability of the state highway agencys representatives to make timely decisions or actions, to provide information relative to the project, and to appreciate design and construction difculties caused by coordination of connecting work or work responsibilities. (Committee for Review, 2003; Callahan, 1998; Chang, 2002; Merrow et al., 1981; Merrow, 1986; Touran and Bolster, 1994) Ambiguous contract provisions dilute responsibility and cause misunderstanding between the state highway agency and other contractual parties, including design consultants and/or project constructors. Providing too little information in the project documents can lead to cost overruns during the execution of the contract. When the core assumptions underlying an estimation are confused by ambiguous contract provisions, forecast accuracy cannot be achieved. (Callahan,
15
1998; Chang, 2002; State of Alaska, 1994; Harbuck, 2004; Mackie and Preston, 1998; MassHighway and ACEC, 1998; Tilley et al., 1997; Touran and Bolster, 1994) Contract document conflicts lead to errors and confusion when preparing an estimate and cause change orders and rework during project construction. (Callahan, 1998; Chang, 2002; State of Alaska, 1994; Harbuck, 2004; Mackie and Preston, 1998; MassHighway and ACEC, 1998; Tilley et al., 1997; Touran and Bolster, 1994)
for Review, 2003; Booz Allen & Hamilton, Inc., and DRI/ McGraw-Hill, 1995; Callahan, 1998; Chang, 2002; Harbuck, 2004; Hufschmidt and Gerin, 1970; Mackie and Preston, 1998; U.S. General Accounting Ofce, 1999a; Merrow et al., 1981; Merrow, 1986; Merrow, 1988; Semple et al., 1994; Touran and Bolster, 1994) Scope creep from external causes is similar to scope creep from internal causes; however, the former category is usually the accumulation of minor scope changes from external participants. (Akinci and Fischer, 1998; Committee for Review, 2003; Booz Allen & Hamilton, Inc., and DRI/McGraw-Hill, 1995; Callahan, 1998; Chang, 2002; Harbuck, 2004; Hufschmidt and Gerin, 1970; Mackie and Preston, 1998; U.S. General Accounting Ofce, 1999a; Merrow et al., 1981; Merrow, 1986; Merrow, 1988; Semple et al., 1994; Touran and Bolster, 1994) Market conditions or changes in the macroenvironment can affect the costs of a project, particularly large projects. The size of the project affects competition for a project and the number of bids that a state highway agency receives for the work. Inaccurate assessment of the market conditions can lead to incorrect project cost estimation. Changing market conditions during the development of a project can reduce the number of bidders, affect the available labor force, or result in increased commodity prices, all of which can disrupt the project schedule and budget. (Committee for Review, 2003; Booz Allen & Hamilton, Inc., and DRI/McGraw-Hill, 1995; Callahan, 1998; Chang, 2002; Hall, 1980; Mackie and Preston, 1998; U.S. General Accounting Ofce, 1999a; Merrow et al., 1981; Merrow, 1986; Merrow, 1988; Pearl, 1994; Sawyer, 195152; Maryland DOT, 2002; Touran and Bolster, 1994; Woodrow Wilson Bridge, 2002) Unforeseen events are unanticipated occurrences that are not controllable by the state highway agency, such as oods, hurricanes, tornadoes, or other weather-related incidents. Typically, these events are called acts of god. These acts can bring construction to a standstill and have been known to destroy work, thereby creating the need for extensive rework or repair. Events controlled by third parties that are also unforeseen include terrorism, strikes, and sudden changes in nancial or commodity markets. These actions can have devastating impacts on projects and project cost. (Akinci and Fischer, 1998; Arditi et al., 1985; Callahan, 1998; Chang, 2002; Hufschmidt and Gerin, 1970; Merrow et al., 1981; Merrow, 1986; Merrow, 1988; Semple et al., 1994; Touran and Bolster, 1994) Unforeseen conditions are notorious for causing project cost overruns. Unknown soil conditions can effect excavation, compaction, and structure foundations. Contaminated soils may be present, thereby resulting in the need for special mitigation work. Utilities are often present that are not described or are described incorrectly on existing drawings. There are a multitude of problems that are simply unknown during the early project phases and that can increase project cost when they become apparent during construction. (Akinci and
16
Fischer, 1998; Arditi et al., 1985; Callahan, 1998; Harbuck, 2004; Hufschmidt and Gerin, 1970; Merrow et al., 1981; Merrow, 1986; Merrow, 1988; Semple et al., 1994; Touran and Bolster, 1994; U.S. General Accounting Ofce, 1999)
Strategies
The methodology used to develop the potential list of strategies, methods, and tools focuses on the causes of cost escalation and potential strategies that would address these causes. This linkage between the causes of cost escalation and strategies was found in the estimation literature, in an assessment of current practice, and in a review of deciencies found in unique practice approaches. From the literature concerning project cost estimation and from interviews with people in the industry, it is clear that there exist eight overarching or global strategies that can affect the accuracy and consistency of project estimates and costs. As mentioned previously, a strategy is a plan of action intended on accomplishing a specic goal. This denition is used as the basis for developing short statements about each strategy as follows:
Management strategyManage the estimation process
supports estimate accuracy and consistency through all phases of project development. The highest levels of state highway agency leadership have the responsibility to publicly explain how the project development processes works and most importantly to ensure that cost estimation practice and cost estimation management processes are transparent. To produce accurate estimates, state highway agency personnel must be properly trained, there must be established estimation processes, and there must be critical reviews of all estimates. Currently, 40 state highway agencies use only on-the-job training to train their estimators. Twenty-six state highway agencies have no published standard estimation procedures. (Schexnayder et al., 2003) Senior management must take an active role in advancing strategies to increase estimator knowledge and estimate consistency.
external participants and assessing the macroenvironmental conditions that can inuence project costs; Risk strategyIdentify risks, quantify their impact on cost, and take actions to mitigate the impact of risks as the project scope is developed; Delivery and procurement strategyApply appropriate delivery methods to better manage cost because project delivery inuences both project risk and cost; Document quality strategyPromote cost estimate accuracy and consistency through improved project documents; Estimate quality strategyUse qualied personnel and uniform approaches to achieve improved estimate consistency and accuracy; and Integrity strategyEnsure that checks and balances are in place to maintain estimate accuracy and to minimize the impact of outside pressures that can cause optimistic biases in estimates.
Off-Prism Strategy
Use proactive methods for engaging external participants and assessing the macroenvironmental conditions that can inuence project costs. In the case of most projects, engineers focus on technical solutions with little attention to community interest or concerns and often fail to recognize market and macroeconomic changes. These cost drivers are termed off-prism items in the literature because they are not within the roadway prism. The lack of focus on such external issues has been changing as some state highway agencies are experimenting with context-sensitive design and construction. (Neuman et al., 2002; Werkmeister and Hancher, 2001) However, technical alternatives are frequently discussed at early stages of
Management Strategy
Manage the estimation process and costs through all stages of project development. State highway agency leadership can advance an estimation management strategy that fosters and
17
project development before community outreach efforts are undertaken, and concerns related to the external effects are not addressed until later in the development cycle. Lack of public involvement also tends to generate a situation in which those groups who feel concern about the project . . . are inclined to act destructively. (Bruzelius et al., 2002) Additionally, how environmental compliance and the acquisition of right-of-way impacts the public is a consideration when addressing offprism issues. Finally, few state highway agencies ever evaluate the impact of macroeconomic market forces on project cost.
lar, contract documents must be clear and unambiguous as to what must be constructed and what is standard. The documents must clearly state the responsibilities of all parties consultants, contractors, the state highway agency, and third parties. It is critical that all parties involved understand thirdparty involvement in the project construction process.
Risk Strategy
Identify risks, quantify their impact on cost, and take actions to mitigate the impact of risks as the project scope is developed. The actual cost of a project is subject to many variables, which can and will signicantly inuence the probable range of estimated costs. The Census Bureau does not present a single forecast population growth; it offers projections based on different assumptions of fertility, mortality, and migration rates. In the case of state highway agency project estimations, any one cost number represents only one possible result based on multiple variables and assumptions. These variables are not all directly controllable or absolutely quantiable. Therefore, cost estimation must consider probabilities in assessing uncertainties and related risks and translate these risks into costs.
Integrity Strategy
Ensure that checks and balances are in place to maintain estimate accuracy and to minimize the impact of outside pressures that can cause optimistic biases in estimates. The potential for conceptual (e.g., parametric) or even design estimation error can result from pressure by project sponsors who seek the approval of their projects. (Cost/Schedule Controls Task Force, 1986) In a conceptual estimate, judgment replaces straightforward material takeoffs and costing; therefore, it is difcult to justify estimates quantitatively. Estimators must be protected from internal and external pressures to produce estimates that are less than some preestablished budget amount.
Summary
The factors that lead to project cost escalation have been documented through a large number of studies and matched to changes in cost estimates. Each factor presents a challenge to the state highway agency seeking to produce accurate project cost estimates. These factors can be mitigated through the strategies that focus on controlling the possible effects of these factors. Table 3.2 illustrates the link between the strategies and cost escalation factors. This table is further developed for each of the project phases in Chapters 5, 6, and 7. The next chapter, Chapter 4, addresses the framework of this Guidebook and provides guidance for navigating through the Guidebook.
Bias Delivery and Procurement Approach Project Schedule Changes Engineering and Construction Complexities
Scope Changes Scope Creep Poor Estimation Inconsistent Application of Contingencies Faulty Execution Ambiguous Contract Provisions Contract Document Conflicts Local Concerns and Requirements Effects of Inflation Scope Changes Scope Creep Market Conditions Unforeseen Events Unforeseen Conditions
Risk
Internal
External
Integrity
19
CHAPTER 4
Guidebook Framework
Background
This chapter describes the Guidebook framework used to present information contained in Chapters 5, 6, and 7. Each chapter covers a different phase of the project development processplanning, programming and preliminary design, and nal design, respectively. And each phase has unique requirements for cost estimation practice and cost estimation management. Although there is overlap and redundancy in the information presented, the overlap and redundancy is necessary to meet the needs of state highway agency personnel involved in each of the project development phases. The structure and format of Chapters 5, 6, and 7 is the same; however, the content varies depending on the project phase, the project information and data available, and the purpose of cost estimates prepared during that phase.
Based on data collected through interviews with state highway agencies and the literature search, over 30 methods and over 90 tool applications are included in the Guidebook. Implementation of the methods and tools varies depending on the project phase.
project complexity?
Tips for success: What makes the use of the method
successful?
Tools: How is the method applied? This question will be
addressed in Appendix A.
20
Cost Estimating and Cost Estimating Management Strategies
Project Complexity
Cost Estimating and Cost Estimating Management Methods Cost Estimating and Cost Estimating Management Tools
Figure 4.2. Strategy, method, and tool example. Table 4.1. Chapter structure.
Sections Guide for Project Phase Content Cost estimation practice and cost estimation management flow chart for project phase Relationship matrix between cost escalation factors and strategies for project phase Methods and tools for implementation to address cost escalation Application of methods for relevant strategies Tools to implement methods
Strategies (1 through 8)
Input
Step
Denotes all action/process steps in the flow charts such as preparation of estimates, review of estimates, and risk analysis. Denotes the documents resulting from the preceding action step(s). They can be different types of estimates, such as the baseline estimate or the state transportation improvement plan estimate.
Document
Milestone
Denotes a milestone in the system, which can relate to a significant point in development. The milestone may require meeting criteria for further actions or repeating the preceding steps.
Decision
Denotes a decision where a binary verdict automatically directs the process to continue on either of the available options based on requirements. This can be a simple gate with a go or no-go decision.
Phase
Represents the different phases of project development. This symbol is placed on the right side of each flow chart.
Each chapter discusses the eight strategies as applicable to that phase together with identied methods that are applicable to each strategy. Subsequently, the tools for each method are listed with the method. Tools often support multiple methods. The methods are sorted alphabetically and numbered with an alphanumeric numbering system for methods within the same alphabet heading. As a consequence, tools are referenced by an alphanumeric codefor example, Tool B1.1 is Tool 1 under Method B1. All tools are found in Appendix A (i.e., the Tool Appendix).
What are examples or applications of the tool? What tips will lead to successful use of the tool? Where can the user nd more information to support devel-
opment of a specic tool? A table of contents is provided at the beginning of Appendix A to guide the user to the location of the tool description in the appendix. The table of contents is arranged by the method name sorted alphabetically with an alphabet-serial number coding pattern. The tools are then listed alphabetically under each method with a serial number sufx to the method code (e.g., B1.1 is Tool 1 under Method B1, and C2.3 is Tool 3 under Method C2).
Tool Appendix
The Tool Appendix describes all the tools referenced for each method in Chapters 5, 6, and 7. The common informational structure for describing each tool is the following:
Summary
A common framework is used in Chapters 5, 6, and 7 to describe cost estimation practice and cost estimation management methods. This framework is structured around factors that can lead to cost escalation and the strategies that address these factors.
What is the tool? What is the tool used for and why is the tool used? What does the tool do or create? When should the tool be used?
22
CHAPTER 5
Introduction
For both states and metropolitan areas, the purpose of transportation planning is to identify a set of the most costeffective projects and approaches that achieve the stated system goals. Federal law requires that state highway agencies develop a statewide transportation plan and that MPOs develop a regional transportation plan (RTP). The horizon year for these long-range plans is usually 25 years into the future. Approaches, or at least terminology, for statewide transportation planning vary across the country. While some states identify major projects, or even unique minor projects, most statewide transportation plans (STPs) do not identify specic projects, but rather establish strategic directions for state investment in the transportation system and present future challenges that could constrain the ability of the state highway agencies to improve the performance of their systems. Statewide plans also often identify areas of the state where more detailed planning is required. One of the more common approaches to providing such focused planning is through corridor or subarea studies. These targeted study efforts usually identify specic projects and their associated costs that are considered during the programming process, when projects are prioritized. The RTP is very different from the STP. The RTP identifies specific projects that are to be implemented over the next 25 years, usually dened in short-, medium-, and long-term implementation stages. Thus, for example, in a typical RTP, one would nd projects that the agency expects to implement in the next 5 years, in the next 5 to 15 years, and in the next 15 to 25 years. Federal law requires the RTP to be scally constrained; that is, the sum of the total project costs in the plan cannot exceed the amount of funding that is expected over the next 25 years. This limit places great importance on having valid and realistic cost estimates for the projects in the MTOs plan. Federal law also requires that the statewide and metropolitan plans be consistent and that plan development include the participation of the state; the MPO; and many other stakeholders, such as local government agencies. Planning-level cost estimates
can have a signicant effect on the overall transportation program and, thus, on the ability of the state highway agency and MTO to meet their area transportation needs. The term conceptual estimation is often used to describe the general method of estimating project costs during the planning phase. As indicated above, the role of cost estimation varies by whether one is developing a statewide plan or a metropolitan plan. However, it is important that, from the beginning of the planning process and through all planning and project development phases, the overall approach and management philosophy toward cost estimation (e.g., year-of-construction dollars, treatment of project risks, and quality control procedures) be consistent. Figure 5.1 provides an overview of the cost estimation practice and cost estimation management processes that can provide input into transportation planning and project-level planning. The level of cost estimate detail will likely vary between estimates prepared for transportation planning and those prepared for project-level planning and could easily vary from one jurisdiction to another. Cost estimates that are prepared during planning have, as their fundamental purpose, to provide an order-of-magnitude estimate of the anticipated funds needed to support long-range plans. These cost estimates are also often used in benet-cost analysis for ranking projects and including them in the 25-year planning horizon. Key inputs into the cost estimation practice and cost estimation management processes are, where applicable, project scope and type, major project parameters, project complexity based on location, and anticipated size. Three sources of information and data on these inputs usually characterize the cost estimation process. The rst of these is third-party stakeholders. For the development of estimates during the planning process, this source of information is usually the most common. The second major source of cost estimation information comes from the planning or engineering staff. For example, when soil conditions require costly design solutions, geotechnical engineers should be consulted because they can
23
Transportation Need Development Phase Needs/Deficiencies
Determine Estimate Basis (Scope/ Location) Input from Third Parties Input from Disciplines
Historical Data
Legend
Input Step
Database
(Recycle Loop)
Document
Milestone
Phase
LONGRANGE PLAN
Figure 5.1. Cost estimation practice and cost estimation management during planning.
provide input based on experience even if they cannot conduct extensive soil tests at this stage of need development. Historic cost data from similar works is the nal source of cost estimation input. Because little if any engineering has occurred prior to the planning process, most estimates at this
stage rely heavily on cost data from past works. The historical data form the basis for the conceptual cost estimates prepared during planning. The cost estimation process is frequently iterative in that initial cost estimates are prepared and used in the planning
PLANNING
24
process to form investment decisions. These same cost estimates become the point of departure for cost estimates prepared during programming, which are necessary when projects are placed in a state transportation improvement program (STIP), and are then further refined as projects make their way through preliminary design and final design. Because cost estimates used for the planning process include considerable uncertainty, it is incumbent upon engineers and planners to understand the likely range of uncertainty associated with these cost estimates and to communicate this level of uncertainty to decisions makers (i.e., managers).
Methodology
This chapter is organized around the cost escalation factors and strategies presented in Chapter 3. A familiarity with the denitions of identied cost escalation factors and strategies is helpful in understanding the methods described in this chapter. Table 5.1 provides a link and quick reference between cost escalation factors and strategies to address estimation issues during planning. The table can be used to select appropriate strategies when systematic cost escalation problems are found in an agency. The remainder of this chapter describes methods
for the application of the strategies, and Appendix A provides information on the tools used with each method. The strategies address cost escalation issues that arise early in planning. All of the strategies can address at least a portion of the cost escalation factors in the earliest development phases. As seen in Table 5.1, the management, scope and schedule, offprism issues, and risk strategies address a large number of cost escalation factors. These strategies can and should be applied in the early stages of planning and continued throughout the project development process. The integrity strategy is also important in dealing with bias that can occur when projects are being developed without a denitive scope. The delivery and procurement strategy is only applied on those projects in which early decisions about procurement methods will be made. Generally, this strategy is not applicable during planning. The document quality and estimation quality strategies have less impact during planning than in the later phases of the project development process. However, these strategies can begin to be applied, particularly when consultants are being used, as is often the case, to develop concepts and related cost estimates. The faulty execution cost escalation factor is not considered an issue during planning. This factor is of greater concern during the project development process.
Table 5.1. Link between strategies and cost escalation factors in the planning phase.
Strategies
Scope and Schedule Document Quality Off-Prism Issues Estimate Quality 5.7 Management Delivery and Procurement
Section Bias Delivery and Procurement Approach Project Schedule Changes Engineering and Construction Complexities
5.1
5.2
5.3
5.4
Risk
5.5
5.6
5.8
Scope Changes Scope Creep Poor Estimation Inconsistent Application of Contingencies Faulty Execution Ambiguous Contract Provisions Contract Document Conflicts Local Concerns and Requirements Effects of Inflation Scope Changes Scope Creep Market Conditions Unforeseen Events Unforeseen Conditions
Internal
External
Integrity
25
Methods and tools presented in Chapter 6 but not presented in this chapter could be used during planning if the state highway agency deems them appropriate to their culture and environment. Further, if the state highway agency must estimate a single project rather than a group of projects during the planning phase, the state highway agency is encouraged to examine the methods and tools in Chapter 6 in addition to those in this chapter.
The budget control method is an essential element in the recycle loop shown in Figure 5.1. A variance report of cost and schedule tool is necessary to control the budget in this loop. Estimates are based upon little more than a summary of key project scope characteristics at this point, but these characteristics and changes to them need to be tracked during the evolving scope denition process. Project Complexity
There is a greater need to control the budget of complex projects due to the detrimental impact this type of project can have on an agencys total program. Rising cost estimates for larger projects could ultimately affect many other projects, causing them to be down-scoped or be cancelled altogether. The budget by corridor tool provides agencies with an approach to control their budgets on complex projects by making cost-benet tradeoffs to the entire system rather than focusing on particular projects. Tips for Success To control a budget successfully, a disciplined cost estimation and monitoring system must be established early in planning and be used continually until a project is constructed. Budget Control must be an active endeavor rather than a passive attempt.
Budget Control
B1.1 B1.2 B1.3 B1.4 B1.5 Budget by Corridor Constrained Budget Standardized Estimation and Cost Management Procedures Summary of Key Scope Items (Original/ Previous/Current) Variance Reports on Cost and Schedule
Communication
C1.1 C1.5 C1.6 C1.7 C4.5 C4.6 Communication of Importance Proactive Conveyance of Information to the Public Simple Spreadsheet Year-of-Construction Costs Major Project Estimation Guidance Standardized Estimation and Cost Management Procedures Complexity Definitions ContingencyIdenfitied
Consistency
Risk Analysis
26
Tools B1.1 Budget by Corridor B1.2 Constrained Budget B1.3 Standardized Estimation and Cost Management Procedures B1.4 Summary of Key Scope Items (Original/Previous/Current) B1.5 Variance of Reports on Cost and Schedule
Tips for Success Communication among all of the involved parties regarding expected project costs substantially increases the level of information associated with all of the projects being considered. Hopefully, this communication will lead to fewer surprises later in project development. Communication should include both verbal and nonverbal methods. Early stakeholder involvement with the project promotes ownership of the project that could possibly lead to increased acceptance. When possible, estimates, especially during planning, should be communicated as ranges of costs, because it is nearly impossible to predict accurately nal costs with the limited information that is available in this phase. If point estimates are required, estimators must be cautious about including an appropriate contingency. Finally, always communicate estimates in inated year-of-construction costs to all internal and external stakeholders to avoid any confusion or discrepancies in the later estimates. Tools C1.1 C1.5 C1.6 C1.7 Communication of Importance Proactive Conveyance of Information to the Public Simple Spreadsheet Year-of-Construction Costs
5.1.2 Communication
Why? Because cost estimates used during the planning process can have such signicant implications to the rest of the proposed investment program, it is important that the different organizations involved with planning, as well as units within these organizations, effectively communicate with each other during the cost estimation process. Because it is the policy boards and commissions of the transportation agencies that most often approve investment programs, it is important that the underlying uncertainties associated with the cost estimates be conveyed to these ofcials as well. This communication must center on the importance of the estimate and the condence that the agency has with the estimate. What will this estimate be used for? If the estimate is being used in a feasibility study, its accuracy will be less important than if the estimate is used for establishing a project budget as part of the programming process. Communication can occur continuously as necessary in the recycle loop shown in Figure 5.1, but the estimators must be cautious about sharing incomplete estimates with stakeholders and even with their counterparts within the agency. If the estimate is to be shared with external stakeholders or will be used for executive management decision making, it should go through a rigorous and appropriate review process. Communication relating to project estimates could include such factors as project engineering and construction complexities, local government concerns and requirements, the signicance of the project, and the required accuracy of an estimate at the particular point in the process. The availability of information through project les, including documentation and agency forms that are available to agency staff and to the public, will help to address questions that might be asked later during project development. The communication method is also discussed in Section 5.2.2. Project Complexity The more complex projects become, the greater the need for communication both within the agency and with external participants. The need to communicate the uncertainty surrounding the cost estimation also increases. As one might expect, larger and more complex projects typically include greater design uncertainty.
5.1.3 Consistency
Why? An estimate is a permanent document that serves as a basis for business decisions. It must be in a format that can be understood, checked, veried, and correctedthere must be consistency. Consistency ensures that estimates are prepared following a single standard. Estimate consistency is important, even as early as planning, because estimates are easier to review and revise when they are prepared in a similar manner. Consistency is achieved by instituting standards that serve as a guide for cost estimation practices and cost estimation management. Agency management should ensure that the agencys planners, or others involved in preparing planning estimates, follow standard practices and use procedures that are documented. In Figure 5.1, the consistency method inuences each step in the process and the types of information used to prepare planning-level estimates. Project Complexity At the planning level, estimates may be required for major projects or corridors. Specialized guidance is required for these larger and more complex facilities. Sound cost management practices are also needed because these major facilities are evaluated throughout the planning phase.
27
Tips for Success Adequate knowledge of agency procedures and practices is important for this method to be successfully implemented. When different organizations or agencies are involved in planning, common procedures must be implemented for consistency to be achieved. When this method is implemented during planning and carried forward into the project development process, improved estimation accuracy can be achieved over time. Tools C4.5 Major Project Estimation Guidance C4.6 Standardized Estimation and Cost Management Procedures
5.2.1 Buffers
Why? Buffers are designed to protect the estimators and project team against external and even internal agency inuences that can cause the misrepresentation of project scope, estimate, and schedule. Buffers are used as a means to ensure integrity in the processes of developing and tracking the project scope, estimate, and schedule. Buffers are important in the re-estimation of costs as projects proceed through development and also in obtaining appropriate approvals. For estimators to act objectively and create
28 Table 5.3. Planning phase scope and schedule strategy: Methods and tools.
SCOPE AND SCHEDULE STRATEGY
Formulate definitive processes for controlling project scope and schedule changes
Buffers
B2.1 B2.2 B2.3 C1.1 C1.2 C2.1 C2.3 C2.4 Board Approvals Constrained Budget Management Approvals Communication of Importance Communication of Uncertainty Agency Estimation Software In-House Conceptual/Parametric Estimation Software Simple Spreadsheet
Communication
Computer Software
accurate estimates, they must be shielded from pressures to make unrealistic cost estimates. Project Complexity High-prole projects may be more susceptible to manipulative pressures. Such pressures are typically present with the larger, more complex projects that affect a larger number of people or projects that have a greater impact on the environment. However, the use of buffers at some minimum standard should also be considered for smaller, less complex projects. Tips for Success The successful use of buffers requires a minimum standard on all projects. However, more extensive protection features should be developed for projects judged by the agency to be of greater vulnerability. Projects should be continuously monitored for indications of increased demands to maintain a xed estimate amount. Such demands are a sure indicator that there is a need for added buffer protection. Tools B2.1 Board Approvals B2.2 Constrained Budget B2.3 Management Approvals
estimate, and schedule uncertainty will help project participants understand the project and the confidence that can be placed in project cost estimates. Communication about the importance of the project and the accuracy of the estimate reduces confusion as the project moves into the project development process and as it establishes the need to develop the project scope, schedule, and estimate to appropriate standards. To manage the project scope and schedule, estimators must clearly communicate the level of uncertainty associated with project cost estimates, especially those in the very early stages of planning. All too often, a cost estimate for a project or design component is quickly produced as a feasibility estimate, but then is later kept as part of the budget decisions as if it were an accurate prediction of cost. Planners must clearly communicate the importance and uncertainty of estimates. Project Complexity As projects become more complex, the need to maintain communication among all project participants increases. While larger projects require more extensive communication efforts, a minimum effort and standard should be set for smaller and less complex projects. Tips for Success The successful application of communication methods requires the involvement of all project participants, including MPOs, local government agencies, and the public. Success in project cost estimation is dependent on the lines of communication remaining open, honest, and forthright.
5.2.2 Communication
Why? As discussed in Section 5.1.2, communication is very important during planning. Communication regarding scope,
29
occur from the earliest planning phase and throughout the project development process. Tools C2.1 Agency Estimation Software C2.3 In-House Conceptual/Parametric Estimation Software C2.4 Simple Spreadsheet
5.3.1 Communication
Why? Communication is a critical key to project development success. The communication of off-prism issues both within the agency and with outside parties can eliminate some of the problems that may be faced later in project development. Early communication can help manage the issues themselves, provide information to parties that will participate later in the project development process, and provide a general awareness to all involved. Project Complexity Projects of all levels of complexity should benet from identication, management, and communication of relevant off-prism issues. Tips for Success Early introduction of communication regarding off-prism issues will increase the likelihood of project success. Inclusion of all parties that may be remotely involved in any off-prism issues encountered during project development should occur early in planning. This will help eliminate resentful actions that could occur as a result of parties believing that they were excluded intentionally.
Table 5.4. Planning phase off-prism issues strategy: Methods and tools.
OFF-PRISM STRATEGY
Use proactive methods for engaging external participants and assessing the macroenvironmental conditions that can influence project costs
Communication
C1.4 C1.5 Definitive Management Plan Proactive Conveyance of Information to the Public
30
Tools C1.4 Denitive Management Plan C1.5 Proactive Conveyance of Information to the Public
endeavor into the project development process will increase the effectiveness and accuracy of cost estimates. Tool I3.2 Percentage of Total Project Cost
Identification of Risk
I2.1 Red Flag Items
Risk Analysis
R3.1 R3.2 R3.4 R3.5 Analysis of Risk and Uncertainty ContingencyIdentified Estimate Ranges Programmatic Cost Risk Analysis
Right-of-Way
R2.2 Advanced Purchase (Right-of-Way Preservation)
31
and team studies or historical checklists should be used on less complex projects. Tips for Success An agency might consider developing a standard form, based on project complexity or type, that identies common risks that should always be considered as a project is being developed. These lists would prompt the involved parties to identify and consider specic project risks. Decisions on what to do about the risks should be considered later in the project development process. Tool I2.1 Red Flag Items
only right-of-way acquisitions, and, as a result, these staff do not have resources to support project planning or to develop tools for developing long-range right-of-way estimates. Poor right-of-way cost estimates can have signicant impacts on estimation accuracy. Tool R2.2 Advanced Purchase (Right-of-Way Preservation)
5.4.2 Right-of-Way
Why? Right-of-way issues are often a major cause of escalating project costs. By identifying and addressing the risks associated with right-of-way issues and values early in project development, it is possible to correctly estimate these costs. As shown in Figure 5.1, right-of-way estimates should involve input from the agencys right-of-way and real estate services section and must be continuously revisited as the scope is recycled through planning and later through the project development process. Project Complexity Project complexity is not always a good indicator of potential right-of-way issues. In the case of project overlays or projects using a similar type of right-of-way, requirements are often minimal; however, projects that involve new alignments or require a greater amount of additional right-of-way acquisition are likely to have higher risks. This problem is not necessarily limited to urban areas; rural areas also experience increases in land values and opposition to property takings. Tips for Success A key to success is to involve the right-of-way and real estate service sections of the agency actively and early in planning and keep them involved as project scope iterations occur. The specialized knowledge found in the right-of-way and real estate service units can provide a strong basis for cost estimates and for identifying potential problems. Another key to success is to educate right-of-way and real estate service staff on the importance of project planning estimates and provide them with resources to perform riskbased estimation. All too often, the duties of these staff involve
32
Tools R3.1 R3.2 R3.4 R3.5 Analysis of Risk and Uncertainty ContingencyIdentied Estimate Ranges Programmatic Cost Risk Analysis
For example, large projects can be designated as designbuild as early as planning. Eventually, when the project is programmed, the design-build contractor will commit to a lump sum price for a project before design is complete and therefore take on nontraditional risks. These risks must be accounted for in the cost estimate. The state highway agency will, in turn, benet from cost certainty earlier in the project development process because the design-build contractor will be committed to this price very early. Planners can begin considering the project packaging in terms of single or multiple contracts during planning. If multiple contracts are used, the dollar value of a single contract may decrease, so the contractor may have less risk to price. Smaller contracts tend to encourage a greater number of bidders and can reduce costs if the market conditions are right. If these decisions are made in planning, the state highway agency must remain consistent with them during the subsequent phases of the project development process or they could risk substantial cost escalation, as documented in Chapter 3 of this Guidebook. Project Complexity
Project size and duration are perhaps the best indicators of complexity for project delivery and procurement decisions. Larger projects may require a greater effort to adequately identify the potential risks and how these risks will impact project costs in relation to proposed project delivery and procurement methods. If project delivery and procurement methods are selected to accelerate construction on any size project, then the use of the risk strategy must account for the potential impact of acceleration. Tips for Success Risk analysis should be closely tied to any alternative project delivery and procurement strategies. The risk strategy should include an evaluation of the impact that project delivery and procurement methods have on cost. Additionally, any project delivery or procurement decisions made during planning must remain consistent throughout the latter phases of project development, or their impact must be accounted for in the state highway agencys cost estimation management systems.
Table 5.6. Planning phase delivery and procurement strategy: Methods and tools.
DELIVERY AND PROCUREMENT STRATEGY
Apply appropriate delivery methods to better manage cost because project delivery influences both project risk and cost
33
not the same, so a method for handling exceptions needs to be built into the system. The software should allow for the incorporation of additional information, even if the information is not required until a later stage of project development. Tools C2.1 Agency Estimation Software C2.4 Simple Spreadsheet
Table 5.7. Planning phase document quality strategy: Methods and tools.
DOCUMENT QUALITY STRATEGY
Promote cost estimate accuracy and consistency through improved project documents
Computer Software
C2.1 C2.4 Agency Estimation Software Simple Spreadsheet
Identifying Off-Prism Issues I3.1 I3.2 Environment Assessment Percentage of Total Project Cost
34
therefore, documentation is vital in reducing the need to repeat estimation efforts. Tips for Success To be successful, the documentation of the estimate basis and assumptions needs to be consistent throughout the agency. Consistency can be achieved by developing a set of forms or a manual that outlines the documentation requirements. Additionally, both the base estimate and the incorporated contingency amount must be documented to properly communicate the accuracy of the estimate. Tool D4.1 Project Estimation File
management should be accomplished quickly because most of these types of issues have or will have political implications. Tools I3.1 Environmental Assessment I3.2 Percentage of Total Project Cost
35 Table 5.8. Planning phase estimate quality strategy: Methods and tools.
ESTIMATE QUALITY STRATEGY
Use qualified personnel and uniform approaches to achieve improved estimate consistency and accuracy
Computer Software
C2.1 C2.3 C2.4 Agency Estimation Software In-House Conceptual/Parametric Estimation Software Simple Spreadsheet
Conceptual Estimation
C3.3 C3.4 C3.5 E2.1 E3.3 P2.1 P2.2 R2.1 R2.2 R2.4 R2.5 Cost/Parameter Using Similar Projects Cost/Parameter Using Typical Sections Trnsport Expert Team In-House/Peer Estimation Checklist Scoping Document Acres for Interchange Advanced Purchase (Right-of-Way Preservation) Relocation Costs Right-of-Way Estimator Training
Right-of-Way
different levels of information detail and quality become known. Tips for Success Each estimator needs to be knowledgeable of the range of estimation tools available and be able to make an informed decision regarding the most appropriate tool to use in estimating a specic project. The estimator needs to have adequate information available for developing each project estimate or needs to have some basis for making reasonable assumptions. Assumptions need to be documented for later review, justication, and revision. Tools C3.3 Cost/Parameter Using Similar Projects C3.4 Cost/Parameter Using Typical Sections C3.5 Trnsport
36
will vary depending on the type of project and its size and complexity. In Figure 5.1, an estimate review is positioned after the project risk has been quantied and an appropriate contingency amount is included in the estimate. While this review is depicted as a single activity, it would normally be repetitive, taking place to some extent whenever a planning-level estimate is revised. Project Complexity At the planning phase, only cost estimates for large projects or corridors in urban areas that are extremely complex will be subjected to an external review by qualied professionals. There may be certain critical elements of these estimates that require a unique expertise to verify estimated costs. This external review should include the results of a risk analysis that identies the risks associated with these critical elements, the high and low cost limits for each critical element, and the assigned probability that the risk will occur. Tips for Success Knowledgeable and experienced individuals who are independent of the project team must conduct this review. The review must closely examine the assumptions that form the basis of the estimate and the scope that is used to prepare the estimate of all critical elements. Tool E2.1 Expert Team
Project Complexity The extent of the estimate review at this stage will vary depending on the type of project and project complexity. As project complexity increases, the reviewer or review team must devote more attention to probing the assumptions that form the basis of the estimate and ensuring that the scope is covered to the extent possible. Tips for Success To be successful, the review must closely examine the assumptions that form the basis of the estimation, and knowledgeable and experienced individuals from within the state highway agency must conduct the review. Conducting reviews at an appropriate time during the development of planning estimates provides some assurance that the estimates are reasonably accurate for the scope and site conditions known at the time. Tool E3.3 In-House/Peer
37
should be included in the estimate. The forms are a graphic view of what has changed since the previous estimate was completed. Tools P2.1 Estimation Checklist P2.2 Scoping Document
Tips for Success The success of implementing additional right-of-way cost efforts is dependent in part on the inclusion of experts from the right-of-way and real estate service sections of the agency. This is particularly important during planning, as there are often issues relating to land value market condition projections that are beyond the expertise of project developers and that should be part of the scope alternatives discussion. Rightof-way estimators must be conscious of escalating costs to the point at which right-of-way will be purchased in the project development process. They must realize that (1) right-of-way can be purchased early in some circumstances and (2) rightof-way is typically purchased before construction begins and should not be escalated to the midpoint of construction like the rest of the estimate. Additionally, these specialists need to be provided with training and resources to develop long-range right-of-way estimates. Tools R2.1 R2.2 R2.4 R2.5 Acres for Interchange Advanced Purchase (Right-of-Way Preservation) Relocation Costs Right-of-Way Estimator Training
5.7.6 Right-of-Way
Why? Early efforts in identifying right-of-way costs can greatly improve the quality of an estimate. Right-of-way costs are often a signicant unknown for planning-level estimates. History has shown that the potential cost of land acquisition can be much higher than predicted, especially when cases go to court for judgment. The ancillary costs of land acquisition, including appraisals, negotiations, consultants, court fees, potential judgment, and others, can be substantial and often have a great amount of uncertainty. In extreme cases, judgments can occur years after the project has been built and can require large program adjustments to compensate. Early identication and inclusion of accurate right-of-way costs in initial estimates will avoid difculties later in project development process phases. As stated in Section 5.4.2, the involvement of right-of-way and real estate services staff with adequate resources is imperative to producing an accurate estimation. Right-of-way costs should also be considered carefully in the Risk Strategy. Project Complexity Projects that require little or no additional right-of-way will not need to consider higher levels of effort in estimating rightof-way cost. However, projects that require the purchase of more than the minimal amounts of right-of-way should benet from increased efforts aimed at quantifying right-of-way cost. Right-of-way issues are not necessarily reliant on complexity, nor are they only a concern reserved for urban projects.
Computer Software
C2.1 C2.4 Agency Estimation Software Simple Spreadsheet
38
applied in the base estimate, contingency estimate, or approval tasks shown in Figure 5.1. Such identication helps in recognizing errors and the existence of bias. One way to maintain estimation integrity is to control the bias that can be introduced into the estimation process. Computers are immune to pressures to introduce bias into the estimate and will use the appropriate values such as average unit cost without feeling the need to change the value to appease others. The use of computer software is also discussed in Sections 5.2.3, 5.6.1, and 5.7.1. Project Complexity The use of computer software as a method to increase project estimation integrity even at early stages is important. However, the need increases as project size and complexity increases. Higher-prole projects are often subject to increased integrity problems as pressure increases both within the agency and from external sources to meet a desired project budget. Tips for Success The availability of estimation software to consultants, MPOs, and the planning department of the state highway agency will help to increase the likelihood that appropriate values are used throughout project planning and later during the development process. Training personnel and consultants on the appropriate use of software will improve the integrity of the estimates. Tools C2.1 Agency Estimation Software C2.4 Simple Spreadsheet
5.9 Summary
Table 5.10 lists all of the methods and tools presented in this chapter for possible use in planning. This list can be used as a quick reference to navigate directly to Appendix A for detailed descriptions of the tools. Tools are listed in Appendix A alphabetically by method as shown in Table 5.10. Table 5.10 can be used as a checklist for an agency estimation department or for project planners responsible for producing planning cost estimates. The checklist forms a self-assessment tool for agencies to benchmark against. The methods and tools were found in highway agencies throughout the country. While no one agency was found to use all of the methods and tools, all methods and tools are used and have the potential to be applied by any one agency.
39
CHAPTER 6
40
COST ESTIMATION PRACTICE AND COST ESTIMATION MANAGEMENT
Project Development Process
ESTIMATION MANAGEMENT
Project Scoping 5-25% Design Project Complexity Project Milestone 15%, 30%, 60%, and 80% Design Project Complexity
Priority Program
PROGRAMMING
*
Design Development/Project Conditions
Market Conditions
Legend
Input Step
STIP
*
NO IMPACT
PRELIMINARY DESIGN
NO
Potential Change?
YES
Database Document
NO IMPACT
NO
Communicate Approval
Decision Project Estimates Phase
Approve Change?
YES
Communicate Approval
Is Estimate on Budget? NO
YES
*represents the dynamic nature of the milestone dependant on the practices of the state highway agency
Communicate Approval
signicant changes in terrain) and the relative magnitude of projected cost. Sufficient scoping should be completed to determine the potential cost impact of right-of-way requirements; utility relocations; environmental mitigation; and public, local government agency, and legislative involvement. Programming estimates are typically developed using parametric or historical bid-based tools in combination with historical percentages for certain elements. In some cases, data from past projects that are similar to the one being estimated can serve as a basis for line-item estimates or costbased estimates. The complexity of the project often drives which estimation method or combination of methods might be best used.
Preliminary design for a project begins at the point in time specied in the priority program. During preliminary design, the project scope is developed in greater specicity. Project cost estimates are often prepared at various times during this time. These estimates often correspond to design milestonessuch as 15%, 30%, 60%, and 80% design completionas delineated in Figure 6.1. These cost estimates can be developed using historical unit cost line-item estimation tools. As design advances, the use of line-item, bid-based estimation is usually more common, but the use of cost-based estimation with a bottom-up approach is often required for major projects. Using historical unit cost data from past or current projects similar to the one being estimated is another cost estimation tool that can be used
41
during preliminary design. The estimator must be careful that the specic tool or tools used t the scope and complexity of the project and time available for preparing the estimate. When the project is within 3 or 4 years of the construction letting date, the cost estimate is rened so that right-of-way and construction can be included in the STIP or so that the STIP budget for these major categories can be updated. This estimate is critical because the STIP is scally constrained and the cost for each project in the STIP must be closely monitored. During preliminary design, cost estimation management is a critical component in achieving accurate estimates. As the design is developed, successive updated cost estimates should be compared to the baseline cost and any changes communicated to the design disciplines. These changes must also be communicated to agency management. As a project moves through programming and into preliminary design, there must be a reevaluation of scope and design based on any additional knowledge related to the project site, market conditions, or the macroenvironment. The ow chart segment on the right side of Figure 6.1 shows three steps and two decision points that are important to managing the budget and identifying potential changes to the baseline budget. Changes could result in potential increases in the budget due to, for example, needed scope additions or design developments. Alternatively, changes could result in a potential decrease in the budget due to, for example, a lower estimated quantity. If the project is under the baseline cost, this should also be identied. Timely reaction to potential project changes and to information on the cost and time impact of changes allows management to better manage project funds and keep external constituencies informed about project status. This timely reaction to changes is especially critical when increased funding is required. The preliminary design effort concludes when the plans and specications are sufciently complete to commence preparation of construction documents for advertising the project. This nal design phase initiates the preparation of the engineers estimate during PS&E development (see Chapter 7).
ing the specic strategies of interest. Detailed information about specic tools can be found in Appendix A. During the programming and preliminary design phase, the availability of additional project information and an enhanced level of scope denition support more detailed and accurate project estimates. The strategies and methods applied in this chapter emphasize improving estimation accuracy by properly identifying major cost items and then using appropriate quantitative analysis techniques to provide consistent estimates throughout design. Strategies and methods to manage costs as design develops are integral to successfully achieving project cost targets. Table 6.1 identies the strategies that may be implemented to address specic cost escalation factors. Further, once a strategy is selected, the user has a choice of methods, classied as either cost estimation management or cost estimation practices, which are briey described in each section of this chapter. Next, the user is guided to a set of tools for each method. The tools are further discussed in detail in Appendix A. The methods and tools discussed in the context of the eight strategies under the programming and preliminary design phase are considered appropriate for this phase. Methods and tools presented in this chapter and not covered in Chapters 5 or 7 could be used during the other phases if the state highway agency deems them an appropriate t within their culture and environment.
Methodology
This chapter addresses cost estimation practice and cost estimation management practices as applicable to the programming and preliminary design phase of project development. The denition of cost escalation factors and strategies described in Chapter 3 are applicable to this chapter. These denitions aid state highway agencies in recognizing those cost escalation factors that are particularly problematic during the programming and preliminary design phase. Table 6.1 can be used to determine which strategies provide solutions to address the cost escalation problems of concern. Chapter 6 suggests methods and tools that are available for implement-
42 Table 6.1. Link between strategies and cost escalation factors during a project programming and preliminary design phase.
Strategies
Scope and Schedule Document Quality Off-Prism Issues Estimate Quality 6.7 Management Delivery and Procurement
Section Bias Delivery and Procurement Approach Project Schedule Changes Engineering and Construction Complexities
6.1
6.2
6.3
6.4
Risk
6.5
6.6
6.8
Scope Changes Scope Creep Poor Estimation Inconsistent Application of Contingencies Faulty Execution Ambiguous Contract Provisions Contract Document Conflicts Local Concerns and Requirements Effects of Inflation Scope Changes Scope Creep Market Conditions Unforeseen Events Unforeseen Conditions
Internal
External
Hence, appropriate evaluation of the impact of such factors must be incorporated into the cost estimation management process. Scope changes are primary contributors to cost escalation, and these changes have to be monitored closely as design detail evolves. The budget control method is employed based on different levels of approvals required for a project to proceed. This method also seeks to periodically identify potential deviations and to assess if a project is on track when compared with the baseline budget. As potential deviations are identied, an assessment of their impact on project costs and time are evaluated to determine whether these changes should be approved by management. Timely identication of the impact of potential changes allows project and agency management to make decisions on how best to use the funds allocated to the project and to the overall program of projects. Project Complexity It is essential to monitor and control budgets during preliminary design, regardless of the project complexity. Cost overruns on a number of small projects can translate into program-level overruns. Budget overruns on larger and more
costly projects are often more visible to stakeholders and may result in unwanted scope reduction or undesirable requests for additional funds. Tips for Success Timely tracking and identication of cost items that may lead to project overruns are necessary to manage the baseline project scope, cost, and schedule. Using a formal procedure and reporting process that requires quantifying the potential impact of changes to the project is essential for successful implementation of this method. Integrating this change management process into the agencys project management approach is also critical. If the budget control method is not followed, then there may be a reduced level of funds for other projects in the program. Tools B1.2 Constrained Budget B1.3 Standardized Estimation and Cost Management Procedures
Integrity
43 Table 6.2. Programming and preliminary design phase management strategy: Methods and tools.
MANAGEMENT STRATEGY
Manage the estimation process and costs through all stages of project development
Budget Control
B1.2 B1.3 B1.4 B1.5 C1.1 C1.2 C1.3 C1.4 C1.5 C1.7 C2.1 C2.2 C4.1 C4.2 C4.3 C4.4 C4.5 C4.6 C4.7 G1.2 R1.1 Constrained Budget Standardized Estimation and Cost Management Procedures Summary of Key Scope Items (Original/Previous/Current) Variance Reports on Cost and Schedule Communication of Importance Communication of Uncertainty Communication within State Highway Agency Definitive Management Plan Proactive Conveyance of Information to the Public Year-of-Construction Costs Agency Estimation Software Commercial Estimation Software Cradle-to-Grave Estimators Estimation Checklist Estimation Manual (Guidelines) Estimator Training Major Project Estimation Guidance Standardized Estimation and Cost Management Procedures State Estimation Section Cost Containment Table Complexity Definitions
Communication
Computer Software
Consistency
B1.4 Summary of Key Scope Items (Original/Previous/ Current) B1.5 Variance Reports on Cost and Schedule
6.1.2 Communication
Why? The fundamental communication goal is the timely transfer of information between project team participants, agency management, and external stakeholders. Project communication management tools and techniques ensure the timely and appropriate collection and dissemination of project information. Through active communication efforts within the agency
and with external entities, project team participants can compile and appropriately address the projects engineering and construction complexities as well as local government concerns and requirements. In Figure 6.1, the communication method is influenced by inputs from disciplines, third parties, and market conditions. Steps that either directly or indirectly facilitate communication include obtaining appropriate approval and communicating approval. The communication effort begins in programming, when the baseline estimate is prepared and the project is included in the priority program. At this point in project development, the project budget is often released to various constituencies. Unambiguous communication of the scope, cost, and time required to design and let the project for construction is
44
critical. Communication of uncertainty associated with the cost estimate is essential. Preliminary design involves a signicant level of scope definition; hence, proper communication of all additions and/or modications to the scope is essential to achieving an accurate estimation. Detailed scope denition also translates into reduced design ambiguity. Proper communication channels established between project participants must promote a better understanding of the impact that design has on project cost. The communication method is also discussed in the scope and schedule, off-prism issues, risk, and integrity strategies of this chapter. Project Complexity In complex projects, which involve a large number of stakeholders, there is an increased need for skillful communication. These projects are often highly visible within government agencies and to the public. Failure to communicate changes to the appropriate entities and project participants involved with complex projects may result in a lack of condence in the state highway agencys cost estimates, and the credibility of the agency could be compromised. Tips for Success The identication and formulation of an effective communication plan is the key to efcient and effective communication. The requirements and deliverables promised to stakeholders must be identied and matched with corresponding deliverables that a project team produces. Project cost should be communicated in year-of-expenditure dollars. Tools C1.1 C1.2 C1.3 C1.4 C1.5 C1.7 Communication of Importance Communication of Uncertainty Communication within State Highway Agency Denitive Management Plan Proactive Conveyance of Information to the Public Year-of-Construction Costs
is prepared, the use of historical bid-based estimates becomes a more common approach. The use of computer software helps in extracting and summarizing historical cost data. This supports standardization of information presentation across the agency. Computers may also help reduce calculation errors and provide summary reports in numerous ways. When estimating line-item costs, computer software can also assist in analyzing multiple alternatives rapidly. In Figure 6.1, computer software can be used extensively in the maintenance and retrieval of historical data. Computer software also is used to prepare base estimate and perform risk analysis. Project Complexity Larger, more complex projects involve a signicant number of cost items. Further, many project participants are often involved in preparing estimates for complex projects. In this environment, computer software can aid in performing numerous calculations quickly, reducing errors, and improving efciency. Computer software can also aid in making changes rapidly, especially when the project team is evaluating a number of alternatives based on estimated costs. Tips for Success Computer software is useful for making calculations and, in particular, summarizing information in a manner that aids in checking estimate results. However, the output of estimation software is only as good as the input. Estimation software that provides some mechanism for checking the output (i.e., through comparisons of cost elements using percentages, ratios, and/or appropriate ranges against historical averages) will enhance the usefulness of the software. Tools C2.1 Agency Estimation Software C2.2 Commercial Estimation Software
6.1.4 Consistency
Why?
An estimate is a permanent document that serves as a basis for business decisions. It must be in a form that can be understood, checked, veried, and corrected. There must be consistency. Consistency ensures that estimates are prepared following a single standard. Estimation consistency is important, especially across state highway agency districts and regions, because estimates are easier to review when they are prepared in a similar format. Consistency is achieved by instituting project management procedures that serve as guides for the cost estimation
45
management process. Agency management should ensure that the agencys estimators, or other project team members involved in preparing estimates, have developed standard practices and use procedures that are documented in a manual of practice and that all project participants involved in cost estimation are trained and knowledgeable in the established procedures. In Figure 6.1, the consistency method inuences each step in the process and the types of information used to prepare the baseline estimate and the estimate updates. Consistency inuences cost management steps, as well. Project Complexity Complex projects require the involvement of many different project participants, often representing different organizations or agencies. Complex projects also span a considerable period of time. Consistency in cost estimation management is essential to bridge the gap between these different project participants and to integrate the ow of information during project development. Although consistency is likely more important for complex projects, it is certainly still important for smaller and less complex projects because the number of these types of projects is generally high within state highway agencies. Consistent cost estimation management across these smaller projects will provide program-level consistency in cost estimation. Tips for Success Adequate training and knowledge of agency procedures and practices are important for this method to be successfully implemented. Using the same estimators throughout project development further contributes to achieving estimate consistency. When different organizations or agencies are involved in a project, consistency can be achieved if common procedures are implemented on a project-specic basis. Tools C4.1 C4.2 C4.3 C4.4 C4.5 C4.6 Cradle-to-Grave Estimators Estimation Checklist Estimation Manual (Guidelines) Estimator Training Major Project Estimation Guidance Standardized Estimation and Cost Management Procedures C4.7 State Estimation Section
concept usually result from a better understanding of the needs that drive a project, and with most scope changes there is a resulting increase in project cost. In order to ensure that designers are aware of how scope changes will affect project cost, it is advantageous to require submittal of a cost estimate along with each design submittal. Using a gated process can focus decision making during project development. A gated process involves identication of critical project development milestone points. At these predetermined milestones, a cost estimate is prepared to support a management review of scope, cost, and schedule before the project can proceed to the next milestone. This gated process prevents a project from moving forward without proper reviews and approvals. This method can reduce potential cost escalation. Setting an approved baseline cost at the end of the programming is an example of a gate in the project development process. In Figure 6.1, gates can be placed at critical points, such as at review and approval steps, to support baseline cost estimates for priority programming and to meet key project requirements such as when a project is included to the STIP. Project Complexity Complex projects involve many components that may easily be overlooked as the estimate is developed. A thorough review prior to releasing the project for further development facilitates scope, cost, and time control. This type of review at a gate in project development may ensure a more reliable estimate and potentially reduce cost growth. Tips for Success The placement of these gates at appropriate points on the project development time line and in conjunction with cost estimate development is critical if this method is to be successful. Standardizing these gates for all projects will further aid in developing consistent and accurate estimates. It is important that the review process at each gate be effective and expeditious to ensure that the project is not delayed. Tool G1.2 Cost Containment Table
46
Further, communication of project complexity and the associated estimate uncertainty is critical during programming and early in preliminary design. An understanding of project complexity will allow for the determination of appropriate risk and contingency, as depicted in Figure 6.1. As presented in Table 2.2, agencies should estimate base (or known) costs separately from risk and contingency (or unknown) costs. Recognition of project complexity is a critical step in determining the uncertainty of a project estimate. Project Complexity Through the act of denition and recognition of project complexity, a proper contingency can be developed. Also, a set of lessons learned for each level in the complexity scale can be developed. This will allow personnel throughout the agency to benet from previous project knowledge. This knowledge should eliminate some of the relearning that takes place during the development of many projects. Tips for Success Recognition of the projects complexity early in its development can aid in ensuring that all criteria for a project of a given complexity are introduced into the cost estimation practice and cost estimation management processes. Criteria can include the size of staff required for the project, the necessary level of review, the level of denition at certain project milestones, and the necessary authorization level for the project, in addition to changes in scope, schedule, and quality. Complexity can also address the project setting (rural or urban). The denition levels and criteria should be established for use throughout the agency, and each project should be cataloged as a certain complexity early in project development. Changes related to complexity should be noted and communicated as they become apparent. Tool R1.1 Complexity Denitions
four different types of cost estimation management methods and two different cost estimation practice methods applicable to the scope and schedule strategy. These methods are listed in Table 6.3.
6.2.1 Buffers
Why? Buffers are used as a means to ensure integrity in the processes of developing and tracking scope, cost, and schedule elements during project development. They are designed to safeguard projects against external and internal inuences that might misrepresent the level of denition of the project scope and the accuracy of the project schedule and budget estimate. In Figure 6.1, buffers can be included as part of the prepare base estimate, perform risk analysis, and review total cost estimate steps to enable estimators to independently develop estimates based on the best information available. Project Complexity Manipulative pressures, especially from external third parties, may influence estimates that are developed for highprole projects. Although such pressures are typically present with more complex projects that often affect a larger number of stakeholders or with projects that have a greater impact on the environment, the establishment of buffers at some minimum standard should also be considered for smaller, less complex projects. Tips for Success Establishing a minimum standard to protect the project scope and cost from external and internal manipulative influences is important to creation of accurate estimates. Careful evaluation of such influences and how these influences should be mitigated during programming and early in design is important. Tools B2.1 Board Approvals B2.2 Constrained Budget B2.3 Management Approvals
6.2.2 Communication
Why? Project communication management ensures the timely and appropriate generation, collection, dissemination, storage,
47 Table 6.3. Programming and preliminary design phase scope and schedule strategy: Methods and tools.
SCOPE AND SCHEDULE STRATEGY
Formulate definitive processes for controlling project scope and schedule changes
Buffers
B2.1 B2.2 B2.3 C1.2 C1.3 C1.4 C1.7 C6.1 C6.2 C6.3 C6.4 D1.2 I1.1 I1.2 I1.3 I1.4 Board Approvals Constrained Budget Management Approvals
Constructability
C5.1 Constructability Reviews
Communication
Communication of Uncertainty Communication within State Highway Agency Definitive Management Plan Year-of-Construction Costs Cost Containment Table Estimation Scorecard Scope Change Form Scoping Documents Delivery Decision Support Cost Containment Table Estimation Scorecard Project Baseline Scope Change Form
Value Engineering
V2.1 Value Engineering
and ultimate disposition of project information. Scope and schedules changes are prevalent in the programming and preliminary design phase of project development. Proper communication of these changes is crucial to cost estimation management. Communication is important in interfacing with external participants, especially when changes originate from third parties. Communication inuences the inputs received from agency disciplines and third parties. The communication method directly guides how the communicate approval step is performed (see Figure 6.1). Project Complexity In complex projects, which involve a large number of stakeholders, there is an increased need for skillful communication. These projects are often highly visible to government agencies and the public. Failure to communicate scope and schedule changes to the appropriate entities and to involved project participants in a timely manner may result in a lack of condence in the state highway agencys cost estimate and schedule. As a consequence, the credibility of the agency could be compromised.
Tips for Success A project communication plan is critical to ensure that this strategy is successfully implemented. This plan should outline who is responsible for what aspects of project communication. This plan must especially focus on how project changes are communicated as the project is developed during programming and preliminary design. Tools C1.2 C1.3 C1.4 C1.7 Communication of Uncertainty Communication within State Highway Agency Denitive Management Plan Year-of-Construction Costs
48
monitored against a performance benchmark as the design is developed. Hence, a project cost baseline consistent with a dened scope and schedule must be established. The establishment of this baseline over the timeline of project development can be variable. One practice is to set this baseline when the scope of all major cost items can be adequately dened (i.e., 80% of cost lies in 20% of the project elements). This typically occurs during programming when an appropriate level of design completion is achieved (10% to 25%), although when the project baseline cost is set varies depending on agency policy. Setting a cost baseline ensures that scope changes and their impact can be documented and evaluated against the project budget. Deviations can be mapped over time for reconciliation with periodic estimation updates. This mapping process cannot successfully occur without a baseline. The baseline estimate document is the output of following all the steps shown on the left side of Figure 6.1 during programming. Project Complexity Complex projects involve many work items, and the probability of change is higher because it is difcult to dene these work items early in design development. Hence, recording potential scope changes and periodically evaluating them for inclusion in the baseline scope ensures that the project will remain on schedule and on budget. Early detection of deviations from the baseline schedule and cost helps the project participants make necessary budget adjustments, recognize if additional funds are needed, and avoid substantial cost overruns. Tips for Success Project baselines are best established only when critical cost elements have been sufciently dened. This means that the design basis and project denition is completed to a level of detail such that critical scope items can be properly estimated. Documenting the scope basis and assumptions that support the baseline cost estimate is also critical. This documentation will be the benchmark from which changes can be identied and assessed as potential deviations from the baseline scope and schedule. Tools C6.1 C6.2 C6.3 C6.4 Cost Containment Table Estimation Scorecard Scope Change Form Scoping Documents
49
The identication method is normally positioned to intercept inputs impacting scope and cost. In Figure 6.1, identication of changes would lter the input from disciplines and the input from third parties. It would also identify any downstream changes to the determine estimate basis (scope/location) step and be used frequently as a basis for performing the steps on the right side of Figure 6.1. The method is also tied closely to the creation of a project baseline method (see Section 6.2.3). Project Complexity Establishing reliable baseline denitions of scope and cost in the early stages of project development for large projects is difcult, primarily because of the many unknowns at that point in time. Further, large projects tend to have more elements to properly scope and estimate. As such, identifying potential changes requires a more systematic approach. Thus, it is with the complex projects that the use of this method will yield the greatest benets. Tips for Success Engineering and construction complexities caused by the projects location or purpose can make early design work very challenging and lead to internal coordination errors between project components. Constructability problems that need to be addressed may also be encountered as the project develops. Early identication of such issues and a structured system for controlling their impacts is essential to achieving estimate quality. Tools I1.1 I1.2 I1.3 I1.4 Cost Containment Table Estimation Scorecard Project Baseline Scope Change Form
when the project is bid. If the trafc management design is developed with construction input, the result should be a more cost-effective and timely project. The constructability method would inuence the type of input received from the disciplines. Constructability would impact the update estimate basis step in Figure 6.1 and inuence the accuracy of the cost estimate and schedule. Project Complexity The more complex a project, especially if the project is set in a highly congested urban environment, the more attention should be given to the integration of trafc control and construction sequencing. This effort will provide a better baseline schedule for the project and, hence, increased accuracy of the estimated project duration. The cost estimate should reect an efcient construction approach. Tips for Success Constructability analysis is most successful when the process is formalized and is an integral part of the programming and preliminary design project phase. Identifying constructability experts is also critical in achieving successful constructability programs. A constructability expert must be able to work effectively with project designers and provide meaningful input as designs are developed. Tool C5.1 Constructability Reviews
6.2.6 Constructability
Why? Construction knowledge and experience must support development of construction schedules. This focus is particularly useful when evaluating alternate construction staging plans to integrate with trafc management strategies. Trafc control and construction staging is often one of the most complex aspects of designing a project. Often designers do not fully understand the impact that a particular trafc control scheme has on ease and efciency of construction. This impact will translate into a schedule that will likely change
50
Project Complexity The FHWA mandates the use of value engineering on federally funded National Highway System projects with an estimated cost greater than $25 million, but small-dollar projects have successfully employed value engineering. Value engineering is effective on projects with alternative solutions that vary with scope and cost, on capacity improvement projects that widen an existing highway (especially in high-volume trafc environments), on projects requiring major trafc control, and on interchanges on multilane facilities. Tips for Success Value engineering is most successful when it is performed early in project development so that the proposed improvements can be easily incorporated into the design. Value engineering is a structured process. It is important to use a knowledgeable and experienced facilitator and have a value engineering team with diverse backgrounds. The value engineering process should be conducted away from the ofce environment to ensure focus and creativity. The period for conducting a value engineering process is typically 3 to 5 days. Tool V2.1 Value Engineering
dened and then developed through design activity, the design often incorporates the inuence of community interest and concerns. In some cases, this could include a requirement for a context-sensitive design. This type of design may add cost to a project, and this possibility should not be overlooked when preparing estimates during programming and preliminary design. During this phase, environmental analysis and clearance activities are completed. The results of these activities may introduce compliance and mitigation requirements that must be also addressed in estimates for design and construction work. Further, macroeconomic events can signicantly inuence cost. These events may drastically influence cost, but historical data may not reect signicant increases due to lack of material and subsequent material price increases. There are ve different off-prism methods described in Table 6.4 for use during the programming and preliminary design phase of project development.
6.3.1 Communication
Why? Failure to account for off-prism issues in the cost estimation process can result in cost overruns. The uncertainties related to off-prism issues have to be identied during programming and throughout preliminary design to mitigate risks associated with these issues. Communication of these uncertainties, the risks, and the associated potential cost impact is a critical method in cost estimation management. Effective communication of off-prism issues must occur within the state highway agency and between all external project stakeholders to achieve project success. The communication method inuences the communicate approval step in Figure 6.1.
Table 6.4. Programming and preliminary design phase off-prism strategy: Methods and tools.
OFF-PRISM STRATEGY
Use proactive methods for engaging external participants and assessing the macroenvironmental conditions that can influence project costs
Communication
C1.1 C1.2 C1.3 Communication of Importance Communication of Uncertainty Communication within State Highway Agency
Estimate ReviewInternal
E3.2 Off-Prism Evaluation
Right-of-Way
R2.5 R2.6 P3.1 Right-of-Way Estimator Training Separate Right-of-Way Estimators Meetings
Public Involvement
51
Project Complexity The importance of off-prism issues to complex and largedollar projects is paramount. Complex project are affected by a multitude of external and internal elements that require careful and timely evaluation, especially since larger projects are often high-prole projects from a community perspective. Tips for Success The establishment of a functional communication protocol is essential for the state highway agency to effectively provide information addressing community interests and concerns while maintaining internal awareness of off-prism issues. A focus on cost estimate attributes tied to scope and schedule and explained in a simple format will keep the public informed. Tools C1.1 Communication of Importance C1.2 Communication of Uncertainty C1.3 Communication within State Highway Agency
not dependent on complexity, it may be more difficult to solve in an urban setting. Tips for Success The location of the project is critical when implementing this method in the off-prism strategy context. The identication of all factors that may impact project scope, cost, and time must be clearly identied so they can be properly addressed in the cost estimate. Estimators should not work in a vacuum because they may fail to consider off-prism issues and other information provided by other state highway agency disciplines. Interaction with others is critical to preparing accurate estimates. Tools R2.5 Right-of-Way Estimator Training R2.6 Separate Right-of-Way Estimators
6.3.2 Right-of-Way
Why? Failure to account for all relevant scope elements when preparing a cost estimate adversely affects the accuracy of an estimate. Some of these elements include right-of-way, utilities, and environmental elements. The impact of these elements will vary for every project, and input from appropriate project team participants must be evaluated to prepare accurate estimates. Scope denition is continuously rened over preliminary design and improves the clarity of project requirements. Hence, an early determination of the parameters related to right-of-way, utilities, and environmental issues, and inclusion of these issues in cost estimates, will improve the accuracy of the estimate. In Figure 6.1, this method guides the type of input received from disciplines when performing the prepare base estimate step. Project Complexity Right-of-way becomes an issue more often when adding system capacity. If a project is located in a highly urbanized area, right-of-way may be costly and acquisition of property can demand considerable time. Utilities can be a problem for projects in any area, but are more likely for projects in urban areas. Environmental compliance may require that land be purchased for creating a new wetland to replace existing wetlands displaced by the project. While this issue is
52
ated. In Figure 6.1, input from third parties and information on current market conditions are inputs that can help implement this method when performing the update estimate basis and prepare base estimate steps. Project Complexity Projects of greater complexity may gain the most benets from proactive efforts to identify off-prism issues, such as environmental concerns, and assess their cost impact. Environmental issues are more related to the location of the project. Environmental regulations and design considerations to accommodate mitigation requirements must be considered when developing cost estimates (e.g., noise reduction near a residential community may require installing noise walls or upgrading existing wetlands). Larger projects can be more substantially impacted by the macroeconomic environment than less complex projects. Tips for Success To enhance the success of identifying off-prism issues and mitigating possible negative impacts, agencies must start this effort early in project development. Continuing this endeavor throughout project development will ensure that the scope and cost reflect the impact of off-prism issues. Communicating off-prism issues to upper management should be accomplished quickly because most of these types of issues have or will have political implications. The ability to evaluate and attribute the most appropriate percentage to cover the cost of different issues will improve early estimate accuracy. Tools
53 Table 6.5. Programming and preliminary design phase risk strategy: Methods and tools.
RISK STRATEGY
Identify risks, quantify their impact on cost, and take actions to mitigate the impact of risks as the project scope is developed
Communication
C1.2 C1.3 Communication of Uncertainty Communication within State Highway Agency
Risk Analysis
R3.1 R3.2 R3.4 R3.5 Analysis of Risk and Uncertainty ContingencyIdentified Estimate Ranges Programmatic Cost Risk Analysis Contract Packaging Delivery Decision Support
Identification of Risk
I2.1 I2.2 R2.1 R2.2 R2.3 R2.4 Red Flag Items Risk Charter Acres for Interchange Advance Purchase (Right-of-Way Preservation) Condemnation Relocation Costs
Right-of-Way
6.4.1 Communication
Why? Communication has been discussed in earlier strategies of this Guidebook. Communicating project uncertainty is critical to understanding what risks the project might encounter and what the potential cost and time impact of these risks would likely be if they are not mitigated. As applicable to the risk strategy, communication predominantly means keeping all project team members and external parties informed about project uncertainties and constraints. Conveying risk-related information in an easy-to-understand manner is extremely important. The communication of risk analysis results is critical during the communicate approval step (see Figure 6.1). Project Complexity Inherently, project complexity typically increases the risk of project cost and schedule increases. Therefore, the importance of communication, particularly communication of estimate uncertainty and the risks associated with that uncertainty and the potential cost consequences is essential to improving stakeholder condence in the accuracy of the cost estimate. Tips for Success The ability to anticipate possible risk-related constraints on both a macro and micro level and the timely communication of their potential impact on project cost is a key to method success.
Tools C1.2 Communication of Uncertainty C1.3 Communication within State Highway Agency
54
preliminary engineering to validate the assumptions used to identify risks in the baseline cost estimate. This approach will reduce ambiguities in project scope as the design is completed. Tools I2.1 Red Flag Items I2.2 Risk Charter
6.4.3 Right-of-Way
Why? Land acquisition and related issues have always constituted a signicant cost estimate risk. During programming, there remains considerable uncertainty related to right-of-way requirements, so the risks remain high and must be accounted for in baseline cost estimates. However, as preliminary design proceeds, there is clarity on project alignment that in turn enables designers and right-of-way estimators to identify the nancial and legal aspects of the required land acquisition. Input from disciplines is critical to performing the risk analysis step, as shown in Figure 6.1. Project Complexity Complexity in this case revolves around several circumstances, such as real estate values, public or business opposition, and compensatory conditions. The more right-of-way needed for the project, the more risks that will have to be considered, including assessment of the potential cost impacts due to adverse settlements when parcels are taken. Furthermore, on larger projects, the time impact of acquiring parcels may be the most critical risk because estimated project durations could be extended signicantly if delays are encountered in acquiring parcels. Tips for Success Early land acquisition may be a key to success for this method. Design efforts to define right-of-way needs in conjunction with specialized advice from real estate personnel can reduce the impact of right-of-way on project cost and time. Tools R2.1 R2.2 R2.3 R2.4 Acres for Interchange Advance Purchase (Right-of-Way Preservation) Condemnation Relocation Costs
55
then the use of the risk strategy must account for the potential uncertainty related to the impact of acceleration. Tips for Success How a project is delivered must be considered when performing the risk analysis. Thus, evaluating the impact that project delivery and procurement approaches have on cost and time is necessary when implementing a project-level risk strategy. Tools D1.1 Contract Packaging D1.2 Delivery Decision Support
56 Table 6.6. Programming and preliminary design phase delivery and procurement: Methods and tools.
DELIVERY AND PROCUREMENT STRATEGY
Apply appropriate delivery methods to better manage cost because project delivery influences both project risk and cost
price this risk based on the level of scope denition, proposed project responsibilities identied in the RFP, and project complexity. Early estimates must reect the impact of using the design-build delivery approach. The influence of project delivery and procurement is important to the prepare base estimate and risk analysis steps (see Figure 6.1). Other procurement methods may accelerate construction, such as when cost plus time (A+B) contracting approaches are used with design-bid-build project delivery. Costs for potential incentives must be included when cost estimates are prepared. The impact of construction acceleration might require increases in labor, material, and equipment costs. These types of impacts must be considered when preparing early cost estimates, especially when historical unit costs are used. The packaging of a project in terms of a single contract or multiple contracts or establishing project limits must be considered early in design. Decisions that impact the number of contracts will inuence the design processes and the costs of construction. The earlier decisions are made on project delivery and procurement approaches, the better the opportunity to incorporate appropriate costs into the estimates congruent with the delivery and procurement approach selected. Project Complexity The larger and more complex the project, the earlier decisions should be made with respect to delivery approach. Even with smaller and less complex projects, where procurement approaches such as cost plus time or incentives and disincentives are used, an early decision will enable cost estimates to properly reect the impact that alternative delivery and contract approaches have on project cost and schedule. Tips for Success Prior to setting a baseline, the use of a decision support tool to identify the appropriate delivery and procurement approach may be benecial to preparing an estimate consistent with the project delivery approach. The point here is to include costs in the estimate that reect the impact of delivery and procure-
ment approaches such as an engineers estimate for a designbuild project. Tools D1.1 Contract Packaging D1.2 Delivery Decision Support
57 Table 6.7. Programming and preliminary design phase document quality strategy: Methods and tools.
DOCUMENT QUALITY STRATEGY
Promote cost estimate accuracy and consistency through improved project documents
Computer Software
C2.1 C2.2 C2.4 Agency Estimation Software Commercial Estimation Software Simple Spreadsheet
Constructability
C5.1 Constructability Reviews
Estimate/Document Review
E1.1 E1.2 Estimate/Document ReviewExternal Estimate/Document ReviewInternal
cost estimates are prepared. Considering the potential for many adjustments due to additions, omissions, and alternative design solutions, it is essential to track adjustments accurately. Computer software enables the estimator to easily incorporate adjustments when more detail is available. A comparative analysis can be performed, especially for alternatives, to produce quality documents supporting project estimates. Tips for Success Successful implementation of computer software to encourage quality documents requires the agency to accurately identify minimum quality standards and to use computer software that portrays the information in a meaningful manner. Since all projects are not the same, the exibility and ease with which changes can be incorporated and tracked with computer software makes the use of computers and supporting software imperative to the document quality strategy. Tools C2.1 Agency Estimation Software C2.2 Commercial Estimation Software C2.4 Simple Spreadsheet
this way, constructability will inuence both update design basis and prepare base estimate steps (see Figure 6.1). Project Complexity As project complexity increases, the need for construction knowledge and experience in reviewing designs becomes critical. Construction input can aid the designer in developing designs that can be constructed more efciently. This need is especially important for very large and complex projects, such as those in urban areas under high-trafc volumes. These types of projects require continuous input from construction experts beginning with project denition during programming and throughout preliminary design. Tips for Success Constructability is most successful when the process is formalized and is an integral part of the programming and preliminary design phase of project development. Identifying and using appropriate constructability experts is also critical in achieving successful constructability reviews. A constructability expert must be able to work effectively with project designers and provide meaningful input on design documents. Tool C5.1 Constructability Reviews
6.6.2 Constructability
Why? The quality of the documents used to prepare estimates impacts the quality of the estimate in terms of accuracy. Thus, design documents that provide the basis for cost estimates must accurately portray the design intent. Implementing constructability analysis will enhance project documents by reducing the potential for errors and omissions and will produce designs that are constructible. Constructability reviews can provide guidance as to the project construction phasing and staging approaches required to cost-effectively build the project. In
58
are approved. As discussed in other sections, a very effective management approach for establishing the reliability of a cost estimate is to subject the estimate to review and verication. Project Complexity The formality of a project estimate review and the depth of the review will vary depending on the type of project and project complexity. In the case of routine, straightforward projects, a formal review may not be necessary. However, as project complexity and scope increase, it is necessary to conduct formal reviews. When very complex projects are being estimated, management should require an external review of the estimate by qualied professionals. Tips for Success Knowledgeable and experienced individuals who bring a broad perspective to the project and estimate formulation should be assigned to conduct these reviews. To be of value, the review must closely examine the assumptions that form the basis of the estimate. Tools E1.1 Estimate/Document ReviewExternal E1.2 Estimate/Document ReviewInternal
vides a platform to easily review, update, and modify estimates. The need for greater accuracy is met by cost-modeling techniques using computer software. Predictive analysis of various parameters (like market conditions) can identify cost inuences. The ability to track changes efciently is another useful feature of computer software. The use of computer software is also discussed in the management, document quality, and integrity strategies of this chapter. Computer software is extensively used in the maintenance and retrieval of historical data. Computer software can efciently perform a large number of computations in support of the estimate preparation and risk analysis steps (see Figure 6.1). Project Complexity Large and complex projects may benet more from computer software because these projects involve increased levels of detail and more calculations. This is particularly the case when multiple alternatives are being considered during the programming and/or early in preliminary design. As alternatives are analyzed, scope adjustments reecting different scenarios are frequent and must be estimated quickly. Computer software aids in timely cost analysis. For more complex projects, tracking changes is also facilitated by computer software. Tips for Success The level of user skills and the exibility of the software will determine the success of computer software. In addition, templates and output formats will enhance multiple-user environments and maintain consistency. Finally, computer software should facilitate automatically changing cost items that are estimated on a percentage basis. Tools C2.1 Agency Estimation Software C2.2 Commercial Estimation Software C2.3 In-House Conceptual/Parametric Estimation Software
6.7.2 Consistency
Why? Estimations must be structured and completed in a consistent manner. Consistency is achieved by instituting operating procedures that serve as guides for all who prepare estimates. Consistency inuences how information is used, such as input from disciplines, input from third parties, market conditions, and historical data (see Figure 6.1). Consistency is also required when preparing the base cost estimate and performing a risk analysis. Estimate consistency enables analysis, evaluation, validation, and monitoring of item costing.
59 Table 6.8. Programming and preliminary design phase estimate quality strategy: Methods and tools.
ESTIMATE QUALITY STRATEGY
Use qualified personnel and uniform approaches to achieve improved estimate consistency and accuracy
Computer Software
C2.1 C2.2 C2.3 Agency Estimation Software Commercial Estimation Software In-House Conceptual/Parametric Estimation Software
Communication
C1.7 Year-of-Construction Costs
Consistency
C4.1 C4.2 C4.3 C4.4 C4.6 C4.7 Cradle-to-Grave Estimators Estimation Checklist Estimation Manual (Guidelines) Estimator Training Standardized Estimation and Cost Management Procedures State Estimation Section
Design Estimation
D2.1 D2.2 D2.3 D2.4 D2.5 D2.6 D2.7 D2.8 D2.9 Analogous or Similar Project Agency Estimation Software Cost Based, Bottom Up Historical Bid Based Historical Percentages Major Cost Items using Standardized Sections Parametric Estimation Spreadsheet Template Trnsport Project Estimation File
Gated Process
Checklists Cost Containment Table
Estimate ReviewExternal
E2.1 Expert Team
Right-of-Way
Acres for Interchange Advance Purchase (Right-of-Way Preservation) Condemnation Relocation Costs
Estimate ReviewInternal
E3.1 E3.3 E3.4 E3.5 P2.1 P2.2 P2.3 Formal Committee In-House/Peer Round Table Year-of-Construction Costs Estimation Checklist Scoping Document Work Breakdown Structure
Project Scoping
Project Complexity Consistent practices and procedures facilitate a multiple-user interface, minimize errors and omissions, and strengthen reporting and data-sharing activities. This becomes essential in the case of large and complex projects because they involve multiple disciplines and often require specialized input that must be acquired and integrated by estimators. Tips for Success Consistency in how information is used and how cost estimates are prepared is essential to producing accurate
estimates. However, each project has different issues and conditions that inuence the type of information used and the approaches to preparing the estimate. Tools C4.1 C4.2 C4.3 C4.4 C4.6 Cradle-to-Grave Estimators Estimation Checklist Estimation Manual (Guidelines) Estimator Training Standardized Estimation and Cost Management Procedures C4.7 State Estimation Section
60
can proceed to the next stage. At these decision milestones, cost estimates are prepared to aid in decision making. This mechanism of not permitting a project to move past a milestone point without proper approvals will allow for checks to ensure that cost estimates reect the known scope and project conditions. Setting an approved cost baseline at the end of programming is an example of a gate in the project development process. A second gate may be when environmental clearance is obtained. A third gate may be when the construction estimation for the STIP is prepared and construction is approved for inclusion in the STIP. The cost estimation practice and cost estimation management processes depicted in Figure 6.1 must coincide with gates in the project development process. Project Complexity Complex projects involve many components that may easily be overlooked as the estimate is developed. A thorough review prior to releasing the project for further development provides a reasonable mechanism for ensuring that the project is ready to move forward to the next stage of design. This type of review at a gate in project development can ensure a more reliable estimate and control cost growth. Tips for Success The placement of gates over the project development time line is critical for this method to be successful. Another important aspect is that the review process at each gate must be effective and be performed in a timely manner to ensure that project development is not delayed. Tools G1.1 Checklists G1.2 Cost Containment Table
6.7.5 Right-of-Way
Why? Right-of-way costs are a signicant component for many projects. Land acquisition requirements must be consistent with the scope of the project. To obtain realistic projections of right-of-way cost, appropriate experts must evaluate geographic, demographic, and market information. Other costs for acquiring land must be factored into estimates so that the estimates include all costs associated with right-of-way. Possibilities of litigations and other public concerns must also be accounted for in the estimate. Scope inputs from design disciplines and third parties are critical to preparing base esti-
61
mates with appropriate contingencies covering right-of-way risks (see Figure 6.1). Project Complexity Typically, more complex projects that intersect with urban neighborhoods, historical sites, or environmentally sensitive areas require greater effort in estimating right-of-way costs. Tips for Success Identication and evaluation of several alternatives may lead to an economical solution when scoping right-of-way requirements during programming and early in preliminary design. Early identication of parcels that will be taken is critical to estimating right-of-way costs. Tools R2.1 R2.2 R2.3 R2.4 Acres for Interchange Advance Purchase (Right-of-Way Preservation) Condemnation Relocation Costs
project stakeholders are informed of all costs related to the project and that these costs are visible. Tool C1.7 Year-of-Construction Costs
6.7.6 Communication
Why? The project development process duration can be 2 years to over 10 years. The identication of project duration, and especially when construction will occur, is critical to accounting for ination effects. Capturing future ination will produce more realistic estimates. Estimate credibility will be increased when the estimate includes future ination. In Figure 6.1, assessing market conditions when preparing base estimates and performing a risk analysis is inuenced by this method. Project Complexity Complex projects typically have longer project duration from programming through construction than simple projects. The dollars added to account for ination can be substantial in complex projects. These dollars must be included in cost estimates to properly reect the estimated costs when construction is scheduled to be completed. Tips for Success Clearly communicating the estimated cost in year-ofexpenditure dollars is critical. This approach ensures that
62
design estimation must t the application in terms of scope, available data, and time to prepare the estimate. Tools D2.1 D2.2 D2.3 D2.4 D2.5 D2.6 D2.7 D2.8 D2.9 Analogous or Similar Projects Agency Estimation Software Cost Based, Bottom Up Historical Bid Based Historical Percentages Major Cost Items using Standardized Sections Parametric Estimation Spreadsheet Template Trnsport
63
benet from the project scoping effort. Good documentation of the project scope eliminates errors and omissions in the estimate. Estimate reviews can be further facilitated if the scope is properly structured and documented systematically. Tips for Success The agency should consider developing standard management practices and a standard set of forms to document the project scope. Because project scope is often revisited during preliminary design, standard practices provide an audit trail of how the projects scope was developed, structured, and changed. Management needs to complete scope forms early and update them regularly as changes are made. Doing so will allow management to track project scope, and estimators will always know what should be included in the estimate. Scope forms provide a graphic view of what has changed since the previous estimate was completed. Tools P2.1 Estimation Checklist P2.2 Scoping Document P2.3 Work Breakdown Structure
6.8.1 Communication
Why? Communication has been discussed in earlier strategies of this Guidebook. As applicable to the integrity strategy, it is predominantly focused on keeping all project team members and external parties informed and updated with respect to the current estimated project cost. Efcient communication channels must be established, and the exchange of information must be clear and succinct. Efforts must be made to ensure that the signicance of cost information, which is communicated, is interpreted appropriately. Communication of uncertainty and any discrepancies observed must be
64 Table 6.9. Programming and preliminary design phase integrity strategy: Methods and tools.
INTEGRITY STRATEGY
Ensure that checks and balances are in place to maintain estimate accuracy and to minimize the impact of outside pressures that can cause optimistic biases in estimates
Communication
C1.2 C1.7 Communication of Uncertainty Year-of-Construction Costs
Consistency
C4.3 C4.5 C4.6 Estimation Manual (Guidelines) Major Project Estimation Guidance Standardized Estimation and Cost Management Procedures Expert Team
Computer Software
C2.1 C2.2 C2.3 Agency Estimation Software Commercial Estimation Software In-House Conceptual/Parametric Estimation Software
Estimate ReviewExternal
E2.1
Estimate ReviewInternal
E3.1 E3.3 E3.4 E3.5 V1.1 V3.1 Formal Committee In-House/Peer Round Table Year-of-Construction Costs Estimation Software Estimation Checklist
brought to the notice of peers immediately for remedial procedures. In Figure 6.1, several steps that are concerned with the transmission of information and approvals are supported by this method. Inputs from disciplines, third parties, and project requirements have to be communicated without ambiguity. Project Complexity Complex projects are highly visible to project stakeholders. Proper communication of estimate information is critical to maintaining stakeholder support. Further, proper communication of changes in project costs and the reasons for these changes is needed to ensure the credibility of the agency with respect to cost estimation management for large and complex projects. Tips for Success Training personnel on tools that are useful to communicate project cost information is helpful. Developing mechanisms to describe project cost information in a simple and understandable manner is important for successful communication.
65
puter software also provides a secure and reliable environment for estimate review and communication. Project Complexity Highly complex projects may have a greater vulnerability to integrity issues in cost estimation management. The need to meet a desired price may inuence the use of data in estimation. Computer software can help identify such problems when checks are generated to determine if data are outside a normal range. Tips for Success Secure and reliable features built into computer software can help ensure the success of the software in resolving cost escalation factors associated with integrity. Restricted and endorsed access by all users will assist in identication of responsible defaulters. Tools C2.1 Agency Estimation Software C2.2 Commercial Estimation Software C2.3 In-House Conceptual/Parametric Estimation Software
budget, then the size of the project makes little difference when applying this method. Tips for Success Proper identication and evaluation of appropriate designs will increase the likelihood of the project being completed within budget. Cost estimates must be periodically updated to ensure that the current cost is under the xed budget. Documenting areas of scope reduction is important so that project stakeholders understand what is being delivered. Tool D3.1 Design to Cost
6.8.4 Consistency
Why? Estimation processes often involve the participation of multiple estimators with diverse backgrounds and approaches to estimation. Practices and regulations can vary from district/ region to district/region within a state. There is a need to establish acceptable and common procedures before any project can be estimated. Procedures and guidelines will lead to consistent approaches to estimating cost and will help to ensure integrity in the estimation process. Procedures should be developed to encompass all steps and inputs shown in Figure 6.1. Project Complexity It may be helpful to develop specific guidelines for estimating major projects, such as those with a cost greater than some fixed figure or having certain attributes. Projects less than this cost should follow standard procedures related to cost estimation management and cost estimation practices. Tips for Success Training and education about the procedures and/or guidelines being adopted for every project is mandatory for all project team participants. Choosing the right estimation approach is essential for this method to succeed. Tools C4.3 Estimation Manual (Guidelines) C4.5 Major Project Estimation Guidance C4.6 Standardized Estimation and Cost Management Procedures
66
estimates at different levels of reviews will improve estimate accuracy. Project Complexity In the case of an uncomplicated overlay project, the review may be limited to verication that all elements are accounted for by the use of a simple checklist. However, as project complexity and scope increase, it is necessary to conduct more formal reviews. Complex projects may have several cost elements that estimators are unfamiliar with and require an expert opinion. Estimate reviews provide the opportunity to minimize ambiguities by imparting appropriate expertise from within the agency. Tips for Success Reviewers must have adequate expertise and credibility from the state highway agency viewpoint based on previous project experience. There should be no tolerance for any compromise on the results of internal review evaluations. Reviewers should ensure that all costs include future ination to the midpoint of construction. Tools E3.1 E3.3 E3.4 E3.5 Formal Committee In-House/Peer Round Table Year-of-Construction Costs
67
Tips for Success Assumptions and the basis used to estimate costs must be clearly documented to validate costs and for future evaluation as estimates are updated and used for cost management. Estimation software should allow for documenting assumptions as the estimator prepares the estimate. Tool V1.1 Estimation Software
work packages are covered in cost estimates is more time consuming and more difcult to achieve on large projects, especially during the programming and preliminary design phase, when project scope is evolving. Tips for Success A key to successful use of this method is the careful consideration of all critical elements that are shown on the checklist during the cost estimation process and ensuring that the impact of these elements is accurately captured in the estimate. Tool V3.1 Estimation Checklist
6.9 Summary
Table 6.10 lists all the methods and tools presented in this chapter for use in the programming and preliminary design phase of project development. This list can be used as a quick reference to help navigate Appendix A for descriptions of the tools. Table 6.10 can also be used as a checklist for selecting tools that should be employed on any one project. The checklist forms a self-assessment tool for agencies to benchmark against. These methods and tools were found in highway agencies throughout the country. While no agency was found to possess all of the methods and tools, all methods and tools exist and have the potential to be applied by any single agency.
69
CHAPTER 7
Introduction
Once a project reaches the nal design phase of its development, cost estimation focuses on the engineers estimate and the projects scope is now reflected in the contract plans and specifications, including specific line items with quantities. Figure 7.1 is a ow diagram of how the cost estimation practice and cost estimation management processes proceed during nal design. As shown in Figure 7.1, consideration of market conditions, the requirements imposed by third parties, and the macroeconomic environment are critical inputs to cost estimation in this phase. In addition, the estimate should reect a level of contingency congruent with project risks. Estimation management would cover the steps of obtaining appropriate approval of the engineers estimate and comparing the engineers estimate with bid prices received from contractors. Additionally, it is necessary to consider the funds available in the STIP once the engineers estimate is complete. Finally, another purpose of the engineers estimate is to obligate funds for construction. In the final design phase of a project, many of the methods and tools of a strategy help address the pressure to meet previous commitments concerning cost and schedule and to expand project scope. Additionally, many of the methods and tools discussed in this chapter help identify and mitigate project risk by drawing attention to market conditions, including the possibility of unforeseen events and unforeseen conditions. Table 7.1 shows the link between strategies and cost escalation factors in the final design phase.
the nal design phase of a project, have historically caused estimation problems for their organization and then apply the appropriate strategies to achieve better performance. Use Table 7.1 to determine which strategies may provide resources to address escalation factors that are causing problems. Specic strategies of interest for the nal design phase, along with the methods and tools that are available, are found within Chapter 7. Detailed information on the tools can be found in Appendix A. Once a strategy is selected to address a cost escalation factor, the user must decide if it is better to use a cost estimation management solution, a cost estimation practice solution, or both. The question of which approach should be used is inuenced by internal agency constraints.
Methodology
This chapter is based on and uses the cost escalation factor denitions and strategies described in Chapter 3. Agencies should seek to identify the cost escalation factors that, during
70
COST ESTIMATION PRACTICE AND COST ESTIMATION MANAGEMENT
Project Scope Type Final Plans/Specs Schedule-Line Items & Quantities Project Complexity Project Development Process
Historical Data
Legend
Input
Engineers Estimate
Step
Bid Data
Decision
Not Awarded
Awarded
ROW = right-of-way RES = real estate service PS&E = plans, specifications, and estimates
Figure 7.1. Flow diagram for cost estimation practice and cost estimation management during nal design.
There are seven different management methods described here for use during the nal design stage of project development, as shown in Table 7.2.
place before the final estimate is prepared. As depicted in Figure 7.1, the determine estimate basis step would encompass this assumption of management control. One way to control scope and cost is to demand that the project design conform to the project budget; this forces designers to be constantly aware of the cost implications of their designs. Even at this late stage in project development, management must maintain strict control of the budget and be regularly updated as to scope and cost changes or to external pressures that could impact cost.
71 Table 7.1. Link between strategies and cost escalation factors in the nal design phase.
Strategies
Scope and Schedule Document Quality Off-Prism Issues Estimate Quality 7.7 Management Delivery and Procurement
Section Bias Delivery and Procurement Approach Project Schedule Changes Engineering and Construction Complexities
7.1
7.2
7.3
7.4
Risk
7.5
7.6
7.8
Scope Changes Scope Creep Poor Estimation Inconsistent Application of Contingencies Faulty Execution Ambiguous Contract Provisions Contract Document Conflicts Local Concerns and Requirements Effects of Inflation Scope Changes Scope Creep Market Conditions Unforeseen Events Unforeseen Conditions
Internal
External
Project Complexity The importance of strict budget control increases with more complex projects and with projects that have longer development durations. Because external groups view project dollars as a source of funds for their pet schemes, longer development times provide more opportunities for such groups to prevail. Tips for Success Budget control is tied to scope control and rests in the hands of state highway agency management. The estimator provides a forecast of cost based on a dened project scope. To control costthat is, to protect the estimatemanagement can use budget control methods to limit scope creep. Tools B1.2 Constrained Budget B1.4 Summary of Key Scope Items (Original/Previous/Current) B1.5 Variance Reports on Cost and Schedule
7.1.2 Consistency
Why? An estimate is a permanent document that serves as a basis for business decisions. It must be in a form that can be understood, checked, veried, and corrected. There must be consistency. Necessary consistency is achieved by instituting operating procedures that serve as guides for all parties engaged in the estimation processes. Therefore, in Figure 7.1, consistency comes to play in all the activities: input from disciplines, input from third parties, assessing market conditions, extracting historical data, prepare base estimate, determine risk, and review estimate. Management should ensure that the agencys estimation group has developed a standard estimation manual of practice and that training is provided to all those involved in estimate preparation. Other good practices are the establishment of a section or staff dedicated to estimate preparation and the use of cradle-to-grave estimators.
Integrity
72 Table 7.2. Final design phase management strategy: Methods and tools.
MANAGEMENT STRATEGY
Manage the estimation process and costs through all stages of project development
Cost Estimation Management Budget Control B1.2 B1.4 B1.5 Constrained Budget Summary of Key Scope Items (Original/Previous/Current) Variance Reports on Cost and Schedule Consistency C4.1 C4.2 C4.3 C4.4 C4.5 C4.6 C4.7 E2.1 E3.1 E3.2 E3.3 E3.4 Cradle-to-Grave Estimators Estimation Checklist Estimation Manual (Guidelines) Estimator Training Major Project Estimation Guidance Standardized Estimation and Cost Management Procedures State Estimation Section Expert Team Formal Committee Off-Prism Evaluation In-House/Peer Round Table Checklists Cost Containment Table Cost Containment Table Estimation Scorecard Project Baseline Scope Change Form B1.2 B1.4
Cost Estimation Practice Budget Control Constrained Budget Summary of Key Scope Items (Original/Previous/Current)
Consistency C4.1 C4.2 C4.3 C4.4 C4.5 C4.6 C4.7 E2.1 E3.1 E3.2 E3.3 E3.4 G1.1 G1.2 I1.1 I1.2 I1.3 I1.4
Cradle-to-Grave Estimators Estimation Checklist Estimation Manual (Guidelines) Estimator Training Major Project Estimation Guidance Standardized Estimation and Cost Management Procedures State Estimation Section Expert Team Formal Committee Off-Prism Evaluation In-House/Peer Round Table
Gated Process
Identification of Changes
Project Complexity Consistency is an important feature of all estimates, but its impact on performance increases with project complexity. Tips for Success Poor administrationincluding overly complex organizational structures, convoluted contracting practices, and inexperienced personnelwill cause project cost problems stretching from the original estimate to completion of construction.
Tools C4.1 C4.2 C4.3 C4.4 C4.5 C4.6 Cradle-to-Grave Estimators Estimation Checklist Estimation Manual (Guidelines) Estimator Training Major Project Estimation Guidance Standardized Estimation and Cost Management Procedures C4.7 State Estimation Section
73
to conduct formal reviews. When very complex projects or projects involving new construction methods are being estimated, management should require that, in addition to the internal review, there be an external review of the estimate by qualied professionals. Tips for Success To be of value, the review must closely examine the assumptions that form the basis of the estimate. Knowledgeable and experienced individuals who are independent of the project team must conduct the review. Tools E3.1 E3.2 E3.3 E3.4 Formal Committee Off-Prism Evaluation In-House/Peer Round Table
As project complexity increases, the benets to be derived from a gated process increase because the gated process forces the project development team to carefully review the issues impacting project cost increases before proceeding.
74
Tips for Success A gated process is a means for achieving project and estimate success because it provides the basis for a structured assessment of scope denition, cost, and schedule before a project can move to the next step in its development. State highway agencies could make a gated process part of their work program update cycles. Tools G1.1 Checklist G1.2 Cost Containment Table
In the case of a complex project for which there is no historical bid data, the development of a bottom up estimate using commercial software maybe the only way to arrive at a realistic estimate of project cost. Tips for Success Estimation programs with preloaded templates help project teams dene the project scope, cost, and schedule. The software provides a means to track estimate changes during project development, and it can assist in project review. A training program is vitalthis can be a formal set of classes for all estimators, mentoring among the estimators in the section, or support for estimators to attend off-site conferences, seminars, or classes pertinent to their work. Tools P1.1 Agency Estimation Software P1.2 Commercial Estimation Software P1.5 Trnsport
75
7.2.1 Buffers
Why? Underestimationdriven by optimismis the demonstrated systematic tendency to be overoptimistic about key project parameters. Internally, underestimation of cost can
arise from the state highway agency estimators or consultants identification with the agency goals for maintaining a construction program. External pressures can also cause problems. Actions by the state highway agency are often required to alleviate perceived negative impacts of construction on the local societal environment as well as the natural environment. Measures may include, but are not limited to, introducing changes to project design, alignment, and the conduct of construction operations. These steps are often taken to appease the local residents, business owners, and environmental groups. All such changes in scope must be approved by management with a full understanding of their cost impacts. Buffers are positioned between or within processes impacting scope and cost. In Figure 7.1, buffers would typically be found separating any scope and schedule decision from actual estimation processes, such as the prepare base estimate step.
Table 7.3. Final design phase scope and schedule strategy: Methods and tools.
SCOPE AND SCHEDULE STRATEGY
Formulate definitive processes for controlling project scope and schedule changes
Buffers
B2.1 B2.2 B2.3 C1.1 C1.2 C1.3 C1.4 C1.7 E2.1 E3.1 E3.2 E3.3 E3.4 E3.5 I1.1 I1.2 I1.3 I1.4 V2.1 Board Approvals Constrained Budget Management Approvals Communication of Importance Communication of Uncertainty Communication within State Highway Agency Definitive Management Plan Year-of-Construction Costs Expert Team Formal Committee Off-Prism Evaluation In-House/Peer Round Table Year-of-Construction Costs Cost Containment Table Estimation Scorecard Project Baseline Scope Change Form Value Engineering
Communication
Identification of Changes
Value Engineering
76
Project Complexity Internal and external pressures can become problems, even on very small (dollarwise) and seemly simple projects. Urban projects that impact the community and projects through environmentally sensitive areas will usually generate signicant external pressure. So the issue is more dependent on project content than on complexity. Tips for Success If state highway agencies truly want accurate project estimates, there must be organization structures in place that shield estimators from external and internal pressures to produce a low project estimate. Additionally, to control scope and, consequently, project cost, management must require that an estimate of the cost associated with any scope change accompany the change request. Tools B2.1 Board Approvals B2.2 Constrained Budget B2.3 Management Approvals
estimate should diminish, but there will still be uncertainty, and the level of uncertainty must be effectively communicated. Communication between internal departments of an agency is imperative throughout project development given the intricacy and number of people involved in developing even the simplest project. Tools C1.1 C1.2 C1.3 C1.4 C1.7 Communication of Importance Communication of Uncertainty Communication within State Highway Agency Denitive Management Plan Year-of-Construction Costs
7.2.2 Communication
Why? A thorough understanding of community expectations, together with the identication and communication of the uncertainty, project scope, and cost unknowns, helps in managing project cost in all phases of project development. Communication is a very important aspect of state highway agency relations with third parties, and it is important in conveying the precision of the estimate. In Figure 7.1, this involves the input from third parties, the determine risk step, and the statements about estimated cost (including the values from the prepare base estimate, review estimate, and engineers estimate activities). Project Complexity Inherently, complexity adds risk to a project; therefore, the importance of communication, particularly communication of uncertainty, becomes more important with project complexity and project visibility. Tips for Success Institutional communication demands attention not just to content, but also to attitudeopenness, accessibility, and sincerity are necessary. As the project moves through preliminary design to nal design, the amount of uncertainty in the
77
any downstream changes to the determine estimate basis (scope/location) step. Project Complexity Establishing reliable baseline denitions of scope and cost in the early stages of project development is difcult, primarily because of the many project unknowns at that time. However, studies have found that projects that receive the most robust front-end planning have the fewest problems during execution. The establishment of a project scope and cost baseline is fairly straightforward for routine projects and becomes more difcult as project complexity increases. Yet it is with the complex project that the use of this method will yield the greatest benets. Tips for Success Engineering and construction complexities caused by the projects location or purpose can make early design work very challenging and lead to internal coordination errors between project components. Constructability problems that need to be addressed may also be encountered as the project develops. Early identication of such issues and a structured system for controlling their impacts is essential to achieving estimate quality. Tools I1.1 I1.2 I1.3 I1.4 Cost Containment Table Estimation Scorecard Project Baseline Scope Change Form
78
found at www.fhwa.dot.gov/ve/vereg.htm and the policy at www.fhwa.dot.gov/ve/veplcyg.htm) requires state highway agencies to ensure that a value engineering analysis has been performed on all federal-aid highway projects on the National Highway System with an estimated cost of $25 million or more and that all resulting, approved recommendations are incorporated into the plans, specications, and estimate. Project Complexity With straightforward or routine projects, there may be limited opportunity to realize savings by means of a value engineering process. However, as project complexity and scope increase, so do the opportunities to apply value engineering and realize signicant savings while retaining quality. Tips for Success During feasibility studies, preliminary design, and even detail design, the relative expenditures for value engineering studies are small compared with the cumulative cost of the project. Typically, engineering fees amount to less than 10% of total construction costs. However, the decisions and commitments made during design have great inuence on the cost of construction, a far greater inuence than what the constructor can effect by making changes during the actual construction process. Tool V2.1 Value Engineering
However, market conditions and macroeconomic events, which state highway agencies and estimators do not commonly consider, can signicantly affect project cost. These events are related to regional or even global economic conditions. Agencies should seek to implement management approaches identied in Table 7.4, which will help in identifying such impacts. There are three different off-prism issues methods described here for use during the nal design phase of project development.
7.3.1 Communication
Why? Communication was stressed for a scope and schedule strategy in Section 7.2, and communication is also extremely important in an off-prism issues strategy. Agencies are very good at articulating the engineering aspects of a project, but often are blind sided by macroeconomic events and challenges. Figure 7.1 has a market conditions input activity to call attention to this need to be aware of the economic conditions under which the project will be pursued. This is an area of analysis where the engineering community has very little experience or training. When dealing with stakeholders, communication of the uncertainty and of project scope and cost unknowns is critically important. As the project moves through design, the amount of uncertainty in the estimate should diminish, but there will still be uncertainty, and the level of uncertainty must be communicated. Communication between internal state highway agency departments is imperative throughout project development given the number of parties involved in even the simplest of projects. There should be a denite point during project development when the scope is xed. This decision point should be clearly identied.
Table 7.4. Final design phase off-prism issues strategy: Methods and tools.
OFF-PRISM ISSUES STRATEGY
Use proactive methods for engaging external participants and assessing the macroenvironmental conditions that can influence project costs
Communication
C1.2 C1.3 C1.5 Communication of Uncertainty Communication within State Highway Agency Proactive Conveyance of Information to the Public Right-of-Way Estimator Training Separate Right-of-Way Estimators
Risk Analysis
R3.2 R3.4 ContingencyIdentified Estimate Ranges
Right-of-Way
R2.5 R2.6
79
Project Complexity Inherently, complexity adds risk to a project; therefore, the importance of communication, particularly communication of uncertainty, becomes more important with increasing project complexity and project visibility. Tips for Success Communication is about both listening to stakeholders and providing accurate information to include knowledge about uncertainty. Estimators must realize that the project cost can be severely impacted by market and macroeconomic factors, and they must communicate this to state highway agency management. Tools C1.2 Communication of Uncertainty C1.3 Communication within State Highway Agency C1.5 Proactive Conveyance of Information to the Public
that feed data to those preparing the estimate. These sections must be active participants in a projects development. Tools R2.5 Right-of-Way Estimator Training R2.6 Separate Right-of-Way Estimators
7.3.2 Right-of-Way
Why? Estimators who work in a vacuum and fail to consider the information provided by other state highway agency disciplines cannot produce accurate estimates. Figure 7.1 shows the estimation processprepare base estimatebeing supported by an input from disciplines step. The costs of various project items that are included in the estimate must be managed in different ways, and they are usually the responsibility of different sections of a state highway agency, so estimators must involve those supporting sections in order to produce accurate project cost estimates. Project Complexity As projects become more complex, there is a greater need for coordination and communication between the disciplines participating in the development of the projects scope and estimate. Many more factorsright-of-way cost, multiple utility companies, railroads, agencies that grant environmental permitsimpact the cost of projects in urban environments and projects that cross environmentally sensitive areas. The typical highway or bridge project team must be expanded to include expertise in dealing with these other matters. Tips for Success An accurate cost estimate and schedule is dependent on information from the many supporting sections of an agency
80
Agencies should be seeking to implement the management solutions identied in Table 7.5. However, it must not be forgotten that success in estimation practice is linked to the working environment created by agency management. There are three different risk methods described here for use during the nal design stage of project development.
the truth about project cost and to identify the precision of estimate values. Tools C1.2 C1.3 C1.4 C1.7 Communication of Uncertainty Communication within State Highway Agency Denitive Management Plan Year-of-Construction Costs
7.4.1 Communication
Why? When dealing with external stakeholders, communication of uncertainty and of project scope and cost unknowns is critically important. Any uncertainty about project scope, schedule, and cost must be clearly communicated both within the agency and to external parties. Communication was stressed in terms of its requirement to support a scope and schedule strategy in Section 7.2 and in terms of listening to third parties in Section 7.3. In terms of a risk strategy, communication has to do with how the precision of an estimate is communicated to agency management and to parties outside of the agency. Figure 7.1 includes two notations depicting these communication actions: the release engineers estimate sidebar and the obtain appropriate approvals step. Project Complexity Inherently, complexity and long project development durations add risk to a project; therefore, the importance of communication, particularly communication of uncertainty, becomes greater with greater project complexity and visibility. Tips for Success Communication is about providing accurate information, including knowledge about uncertainty. To maintain creditability with stakeholders, it is important to tell the public
Table 7.5. Final design phase risk strategy: Methods and tools.
RISK STRATEGY
Identify risks, quantify their impact on cost, and take actions to mitigate the impact of risks as the project scope is developed
Communication
C1.2 C1.3 C1.4 C1.7 I2.1 I2.2 Communication of Uncertainty Communication within State Highway Agency Definitive Management Plan Year-of-Construction Costs Red Flag Items Risk Charter
Risk Analysis
R3.2 R3.3 ContingencyIdentified ContingencyPercentage
Identification of Risk
81
typically based on a scientic assessment of risk rather than on simple engineering judgment. The charter may address the likelihood of the risk, the cost and schedule implications of the risk, and mitigation suggestions, as well as identify which risks can have the largest impacts on the project. Tools I2.1 Red Flag Items I2.2 Risk Charter
Table 7.6. Final design phase delivery and procurement strategy: Methods and tools.
DELIVERY AND PROCUREMENT STRATEGY
Apply appropriate delivery methods to better manage cost because project delivery influences both project risk and cost
Constructability
C5.1 Constructability Reviews Market Conditions
82
global economic conditionsthat is, off-prism issues. The macroenvironment can affect project cost in two ways: (1) by being unknown or unrecognized by project managers and estimators and (2) by changes in the environment that are completely external to the project. This method, Off-Prism Issues, is also another strategy unto itself. See Section 7.3 for more information about this strategy. However, note that the off-prism issue tool that most directly relates to delivery and procurement is I3.3, Market Conditions. Project Complexity As project complexity increases, the number of off-prism issues to be considered increases. Tips for Success Unlike other aspects of project planning and estimation, understanding the macroenvironment has never been standardized as part of project estimation. It is therefore important to develop planning processes that focus on community concerns, externally imposed requirements, and external market conditions. Tool I3.3 Market Conditions
provide guidance as to the project construction phasing and staging approaches required to cost-effectively build the project. In this way, constructability will inuence both update design basis and prepare base estimate steps (see Figure 6.1). Project Complexity As project complexity increases, the need for construction knowledge and experience in reviewing designs becomes critical. Construction input can aid the designer in developing designs that can be constructed more efciently. This need is especially important for very large and complex projects, such as those in urban areas under high-traffic volumes. These types of projects require continuous input from construction experts beginning with project denition during programming and throughout preliminary design. Tips for Success Constructability is most successful when the process is formalized and is an integral part of the programming and preliminary design phase of project development. Identifying and using appropriate constructability experts is also critical in achieving successful constructability reviews. A constructability expert must be able to work effectively with project designers and provide meaningful input on design documents. Tool C5.1 Constructability Reviews
7.5.2 Constructability
Why? The quality of the documents used to prepare estimates impacts the quality of the estimate in terms of accuracy. Thus, design documents that provide the basis for cost estimates must accurately portray the design intent. Implementing constructability analysis will enhance project documents by reducing the potential for errors and omissions and will produce designs that are constructible. Constructability reviews can
Table 7.7. Final design phase document quality strategy: Methods and tools.
DOCUMENT QUALITY STRATEGY
Promote cost estimate accuracy and consistency through improved project documents
Computer Software
C2.1 C2.2 E1.1 E1.2 Agency Estimation Software Commercial Estimation Software Estimate/Document ReviewExternal Estimate/Document ReviewInternal
Estimate/Document Review
83
Project Complexity The formality of a project estimate review and the depth of the review will vary depending on the type of project and project complexity. In the case of routine straightforward projects, a formal review may not be necessary. However, as project complexity and scope increase, it is necessary to conduct formal reviews. When very complex projects are being estimated, management should require that there be an external review of the estimate by qualied professionals. Tips for Success To be of value, the review must closely examine the assumptions that form the basis of the estimate. Knowledgeable and experienced individuals who bring a broad perspective to the project and estimate formulation should be assigned to conduct the review. Tools E1.1 Estimate/Document ReviewExternal E1.2 Estimate/Document ReviewInternal
84
used by both state highway agency estimators and design consultants retained for estimation purposes. This guidance document should be specically written for those having responsibility for preparing the nal engineers estimate and should discuss how assumptions are to be documented. It should both address how unit costs are to be derived from the agencys databases and supply the documentation necessary to support decisions to use other cost values. Tool D4.1 Project Estimation File
egy for use during the nal design stage of project development. Management support for internal estimate reviews is usually not an issue, but in the case of complex projects, management should have procedures in place for organizing and conducting external reviews.
Table 7.8. Final design phase estimate quality strategy: Methods and tools.
ESTIMATE QUALITY STRATEGY
Use qualified personnel and uniform approaches to achieve improved estimate consistency and accuracy
Consistency
C4.2 C4.3 C4.4 C4.5 C4.6 C4.7 Estimation Checklist Estimation Manual (Guidelines) Estimator Training Major Project Estimation Guidelines Standardized Estimation and Cost Management Procedures State Estimation Section Expert Team Formal Committee Off-Prism Evaluation In-House/Peer Round Table Agency Estimation Software Commercial Estimation Software Cost Based Historical Bid Based Trnsport
Estimate ReviewExternal
E2.1 E3.1 E3.2 E3.3 E3.4 Expert Team Formal Committee Off-Prism Evaluation In-House/Peer Round Table
Estimate ReviewExternal
E2.1 E3.1 E3.2 E3.3 E3.4 P1.1 P1.2 P1.3 P1.4 P1.5
Estimate ReviewInternal
Estimate ReviewInternal
85
nation step. However, for major projects this could be a repetitive activity. Project Complexity The formality of a project estimate review and the depth of the review will vary depending on the type of project and the projects complexity. In the case of very complex projects or projects involving new construction methods, estimation management should require that there be an external review of the estimate by qualied professionals. Tips for Success The external review should carefully study the scope and schedule of the project as described in the contract documents. To be of value, the review must closely examine the match between the stated scope and the project design as presented in the contract documents that are available at this point in project development. Tool E2.1 Expert Team
Tools E3.1 E3.2 E3.3 E3.4 Formal Committee Off-Prism Evaluation In-House/Peer Round Table
7.7.3 Consistency
Why? Consistency is achieved by instituting operating procedures that serve as guides for performing estimation processes. Therefore, in Figure 7.1, consistency comes to play in all the processes: the input from disciplines, input from third parties, market conditions, historical data, prepare base estimate, determine risk, and review estimate. Estimates must be structured and completed in a consistent manner. Uniform estimate presentation supports analysis, evaluation, validation, and monitoring of item costing. The purpose of a uniform estimate structure is to avoid duplications as well as to ensure that there are no omissions. Project Complexity Attainment of estimation efciencies across the agency demands that there be consistent estimation processes to provide ease in reporting, enable data sharing, and make recognition of errors much easier. This becomes critically important as project complexity increases. Consistency enables multiple estimators to complete various items of the estimate and then combine and coordinate their work. These methods permit a second estimator to continue the work from any point where the rst estimator stops or to easily check the work of another estimator. Tips for Success The foundation of a good estimate is the formats, procedures, and processes used to arrive at the cost. Success in terms of estimate quality is attained by investing the time and effort in developing consistent estimation processes that match how the agency develops its projects. Tools C4.2 C4.3 C4.4 C4.5 C4.6 Estimation Checklist Estimation Manual (Guidelines) Estimator Training Major Project Estimation Guidelines Standardized Estimation and Cost Management Procedures C4.7 State Estimation Section
86
low project estimate will support accurate project estimation. Estimate reviews to ensure integrity are repetitive, taking place to some extent whenever the estimate is modied, as shown with the estimate review activity in Figure 7.1. Agencies should, therefore, institute the estimating practices identied in Table 7.9. There are two different integrity methods described here for use during the nal design phase of project development.
Table 7.9. Final design phase integrity strategy: Methods and tools.
INTEGRITY STRATEGY
Ensure that checks and balances are in place to maintain estimate accuracy and to minimize the impact of outside pressures that can cause optimistic biases in estimates
Estimate ReviewExternal
E2.1 E3.1 E3.3 E3.4 Expert Team Formal Committee In-House/Peer Round Table
Estimate ReviewInternal
87
7.9 Summary
Table 7.10 lists all of the methods and tools presented in this chapter for use in the nal design phase of project development. This list can be used as a quick reference to navigate directly to the Tool Appendix for the descriptions of the tools. Tools are listed in Appendix A alphabetically by method, as shown in Table 7.10. Table 7.10 can also be used as a checklist for selecting tools that should be employed on any one project. The checklist forms a self-assessment tool for agencies to benchmark against. These methods and tools were found in highway agencies throughout the country. While no agency was found to possess all of the methods and tools, all methods and tools exist and have the potential to be applied by any single agency.
88
CHAPTER 8
Implementation
Introduction
This Guidebook is intended to assist in creating a strategic change in agency estimation and cost management approaches. It aligns strategies with identied problem areas and can be used to create organizational structures for achieving consistent and accurate project estimates. Additionally, it presents detailed methods and tools to support the strategic approaches. While individual strategies, methods, and tools should be implemented, they should not be used in an al la carte fashion. Implementation must occur within the context of a greater vision for integrating cost estimation practice and cost estimation management processes across all agency programs and with agency consultants. Although the estimation approach transformation can begin at any organizational level, ultimately all levels must participate to create a cultural change in addressing the challenges of cost estimation practice and cost estimation management throughout planning and the project development process. Table 8.1 summarizes the implementation goals at the organization, program, and project levels. Some of the goals may require organizational change, and all of the goals will require a commitment of resources. This chapter describes each of the implementation thrusts in Table 8.1 and concludes with an integrated approach to their implementation.
Chapter 3 of this Guidebook presented eight strategies that were developed by observing and synthesizing practices from highway agencies around the country:
Management strategyManage the estimation process and
costs through all stages of project development; Scope and schedule strategyFormulate definitive processes for controlling project scope and schedule changes; Off-prism strategyUse proactive methods for engaging external participants and assessing the macroenvironmental conditions that can inuence project costs; Risk strategyIdentify risks, quantify their impact on cost, and take actions to mitigate the impact of risks as the project scope is developed; Delivery and procurement strategyApply appropriate delivery methods to better manage cost because project delivery inuences both project risk and cost; Document quality strategyPromote cost estimate accuracy and consistency through improved project documents; Estimate quality strategyUse qualied personnel and uniform approaches to achieve improved estimate consistency and accuracy; and Integrity strategyEnsure that checks and balances are in place to maintain estimate accuracy and to minimize the impact of outside pressures that can cause optimistic biases in estimates.
The implementation of these strategies will require a long-term commitment to change. Implementation should be approached as a continuous process of assessing, planning, assigning responsibility, and measuring performance. Honest assessment of the strategies is imperative at the beginning of this process. Planning requires a thoughtful approach to stafng and resource commitment in those areas that need the most improvement. The outcome of assessment and planning is the assignment of responsibilityexecutive managers must champion the implementation of specic strategies. Finally,
Implementation Focus
Strategies
Implementation Goals
Implement strategies across the agency: Assess current status of strategy implementation Plan for long-term implementation Assign responsibility for implementation Measure results of implementation Implement methods across programs: Assess current status of method implementation Develop policies and procedure manuals Develop training and education Implement tools across projects: Assess current status of tool implementation Determine subject matter experts Conduct pilot studies for new implementation Develop or revise agency-specific tools
Program Level
Methods
Project Level
Tools
the party that is assigned the responsibility for implementation should measure the performance of the implementation effort and periodically report on the status of progress. The process will create a loop of continuous improvement, as depicted in Figure 8.1.
Program Manager, State Construction Engineer, Director of Project Development, Director of Information Technology, Transportation Planning Administrator, Value Engineering Coordinator, Director of Preconstruction, District/Region Preconstruction Engineer, State Estimates Engineer, and Senior Project Manager.
In Connecticut, design consultants often prepare project estimates and have a place on the committee. Other committee members included representatives from other areas in the state highway agency, such as maintenance, utilities, trafc engineering, right-of-way, real estate services, and environmental. External partners included the FHWA, local governments, MPOs, counties, cities, and local governments.
Assessing
Measuring Performance
Planning
Assigning Responsibility
90
the workshop loosely followed the organization of this Guidebook and is outlined as follows:
Introduction
Strategic goals of cost estimation practice and cost estimation management Presentations and perspectives from state highway agency peers and program managers Discussion of current and available strategies, methods, and tools Planning Programming and preliminary design Final design Discussion of strengths, weaknesses, opportunities, and threats Discussion of strategies for a path forward The steering committee and workshop examples are provided to demonstrate two initiatives that will assist in the implementation of estimation strategies at the organizational level. The key is to address the problem in a systematic manner.
Currently in Use
91
research. While the list is not intended to be comprehensive, it can be used as a starting point for the development of policies and procedures:
Project scope denition and estimate basis, Project baseline denition, Estimate timing/milestones, Scope change process, Project cost containment, Communication of estimates, Cost risk assessment process, Application of contingency, Estimate quality control and quality assurance, Effects of ination and year-of-construction costs, Appropriate estimation methods, Available estimation tools, and Historic data maintenance and use.
mation staff. However, if a new risk-based methodology for determining the contingency included in estimates is deployed throughout project development, implementation of this methodology will require education and training components across a broader cross section of disciplines. Because, in many states, consultants prepare project estimates, there is also a need to train consultant engineers concerning the state highway agencys cost estimation standards and procedures.
Examples of Use
B1.5
Buffers
B2.1 B2.2 B2.3
Additional Methods
92
conjunction with a detailed review of the tools in Appendix A and the methods described in Chapters 5 through 7. Rather than simply noting a yes or no answer for the assessment of tools, the table suggests noting examples of use. This is necessary because the detailed application of the tools can vary from agency to agency and even within an agency. For example, the tool B2.3, management approvals, can take many different forms throughout an agency. The key in this example would be to note where the management approvals exist and discuss whether there is a need for this tool in other places in the planning and project development process. Where tools are already in use by an agency, it is helpful to identify a subject matter expert. Subject matter experts can also be assigned to investigate and develop tools that are not currently in use. Comments for future use should describe whether the tool has potential for implementation and how the agency should begin to implement the tool.
local and stakeholder involvement. Some of the tools presented in Appendix A were developed through national initiatives sponsored by AASHTO or the NCHRP, but the majority of tools were developed within individual agencies. State highway agencies should strive to continuously develop and improve on their suite of cost estimation practice and cost estimation management tools. When, due to a specic project requirement, new tools are developed, agency management should consider implementation of the tool across projects.
Management planDevelop a definitive management plan for the oversight of estimates. Public information plan Develop a definitive public information plan for communicating cost estimates to the public. TrainingDevelop estimation training modules for all branches of the agency that communicate (1) the importance of accurate cost estimate communication and (2) uncertainty involved in cost estimation.
will form a set of implementation activities that provide an actionable path forward. For example, Table 8.4 provides a set of three tools that can be implemented to improve the communication of estimates. The fourth column of Table 8.4 provides for the assignment of responsible parties, which will most likely come from the subject matter experts identied in Table 8.3. This column also provides for a noting of performance measures. While all tools should contribute to greater estimate consistency and accuracy, the performance measures should be specic to each tool. For example, a performance measurement for the management plan tool could be the percentage of management plans that contain specic references to cost management procedures. Using a structure similar to that shown in Table 8.4 provides a framework for implementing the strategies, methods, and tools described in this Guidebook. But agencies can develop
Summary
This chapter illustrates a purposeful approach to integrating and implementing the concepts found in this Guidebook. The framework proposed in the previous section is one method for creating a strategic path forward with the goal of improving cost estimation practice and cost estimation management. There is no one correct path to success. Agencies can develop other approaches that use the methods and tools presented in this Guidebook. However, to repeatedly achieve accurate and consistent cost estimates, agencies should adopt a systematic approach to cost estimation practice and cost estimation management that addresses cost escalation factors across the entire planning and project development process spectrum.
94
CHAPTER 9
Path Forward
Industry Problem
State highway agencies face a major challenge in controlling project budgets over the time span between project initiation and the completion of construction. Project cost increases, as reected by budget overruns during the course of project development, are caused by any number of factors, such as an inadequate project scope denition at the time of planning or programming, insufcient information on the extent of utility relocation requirements, insufcient knowledge of rightof-way costs, added environmental mitigation costs necessary to avoid impacts, trafc control requirements, and work-hour restrictions. The objective of this Guidebook is to assist state highway agencies in achieving better estimate consistency and accuracy during planning and project development.
A Strategic Approach
The cost escalation factors that lead to project cost increases have been documented through a large number of studies and matched to cost estimate changes that occur during project development. Each factor presents a challenge to a state highway agency seeking to produce accurate project cost estimates and managing project costs. These factors can all be addressed by using a strategic approach to estimation and cost management that is structured around the eight strategies and the following three elements:
Planning and project development process phases, Project complexity, and Basic cost estimation practice and cost estimation manage-
ment steps.
Guidebook Development
The Guidebook was developed after a focused review of current state highway agency estimation practices and an extensive examination of recent estimation research. Over half of the state highway agencies, representing all parts of the country, provided input on their current estimation practices and the problems they are experiencing. By a critical review of the literature and state highway agency information, the root causes of problems in cost estimation practice and cost estimation management were identied. The information also permitted the identication of viable and successful approaches to cost estimation practice and cost estimation management. An analysis of estimation literature and the information provided by the state highway agencies led to the development of eight strategies to address 18 factors that cause cost increases as experienced by state highway agencies during planning and project development. These eight strategies are linked to over 30 recommended methods for implementing the eight strategies and to over 90 tools for executing the specic methods.
Cost estimation practice and cost estimation management are processes that require the completion of a number of specic cost estimation steps. The cost estimation process necessitates completion of four basic steps that are applicable to the process across each development phase. These cost estimation steps are usually preformed sequentially and repeatedly as project development proceeds: 1. 2. 3. 4. Determine estimate basis. Prepare base estimate. Determine risk and set contingency. Review total estimate.
There are ve cost estimation management steps. Implementation of these steps varies by project phase. The cost estimation management steps are also preformed repeatedly as project development proceeds: 1. Obtain appropriate approvals. 2. Determine estimate communication approach.
95
3. Monitor project scope/project conditions. 4. Evaluate potential impact of change. 5. Adjust cost estimate.
Keys to Success
Disciplined cost estimation management and cost estimation practices should be applied in the context of the eight global strategies. This research has determined that 10 key principles must be followed to ensure creation of consistent and accurate estimates. Each individual principle in itself can help improve cost estimation management and cost estimation practice. However, maximum improvement of these two processes will only occur if the 10 key principles are incorporated into the agencys business practices throughout the organization. Within each group, the key principles are prioritized as follows. Cost estimation management: 1. Make estimation a priority by allocating time and staff resources. 2. Set a project baseline cost estimate during programming or early in preliminary design, and manage to this estimate throughout project development. 3. Create cost containment mechanisms for timely decision making that indicate when projects deviate from the baseline. 4. Create estimate transparency with disciplined communication of the uncertainty and importance of an estimate. 5. Protect estimators from internal and external pressures to provide low cost estimates. Cost estimation practice: 1. Complete every step in the estimation process during all phases of project development. 2. Document estimate basis, assumptions, and back-up calculations thoroughly.
3. Identify project risks and uncertainties early, and use these explicitly identified risks to establish appropriate contingencies. 4. Anticipate external cost inuences and incorporate them into the estimate. 5. Perform estimate reviews to conrm that the estimate is accurate and fully reects project scope.
Challenges
Implementing new concepts involves facing the challenges that accompany change. State highway agencies must consider several challenges when deploying this Guidebook:
Challenging the status quo and creating a cultural change
requires leadership and mentoring to ensure that all steps in the cost estimation management and cost estimation processes are performed. Developing a systems perspective requires organizational perspective and vision to integrate cost estimation management and cost estimation practice throughout the project development process. Dedicating sufficient time to changing agency attitudes toward estimation and incorporating the strategies, methods, and tools from this Guidebook into current state highway agency practices is difcult when resources are scarce. Dedicating sufficient human resources to cost estimation practice and cost estimation management beyond the resources that have previously been allocated to estimation processes. Meeting these challenges will ultimately require a commitment by the agencys senior management to direct and support change. The benet of this commitment will be manifested in projects that are consistently within budget and on schedule and that fulll their purpose as dened by their scope. This benet will also improve program management by allowing for better allocation of funds to projects to meet the needs of the ultimate customer, the public.
96
References
Akinci, Burcu, and Martin Fischer (1998). Factors Affecting Contractors Risk of Cost Overburden, Journal of Management in Engineering, Vol. 14, No. 1, American Society of Civil Engineers. Anderson, Stuart D., and Byron C. Blaschke (2004). NCHRP Synthesis of Highway Practice 331: Statewide Highway Letting Program Management, Transportation Research Board. http://trb.org/news/blurb_ detail.asp?id=4200. Arditi, David, Gunzin Tarim Akan, and Sam Gurdamar (1985). Cost Overruns in Public Projects, Project Management, Vol. 3, No. 4, Butterworth & Co. (Publishers) Ltd. Association for the Advancement of Cost Engineering (AACE) International (1997). AACE International Recommended Practice No. 17R-97: Cost Estimate Classification System. Booz Allen & Hamilton, Inc., and DRI/McGraw-Hill (1995). The Transit Capital Cost Index Study, Federal Transit Administration. http://www.fta.dot.gov/printer_friendly/publications_4855.html. Bruzelius, Nils, Bert Flyvbjerg, and Werner Rothengatter (2002). Big Decisions, Big Risk: Improving Accountability in Mega Projects, Transport Policy, Vol. 9, No. 2. Callahan, Joel T. (1998). TCRP Synthesis of Transit Practice 28: Managing Transit Construction Contract Claims, Transportation Research Board. http://www.trb.org/news/blurb_detail.asp?id=2433. Carr, Robert I. (1989). Cost-Estimating Principles, Journal of Construction Engineering and Management, Vol. 115, No. 4, ASCE. Chang, Andrew Shing-Tao (2002). Reasons for Cost and Schedule Increases for Engineering Design Projects, Journal of Management in Engineering, ASCE, January. Committee for Review of the Project Management Practices Employed on the Boston Central Artery/Tunnel (Big Dig) Project (2003). Completing the Big Dig: Managing the Final Stages of Bostons Central Artery/Tunnel Project, National Academies Press. http://www. nap.edu/catalog/10629.html. Condon, E., and F. Harman (2004). Playing Games, 2004 AACE International Transactions, PM.14.1-6. Cost/Schedule Controls Task force (1986). Scope Denition Control, the Construction Industry Institute, Publication 6-2, Bureau of Engineering Research, University of Texas at Austin. Daniels, B. (1998). A Legacy of Conict: Utahs Growth and the Legacy Highway, Hinckly Journal of Politics, University of Utah, Autumn. Flyvbjerg, B., M. S. Holm, and S. Buhl (2002). Understanding Costs in Public Works Projects: Error of Lie? Journal of the American Planning Association, Vol. 68, No. 3. Hall, Peter (1980). Great Planning Disasters, University of California Press.
Harbuck, R. H. (2004). Competitive Bidding for Highway Construction Projects, 2004 AACE International Transactions, EST.09.1-4. Hudachko, T. (2004). Legacy Parkway SEIS Moving Forward, Shared Solutions, Utah Transit Authority and Utah Department of Transportation. Hufschmidt, Maynard M., and Jacques Gerin (1970). Systematic Errors in Cost Estimates for Public Investment Projects, The Analysis of Public Output, J. Margolis (ed.), Columbia University Press. Mackie, Peter, and John Preston (1998). Twenty-One Sources of Error and Bias in Transportation Project Appraisal, Transport Policy, Vol. 5, No. 1, Institute for Transport Studies, University of Leeds, United Kingdom, 17. Maryland DOT (March 1, 2002). Summary of Independent Review Committee Findings Regarding the Woodrow Wilson Bridge Superstructure Contract. Massachusetts Highway Department (MassHighway) and the American Consulting Engineers Council (ACEC) (1998). Measuring Design Quality. Merrow, Edward W. (1986). A Quantitative Assessment of R&D Requirements for Solids Processing Technology Process Plants, Rand Corporation. http://www.rand.org/pubs/reports/R3216. Merrow, Edward W. (1988). Understanding the Outcomes of MegaProjects: A Quantitative Analysis of Very Large Civilian Projects, Rand Corporation. http://www.rand.org/pubs/reports/R3560. Merrow, Edward W., Kenneth K. Phillips, and Christopher W. Myers (1981). Understanding Cost Growth and Performance Shortfalls in Pioneer Process Plants, Rand Corporation. http://www.rand.org/pubs/ reports/R2569. Neuman, Timothy R., Marcy Schwartz, Leofwin Clark, and James Bednar (2002). NCHRP Report 480: A Guide to Best Practices for Achieving Context Sensitive Solutions, Transportation Research Board. http://www.trb.org/news/blurb_detail.asp?id=1373. New Jersey DOT (1999). Modified Design/Build Program: Progress Report #6. Noor, I., and R. I. Tichacek (2004). Contingency Misuse and Other Risk Management Pitfalls, 2004 AACE International Transactions, RICK.04.1-7. Parsons Brinckerhoff Quade & Douglas, Inc. (2002). Final Draft: DesignBuild Practice Report, New York State Department of Transportation. http://www.dot.state.ny.us/design/designbuild/dbprarep.pdf. Pearl, R. (2004). The Effect of Market Conditions on Tendering and Forecasting, AACE Transactions, Association for the Advancement of Cost Engineering International.
97
Pickrell, Don H. (1990). Urban Rail Transit Projects: Forecast Versus Actual Ridership and Costs, report DOT-T-91-04, U.S. Department of Transportation. Pickrell, Don H. (1992). A Desire Named Streetcar: Fantasy and Facts in Rail Transit Promotions and Evaluation, Journal of the American Planning Association, Vol. 58, No. 2. Ripley, P. W. (2004). Contingency! Who Owns and Manages It! 2004 AACE International Transactions, CSC.08.1-4. SAIC (2002). 2002 Survey by SAIC for Illinois DOT on the Current Use of Design-Build, Federal Highway Administration, www.fhwa.dot. gov/programadmin/contracts/survey02.cfm. Sawyer, John E. (19511952). Entrepreneurial Error and Economic Growth, Explorations in Entrepreneurial History, Vol. 4, No. 4, pp. 199204, 195152. Schexnayder, Cliff J., Sandra L. Weber, and Christine Fiori (2003). Project Cost Estimating: A Synthesis of Highway Practice. Report for NCHRP Project 20-07/Task 152. http://cms.transportation.org/ sites/design/docs/Project%20Cost%20Estimating%20Report.pdf. Schroeder, D. V. (2000). Comments on Legacy Highway Final Environmental Impact Statement, Sierra Club. http://utah.sierraclub.org/ ogden/legacycom.html. Semple, Cheryl, Francis T. Hartman, and George Jergeas (1994). Construction Claims and Disputes: Causes and Cost/Time Overruns. Journal of Construction Engineering and Management, ASCE, Vol. 120, No. 4. State of Alaska (1994). Department of Transportation and Public Facilities Highway Design Cost and Quality Comparison, Division of Legislative Audit. www.legaudit.state.ak.us/pages/audits/1995/pdf/4472.pdf. Tilley, P. A., A. Wyatt, and S. Mohamed (1997). Indicators of Design and Documentation Deficiency, Proceedings of the Fifth Annual Conference of the International Group for Lean Construction, 1617 July, Australia, 137148. Touran, Ali, and Paul J. Bolster (1994). Risk Assessment in Fixed Guideway Transit System Construction, Federal Transit Administration. U.S. General Accounting Ofce (1997). Transportation Infrastructure: Managing the Costs of Large-Dollar Highway Projects, report GAO/ RCED-97-47. http://ntl.bts.gov/lib/5000/5900/5978/rc97047.pdf. U.S. General Accounting Ofce (1999). Transportation Infrastructure: Impacts of Utility Relocations on Highway and Bridge Projects, report GAO/RCED-99-131. U.S. General Accounting Ofce (1999a). Mass Transit: Status of New Starts Transit Projects with Full Funding Grant Agreements, report GAO/RCED-99-240. www.gao.gov/archive/1999/rc99240.pdf. U.S. General Accounting Ofce (2002). Transportation Infrastructure Cost and Oversight Issues on Major Highway and Bridge Projects, report GAO-02-702T. www.gao.gov/new.items/d02702t.pdf. U.S. General Accounting Ofce (2003). Federal-Aid Highways: Cost and Oversight of Major Highway and Bridge ProjectsIssues and Options, report GAO-03-764T. http://www.gao.gov/new.items/d03764t.pdf. Utah Department of Transportation (2004). Legacy Parkway Project History. www.udot.utah.gov/index.php/m=c/tid=1056. Weiss, Lawrence L. (2000). Design/BuildLessons Learned to Date (Design/Build Initial Report), South Dakota Department of Transportation. Werkmeister, Raymond F., Jr., and Donn E. Hancher (2001). ParisLexington Road Project: Project Report, Transportation Research Record 1761: Construction 2001, Transportation Research Board. Woodrow Wilson Bridge Project (February 29, 2002). Bridge Superstructure Contract (BR-3): Review of the Engineers Estimate vs. the Single Bid.
APPENDIX A: TOOLS
A-iii
CONTENTS
A-1
A-1 A-1 A-2 A-4 A-4
B1 Budget Control
B1.1 Budget by Corridor B1.2 Constrained Budget (Also see B2.2) B1.3 Standardized Estimation and Cost Management Procedures (Also see C4.6) B1.4 Summary of Key Scope Items (Original/Previous/Current) B1.5 Variance Reports on Cost and Schedule
A-6
A-6 A-6 A-8
B2 Buffers
B2.1 Board Approvals B2.2 Constrained Budget (Also see B1.2) B2.3 Management Approvals
A-8
A-9 A-9 A-10 A-12 A-15 A-18 A-21 A-22 A-25 A-26 A-29 A-29 A-31 A-32 A-33 A-35 A-40 A-42 A-43
C1 Communication
C1.1 C1.2 C1.3 C1.4 C1.5 C1.6 C1.7 C2.1 C2.2 C2.3 C2.4 C3.1 C3.2 C3.3 C3.4 C3.5 Communication of Importance Communication of Uncertainty Communication within State Highway Agency Denitive Management Plan Proactive Conveyance of Information to the Public Simple Spreadsheet (Also see C2.4, D2.8) Year-of-Construction Costs (Also see E3.5) Agency Estimation Software (Also see C3.1, D2.2, P1.1) Commercial Estimation Software (Also see C3.2, P1.2) In-House Conceptual/Parametric Estimation Software Simple Spreadsheet (Also see C1.6, D2.8) Agency Estimation Software (Also see C2.1, D2.2, P1.1) Commercial Estimation Software (Also see C2.2, P1.2) Cost/Parameter Using Similar Projects Cost/Parameter Using Typical Sections Trnsport (Also see D2.9, P1.5)
A-39 C4 Consistency
C4.1 Cradle-to-Grave Estimators C4.2 Estimation Checklist (Also see P2.1, V3.1) C4.3 Estimation Manual (Guidelines)
A-iv
A-44 A-45 A-46 A-49 A-50 A-52 A-52 A-54 A-57 A-60 A-64 A-69 A-70 A-71 A-73 A-75 A-76 A-77 A-83 A-85 A-88 A-91 A-94 A-95 A-96 A-98 A-99 A-101 A-102 A-103 A-104 A-105 A-107 A-108
C4.4 Estimator Training C4.5 Major Project Estimation Guidance C4.6 Standardized Estimation and Cost Management Procedures (Also see B1.3) C4.7 State Estimation Section C5.1 Constructability Reviews C6.1 C6.2 C6.3 C6.4 Cost Containment Table (Also see I1.1, G1.2) Estimation Scorecard (Also see I1.2) Scope Change Form (Also see I1.4) Scoping Documents (Also see P2.2)
A-v
A-109 A-110 A-111 A-113 A-116 A-119 A-119 A-121 A-122 A-124 A-125 A-127 A-128 A-130 A-131 A-132 A-134 A-137 A-139 A-141 A-142 A-144 A-145 A-148 A-149 A-155 A-157 A-159 A-163 A-164 A-167
I1.3 Project Baseline I1.4 Scope Change Form (Also see C6.3) I2.1 Red Flag Items I2.2 Risk Charter I3.1 Environmental Assessment I3.2 Percentage of Total Project Cost (Also see E3.2) I3.3 Market Conditions P1.1 P1.2 P1.3 P1.4 P1.5 Agency Estimation Software (Also see C2.1, C3.1, D2.2) Commercial Estimation Software (Also see C2.2, C3.2) Cost Based Historical Bid Based (Also see D2.4) Trnsport (Also see C3.5, D2.9)
A-1
B1 Budget Control
Budget control tools assist in providing a disciplined approach to scope decisions that impact project cost. Budget control must begin early in project development. Two simple but essential principles of the budget control process must be clearly understood: (1) there must be a basis for comparison, and (2) only future costs can be controlled.
information becomes available over time. Used in conjunction with the constrained budget and/or design to cost tools, budgeting by corridor can provide a means to manage a portfolio of projects in a logical manner. When? This tool is used for preparing long-range estimates during the planning phase of project development. Examples The Washington State DOT has created an Urban Corridors Ofce in the Seattle Metro area to manage the states largest corridors. The Seattle-based Urban Corridors Ofce directs six of the DOTs largest projects, including the SR 99 (Alaskan Way Viaduct and Seawall Replacement Project), SR 520 (Bridge Replacement and HOV Project), and SR 509 (I-5 Freight and Congestion Relief, Access Downtown [Bellevue], I-90 Two-Way Transit and HOV, and I-405 Congestion Relief and Bus Rapid Transit Projects). More information can be found at http://www.wsdot.wa.gov/consulting/Ads/UrbanCorridors/ Misc/UCOOrganization.pdf. Tips A state highway agency may need to reorganize its management structure to effectively budget and control costs by corridor. This tool should be used in conjunction with other tools, such as constrained budget and design to cost. Resources Washington State DOT Urban Corridors Ofces: http:// www.wsdot.wa.gov/consulting/Ads/UrbanCorridors/Misc/ UCOOrganization.pdf.
A-2
What Is It? Highway projects often are authorized with resource limitations, particularly budget limitations. The projects are usually reconstructions, extensions, or additions to existing roadways. State highway agencies are often willing to undertake these projects with a specic cost commitment approach, which typically means that these projects have to be completed within a xed budget. Scope denition for such projects is directly related to the funds available. The constrained budget tool is perceived as a regulatory mechanism to evaluate and limit project scope to the absolutely necessary items alone and prevent any cost overruns. Why? Highway projects involve a huge sum of monetary resources, which often involve a signicant amount of consideration and give and take by legislators. The need and feasibility of a project has to be adequately justied while funds are being sought. In a resource-limited environment, some projects may be approved based on a limited resource allocationbudget. A mechanism is required to carefully monitor and use resources for such projects. The constrained budget tool was developed with these requirements in mind. What Does It Do? This tool is used to constantly evaluate whether or not the total project cost is within a predened or mandated budget while attempting to scope and design the project within the xed budget. The tool can also be perceived as a cost-cutting technique. The tool also ensures that critical elements of the project are sufciently included in the scope. This tool causes designers to seek innovative and low-cost designs as a means of meeting the cost restraints. When? This tool is used early in the project development process in the programming and preliminary design phase. The tool is needed when a budget has been mandated and when no increases will be allowed. Examples The state of Washington has recently passed several gas taxes that included legislated line-item budgets for different projects. These budgets are considered xed and cannot be increased. Cost estimates for many of these projects were prepared based on limited scope. WSDOT has initiated project control and reporting procedures to ensure that these constrained budgets are met.
Tips When developing a project under a constrained budget, the state highway agency should use a number of different tools to support this method. For example, Tool D3.1, design to cost, is an excellent tool to help ensure that the design is constantly being assessed from a cost estimate perspective. Tool V2.1, value engineering, should be used to evaluate different design alternatives to determine the lowest-cost option that provides the most scope for a project. Other budget control tools should also be used in conjunction with this tool. One issue that state highway agency estimators have to carefully consider under the constrained budget tool is articially reducing costs to maintain the budget as the design is developed. The integrity strategy should be followed to prevent this pressure from occurring. Resources WSDOT (2006). Project Management On-Line Guide. www. wsdot.wa.gov/Projects/ProjectMgmt. Project Management Institute (2004). A Guide to the Project Management Body of Knowledge: PMBOK Guide, Third Edition, Project Management Institute.
B1.3 Standardized Estimation and Cost Management Procedures (Also See C4.6)
The objective of standardizing procedures is to establish a common basis for all state highway agency project participants to follow when preparing cost estimates and to manage costs in a similar manner over the project development process. Change occurs frequently on projects as they are developed. Changes come from, for example, added scope, design development, and different site conditions than anticipated. Adopting standard procedures will aid project participants when making decisions regarding potential changes to current budgets, with the goal of controlling the project baseline budget. The integration of both cost estimation practice and cost estimation management through standardized procedures is a critical feature to successfully managing cost escalation. What Is It? This tool establishes a set of standards and procedures within a state highway agency to guide the preparation of estimates and management of costs through the various stages of project development. The objective is to provide a coherent policy basis for alleviating cost escalation by consistently providing timely feedback on the potential impact of changes to project budgets. Procedures provide a basis for how costs are managed, including who has authority to make decisions regarding changes to current budgets.
A-3
Why? Changes often impact costs, and the necessity to constantly monitor these impacts in relation to the budget is necessary to control cost escalation. The most effective cost management system is one that will allow the project team to develop designs and make decisions regarding design alternatives with full knowledge of the cost impact of their decisions. Standardized cost management procedures should facilitate controlling cost escalation throughout programming and design of project development. They also can help establish a cost-conscious atmosphere within the project team environment. What Does It Do? These procedures formalize project cost control approaches that will be followed throughout the project development phases through a standardized process for (1) monitoring project development for potential changes to the budget, (2) submitting potential changes, and (3) obtaining management approval of these changes. This cost control process aids the project team in monitoring costs and alerts the team to any major impacts with regard to the current budget. When? Standardized procedures must be established at an agency level for guiding project development work, specically for cost estimation and cost management. The procedures should be applied throughout the project development process. However, cost management can only begin when a baseline scope, cost, and schedule are set. Examples The Missouri DOT has developed a set of estimation and cost management procedures that are applied from need identication through to the nal design stages. These procedures are closely tied to the Missouri DOT project development process. There are clear denitions of terms and the identication of a timeline for the different steps to be followed for a project to be realized. As a need is transformed into a real project, based on available information, appropriate estimation techniques are indicated to accurately derive cost estimates. Further, signicant taskssuch as public input, environmental considerations, and the proper channels to obtain approvals as cost estimates are developedhave been incorporated into the Missouri DOT procedures (see C4.6 example). An outline of the contents of the Missouri DOT procedure is provided below: 1-02.1 PURPOSE 1-02.2 GENERAL OVERVIEW 1-02.3 NEEDS INDENTIFICATION
1-02.4 NEEDS PRIORITIZATION 1-02.5 INITIAL PROJECT ESTIMATES 1-02.6 PROJECT SCOPING 1-02.7 PROJECT SCOPING MEMORANDUM 1-02.8 PROJECT SCOPING CHECKLISTS 1-02.9 PROJECT PRIORITIZATION 1-02.10 STIP COMMITMENTS 1-02.11 SCOPE CHANGES 1-02.12 PROJECT COST ESTIMATES 1-02.13 ENGINEERS ESTIMATE 1-02.14 BID ANALYSIS PROCESS 1-02.15 RECOMMENDATION FOR AWARD OR REJECTION OF BIDS A tracking system for potential amendments to budgets is also covered in the Missouri DOT procedures to monitor changes and update the estimate accordingly. A set of submittal and approval forms indicating changes and justication of these changes to current budgets keeps key personnel informed of cost variations. An example of a project control form for scope changes included in the Missouri DOT procedure can be found under Tool C6.3, scope change form. Tips Budget control can only begin once a baseline cost estimate is prepared for a project. Cost management procedures should include project control forms and directions on when and how to complete these forms. Further, the procedures should identify levels of approval for accepting changes to the budget based on dollar size of the change. Smaller cost changes can be approved at the project level, while larger cost changes would require region/district or headquarters management approval. Resources Becker, Daniel (2003). Controlling Construction Costs During Design, AACE Transactions, AACE International, Vol. F-5, 14. Schloz, Michael J. (1977). Project Cost Management During Conceptual Engineering, AACE Transactions, AACE International, 167172. Sturgis, Robert P. (1967). For Big SavingsControl Costs while Dening Scope, AACE 11th National Meeting, AACE International, Vol. 67-C.3, 4952. Missouri DOT (2004). Chapter 1, General Information: Needs Identification Project Scoping and STIP Commitments, Section 1-02, Project Development Manual, Revision April, 12, 2004. www.modot.org/business/manuals/ projectdevelopment.htm. Project Management Institute (2004), A Guide to the Project Management Body of Knowledge: PMBOK Guide, Third Edition.
A-4
Tips As a means to monitor budget and schedule variances, compare original and current project scopes at key project development milestones and when changes arise. Resources California DOT Division of Design. Project Development Procedures Manual. www.dot.ca.gov/hq/oppd/pdpm/ pdpmn.htm. South Dakota DOT. Scope SummaryRoad Design Manual. www.sddot.com/pe/roaddesign/docs/rdmanual/rdmch03.pdf.
A-5
Element Grading Aggregates Paving Bridge Approach Panels Mobilization Removal/Salvage Drainage Traffic Control Turf/Erosion Signing Lighting Temporary Construction Utilities Aesthetics Retaining Walls Noise Walls Bridges Signals/Traffic Management Systems Right of Way Project Development/ Delivery
Includes
Examples Cost containment tables are a simple but powerful form of variance reporting. Sections C6.1 and I1.1 contain excellent descriptions and examples of cost containment tables. Figure C6.1 can be used to create a variance report, which is simply a report that documents variances in cost to management as a project progresses through the development process. Variance reports are generated at key project milestones or when signicant changes in the project occur. Tips Consider different variance report details and intervals depending on the level of complexity of the project or phase of project development. Intervals should be closer together on
highly complex projects or projects that are in a phase of high activity. Even during periods of inactivity, projects should be regularly examined to ensure that there are no variances in project costs or schedule. Variances should be reported to appropriate levels of management if the magnitude of the deviation warrants. Consideration should be given to the impact of multiple small deviations that alone do not account for much difference from the budget or schedule but collectively amount to a problem. Safeguards should be in place to watch for this type of activity. Resources FHWA (2004). Lessons Learned: Federal Task Force on the Boston Central Artery/Tunnel Project (Summary of 34 Rec-
A-6
ommendations). www.fhwa.dot.gov/programadmin/mega/ lessonsa.htm. Federal Aviation Administration (FAA) uses baseline instability or variance from an origin to determine cost and schedule deviations. See www.faa.gov/acm/acm10/reports/ Instability/introduction.htm. Metropolitan Transportation Authority of New York, Sample of Variance Report can be found at www.mta.net/ board/Items/2005/04_ April/20050407OtherSectorWES_ Item2D.pdf Washington DOT, Set of Deviation Guidelines: www. wsdot.wa.gov/NR/rdonlyres/76FAB4F0-7EBD-4104-9441B80D690DE4C1/0/DVP.pdf.
When? Board approvals can and should be used at key points during the development phase. Board approvals not only help to maintain clear scope denition, they also improve general communication between parties. (Also see C1.1, Communication of Importance.) Examples Washington State DOT uses board approvals to increase communication between the state and local agencies as well as all other parties involved with the project. For instance, board approvals are often used to discuss and decide upon deviations from standard procedures or varying design options. Table B2.1 is an example of choices that would need to be considered during a board meeting for approval. Involving key parties in scope decisions through a board approval process from the start of the design process can deter conicts that may surface later in project development and place undue pressure on estimators to maintain unrealistic budgets. Tips Use a facilitator to ensure that board meetings progress following the agenda and cover all of the required topics in a timely manner. Be prepared and take a proactive role; do not use board approvals as a crutch. Resources Washington State DOT, Design Manual. An online PDF version can be found at www.wsdot.wa.gov/fasc/Engineering Publications/Manuals/DesignManual.pdf. This le is very large (70 MB) and may take a long time to download. Washington State DOT, Building Projects That Build Communities, Chapter Three: Working Through Design, Review and Approval. An online PDF version can be fount at www.wsdot.wa.gov/biz/csd/BPBC_Final/#BPBC_Final.
B2 Buffers
The objective of buffers is to protect the state highway agency and particularly estimators from outside pressure that could bias or manipulate a project estimate. Buffers take the form of structured estimate approval processes. These formal estimate approvals obligate management and external parties to recognize and acknowledge changes in project scope and schedule.
What Is It? The constrained budget tool restricts the project cost to a predened limit and connes scope development within this cost constraint. Why? Scope development is often subject to external or internal pressures to maximize the scope for a project, which may have an impact on the estimators decisions when preparing cost estimates. The constrained budget tool reduces the impact of such potential barriers for an estimator by setting cost constraints up front and then ensuring that the design is constantly tested against these cost constraints through frequent estimate updates. What Does It Do? This tool will require that the project team and estimators closely monitor project costs to keep costs within the xed budget, as there is no possibility for seeking additional funds. This tool acts as a buffer because it, by default, protects the estimator from pressure to articially reduce cost. When? This tool is used in programming and early in preliminary engineering and consistently acts a budget control mechanism throughout the design process.
Examples The State of Washington has recently passed several gas taxes that included legislated line-item budgets for different projects. These budgets are considered xed and cannot be increased. Cost estimates for many of these projects were prepared based on limited scope. WSDOT has initiated project control and reporting procedures to ensure that these constrained budgets are met. As part of project control and reporting procedures, quarterly reports are presented to region and headquarters management with the intent to provide the most current cost and reveal any potential cost increases so decisions can be made to realign cost estimates with the xed budgets. This is an effort to reduce surprises and, in this way, protect the project team from downward biasing of costs simply to meet a given budget. Tips When developing a project under a constrained budget, the state highway agency should use a number of different tools to support this method. For example, Tool D3.1, Design to Cost, is an excellent tool to help ensure that the design is constantly being assessed from a cost estimation perspective. Tool V2.1, Value Engineering, should be used to evaluate different design alternatives to determine the lowest-cost option that provides the most scope for a project. Other budget control tools should also be used in conjunction with this tool. One issue that state highway agency estimators have to carefully consider under the constrained budget tool is articially
A-8
reducing costs to maintain the budget as the design is developed. Management can play an important role in reducing pressures to estimate on the low side. Resources Washington State DOT (2006), Project Management Online Guide. www.wsdot.wa.gov/Projects/ProjectMgmt. Project Management Institute (2004). A Guide to the Project Management Body of Knowledge: PMBOK Guide, Third Edition.
Examples Scope changes usually drive cost changes, so those authorized to sign off on scope changes need to know the cost impacts. Therefore, the agency may structure the approval process based on the effect of the requested change on estimated project cost. To do this, it is necessary that an estimate of the cost effects of any scope change be submitted with the approval request. All major scope changes to a project must be approved by at least two members of the agencys senior management, and a copy of the scope change approval letter is retained in the project estimation le. All major cost increases/decreases to a project must be approved by at least two members of the senior management. Such approvals must be in writing, and copies of the approval letters must be maintained both by project management and by those responsible for developing the project estimate (there should also be a copy in the estimation le). Tips An agency can set dollar limits that determine when agency management approval is required. These dollar limits can be graduated and tied to different levels of responsibility within the project team, within the management hierarchy of a region/district, or within the headquarters at a senior management level. Resources Missouri DOT (2004). Chapter 1, General Information: Needs Identification Project Scoping and STIP Commitments, Section 1-02, Project Development Manual, Revision April, 12, 2004. www.modot.org/business/manuals/ projectdevelopment.htm.
C1 Communication
Proper communication of project cost estimates can help to solve many cost escalation problems. Key communication points are the communication of importance and the communication of uncertainty. A key question that must be communicated with each estimate is what decisions will be made from this estimate? Estimators need to know the purpose of an estimate to know the appropriate level of effort to expend on an estimate. The decisions that will be made from the estimate must be communicated at the time the estimate is being generated. Likewise, estimators have an obligation to communicate the level of uncertainty associated with an estimate so that inappropriate decisions are not made from the estimate.
A-9
The use of milestone estimates to convey importance is also very helpful. Pennsylvania DOT uses the following milestones in their estimating process:
Program amount (amount approved by the Program
Management Committee [PMC]) Engineering and environmental (E&E) scoping eld view 30% (design eld view) 75% (after nal design eld view) 95% (engineers estimate) Bid amount
By using these critical milestones, Pennsylvania DOT can convey the importance of these estimates. They know what decisions will be made at each of these milestone and what the current estimate is to communicate to external stakeholders. Estimates in support of design decisions will not be confused with milestone estimates. For more information on the Pennsylvania DOT system, see C6.1, Cost Containment Table. Tips Through workshops and continued reinforcement of the concept, develop an agency understanding of accurate estimate importance and the impact that inaccurate estimates may have on a project and program. Resources The Construction Industry Institute has numerous tools available on its website. Search for communication of importance at www.construction-institute.org.
A-10
Why? Projects are not well dened in the early stages of their development. Identication and communication of the projects early stage uncertainty and the fact that unknowns can impact scope and estimated costs will help in managing project expectations. What Does It Do? Communication of uncertainty creates transparency in the estimation process. It buffers estimators by conveying that estimates are not absolute, but rather predictions based upon the best information known at the time. This tool allows for more prudent decisions to be made from cost estimates. When? The identication and communication of the uncertainty in relation to project scope and cost unknowns helps in managing project cost in all phases of project development, but particularly in the programming and preliminary design phase. As the project moves from programming through preliminary design, the amount of uncertainty in the estimate should diminish. Good cost management techniques communicate specically how the design process has removed the uncertainty. Examples Examples of communication of uncertainty can be seen under the risk analysis method, R3.1. The following illustration from Washington State DOTs Cost Estimate Validation Process (CEVP) program is an excellent example of how to convey uncertainty concisely to the project team and any number of stakeholders. The Washington State DOT CEVP summary example (Figure C1.2) is an excellent demonstration of how to convey estimate uncertainty. It provides a cost range, rather than a point estimate, for both cost and schedule. It lists the risks associated with the project so that readers understand what is driving the uncertainty in an estimate. It also lists changes from periodic or milestone estimates. While the CEVP example may be too elaborate for most projects, the point of communicating estimates with a range or with a list of risks is applicable to most projects. Tips Transparently convey the uncertainty of each estimate. An estimate with uncertainty is not a bad estimate; it is a realistic estimate. Conveying uncertainty will allow better decisions to be made from estimate information.
Resources Caltrans Ofce of Project Management Process Improvement (2003). Project Risk Management Handbook. FHWA (2004). Major Project Program Cost Estimating Guidance. http://www.fhwa.dot.gov/programadmin/mega/ cenal.htm. Molenaar, K. R. (2005). Programmatic Cost Risk Analysis for Highway Mega-Projects, Journal of Construction Engineering and Management, Vol. 131, No. 3. Washington State DOT (2006). Cost Estimating Validation Process (CEVP) website. www.wsdot.wa.gov/Projects/ ProjectMgmt/RiskAssessment.
A-11
A-12
What Does It Do? A communication plan establishes a logical channel for project participants internal to the state highway agency to interact with each other. A good plan will eliminate ambiguities like where to nd what information and whom to consult for a specic problem in relation to the many different aspects of the project (including cost estimation management and cost estimation practice). In particular, the communication plan should identify who needs to be notied when changes are made that impact scope, cost, and/or schedule. When? An internal communication plan is used during all phases of the project development. However, this plan must be created as early as possible and may have to be updated as newer participants join the project team. The project team must be informed of any changes. Examples Lead project personnel can assign team members to create a stakeholders analysis with input from all participants, and then a communication matrix can be formulated. This process involves collection of data, such as different modes of communicating with different stakeholders (stakeholders as used in this example means project team members), period of unavailability, and alternative contact information. The top of Figure C1.3 shows a sample stakeholder analysis. Subsequently, a communication matrix is formulated matching the work breakdown structure (WBS) with all deliverables and timelines clearly indicated, as shown in the bottom of Figure C1.3. This will help eliminate ambiguities in determining responsible participants at any point in the project and will help reduce any delays caused by a communication blackout. Table C1.3 shows the table that Washington State DOT uses to structure the internal communication plan. The table addresses communication between and among the teams as well as communication protocols. The table helps to ensure that communication is open, honest, continuous and efcient. Tips A formal list of all project participants and their contact information must be created for every project, along with the participants duties and responsibilities. A portion of this list must be dedicated to communication related to cost estimation practice and cost estimation management. Educate and train project participants within a state highway agency on the importance of efcient communication. Ensure project participant awareness of the project communication plan.
Resources Harder, Barbara T., Neil J. Pedersen, Tom Warne, and Barbara Martin (July-August 2005). On Budget and On Time, TR News, Transportation Research Board. Caltrans (2003). Project Communication Handbook. www. dot.ca.gov/hq/projmgmt/documents/pchb/project_ communication_handbook.pdf. Additional information can be found at www.dot.ca.gov/hq/projmgmt/guidance_pchb.htm. Project Management Institute (2004), A Guide to the Project Management Body of Knowledge (PMBOK Guide). Washington State Project Management Process, Communication Plan Template, can be found at www.wsdot. wa.gov/Projects/ProjectMgmt/OnLine_Guide/Tools/ Communication_Plan.doc.
A-13
Figure C1.3. Sample stakeholder analysis (above) and communication matrix (below) (Caltrans Project Communication Handbook).
ture of work, and execution required by the executive management and project teams to complete a quality project on time, within budget, and safely. What Does It Do? The communication of a denitive project management plan can help to clarify project objectives, strategies, cost control requirements, project milestones, and project personnel. It can ultimately help state highway agencies to manage taxpayer resources for the highest possible return on value. It communicates that each project is unique and requires individual project management attention.
When? This tool can be used during all phases of project development. In planning, it will likely be most effective on large projects with clearly dened boundaries. The tool will be most helpful from preliminary engineering through nal engineering and into construction. Examples There are proven industry standards for project management. Perhaps the most pervasive standard is the Project Management Body of Knowledge (PMBOK) from the Project
Set guidelines
Clarify chain of command guidelines with other agencies and contractors Set protocols
Management Institute (PMI). According to the PMBOK, the organization and presentation of the project plan should include the following: 1. 2. 3. 4. 5. 6. 7. 8. 9. 10. Project charter A description of the project management strategy Scope of work, with the projects objectives Dene quality-level analysis Cost estimates, schedule start and nish dates, and responsibility assignments Performance measurements and baselines for technical scope, schedule, and cost Major milestones and the corresponding dates Required personnel and their expected cost Risk management plan (including main risks) and planned strategies, solutions, and contingencies for each risk Subsidiary management plan, including: Scope management plan Schedule management plan Cost management plan Quality management plan Stafng management plan Communications management plan
11. Open issues and pending decisions A second example comes from Washington State DOT. In July of 2005, the secretary of transportation issued Executive Order E 1032 to address project management at the agency level. The executive order contained guiding principles for the agency to follow. It provides an excellent point of discussion for this tool. The introduction of the executive order states as follows:
The Washington State Department of Transportation (WSDOT) has rened its project management process for delivery Capital Transportation projects. This process includes best practices, tools, templates and examples and will enhance the communication process for both pre-construction and construction project management. The Process, tools and templates can be found at www.wsdot.wa.gov/Projects/ProjectMgmt.
The project management website contains tools, templates, and examples that help project managers create denitive management plans. The website is extremely detailed. It covers tools and training in such areas as project management, cost
A-15
risk assessment, cost estimate validation, value engineering, project control and reporting, and innovative project delivery. Figure C1.4 provides a concise overview of the process. Communicating a denitive project management plan will assist in project estimation management and has proven successful in assisting to deliver projects on budget. Tips Intuition and numerous research studies have shown the benets of pre-project planning. A denitive management plan should be created early and revisited at key milestones throughout the project lifecycle. Resources Project Management Institute (2004). Project Management Body of knowledge (PMBOK Guide). www.pmibookstore.org/ PMIBookStore/productDetails.aspx?itemID=358&varID=1.
municate how they are managing the resources to maximize a states transportation system. Cost estimation practice and cost estimation management are vital processes to manage these resources. Transparency and proactive conveyance of estimate information can assist in cost estimation management. What Is It? This tool is a proactive approach for conveying cost estimate information to the public. It includes an action plan established for taking a proactive rather than defensive (or reactive) posture in gathering and transmitting information. Why? Public input can be vital to successful project completion. The public is the customer of every state highway agency. If the public does not agree with the project or some aspects of the project, there can be major impacts to project cost, schedule, and scope. Open and honest communication with the public can limit problems that impact project development. What Does It Do? A communication plan and the activation of the plan can create an open and honest dialogue between the agency and public. It creates accountability in cost estimation management for both the state highway agency and the public. This open exchange
A-16
creates a positive atmosphere in which the agency and public can express goals, questions, comments, and concerns. Not only does this allow for an exchange of information, but it also produces an air of accountability. The plan needs to be developed and followed actively throughout project development. When? To be effective, the plan needs to be instituted in the earliest stages of project development. Communication plans may be standard for all projects, but large, complex, and sensitive projects require more extensive information exchanges than small, simple projects. Examples Some state highway agencies have public awareness plans that include websites for larger projects. While this may be very benecial, state highway agencies should also make information available to the public regarding smaller, less controversial projects. This does not have to be a high-cost initiative on all projects. Consider using local and regional media, local schools, fairs, malls, focus groups, sponsorship of teams in walk-a-thons or benet races, advisory groups, town hall meetings sponsored by local organizations, billboards, yers, logo design competitions, or appearances at local civic club meetings.
Virginia DOT (VDOT) has created a Dashboard website, shown in Figure C1.5, which provides a wide variety of information to the general public regarding VDOT operations. The VDOT Dashboard site allows the public access to information on the number of projects in each phase of development, realtime information on specic projects, and milestone accountability of project development and engineering project activities. Information is transmitted using a traffic signal framework. The website enables the public to track any project. The website allows open communication between VDOT and the public and creates accountability to the public. Resources The VDOT Dashboard website: www.virginiadot.org. Scenario Planning: www.fhwa.dot.gov/planning/scenplan/ index.htm. Public Involvement Techniques for Transportation Decision-Making: www.fhwa.dot.gov/reports/pittd/cover.htm. Bell, J. (1998). Public Involvement, Low Budget Can Mean High Effectiveness, Proceedings: National Conference on Transportation Planning for Small and Medium-Sized Communities, http://ntl.bts.gov/card_view.cfm?docid=703. ODowd, Carol (1998). A Public Involvement Road Map, Proceedings: National Conference on Transportation Planning for Small and Medium-Sized Communities. http://ntl.bts.gov/ card_view.cfm?docid=701.
(a) Homepage
A-17
A-18
Engineering Dashboard Project Details
UPCs 4730 State Project # 0638073176
Map It Six-Year Program Details Construction Details Send Feedback Print Page
Summary
Description District County RTE 638 - RECONSTRUCTION (DILLWYN, PRINCE EDWARD) Lynchburg PRINCE EDWARD Residency Town Route 0638 DILLWYN
Contact Information
Manager/Designer Bruce Wooldridge William Leatherwood Phone 434-856-8253
Contact
Phone 434-947-2314
Schedule
Baseline Ad Date Current Ad Date Actual Ad Date 11/10/2009 11/10/2009
Cost Estimates
Scoping Estimate Current Estimate Estimate Date Variance $1,787,663 $1,343,100 3/15/2005 -25%
Shoemaker, Lee, and Tom Schwetz (1998). Sustaining Public Involvement in Long Range Planning Using Stakeholder Based Process: A Case Study from Eugene-Springeld, Oregon, Proceedings: National Conference on Transportation Planning for Small and Medium-Sized Communities. http://ntl.bts. gov/card_view.cfm?docid=702.
Spreadsheets and checklists, which identify the elements and activities included in (and excluded from) the estimate, can effectively communicate project cost and the distribution of that cost. What Is It? Spreadsheets are formatted standard lists of items that an estimator should consider when calculating the cost of a project. Because spreadsheets are usually straightforward documents, they are very good tools in communicating estimate completeness and the allotment of costs to the different portions of work.
A-19
Activities
Begin Date Activity AUTHORIZE PE SERP-NOTICE TO STATE AGENCIES SCOPE PROJECT Code Scheduled 12 18 22 05/16/1987 04/01/2004 04/01/2004 03/16/2001 Actual 05/16/1987 04/07/2004 04/01/2004 03/16/2001 End Date Scheduled 05/18/1987 07/30/2004 08/31/2004 11/30/2001 Actual 05/18/1987 06/11/2004 06/11/2004 03/20/2002
CONDUCT LOCATION 31S SURVEY PLAN DESIGN/PRELIMINARY 36F F.I. R/W&UT DATA44 HEARING/PUBLIC INV APPROVE WILLINGNESS FURNISH PLANS R/W&UT 47
07/16/2004
07/16/2004
12/13/2004
12/13/2004
12/13/2004
12/13/2004
09/28/2007
10/07/2007
02/04/2008
51
02/04/2008
04/04/2008
04/04/2008
04/19/2008
04/14/2009
10/13/2009
04/19/2008
04/14/2009
71
07/01/2009
10/13/2009
80
10/20/2009
11/10/2009
Why? A well-designed spreadsheet will clearly communicate the total estimated cost of the project, as well as what is included in the estimate and what the various categories of work are expected to cost. A secondary objective is to guide organizations toward improved estimation processes and practices. What Does It Do? The objective of a spreadsheet is to provide guidelines that (1) facilitate creation of a complete estimate and (2) support
the evaluation of cost and schedule credibility. Spreadsheets serve to document estimate completeness in an easy-to-read format, which facilitates project cost communication in a uniform and structured manner. When? Different spreadsheet formats (with different levels of detail) are used in the course of project development as project scope is quantied and additional information becomes available. However, spreadsheets should be designed so that major categories can easily be expanded as project detail is better dened.
A-20
Examples The detail of an estimation spreadsheet will vary by project type and by the point in time when the estimate is being created. In the earliest stages of project development, there is limited project denition and design knowledge. One state highway agencys early stage spreadsheet has only ve cost categories: 1. 2. 3. 4. 5. Grading and drainage Base and pavement Lump items Miscellaneous Engineering and construction
basic categories can be expanded as additional information about the project is developed. Sheets from Georgia DOT spreadsheets are shown in Table C1.6. Tips The calculation of estimated costs during the early phases of project planning usually employs parametric techniques based on historical cost data. Therefore, to be truly effective, the agency must have cost databases for organizing and retaining information on completed projects. Resources
The sheet also requires calculation of a total cost and a total cost per mile to provide transparency in comparing the cost to similar projects, thereby assessing reasonableness. These
Table C1.6. Georgia DOT spreadsheets.
Michigan DOTs Road Cost Estimating Checklist can be found at www.michigan.gov/documents/MDOT_0268_Road_ Cost_Est_120543_7.pdf.
$2,454,000.00 $0.00 $416,000.00 $565,000.00 $3,302,000.00 $255,000.00 $563,000.00 $225,000.00 $113,000.00 $20,000.00 $353,000.00 $17,000.00 $46,000.00 $5,875,000.00 $200,000.00 $6,075,000.00 $1,309,200.47 $738,420.05 $8,122,620.52 $8,123,000.00
tion continually reduces the agencys capacity to preserve, maintain, and modernize the transportation system. While it is common to communicate a net present value for estimates when comparing projects or design options, it is not a good idea to communicate the estimate to external parties in anything but year-of-construction costs. What Does It Do? State highway agencies can be prepared in advanced to evaluate the construction cost for the project at its programmed date. This tool improves estimate accuracy by identifying the effect of inflation on project cost. Implications for decision making regarding transportation infrastructure based on budget will be clear to the public, and concerns about strategic misrepresentation (or lying) will be dismissed. It denes an estimated cost made in current dollars in terms of cost at the time of construction. When? Year-of-construction cost recognizes the cost escalation effect of ination across the period of development and construction. Estimates should be communicated in year-ofconstruction costs from the earliest points in the project development process. This is very important for projects having long development and/or construction periods. Examples The year-of-construction cost will vary depending on when the estimate is created and the year-of-construction
A-22
and economic variations caused by external factors, such as ination. To calculate the year-of-construction cost, adjustments should be made from current dollar estimates by applying a cumulative ination factor for the year of construction. MnDOT applies ination factors as developed by the Ofce of Investment Management and approved by the Transportation Program Investment Committee. Table C1.7, which is a MnDOT table, illustrates a consistent standard to be applied in adjusting project estimates. Shortterm ination rates are higher because they can be more volatile. Long-term rates are lower because the economic cycles are expected to dampen the rates over time. The table has limited life and must be updated on a periodic basis. Similarly to other state highway agencies, the Washington State DOT maintains it own Construction Cost Index (CCI) that is applied to projects across the state. WSDOT also maintains ination rates for right-of-way costs (R/W Cost Index) because these costs can increase at substantially higher rates than general construction ination depending upon the location of the parcels. WSDOT maintains these values internally, but the values can be obtained by contacting the WSDOT Strategic Planning and ProgrammingSystems Analysis and Program Development Ofce. The FHWA also tracks cost changes that can be used to project future ination on federal aid projects. This information can be found at www.fhwa.dot.gov/programadmin/ pricetrends.htm. Tips Project costs estimates provided in the Statewide Transportation Improvement Plan (STIP) should be calculated in year-of-construction costs. Use discipline in communicating year-of-construction costs at each phase of the project development. Federally funded local projects may either be adjusted for ination as described above or capped at a xed level of federal funds.
Resources FHWA price trends for federal aid highwy construction: www.fhwa.dot.gov/programadmin/pricetrends.htm. Minnesota DOT (2002). Ten Year Highway Work Plan http:// www.leg.state.mn.us/docs/2004/other/040069.pdf. Washington State DOT Strategic Planning and Programming website: http://www.wsdot.wa.gov/planning.
Table C1.7. Inflation factors for current WP/SP to be consistent with 02-04 STIP guidance.
STATE FISCAL YEAR 01 Current WP/SP FY 02-04 STIP CUMULATIVE 02 03 04 05 06 07 08 09 10
--
---
.06 .06
1.06
.06 .06
1.1236 1.12
.0325
.0325
.0325
.03
.03
.03
1.160 1.16
1.1978 1.20
1.237 1.24
1.274 1.27
1.312 1.31
1.351 1.35
A-23
stand-alone systems or in conjunction with other software. These programs generally have limited capabilities and were designed to run on mainframe computer systems. Additionally, many state highway agencies and individual estimators have not gone as far as developing software but have created spreadsheet programs to support estimate development (see Sections C1.6 and C2.4). What Is It? The various software packages developed by state highway agencies are designed to address very explicit agency estimation approaches and satisfy discrete agency objectives. Some agency software has been created for use exclusively during specic project development phases (also see Section E3.1). Why? Due to the computers ability to handle large data sets and its calculation exibility, the estimator can easily adjust unit costs or percentages to match each projects unique conditions and can generate answers to specic agency questions. Many agency-developed estimation software programs are connected to other management software that the agency employs. What Does It Do? Computer software allows the user to readily employ several different estimation databases for parametric or line-item estimation and for performing what-if analyses. The programs typically allow the user to draw prices from historical bid data, historical cost data, reference tables, or a collection of price derivations. All of the data used to generate an estimatesuch as historical costs, crew wages, equipment and material costs, production rates, and assumptionscan be stored to provide a sequential record of estimate development. When? To address very specic estimation requirements, custom agency software may be the only solution. Agency software can be very good in addressing distinctive requirements imposed on any individual state highway agency; however, software development is tedious and costly, and continuing support is a critical issue. Agencies should rst look to commercially developed and supported software such as the AASHTO Trnsport, which has been developed specically to meet the needs of state highway agency estimation. Examples North Carolina DOT approaches project estimation by building estimated cost from the bottom up currently uses a slightly modied commercial estimation program. This program is used by many contractors and was originally developed
to facilitate detailed estimation by a large contracting organization. This program and similar ones of this type enable state highway agencies to development estimates from the bottom up based on crew productivity, construction methods, and selected equipment. Virginia DOT (VDOT) expanded an in-house-developed software system that was initially created through the combined efforts of two districts. The VDOT Project Cost Estimate System (PCES) is currently being used during the middle stages of project development (see Figure C2.1). Virginia is looking to expand its use of the system to the earlier stages of project development. The initial software system specically guided the estimator through decisions about the following:
Costs common to every project (i.e., the costs of every
usual element averaged and factored according to geometric classication), such as stone, asphalt, grading, pipes, erosion control, pavement markings, and moderate shoulder widening Costs specic to each project that are typically overlooked, such as crossovers, turn lanes, and curb and gutter Costs of unique or unusual items requiring a specic dollar input determined by a specialist in a particular eld That original template was modified to include the following:
Data from the entire state rather than just a few districts Interstate projects Right-of-way Utilities Estimation curves and relationships based on a wider variety of projects Construction engineering and inspection at a variable rate based on project cost A wider range of bridge estimates This software is not only an estimation tool, but also a management tool in that a number of items must be checked off, dated, or entered before a project can continue to the next level of development. Tips Many times, estimators spend more time with the tools they use to create the estimate (computers and software) than studying and analyzing the project. It is important that agencydeveloped software be user friendly and structured so that it is easy to input the required data into the system. Resources Kyte, C. A., M. A. Perfater, S. Haynes, and H. W. Lee (2004). Developing and Validating a Highway Construction Project Cost Estimation Tool, Virginia Transportation Research Council, Charlottesville, Virginia, December 2004, VTRC 05-R1. Can
A-24
Figure C2.1. Example of summary page available in VDOTs Project Cost Estimating System.
be found at www.virginiadot.org/vtrc/main/online%5Freports/ pdf/05-r1.pdf. Barlist is a reinforcing steel quantity-estimating tool developed at the Washington State DOT. It can be found at www. wsdot.wa.gov/eesc/bridge/software/index.cfm?fuseaction= download&software_id=45. Trnsport is AASHTOs transportation software management program. It is an integrated construction contract management system that has been developed based on the experience and needs of AASHTOs member agencies. The New York State DOT (NYSDOT) and the New York State Thruway Authority (NYSTA) developed a website to support their transition to the Trnsport system. This website can be found at www.dot.state.ny.us/trns-port/index.html. The About Trnsport page of the website describes how, in years past, the NYSDOT used the mainframe versions of Trnsport Proposal and Estimates System (PES), Letting and Awards Sys-
tem (LAS), and Decision Support System (DSS), but as other agencies moved from the mainframe to the client/server versions, AASHTO decided to drop support of the mainframe version:
NYSDOTs options were to run the mainframe system without vendor support (a risky proposition), replace Trns-port with a new system, or migrate to the client/server version. The decision was made to migrate to the client/server version, and to implement additional modules, to provide a more functional and integrated system which covers the full lifecycle of capital projects.
Similarly, the NYSTA had been using BIDLET, a Clipperbased estimation and bid management system developed in house. As stated in the same website,
As computer technology and operating systems have advanced BIDLET has required increasingly greater resources to maintain its
A-25
[sic] operation. The decision was made to replace BIDLET with the client/server version of Trns-port. The NYSDOT and the Thruway Authority investigated and have subsequently been working on a joint implementation of Trns-port to take advantage of the cost savings and efciencies that could be realized from utilizing a single common installation. Ability to quickly copy entire estimates, individual or
multiple work (bid) items, and/or activities from previous estimates Ability to track all changes made to the estimate and who made the change When? Commercial estimation software offers the most effective means of preparing and managing estimates for medium to large projects involving multiple cost items. For very large, complex projects, computer software may be the only effective and efcient method for handling large amounts of information. Examples The Trnsport Estimator module is used by 22 state highway agencies (as of August 7, 2002). Historic bid price databases can be created using Decision Support System module of the construction contract information historical database. Another commercially available system that is used by several state highway agencies is Bid Tabs by Oman systems. This system is used as a stand-alone system or in conjunction with Trnsport by seven state highway agencies (as of August 7, 2002). Two other state highway agencies are in the process of testing this software (as of August 7, 2002). One state highway agency (as of August 7, 2002) uses Heavy Construction Systems Specialists (HCSS) Heavy Bid, which is a program used by many contractors and was originally developed to facilitate detailed estimation by a large contracting organization. One state highway agency (as of August 7, 2002) uses AutoCAD to perform quantity takeoff for project estimates by combining plan views of the project area with elevation information to get a three-dimensional view of the project. Tips The effectiveness of any computer software program is directly related to product support and training. When selecting software, always ensure that product support will be available and that training and training material will be provided. Resources For more information about Trnsport Estimator, contact the AASHTOWare contractor: Info Tech, 5700 SW 34th Street, Suite 1235, Gainesville, FL 32608. Phone 352-381-4400; Fax 352-381-4444; [email protected]; www.infotech.com. Oman Systems, Inc., P.O. Box 50820, Nashville, TN 37205. Phone 800-541-0803; Fax 615-385-2507; www.omanco.com. Heavy Construction Systems Specialists, Inc. (HCSS), 6200 Savoy, Suite 1100, Houston, TX 77036. Phone 800-6833196 or 713-270-4000; Fax 713-270-0185; www.hcss.com; [email protected].
matched to project complexity and level of design, whether from scratch, other current estimates, or historical backups Ability to easily change, back up, and restore estimates Ability to draw from unlimited amounts of historical cost data and/or labor and equipment rate tables
A-26
Because these estimates can be prepared based on only a limited amount of denitive project information, they support the following:
Scope development tasks Investigation of alternative design concepts Examination of alternative proposals for enhancements
and upgrades Identication of key design elements Recognition of key project parameters Prioritization of needs versus wants Disclosure of key assumptions
When? Early in project development, it is usually not possible to create a bottom up estimate based on a fully developed scope of work. Conceptual estimation is an excellent estimation methodology that can provide reliable estimates based on limited scope denition. Parametric estimation techniques can also use validated change order request pricing. Examples Pennsylvania DOT (PennDOT) uses parametric values in determining cost estimate at planning and early design stages. The Washington State DOT (WSDOT) Urban Planning Ofce has developed a tool termed Planning Level Cost Estimation (PLCE). The PLCE tool is a parametric estimation tool created to help plan and budget for large improvement projects. The output of this tool is a range of total project costs, including preliminary engineering, right-of-way (if applicable), and construction. The tool focuses on major project elements and creates costs for other minor elements using factors. This program is based on WSDOT data for large projects using recent cost data. The tool can reect regional differences. The output needs to be reviewed carefully by planners and other disciplines. The tool uses Microsoft Access as the database. Figure C2.3 shows a owchart of the process, a typical screen capture for the mainline add of two lanes, and a typical summary output. Tips All parametric estimation techniques, including cost estimation relationships (CERs) and complex models, require credible data before they can be used effectively. Data should be collected and maintained in a manner that provides a complete audit trail with expenditure dates so that dollar-valued costs can be adjusted for ination. While there are many formats for collecting data, an example of one commonly used by state highway agencies would be the standard contract pay items. Technical noncost data that describe physical, performance, and engineering characteristics of a project must also
A-27
MAINLINE ROW
INTERCHANGE STRUCTURE ENVIRONMENT
QUANTIY, AREA DENSITY TYPES TYPES, SIZE TYPES, SIZE UTILITY, CE, TAX,
USER INPUT
UNCERTAINTY ASSESSMENT
(a) Flowchart
Figure C2.3. WSDOTs Planning Level Cost Estimation tool. (continued on next page)
A-28
be collected. Once collected, data need to be adjusted for items such as production rate, improvement curve, and ination. This is also referred to as the data normalization process. CERs are analytical equations that relate various cost categories (in either dollars or physical units) to cost drivers, or variables. CERs can take numerous forms, ranging from informal rules of thumb to formal mathematical functions derived from statistical analysis of empirical data. Developing a CER requires a concerted effort to assemble and rene data. In deriving a CER, assembling a credible database is especially important and, often, the most time-consuming activity. Resources The paper Parametric Estimating Methodology for Transit Project Planning, by Robert H. Harbuck, PE CCE, which is
part of the 2001 AACE International Transactions, provides an overview for transit project applications. A copy can be found on the Parsons Brinckerhoff website at: www.pbworld.com/ library/technical_papers/pdf/46_ParametricEstimating.pdf. The Association for the Advancement of Cost Engineering (AACE International) Professional Practice Guide #6, Construction Cost Estimating, presents information on conceptual and parametric estimation. NASA has a Parametric Cost Estimating Handbook. This handbook is intended to be used as a general guide for implementing and evaluating parametric-based estimation systems and as the text material for a basic course in parametric estimation techniques. It can be found at http://cost.jsc.nasa. gov/PCEHHTML/pceh.html. Washington State DOT, Urban Planning Ofce, Seattle, Washington.
A-29
Tips Computer spreadsheets such as Excel require less initial investment than commercial estimation software and tend to be very exible. The list of included items on spreadsheets is often not exhaustive, and space should be provided in each section of the spreadsheets to allow the entry of additional cost items that may be unique to a particular project. Resources Georgia DOT (GDOT) has posted on the Internet (www. dot.state.ga.us) the format for submitting scope and cost estimates for GDOT projects in the form of Excel workbooks to expedite the review and approval process. Type GUIDELINES FOR SCOPE & COST ESTIMATE WORKBOOKS in the search box on the home page. There are also commercial estimation programs that have seamless integration with Microsoft Excel. See Hard Dollar Construction Estimating Software at www.harddollar.com/ software/Take-Off-Analysis.asp.
C3 Conceptual Estimation
During the earliest stages of project development, prior to any design work, there is limited information about the project. However, there is the need to establish the approximate cost in order to evaluate options and to make choices between transportation needs and feasibility. Because there is very little project denition at this point in time, conceptual estimates usually rely on parametric techniques to extrapolate from past experience the economic impact cost of future projects. These techniques are applied using custom cost estimation relationships or commercially available tools. Such estimates are normally prepared prior to the National Environmental Policy Act (NEPA) decision document. The accuracy of these estimates is directly related to the specicity of project denition. These techniques are used to determine the approximate cost of the project. In some cases, the estimated dollar amount is expressed as a range; this is a very good practice.
A-30
What Is It? A parametric cost estimate is one that uses cost estimation relationships and associated mathematical algorithms (or logic) to establish the cost estimate for a project. Parametric estimation using statistical techniques and historical databases can produce a range of probable costs rather than a single deterministic cost. The method can be applied to develop an estimate before design is complete. The conceptual estimation techniques with 1% to 15% project denition can produce a project estimate with an accuracy range of +40/20% to +120/60% according to the Association for the Advancement of Cost Engineering International (AACE). Why? During the early stages of project development, it is difcult to develop denitive cost numbers based on material quantities or specic work items, as these have not yet been dened. Computer-driven conceptual estimation tools can bring speed, accuracy, and flexibility to estimation processes. They are also applicable for projects of an emergency nature that must be completed rapidly and for which there is limited scope denition. What Does It Do? When the only denitive information about a project is general parameters such as location, length, and maybe the number of roadway lanes an estimate can be derived from a weighting of historical cost records from previous projects. The technique uses cost estimation relationships to build the cost of individual parts of the project and parametric models to prepare estimates for an entire project. Parametric models incorporate many equations, ground rules, assumptions, logic, and variables that describe and dene the particular situation being studied and estimated. Parametric models make extensive use of cost history databases. When? Early in project development, it is usually not possible to create a bottom up estimate, as a fully developed scope of work is yet to be created. Conceptual estimation is an excellent costing methodology that can provide reliable estimates based on a limited denition of project scope. Conceptual estimation techniques can also be used to price validated change order requests. Examples Penn DOT uses parametric values in determining the cost estimate at the planning and early design stage.
Tips All parametric estimation techniques, including cost estimation relationships and complex models, require credible data before they can be used effectively. Data should be collected and maintained in a manner that provides a complete audit trail with expenditure dates so that dollar-valued costs can be adjusted for ination. While there are many formats for collecting data, an example of one commonly used by state highway agencies would be the standard pay items. Technical noncost data that describe physical, performance, and engineering characteristics of a project must also be collected. Once collected, data need to be adjusted for items such as production rate, improvement curve, and ination. This is also referred to as the data normalization process. Cost estimation relationships are analytical equations that relate various cost categories (either in dollars or physical units) to cost drivers, or variables. They are created in a stepped process involving development of a unit cost by a weighting of historical data to which appropriate corrective adjustments are applied. Ination/deation adjustment. The unit cost must be adjusted for the time difference between the historical projects and the estimated project. Various indexes of economic trends are available to support a correction. See the Engineering News Record quarterly construction indexes. Location adjustment. The historical cost data are only reliable for the specic locations of the encompassed projects. Consequently, the relative difference in the cost of materials, equipment, and labor between locations of past projects and the current project requires an adjustment in unit cost. Project size adjustment. Project size can affect cost; therefore, in developing a cost estimation relationship, size of the historical projects compared with the estimated projects must be factored in. Unit cost adjustments. The cost of certain items (e.g., specic hardware) is independent of project size; as a result, it is necessary that the estimator have a clear understanding of the proposed project scope. In deriving a cost estimation relationship, assembling a credible database is especially important and, often, the most time-consuming activity. Resources The paper Parametric Estimating Methodology for Transit Project Planning, by Robert H. Harbuck, which is part of the 2001 AACE International Transactions, provides an overview for transit project applications. A copy can be found on the Parsons Brinckerhoff website at www.pbworld.com/library/ technical_papers/pdf/46_ParametricEstimating.pdf.
A-31
The Association for the Advancement of Cost Engineerings (AACE Internationals) Professional Practice Guide #6: Construction Cost Estimating presents information on conceptual and parametric estimation. NASA has a Parametric Cost Estimating Handbook. This handbook is intended to be used as a general guide for implementing and evaluating parametric-based estimation systems and as the text material for a basic course in parametric estimation techniques. It can be found at http://cost.jsc.nasa. gov/PCEHHTML/pceh.html.
rithms (or logic) to establish the cost estimate for a project. These statistical techniques, together with historical databases, can produce a range of probable project costs. The method can be applied to develop an estimate before design is complete. Table C3.2 is from the Association for the Advancement of Cost Engineering (AACE) International. The table provides a sense of the accuracy that can be achieved using a conceptual estimation methodology in relation to the amount of project denition. During early project development, scope denition and design will be limited. Under the AACE International matrix, early estimates would be either Class 5 or 4. Why? During the early stages of project development, it is difcult to develop denitive project cost numbers based on material quantities or specic work items, as these have not yet been dened. Computer-driven conceptual estimation tools can bring speed, accuracy, and exibility to estimation processes. Because development and maintenance of individual or specialized software packages can be expensive and requires special talents, it is often more economical to use commercially available software, which spreads the product cost over a larger user base. In the case of conceptual estimation, commercial software providers often also have extensive databases that can be provided with the product. What Does It Do?
When the only denitive information about a project are general parameters such as location, length, and maybe the number of roadway lanes, an estimate can be derived from a weighting of historical cost records from previous projects.
Methodology
Typical estimating method
Screening or Feasibility Concept Study or Feasibility Budget, Authorization, or Control Control or Bid/ Tender Check Estimate or Bid/Tender
Stochastic or Judgment Primarily Stochastic Mixed, but Primarily Stochastic Primarily Deterministic Deterministic
Class 2 Class 1
A-32
The technique uses cost estimation relationships to build the cost of individual parts of the project and parametric models to prepare estimates for an entire project. Parametric models incorporate many equations, ground rules, assumptions, logic, and variables that describe and dene the particular situation being studied and estimated. Parametric models make extensive use of cost history databases. When? Early in project development, it is usually not possible to create a bottom-up estimate, as there is no fully developed scope of work. Conceptual estimation is an excellent costing methodology that can provide reliable estimates based on a limited definition of project scope. Conceptual estimation techniques can also be used to price validated change order requests. Examples Trnsport cost estimation relationships is a job and program cost estimation and planning tool that provides a highly productive environment to prepare parametric, cost-based, and bid-based job cost estimates. Tips The estimator is the key to any estimation process and must know the software being used, its capabilities, and its limitations. To become procient at any task, training is required. This is especially true with estimation software. Training will greatly enhance the prociency and efciency of estimators using any software. One of the greatest benets of computer estimation is the storage and retrieval of historical data. All parametric estimation techniques, including cost estimation relationships and complex models, require credible data before they can be used effectively. Data should be collected and maintained in a manner that provides a complete audit trail with expenditure dates so that dollar-valued costs can be adjusted for ination. While there are many formats for collecting data, an example of one commonly used by state highway agencies would be the standard pay items. Technical noncost data that describe physical, performance, and engineering characteristics of a project must also be collected. Once collected, data need to be adjusted for items such as production rate, improvement curve, and ination. This is also referred to as the data normalization process. Cost estimation relationships are analytical equations that relate various cost categories (in either dollars or physical units) to cost drivers, or variables. Cost estimation relationships are created in a stepped process involving development of a unit cost by a weighting of historical data to which appropriate corrective adjustments are applied.
Ination/deation adjustment. The unit cost must be adjusted for the time difference between the historical projects and the estimated project. Various indexes of economic trends are available to support a correction. See the Engineering News Record quarterly construction indexes. Location adjustment. The historical cost data are only reliable for the specic locations of the encompassed projects. Consequently, the relative difference in the cost of materials, equipment, and labor between locations of past projects and the current project requires an adjustment in unit cost. Project size adjustment. Project size can affect cost; therefore, in developing a cost estimation relationship, size of the historical projects compared with the estimated projects must be factored in. Unit cost adjustments. The cost of certain items (e.g., specic hardware) is independent of project size; as a result, it is necessary that the estimator have a clear understanding of the proposed project scope. In deriving a cost estimation relationship, assembling a credible database is especially important and, often, the most time-consuming activity. Resources The paper Parametric Estimating Methodology for Transit Project Planning, by Robert H. Harbuck, which is part of the 2001 AACE International Transactions, provides an overview for transit project applications. A copy can be found on the Parsons Brinckerhoff website at www.pbworld.com/library/ technical_papers/pdf/46_ParametricEstimating.pdf. The Association for the Advancement of Cost Engineering Internationals (AACE Internationals) Professional Practice Guide #6: Construction Cost Estimating presents information on conceptual and parametric estimation. NASA has a Parametric Cost Estimating Handbook. This handbook is intended to be used as a general guide for implementing and evaluating parametric-based estimation systems and as the text material for a basic course in parametric estimation techniques. It can be found at http://www1.jsc.nasa.gov/ bu2/PCEHHTML/pceh.htm. AASHTOWare is AASHTOs transportation software solutions. See http://aashtoware.org/?siteid=28.
A-33
used in conjunction with an order-of-magnitude quantity parameter of the project being estimated, such as centerlinemiles, to provide a basis for approximating the total cost of the facility. What Is It? Early in program (or project) development, there is very limited scope denition as to how a transportation need should be addressed. Because there are often similarities between a current need and a recently programmed, designed, or completed project, the cost basis for estimating the future program area (a project or groups of projects) is the relationship to the similar project for which there are cost data. The cost of the similar project is often expressed in terms of a cost per mile. Why? The purpose of this tool is to rapidly assess the approximate costs for addressing a transportation need or needs. What Does It Do? This tool provides an easy way to quickly approximate the order-of-magnitude cost of a potential transportation program (project or groups of projects). The concept is based on identifying an existing project that is almost identical in scope to the project that is being estimated. The tool relies on historical cost data. The historical data have to be modied to t any differences in scope, location, and other project characteristics that might exist between the similar project and the new project or program area. When? This tool is used for preparing conceptual estimates during the planning phase of program (or project) development. Examples Several state highway agencies use historical cost data from similar projects to generate cost-per-mile factors for longrange planning estimates. One transportation agency identies similar type projects within the state that are in the programming phase and uses the current average cost-permile estimates from those projects to prepare the conceptual estimates for its planning phase projects. The cost-per-mile data could be obtained from a single programmed project or from a number of similar programmed projects. The key to this estimation practice is using similar projects that have a more dened scope than the project in the long-range planning phase. The planning engineers in the respective districts provide the estimators with the current cost-per-mile estimate for the programmed projects, which were created using para-
metric and line-item historical bid-based estimation tools. Thus, the conceptual estimates reect all project cost elements, including costs for design, utilities, construction, and right-of-way. If the project includes structures, the estimator attempts to separate and remove the structure cost in the programming phase estimates and then estimates the current projects structures separately. Other state highway agencies develop lane-mile factors in a similar manner as the one describe here, but they use costs for projects that have already been let instead of projects still in the programming phase. Tips Applying this tool requires the user to match basic scope items to projects that are deemed similar in scope to the transportation program or project being estimated. The user must ensure that all scope items are covered in relation to the similar project. If there is not a perfect match, appropriate adjustments in cost should be made. For example, if the similar project has fewer structures than the transportation need being estimated, an appropriate adjustment in the cost estimate should be made to account for fewer structures. There may also be location differences that must be accounted for when using costs of similar projects. Costs should be adjusted to include future dollars that is, the time at which the transportation need is likely to become a project with a construction target date. This tool is useful for developing quick estimates for a program or project provided that the level of scope similarity is very high. The cost of the similar project should include all elements, including preliminary design costs, right-of-way, utility adjustments, contract administration, and construction. If one of these elements is not in the scope of the new transportation need, then the cost for this element must be deleted from the similar estimate. Alternatively, cost for elements could be added to adjust for differences between a similar project and a new transportation need. Contingencies should be included to cover uncertainties in the cost estimate. Simple spreadsheets can be used to summarize cost estimation elements when using this tool. Resources The data for the Wisconsin DOT method of calculating construction costs for a roadway improvement project based on controlling cost items (these are the certain bid items that comprise the majority of total construction costs) can be found at www.dot.wisconsin.gov/localgov/highways/docs/ district-controlling.pdf.
A-34
parameters, such as dollars per centerline-mile or dollars per square foot of decking, are used in conjunction with gross quantities to provide a basis for approximating the partial cost of a facility. What Is It? Early in program (or project) development, very limited scope denition is available for solving a potential transportation need. The proposed facilities are often described in terms of a parameter such as a centerline-mile of roadway improvement, the number of lanes, and the type of construction (new or reconstruction) or number of bridges. For example, typicalpavement-type sections are used as the basis for estimating pavement construction cost for a given or standard pavement length and thickness or for a typical shoulder width. Historical cost data are provided in terms of cost factors (e.g., dollars per centerline-mile) and percentages for certain scope categories. Historical data reect average costs and are not necessarily specic to any one area within a state. Why? The purpose of this tool is to develop approximate capital costs for a transportation need or needs so that estimates of funds required for long-range programs can be determined. What Does It Do? This tool is easy to use and provides a quick approximation of the magnitude of the cost for addressing a transportation need or correcting a deciency. The concept is based on identifying those cost elements that are likely to be a substantial portion of a projects capital cost. The tool relies on historical data for developing standardized or typical congurations that represent types of transportation facilities. When? This tool is used for preparing a transportation program (or project) conceptual estimate during the planning phase of program (or project) development. Examples One unique approach to applying cost-per-mile factors is developing typical project sections (e.g., pavement sections and type) that correspond with lane-mile cost factors. Using this approach, one state highway agency created an estimation handbook that has sketches of typical roadway sections that are used to generate conceptual estimates. At the planning stage, the pavement thickness, materials, and lane widths are typical values. Depending on the projects standard characteristics, the estimator chooses the corresponding project from the hand-
book. Then, the estimator selects the appropriate cost chart that best ts the anticipated project structure. Cost is still in dollars per lane-mile but it reects a typical structural section that is identied early in project development. The typical sketches also aid the estimator in deciding on the additional project elements that will be required. This process provides the base construction cost; therefore, the preliminary engineering, civil engineering, inspection, and right-of-way costs are added to this lane-mile cost. The right-of-way is factored into the estimate as a percentage of the estimated construction cost, and the engineering costs are based on historical ratios of engineering to construction cost. The engineering cost includes preliminary engineering, construction engineering inspection, right-of-way support, and related overhead costs. The factors in this state highway agency handbook represent present day costs that must be inated to the projects midpoint of construction. This planning manual has ination factors that are applied to the planning estimates. The sum of the calculated elements determines the long-range planning estimates total amount. This estimation method provides the state highway agency with a consistent and transparent approach to estimating the cost of transportation needs. Consistency of approach continues as the project is further developed because the state highway agency uses an estimation methodology that builds upon the lane-mile typical section at each project development phase. The difference between the estimates in each phase is the incorporated level of project detail. Furthermore, estimate development is documented by the systematic preparation of narratives. The approach also has standard project cost components that must be considered for inclusion in the estimate; this helps the estimators avoid the problem of cost-item omission. Two state highway agencies reported using lane-mile cost factors with typical sections for their planning estimates, but their methods were not consistently used within the state highway agency as the procedure previously described. One state highway agency uses three spreadsheet templates specically for its central, northern, and southern regions. The templates categorize typical projects into rural or urban location and into new or widening projects. The number of roadway travel lanes and the median type is used to further dene each typical section. The spreadsheet templates have columns associated with costs for grading and drainage, base aggregate and pavement, lump-sum items (e.g., pavement markings and signs), miscellaneous items, engineering and contingency, total project cost, and total cost per mile. The length of the proposed project is entered into the template, and costs for each typical section listed are calculated. This template provides the state highway agency with different design alternatives along with an estimate for each design so that designs can be compared. Another state highway agency has a cost sheet that lists similar project types and associated cost-per-mile factors. The
A-35
cost sheet separates projects into rural and urban with project types listed by the number of roadway travel lanes. From the cost sheet, the estimator chooses the thickness of the pavement and the median type. The cost sheet also renes cost numbers based on work type (reconstruction or new construction). Furthermore, the sheet provides information for estimating the cost of miscellaneous improvements, such as signaling. Percentages of the total project cost are used to estimate right-of-way and utility cost. This state highway agency is in the process of rening its estimation software to include the computerization of planning estimate preparation. Two illustrations of typical cost data that support this tool are shown here. The rst illustration (Table C3.4-1) relates to bridge costs and shows typical structural sections. The second illustration (Table C3.4-2) shows typical costs for roadway sections, bridge types, and other relevant costs such as rightof-way and construction engineering. Tips Applying this tool requires the user to match basic scope items to typical congurations and/or sections representing different types of transportation need solutions. The user also must ensure that all scope items are covered and that the database provides sufcient information to estimate all pertinent scope elements for the proposed solution, such as right-of-way, preliminary engineering, and utility relocation. If necessary, costs should be adjusted to include future dollars, adjusted to time-of-construction dollars. Cost adjustments may also be necessary when the scope is different form that used to make the estimate or unique conditions exist. Simple spreadsheets can be used to make calculations and summarize cost estimation elements. Resources Florida DOT Ofce of Planning Policy (March 2003). Policy Analysis and Program Evaluation, 2002 Transportation Costs. Caltrans Division of Engineering Services, Structure Ofce Engineer (2003). Comparative Bridge Costs. http://www.dot. ca.gov/hq/esc/estimates. The Wisconsin statewide average costs per mile for various roadway improvement projects based upon the states classication such as a resurfacing, pavement replacement, reconditioning or reconstruction project can be found at www.dot. wisconsin.gov/localgov/highways/docs/statewide-cost permile.pdf.
management system. It uses the most current information systems technology and is based on the experience and needs of AASHTOs member agencies. Trnsport capabilities encompass the full functionality of a construction contract management system. It is an integrated system consisting of 11 modular components, which can be used individually or in combinations as appropriate. Each module (see Figure C3.5) addresses the needs of the highway agency at a particular milestone in the construction contracting life cycle, representing three functional areas: preconstruction, construction, and decision support. What Is It? The Cost Estimation System (CES) is the primary Trnsport module, and, as shown in the estimation workow schematic, it is most appropriately used in the conceptual estimation stage. It provides a highly productive environment for preparation of parametric, cost-based, and bid-based project cost estimates. The CES module, when used in a conceptual estimation context, estimates the cost of parameters involved in the breakdown of a project. A parameter could be general characteristics such as project type, length, and location, or more specic information such as quantities and prices of major items. Parametric estimation uses three statistical modeling techniques: (1) project breakdown estimation, which determines the major cost drivers, called major items, for the breakdown; (2) major item quantity estimation, which determines appropriate quantities of major items; and (3) major item price estimation. Adjustment of any of the calculated values to better reect estimator knowledge of the project is possible, and CES will recalculate the estimate by using the rened data. A very popular calculating approach among state highway agencies is the lane-mile historic cost averages, which is an inbuilt feature of this module backed by the Bid Data Analysis and Decision Support System (BAMS/ DSS) historic database feature of Trnsport. Why? At the conceptual estimation stage, it is an ordinary practice for state highway agencies to use lane-mile costs to estimate a project. The lane-mile cost parameter is a built-in feature of the Trnsport CES module. The CES module, however, emphasizes an item-level-quantity-based approach as opposed to estimating at a project level using a cost-per-lane-mile parameter. This approach may improve early estimate accuracy. Developing quantities early may enable continuous tracking and control by initiating quantity estimates at the outset. To efciently perform these functions, a comprehensive project breakdown schematic is necessary, along with the ability to correlate them to historical databases. The CES module of Trnsport can be used to accomplish this correlation.
A-36
Short Spans, Low Structure Height, No Environmental Constraints, Large Projects, No Aesthetic Issues, Dry Conditions, No Bridge Skew Urban Location Seat Abutment Spread Footing No Stage Construction Factors That Will Increase the Price Over the High End of the Price Range Structures With More Than 2 Construction Stages Unique Substructure Construction Widenings Less Than 5M
(STR. DEPTH/MAX SPAN)
COMMON SPAN RANGE (meters)
Factors for Higher End of Price Range Long Spans, High Structure Height, Environmental Constraints, Small Project, Aesthetic Issues, Wet Conditions (cofferdams required), Skewed Bridges Remote Location Cantilever Abutment Pile Footing 2 Stage Construction
STRUCTURAL SECTION RC SLAB RC T-BEAM RC BOX CIP/PS SLAB CIP/PS BOX PC/PS SLAB PC/PS BULB T GIRDER PC/PSI PC/PS BOX STRUCT STEEL I-GIRDER
SIMPLE
CONTINUOUS
REMARKS
5-13 12-18 15-37 12-20 30-76 6-15 9-37 27-44 15-37 37-61
800 - 1, 200 850 - 1, 400 950 - 1, 450 950 - 1, 300 800 - 1, 200 1,300 - 1, 950 1,100 - 1, 800 1,100 - 2, 100 1,300 - 1, 700 1,500 - 2, 700
NO FALSEWORK REQUIRED THESE ARE THE MOST COMMON TYPES AND ACCOUNT FOR ABOUT 80% OF BRIDGES ON CALIFORNIA STATE HIGHWAYS.
0.06
(+75 m m AC)
0.055
(+75 m m AC)
0.045
0.04
18-91
NOTE: Removal of a box girder structure costs from $160 - $215 per square meter.
A-37
Short Spans, Low Structure Height, No Environmental Constraints, Large Projects, No Aesthetic Issues, Dry Conditions, No Bridge Skew Urban Location Seat Abutment Spread Footing No Stage Construction Factors That Will Increase the Price Over the High End of the Price Range Structures With More Than 2 Construction Stages Unique Substructure Construction Widenings Less Than 15 ft.
(STR. DEPTH/MAX SPAN) COMMON SPAN RANGE (feet)
Factors for Higher End of Price Range Long Spans, High Structure Height, Environmental Constraints, Small Project, Aesthetic Issues, Wet Conditions (cofferdams required), Skewed Bridges Remote Location Cantilever Abutment Pile Footing 2 Stage Construction
STRUCTURAL SECTION RC SLAB RC T-BEAM RC BOX CIP/PS SLAB CIP/PS BOX PC/PS SLAB PC/PS BULB T GIRDER PC/PS I PC/PS BOX STRUCT STEEL I-GIRDER
SIMPLE
CONTINUOUS
REMARKS
0.06 0.07 0.06 0.03 0.045 0.03 (+3" A C) 0.06 (+3" A C) 0.05 0.055 0.06
0.045 0.065 0.055 0.03 0.04 0.03 (+3" A C) 0.055 (+3" A C) 0.045 0.05 0.045
16-44 40-60 50-120 40-65 100-150 20-50 30-120 90-145 50-120 120-200
75-110 80-130 90-135 80-100 75-110 120-180 100-170 100-200 120-160 140-250
NO FALSEWORK REQUIRED THESE ARE THE MOST COMMON TYPES AND ACCOUNT FOR ABOUT 80% OF BRIDGES ON CALIFORNIA STATE HIGHWAYS.
0.045
0.04
60-300
150-215
NO FALSEWORK REQUIRED
NOTE: Removal of a box girder structure costs from $15 - $20 per square foot.
What Does It Do? The CES module of Trnsport provides a full range of cost estimation capabilities from conceptual estimation to the engineers nal estimate required for nal approval. Estimators can migrate their work through each stage of estimation, splitting and combining projects as required, moving smoothly from each stage of estimation. This tool allows import of data from other design software, such as computer-aided design and drafting (CADD). The parametric estimation capability of CES is, however, of particular interest for this application. The CES module creates estimates using item-based historical prices from the BAMS/ DSS module. It permits the creation of estimates from scratch or by importing older project estimates from existing Trnsport modules that may have similar parameters, such as project type, length, and location, or more specic information such as quantities and prices of major items. Estimates are created and categorized on a project-by-project basis using an
item-based approach. Predened line items that are built into the program are directly linked to historical databases. The module also permits customization for unique items. It also facilitates the listing and tracking of sources of funding on each project. Item pricing can be based upon equipment and labor, previous bid and regression analysis, references to similar projects, and ad hoc. As items are added, CES automatically calculates and updates the estimate based on the pricing method chosen. This computer-based tool allows customization to improve accuracy and also generates an array of reports to help document and track project costs. When? This tool can be used in the planning phase of project development to create early estimates based on major project parameters and other factors. In this way, CES can be an efcient tool for quickly estimating project costs for purposes of long-range planning.
Examples In years past, the NYSDOT used the mainframe versions of Trnsport PES, LAS, and DSS, but as agencies moved from the mainframe to the client/server versions, AASHTO decided to drop support of the mainframe version. NYSDOT then migrated to the client/server version. Tips This tool can be used at all stages of estimation, bridging easily from one Trnsport module to another module that has been developed to be used at different stages of project development. These features help improve accuracy and handle more complex circumstances. Thus, the user can start with the planning estimate developed in CES and then move to estimation in the other project phases. The estimator should check the output of the CES model to ensure that the estimate is consistent with estimated costs using other agency historical data. The estimator must ensure that all project costs are covered, such as right-of-way and preliminary engineering. These costs may not be generated by CES. Additional information can be found using the following website dot.state.ny.us/trns-port/about.html.
Resources The Technology Implementation Company, in Gainesville, Florida. See website addresses www.infotech.com and www. cloverleaf.net. AASHTOWare, the transportation software system of AASHTO. See website at www.aashtoware.org.
C4 Consistency
The estimate is the beginning and the foundation of the entire project cost control process. All project estimates should be developed and treated as permanent documents that function as a basis for business decisions. Therefore, an estimate must be in a form that can be understood, checked, veried, and corrected. There must be consistency of presentation within an individual estimate and consistency across all estimates prepared by an agency. Consistency is an important feature of all estimates, but its impact on performance increases with project complexity. The consistent presentation of state highway agency estimates supports avoidance of duplications, omissions, and errors within an estimate and strengthens the estimate review processes. Successful estimation improvement is not so much about computers and data per se, as it is about
creating an organizational culture and climate that support state highway agency estimators and the estimation process.
(i.e., team to team) passage of scope, schedule, and estimation responsibility as the project passes from one development stage to another. Why? When project development is a stepped process with stage responsibility passing from one team to another (i.e., over-thewall deliverables) there is always the possibility that critical knowledge will be lost during a hand-off between teams. One approach used to avoid this problem of lost project knowledge is the reliance on a dedicated team to move the project through all development phases. This approach would also place estimation responsibility with the same person or persons during all of the projects development stages. What Does It Do? The use of cradle-to-grave estimators improves the knowledge base of the estimator or estimation team concerning all
Figure C3.5. Estimation workow and functional areas where Trnsport models assist.
A-42
project details. With this approach, estimators gain knowledge about the reasons for revisions, the existence of constraints, the required coordinate with other schedules, and the regulatory procedures that affect the project. When estimators possess such knowledge, estimate quality is improved because there is a better understanding about external cost drivers. When? The use of cradle-to-grave estimators can be very benecial in the case of projects that will be impacted extensively by thirdparty agreements, utility conicts, coordination issues, and scheduling uncertainty. Even with simple and straightforward projects, the use of cradle-to-grave estimators will work, but the realized benets are usually not as signicant. Examples The use of cradle-to-grave estimators is found more in the private sector of the construction industry, where the estimator is a member of the project development team and not an auxiliary or separate support staff. It has been reported by engineering rms working for the chip and technology industry that, by making the estimator a member of the project development team, the rms are saving to the original budget because of early value engineering and cost input. Tips To realize the full potential of this estimation approach, the estimator must become an integral part of the project development team and be fully informed about coordination issues, external agreements (environmental, utility, and societal), and schedule constrains. Resources The Trnsport Estimator and CES modules are both cost estimation systems. CES is a client/server system that is tightly integrated with Trnsport PES, sharing databases and supporting direct project import/export and check-in/check-out processes. CES supports cradle-to-grave project estimation.
dently evaluate supporting data upon which the estimates are based, but the checklist helps to ensure estimate completeness. What Is It? Checklists are templates that estimators and reviewers use to ensure a complete estimate. They guide the estimator through suggested items and consideration of factors that impact project cost. Why? While estimators and project managers are generally very familiar with assembling cost data and developing an estimate, the estimation process requires consideration of a very large number of work items and the factors that impact the cost of individual items, as well as factors that impact the cost of the project in general. Checklists serve to delineate the large number of factors, which must be considered during estimate preparation. Therefore, they are an excellent means of avoiding omissions and for calling attention to the interaction between factors that can impact cost. What Does It Do? Checklists guide the estimator through suggested work items and cost factors. A checklist serves to ensure that all cost categories are accounted for in an estimate. The answers to the checklist questions will provide an overview of the estimates completeness and focus the estimators attention on critical questions. The checklists can be divided into major work areas, such as roadway and structural, to support specic parts of project estimate development. When? Checklists can support estimate creation at all stages of project development. The purpose of a checklist is to assist the estimator in planning, formatting, and developing a complete estimate. Checklists should be as inclusive as possible, with questions that specically probe the estimate at the different stages in project development. Examples North Carolina DOT has an estimation checklist for functional and preliminary estimates. The list, which contains the various items included on a project, as well as the units of measurement to be used in estimating the items, is as follows:
Clearing and grubbing (acre or hectare) Earthwork (cy or m3)unclassied, borrow, undercut, etc.
A-43
Fine grading (sy or m2) Drainage (per mile or kilometer) Paving (ton or mtn, w/pavement design, or sy/m2 without) Stabilization (sy or m2) Shoulder drains (lf or meter) Curb and gutter (lf or meter) Guardrail (lf or meter) Anchor units (each type) Fencing (mile or kilometer) Interchange signing (type and location) Trafc control plan (TCP) (per mile or kilometer) Thermo and markers (per mile or kilometer) Utilities (lf or meters) Erosion control (acres or hectares) Trafc signals (each and location) Retaining walls/noise walls (sf or m2, with avg. height) Bridges (individual location) Reinforced concrete (RC) box culverts (individual location) Railroad crossing (eachwith or without gates)
(UPB) or approved construction cost data (e.g., the General Construction Cost Engineering Standards published annually by Richardson Engineering Services or the price data published by R. S. Means Company). Basis for estimates is provided or explained; all assumptions, quotes, crew sizes, and other cost factors are documented. Estimates are escalated to the expected midpoint of construction using the latest approved management control plan or Office of Management and Budget (OMB) (for Civil Works projects) index. Estimates are prepared in accordance with latest Corps cost engineering regulations and technical manuals. Estimates include risk analysis to cover unknown conditions or uncertainties on work schedules. Estimates are internally reviewed prior to submittal.
Tips There can be many individual checklists to support different phases of estimate preparation and specic cost areasa plan review checklist; a site checklist; a checklist for developing quantities; and a checklist to consider construction noise, dust, and other construction nuisance issues. Resources The following list is from the FHWAs Engineers Estimate Checklist for Full Oversight Projects:
Check approximately 1520% (more if possible) of the bid
This checklist could serve as review guidance for any state highway agency. Defense Logistics Agencys In-House Cost Estimate Checklist (available online at www.dla.mil/j-3/a-76/IRLine02.html) is not designed for projects of the type that state highway agencies usually handle, but it does contain some very good questions that a state highway agency might want to include in its own checklist, including the following:
Is ination calculated correctly? If costs are based on historical data, are appropriate adjust-
ments included?
quantities? Do the pay items correspond to the type of work proposed? Are the units of measure appropriate for the pay item? Is the quantity for the pay item reasonable for the project? Does the unit price seem reasonable for the type, size, and location of the project?
The FHWA also has posted on the web a checklist document: Checklist and Guidelines for Review of Geotechnical Reports and Preliminary Plans and Specications. The PS&E portion of the checklist applies to specic geotechnical features, such as pile foundations, embankments, and landslide corrections. This checklist can be found at www.fhwa.dot.gov/bridge/ checklist.htm. The U.S. Army Corps of Engineers estimate review checklist from ER1110-1-12 requires that the reviewer verify the following:
A-44
ranging issues of estimation practice, such as consideration of external factors that affect construction cost and how to accommodate project risk in contingency amounts.
Why? The foundation of a good estimate is the formats, procedures, and processes used to arrive at project cost. A survey of state highway agencies in 2003 found that only 16 had manuals that provided formal guidance for preparing estimates, and most of these tended to describe how to use the particular state highway agencys estimation system and failed to address broader issues of good estimation practice, such as consideration of external factors that affect project cost. Estimate consistency and accuracy is achieved by instituting procedures that serve as guides for all parties engaged in the estimation processes. What Does It Do? An estimation manual provides guidelines for the preparation of all project estimates developed by the state highway agency. It should provide information on a range of processes and techniques matched to varying project types (straightforward to complex) and to project development stage. When? The manual should address estimate preparation during all phases of project development, not just during plans, specications, and estimates (PS&E). Examples Examples of estimation manuals can be found at www. state.nj.us/transportation/eng/CCEPM/ and www.dot.state. il.us/desenv/BDE%20Manual/BDE/pdf/chap65.pdf. The Queensland Government of Australia has its manual online at www.mainroads.qld.gov.au/MRWEB/Prod/Content. nsf/0/02c5ce00d16de3764a256e4000101970?OpenDocument. Tips The following ideas should be part of the estimation manual:
All estimates should be prepared electronically and stored
Trafc engineering, Environmental compliance, and Right-of-way. The designer should conrm that the estimate is consistent with the project scope. Estimates should be updated at design milestone points: preliminary design, 30%, 60%, and nal design. All support units should be required to update and submit their portion of the estimate at the milestone points. The 60% and nal design estimates should be based on actual quantity take-offs. There should be consistent methods for estimating both the quantities and prices of minor items. There should be a standard method for handling ination and a dened ination percentage that is applied to the estimate. The estimate for long-duration projects should be stated in year-of-construction costs. The estimation manual itself should be updated annually in the areas of ination factors, contingency amounts or percentages to be used, and possibly other factors that change with time and market conditions.
Resources Visit these sites for additional information and guidance on cost estimation practices:
Transportation Estimators Association (TEA): tea.
cloverleaf.net/.
FHWA Guidelines on Preparing Engineers Estimate, Bid
Reviews, and Evaluation: www.fhwa.dot.gov/program admin/contracts/ta508046.htm. FHWAs Major Project Program Cost Estimating Guidance: www.fhwa.dot.gov/programadmin/mega/cenal.htm.
in a centralized database. Estimators should become familiar with the project site. A formal site review helps in identifying constructability issues that can be overlook during a paper plan review. Prime estimators should obtain written estimates from supporting units, including
A-45
agency; or support for estimators to attend off-site conferences, seminars, or classes pertinent to their work. These activities should support estimation skill in using techniques for achieving accurate estimates and knowledge about the state highway agencys estimation procedures. Why? Cost estimators must be able to interpret details from scoping documents during early phases of project development or from the plans as design progresses and then make sound and accurate judgments using poorly dened information or only minimal information. To do these things, estimators must receive formal training in (1) estimation methods appropriate to different levels of project detail and (2) methods for properly using the estimation software that is available. What Does It Do? Formal training programs can provide state highway agency estimators with a solid background in methods, materials, and regulations, including methods to analyze bid documents (reading and understanding contracts, plans, and specications); methods to evaluate special conditions affecting project cost; and methods to analyze project risk for developing realistic contingency amounts. Training programs will serve to maximize the potential of software programs for improving estimation processes by providing estimators with a broader understand of how these systems can be used. Training should also provide opportunities to obtain practical construction experience because such experience is an important component of estimator training. Field experiences enhance knowledge about construction methods and provide awareness of the on-site construction difculties that impact job cost. When? Training must be continuous because new construction techniques are always being introduced and the cost of work changes with economic conditions. Additionally, new computer systems are constantly being introduced and the potential of these systems is dependent on knowledge of how to use them effectively. But maybe most important is the issue of accounting for new rules and regulations that impact project costs. Examples One state highway agency (New York) has developed a computer-based training CD with training modules for each phase of project development. The agency has central ofce
training sessions for the estimating engineers and conducts an annual class to bring the estimators together to discuss issues. Tips If the agency uses the AASHTO Trnsport estimation software, the agency should support estimator participation in the Trnsport Users Group (the TUG), which seeks to provide a forum for a unied voice to direct the course of Trnsport development. The TUG additionally provides input to the Product Management Task Force on product effectiveness, deciencies, and needed enhancements and helps to dene product training and support needs. Resources To expand the knowledge base of department estimators, their participation in the Transportation Estimators Association (TEA) should be supported. TEA publishes guidelines used by transportation estimators (cost based, historical based, and parametric), publishes a newsletter for transportation cost estimators, sponsors an annual cost estimation workshop, and seeks to achieve the following goals:
Advance cost estimation techniques; Develop new, innovative cost estimation techniques; and Disseminate information about cost estimation experiences
and new practices. The homepage for the TEA can be found at http:tea.cloverleaf.net/. The homepage for the TUG can be found at www.tug. cloverleaf.net/default.htm.
an estimated total program cost greater than $500 million (expressed in year-of-expenditure dollars) or Has an estimated total cost approaching $500 million, with a high level of public or Congressional intent. The total program cost estimate includes engineering, construction, right-of-way, and related costs, which will be identied by this guidance. Although this guidance is for major projects, it may also be applied to other projects.
A-46
What Is It? The major project estimation guidance is a compilation of key principles to be followed when preparing a cost estimate for signicantly large projects. The magnitude of investment on such projects is associated with greater risks, which have to be carefully monitored. These guidelines provide a complete overview of all critical elements that must be estimated and included in the cost estimate and their importance. Why? Estimates are central to establishing the basis for key project decisions, for establishing the metrics against which project success will be measured, and for communicating the cost status of a project at any given point in time. Logical and reasonable cost estimates are necessary in maintaining public condence and trust throughout the life of a major project. Cost increases over and above the early planning and environmental estimates for major transportation projects have become an increasing concern to Congressional and political leaders, federal and state executive management, and auditing agencies. Major projects by nature are usually more complex and contain more risk elements than other projects. Careful attention must be provided when preparing cost estimates for major projects. Traditional estimation methods may not be appropriate in all cases. This guidance is intended to assist state highway agencies, the FHWA, and other sponsoring agencies to ensure that all program cost estimates are prepared using sound practices that result in logical and realistic initial estimated costs of the projects, thereby providing a more stable cost estimate throughout the project continuum. What Does It Do? Major projects are associated with greater risks and require more effort to properly estimate project cost. There are many aspects of major projects that must be considered when preparing cost estimates. These guidelines, hence, familiarize estimators with the requirements of such estimates and provide a standardized framework and checklist of items to be included in the estimate. When? These guidelines indicate how to maintain consistency in estimation through all project development process phases, but the guidelines are most extensively and appropriately applied in the programming and preliminary design phase. These guidelines could be referred to as late as during plans, specication, and estimates (PS&E) phase.
Examples The key principles for project cost elements are as follows.
Integrity Contents of a cost estimate Year-of-expenditure dollars Basis of a cost estimate Risk and uncertainty Project delivery phase transitions Team of experts Validation of estimates Revalidation of estimates Release of estimates and estimation information Program cost estimation elements Preliminary engineering Right-of-way External third-party (e.g., utilities and railroad adjustments) Transportation demand and management and transportation system management Construction estimate Construction contingencies Construction administration Public outreach Management reserve Integration of program costs estimates throughout the project continuum Quality assurance/quality control
Tips State highway agencies should incorporate these procedures into their cost estimation process by adapting them to t into agency approaches for estimating major projects. Developing checklists based on such guidelines and other input from within the state highway agency or from experts outside of the state highway agency, as applicable to major projects, would improve estimates in terms of consistency. Continuous improvement of such checklists through lessons learned from past major projects can help in improving accuracy. Resources More information is available from the FHWA publication, Major Project Program Cost Estimating Guidance, June 8, 2004: www.fhwa.dot.gov/programadmin/mega/cenal.htm.
C4.6 Standardized Estimation and Cost Management Procedures (Also See B1.3)
The objective of standardizing procedures is to establish a common basis for all state highway agency project develop-
A-47
ment participants to follow when preparing cost estimates and when managing costs over the project development process. The integration of both cost estimation practice and cost estimating management through standardized procedures is a critical feature to achieving consistent project results. What Is It? This tool establishes a set of standards and procedures within a state highway agency to guide the preparation and management of costs throughout the various phases of project development. The objective is to provide a coherent policy basis for alleviating cost escalation by consistently applying tools used for cost estimation practice and cost estimation management. These procedures typically include standard formats for summarizing costs estimates and for tracking changes. Why? In many state highway agencies, projects are estimated and managed in regions or districts. However, nal project approval of estimated costs and changes is often made at the state highway agency headquarters. Standard procedures can provide estimate and cost management consistency across the different regions or districts within a state. Using common formats will make review and approval processes more efcient. Projects are often similar, and past projects provide valuable input for future projects. However, projects must be compared on a common basis. A common basis is achieved by following similar procedures for every project. Standardized procedures facilitate this. Standardized procedures help in establishing familiar estimation and cost management processes for project participants, which, in turn, should improve prociency over a period of time and minimize errors. What Does It Do? By following standardized procedures, project managers and estimators apply consistent approaches to estimating cost and controlling costs. These approaches will likely generate more accurate and realistic estimates with less room for errors. Standardized procedures also help in documenting previous projects in a format that permits easy extraction of necessary information in future. When? Standardized procedures must be established at an agency level for guiding project development work and specically for cost estimation and cost management. They should be applied throughout the project development process. However, cost
management can only begin after the projects baseline scope, cost, and schedule are set. Examples Missouri DOT has developed a list of items to be considered during design that is followed for every project to prevent omissions. Similarly, they have standard lists for procedures to be followed while estimating for right-of-way, environmental, utilities, and bridge considerations. There are also guidelines on acceptable estimation approaches to adopt based on the information available during different periods when estimates are developed. Given that, for many highway projects, 80% of the cost is often attributed to 20% of the line items, which often constitute grading, drainage, and paving quantities, elaborate and updated cost databases on these items have signicant impact on cost estimate accuracy. Missouri DOT has developed a list of items to be considered during design that is followed for every project to prevent omissions. Similarly, it has standard lists for procedures to be followed while estimating for right-of-way, environmental, utilities, and bridge considerations as shown below:
1-02.12 (10) (b) DESIGN CONSIDERATIONS. Below is a partial list of design items. Other items may be considered and included in the estimate, as necessary. Grading (Class A, Class C Excavation, Borrow) Pavement designinclude curb and gutter if applicable. (See Section 6-03 for pavement design considerations) Drainagestream crossings, closed systems, open channel Detention storage basins Shoulder widening Resurfacing Signals, lighting, signing (include temporary signals) Temporary by-pass Trafc control, detours, etc. Construction incentives Pavement edge treatment Guardrail items Urban contingencies (i.e., enhancements, landscaping, etc.) Erosion control (seed and mulch, rock ditch liner, paved ditch, rock blanket) Temporary erosion control Mobilization 1-02.12 (10) (c) RIGHT-OF-WAY CONSIDERATIONS. If right-of-way acquisition is involved, a written request for an estimate should be made to the district right-of-way manager with the following information: Latest available plans Tentative or actual right-of-way required Access controls Anticipated improvements to be taken Proposed borrow areas Proposed mitigation sites for parklands, wetlands, etc.
A-48
Right-of-way personnel should develop the estimate according to the guidelines and policies of the right-of-way manual. 1-02.12 (10) (d) ENVIRONMENTAL CONSIDERATIONS. The Environmental Section of GHQ [General Headquarters] design should be consulted to determine if there are any environmental or cultural resource issues that may affect the cost of the project. They will also be able to provide assistance in determining any associated costs. The Environmental Section should be furnished with the following applicable items: Request for Environmental Studies (RES) form (see Subsection 2-03.2) Latest available plans Location layout of structures, suspected wetlands and unusual features Photographs Environmental staff should give consideration to how the following items will impact the project costs: Parklands Wetlands Historic structures (include bridges) Hazardous waste sites Threatened and endangered species Archeological sites Noise mitigation Socio-economic impacts Earthquake design necessity Nearby structures that are similar Number of bridge rehabilitations Clearance requirements Enhancements (Special aestheticsrailing, lighting, girders, concrete surface texture, etc.)
Missouri DOT process also addresses quality control and quality assurance as these two functions relate to ensuring estimate consistency across Missouri DOTs planning and project development process. The following parts of their procedure highlight their approach to quality control and quality assurance.
1-02.12 (6) QUALITY CONTROL. The district engineer is responsible for maintaining the consistency of the estimates and their documentation within each district. The district engineer should establish a district Cost Estimate Quality Control Review Team that will implement a plan to ensure quality control of all project estimates. It is recommended this team include the districts transportation planning coordinator, project development engineer, right-of-way manager, transportation project managers, and other personnel deemed necessary. This team is not expected to inspect each estimate in detail, but rather establish consistent procedures for the appropriate preparation and updating of the project estimates. 1-02.12 (7) QUALITY ASSURANCE. The GHQ design technical support engineers will provide quality assurance to their assigned districts to ensure consistent cost estimates are produced throughout the department. This will be accomplished through periodic reviews of selected project estimate les, the districts project estimation process, the districts quality control plan, and the districts plan for review and updating of the STIP [state transportation improvement plan] estimates. The results of all quality assurance reviews should be reported on the quality assurance form, Figure 1-02.8, and submitted to the district engineer and the Chief Engineer. Reviews may be conducted by the district review team, the GHQ design technical support engineer, or jointly performed by both parties. The participation of other GHQ personnel, including a bridge structural liaison engineer and structural project manager, a right-of-way eld liaison, and other project core team members, should be required as appropriate.
1-02.12 (10) (e) UTILITIES CONSIDERATIONS. The district utility engineer should be furnished with the following applicable items: Latest available plans Photographs The district utility engineer should consider the following in developing the associated utility cost estimate for the project: Known major utilities Railroad crossings Determine if existing utilities are on existing highway right-ofway or private easement Coordinate with appropriate utility companies 1-02.12 (10) (f) BRIDGE CONSIDERATIONS. GHQ Bridge will provide cost estimates for the bridge structures associated with a project. Upon receipt of the bridge survey, GHQ Bridge will review the bridge survey data and make an in-depth analysis of the proposed crossing. The analysis will include hydraulic design of the waterway opening for stream crossings, geometric layout for grade separations, economic analysis of structure types and span lengths, and investigation of any special features evident from the bridge survey data. A tentative bridge layout will be prepared. The following bridge-related items should be considered by the core team when developing costs for bridges and other drainage structures: Number of major stream crossings Flood plain proximity to crossing location
Tips Identifying tasks that are repeated for every project and adopting an efcient method to accomplish these tasks are necessary for this tool to be successful. Also, adequate training and awareness among participants is also essential for this tool to be successful. Resources Missouri DOT (2004). Chapter 1, General Information: Needs Identication Project Scoping and STIP Commit-
A-49
When? Consolidation of project estimation functions in a single location is usually the result of personnel issues, such as lack of qualied staff and limitations on the number of staff positions. But consolidation can also be driven by the need for estimators to interact with multiple sections within the state highway agency. Examples The California DOT (Caltrans), which has 12 districts, has consolidated all estimation structures into a single ofce in the Engineering Service Center located in Sacramento. The districts take the lead in developing all project estimates, but the estimation group, which is in the Engineering Service Center, provides the bridge cost part of an estimate. This group also produces conceptual estimates for alternatives during the early stages of project development. Tips One of the problems with having a single estimation group is establishing good communication with the state highway agencys districts that are being served. For a consolidated estimation group to be effective, there needs to be good communication between the projects designer and the estimation group so that the experience of both groups can be fully used. Resources Florida Dot State Estimates Ofce: www.dot.state..us/ estimates. The Caltrans Division of Engineering Services, Cost Estimates Branch, web page is located at www.dot.ca.gov/hq/esc/ estimates. This page provides access to Caltranss Bridge Construction Cost Index, Construction Statistics, and Comparative Bridge Cost in both English and Metric units. The Caltrans estimation portion of the bridge design manual is found at www.dot.ca.gov/hq/esc/techpubs/manual/ bridgemanuals/bridge-designaids/page/bda_11.pdf.
C5 Constructability
In a broader context, the intent of constructability is to apply construction knowledge and experience during all phases of project development to help achieve the project objectives. The application of construction knowledge and experience can occur in a number of ways depending on the project phase and complexity of the project. The ultimate goal of constructability is to enable cost-effective construction by improving the efciency of construction through better project designs. If properly implemented on projects, the design intent should be
knowledge,
Achieves better estimated documentation, Makes possible interaction between estimators to discuss
approaches, and
Enhances the ability to support externally imposed schedule
A-50
clear to the contractor through the contract plans and specifications, and the design should be constructable, thereby improving the likelihood of receiving consistent bids when the project is advertised for construction. During construction, fewer claims should result in problems with the design. Constructability is formalized through a review process. This process determines when reviews will occur, who will perform the reviews, what level of review is necessary, and how recommended changes will be incorporated into project designs. The tool involves constructability reviews. With respect to cost estimation practice and cost estimation management, constructability reviews will have their most significant impact if performed during the programming and preliminary design phase in support of improving document quality while preventing and/or reducing the impact of scope and schedule changes. This tool can also ensure that nal design documents are clear and error free.
introduced at the end of the design phase, potential changes may be difcult to incorporate into the design in a timely manner. Delaying this vital and project-critical review can lead to inefciencies. At worst, the lack of a timely constructability review will lead to cost overruns, time overruns, and possibly substandard quality. Using constructability reviews early will ensure high-quality project design documents and reduce the potential for change. What Does It Do? A constructability review helps in determining whether a contractor can ultimately submit a competitive bid based on what is shown in the contract plans and specications. Constructability reviews provide an opportunity to remove many common problems with plans and specifications. A constructability review concentrates on whether the information shown on drawings and within specications can be constructed. Further, constructability reviews can aid in suggesting improvements to designs that support efcient construction methods, phasing and sequencing, and site access approaches. When? Constructability reviews can be applied during each phase of the project development process. Maximum benets occur when people with construction knowledge and experience become involved from the very beginning of the project life cycle. Examples Enhanced Constructability Review is a new Caltrans pilot project whereby the highway construction industry can review preliminary design plans and submit comments to Caltrans regarding the constructability of a project. The intent is to draw on the vast experience of the industry to ensure that plans and specifications are biddable and buildable. Contractors can review the draft project plans and specications provided on this Caltrans website and voluntarily provide comments. Comments submitted through the website are forwarded to Caltrans designers and may be incorporated into the nal design. Comments that are submitted may be posted on the website. A sample agenda for constructability review meetings from one state highway agency is presented in Figure C5.1. Tips Conducting a constructability review incorporates contractor knowledge into the total construction project develop-
A-51
Constructability Review Meeting Agenda Project: ___________________________________________________________________ Project No.: ______________________________________ Date: ____________________ Meeting Location: ___________________________________________________________ Agenda Item Introduction I Traffic A. Design office specific items of concern B. Traffic office specific issues of concern C. Stage construction II Environmental A. Design office specific items of concern B. Environmental office specific issues of concern III Hydraulics/Utilities A. Design office specific items of concern B. Hydraulic/Utilities specific issues of concern IV Structures/Geotechnical A. Design office specific items of concern B. Structures/Geo. specific issues of concern V Right-of-Way A. Design office specific items of concern B. Right-of-way specific issues of concern VI Traffic Control A. Design office specific items of concern B. Traffic control specific issues of concern VII Construction/Maintenance A. Design office specific items of concern B. Construction/Maintenance issues of concern VIII Recap of issues A. Issues B. Responsible parties for resolution C. Deadlines dates Speaker Time Frame
ment process. This review provides the state highway agency with the following advantages:
Many problems can be identied before the construction
phase. This can prevent costly change orders, extra work orders, and nancial bombshells. Plans and specications can be improved. Contractor claims can be reduced. Building quality can be enhanced. Cost can be reduced. Project schedules can be shortened. Environmental permit violations and/or noncompliance can be reduced. There can be cooperative team relationships between all parties involved in a project. All parties can gain more time to concentrate their efforts on producing a high-quality, cost-effective project.
neering program; rather, they are intended to review projects during the design phase for constructability issues. The constructability review should concentrate on quantities for each item of work called for in the plans and specications. What is material used for? How much? Where does it go on the project? Are the quantities correct? Reasonable? Misleading? Duplicated? Unnecessary? Contingent? Resources Anderson, S, and D. Fisher (1997). NCHRP Report 391: Constructability Review Process for Transportation Facilities, Transportation Research Board. Oregon DOT Constructability Review Process, www. oregon.gov/ODOT/CS/OPO/construction/constructability_ reviews.shtml#Constructability_Review_Process.
Constructability reviews are not intended to replace or change a designers duties or the handling of a value engi-
A-52
to support the various alternative solutions that are being explored at the earliest stages of design. When the preferred design becomes apparent or when project-funding limits are set, a baseline cost estimate should be established. That baseline can best be dened as the estimate that is used to manage change and make design decisions that affect project cost. The baseline estimate sets the basis for funding and for measuring project performance. It is important to note that the baseline refers to a project of a certain scope and dimension; any future design or scope changes that alter the actual capacity of the project by denition change the project and require a new baseline, and not just an adjustment to the existing cost and schedule estimates. Four tools have been identied in this research to assist in the creation of a project baseline: cost containment tables, an estimation scorecard, a scope change form, and scoping documents.
tainment tables permits quick identication of cost escalation as it occurs. When standardized in a state highway agency, cost containment tables allow for comparison of cost escalation by the variables captured in the tables. The use of the cost containment table establishes minimal milestones that are consistent throughout the state highway agency. They create accountability for the project team for changes in the estimates from one milestone to the next. When? The effort to manage project costs continues from the programming and advanced planning/preliminary design stage through nal design until the project letting. The cost containment table should only be used when a project baseline estimate is established. Examples Pennsylvania DOT developed a cost containment form that provides information on cost breakdown and milestone estimates. This table is shown in Figure C6.1. Pennsylvania DOT has found that this table creates accountability and transparency. If costs escalate from one milestone to the next, the project teams are charged with bringing the project back into budget or justifying the reason for this escalation (i.e., rightof-way cost escalation, varying material prices, other scope change, or estimate error). Tips A cost containment table requires updating at each predetermined project milestone. At each project milestone where the table is used, the estimate must be broken down into specied items. If substantial changes are present, they can be easily identied to indicate a need for further review. Cost containment tables should be only one tool in managing cost escalation. A drawback of the cost containment table is that it only provides a rearview mirror look at cost escalation. While knowing that there is a problem at critical project milestones is essential, project teams should strive to anticipate cost escalation whenever possible and mitigate their effects before they occur. Resources Pennsylvania DOT (2001). Estimating Manual. ftp://ftp. dot.state.pa.us/public/Bureaus/design/PUB352/inside_cover_ page.pdf.
A-53
Cost Containment Table District: County: Program Yr: Project: Short Title: Cost Containment Milestone Estimate Program Amount (PMC approved amount) Cost Breakdown Engineering: Preliminary Engineering Final Design R/W Utilities Construction Total Cost: Scope Comments $
Bid Amount $
ing cost estimation management throughout the project development process. An estimation scorecard is an objective measure of estimate accuracy or project scope growth. It should be created by the entire team and aligned with the project objectives that will ultimately drive the perceived project success. What Is It? An estimation scorecard is an evaluation tool to measure the success of cost estimation practice and cost estimation management during the project development processes. The format of the scorecards can vary depending upon individual agency objectives, but the goal is to create an objective score for performance in cost estimation practice and/or cost estimation management. Why? Early identication and measurement of the project success criteria helps to ensure that there is no miscommunication regarding functionality and physical structure of the completed project. This helps to clearly align project scope with expectations, thereby limiting scope changes.
What Does It Do? Estimation scorecards are commonly used when consultants are preparing the project design and estimate, but they can also be used internally for agency evaluations. Estimation scorecards indicate the measures that will be used at project completion to evaluate success. During various points in the project development or once the project is complete, performance measures can be derived from comparison of target values designated during project development and the achieved values measured after project completion. When? The evaluation criteria of the estimation scorecard are developed early in the project development process and used in the latter phase to determine the success of the project. Examples Coors Brewing Company has found it benecial to develop benefit and execution scorecards to evaluate the benefit of the project as well as execution. These scorecards are completed early in project development and are used at project
A-54
completion to evaluate success of the project. This tool is also used for payment of services. Figure C6.2 shows the Coors Brewing Company benefit scorecard and execution scorecard. The scorecard is developed for each project, one for execution and another for benet. The benet scorecard communicates the benets of the project. The elements of the benet scorecard for determining project success are dened based on the project. The weights for each benet are determined by the project team that develops the benet items as well as how the results will be measured early in project development. After the project is completed, these benets are assessed. The result for each benet can either be above the target value (AT), on target (OT), or below the target value (BT). The success of the project is dependent on the evaluation of the perceived benets. The execution scorecard is similar to the benet scorecard in that the weights of the given evaluation items, project cost, schedule, and quality/performance are determined early in project development by the project team. The elements of the execution scorecard for determining project success are cost, schedule, and quality/performance. The measurement characteristics are also dened. Once the project is completed, these characteristics are assessed. The results for each can either be above target (AT), on target (OT), or below target (BT). While the example above was created by a private-sector company for a process facility, the concept can easily be translated to public-sector transportation projects. State highway agencies should develop clear and concise project goals at the beginning of each project. These goals can be used to measure project success, either internally for the state highway agency or externally for consultants. An example of project goals, which relate to benets in the scorecard, is taken from Colorado DOTs Colorado Springs Metro Interstate Expansion Project (COSMIX; http://www.cosmixproject.com): 1. Maximize capacity and mobility improvements in the corridor within the program budget. 2. Minimize inconvenience to the public during construction. 3. Provide a quality project. 4. Complete by the end of calendar year. 5. Provide a visually pleasing nal product. A benet scorecard can be created in a fashion similar to Figure C6.2 using the project goals above. The weighted goals can be scored and used in an execution scorecard to measure cost estimation performance and overall management performance. Tips The use of the scorecards can ensure that all team members are clear about the expectations for a successful project. The
tool will help to facilitate a structured discussion about what will dene success on each project, and it will provide an objective measurement for this success. Develop the scorecard as a team. Consider developing an overall project scorecard as well as discipline-specific scorecards. Resources U.S. Department of the Interior (2005). The Quarterly Scorecard and Corrective Actions Reports for Constructed Asset Investments. www.doi.gov/pam/QuarterlyReport Guidance61605.pdf.
A-55
A-56
When? Changes should be tracked throughout project development. The form may change slightly and require more detail as the project progresses through development; however, the concept and purpose of the form remains constant. The usefulness of the scope change form in regards to cost will be more benecial after the project baseline is set. Examples Missouri DOT (MDOT) has created a form for tracking both scope and estimate changes. The form and the instructions for how to complete it are shown in Figure C6.3.
Tips Scope change forms should explicitly require all the information needed to track project changes, including scope, schedule, and cost impacts, as well as explanations and approvals. Forms should be standard; however, there should be the ability to deviate from the form for special project circumstances. Resources California State DOT Project Development Procedures Manual (PDPM) Chapter 6 addresses project cost, scope, and schedule changes: dot.ca.gov/hq/oppd/pdpm/chap_htm/ chapt06/chapt06.htm.
MEMORANDUM
Missouri Department of Transportation Project Development District TO: FROM: Date: Subject: Route , Job No. Non-Major Project Scope/Estimate Change Project Stage: Annual Review/Milestone Completion Submittal of P,S,&E Scope Change: (Describe the elements and details of the project that have changed since the project initially included funds in the STIP for right of way or constriction or since the last scope/estimate change was approved) (If a project scope/estimate memorandum has not previously been approved for the project, the details of the project that have changed since approval of the original project-scoping memorandum should be documented here.) (Projects that require submittal of this letter due solely to a change in cost may not necessarily include a change in the projects scope.) Reason for Change: (Provide the reasons that the change in the projects scope is necessary. The information provided should be detailed enough to allow someone unfamiliar with the project details to gain a general understanding of why the recommended change is necessary.) (Projects that require submittal of this letter due solely to a change in cost may not necessarily include a change in the projects scope. However, the reasons for the cost change shall be fully described in adequate detail to allow someone unfamiliar with the project details to gain a general understanding why the recommended change is necessary.) County (District Engineer) Your Name Project Manager
Figure C6.3. Missouri DOT non-major project scope/ estimate change form.
A-57
Source of Additional Funding: (This section is only required if the project scope/estimate change results in an increase in the total project cost.) (If the change results in an increase in cost, the source of the additional funds should be identified. Any associated impacts to other STIP commitments should also be discussed in this section, if applicable.) Project Estimate Change: Approved STIP Amount: Revised Cost Estimate: Am ount of Change: (+/-) Percent Change: (+/-) $ $ $ ($1,000s) ($1,000s) ($1,000s) %
(The estimate amounts shown here should reflect the total amounts included in the STIP for right of way and construction as compared to the revised estimates for the same items. For example, if a project only has right of way funds included in the latest approved STIP then the cost comparison only needs to include the revised right of way costs. If right of way and construction funds are both included in the latest approved STIP then the revised total of these costs should be compared to the previous total of these costs.) (In order to ensure an accurate comparison of the project costs, the revised costs should be compared to the latest approved amounts found in District STIP database. Any amounts obtained from the database should be obtained from the Internal Report category since these amounts do not include any inflation factors.) Change in Construction Aw ard Date: Approved STIP Construction Award Date: Revised Construction Award Date: Quarter Quarter of of FY FY
Date:
Chapters 2 and 3 in the New York State DOTs Project Development Manual (PDM) discusses changes in project cost, scope, and schedule: www.dot.state.ny.us/cmb/consult/dpm1/ pdm_01_30_04.html.
What Is It? Scoping documents are standardized forms that state highway agencies use to explicitly dene and document the scope of a project. They are often developed in the form of a checklist. They represent past project experience and list key scope items and lessons learned from past projects. Why? Scoping documents are a tool to aid in project scope definition and documentation. They can be used before any major engineering efforts take place. They can also be used in the cost estimation process to define the estimate basis and aid in the establishment of an appropriate level of contingency.
A-58
What Does It Do? The development of a standard scoping document provides consistency in project scope denition early in the project development process. Completion of a scoping document for each project assists in documenting the estimate basis, dening the baseline estimate, dening contingency, and tracking scope changes. This document will aid in identication of the true purpose of the project and serve as a reminder of project intentions throughout project development. The document aids in identication of elements to be included in estimate and schedule considerations. When? The scoping document should be completed early in project development to establish a baseline scope of the project and basis for the early project estimates. The document should be reviewed throughout the development of the project to check for changes in scope.
Examples Many state highway agencies use some sort of scoping document. The documents range in complexity and specicity. Some state highway agencies use a simple memo as their scoping document, while other agencies have longer, more detailed forms. Figure C6.4-1 provides an example of a scoping document from Virginia DOT. Figure C6.4-2 provides an example of a scoping document from the Missouri DOT. Tips A scoping document is an excellent tool to dene an estimate basis. Use the scoping document in a team environment with all of the appropriate disciplines represented whenever possible to minimize the chance of any oversights. Scoping documents should permit some exibility for special-case projects, both the very straightforward and the more complex.
A-59
Resources The Vermont Agency of Transportation Project Development Process is online at www.aot.state.vt.us/progdev/Sections/ PDManual/01mantabl.htm. The New York State DOT Design Quality Assurance Bureau scoping process can be found in the first three chapters of the Project Development Manual: www.dot.state.ny.us/cmb/ consult/dpm1/pdm_01_30_04.html. Project initiation documents mark the transition from planning and programming to advanced planning (using the terms in NCRHP Project 8-49). These documents are described in Chapter 9 of the California DOT Project Development Proce-
A-60
on which a project is advertised and bid (are there many projects being advertised by other agencies during the same time frame?) and on the manner in which the work is packaged into individual contracts (what is the size of a single contract, and is there coordination between adjoining contracts?).
prices, a much greater impact than anticipated by the project planners and estimators. The manner in which work is packaged into individual contracts affects contract prices and must be accounted for when estimating project cost. State highway agencies should seek to package projects in such a way that there is effective management of cost, schedule, and risk. Heeding the recommendations of an independent review committee, Maryland DOT repackaged the contract into three contracts and rebid the project approximately a year later. The first rebid contract came in 11% over the estimate, but there were five bidders and it was a workable bid, and the other two contracts both came in below the estimates, one by 28% and the other by 25%.
A-61
Contract packaging is important for maintaining competition and receiving competitive bids. What Is It? In packaging contracts, there must be a weighing between economy (usually measured as competition) and work efciency. Based on thoughtful analysis and consideration of a program or projects physical work elements and on the market conditions existing at the work location, contract packages are developed that minimize the total cost of construction. Contract packaging, which is based on such forethought, requires interaction between estimators, the project development team, and the state highway agency personnel responsible for managing project construction as the estimator and construction management personnel will be able to call attention to packaging affects on project cost. Why? Project size (contract dollar), equipment requirements, physical features, and the responsibilities (i.e., risk) imposed on the contractor are all critical factors impacting the bid price
of work. There are opportunities to reduce contract cost by conscientiously considering the contract package in respect to these factors. At the same time, estimators must consider the impacts of contract packaging when developing the project estimate. A California DOT (Caltrans) study on the impact of competition on final bid results found a clear and undeniable relationship between the number of bids received and the contact low bid compared with the engineers estimate. Strategies that increase competition (i.e., the number of bidders per project) will lower project cost. Contract packaging is particularly important in the case of large aggregate dollar value work and work of a specialized nature. The geographical location of a contract or work sites is an additional factor that should be considered. Any factor that affects the number of bidders that can be expected on a project should be evaluated. Caltrans found that the relationship between the average number of bidders and the bid price changes based on project dollar size, as shown in Table D1.1. This table makes it clear that even for small dollar jobs, it is important to consider the effects of competition.
A-62
What Does It Do? Contract packaging affects project cost; therefore, knowledge of such impacts can result in contracting packages structured to achieve the work at lower cost. By structuring contracts to facilitate maximum participation by the contracting community, state highway agencies can often lower bid prices. Increasing competition also leads to the continued potential for long-term savings by maintaining a viable base of competition. When? The contract packaging control procedures should be established from the initial conceptual phase through bidding. Examples A review of the Maryland DOT estimate compared with the single bid for the Woodrow Wilson Bridge superstructure contract found the following:
be formed, thereby further reducing the competition. The work was repackaged into three contracts. The rst contract was successfully bid with ve contractors competing. The second contract had six bidders and came in 28% below the engineers estimate. The third contract had four bidders and was 25% below the engineers estimate. Tips State highway agencies should consider the following when packaging contracts:
Contracting method (the history of design-build projects
by state highway agencies indicates that change orders average 2%, while design-bid-build contract change orders average 5%)
A-63
MEMORANDUM
Missouri Department of Transportation
Project Development District TO: FROM: (Director of Project Development) Your Name Project Date: Subject: Route , Job No. County Manager
Draft Project Scoping Memorandum (The information provided in the draft project scoping memorandum should be detailed enough to allow someone unfamiliar with the project details to gain a general understanding of the recommended actions that will be taken to address the need.) Need: (This should include a description of the deficient items that indicate the initial need for the project. In addition any other deficient items or safety needs that are identified through the initial stage of the project scoping process should be included.) Scope: (The description of the projects scope should be as complete as possible at this early stage of the project development process. However, it is reasonable to assume that level of detail that is available will be limited to describing broad concepts and general details of the project.)
earthmoving equipment Coordination with adjacent contracts Trafc control limitations Utility relocation activities (Can this work be accomplished before the prime contract [advance utility relocation] or will there be extensive coordination of work?) Accomplishment of hazardous remediation work as a separate contract in advance of the prime contract Large-dollar contracts (Such contracts can limit competition because contractors are not able to obtain bonding. In the case of mega-dollar projects, there is a limit to the risk that the bonding community is willing to assume. To protect themselves, the bonding companies join together to write large bonds. This practice further limits the availability of a contractor to obtain a bond.)
thereby allowing for efcient use of earthwork (balancing cut and ll requirements). In respect to all these considerations, there must be a balance between the cost of administration for multiple contracts and the potential benets from having multiple contracts. Resources While the California DOT report is specic to conditions in that state, it provides a good indication of competition impacts on project cost (see Impact of Competition on Final Bid Results for Transportation Related Construction Project, Nov. 15, 2001, Caltrans, Division of Engineering Services). Maryland DOT (MDOT) information on the Woodrow Wilson Bridge contract packaging can be found at www.mdot. state.md.us/News/2003/May2003/Wilson%20Bridge. Former Utah DOT chief Tom Warne led the Independent Review Committee (IRC) that MDOT established to examine the Wilson Bridge situation. The IRC recommendations for
During the design phase of project development, there should be a strategic separation of projects within a corridor,
A-64
Budget: Grading & Drainage + $0 Base & Surface + $0 Bridges + Misc. + Estimated Contract Total = $0
Construction Contingency (est. @ 3% of contract total) Contract Total+ Construction Contingency= $0
$0
$0
$0 Utilities $0
Non Contractual Items $0
R/W Incidentals + $0
Total Incidentals
$0
$0
Construction Incentives/ Contract Acceleration $0 Program Estimated Total = $0
Schedule: Milestone Initial Concept Approval Environmental Document Approval Preliminary Plans Approval Project Scoping Memorandum Approval Implementation Plan: Schedule
(The implementation plan should include a discussion of how development of the project will proceed beyond this stage. This should include the time frame for developing the project to enough detail to allow completion of the project scoping memorandum. Any other pertinent information related to implementation of the project should also be included. Projection of the project schedule beyond the project scoping memorandum will not be possible at this point in the process since the project prioritizations process will be used to determine priority for the fully scoped project.)
advancing the project included: value-engineering opportunities, contract modications, review of bonding/surety issues, and project modications to enhance competition. The full report is available from MDOT. There is also a TRB paper, Adventures in Building Another Washington Monument: Woodrow Wilson Bridge Project Re-Bidding Outcomes, by Robert Douglass, Robert Healy, Thomas Mohler, and Shirlene Cleveland, which was presented in the 2004 TRB Annual Meeting.
price construction contracts are awarded to the lowest bidder, is the traditional method for delivery of U.S. highway projects and is used in the majority of cases today. However, this traditional project delivery method has received criticisms stemming from long delivery times, excessive cost growth, and litigious relationships. Continuing to face increasing demands of the traveling public with declining staffs, federal, state and local agencies are employing alternative project delivery, procurement, and contracting methods to improve the efciency and effectiveness of public-sector project delivery. What Is It? Project delivery decision support is a tool that assists state highway agencies in choosing the appropriate project delivery
A-65
I have reviewed the scope of this project and offer the following comments:
(Design Technical Support Engineer) I recommend proceeding with the development of this project subject to the following comments:
Figure C6.4-2. (Continued). Table D1.1. Relationship of bid price to estimate considering project size (Caltrans study).
Project Size, $ Ave. No. Bids Percent over PS&E if only one bid Expected reduction by increasing the average by one bidder
A-66
method. It provides a clear understanding of the advantages and disadvantages of alternative delivery methods so that state highway agencies can make informed decisions about the most effective choice for the available alternatives to meet the specic project goals. The following is a sample of alterative project delivery methods in use by state highway agencies at the time that this document was being prepared. Project delivery methods:
Construction management at risk Design-build (and variations, such as design-operate-
maintain and design-warranty) Indenite quantity/indenite delivery Job order contracting Public-private partnerships Procurement methods:
high potential for project delivery time savings and, in essence, xes a projects cost earlier in the project development process than the traditional process. When design-build is selected, different approaches must be taken for cost estimation practice and cost estimation management. Cost estimation practice may require the use of more rigorous conceptual estimation tools and a more rigorous risk analysis because designs will not be complete and quantities will not be known at the time of project award. Cost estimation management will require different change management procedures because the designbuilder is responsible for the nal project design (including nal quantities) and changes in cost estimates due to scope additions or deletions can be more difcult to manage. What Does It Do? Project delivery decision support provides an understanding of why an alternative delivery method might be appropriate for a project given a set of unique project goals. It provides guidance for cost estimation practice and cost estimation management. When? Project delivery decisions should be made as early as possible in the project development process to optimize their impact. Decisions for the overall project delivery method (i.e. design-build, public-private partnership, etc.) should preferably be made during the project scoping process or shortly thereafter. Decisions regarding innovative procurement methods such as best-value or qualications-based procurements should be made as early as possible as well. Other, less significant procurement and contracting decisions (e.g., A+B bidding, additive alternates, and lane rental) can be made sometime in the preliminary engineering development. Examples There are numerous examples of project delivery decision tools. Five national examples are provided here, but numerous states have developed decision support tools as well. Utah State University Innovative Contracting Website. The Federal Highway Administration sponsored the development of an innovative contracting website to provide decision support for innovative contracting methods. A screen clip of the website is provided in Figure D1.2. The Utah State Universitys Innovative Contracting website includes information concerning various construction contracting methods, such as design-build, warranties, costplus-time bidding, lane rental, and job order contracting. State DOT work plans and evaluation reports from FHWAs
Cost + time bidding (A+B) Multi-parameter bidding (A+B+C) Best-value procurement Alternate designs Alternate bids Additive alternates Negotiated or qualifications-based selection (for construction) Contracting and payment methods:
Lane rental Incentive/disincentive payments Warranty contracting Lump sum payment methods
When selecting alternative project delivery methods, state highway agency personnel should consider such issues as risk allocation, legal implications, statutory restrictions, and administrative issues. The decision to use an alternative delivery method invariably involves a tradeoff between cost and other factors such as time, user delays, or quality. Delivery decision tools can help to dene and quantify the tradeoffs. Why? The choice of project delivery method often hinges on a projects cost or time constraints, and estimators must understand how to estimate the cost tradeoffs involved in the decision to use an alternative delivery method. For example, the designbuild project delivery method can be used to award a lumpsum contract for both the design and construction of a project much earlier in the project development process than the traditional design-bid-build method. This early award offers a
A-67
Special Experimental Project No. 14, Innovative Contracting, are provided. The site also features a best practices guide and a decision tree for selecting the appropriate contracting technique. NHI Alternative Contracting Course (Course No. 134058). The Federal Highway Administrations National Highway Institute (NHI) is offering a course on Alternative Contracting (Course No. 134058). A short description of the course is listed below, and more information on the course availability can be found on the NHI website at www.nhi. fhwa.dot.gov.
Course Objective The estimated 2-day training course will teach participants how to select the appropriate projects for alternative project delivery strategies, choose the correct alternative contract provisions, and recognize the legal and programmatic implications associated with these techniques. The course design is to be flexible, allowing the requesting agency to customize the presentation for increased emphasis on topics of interest to the agency. The target audience includes personnel working in contract administration, project development and design, and the management of highway construction, including contribution of information in contract provisions.
Upon completion of the course, participants will be able to: Identify alternative project delivery, procurement, and contract management methods for highway construction Identify objectives for the use of alternative project delivery, procurement, and contract management methods Differentiate among traditional design-bid-build and alternative project delivery, procurement, and contract management methods based on relative advantages and risks
AASHTO Primer on Contracting for the 21st Century. The Primer on Contracting for the 21st Century is an updated version of the Primer on Contracting 2000, which was published in 1997. The new primer describes various contracting and contract administration methods that are currently being used by contracting agencies in their transportation programs and provides contacts within these agencies for use in obtaining additional information. This report was prepared by the Contract Administration Task Force of the AASHTO Highway Subcommittee on Construction. The document can be found in the references section of the AASHTO Subcommittee on Constructions website http://construction.transportation.org. NCHRP Project 10-49, Improved Contracting Methods for Highway Construction Projects. The project reviewed relevant domestic and foreign literature; surveyed the construction industry; identied and evaluated contract-
A-68
ing practices with consideration to compatibility with the low-bid system, impact on state highway agency resources, product quality, and risk allocation; and developed guidelines for three nontraditional contracting methods: warrant, multi-parameter, and best value. The agencys final report that contains the findings of the literature review, discussions of current use, and analysis of survey results has been distributed to all state highway agencies. The guidelines for nontraditional contracting methods have been published as NCHRP Report 451 (http://www.trb.org/news/blurb_detail. asp?id=5476) NCHRP Project 10-61, Best Value Procurement Methods for Highway Construction. NCHRP Project 10-61 provides decision support for best-value procurement of U.S. highway construction. The resulting report outlines a comprehensive process that state transportation agencies can use to create best-value methods in their individual states. The research effort investigated best-value concepts currently in use in the construction industry, evaluated their relative effectiveness, and recommended a best-value system or systems that may be used in conjunction with a traditional design-bid-build delivery system for highway construction. The research products include:
A common denition and a conceptual framework for the
design solutions to maximize the entire project teams input into meeting customer needs. Resources AASHTO Subcommittee on Constructions website. See references for Primer on Contracting for the 21st Century (http:// construction.transportation.org). Anderson, S. D., and J. S. Russell (1998). NCHRP Report 451: Guidelines for Warranty, Multi-Parameter and Best-Value Contracting, Transportation Research Board. http://www.trb. org/news/blurb_detail.asp?id=5476. FHWAs National Highway Institute, www.nhi.fhwa. dot.gov. NCHRP Project 10-49 website, http://www.trb.org/TRB Net/ProjectDisplay.asp?ProjectID=266. NCHRP Project 10-61 website, http://www.trb.org/TRB Net/ProjectDisplay.asp?ProjectID=281. Scott, S., K. R. Molenaar, D. D. Gransberg, and N. Smith (2006). NCHRP Report 561: Best-Value Procurement Methods for Highway Construction Contracts, Transportation Research Board. http://www.trb.org/news/blurb_detail.asp?id=6903. Utah State University, Technology Transfer (T2) Center, Innovative Contracting website, www.ic.usu.edu.
use of best-value procurement methods for highway construction projects A best-value procurement system that allows for exibility in the choice of parameters and award methods An implementation plan that includes both a project screening system for selecting candidate projects and a step-bystep process for selecting appropriate parameters, criteria, and award algorithms Recommendations regarding models to use for legislation and procurement regulations A compendium of case studies for best-value procurement in the highway construction industry A training tool to assist agencies with implementation
D2 Design Estimation
Design estimation commences when a project enters into the programming phase and continues throughout preliminary engineering. Design estimation is critical during programming because during programming is often when a baseline scope, cost, and schedule are determined. Design estimation tools must produce consistent and accurate estimates. However, the use of these tools will vary depending on the level of project scope denition, the project type, and the complexity of the project. Computer software is used to facilitate the application of these types of estimation tools. A variety of tools can be used to support design estimation:
Analogous or similar project: This tool relies heavily on one
The results of NCHRP Project 10-61 have been published as NCHRP Report 561: Best-Value Procurement Methods for Highway Construction Contracts. (http://www.trb.org/news/ blurb_detail.asp?id=6903). Tips Choose delivery methods that better align goals and that allocate risk properly. The U.S. highway industry must evolve from the traditional one size ts all project delivery method. A renewed focus should be given to alternative delivery methods that promote early industry involvement and life cycle
project that is very similar to the project being estimated. The reference (i.e., analogous or similar) project is typically one that was previously constructed; is currently under construction; is bid for construction; or has a completed plans, specications, and estimates (PS&E) level estimate. Line items, quantities, and unit costs are used as a basis for estimating the current project. Similar costs from the reference project are used to estimate preliminary engineering and construction engineering costs. Cost-based, bottom up: This tool relies on the cost-based estimation approach, wherein construction costs, based on a selected productivity, are estimated for labor, material,
A-69
equipment, contractor overhead, and contractor prot for each major line item. Estimates of preliminary engineering and construction engineering are estimated from the bottom up. This means that resources are specically identied for each element and tied to timeproductivitywhen these resources will be engaged on the project. Historical bid based: The use of historical data from recently bid contracts is the most common state highway agency estimation approach. Under this approach, bid data are summarized and adjusted for project conditions (project location, size, quantities, etc.) and the general market conditions. Line items are developed for major elements of work so that quantities and historical unit prices can be applied to these line items. Often, percentages are used to estimate items where little or no denition is available. Standard percentages are used to estimate preliminary engineering and construction engineering costs. Historical percentages: This tool is used in conjunction with other tools such as historical bid-based estimation. Historical percentages are used to estimate costs for items that are not typically dened early. A percentage is developed based on historical cost information from past projects to cover certain items. This percentage is based on a relationship between the selected items and a total cost category such as direct construction. Contractor mobilization, construction engineering, and preliminary design (often referred to as preliminary engineering) are often estimated based on a historical percentage of construction. Major cost items using standard sections: Typical sections are developed for different roadway or bridge types. These typical sections are tied to cost data that reect the work to be completed for each section. As a project scope is developed, typical sections that are similar to the project being estimated are used to generate a new cost estimate for a project. Standard percentages are used to estimate other costs associated with the typical sections, such as trafc control items and preliminary engineering and construction engineering costs. Parametric estimation: Parametric estimation techniques are used primarily to support development of programming or early preliminary engineering estimates, which are developed when very little project scope denition is available. Major project parameters are identied. Statistical relationships and/or nonstatistical ratios between historical data and other parameters (e.g., tons of asphalt and square footage of bridge deck) are used to calculate the cost of various items of work.
(i.e., analogous or similar) project is typically one that was previously constructed; is currently under construction; is bid for construction; or has a completed plans, specications, and estimates (PS&E) level estimate. Line items, quantities, and unit costs are used as a basis for estimating the current project. Similar costs from the reference project are used to estimate preliminary engineering and construction engineering costs. What Is It? Analogous estimation is an estimation tool that uses the values of parameters (such as scope, cost, and time) or measures of scale (such as size, quantities, and complexity) from a similar previous project as the basis for estimating the same parameters or measures for a future project. This tool is a form of expert judgment. It is most reliable when previous projects are in fact similar in terms of major parameters and not just in appearance. Future projects often have common elements associated with other completed or ongoing projects. Why? This tool provides a quick and cost-effective approach for developing a programming-type estimate or to prepare an estimate during the early phases of preliminary engineering. The availability of information based on real project experience is an invaluable input for determining future project cost. Identifying similarities in a completed or current project and comparing that project to one that is being estimated can provide excellent cost history for estimation purposes. Further, using lessons learned to adjust a project estimate that is based on a similar past project can improve estimate accuracy. What Does It Do? This tool provides an approach to preparing an early estimate that has sufcient reliability and accuracy for use in programming a project. Further, the tool provides sufcient detail to subsequently track changes in quantities and unit costs as the project is designed. When? Analogous or similar project estimation is perhaps best used during programming and early in preliminary engineering. It can also be used in planning in a slightly different form (see C3.3). Examples In late 2003, when Caltrans received a single bid for the self-anchored-suspension (SAS) span of its San Francisco-
A-70
Oakland Bay Bridge Project, the upper levels of California government seriously considered going forward with a skywaytype structure instead of the costly SAS. Caltrans therefore had to prepare an early estimate for a Skyway Extension Bridge span. At the time of this estimate preparation, the design was only 5% complete. The proposed project was very similar in scope to the existing Skyway Extension Bridge work that was under construction at that time. Further, the foundation system was also very similar to cost data that were available from a bid on another type of bridge to be located at the same location. These two past projects were used to develop the cost estimate for the Skyway Extension Bridge span project estimate. The estimator used both quantities and unit costs from the two similar projects. Appropriate adjustments were made to both quantities and unit costs to fit the current bridge situation and reect the unique site conditions for the proposed bridge as well as current market conditions. These adjustments were extremely important for this billiondollar project. Cost estimates for preliminary engineering, environmental impacts, and construction engineering were also based on costs from the similar bridge projects. The Washington State DOT prepared an estimate for another component of a pavement project on an existing state route. The project increases the capacity of the route by adding two lanes to an existing two-lane highway. This current estimate was based on a previously completed estimate for an earlier stage of a project on the same road. The estimator used the previous estimate that was based on an approximately 1-mile section of roadway to estimate another 2 miles of roadway for the next stage of the project. The estimator used ratios to adjust quantities for the new project estimate. Unit prices were also used, but were adjusted to reect current dollars and several slight differences in complexity of the new project in the earthwork category. Tips The user of this tool must understand that the reference project is in fact similar to the project being estimated and not just similar in appearance. Thus, the estimator must make a careful assessment of the scope and site conditions of both the project being estimated and the reference project. Adjustments may be required to the reference project scope and cost data to t the project being estimated. Differences between the reference (or analogous/similar) project and the current project should be carefully documented as part of the estimate back-up calculations. Resources Project Management Institute (2004). A Guide to the Project Management Body of Knowledge (PMBOK Guide).
A-71
When? To address very specic estimation requirements, custom agency software may be the only solution. Agency software can be very good in addressing distinctive requirements imposed on any individual state highway agency; however, software development is tedious and costly, and continuing support is always a critical issue. Agencies should rst look to commercially developed and supported software such as the AASHTO Trnsport product, which has been developed specically to meet the needs of state highway agency estimation. Examples Virginia DOT expanded an in-house-developed software system that was initially created through the combined efforts of two districts. This Project Cost Estimate System (PCES) is currently being used during the middle stages of project development. Figure C2.1 is a sample summary page from PCES. The state is looking to expand its use to the earlier stages of project development. The initial software specically guided the estimator through decisions about the following:
Costs common to every project, such as stone, asphalt, grad-
studying and analyzing the project. It is important that agencydeveloped software be user friendly and structured so that it is easy to input the required data into the system. Resources Kyte, C. A., M. A. Perfater, S. Haynes, and H. W. Lee (2004). Developing and Validating a Highway Construction Project Cost Estimation Tool, Transportation Research Record 1885: Transportation Management and Public Policy 2004, Transportation Research Board. http://www.trb.org/news/blurb_ detail.asp?id=4517. Barlist is a reinforcing steel quantity-estimating tool developed at the Washington State DOT. It can be found at www. wsdot.wa.gov/eesc/bridge/software/index.cfm?fuseaction= download&software_id=45.
ing, pipes, erosion control, pavement markings, and moderate shoulder widening (i.e., the costs of every usual element averaged and factored according to geometric classication) Project-specic costs that are typically overlooked, such as crossovers, turn lanes, and curb and gutter Costs of unique or unusual items requiring a specic dollar input determined by a specialist in a particular eld The initial software was modied to include the following:
Data from the entire state, rather than just a few districts Interstate projects Right-of-way Utilities Estimation curves and relationships based on a wider variety of projects Construction engineering and inspection at a variable rate based on project cost A wider range of bridge estimates This software is not only an estimation tool, but also a management tool in that a number of items must be checked off, dated, or entered before a project can continue to the next level of development. Tips Many times, estimators spend more time with the tools they use to create the estimate (computers and software) than with
This tool is especially applicable for very large and complex projects. The unique character of these projects, geographical inuences, market factors, and the volatility of material prices
A-72
can make historical bid pricing an unreliable method of estimating project costs. In addition, long design and construction durations for these projects make the use of percentages for estimating PE and CE costs potentially unreliable. Hence, cost-based, bottom-up estimation can provide more accurate and defendable estimates. What Does It Do? Bottom-up estimates are, as the term suggests, developed from the bottom up. Costs are estimated based on the lowest component level of work, such as identifying crews, production rates, materials, and equipment for construction items; assigning resource requirements for detailed design elements; and estimating agency construction staff support for administering the construction contract. Costs at the lowest levels are estimated and then summarized to different levels to ultimately generate a total project cost estimate. When? This tool can be used for large projects that are in the programming phase or early in the preliminary design phase of project development. The tool can be used to estimate components of projects that are not that large but still complex. It is a very good method for developing plans, specications, and estimates (PS&E) when nal plans and quantities are known. Examples When Caltrans was attempting to estimate the capital outlay support (COS) cost or what could be referred to as the departments overhead cost for the Skyway Extension Bridge, the projects design was in its infancy (5%). A bottom-up approach was used to provide an independent validation of the initial numbers developed using a percentage estimation approach. Six functional areas were identied and solicited to provide COS workload estimates based upon their anticipated relevance on this project. The primary functional areas were project management, environmental, structure design, roadway design, construction, and materials engineering and testing services (METS). Within these primary functional areas, subfunctions such as surveys, hydraulics, and electrical were represented by the primary function they support. The functional groups submitted hours by the work breakdown structure for the Skyway Extension Bridge through all phases of the work. The COS dollar estimate was calculated using the workload estimates provided by the functional experts and applying the present associated state personnel rates and consultant rates. The consultant rates were from existing consultant contracts. To better capture the effects of escalation as a function of resource types, an escalation of 3.5% was applied to state resources, and an escalation of 5% was applied to consultant resources.
Follow-up interviews were conducted with the functional experts to clarify assumptions used in building the workload estimates. This effort resulted in the identication of specic line-item contingencies not captured in the workload estimates. Rather than apply an across-the-board contingency factor to the entire COS estimate to account for unknowns, specic percentages were used depending upon the phase of the project. A 35% contingency was applied during the design phase to provide for potential added costs associated with major design modications and unknown special studies that may be needed. This unknown potential added cost was not captured in the 6-month design delay calculation. The 6-month design delay calculation was based solely upon the concept of extended review times due to public scrutiny resulting in minimal design changes. A 20% contingency was applied to the construction phase to account for potential added cost associated with use of additional expert consultants or independent analysis for construction engineering. A lower percentage was used during the construction phase because the costs for a 1-year construction delay reected the extended use of all support staff in the construction phase. The delay costs were calculated by preparing two separate scenarios: (a) a 6-month design delay during design and (b) a 12-month construction delay. The worst-case situation of both design and construction delay combined was evaluated. For simplicity, delays were applied at the peak workloads and for a sustained duration. The bottom-up estimate more accurately reflected the impact of delays because it took into consideration the resource type and the work being performed. A relatively lower delay cost during design was indicative of the ability to quickly mobilize and demobilize consultant design staff. Higher delay costs during the construction phase reected the fact that mobilization and demobilization of staff are not a viable option for short-term sporadic delays in a construction environment. The bottom-up delay costs captured the higher end of delay costs by applying a sustained level at the peak stafng level. Delay costs may actually be lower if the delays occur earlier in the project, when stafng levels are much lower. The bottom-up method segregated the specic costs and claried the relationship between the functional components of the estimate and the contingency components. Tips Detailed cost-based bottom-up estimation requires a great deal of knowledge about construction methods, supply systems, labor markets, and method productivity specic to the area where the work is being performed. It also requires more time to prepare a detailed estimate than that which is needed for estimation methods that simply apply bid averages to work items. This is because the estimator must conceptualize the construction process in order to prepare an accurate estimate.
A-73
Most state highway agencies that do this kind of estimation have dedicated estimation sections whose personnel have the necessary construction experience. State highway agencies that do perform detailed estimates typically use computer software that supports estimate development, but the software is not critical to the estimation process itself. The software may be used to track cost trends or simply allow the estimator to report the estimate to other sections of the state highway agency more efciently. The basic information that is necessary to perform a detailed estimatesuch as crew sizes, equipment types, production rates, and labor and material costscan be derived from a variety of resources. This may require contacting local contractors or using a database such as RS Means Heavy Construction Cost Data (see Section P1.3). The estimator will have to call suppliers of materials to obtain unit costs for materials and similar resources for determining equipment production and rental rates. It is important that the estimator be familiar with available resources, know how to nd the resources, and most importantly has a competent knowledge of construction processes. All of these elements are necessary in order to develop an accurate cost-based, bottom-up estimate. Resources The AASHTO Subcommittee on Design, Technical Committee on Cost Estimating is developing guidance on historical cost-based estimation. Draft papers are prepared, but not approved for release. If interested, contact the chair of this technical committee. See this website for key contact persons: http:// design.transportation.org/?siteid=59&pageid=756. Church, Horace K. (1981). Excavation Handbook, McGrawHill Book Company. Associated General Contractors of America (1999). Construction Estimating & Bidding Theory Principles Process. Publication No. 3505. Means, R. S., and M. A. Kingston (2006). Heavy Construction Cost Data, www.rsmeans.com. Oberlender, Garold D., and Steven M. Trost (2001). Predicting Accuracy of Early Cost Estimates Based on Estimate Quality, Journal of Construction Engineering and Management, Vol. 127, No. 3. Parker, Albert D., Donald S. Barrie, and Robert M. Snyder (1984). Planning & Estimating Heavy Construction, McGrawHill Book Company. Rignwald, Richard C. (1993). Means Heavy Construction Handbook, R. S. Means Company, www.rsmeans.com. R. S. Means Company (published annually). RSMeans Building Construction Cost Data, www.rsmeans.com. R. S. Means Company (published annually). RSMeans Heavy Construction Cost Data, www.rsmeans.com. Smith, Francis E. (1976). Earthwork Volumes by Contour Method, Journal of the Construction Division, American Society of Civil Engineers, Vol. 102, CO1, March.
Frank R. Walker Company (published periodically). Walkers Building Estimators Reference Book, Lisle, IL.
A-74
When? Historical bid-based estimation can be used during programming and throughout preliminary engineering as long as the project scope can be described in terms of line items for which quantities can be developed. Examples The rst decision is how many bids from each project should be included in the data. There is signicant variance as to how state highway agencies approach this issue. All 50 state highway agencies responded to this question because even those state highway agencies that use a detailed estimation procedure track historical bid average costs for minor work items. Among the 50 states,
updated after each letting or on an annual or on some other recurring basis. In addition to these two factors (i.e., how many bids to use and how often to make system updates), the department must decide for what period of time data will be retained in the database and how far back price data should be considered to determine average prices used in estimates. Typical look-back periods are 1 year, 18 months, or 2 years for use in averages. Nine state highway agencies retain data for as long as records exist. Estimators can examine and use the data for items that are not frequently encountered or items that have seasonal price swings. An averaging of data would obscure seasonal pricing. Estimators should know exactly how the prices they are using were created, because there are multiple mathematical methods to arrive at an index value or average value. Three common methods of deriving an index value are: Index value (average) = Index value (inverse) =
20 state highway agencies use low bid only 1 state highway agency uses low and second bid 15 state highway agencies use the three lowest bids 11 state highway agencies use all bids, but may exclude single bids that are very high or low 2 state highway agencies use all bids except high and low 1 state highway agency uses bid analysis to determine a reasonable bid amount for each line item Table D2.4 summarizes the estimation performance of the above practices. The one agency using a reasonable price and the two agencies using all bids except high and low reported the best performance. The one agency that used reasonable price to create its estimates did not have any experience using the approach for projects valued at more than $100 million, and, as with the two agencies that use all bids except high and low, this agencys total project experience over a 5-year period was limited. Of the remaining practices, using the three low bids produced the best results. Tips After it is decided which bid prices will be used to create the average price, a timetable must be established that species the frequency of data updates. Databases can be refreshed and
C
i =1
i =1
Index value (root of the product) = ( C1 C 2 C 3 . . . Cn ) where C = the individual costs elements and n = the numbers of cost elements.
( 1C )
i
Such information should be part of the state highway agencys estimation manual. Connecticut has several different sets of bid data information that the estimator can use as the situation dictates, as shown in Figure D2.4. A three low-bid printout is created for each project bid. At the end of each calendar year, average prices are computed, and every 2 years weighted unit prices are prepared. Resources The AASHTO Subcommittee on Design, Technical Committee on Cost Estimating is developing guidance on historical
Table D2.4. Number of bids used for historic bid price estimation.
Number of bids used Reasonable price All except high and low Three lowest Low only All Low and second Number of DOTs 1 2 15 20 11 1 Reported projects 24 64 497 755 260 24 Number reported more than 5% over estimate 1 3 88 169 74 13 % 4.2 4.7 17.7 22.4 28.5 54.2
A-75
cost-based estimation. Draft papers are prepared, but not approved for release. If interested, contact the chair of this technical committee. See this website for key contact persons: http://design.transportation.org/?siteid=59&pageid=756. The data for the Wisconsin DOT method of calculating construction costs for a roadway improvement project based on controlling cost items (these are the certain bid items that comprise the majority of total construction costs) can be found at: www.dot.wisconsin.gov/localgov/highways/docs/districtcontrolling.pdf.
quantities and unit prices for these line items is difcult due to this lack of denition in the design. One tool that is often used to estimate known but not quantied line items is developing historical percentages to cover those items. Historical percentages can be developed using projects that are relatively similar in scope and complexity. This tool relies on an agency having standard line-item numbers to aid in preparing such percentages. Historical percentages are typically developed for estimating contractor mobilization, construction engineering, and preliminary engineering costs. Why? There are circumstances when the estimator simply does not have sufcient time and information to detail all line items and develop quantities for these line items. With a good database of historical bid prices used on past projects, combined with standard line items for reference, developing percentages for a group of similar line items may take less time and be just as accurate as trying to estimate quantities for these line items. What Does It Do?
Cost estimates contain many line items when fully detailed through the engineers estimate at the end of nal design. However, early in project development, identifying and quantifying
A-76
all line items is difcult at best. This tool provides a methodology for estimating costs for these unidentied line items. When? Historical percentages are best applied when there are many small items that cannot be quantied due to lack of design. This tool can also be used when time to prepare the estimate is a constraint. Historical percentages are commonly used for estimating contractor mobilization, construction engineering, and preliminary engineering costs. This tool is most applicable in the programming and early design phases of project development. Examples On a recent Washington DOT (WSDOT) project that is early in preliminary engineering, a historical percentage was used to determine the estimated costs for erosion control and planting. This category of work has a set of standard line items under Section 17 of WSDOTs Standard Item Table. In this case, several similar projects, both completed and recently estimated, were used to develop a percentage range for the erosion control and planting component of the estimate. The percentages were based on a ratio of costs for this section to total direct construction costs without mobilization. The range varied from 2% to 9%. WSDOT provides guidance on some historical percentages. For example, mobilization, construction engineering (CE), and preliminary engineering (PE) costs are estimated typically using this approach. Mobilization is a percentage of direct construction cost. Suggested percentages based on construction cost are provided in the WSDOT Plans Preparation Manual, Division 8. Typical percentages used on recent projects have varied from 7% to 12%. Typically, ranges for CE costs are also shown in the Plans Preparation Manual, Division 8. These ranges are based on program type (preservation and improvement) and construction cost. The range for PE cost is typically between 7% and 15%. Tips The project from which historical percentages are developed should be very similar in scope and complexity to the project being estimated. The following approach to developing and applying this tool may be useful: 1. Identify components or project elements that can be estimated using a percentage. 2. Find several different projects that are similar. 3. Identify line items and actual cost for those items. 4. Calculate the sum cost of these items and determine the ratio percentage of the sum to total costs for several projects (e.g., percent of construction).
5. Select percentage that best ts the project being estimated. 6. Apply the percentage to the project, and incorporate the item into the cost estimate. The percentage selected must be consistent with the scope, complexity, and schedule for the project being estimated. As the dollar size of the project increases, historical percentages normally decrease. Construction execution can also impact mobilization and construction engineering costs. Resources Washington State DOT Plans Preparation Manual, Standard Item Table, can be found on the following website: http:// www.wsdot.wa.gov/eesc/design/projectdev.
A-77
number of designs but having the exibility to customize components improves the efciency of estimate development. What Does It Do? This tool is feature driven and template based to match the conceptualized project scope. It consists of a limited number of models conceptualized on standard roadways. The concept is to identify and group all major roadway types in terms of magnitude and allocate minimum design elements to each type. Each design element is further associated with parameters such as dimensions, pavement designs, and pay items. Similar standardized sections can be developed for structures. A model is chosen from the available list as appropriate to the project requirements and customized for any additional facility components that may be required. The tool should be able to generate multiple versions based on design renement and be used for tracking changes. The tool also should have default values based on historical databases and predetermined formulas. Validation and customization of values are permitted to produce more accurate estimates. When? This tool is used in programming when a project is being scoped for inclusion in an authorized program. Design is typically between 5% and 25%. The tool is used to update estimates periodically as design progresses (25% to 80%) until adequate information is generated from nal plans and specications to develop plans, specications, and estimates (PS&E) using line items and historical bid pricing. Examples Florida DOT (FDOT) has pioneered this concept by developing long-range estimates (LRE), which have four hierarchical levels: project, version, sequence, and component. The project level contains general information like the project, location, key personnel, time periods, budgeted costs, and project delivery. A number coding is further associated with each project to distinguish between ofcial and unofcial projects. The version level allows for coding the projects in multiple ways, for alternative designs. But, a primary version has to be designated for reporting and reviews. Costing information is summarized back to the version level. The sequence level accommodates choice of alternative designs from 12 section models representing type of construction, median, and shoulder type. Each model has default values that represent average conditions. These values can be modied to reect current conditions. Multiple sequences are possible when there are changes in the characteristics of the typical section. The component level relates to specic pay items, groups, and types of work. These pay items, groups, and types of work can either be optional or required. The latter are generated auto-
matically, while the former are at the discretion of project requirements. A tab system facilitates easy navigation through the levels. The virtual private networking feature of the LRE enables remote operation. For bridges, a cost reference sheet based on most common sections, designs, and spans is developed on a unit basis and incorporated at the preliminary design phase. Also, additional costs such as mobilization and contingency can be attributed on a percentage basis. The LRE provides for customization in terms of additional or extra items with relevant input from the estimator on parameters such as unit costs, quantity, and dependencies. This can also be calculated on a percentage basis of some dependent standard element. Figures D2.6-1 through D2.6-6 show various screen captures of the FDOT LRE. Tips Applying this tool requires the standardization of roadway sections by the agency. Care must be taken to include all major elements into each standardized model and to allow for exibility to adjust sections to t unique project conditions. Generating and maintaining bid history databases from previous projects are also essential elements for this tool. The user has to understand what is covered in the estimate using this approach and what must be added to cover all components of the project. Resources FDOT State Estimates Ofce, 605 Suwannee St., MS 34, Tallahassee, FL 32399-0450.
A-78
Figure D2.6-1. Screen capture of the FDOT LRE (showing main screen).
Why? The purpose of parametric estimation is to develop early project estimates when information is restricted to only gross dimensions work features. An item-level quantity approach based on predicting item quantities from preliminary quantity information is another potential parametric approach. While parametric estimation can be used in the planning phase, this
tool can provide a more detailed cost breakup than the traditional cost-per-lane-mile estimation. This more detailed cost breakup should improve accuracy and alleviate cost overruns. The tool is developed to provide simplied, reliable, early estimates that are based on current prevailing costs. The potential to separate quantity uncertainty from price uncertainty provides a better platform to track and analyze the effects of changes during project development.
Figure D2.6-2. Screen capture of the FDOT LRE (showing one of the standard sections).
A-79
Figure D2.6-3. Screen capture of the FDOT LRE (showing another standard section).
What Does It Do? A major fraction of a transportation projects costs is often attributed to one component, and many projects may have a common critical cost component. One parametric approach takes advantage of this fact and seeks to quantify the critical component in a unit volume. All pavements are three-
dimensional (length, width, and depth), and these parameters are typically known fairly early in project development. The concept is to develop factors based on roadway sections for different dimensions and associate them with a historical cost database considering all major items to construct the roadway. The individual factors are extracted as applicable to the project and are then cumulated for all elements in the
A-80
Figure D2.6-5. Screen capture of the FDOT LRE (showing multiple-sequence section selection).
Figure D2.6-6. Screen capture of the FDOT LRE (showing project totals).
A-81
estimate to derive a single factor, which is multiplied with a cost multiplier (i.e., ratio) representing closely a past project of similar type and scope. This tool, however, estimates cost for roadway construction only and does not include other project elements such as right-of-way or bridges. In another example, the item-level, quantity-based estimation approach enables continuous tracking and control by initiating quantity estimates at the outset. The basic estimation parameters, as derived from the statistical analysis, are then documented for future input in quantity calculation. The concept behind this tool development is to match historical data with current project elements and subject them to quantity model development using statistical techniques. Such analyses will provide estimators with cost-sensitive project elements, which can be closely monitored for improving estimate accuracy. Several parameters based on design, project locations, and other topographical and geographical conditions that may inuence project costs are incorporated into such modeling to improve accuracy. Major cost elements are hence identied, and a standard can be established for future reference with constant validation for current markets. When? This tool is used early in project estimating, through programming and early into the preliminary engineering phases of project development. Parametric estimation may be best used on less complex projects that tend to be more standard in terms of project components such as preservation projects (i.e., overlays) or bridge rehabilitation projects. Examples Minnesota DOT has developed a cost estimation tool based on the physical dimensions of the roadway using the length, width, and depth (LWD) methodology. The DOT uses a LWD factor, which is a cumulative computation of each roadway, shoulder, or ramps LWD volume. A project LWD factor is multiplied by a selected multiplier/LWD cost multiplier, which constitutes all major items to construct a roadway only, such as mobilization, removals and salvage, grading, aggregates, paving and approach panels, by-pass and temporary construction, drainage, concrete items, traffic control, turf/ erosion, and miscellaneous. Items such as bridges, signals, noise and retaining walls, traffic management systems and other special constructions are not included in the LWD cost multiplier and have to be estimated separately. ROW cost is also not included. A scope form is completed for every project at its inception. This form is used for extracting information revolving mainly around pavements for the three dimensions. It is preferred to have a separate entry for different depths along with areas.
A centralized database is maintained to generate cost multipliers calculated from past and current projects within a 5-year time frame. These cost multipliers are supplied on a projectby-project basis. The estimator requests these multipliers when they are required. The combination of the LWD factors and the cost multipliers culminate in a roadway cost, to which other costs, such as bridges and signals, are added to determine project totals. The tool inputs are through Excel spreadsheets and Word templates, while databases are queried with Access. Figures D2.7-1 and D2.7-2 show screen captures of the LWD tool. Texas DOT supported a study to develop an item-level, quantity-based estimation method. This method was developed on the belief that it was possible to segregate unit prices from estimates. The method is schematically represented in the ow chart shown in Figure D2.7-3. An overview of the systematic procedures for the quantitybased approach is illustrated in Figure D2.7-4. The approach was based on identifying factors affecting an item-level quantication from literature survey combined with experience obtained from past projects. These factors were then formulated along statistical techniques to establish correlations and develop models based on several assumptions. Several iterative steps rened the model to an acceptable computational program, which was then veried with current prices to validate the model. Another key aspect of this method was effective use of work breakdown structures, which are often the framework of estimates. The item-level, quantity-based approach employs quantity estimation models at project inception to produce preliminary estimates. Items comprising 80% of project costs based on historical data were identied as major work items. For each major work item, a statistical parametric model was developed to predict the quantity during the conceptual planning phase of the project. The results of the statistical analysis show a strong relationship between the item quantities and the parameters adopted in the models. The quantity prediction models are being integrated into an item-level cost estimation system to predict both major item costs and total project cost. By segregating unit prices from item quantities, the quantity-based approach provides an opportunity to document both price ination over time and changes in project scope. Sample outputs from such statistical analysis that aid in predicting costs based on quantities are shown in Figure D2.7-5. Tips The estimator needs to ensure that all project costs are covered, especially costs that may not be generated using the parametric approach, such as right-of-way.
A-82
Figure D2.7-1. Screen capture of the LWD tool showing post letting project history.
Figure D2.7-2. Screen capture of the LWD tool showing multiplier adjustment options.
A-83
Identication of those elements that contribute to the major fraction of a projects total cost is critical to this tool. The tool relies on cost predictions for items of work based on statistical predictions. Hence, identication and inclusion of cost items that contribute to 80% of the cost for each estimate is crucial for the tools success. The standardization of such elements in relation to project types is to a large extent the basis of implementing this tool. The tool can model additional items that may not be standard as long as historical information is available. Resources Minnesota DOT (2002). Documentation of Guidelines for Statewide Uniform Cost Estimates.
Chou, Jui-Sheng, Min Peng, Khali Persad, and James T. OConnor (2006). Quantity Based Approach to Preliminary Cost Estimates for Highway Projects, Transportation Research Record 1946: Construction 2006, Transportation Research Board. http://gulliver.trb.org/news/blurb_detail.asp?id=6858. Project Management Institute (2004). A Guide to the Project Management Body of Knowledge (PMBOK Guide), Third Edition.
A-84
Figure D2.7-5. Sample predicted values of logarithmic engineering quantity versus historical values for representative work items.
that all components of project cost have been considered and accounted for in the estimate. Because these are usually straightforward documents they are good tools for communicating estimate completeness and the allotment of cost to the different portions of work. What Is It? Spreadsheet templates are standard item lists of things an estimator should consider when calculating the cost of a project. When constructed in an electronic spreadsheet program, they provide computing, text-editing, and formatting capabilities at high speed and low cost. Electronic spreadsheet templates can store both the formulas and the computed values returned by the formulas. Why? By using a spreadsheet template to guide estimate development, state highway agencies can improve estimate accuracy by ensuring that critical cost items are included in the cost total and that the estimator considers signicant impacting factors when preparing the estimate. Furthermore, a welldesigned spreadsheet will clearly communicate the total estimated cost of the project, as well as what is included in the estimate and what various categories of work are expected to cost. This allows easy comparison to historical values for making rapid sanity checks of estimated costs. What Does It Do? Spreadsheet templates (1) provide estimate development guidelines that facilitate creation of a complete estimate and (2) support the evaluation of cost and schedule credibility. They serve to document the estimate and provide an easy-toread format, which facilitates communication about the project costs in a uniform and structured manner. Monte Carlo
simulation can also be added to spreadsheets for doing probabilistic estimation or risk analysis. When? Different spreadsheet templates can be used in the course of project development as scope is quantied and additional information becomes available. However, templates should be designed so that major categories can easily be expanded as project detail is better dened. Spreadsheet templates are also excellent tools for supporting and documenting quantity takeoff. Examples The detail of a spreadsheet template will vary by project type and by the point in time when the estimate is being created. In the earliest stages of project development, there is limited project denition and design knowledge. One state highway agencys early-stage spreadsheet has only ve cost categories: 1. 2. 3. 4. 5. Grading and drainage Base and pavement Lump items Miscellaneous Engineering and construction
The sheet also formulates calculation of a total cost and a total cost per mile, which provides transparency in comparing the cost with similar projects. These basic categories can be expanded as additional information about the project is developed. Tips Computer spreadsheets such as Excel require less initial investment than commercial estimation software and tend to be very exible. The list of included items on spreadsheets is
A-85
often not exhaustive, and space should be provided in each section of the spreadsheets to allow the entry of additional cost items that may be unique to a particular project. Resources Michigan DOTs Road Cost Estimating Checklist can be found at www.michigan.gov/documents/MDOT_0268_Road_ Cost_Est_120543_7.pdf. New Jersey DOT has posted on the Internet (www.state. nj.us/transportation/eng/CCEPM/) a Preliminary Estimate (English or Metric) Spreadsheet (zip 85k). Georgia DOT has posted on the Internet (www.dot. state.ga.us/) the format for submitting scope and cost estimates for GDOT projects in the form of Excel workbooks to expedite the review and approval process. Type Guidelines for scope & cost estimate workbooks in the search box on the home page.
(TRACER) software is a parametric cost estimation tool created to help plan and budget for highway and bridge construction/renovation projects at the predesign and preliminary design phases. TRACER was developed by Earth Tech. What Is It? Trnsport has three modules (Cost Estimation System, Estimator, and Proposal and Estimates System) that interact with each other or work independently, as applicable, to produce design estimates. Figure D2.9-1 shows the interaction of these modules. The Cost Estimation System (CES) and Estimator modules are the most popular modules among state highway agencies that use Trnsport for design estimation. The CES module is a network-dependent module that is fully integrated with the other database-oriented Trnsport modules. It provides a highly productive environment in which to prepare parametric, bid-based, or cost-based estimates. The Trnsport Estimator module is a highly interactive, PCbased, stand-alone estimation system for highway construction that uses a graphic user interface to prepare detailed estimates. It is well suited for distributing the estimation function both throughout the agency and to the supporting consulting community. The Proposal and Estimates System (PES) module is designed for use at relatively advanced design stages, when more project data are available. This module accepts data in a project, category, and item level, and grouping of multiple projects is allowed to track all related costs and sources of funding. The ability of this module to interact with the Bid Data Analysis and Decision Support System (BAMS/DSS) module of Trnsport and the exchange of this function with the CES module are the key attractions in parametric estimation. TRACER is a new computer-based tool developed to support parametric estimation. The database that supports this tool is the RS Means Heavy Construction Cost Data manual.
A-86
Why? During programming and preliminary design, specic elements are dened for a project, and cost estimates are prepared using a number of different tools. The Trnsport estimation software can facilitate the use of several design estimation tools, such as historical bid-based and cost-based, bottom-up approaches. This software allows the estimator to build up an estimate as the design progresses. When software is linked to a historical cost database, selecting unit cost information can be more efcient because the user works within the software to nd the appropriate historical bid costs that t the element being estimated. Further, changes in the cost estimate can be made easily as new information or modications to existing information are made. The software can be used to eventually develop the engineers estimate and support preparation of bid documents. In programming, if quick estimates are desired using major project parameters, TRACER can be used. Minimal input is required to generate a construction cost estimate. What Does It Do? The CES module contains a standard set of cost groups for parametric estimation. It is also equipped with tools that, coupled with its integration with the other Trnsport components, permit the uploading of historical labor, equipment, material and crew data for more detailed estimates. Its parametric estimation strategy uses cost groups that are based on major project types. They are groupings of items that are usually known early in the planning process for the type of project. Trnsports Estimator module supports generation of cost estimates using cost-based or bid-based techniques. Hybrid estimates are easy to create, allowing cost- and bid-based methodologies to be used in the same project estimate. Estimator can also reference a price lookup table if data are lacking or can perform ad hoc data entry of unit prices. The reference data used to generate estimates, including wages, equipment costs, material costs, production rates and historical bid data, are stored and maintained in the computer. Estimator will automatically apply the weighted average price to line items, providing statistically valid estimates. If the historical data set is sufciently large, regression coefcients can be calculated and applied. Estimator can also bridge between the other modules and design systems to enhance data exchange. TRACER uses statistical relationships between major systems of a highway project, termed modules, and the details that describe that system. For example, a bridge module is available to estimate the cost of a bridge. The user then provides the system denition for the bridge. In this case, three basic elements are requiredbridge size (length and width),
separation type (over highway and height), and denition (superstructure and substructure type). This is the only input required. TRACER then generates all direct construction costs. Contractor overhead and prot must be added. A template is provided to insert these values. TRACER costs can be adjusted for different locations. When? These modules of Trnsport can be used in both programming and preliminary engineering. CES can be used in programming to create a parametric estimate. It can also be used for bid-based estimation at the programming phase if sufcient design details are available to support line-item-type estimates. All three modules can be used during preliminary engineering to support on-going design estimates. TRACER is probably most applicable during programming. Examples In the past, the NYSDOT used the mainframe versions of Trnsport PES, LAS, and DSS, but as agencies moved from the mainframe to the client/server versions, AASHTO decided to drop support of the mainframe version. NYSDOTs migrate to the client/server version. Figure D2.9-2 shows the interaction of estimation-related Trnsport modules. A CES product tour is available at https://www.nysdot.gov/ portal/page/portal/main/business-center/trns-port/ modules/ces (click on CES Product Tour at the bottom). An Estimator product tour is available at http://www. infotech.com/software_solutions/estimator.php (click on Product Tour on the left). When using TRACER, the estimator needs to check the results against past history to verify the estimate. Several screen captures are shown in Figures D2.9-3 through D2.9-5. Tips Estimators who have access to the Trnsport database should use CES, while estimators without a connection to the network should use Estimator. The information generated by the CES module for costbased estimation includes the following:
Detailed job estimate snapshots Labor Equipment Materials Cost sheets Crews Programs
A-87
when Estimator is properly congured with BAMS/DSS, another Trnsport module. Reference prices or ad hoc data entry is permitted when historical data are not available. Cost-based estimation techniques are exible, yet structured and simple. In-built Estimate verication processes improve accuracy.
The estimator must ensure that all project costs are covered, such as right-of-way and preliminary engineering costs. These costs may not be generated by CES. The estimator must check all input and output to ensure that the estimated costs for major line items are within expected agency tolerances for the project type being estimated. This check can follow the Puerto principle: 80% of the estimated cost of construction is covered in 20% of the items. Comparing the overall estimate with estimates from similar-type projects that are recently bid or completed is another method of checking an estimate. Finally, using the statistical techniques in CES and Estimator may help identify line-item estimates that are outside normal cost ranges for that item.
A-88
Figure D2.9-3. TRACER system denition input for a bridge over a roadway.
Additional information can be found using the following website: dot.state.ny.us/trns-port/about.html. Resources The Technology Implementation Company, Gainesville, Florida, see website addresses: www.infotech.com or www. cloverleaf.net. AASHTOWare, Transportation Software Solutions, American Association of State Highway and Transportation Officials, www.aashtoware.org.
state highway agencys program are sometimes xed independently of the scope of the project. When this scenario occurs, the preliminary engineering effort is substantially inuenced by the dollars available for construction and right-of-way. Project scopes must be tailored to t the budget; thus, the focus of engineering becomes a constant tradeoff between costs and scope.
A-89
Figure D2.9-4. Additional TRACER information created by the bridge system denition (beams).
The scope will be reduced if the current cost estimate is higher than the xed budget. Scope may be added if the current estimate is substantially less than the xed budget. What Is It? Design to cost is a method of controlling project cost by establishing cost goals at specified levels of a project work breakdown structure and then requiring the project to make scope tradeoffs during the engineering process. These tradeoffs will ensure that the facility built will meet the cost goals. In design to cost, the cost goals are added to the existing design requirements to form additional requirements of the project. Why? This tool is used most often when external sources mandate a xed budget for a project. The budget may have been prepared with little or no information on the project or may
be based on cost information that has not been recently updated. If there is little or no possibility of obtaining additional funding, then the project team must develop a design that meets the mandated budget. This often will lead to a scope that is less than that which was envisioned by the external source. What Does It Do? This tool is based on constant evaluation of different scope options available to construct a project while continuously checking cost ramications of these scope options in order to not exceed the predened total project cost. This tool can foster innovative design solutions, which can help in alleviating cost overruns. When? This tool should be used early in programming or preliminary engineering, when design criteria and basis are being
A-90
Figure D2.9-5. TRACER direct construction cost output for this bridge (without markups).
established. The project design team will need adequate time to explore alternative design solutions in an attempt to maintain the project within the mandated budget. Examples The ow chart in Figure D3.1 illustrates typical steps followed to implement the design-to-cost tool. The process is iterative until the estimate cost of the project is aligned with the established budget. This alignment process xes the scope of the project. Tips Several factors are important when using the design-tocost approach:
competitive pricing requirements by the key participants in the development process Establishment and allocation of target costs down to a level of the construction cost components where costs can be effectively managed Commitment by estimators to match development budgets and target costs Stability and management of requirements to balance requirements with affordability and to avoid creeping elegance An understanding of the highway construction cost drivers and consideration of cost drivers in establishing highway specications and in focusing attention on cost reduction Creative exploration of concept and design alternatives as a basis for developing lower-cost design approaches
A-91
Why?
Access to cost data to support this process and empower
to provide improved cost data Continuous improvement through value engineering to improve product value over the long term Resources Crow, Kenneth (2000). Achieving Target Cost/Design-toCost Objectives, SAS Institute. http://www.bettermanage ment.com/library/library.aspx?l=12369.
Good documentation supports the cost estimates credibility, aids in the analysis of changes in project cost, enables reviewers to effectively assess the estimate, and contributes to the population of state highway agency databases for estimating the cost of future projects. Each project should have an individual project estimation le that is separate from the general project le or the correspondence le. The primary purpose of this requirement is to ensure that each project has a well-documented and easily retrievable history of the assumptions, methods, and procedures used to estimate the costs associated with the projects specic scope of work. Having this information contained in one location and separated from other project documentation will help ensure that the estimate information is readily accessible and uncluttered with other project information. What Does It Do? A project estimation le provides a corporate memory and historical database for cataloging the basic reasons behind the original estimated cost, as well as reasons for subsequent cost revisions. Additionally, it usually provides other project descriptive information, such as trends that affect the item cost, cost from similar past projects, and external factors that limit construction operations. This historical le allows easy
A-92
comparison of the current estimate with previous estimates and resolution of discrepancies When? The project estimation information should be retained in the central ling system from the time the initial project estimate is prepared until project close-out. The project estimation le should include all cost estimates prepared for the project up to and including the completed contract plans, specications, and estimates (PS&E). Archiving the cost estimation les is a good practice because these les can be useful in reconciling completed project cost and responding to inquiries. Examples For each bid item element, there should be a description of the derivation of its estimated cost in sufcient detail to allow an independent reviewer to determine whether the estimate is complete, accurate, and realistic. The following information should be provided:
Item number and title. Item description and any tailoring used for this estimate. Methodology. Describe how the items costs were esti-
Level of knowledge about scope. Level of risk. Level of estimate detail. Techniques used to compete the estimate. Experience of those who developed the estimate. Cost tractability. When a prior cost estimate exists, a cost track should be prepared. The cost track should provide a concise explanation for any cost change to an item from the prior estimate. Who participated in the development of the estimate. A description of an approach used by the Missouri DOT regarding estimate documentation is shown below:
1-02.12 (5) DOCUMENTATION OF PROJECT ESTIMATES. Each project will have an individual project estimate le that is separate from the general project le or the correspondence le. The purpose of this requirement is to ensure that each project has a well documented and easily retrievable history of the assumptions, methods and procedures used to estimate the right of way and construction costs associated with the specic scope of work identied for the project. Having this information contained in one location and separated from other project documentation will help ensure that the estimate information is readily accessible from a known location and uncluttered with other project information. At a minimum the project estimate le should include any assumptions that have been made, the current project scope, maps, photos, as-built plans, functional classication, design criteria and a copy of or reference to the cost data used to support the estimate. This basic information should be included in each project estimate le regardless of the stage of project development. A sheet should be placed in the front of each estimate le so the project manger can record the date and current project milestone or project development stage each time the project estimate is changed, updated or reviewed. A signature line should also be included to document the project managers review of the estimate le. Depending on the level of project development that has occurred on the project, the amount and type of documentation contained in the project estimate le will vary. For projects that do not have clearly dened scopes and in the absence of other estimating methods, the cost-per-mile type of estimates described in Section 1-02.5 are suitable and acceptable to develop the initial project estimate. Cost-per-mile factors may be developed from a previously constructed project of similar type and conditions or the generic cost per mile factors included in Figure 1-02.1 may be applied to the estimated project length to develop an initial project cost. Information used to develop the project specic cost per mile factors or the generic factors from Figure 1-02.1 that are used should be well documented and included in the project estimate le. This information may consist of items such as estimate software, bid tabulation data from similar projects, unit bid price books, or some other reputable resource. Additionally any deviations from the generic cost per mile factors, that are determined to be warranted by the estimator, shall have well documented reasons included in the project estimate le.
mated. Depending on the choice of methodology, the estimator could include one or more of the following practices: The use of unit prices from the departments historical bid tab database. This is the most common approach. Under this approach, bid data are summarized and adjusted for project conditions (project location, size, quantities, etc.) and the general market conditions. The actual cost approach (i.e., a bottom-up estimate). This approach takes into consideration factors related to actual performance of the work (i.e., cost of labor, equipment, and materials; sequence of operations; and production rates). This approach requires the estimator to have a good working knowledge of construction methods and equipment. How lump-sum items are handled. Base year of the cost calculation. For long-duration projects it is a good practice to present the items estimated cost in constant year dollars, both total dollars and distributed across scal years. Detailed, clear environmental items (requirements). How indirect costs are determined. Each contingency allowance assigned to the various parts of the estimate. If extraordinary conditions exist that call for higher contingencies, the rationale will be documented. All uncertainties and risks associated with the estimate.
A-93
The district may prepare a master reference le that contains the cost-per-mile, unit costs, accepted PE [preliminary engineering] and CE [construction engineering] cost as a percentage and other critical policy and procedures that are used to prepare project estimates on an annual basis in order to avoid duplication of the information in multiple project estimate les. However, this master le must be kept as a permanent reference le that can be cited and reference to. It must be included in each individual project estimate le. Variations of the Miscellaneous and Utility Costs percentage (see Figure 1-02.1) should also be documented in the project estimate le. As discussed in Subsection 1-02.6(4) some projects that are not complex and have a small scope of work may warrant the inclusion of a cost adjustment factor to compensate for the short project development time and project uncertainties. These cost adjustment factors shall be well documented in the project estimate le and have a reproducible basis. These factors should only be applied to projects that fall into the small noncomplex category. They shall not be applied to all project estimates as a matter of district practice. A cost adjustment factor will never be considered as an acceptable substitute for preparing a well documented and accurate estimate if adequate project information is available. Once the project scoping phase of the project is completed and estimates are being produced for inclusion in the STIP [statewide transportation improvement program], cost-per-mile type estimates will no longer be acceptable. All estimates made beyond this stage of project development shall be based upon estimated pay item quantities and unit costs. Copies of all pertinent information related to the project estimate, including all documentation of the quantities and unit costs used, shall be included in the project estimate le. All estimate data sheets should include the date of preparation and the estimators name. Each time a nal Project Amendment Tracking System (PATS) form is prepared for the project a copy should be placed and retained in the project estimate le. Another copy of the PATS form will be provided to the district transportation planning coordinator, who will be responsible for ensuring a copy is also immediately submitted to GHQ [General Headquarters] Transportation Planning. This procedure should be followed for all projects, whether designed internally or by a consultant. The documentation included in the estimate le must substantiate the latest nal PATS form that has been submitted to GHQ Transportation Planning. In addition, any project scope change approval letters required by Sections 1-02.11 and 1-02.12(9) shall also be retained in the project estimate le. The project estimate les for all projects under development in the district should be located in one central location. District management is responsible for establishing estimating procedures, within their district, that will indicate the person responsible for maintenance of the project estimate les and the central location for the les. The district estimating procedures should also establish general guidelines for the contents that should be maintained in the le. The project estimate information should be retained in the central ling system from the time the initial project estimate is prepared until after the project has been included in the Accountability Report to the Legislature. The project estimate le should include all cost estimates prepared for the project up to and including the completed Contract Plans (PS&E) Estimate. Cost data following submission of Contract Plans to GHQ is not required in the project estimate file. Once the project data has been included in the accountability report, there is no requirement to archive the cost estimate les. However, the district may wish to retain cost data longer for purposes such as reconciling completed project cost with GHQ Transportation Planning, responding to additional inquiries related to the Accountability Report, or until there is a final payout on the project by FHWA, etc.
Tips The project estimation le should, at a minimum, include any assumptions that have been made, the current project scope, maps, photos, as-built plans, functional classication, design criteria, and a copy of or reference to the cost data that were used to develop the estimate. This basic information should be included in each project estimation le regardless of project development stagethe creation of the le begins with the very rst estimate. A sheet should be placed in the front of each estimation le so the project manger can record the date and current project milestone or project development stage each time the project estimate is changed, updated, or reviewed. A signature line should also be included to document the project managers review of the estimation le. When items are estimated by percentages of other costs, as is often done for miscellaneous and utility costs, the percentage should also be documented in the project estimation le. Some projects that are not complex and have a small scope of work may warrant the inclusion of a cost adjustment factor to compensate for the short project development time and project uncertainties. These cost adjustment factors shall be well documented in the project estimation le and have a reproducible basis. These factors should only be applied to projects that fall into the small noncomplex category. They should not be applied to all project estimates as a matter of common practice. A cost adjustment factor will never be considered an acceptable substitute for preparing a welldocumented, accurate estimate if adequate project information is available. Depending on the level of project development that has taken place, the amount and type of documentation contained in the project estimation le will vary. Information used to develop the initial estimate, such as cost-per-mile factors or the generic factors, should be well documented and included in the project estimation le. This information may consist of references to software databases, bid tabulation data, unit bid price book data, or some other reputable resources. Additionally, any deviations that are determined to be warranted by the estimator from the generic cost factors shall be well documented in the project estimation le.
A-94
The estimation procedures manual should also establish general guidelines for the contents of the le. The documents that serve as the basis of the estimates should do the following:
Provide a description of site conditions (railroad through or
should additionally be subjected to an external review and comparison with the estimate. What Is It? This tool consists of an external estimate/document review process structured to minimize or eliminate contractorperceived project risk by ensuring that the construction documents are fully coordinated, complete, and buildable. It should be employed after the agencys own internal estimate/ document review. Specically, it adds an important dimension to estimate/document reviews because the reviewers have not been privy to how the plans and project documents were developed. Therefore, the reviewers shape their opinion of the work strictly by what is presented in the documents. Why? Many times, the agency personnel who regularly review project documents are so familiar with the project or how the state highway agency describes project elements that their historical knowledge prevents them from completing a valid review of the projects documents compared with the estimate. This can be a serious problem in the case of very large or complex projects where a critical review of the documents is most important for ensuring clarity of plans and specications. The primary method used by contractors to cover document ambiguity is adding dollars to the bid prices, and that creates a disparity with the state highway agencys estimate. What Does It Do? External estimate/document reviews support the development of accurate cost estimates for large and complex projects by bringing an independent perspective to the quality of the project documents, particularly in terms of their relationship to the assumptions upon which the estimate is based. It is a process that ensures that construction requirements are complete and not in conict. When? The FHWA believes that an external review is appropriate prior to the first release of an estimate to the public for large and complex projects. External estimate/document reviews should also be conducted for large and complex projects during the latter stages of design development. It is important to conduct such a review prior to advertising a project, and such a review must use the final project documents. Therefore, the review must be scheduled with suffi-
adjacent, utilities, need for stage construction, etc.) Describe assumed construction methods and alternatives considered Explain the decision criteria used for evaluating alternatives List and explain all general assumptions that apply to all alternatives List and explain all specic assumptions (e.g., excavation costs assume 30% rock) Include a full listing of the item take-offs (quantities)
Resources Missouri DOT (2004). Chapter 1, General Information: Needs Identication Project Scoping and STIP Commitments, Section 1-02, Project Development Manual. www. modot.org/business/manuals/projectdevelopment.htm. Many state highway agencies use the commercial estimation software Trnsport Estimator by InfoTech. This software requires the estimator to input much of the data that should be in a project estimation file. See the NYSDOT TrnsPort Estimator Guidelines, Draft May 6, 2004 version, which can be found at www.dot.state.ny.us/trns-port/files/ nysdotestguide.pdf.
E1 Estimate/Document Review
In the construction world, designers provide contractors and subcontractors with graphical and written representations (i.e., the project plans and contract documents) that describe what is to be constructed, the required quality, and sometimes how it must be constructed. The constructors must transform these concepts into physical reality. The quality of this transformation from abstraction to reality not only determines the quality of design work provided by the designers, but also impacts how the work is priced. Bafing drawings or any ambiguous wording as to what quality or limitations to construction activities are expected affects project cost.
A-95
cient time after the review for making any necessary corrections to the documents. Examples While no external estimate/document review examples exist that strictly match the tool outlined here, research has repeatedly indicated the need for such a process. Many agencies do have review formats in place for the documents in general that could be used as the starting point for developing this tool. The Central Federal Lands Highway Division, in the Design Resources section of its website, has a Document Review Comment and Response form (www.chd. gov/design/_documents/misc_forms/design/PSE_CMT.doc). Tips The most important factor in the success of this tool is engaging independent external experts, who could be retired construction professionals or construction professors who have had actual eld experience. These reviews should evaluate all project documents because many times geotechnical, hazardous material, and environmental reports, which are included only by reference in the bid package, contain information or directions that affect how the work must be conducted and therefore inuence bid prices, particularly if there is a conict between these reports and the project plans and specications. The design engineers should provide a written response to all project estimate/document review comments. Responses to review comments must be available to the project team prior to production of the bid documents so as to allow sufcient time for the estimators to properly prepare the PS&E. For projects that will be constructed using multiple contracts, a phasing or staging plan should be provided to delineate the boundaries of each phase. The same would be true of multiple projects in a corridor. Additional tips can be found in Tool E1.2, Estimate/Document ReviewInternal. Resources Alaska Division of Legislative Audit (1994). Department of Transportation and Public Facilities Highway Design Cost and Quality Comparison. http://www.legaudit.state.ak.us/ pages/audits/1995/pdf/4472.pdf. Tilley, P. A., A. Wyatt, and S. Mohamed, S. (1997). Indicators of Design and Documentation Deciency, Proceedings of the Fifth Annual Conference of the International Group for Lean Construction, 1617 July, Australia, 137148. The Massachusetts Highway Department and the American Consulting Engineers Council of Massachusetts (1998). Measuring Design Quality.
of the plans.
Provide item X as required. Provide item Y if necessary.
A-96
Contractor to provide item Z as needed. If phased construction is required by the agency, the agency
will allow a 30-day time extension for the contract. Most state highway agencies have policies and procedures in place for the review of project plans and contract documents. However, most of these processes have as their purpose to ensure that the project has been properly designed and that all necessary contract language is included in the document package. These existing reviews are for the purpose of checking completeness to general agency standards, whereas the reviews developed under this tool seek to establish clarity and eliminate presentation-related conicts. When? Estimate/document reviews should be conducted at each design development phase (30%, 60%, 90% design). A cost estimate should be provided along with the intermediate design phase documents. At 100% design and prior to advertising a project, there should be a comprehensive in-house review of the project plans and all contract documents. All projects receive the same type of reviews; however, larger projects usually warrant a more in-depth review. Examples While no estimate/document review examples exist that match the strict purpose of this tool, many agencies have review formats in place for the documents in general. The Central Federal Lands Highway Division, in the Design Resources section of its website, has a Document Review Comment and Response form: www.chd.gov/design/_ documents/misc_forms/design/PSE_CMT.doc. Georgia DOT has the material for Field Plan Review Inspections posted in the Transportation Online Policies and Procedures System (TOPPS) section of its website: www. dot.state.ga.us/topps/ss/engserv/2440-1.htm. Tips The methodology for conducting an estimate/document review should be to focus on project buildability from a contractors perspective of risk. The project manager should immediately arrange a meeting with the designers to resolve issues if any review comments indicate a conict between the design documents and the projects scope and/or standards of practice or conicts within the documents. The design engineers should provide a written response to all project estimate/document review comments. Responses to all project estimate/document review comments must be submitted prior to production of the bid documents so as to allow sufcient time for the estimators to properly prepare the PS&E.
The project manager should immediately arrange a meeting with the designers to resolve issues when review comments indicate a conict between the design documents and the projects scope and/or standards of practice. Each contract requirement should be stated only one time and in the most logical location in the contract documents. Information in one document should not be repeated in any of the other documents. Each document has a specic purpose and should be used precisely for that purpose. This simplies the retrieval of information and substantially reduces the possibility of conicts and discrepancies. Everyone involved with a project benets from this standardized approach to the placement of information within the construction documents. Resources Alaska Division of Legislative Audit (1994). Department of Transportation and Public Facilities Highway Design Cost and Quality Comparison. http://www.legaudit.state.ak.us/pages/ audits/1995/pdf/4472.pdf. Tilley, P. A., A. Wyatt, and S. Mohamed (1997). Indicators of Design and Documentation Deciency, Proceedings of the Fifth Annual Conference of the International Group for Lean Construction, 1617 July, Australia, 137148. The Massachusetts Highway Department and the American Consulting Engineers Council of Massachusetts (1998). Measuring Design Quality.
E2 Estimate ReviewExternal
The most effective means of improving estimate quality is to rene the methods of identifying errors and omissions, not to rene estimation methods or computer software. No estimate should be released without review. Estimate reviews should be conducted at strategic times during estimate preparation to improve accuracy and completeness. The formality of a project estimate review and the depth of the review at each stage in project development will vary depending on the type of project and project complexity. The rst review of the estimate should be conducted by the team that prepared the estimate. This is essentially a screening review that ensures that the math is correct, the process is documented, and agency guidelines were followed. When very complex projects or projects involving new construction methods are being estimated, management should require that there be an external review of the estimate by qualied professionals.
A-97
ment is what identies mistakes, detects awed assumptions, and identies where the process has missed critical cost drivers. The surest way of conducting a successful external review is by selecting a panel of independent reviewers that have as broad a range of engineering experience as the project demands. What Is It? External reviews concentrate on the estimation process and methodology. They are applied based on project scope and design development at the point in time when the review is conducted. An external review should include a risk analysis that identies the critical elements of the estimate and possible impacting risks. Why? Large projects with multiple interacting activities, urban projects with numerous stakeholders, and projects using new technology all test the estimators ability to properly account for all cost drivers when developing a project estimate. Therefore, a review that brings a viewpoint completely external to that of the state highway agency should be part of an inclusive review process. This includes a requirement for internal reviews of the estimate calculations and the applied unit costs. What Does It Do? The reviewers seek to assess the reasonableness of the assumptions supporting the cost and schedule estimates and assess the rationale for the methodology used. Reviewers receive a brieng from the project team and the estimators and are given access to all available project documentation. By applying parametric techniques or ratios to analyze costs and schedule reasonableness, they check the completeness of the estimate. However, they usually do not perform quantity takeoffs or estimate individual items. The result is a report that details ndings and recommendations. In the case of a very complex project with critical cost drivers, it is sometimes necessary for the reviewers to develop an independent, bottom-up estimate of their own to ensure estimate reasonableness. This may or may not involve quantity takeoffs, but usually does necessitate vendor quotations and productivity analysis of the critical cost items. When? Independent external reviews are more typically employed on PS&E of large complex projects. However, having such reviews conducted much earlier in the design process can pro-
vide real benets because they often discern cost drivers that can be addressed by design changes, thereby reducing project cost. Examples Several state highway agencies have used retired heavy construction personnel to conduct estimate reviews and in some cases have even staged mock bids. As an after-the-fact example, on December 13, 2001, Maryland DOT opened bids for the Woodrow Wilson Bridge superstructure contract. A single $860 million bid was received. That amount was more than 75% higher than the engineers estimate for the contract. Maryland formally rejected the bid because it far exceeded the projects budget. An independent review committee (IRC) was organized to identify and evaluate the reasons for the large discrepancy between the engineers estimate and the bid submitted. The IRC determined that the owner-produced estimate was technically solid, based on the tangible factors like the cost of steel, concrete, and other materials. But certain signicant factors, particularly for large construction projects, are difcult to quantify in an estimate. The IRC went on to state that the estimate did not sufciently take into account the intangibles of market factors, specically the following:
Contractors capable of bidding a project of that size were
seeking larger margins to protect themselves due to recent experiences on other mega-projects and to associated project risks. There were several other large bridge projects bidding in the same period, a completely external factor that caused a lack of competition. Equipment demands on projects of this size are substantial. Maryland DOT took the advice of the IRC and repackaged the contract and rebid the project approximately a year later as three independent contracts. The first contract rebid came in 11% over the estimate, but there were five bidders and it was a workable bid. The other two contracts both came in below the estimates, one by 28% and the other by 25%. Tips The reviewers need to be experienced professionals who have an understanding of engineering and construction complexities. Market conditions or changes in the macroenvironment can affect the costs of a project, particularly large projects. Often, only large contractors or groups of contractors can handle the construction tasks or even obtain bonding for a large project. The size of the project affects competition for a project and the number of bids that a state highway agency receives for
A-98
the work. External independent reviews are usually more attuned to the impacts of such factors on project cost. Resources Maryland DOT (March 1, 2002). Summary of Independent Review Committee Findings Regarding the Woodrow Wilson Bridge Superstructure Contract. The full report is available from the MDOT. Woodrow Wilson Bridge Project Bridge Superstructure Contract (BR-3): Review of the Engineers Estimate vs. the Single Bid, February 28, 2002. This report is available from Maryland DOT. Douglass, Robert, Robert Healy, Thomas Mohler, and Shirlene Cleveland (2004). Adventures in Building Another Washington Monument, Woodrow Wilson Bridge Project Re-bidding Outcomes, presented at the 2004 TRB Annual Meeting.
contract administration engineer, a state maintenance engineer, and two project/eld engineers. What Is It? A formal committee estimate review is a cost estimate validation tool. This cost validation tool entails an objective review of the estimate by a group of experienced third-party state highway agency individuals who did not participate in development of the estimate. Why? The most effective means of improving estimate quality is, not to rene estimation methods or computer software, but to rene the methods of identifying errors and omissions. This is a tool to ensure that estimation criteria and requirements have been met and that a well-documented, defensible estimate has been developed. What Does It Do? The review committee seeks to subjectively determine estimate accuracy, based on the totality of the information available. In particular, the committee:
Determines whether the estimate satisfies the project
E3 Estimate ReviewInternal
Estimate reviews should be conducted at strategic times during estimate preparation to improve accuracy and completeness. The formality of a project estimate review and the depth of the review at each stage in project development will vary depending on the type of project and project complexity. No estimate should be released without internal reviews. The team that prepared the estimate should conduct the rst review of the project estimate. This is essentially a screening review that ensures that the math is correct, the process is documented, and department guidelines were followed. In the case of a straightforward overlay project, a formal review may not be necessary. However, as project complexity and scope increase, it is necessary to conduct formal reviews with either an in-house/peer review or a formal committee review. When very complex projects or projects involving new construction methods are being estimated, management should require that there be an external review of the estimate. There can be several different approaches to estimate reviews: (1) a review of calculations and applied unit costs, (2) a review of the process and methodology, or (3) a very complete review that encompasses evaluation of both calculations and mythology. All reviews must closely examine the assumptions that form the basis of the estimate, internal logic, completeness of scope, and estimation methodology.
criteria: The committee seeks to ensure that the estimate conforms to the project scope and design documents. Appraises the estimate methodology: The committee must be able to follow and check the estimate methodology. Steps to do this would include verifying estimation techniques and sources of estimate data. The committee should be able to clearly understand the origin of all numerical data in the estimate. Identies uncertainties: The committee should conrm all uncertainties documented in the estimate and identify other uncertainties in the estimate that were missed or glossed over. It is good to note these uncertainties at this time so that an accurate estimate can be developed. Documents the nding: The ndings of the estimate review must be documented. The committee may use an estimate review checklist or prepare a concise written report that documents the ndings. A sample estimate review checklist is present here in the example part of this section. When? Reviews are typically employed on plans, specications, and estimates (PS&E). However, as the project design is developed and the revised estimates are generated, it is good practice to conduct a review of the revised estimate, particularly at the major design development stages, 30% and 60%. These earlier reviews can provide real benet because they often discern
A-99
cost drivers that can be addressed by design changes and, in so doing, reduce project cost. Example Here is an example of a checklist used by a formal committee when conducting a review.
REVIEW CHECKLIST Review Date: Review Location: Project Name: Reviewers Names and Organizations: Background Data and Conditions: Is there complete technical scope documentation, including the following elements? ____ Description of the work to be performed; ____ Performance criteria and requirements; ____ Discrete tasks and deliverables; ____ Resource requirements; ____ Sequence of events and discrete milestones; ____ Work not included in the scope. Have milestone descriptions been developed for each milestone associated with the project? Does the technical scope documentation for the estimate include descriptions of support associated with the work to be performed? Is the technical scope for the estimate consistent with the site, regulatory requirements and constraints (e.g., permit conditions, regulations) identied during the planning process? Cost Estimate Are appropriate historical cost data used in the estimate? Are direct costs that are associated with individual activities included in the cost estimate clearly and individually identied? Are indirect, overhead, or other costs clearly and individually identied? Has the cost estimate been updated in a timely manner in response to relevant changes in its basis, background data, or assumptions? Are an appropriate change control document and an estimate development history attached to the cost estimate? Does the estimate development history include an itemized and chronological list of the changes made to the cost estimate since initiation of its preparation, and the rationale for each change? Are activities, quantities, and unit costs associated with the work to be performed clearly identied and dened in the cost estimate? Are the assumptions and exclusions upon which the cost estimate is based clearly identied and dened in the estimate? Are time and cost assumptions and cost elements associated with each activity clearly identied, dened, and documented in the estimate? Cost elements for program activities include: Quantities Unit of measure Material cost Overhead rate Total overhead allocated
Are signicant estimator ndings identied during preparation of the estimate documented? Have factors been used to adjust the costs? If so, have they been adequately documented and appropriately applied? Have escalation factors been used to escalate the estimate? Are the escalation factors adequately documented and appropriately applied? Are indirect rates used in the estimate adequately documented and appropriately applied? Are estimate summary and detailed reports included, and do they provide cost totals for each cost element in the estimate? Is a schedule included with the estimate? Are activities included in the schedule consistent with those included in the technical scope? Are milestones and deliverables included in the schedule consistent with those included in the technical scope documentation and the estimate?
Tips The reviewer must try very hard to eliminate confusion in the contract documents and specifications. Check the estimated cost of any items that represent unfamiliar work or items for which there is only a limited database of historical information. Investigate whether the percentages used to estimate overhead and other costs besides the direct cost are realistic. It is good practice to include younger state highway agency staff as members of the committee so that they can learn from the discussion, but many times they will also contribute a completely new perspective. Resources FHWA (2004). Major Project Program Cost Estimating Guidance. While aimed at estimation for major projects, this document does contain many ideas that can be incorporated into a review process and stresses the need for review teams to have diverse membership composition.
A-100
Why? Every project is executed in the context of a particular political, economic, and cultural environment. The legal system, labor practices, and even the global demand for construction materials are manifestations of a projects macroeconomics. The macroeconomy can affect cost growth in two ways: (1) by being unknown to some degree to estimators and managers and (2) by changes in the environment. Unlike understanding other aspects of project planning and estimation, understanding the macroenvironment has never been standardized as a part of project estimation. What Does It Do? In the case of very large projects, the amount of risk that even the largest contracting organizations can tolerate is exceeded. Therefore, contracting rms must develop strategies to minimize their risks. Some of these strategies involve increased cost to the project owner. In the case of risks that cannot be quantied, that cost increase can be signicant. Additionally, if the contractor perceives that an owner is seeking through the contract language to shift risk to the builder, sufcient additional cost will be included in the bid to cover that added nancial exposure. An off-prism review is conducted from the perspective of how contractors perceive risk and specically considers the construction marketplace and macroeconomic factors impacting contractor risk. When? Because reviews are the best means for ensuring estimate accuracy and for minimizing the potential for unanticipated surprises concerning the nancial condition of the project, it is good practice to perform a review each time an estimate is revised. However, in the case of off-prism evaluations, an estimate review should also occur any time there is a change in macroeconomic conditions or the construction marketplace. When the underlying economic assumptions for the estimate change, the estimate will need to be revisited. Examples The FHWA document Major Project Program Cost Estimating Guidance, June 4, 2004, specically calls attention to the following factors that affect project cost:
Contracting method: Innovative contracting techniques
the project should be considered to determine the most economical and advantageous way of packaging the contracts for advertisement. A value analysis is a systematic approach by a multidisciplined team to identify functions of a project, establish a worth for each function, and generate alternatives that satisfy each function at the lowest life cycle cost. Surety issues: Obtaining bid and performance bonds for major projects is difcult, especially for smaller contractors. If bonding requirements are not reduced, then an increased amount for obtaining bonds should be included in the cost estimate. Bidding climate impact: Estimators should consider the economic impact of the project on the local economy. For example, material manufacturers that would normally compete with one another may need to combine resources in order to meet the demand of the major project. Extremely large construction packages also have the potential to reduce the number of contractors that have the capacity to do the work, and the project may need to be split into smaller contracts to attract additional competition. In addition, the timing of the bid solicitations can also have an affect on the cost because contractors may be more competitive during the winter months when trying to build some inventory. Cost estimates should also consider controls on the use of labor. Industry capacity: The number of potential qualied contractors that are able to bid on major projects are limited to those that have the capacity to construct the project. Contractors that bid on major projects often bid on projects throughout the country. If other major projects are being advertised concurrently, this may have a limiting effect of competition and would result in higher bids. Highly specialized designs and technology: Cost estimates should consider the impact of any requirement to use rstof-a-kind technology, new materials, or innovative construction methods. Construction time: The impacts of construction activities (e.g., sequencing, trafc control, haul routes, accessibility, and geographic locations) should be considered when developing cost estimates. Also, costs associated with work time restrictions and night work must be considered. Construction incentives: The cost for the contractor to meet material and performance incentives must be included in the cost estimate.
such as design-build, cost-plus-time bidding, and lane rental should be taken into consideration when preparing the estimate. Design-build contracts and contracts with performance-based specications or warranties impose a higher risk on the contractor and may increase a contractors bid. Any stipend costs should be included in the estimate.
Tips Bid options (i.e., simultaneous procurements of similar scopes with options to award) should also be considered for potential cost savings resulting from economies of scale and reduced mobilization. A value analysis should be performed
A-101
on the project to determine the most economical and advantageous way of packaging the contracts for advertisement. Some questions that are often decided by contractors but not normally part of a state highway agencys estimation methodology include the following:
Is this a labor-intensive project? Does the project depend heavily on certain pieces of
Check mathematical extensions and correctness. Check takeoff for omissions or oversights. Check for conformity between amounts of work (item
quantities) with the schedule durations to determine correctness. Check the calculations of the indirect costs. Examine the estimate for buried contingency. Compare the estimate with any similar project for an orderof-magnitude check. When?
equipment? Is there a danger of material price increases? What is the cash ow of the project? Resources Arizona DOT (1989). Estimating Guidelines. Schexnayder, Cliff (2001). Construction Forum, Practice Periodical on Structural Design and Construction, ASCE, Vol. 6, No. 1.
Each time a revised estimated is generated, there should be a review. An estimate review is the best means for ensuring accuracy and minimizing the potential for unanticipated surprises concerning the financial condition of the project. Examples North Carolina DOT uses a formal internal estimate review process. The process coincides with the project development process milestones. Following is the approach used by Missouri DOT regarding timing of estimate reviews:
1-02.12 (4) REVIEW OF ESTIMATES. Project cost estimates should be reviewed and updated periodically. At a minimum, project cost estimates should be reviewed on an annual basis. A new or revised project estimate should be prepared at the following major milestones or stages of project development: project initialization, conceptual plan/environmental document completion, preliminary plan completion, right of way plan completion, and contract plans completion (PS&E). The estimated project costs should be submitted to GHQ [General Headquarters] Transportation Planning at least annually, at the above noted project development milestones/stages, or when signicant project scope changes are identied using a PATS [Project Amendment Tracking System] form (see Figure 1-02.7). If an annual review of the previous estimate is conducted and it is determined that no change is necessary, the project estimate le should include documentation to indicate that the previous estimate has been reviewed and remains valid. Revised cost estimates submitted for projects that are scheduled for expenditure of funds within the current scal year of the STIP [statewide transportation improvement plan] will not be reected in the STIP or the approved PATS database. For example, if the project is to be awarded during the current scal year, the construction cost reected in the STIP will not be revised to account for project estimates prepared after the beginning of the scal year. Similarly, if a project has right of way funds included in the current scal year of the STIP, the right of way amount will not be revised based on a revised estimate submitted in the same scal year. Even though these costs will not be reected in the STIP, the revised project estimates should still be prepared in accordance with the recommended schedule. However, the submission of a
E3.3 In-House/Peer
An objective estimate review can be accomplished by a group of experienced third-party state highway agency individuals who did not participate in development of the estimate. For large or complex projects, the review is usually conducted with the project team and estimator so that the reviewers can better understand the execution plan, estimate basis, and project challenges in regards to scope and pricing. What Is It? A peer review typically involves an estimate validation by state highway agency estimator who has not worked on the estimate being reviewed. The state highway agency reviewer must have the experience and knowledge to carefully appraise the materials presented. In the case of larger projects, this peer validation may involve a peer team. Why? The foundation of a good estimate is the formats, procedures, and processes used to arrive at the cost. Poor estimation includes general errors and omissions from plans and quantities and general estimation procedure and technique inadequacies. It is easy for members of the state highway agency to conduct an estimate review because they are familiar with the formats, procedures, and processes that the agency has in place and therefore can easily spot deciencies. What Does It Do? A peer review checks the estimate for completeness and correctness, including, but not limited to, the following:
A-102
PATS form to GHQ Transportation Planning will not be required in this situation. This is the only exception that exists for not submitting a PATS form to GHQ Transportation Planning each time a revised estimate is prepared. All estimated costs should be submitted in current dollars. GHQ Transportation Planning will make any necessary ination adjustments. Estimate revisions will impact a districts funding balance and be used to calculate the current cost of the program, but not be used to determine any changes in the district funding distribution.
body of knowledge and experience to the review to engage in a dialogue. What Is It? A round-table estimate review is like the process used by contractors to validate their cost estimates before a bid letting. The project team assembles and has a detailed discussion of the schedule, conditions, and expected construction methods for the major cost items, as well as all known site conditions. Only after that discussion does the actual review of total cost and item cost begin. The cost review is top down by broad classes: direct cost total and major items, state highway agency eld support cost, state highway agency administrative support cost, and included contingency. Why? All project estimates are very complex in terms of the factors that can determine work item costs, and estimators must make numerous judgments based on perceptions of work conditions and the physical conditions at the project site as the estimate is developed. Therefore, it is good practice to capture a different perspective from agency experts in order to validate the estimators assessment. What Does It Do? Using a committee to review an estimate brings knowledge from agency experts with a broad base of experience. The reviewers who compose the committee should represent diverse sections of the agency having specic knowledge of costimpacting factorsfor example, personnel from the agencys right-of-way section for reviews during planning and design development and personnel from the construction ofce for a review of PS&E. When? Periodic reviews of estimates are important because conditions and underlying assumptions for the original and subsequent estimates often change; thus, estimates need to be revised to account for these changes. When estimates are revised, there should be a review because reviews are the best means for ensuring accuracy and minimizing the potential for unanticipated surprises concerning the nancial condition of the project. Examples North Carolina DOT uses a formal internal estimate review process. The process coincides with the project development process milestones.
the estimate?
Are the assumptions made in the estimate consistent with
the technical scope and schedule of the project? Are the activity durations in the schedule consistent with the estimated cost? Are indirect rates, escalation factors, and other factors used appropriately? Have the ndings and recommendations of the peer review been documented in a peer review document? Is the peer review document included with the cost estimate documentation? Have the ndings and recommendations of the peer review been addressed in revisions to the cost estimate? Are activities included in the schedule consistent with those included in the technical scope documentation and estimate?
Resources Opfer, Neil D. (Fall 1997). Construction Peer Review: A Technique for Improving Construction Practice, Journal of Construction Education, Vol. 2, No. 3, pp. 211221. While this article discusses a peer review of contractor organizations, it includes several important peer review fundamentals. One of these is the point that the techniques success depends on signicant resource commitments, including time. Missouri DOT (2004). Chapter 1, General Information: Needs Identication Project Scoping and STIP Commitments, Section 1-02, Project Development Manual. www. modot.org/business/manuals/projectdevelopment.htm.
A-103
Resources U.S. Department of Energy (1997), Check Estimates and Independent Cost Estimates. www.directives.doe.gov/pdfs/ doe/doetext/neword/430/g4301-1chp13.pdf. FHWA (2004). Major Project Program Cost Estimating Guidance. While this document is aimed at the estimation for major projects, this document contains many ideas that can be incorporated into a review process and stresses the need for review teams to have diverse membership composition.
with associated cost impacts because of late delivery or because there was no compensating incentive to deliver the project on time or ahead of schedule? Constructability: Is a unique design creating some unknown factors that could impact the cost of the project? Are specialized or large machines needed to construct the project? Government oversight: Do the various government entities involved and the political sensitivity raise concerns as to who is ultimately accountable and empowered to make quick decisions? (Delays in decision making by an owner causes a contractor to incur uncompensated additional costs.) Other major projects: Are there other projects that may interfere with the contractors ability to estimate this project? (Even major contractors have limited estimation capability; to estimate more than one large project during the same time frame is often impossible.) Tips An estimate review does not dig into every detail of the estimate, but it should always test the vital few items and assumptions. The Italian economist Vilfredo Pareto observed that 20% of something is always responsible for 80% of the results. That observation is recognized today as a universal principle called the 80/20 rule, or Pareto principle. The Pareto principle should guide the estimate review. Applying the rule allows the reviewers to set priorities. After a general overview analysis of the estimate, the reviewers should concentrate on the items that are the projects primary cost drivers. The reviewers should carefully examine the selected items based on a list of important issues:
Correctness of quantities Appropriateness of unit cost Validity of assumed construction method, considering site
cost (this is critically important in the cast of large, complex projects) Unforeseen engineering complexities Changes in economic and market conditions Changes in regulatory requirements Pressures by local government or other stakeholders Transformation of community expectations Market availability of materials and/or equipment Concise explanation of how contingency amounts were developed Construction schedule
There should be comparisons of costs to benchmark ratios and factors for similar projects.
A-104
idea to communicate the estimate to external parties in anything except year-of-construction costs. What Does It Do? This tool provides an internal estimate review milestone for the estimation team. It is one of the nal steps before the estimate is communicated to the project team members and to external stakeholders. This tool improves estimate accuracy by identifying the effect of ination on project cost. It denes an estimated project cost, which is developed in current dollars, in terms of the expected cost at the time of construction. When? Year-of-construction cost recognizes the cost escalation affect of ination across the time period between when the estimate is made and when the project is constructed. Estimates should be communicated in year-of-construction costs from the earliest points in the project development process. This is very important for projects having long development and/or construction periods. Examples Florida, Minnesota, and Washington State DOTs have developed tools for calculating year-of-construction costs. Refer to Section C1.7 for specic examples. Most other state highway agencies have developed tools similar to those used in Florida, Minnesota, and Washington State. Tips Include a formal step in the estimate review process to ensure that the estimate is being communicated in year-ofconstruction costs. Use discipline in communicating year-ofconstruction costs at each phase of the project development. Resources Florida DOTs Long Term Construction Cost Ination Forecast can be found at www.dot.state..us/planning/policy/ costs/ination.pdf. Minnesota DOTs Ten Year Highway Work Plan: 2004 2013 can be fount at www.oim.dot.state.mn.us/pdpa/200413_10-YrHwyWorkPl.pdf. Washington State DOTs Strategic Planning and Programming website is http://www.wsdot.wa.gov/planning.
Checklists and cost containment tables are two tools that can be used in support of the gated process method of cost estimation management.
G1.1 Checklist
A checklist is a tool commonly used by estimators to begin an estimate or ensure that an estimate adequately addresses project scope. Checklists are valuable tools when creating conceptual project estimates when little or no engineering information is available. Checklists are also valuable quality control tools when completing estimates at any phase of project development. Checklists can be used in conjunction with gated processes to ensure that all relevant items of scope are estimated before a project moves onto the next phase of project development. What Is It? A checklist is a form that indicates the completion or incompletion of specied project milestones. Checklists are typically developed through experience with many estimates. Checklists often address items that are commonly overlooked or have high cost value. Checklists can be used in a gated process to ensure that a project will not move to the next stage of project development without the completion of critical estimation milestones. Why? In order for a project to progress smoothly, critical cost estimation items must be completed or accounted for before another phase may begin. The checklist is a simple tool for identifying the level of progress that has or has not been made on the project. Checklists help to ensure that major scope items are not forgotten as a project moves through the development process. What Does It Do? A checklist can assist estimators in ensuring that an estimate is complete. A checklist can serve as a simple Go or No-Go signal for moving a project to the next phase of development. After each phase or activity is completed, the item will be checked off of the checklist, and the next set of responsibilities will be addressed. Checklists can also be used to help set reasonable contingencies because they can give some indication about the unknowns in a project. When? Checklists can be used on every project. The checklist can be developed during the programming and planning phases. The checklist can be used from the planning phase through
G1 Gated Process
A gated process creates a formal mechanism to stop the project development process if a projects cost escalates beyond an acceptable limit during the project development process.
A-105
the completion of the project. It is often valuable to develop checklists that correspond to major milestones in project development (see Cost Containment Table tools). Examples Mississippi DOT uses a comprehensive checklist to aid with project development. Although this example does not contain specic estimation milestones, it serves as a good basic example of a checklist. A few select portions of this checklist are seen in Figure G1.1, and a full version can be found in the resources section. Tips Checklists are simple tools for managing a current project, as well as reviewing completed projects. Add extra notes and lessons learned to the checklist as the project progresses to be used for referencing in the future. Checklists are generally set up to allow a logical progression of activities. However, it is often possible to overlap phases and activities for increased budgeting and scheduling efciency. Resources FHWAs Construction Program Management and Inspection Guide, Checklist for review of estimate is available at www.fhwa.dot.gov/construction/cpmi04ge.htm. FHWAs Plan, Specications, and Estimates Checklist is available at www.fhwa.dot.gov/construction/cpmi04gi.htm. Illinois DOTs Checklist for Engineers Final Payment Estimate is available at www.dot.state.il.us/Forms/bc111.dot. Michigan DOTs Memo for Final Estimates is available at www.michigan.gov/documents/IM00-20_ 40872_ 7.pdf. Mississippi DOTs Project Development Checklist is available at www.mdot.state.ms.us/localgov/planning/pdm/ checklist.pdf.
project costs and alerting team members when corrective action must be taken because of changes impacting project scope, cost, and schedule. Why? Under a gated process method, a cost containment table can be used as a checkpoint at the completion of each milestone to ensure that sufcient budget, schedule, or project goals have been met. The project can proceed toward the next milestone given a satisfactory completion of the prerequisite activities per the cost containment table. What Does It Do? The cost containment table is a tool for cost estimation management that is used to ensure that the project is within budget. It can also be used to verify that the scope of work is in alignment with what was dened during programming and planning. When? Develop a cost containment table, along with feasibility studies, early in the project development process. Use the cost containment table throughout all phases of the project. Examples Please refer to the example of a cost containment table from Pennsylvania DOT in Section C6.1 and Figure C6.1. This table can be used as a tracking and communication mechanism in a gated process. Because management must approve the cost containment table before the project moves to the next phase of project development in the Pennsylvania DOT example, the DOT has essentially created a gated process. The strength of the gated process will depend on the policies, procedures, and management discipline involved. Tips Begin to use the cost containment table early in the project development process. Update the table at all project milestones. Be proactive in the use of cost containment tables for establishing gated processes. Resources Pennsylvania DOTs Estimating Manual is available at ftp:// ftp.dot.state.pa.us/public/Bureaus/design/PUB352/inside_ cover_page.pdf. The FHWA uses lessons learned from past projects to comment on the importance of cost containment. The following link references the Boston Central Artery/Tunnel: www.fhwa. dot.gov/programadmin/mega/lessons.htm.
A-106
A-107
I1 Identification of Changes
The identication method is normally positioned in the nal stages of engineering to intercept inputs impacting scope and cost. The four tools used in this methodI1.1, Cost Containment Table; I1.2, Estimation Scorecard; I1.3, Project Baseline; and I1.4, Scope Changewill have been established much earlier in the project development process, but will be used late in the engineering process to identify any deviations from the project baseline estimate. The scope and cost baseline of every project should be the reference to which all
changes are compared. Throughout project development and construction, the baselines are used to evaluate performance. Most agencies that practice baselining of their projects report doing so usually at the point when an identied need becomes a real project and is budgeted.
A-108
The cost containment tool is used in the identication method to quickly call attention to any deviations in budget. Managing to a baseline cost estimate is one of the most common measures of estimation management success. As a project moves forward through its development stages, cost containment tables provide a benchmark against the project baseline. They create a standard tool that can be used by team members to track cost growth and provide immediate feedback for executive management. What Is It? A cost containment table is an estimate reporting system that requires project team members to document summarylevel estimates at critical points in the project development process. It provides executive management with estimate totals as the project moves through critical milestones during its development. These milestones will vary from state highway agency to state highway agency, but they can include scoping, programmed amount, preliminary engineering, nal engineering, award, and closeout. They can also include estimate subtotals for items like engineering, right-of-way, and construction. Why? Cost containment tables provide a simple and concise tool for managers and project team members to monitor and react to cost escalation as projects transition through critical phases during their development. In the context of the identication method, cost containment tools identify changes to the budget and provide information for helping the designers and estimator get the project back on budget. What Does It Do? Cost containment tables create transparency and accountability in the management of a cost baseline. The use of cost containment tables permits quick identication of cost escalation as it occurs. When standardized in a state highway agency, cost containment tables allow for comparison of cost escalation by the variables captured in the tables. The use of the cost containment table establishes minimal milestones that are consistent throughout the state highway agency and creates accountability for the project team for changes in the estimates from one milestone to the next. When? The effort to manage project costs continues from the programming and preliminary design stage through nal design, and until construction closeout. In the identication method,
the tool will be used during the nal design and letting to ensure that cost escalation has been captured. For instance, if the price of a commodity such as steel or cement escalates rapidly during nal design, the engineers estimate will reect the escalation and the cost containment table tool will alert the project team to the fact that the project scope may need to be adjusted to t within a constrained budget. The table acts as a gated process to stop the project from progressing until it is estimated to be on budget. The cost containment table should only be used when a project baseline estimate is established. Example An excellent example of a cost containment table from the Pennsylvania DOT is described in Section C6.1 and shown in Figure C6.1. Tips A cost containment table requires updating at each predetermined project milestone. At each project milestone when the table is used, the estimate must be broken down into specied items. If substantial changes are present, they can then be easily identified, thereby indicating a need for further review. Cost containment tables should be only one tool in managing cost escalation. A drawback of the cost containment table is that it only provides a rearview mirror look at cost escalation. While knowing that there is a problem at critical project milestones is essential, project teams should strive to anticipate cost escalation whenever possible and mitigate their effects before they occur. Resources Pennsylvania DOTs Estimating Manual is available at ftp:// ftp.dot.state.pa.us/public/Bureaus/design/PUB352/inside_ cover_page.pdf.
A-109
What Is It? An estimation scorecard is an evaluation tool to measure the success of cost estimation practice and cost estimation management during the project development processes. The format of the scorecards can vary depending upon individual agency objectives, but the goal is to create an objective score for performance in cost estimation practice and/or cost estimation management. Why? Measurement of estimate performance is critical to improve future estimation practices. Early identication and measurement of the project success criteria helps to ensure that there is no miscommunication regarding functionality and physical structure of the completed project. What Does It Do? Estimation scorecards provide objective measures of estimate success. Estimation scorecards are commonly used when consultants are preparing the project design and estimate, but they can also be used internally for agency evaluations. Estimation scorecards indicate the measures that will be used at project completion to evaluate success. Once the project is complete, performance measure can be derived from comparison of target values designated during project development and the achieved values measured after project completion. When? The evaluation criteria of estimate success and the physical scorecard itself should be developed early in the project development process. It is then used in the identication method in the later stages of project development to determine estimate success and to help collect lessons learned for future estimates. Examples Section C6.2 provides examples from a scorecard developed by the Coors brewing company for construction of their capital facilities. Tips The use of the scorecards can ensure that all team members are clear about the expectations for a successful project. The tool will help to facilitate a structured discussion about what will dene success on each project, and it will provide an objective measurement for this success.
Develop the scorecard as a team. Consider developing an overall project scorecard as well as discipline-specific scorecards. Resources U.S. Department of the Interiors The Quarterly Scorecard and Corrective Actions Reports for Constructed Asset Investments is available at www.doi.gov/pam/QuarterlyReport Guidance61605.pdf.
A-110
programming and the beginning of preliminary engineering. Controlling the project baseline is absolutely essential for project success. Other than misunderstood requirements, poor cost and schedule estimates, and technical difculties, the issues that will most likely imperil a project are unexpected changes.
Project Denition An electronic document that records the purpose and need of the project, along with program level and design constraints.
When? The project baseline tool is used when the project is authorized for inclusion into the state highway agency program for design and construction letting. This occurs at the end of programming. However, the extent of the design effort to support the creation of a project baseline may vary depending on project size and complexity. Some preservation projects, such as an overlay, can be dened with only as much as 10% design completion. This may be adequate to set the baseline cost. Other larger and more complex projects may require as much as 25% design completion before setting the baseline cost. Examples The Washington State DOT (WSDOT) has a scoping phase that starts its project development process. The scoping phase is described as follows in WSDOTs 2006 Design Manual:
Scoping phase The rst phase of project development for a specic project. It follows identication of the need for a project and precedes detailed project design. It is the process of identifying the work to be done and developing a cost estimate for completing the design and construction. The Project Summary, engineering and construction estimates, and several technical reports (geotechnical, surfacing, bridge condition, etc.) are developed during this phase.
The Project Definition component includes the cost estimate for preliminary engineering, right-of-way (if part of the project scope) and construction. The Project Summary document is reviewed and approved by WSDOT region management and headquarters prior to including the project in the biennial program. Tips The project baseline cost estimate has to be at a certain level of detail to be meaningful for controlling costs. That is, cost elements must be dened sufciently, with the estimate basis, assumptions, and calculations clearly documented (see the Project Estimation File tool). The project baseline should be established as early as possible in the project development process, but not before sufcient level of detail is available to allow for tracking changes to project scope and cost. Resources Washington State DOT (2005). Design Manual, Section 330, Design Documentation, Approval, and Process Review. Chapman, James (2005). Principle Based Project Management, Rule Number 6, Establish Baseline Controls. www. hyperthot.com/project.htm.
This scoping phase provides sufcient project design to prepare a baseline scope, cost, and schedule. This baseline supports the biennial programming of projects. The scoping phase has specic documentation that is required to support the project. This documentation, referred to as a Project Summary, contains three main components, as described in WSDOTs Design Manual:
Design Decisions Summary An electronic document that records major design decisions regarding roadway geometrics, roadway and roadside features, and other issues that inuence the project scope and budget. Environmental Review Summary An electronic document that records the environmental requirements and considerations for a specic project.
A-111
of any scope change serves to limit change, as all such proposals must be carefully reviewed. Controlling scope change serves to control cost growth. An additional reason for tracking changes to the project is to ensure that no changes take place without the full knowledge of the project team, including designers, managers, and estimators. What Does It Do? Scope change forms make possible easy comparison of the current project scope, schedule, and cost with the established baseline of the project. The form should require that the documented change, as well as any impacts of the change to project scope, schedule, and cost, be specically acknowledged. An explanation is required with each change. Appropriate approvals should be required depending on the size and nature of changes. When? The scope change form should be used for all changes after the project baseline is established and may even be used before the baseline is established. It should continue to be used in the identication method during the latter stages of project development. As projects progress toward nal design, management approval of scope changes is more critical and the scope change form provides an excellent tool to ensure that the approval is obtained and tracked. Examples An excellent example of a scope change form is discussed in Section C6.3 and shown in Figure C6.3. A form used by Missouri DOT is provided with instructions on how to complete it. Additional examples from the California DOT and the New York State DOT can be found through the web links in the resources part of this tool description. Tips Scope change forms should explicitly require all the information needed to track project changes, including scope, schedule, and cost impacts, as well as explanations and approvals. Forms should be standard; however, there should be the ability to deviate from the form for special project circumstances. Resources California DOTs Project Development Procedures Manual (PDPM) Chapter 6 addresses project cost, scope, and schedule changes: dot.ca.gov/hq/oppd/pdpm/chap_htm/chapt06/ chapt06.htm.
Chapters 2 and 3 in the New York State DOTs Project Development Manual (PDM) discusses changes in project cost, scope, and schedule: www.dot.state.ny.us/cmb/consult/dpm1/ pdm_01_30_04.html.
Risk identication Risk analysis (qualitative and/or quantitative) Risk mitigation planning Risk monitoring and control
Red ag items and risk charters are two tools that assist estimators in both identifying and monitoring risks throughout the project development process. These tools support risk identication early in the project development process to assist in setting appropriate project contingencies. The tools also support the risk monitoring and control process to assist in contingency resolution as the project scope, design, and project delivery methods become fully dened.
A-112
Why? By listing items that can potentially impact a projects cost or schedule, and by keeping the list current, the project team has a better perspective for setting proper contingencies and controlling cost escalation. Occasionally, items that are considered a risk are mentioned in planning but soon forgotten. The red ag item list facilitates communication between estimators and designers concerning these impacting items. By maintaining a running list, these items will not disappear from consideration and then later cause problems. What Does It Do? At the earliest stages of project development, an agency develops a list of impacting items, based primarily on engineering judgment or historical records of problems. The red agging of these items may not involve any formal qualitative or quantitative risk analysis of the factors, but it keeps the team mindful of their existence. The list also helps the team to remove contingency from the project cost estimate as the design progresses and risk issues are resolved. When? The composition of a red ag item list is done in the earliest stages of project development. The list should then be updated at each major milestone or as new items are identied. The list will be most useful if it is maintained and updated throughout the project development process. Examples California DOT has developed a sample list of risk in its Project Risk Management Handbook. The list is provided in Tables I2.1-1 through I2.1-4. This sample list of risks can be used as the basis for creating a list of red ag items for an individual project. The Caltrans list is quite comprehensive, and
any single projects list of red ag items should not include all of these elements. Washington State DOT also uses a Sample Risk Elements checklist for its cost risk assessment process. Sections I2.2 and R3.5 provide tools to help lter (qualitatively or quantitatively) the risks for each project to ensure that only the most critical risks in terms of cost impacts are being considered. Tips The list of red ag items should be developed in an interdisciplinary team environment. This activity works well during the scoping process. Consider brainstorming sessions with representatives from multiple discipline areas for creation of a list of red ag items. In addition to scoping documents or lists of standard items like that in Tables I2.1-1 through I2.1-4, individuals should use their own knowledge of the project and consult with others who have signicant knowledge of the project or its environment. Resources Caltrans Ofce of Project Management Process Improvement (2003). Project Risk Management Handbook. Curran, Michael W. (1998). Professional Practice Guide #2: Risk. Association for the Advancement of Cost Engineering International. FHWA (2004). Major Project Program Cost Estimating Guidance. Grey, S. (1995). Practical Risk Assessment for Project Managers. John Wiley and Sons, Chichester, England. Molenaar, K. R. (2005). Programmatic Cost Risk Analysis for Highway Mega-Projects, Journal of Construction Engineering and Management, Vol. 131, No. 3. NCHRP (2005). NCHRP Project 20-7/172 Final Report, Recommended AASHTO Design-Build Procurement Guide, Washington, D.C.
Technical Risks
Design incomplete Right of Way analysis in error Environmental analysis incomplete or in error Unexpected geotechnical issues Change requests because of errors Inaccurate assumptions on technical issues in planning stage Surveys late and/or surveys in error Materials/geotechnical/foundation in error Structural designs incomplete or in error Hazardous waste site analysis incomplete or in error Need for design exceptions Consultant design not up to Department standards Context sensitive solutions Fact sheet requirements (exceptions to standards)
A-113 Table I2.1-2. Caltrans sample external and environmental risk list.
Risk Category Individual Risks
External Risks
Landowners unwilling to sell Priorities change on existing program Inconsistent cost, time, scope, and quality objectives Local communities pose objections Funding changes for fiscal year Political factors change Stakeholders request late changes New stakeholders emerge and demand new work Influential stakeholders request additional needs to serve their own commercial purposes Threat of lawsuits Stakeholders choose time and/or cost over quality Permits or agency actions delayed or take longer than expected New information required for permits Environmental regulations change Water quality regulation changes Reviewing agency requires higher-level review than assumed Lack of specialized staff (biology, anthropology, archeology, etc.) Historic site, endangered species, wetlands present EIS required Controversy on environmental grounds expected Environmental analysis on new alignments is required Formal NEPA/404 consultation is required Formal Section 7 consultation is required Section 106 issues expected Project in an area of high sensitivity for paleontology Section 4(f) resources affected Project in the Coastal Zone Project on a Scenic Highway Project near a Wild and Scenic River Project in a floodplain or a regulatory floodway Project does not conform to the state implementation plan for air quality at the program and plan level Water quality issues Negative community impacts expected Hazardous waste preliminary site investigation required Growth inducement issues Cumulative impact issues Pressure to compress the environmental schedule
Environmental Risks
Project Management Institute (2004). A Guide to Project Management Body of Knowledge (PMBOK Guide). Washington State DOT (2006). Cost Estimating Validation Process (CEVP) website: www.wsdot.wa.gov/Projects/ ProjectMgmt/RiskAssessment.
tude of potential cost and schedule risk impacts as the project progresses through the development process and the risks are resolved. What Is It? A risk charter is a document containing the results of a qualitative or quantitative risk analysis. It is similar to a list of red ag items (see Section I2.1), but typically contains more detailed information concerning the potential impact of the risks and the mitigation planning. The risk charter contains a list of identied risks, including description, category, and cause. It may contain measurements of magnitude such as the probability and impact of occurrence. It may also contain proposed mitigation responses, owners of the risk, and current status. This method may be more effective than simply listing the potential problem areas, as with the red agging, since it is
A-114 Table I2.1-3. Caltrans sample organizational and project management risk list.
Risk Category Individual Risks
Organizational Risks
Inexperienced staff assigned Losing critical staff at crucial point of the project Insufficient time to plan Unanticipated project manger workload Internal red tape causes delay getting approvals, decisions Functional units not available, overloaded Lack of understanding of complex internal funding procedures Not enough time to plan Priorities change on existing program New priority project inserted into program Inconsistent cost, time, scope and quality objectives Project purpose and need is poorly defined Project scope definition is poor or incomplete Project scope, schedule, objectives, cost, and deliverables are not clearly defined or understood No control over staff priorities Too many projects Consultant or contractor delays Estimating and/or scheduling errors Unplanned work that must be accommodated Communication breakdown with project team Pressure to deliver project on an accelerated schedule Lack of coordination/communication Lack of upper management support Change in key staffing throughout the project Inexperienced workforce/inadequate staff/resource availability Local agency issues Public awareness/support Agreements
Table I2.1-4. Caltrans sample right of way, construction, and regulatory risk list.
Risk Category Individual Risks
Utility relocation may not happen in time Freeway agreements Railroad involvement Objections to Right of Way appraisal take more time and/or money Inaccurate contract time estimates Permit work windows Utility Surveys Buried man-made objects/unidentified hazardous waste Water quality regulations change New permits or new information required Reviewing agency requires higher-level review than assumed
Construction Risks
Regulatory Risks
A-115
integrated into the risk monitoring and control processes. The terms risk charter and risk register are synonymous in the industry. Why? A risk charter is used to identify, communicate, monitor, and control risks. It provides assistance in setting appropriate contingencies and managing the cost estimation process. As part of a comprehensive risk management plan, the risk charter can help to control cost escalation. It is appropriate for large or complex projects that have signicant uncertainty. What Does It Do? The charter organizes risks that can impact project cost and project delivery. A risk charter is typically based on either a qualitative or quantitative assessment of risk, rather than simple engineering judgment. The identied risks are listed with relevant information for quantifying, controlling, and monitoring. The risk charter may include relevant information, such as the following:
charter will be helpful in a risk identication capacity. As the project progresses, more rigorous and quantitative risk management can be done and the charter will become an even more valuable tool for cost estimation management and risk monitoring and control. Examples Washington State DOT has built a Cost Estimating Validation Process (CEVP). The CEVP uses a risk charter (or risk register) as a fundamental tool in its comprehensive validation process. The CEVP is explained in more detail in Sections C1.2 and R3.5. Figures I2.2-1 and I2.2-2 show two aspects of the CEVP that are relevant to describing a risk charter. Figure I2.2-1 provides a summary example from a risk identication exercise that is part of the CEVP. Figure I2.2-2 provides a summary of risk descriptions in the risk charter for the CEVP analyses. For more information on these rst nine projects, see K. R. Molenaars 2005 article, Programmatic Cost Risk Analysis for Highway Mega-Projects, in ASCE Journal of Construction Engineering and Management, Vol. 131, No. 3, pp. 343353. For more information on the current CEVP, see the Washington State DOTs 2006 CEVP website at www.wsdot.wa.gov/ Projects/ProjectMgmt/RiskAssessment. Tips The risk charter should be developed in conjunction with a comprehensive risk management plan. It should be developed in an interdisciplinary team environment and may require external facilitation. Resources Caltrans Ofce of Project Management Process Improvement (2003). Project Risk Management Handbook.
Risk description Status Date identied Project phase Functional assignment Risk trigger Probability of occurrence (%) Impact ($ or days) Response actions Responsibility (task manager)
When? This technique can be used throughout project development. At the earliest stages of project development, the risk
Risk Issue: Commercial Property Value Issue: Project ROW costs were developed by applying a percentage increase to the assessed valuations for each parcel. During the CEVP review the estimated cost of commercial properties carried in the ROW estimate for the project have been updated, and the multiplier increased to 75% of the assessed value, to better reflect current market conditions. There is a low level of confidence in the updated values and it is estimated that actual market conditions may be as high as 100% of the assessed valuations. Impacts: The actual market conditions will increase the cost of acquiring commercial properties by an average of $25M. There are no significant schedule impacts. Probability: 85%. Mitigation: Monitor the commercial real estate market and track the actual cost of recent transactions. Keep the project ROW estimate up to date and reflective of the current commercial property real estate market. Buy early if appropriate.
Figure I2.2-1. Summary example of risk event identication exercise that is part of WSDOTs CEVP.
A-116
Market Conditions Implementing several mega-projects at the same time may create a shortage in management, contractors, financing/funding, labor, and material. Labor Disruptions Labor shutdowns are likely. Storm Water Treatment and/or Quantities Stricter requirements in the future would require additional cost to provide additional detention ponds, the collecting and treatment of all runoff, which may have a base amount in the estimate but there may be higher amounts of treatment required or higher then expected volumes. Changes in Permitting Permit requirements may change over the long duration of some projects. Off and On Site Wetlands There is a chance that conditions actually encountered in the field may be different than assumed when the base estimate was compiled and the measures used my also change requiring additional mitigation. Environmental Impact Statement Disagreement between WSDOT and resource agencies and/or among agencies and the public on project impacts and associated disagreement on mitigation approaches may prompt impacts. NEPA/404 Merger Pro cess Failure to reach concurrence on the range of alternatives and a preferred alternative could delay the environmental process. Utility Issues Routine investigations and coordination with utility companies can identify and relocate conflicting utilities throughout the project. However, unforeseen discovery of previously unknown utilities, and the need to relocate these utilities after the job is awarded and construction has started can be a significant cost and schedule liability to the project. Utilities, adjacent landowners, and other affected parties may demand betterment or excessive mitigation. Rail Lines (Regular and Light) Regional and national offices may need to approve new railroad alignments and ROW or the encroachment of new highway alignment on existing rail ROW.
Figure I2.2-2. Summary risk charter risk descriptions from the WSDOT CEVP analyses.
Curran, Michael W. (1998). Professional Practice Guide #2: Risk. Association for the Advancement of Cost Engineering International. FHWA (2004). Major Project Program Cost Estimating Guidance. Grey, S. (1995). Practical Risk Assessment for Project Managers. John Wiley and Sons, Chichester, England. Molenaar, K. R. (2005). Programmatic Cost Risk Analysis for Highway Mega-Projects, Journal of Construction Engineering and Management, Vol. 131, No. 3. NCHRP (2005). NCHRP Project 20-7/172 Final Report: Recommended AASHTO Design-Build Procurement Guide. Project Management Institute (2004). A Guide to Project Management Body of Knowledge (PMBOK Guide). Washington State DOT (2006). Cost Estimating Validation Process (CEVP) website: www.wsdot.wa.gov/Projects/ ProjectMgmt/RiskAssessment.
A-117
Right of Way Acquisition Problems Changing property values, revolving funds, etc. may cause problems along with property owners who may hold out and cause economic problems and/or delays. Right of Way Value and Impact Several risks may be encountered such as property owner relocation, sudden growth, and area development, which may cause monetary and time impacts. Program Management The organizational make-up of WSDOT is being revised to accommodate mega-projects. This management structure will need constant care and feeding to ensure that decisions and information are growing in a responsible way. Geotechnical Conditions Inadequate geotechnical investigations during the conceptual and alignment selection phases can cause unforeseen conditions during excavation and construction of tunnels, bridges, walls, etc. This could be compounded by inadequate characterization of groundwater conditions. Design Change in Seismic Criteria The Am erican Association of State Highway Transportation Officials (AASHTO) is developing new seismic design criteria for bridges. The timing of the release of this criteria and WSDOTs adoption of the criteria is uncertain. Bridge Foundations The foundation type for bridges in the project may need to be adapted to new information that becomes available as the project progresses. Local Arterial Improvements and Access Local agencies may demand additional improvements to local arterials as a condition for support of the project. Inadequate Design/Design Uncertainty for Interchanges Interchanges may be planned but there may be some uncertainty from the design (i.e. unit cost, inadequate design, deviation approval, municipality involvement, etc.) Traffic Demand Traffic demands may not be accurate in some areas (i.e. inconsistent growth patterns, age of traffic projections). Contaminated Soil It is possible that even after thorough due diligence and the identification of contaminated sources during design of the project, new contaminated soils or groundwater may result in discovery of new or unknown conditions that need to be taken care of during construction. Natural Hazards Storms, floods, earthquakes, etc. can cause damage to work under construction and may result in shut down during construction. Such conditions damage the temporary water pollution controls, temporary structures, and earthwork, which must then be repaired. Work Win dow There may be restrictions in conducting some activities (i.e. earthwork) during some parts of the year (i.e. winter). Auxiliary Lanes There may be uncertainty regarding if auxiliary lanes are going to be used/constructed temporarily during construction and/or permanently. Staging Areas Due to limitations in ROW and traffic flow staging areas may be inadequate for construction.
A-118
tify potential project scope issues related to ensuring that an appropriate cost is included in the project estimate to cover environmental mitigation. What Is It? An environmental assessment is a concise public document that a state agency prepares under the National Environmental Policy Act (NEPA) to provide sufcient evidence and analysis to determine whether a proposed agency action would require preparation of an environmental impact statement (EIS) or a nding of no signicant impact (FONSI). NEPA was signed into law on January 1, 1970. The act establishes national environmental policy and goals for the protection, maintenance, and enhancement of the environment, and it provides a process for implementing these goals within the federal and state agencies. Many times, environmental issues driven by parties external to a project can cause additions to project scope that signicantly affect project cost. This tool seeks to direct state highway agency attention to exploring these possibilities during project development in a proactive instead of reactive manner. Why? A study made by the U.S. General Accounting Ofce identied expedition of the authorizations from environmental and resource agencies as one of the most promising approaches for reducing the time it takes to plan, design, gain approval for, and build a federally funded highway project. For works in which the environmental impact is considerable, mitigation measures may pose a signicant cost. Failing to consider these regulations may jeopardize not only the original budget, but also the whole project. What Does It Do? An environmental impact assessment (EIA) is a sound precaution and a proactive measure. Increasingly, successful project development is viewed in terms of its nal resultits operational environmental performance, its acceptance by stakeholders, its contribution to sustainable development, and, critically, the scale or magnitude of environmental impact over all life cycle phases. For astute proponents, the evidence suggests that EIA followup has a valuable role to play in good project development practice. When? Environmental considerations are evaluated from the inception of a project and are constantly reviewed during all phases of project development. However, the impact of environmental regulations on a project is most critical during the pro-
gramming and early in the preliminary engineering. The NEPA process must be completed, and all potential impacts considered, prior to full design of the project. This may require that several alternatives be investigated and related costs compared in terms of potential mitigation solutions to address environmental issues. Examples The FHWA document, Major Project Program Cost Estimating Guidance, June 4, 2004, specically calls attention to environmental work that affects project cost:
Environmental Work: Although the intent of a project may be to avoid environmentally sensitive resources, some degree of environmental consideration and analysis is required for all major projects. If work associated with the alternative in the NEPA document is not included as part of the cost estimate, the NEPA document should note where the cost for the outstanding cost element could be found. For example, this could be short-term improvements that are already included in the Statewide Transportation Improvement Program (STIP). Any additional environmental avoidance, minimization, mitigation, remediation, and enhancement costs must also be included in the cost estimate. Costs to mitigate impacts to natural resources, cultural resources, neighborhoods, and so on, must either be individually estimated or included in a contingency amount. Although large contingencies may be appropriate if no resource surveys have been conducted, resource surveys conducted as part of the NEPA process provide valuable information for rening cost estimates. Additionally, some major projects may have enhancement work that is not directly related to the project. This may include other transportation modes and nontransportation related work. These costs must be captured and included in the cost estimate. A major project that has a potentially significant effect or impacts on environmental resources or has opposition from environmental or community groups or regulatory agencies, tends to include more environmental mitigation which results in higher costs than those projects with relatively little impact or oppositions. Moreover, contingencies should be included for projects that include Intelligent Transportation System attributes, as well as in those States that are implementing Context Sensitive Strategies/Context Sensitive Design since very little historical data exists or is included in previous cost gures.
Tips Federal, state, tribal, or local agencies having special expertise with respect to an environmental issue or jurisdiction by law may be a cooperating agency in the NEPA process. A cooperating agency has the responsibility to assist the lead agency by participating in the NEPA process at the earliest possible time; by participating in the scoping process; by developing information and preparing environmental analyses that include portions of the environmental impact statement wherein the cooperating agency has special expertise; and by making avail-
A-119
able staff support at the lead agencys request to enhance the lead agencys interdisciplinary capabilities. Basic information about the NEPA process is available online: www.epa.gov/compliance/basics/nepa.html#requirement. Resources U.S. General Accounting Ofce (2003). Perceptions of Stakeholders on Approaches to Reduce Highway Project Completion Time, report GAO-03-398. http://www.gao.gov/new.items/ d03398.pdf. Marshall, Ross (September 2005). Environmental Impact Assessment Follow-Up and Its Benets for Industry, Impact Assessment and Project Appraisal, Vol. 23, No. 3. NEPA website: www.epa.gov/compliance/basics/nepa.html.
neighborhoods, and so on must be either individually estimated or included in the estimate as an allowance amount. It is advisable to account for any such occurrences, and an acceptable quantication of these impacts is often recognized in the form of a percentage of total project costs. What Does It Do? This tool acts as a safeguard to reduce the chance of any cost overruns due to known but unquantied circumstances related to off-prism issues. When? It is benecial to include an allowance for off-prism issues early in programming and preliminary design and assess if the assumed percentage is reasonable based on project scope development and the location of the project. Inclusion of the allowance is especially critical when setting a project baseline cost that is programmed. Examples Using historical cost data, Caltrans has sometimes estimated capital outlay support cost in the environmental process as a percentage of the estimated project construction cost. In the case of one particular project, this was a straight 1% of the estimated construction cost estimate. Caltrans also spreads this total amount across the project schedule and applies an annual escalation rate (i.e., ination rate) to the outlay timed amounts. Tips An alternative to handling the potential cost of off-prism issues is to identify these items as risks to the project and cover them in contingency. Resources More information is available from the FHWAs publication, Major Project Program Cost Estimating Guidance, June 8, 2004, http://www.fhwa.dot.gov/programadmin/mega/ cenal.htm.
A-120
on the specic date on which a contract is advertised and bid and depending on the type of materials that are required to construct the work. Many market condition circumstances are beyond the control of a state highway agency and will affect all purchasers of construction services, but not always in the same way because of the different risk-shifting contract clauses. What Is It? This is a tool that establishes a formal process to analyze market capability to respond to the project as designed and packaged for bid. The process seeks to provide management with assurance that cost impacts driven by market conditions, both global pressures on material prices and the local construction situation, have been considered in developing the projects design, contract packaging, and estimated cost. Why? In developing a cost estimate, it is necessary to consider changes in the contracting situation and in general economic conditions. This is particularly true whenever historical prices are being used. Contractors usually enter into contracts with state highway agencies, which x the price over the term of a project, but for some materials the contractor cannot secure xed prices from the suppliers; therefore, project bidders must account for the risk of uctuating material prices in their bids. What Does It Do? Contracting rms must develop strategies to minimize their risks. A primary strategy involves increased cost to the project owner. In the case of risks that cannot be quantied, such as volatility of material prices or even the availability of materials, that cost increase can be signicant. Additionally, if the contractor perceives that an owner is seeking through the contract language to shift risk to the builder, sufcient additional cost will be included in the bid to cover that added nancial exposure. This tool is the establishment of a structured process to continually analyze market forcescost of materials and availability of competitionand the impact of market changes on project cost. When? Market conditions are volatile and will most likely change after a project is initiated but before issuance of bid documents; therefore, the process of evaluating market conditions and their affect on the estimate must be continuous through all phases of project development. When a change in market conditions is identied, the estimate must be adjusted to reect the new conditions.
Examples The FHWA document Major Project Program Cost Estimating Guidance, June 4, 2004, specically calls attention to the following market condition factors that affect project cost:
Acquisition strategy analysis: A separate analysis should
consider the most economical and advantageous way of packaging the contracts for advertisement. Bidding climate impact: Estimators should consider the economic impact of the project on the local economy. For example, material manufacturers that would normally compete with one another may need to combine resources in order to meet the demand of a major project. Extremely large construction packages also have the potential to reduce the number of contractors that have the capacity to do the work, and the project may need to be split into smaller contracts to attract additional competition. In addition, the timing of the bid solicitations can affect the cost. Cost estimates should consider availability of labor. Industry capacity: The number of potential qualied contractors that are able to bid on a project is limited as project size increases. Contractors that bid on major projects often bid on projects throughout the country. If other major projects are being advertised concurrently, this may have a limiting effect of competition and can result in higher bids. Highly specialized designs and technology: Cost estimates should consider the impact of any requirement to use rstof-a-kind technology, new materials, or innovative construction methods. Tips A market survey should be carried out on sizable projects to determine where the bidders will come fromis the local market sufciently large to accommodate the project, or will the major subcontractors be at capacity and therefore likely to bid high, if at all? Also, a reading of the market prior to nalizing the PS&E is useful for validating the estimate and can be included in a risk assessment to determine a range of expected bids. Three circumstances are worthy of special consideration:
Changes in the level of competition Limited competition Differing economic conditions
Continuously update the estimate to reect current market conditions. Resources FHWA (2004). Major Project Program Cost Estimating Guidance. www.fhwa.dot.gov/programadmin/mega/cenal.htm.
A-121
Caltrans Division of Engineering Services (November 15, 2001). Impact of Competition on Final Bid Results for Transportation Related Construction Project (Draft). Merrow, Edward W., Kenneth E. Phillips, and Christopher W. Myers (1981). Understanding Cost Growth and Performance Shortfalls in Pioneer Process Plants, Rand Corporation. http:// www.rand.org/pubs/reports/R2569. Merrow, Edward W. (1988). Understanding the Outcomes of Megaprojects: A Quantitative Analysis of Very Large Civilian Projects, Rand Corporation. http://www.rand.org/pubs/ reports/R3560. Sawyer, John E. (19511952). Entrepreneurial Error and Economic Growth, Explorations in Entrepreneurial History, Vol. 4, No. 4, pp. 199204, 195152. Merrow, Edward W. (1986). A Quantitative Assessment of R&D Requirements for Solids Processing Technology Process Plants, Rand Corporation. http://www.rand.org/pubs/reports/ R3216. Maryland DOT (March 1, 2002). Summary of Independent Review Committee Findings Regarding the Woodrow Wilson Bridge Superstructure Contract. The full report is available from the MDOT. Woodrow Wilson Bridge Project Bridge Superstructure Contract (BR-3): Review of the Engineers Estimate vs. the Single Bid, February 28, 2002. This report is available from Maryland DOT.
current market conditions may be required, this approach typically produces an accurate estimate and is useful in estimating unique items of work where there is insufcient bid history. 3. Combined: Most projects contain a small number of items that together account for a signicant portion of the projects total cost. These signicant contract items may include Portland cement concrete pavement, structural concrete, structural steel, asphalt concrete pavement, embankment, or other specialty items. Prices for these items are estimated using the bottom-up approach. The remaining items are estimated based on historical prices and adjusted as appropriate for the specic project.
A-122
ity of a computer is an important asset in developing estimates for projects having a large number of cost (i.e., work) items. What Does It Do? Agency software, besides providing a calculation framework, allows the estimator to effectively employ the agencys historical databases in a selective yet rapid manner. The software should also be capable of performing what-if analyses. Typically, the software, be it agency or commercial, provides a sequential record of the data used to generate the estimate and all assumptions. When? To address very specic PS&E requirements, custom agency software may be the only solution. Agency software can be very good in addressing distinctive requirements imposed on any individual state highway agency; however, software development is tedious and costly, and continuing support is a critical issue. Agencies must therefore recognize the size and complexity of the software development undertaking and must balance such a commitment against the performance of commercially developed and supported software, such as AASHTOs Trnsport, which has been developed specically to meet the needs of state highway agency estimation. Examples One state highway agency that approaches project estimation by building estimated cost from the bottom up currently uses a slightly modied commercial estimation program. The commercial program is used by many contractors and was originally developed to facilitate detailed estimation by a large contracting organization. This program and similar ones of this type enable state highway agencies to develop estimates from the bottom up based on crew productivity, construction methods, and selected equipment. California DOT (Caltrans) has its Basic Engineering Estimating System (BEES). General information about BEES can be found in the Caltrans Plans, Specications and Estimates Guide. BEES has the capability of segregating estimates by structure, alternative designs, and so forth. The BEES software is a subsystem of the Caltrans Project Information System and Analysis (PISA) and uses the information contained in the Caltrans Project Management Control System (PMCS) and their Standard Item List. The estimate data are available for bid opening purposes and for contract progress payments. Tips It is important that agency-developed software be user friendly and structured so that it is easy to input the required data. To be usable and reliable, estimation software must:
of every bid item is known at any given time during estimate preparation Be mathematically consistent and automatically make adjustments everywhere when a revision is made Be devoid of instructions using program le names or other programming language Have databases designed so they are accessible within an extremely short time without scrolling through a myriad of items Allow the use of arbitrary unit prices not drawn from the database Allow the estimator to have cost templates for standard items Identify the source (database or plug) of all prices Be able to sort and print the data generated by the estimate in several different formats Automatically identify prices that are outside of specied ranges
Resources Washington State DOT, Barlist bridge software download site, www.wsdot.wa.gov/eesc/bridge/software/index.cfm? fuseaction=download&software_id=45. Caltrans, Chapter 20: Project Development Cost Estimates, Project Development Procedures Manual (PDPM). www.dot.ca.gov/hq/oppd/pdpm/chap_htm/chapt20/ chapt20.htm. A list of Basic Engineering Estimating System (BEES) standard contract items and the weighted averages of the low bidders prices for those items can be found at www.dot.ca.gov/ hq/esc/oe/awards.
A-123
heavy construction industry. It is also interesting to note that the same survey found that about 26% of the market uses Microsoft Excel. What Is It? Estimation software is any computer program that assists the state highway agency in developing project cost estimates. Estimation software has preloaded templates that help the estimator and project team dene the project scope, cost, and schedule. The software provides a means to track project development and can assist in project reviews. Several very good commercial programs are available and being used by a large number of state highway agencies. Why? Because development and maintenance of specialized agency software can be expensive and requires special talents, it is often more economical to use commercially available software, which spreads the programs development and maintenance cost over a larger user base. Software providers can also help state highway agencies structure their databases to better support the estimation process. Additionally, because the software provider works with many agencies and estimators, it has a broad knowledge of estimation and software issues. What Does It Do? Computers and estimation software enhance the ability of engineers to manage large data sets that are needed in developing estimates for all types of projects. Computers and estimation software can:
Develop an unlimited number of estimates matched to proj-
project development to create an estimate that can then be expanded at the PS&E stage when design is complete and quantities fully quantied. Examples The Cost Estimation System (CES) is the primary AASHTO Trnsport module for construction cost estimation. It provides a variety of estimation methods and full integration with the other Trnsport components. Available on the client/server platform and fully integrated with PES and BAMS/DSS (other Trnsport modules), CES provides an environment in which parametric, cost-based, and bid-based job cost estimates can be prepared. Historic bid price databases can be created using the BAMS/DDS module of Trnsport. BAMS/DDS is the Decision Support System module of the construction contract information historical database. Another commercially available system that is used by several state highway agencies is Bid Tabs by OMAN systems. As of August 7, 2002:
Trnsport is used by 22 state highway agencies. Bid Tabs is used either as a stand-alone or in conjunction
with Trnsport by seven state highway agencies. Two other state highway agencies are in the process of testing Bid Tabs. One state highway agency uses HCSS HeavyBid, which is used by many contractors and was originally developed to facilitate detailed estimation by a large contracting organization. (See www.hcss.com/HBstdFeatures.asp.) One state highway agency uses AutoCAD to perform quantity takeoff for project estimates by combining plan views of the project area with elevation information to get a threedimensional view of the project. Tips The estimator is the key to any estimation process and must know the capabilities and limitations of the software being used. Therefore, the effectiveness of any software is directly related to product support and training. When selecting software, always ensure that product support will be available and that training and training material will be provided. Resources For more information about Trnsport Estimator, contact the AASHTOWare contractor: Info Tech, 5700 SW 34th Street, Suite 1235, Gainesville, FL 32608. Phone (352) 381-4400; Fax (352) 381-4444; E-mail [email protected]; Internet www. infotech.com.
ect complexity and level of design, whether from scratch, other current estimates, or historical backups Easily change, back up, and store estimates Draw from unlimited amounts of historical cost information and/or labor and equipment rate tables Quickly copy entire estimates, individual or multiple work (i.e., bid) items, and/or activities from previous estimates Provide a record of what changes were made to the estimate and who made the changes
When? Commercial estimation software offers the most effective way to prepare and manage estimates for medium to large projects involving multiple cost items. For very large, complex projects, software may be the only effective and efcient method. Most software can be used in the earliest stages of
A-124
Oman Systems, Inc., P.O. Box 50820, Nashville, TN 37205. Phone (800) 541-0803; Fax 615-385-2507; Internet www. omanco.com. Heavy Construction Systems Specialists, Inc. (HCSS), 6200 Savoy, Suite 1100, Houston, TX 77036. Phone (800) 683-3196 or (713) 270-4000; Fax (713) 270-0185; Internet www.hcss. com; E-mail [email protected]. Hard Dollar BID*BUILD estimation and job control software built on a Microsofts platform. http://www.harddollar. com/Solutions/project_driven/scheduling.asp. BID2WIN software is a Windows-based cost estimation and bidding program built on Microsoft.NET and SQL Server technology, www.bid2win.com. Timberline estimation software operates several different Microsoft platforms: www.sagetimberlineofce.com/software/ estimating/default.aspx.
defendable costs to support the decision for contract award/ rejection and any future price negotiations with the contractor. At the PS&E phase, work items are well dened so that the construction operations involved with a work item can be visualized to support the development of cost-based estimates. What Does It Do? Cost-based estimates contain six basic elements: time, equipment, labor, material, overhead, and prot. Generally, a work statement and set of drawings or specications are used to take off material quantities required for each distinct task performed in accomplishing a given construction operation. From these quantities, direct labor, materials, and equipment are derived. Contractor overhead and prot are then added. The total cost divided by the quantity gives the unit price for the work item. This unit cost can then be input into the engineers estimate to provide for a unit cost for the work item. This is necessary for the state highway agency to compare the engineers estimate with the contractors unit price bid for the same item. When? This tool is used most often when detailed plans and specications are complete but there is a lack of historical bid data to estimate costs for a specic item of work. Typically, this work item is unusual in nature and not commonly encountered by the estimator. The estimator must still convert the cost-based estimate for an item to an equivalent unit price for incorporation into the engineers estimate. Examples The AASHTO Subcommittee on Design Technical Committee on Cost Estimating is developing a guidance paper on cost-based estimation. The type of content covered in this paper is outlined below:
Introduction Denitions Elements of a Cost-Based Estimate Building a Task Material Quantity Breakdowns Obtaining Prices Quote Maintenance Equipment Needs Identication Ownership Rates Operation Costs Resources Labor Needs Identication Required Wage Rates Time Production Rates
A-125
Effect on the Estimate Resources Overhead & Prot Administration Labor Lump Sum Items Software Applications Examples References
Smith, Francis E. (1976). Earthwork Volumes by Contour Method, Journal of the Construction Division, American Society of Civil Engineers, Vol. 102, No. 1. Frank R. Walker Company (published periodically). Walkers Building Estimators Reference Book.
While still in draft form, this guidance provides quantitative examples of cost-based estimation for such items as material, equipment, labor, and time, as well as the application of these components in preparing the PS&E using this tool. Tips The estimator should have construction experience in order to be able to visualize a line item in terms of the operations needed to construct the work. The estimator also needs to locate sources of information related to production rates and crews, which includes calling suppliers of materials to obtain unit costs for materials and similar resources for determining equipment production and rental rates. This may require using a resource such as the RSMeans Heavy Construction Cost Data. Resources AASHTO Subcommittee on Design, Technical Committee on Cost Estimating, is developing guidance on historical bidbased estimation and cost-based estimation. Draft papers are prepared but not approved for release. To learn more, contact the Chair of this technical committee. See this website for key contact persons: http://design.transportation.org/?siteid= 59&pageid=756. Church, Horace K. (1981). Excavation Handbook, McGrawHill Book Company. Associated General Contractors of America (1999). Construction Estimating & Bidding Theory Principles Process. Publication No. 3505. R. S. Means (2006). Heavy Construction Cost Data, www. rsmeans.com. Oberlender, Garold D., and Steven M. Trost (2001). Predicting Accuracy of Early Cost Estimates Based on Estimate Quality, Journal of Construction Engineering and Management, American Society of Civil Engineers, Vol. 127, No. 3, May/June. Parker, Albert D., Donald S. Barrie, and Robert M. Snyder (1984). Planning & Estimating Heavy Construction, McGrawHill. Rignwald, Richard C. (1993). Means Heavy Construction Handbook, R. S. Means Company. R. S. Means Company (published annually). RSMeans Building Construction Cost Data. www.rsmeans.com. R. S. Means Company (published annually). RSMeans Heavy Construction Cost Data. www.rsmeans.com.
A-126
to provide the historical data to the estimator. The more data that are available and organized by project type, size, and location, the better resource the estimator has to produce an estimate that reects the known scope and site conditions of the new project. Unit prices are adjusted for the specic project conditions in comparison to the previous projects. Adjustments are generally made based on the project location, size of the project, project risks, quantities, general market conditions, and other factors. The estimator has to rely on engineering judgment and experience to make these adjustments. When? This technique can be used as early as the programming phase but is validated to a greater extent in the PS&E stage, when project quantities are better known. Examples Collection, sorting, and retrieval of data are the key to success with this method. The usage of computer software provides an efcient way to handle the data. To organize the data, it is helpful to collect data by category, such as general project information, bid data, and projectspecic information. Using a data entry form, such as the one in Figure P1.4-1, to input general project information and project-specic information is an effective way to collect project information. Using a spreadsheet is another effective way to import bid data. Figure P1.4-2 shows an example of bid data placed into a spreadsheet to be exported to a database. Further, provisions are often made in the software to include project-specic or unique items, such as new line items, force account work, bidding climate, time of year, expected competition, other contracts, and specialty work. These types of provisions can aid in the estimation and improve estimate accuracy.
Tips Several historical databases are available that provide current values for estimating costs of the various units of work for a project. The databases are compiled from records of actual project costs and ongoing price quotations from suppliers. The databases are published annually in the form of books, CDs, and computer-based extranets. There is, however, a danger of applying any historical database pricing without rst adjusting the data for the particular aspects of the project under consideration. In construction, every project is unique, with a distinct set of local factors (such as size of project, desirability, level of competition, exibility of specications, work site, and hour restrictions) that come into play in bidding. When an estimation system that is attached to a price database is used, the estimator should still review each line item price to determine if it is applicable to the project being estimated. Blindly applying database prices can lead to inaccurate estimates. Location factors should also be applied only after rst considering the project size and particular nature to determine where the bidders will come from. If a large project is in a small town, the location factor for that town likely will not apply, as the bidders will be coming from elsewhere. The bids may, as a result, be much higher than the factor would indicate because the wages will be based on another location and the bidders may have to pay accommodation and travel costs for some of their workers. Resources The AASHTO Subcommittee on Design, Technical Committee on Cost Estimating, is developing guidance on historical bid-based estimation and cost-based estimation. Draft papers are prepared but not approved for release. To learn more, contact the chair of this technical committee. See this website for key contact persons: http://design.transportation. org/?siteid=59&pageid=756.
A-127
new modules. Figure P1.5 shows a generic estimation workow and functional areas where Trnsport models can assist. Each module addresses the needs of the highway agency at a particular milestone in the construction contracting life cycle, representing three functional areas: preconstruction, construction, and decision support. What Is It? The Trnsport Proposal and Estimates System (PES) addresses the needs of the highway agency during the pre-
Figure P1.5. Estimation workow and functional areas where Trnsport models assist.
A-128
letting phase of project development. PES supports preparation of the PS&E for state and federal aid highway construction projects. PES provides design, project construction administration, and estimation sections with tools to assist in project denition, funding specication, project cost estimation, contract proposal creation, and bid letting packaging. Why? The Trnsport PES module is designed for exibility in project denition and in associated funding requirements (such as proposal creation using multiple funding units, differing construction engineering and contingency percentages, identication of special provisions and supplemental specications, addendum processing, and alternative specications at both category and line-item levels) to track and manage project scope and cost information. What Does It Do? The Trnsport PES module is an interactive, online system that enables management of project information during the pre-letting phase of a highway construction project development. PES permits the exible denition of a project and its associated funding requirements to track and manage project cost information and set up a bidding proposal prior to the bid letting activity. It allows for data to be entered at the project, category, and item level. Grouping of multiple projects to track all related costs and funding sources is also possible. PES has import capabilities for receiving item and quantity data from design systems and can exchange data with the CES and estimating modules of Trnsport (see Sections D3.5 and D2.9). When? The PES module of Trnsport is most frequently used to support the PS&E phase and the development of an engineers estimate. Examples In years past, the New York State DOT (NYSDOT) used the mainframe versions of Trnsport PES, LAS, and DSS, but as agencies moved from the mainframe to the client/server versions, AASHTO decided to drop support of the mainframe version. NYSDOT then migrated to the client/server version. Tips The estimator can use different reports generated by the PES module:
Detailed cost estimate and funding summary Proposal schedule Special provisions listing Proposal schedule with estimated prices
The estimator must check all input and output to ensure that the estimated costs for major line items are within expected agency tolerances for the project type being estimated. This check can follow the Puerto principle, in that 80% of the estimated cost of construction is covered in 20% of the items. Comparing the overall estimate with estimates from recently bid or completed similar-type projects is another method of checking an estimate. Additional information can be found on the following website: dot.state.ny.us/trns-port/about.html. Resources The Technology Implementation Company, Gainesville, Florida: www.infotech.com or www.cloverleaf.net. AASHTOWare, Transportation Software Solutions, American Association of State Highway and Transportation Ofcials, www.aashtoware.org.
P2 Project Scoping
Scoping ensures that the development team is concentrating on the best opportunity for improvement. Projects have a greater success rate if the scoping sets clear parameters and determines what is in scope or out of scope for a particular project, what resources and skills will be required, and a time frame for completion. To ensure that the project is based on valid analysis rather than assumption, it is important to invest sufcient time up front to dene the primary objectives. Without this process, a project may be too nebulous or unwieldy for the team to manage and, therefore, will not produce the desired resultsit will continually experience scope changes and scope creep, and a valid estimate cannot be developed.
A-129
What Is It? Checklists serve as guides in preparing, checking, and reviewing cost estimates. These templates ensure that estimators and reviewers develop a complete estimate. They guide the estimator through suggested items and consideration of factors that impact project cost. Why? While estimators and project managers are generally very familiar with assembling cost data and developing an estimate, the estimation process requires consideration of many work items and the factors that impact the cost of individual items, as well as factors that impact the cost of the project in general. Checklists serve to delineate the many factors that must be considered during estimate preparation. Therefore, checklists are an excellent means of (1) ensuring that the estimate completely addresses the stated scope of the project, (2) avoiding omissions, and (3) calling attention to the interaction between factors that can impact cost. What Does It Do? Checklists guide the estimator through suggested items and serve to ensure that all cost categories are accounted for in an estimate. The answers to the checklist questions will provide an overview of the estimates completeness and focus the estimators attention on critical questions. The checklists can be divided into major work areas, such as roadway and structural, to support specic parts of project estimate development. There can also be checklists that help the estimator identify background concerns that impact project cost. When? Checklists can support estimate creation at all stages of project development. The purpose of a checklist is to assist the estimator in planning, formatting, and developing a complete estimate. Checklists should be as inclusive as possible, with questions that specically probe the estimate at the different stages in project development. Example The North Carolina DOT has an estimate checklist for functional and preliminary estimates. It includes the various items included in a project estimate, as well as the units of measurement to be used in estimating the items:
Clearing and grubbing (acre or hectare) Earthwork (cy or m3)unclassied, borrow, undercut, etc. Fine grading (sy or m2)
Drainage (per mile or kilometer) Paving (ton or mtn, w/pavement design, or sy/m2 without) Stabilization (sy or m2) Shoulder drains (lf or meter) Curb and gutter (lf or meter) Guardrail (lf or meter) Anchor units (each type) Fencing (mile or kilometer) Interchange signing (type and location) Trafc control plan (TCP) (per mile or kilometer) Thermo and markers (per mile or kilometer) Utilities (lf or meters) Erosion control (acres or hectares) Trafc signals (each and location) Retaining walls or noise walls (sf or m2, with avg. height) Bridges (individual location) Reinforced concrete (RC) box culverts (individual location) Railroad crossing (eachwith or without gates)
Tips There can be many individual checklists to support different phases of estimate preparation and specic cost areasfor example, a plan review checklist; a site checklist; a checklist for developing quantities; and a checklist to consider construction noise, dust, and other construction nuisance issues. Resources Checklists for reviewing a prepared estimate are used by the FHWA and state highway agencies. The following is FHWAs Engineers Estimate Checklist for Full Oversight Projects:
Check approximately 1520% (more if possible) of the bid
quantities? Do the pay items correspond to the type of work proposed? Are the units of measure appropriate for the pay item? Is the quantity for the pay item reasonable for the project? Does the unit price seem reasonable for the type, size, and location of the project?
The FHWA also has a checklist document, Checklist and Guidelines for Review of Geotechnical Reports and Preliminary Plans and Specications, which is posted on the FHWA website. In the PS&E portion of this document is a checklist that applies to specic geotechnical features, such as pile foundations, embankments, and landslide corrections. This checklist can be found at: www.fhwa.dot.gov/bridge/checklist.htm. The U.S. Army Corps of Engineers estimate review checklist from ER1110-1-12 requires that the reviewer verify that:
A-130
Estimates are based on approved scope of work and latest
(UPB) or approved construction cost data (e.g., the General Construction Cost Engineering Standards published annually by Richardson Engineering Services or the price data published by R. S. Means Company). The basis for the estimates is provided or explained; all assumptions, quotes, crew sizes, and other cost factors are documented. Estimates are escalated to the expected midpoint of construction using the latest approved management control plan or OMB [Ofce of Management and Budget] (for Civil Works projects) index. Estimates are prepared in accordance with latest Corps cost engineering regulations and technical manuals. Estimates include risk analysis to cover unknown conditions or uncertainties on work schedules. Estimates are internally reviewed prior to submittal.
mation process during the latter stages of project development. The scoping documents can be used as a guide to ensure that all critical scope items are included in an estimate or to assist in communicating the estimate basis. What Is It? Scoping documents are standardized forms that state highway agencies use to explicitly dene and document the scope of a project. They are often developed in the form of a checklist. They represent past project experience and list key scope items and lessons learned from past projects. Why? A scoping document is a tool to aid in project scope denition and documentation. It is a key tool in the scoping method of estimation. Scoping documents can be used before any major engineering efforts take place. They can also be used later in the cost estimation process to dene the estimate basis and to aid in establishing an appropriate level of contingency. What Does It Do? The development of a standard scoping document provides consistency in project scope denition early in the project development process. Completion of the scoping document for each project clearly identies the original project scope, which can be used in the documentation of the estimate basis or in the establishment of the estimate baseline. The scoping document can help document subsequent changes. This document will aid in identication of the purpose of the project and serve as a reminder of project intentions throughout project development. The document aids in identifying elements to be included in estimate and schedule considerations. When? The scoping document should be completed early in project development to establish a baseline scope of the project and a basis for the early project estimates. It can be reviewed at each project milestone to ensure that all critical scope items are included in the estimate and that the extraneous items of scope are not included. The document should be reviewed throughout the development of the project to check for changes in scope. Examples Numerous examples of scoping documents are provided in Section C6.4. Many state highway agencies use some sort of scoping document. Scoping documents vary in complexity and
This checklist could serve as review guidance for any state highway agency. Defense Logistics Agencys In-House Cost Estimate Checklist, at www.dla.mil/j-3/a-76/IRLine02.html, is not designed for projects of the type that state highway agencies handle, but it does contain some very good questions that a state highway agency might want to include in its own checklist, including:
Is ination calculated correctly? If costs are based on historical data, are appropriate adjust-
ments included? Wisconsin DOTs (WisDOTs) early project scoping tools can be found at www.dot.wisconsin.gov/localgov/highways/ tools.htm. WisDOTs Local Agency Guidelines: Appendix 14.52 Project Development Checklist can be found at http://www. mrsc.org/Subjects/PubWorks/construct/c3-checklst.pdf. The Port Angeles Public Works Departments Project Development Checklist can be found at http://www.mrsc. org/govdocs/p54pwprojdevchklst.aspx.
A-131
specicity. Some state highway agencies use a simple memo as their scoping document, while other agencies have longer, more detailed forms. Figure C6.4-1 provides an example of a scoping document from Virginia DOT, and Figures C6.4-2 provides an example of a draft project scoping memoranda from Missouri DOT. Tips A scoping document is an excellent tool to dene an estimate basis. Use the project scoping document in a team environment with all of the appropriate disciplines represented whenever possible to minimize the chance of any oversights. Scoping documents should permit some exibility for special-case projects, both the very straightforward projects and the more complex projects. Revisit the project scoping document at critical cost estimation practice and cost estimation management milestones throughout the project development process. Resources The Vermont Agency of Transportation Project Development Process Manual is online at http://www.aot.state.vt.us/ progdev/Sections/PDManual/01mantabl.htm. The New York State DOT Design Quality Assurance Bureau scoping process can be found in the first three chapters of the Project Development Manual, http://www.dot.state.ny.us/ cmb/consult/dpm1/pdm_01_30_04.html. The Missouri State DOTs report, Implementation of Recommendations for Project Scoping, is online at www. modot.org/design/scopingreport_ 0403.pdf. A series of scoping resources is available from the Virginia DOT online at www.virginiadot.org. A particularly helpful Virginia DOT guidance document for a scoping meeting is listed at www.virginiadot.org/projects/Resources/CE-1-Scoping.pdf. Project initiation documents mark the transition from planning and programming to advanced planning. Such documents are described in Chapter 9 of the California DOT Project Development Procedures Manual (PDPM), on the Internet at http://www.dot.ca.gov/hq/oppd/pdpm/pdpmn.htm.
project components that organizes and denes the total scope of the project. Work not in the WBS is outside the scope of the project. As with the scope statement, the WBS is often used to develop or conrm a common understanding of project scope. Each descending level represents an increasingly detailed description of the project. What Is It? A basic WBS is illustrated in Figure P2.3-1. Why? The WBS is an excellent tool for documenting the project scope, scope changes, and scope creep. Each change to the WBS is a change in the project teams understanding of the project scope. Small incremental changes (i.e., scope creep) can be documented by comparing the current WBS with earlier versions. A WBS can be a basis for developing a WBS for future projects that have similar project characteristics. What Does It Do? A good WBS fully documents the teams current understanding of the project scope. It can be amended in three ways:
Deleting WBS elements, indicating a decrease in expected
scope.
Adding WBS elements horizontally, indicating an increase
in expected scope.
Adding WBS elements below an existing element, indicat-
ing an increased understanding of the existing scope. When? The initial WBS should be developed immediately after the scoping document is completed (see Section P2.2). It may be part of, or an attachment to, the scoping document. Examples Washington State DOT has initiated a project management process as an executive order. A major component of the project management process is to plan the work. One activity under plan the work is the preparation of a work breakdown structure. A description of this activity is shown in Figure P2.3-2. Tips Build the WBS to the level at which you plan to manage the work. Specialty groups are a part of the project team, but they
A-132
State Highway Improvement
Environmental Document
Right of Way
Construction
Construction Engineering
Construction Contract
Earthwork
Drainage
Pavement
Structures
Bridge 1
Bridge 2
Soundwall
Substructure
Superstructure
should identify their deliverables and be responsible for managing their tasks and reporting progress. Remember, a good WBS is not a detailed to do list. Resources A Guide to the Project Management Body of Knowledge (3rd ed., 2004) and Practice Standard for Work Breakdown Structures (2002), both published by the Project Management Institute. Washington State DOT (undated), Project Management OnLine Guide, see website http://www.wsdot.wa.gov/Projects/ ProjectMgmt/Process.htm. Project Management Institute (2004). A Guide to Project Management Body of Knowledge (PMBOK Guide).
ment process and who, if left out of this process, could prove to be obstructive.
P3.1 Meetings
Getting started in public involvement need not be difcult. Clearly dene the goals and objectives of the public involvement program, and then make them specic to the project. Offer people ways to participate that match their level of interest and commitment. Invite those who are highly involved to address specic tasks or issues on a regular basis. Scope issues may be raised through the people most closely impacted by the project. What Is It? Public meetings and other outreach efforts provide an opportunity for the public to participate in a general review of a specic project. These meetings also give the state highway agency a forum for providing details about the project, including the purpose of, and need for, the project. The purpose and need information informs the public that the project will correct a problem or deciency, such as relieving congestion and improving safety. Further, the state highway agency can inform the public how the project will correct the deciency (i.e., the scope of the project), such as adding lanes to improve trafc
P3 Public Involvement
People want to have a voice in transportation project decision making. State highway agencies must solicit public involvement to accommodate the publics voice in order to create a successful project. However, the public often nds both metropolitan and statewide transportation programs incomprehensible. Extra effort may be needed to obtain involvement by people unaccustomed to participating in the project develop-
A-133
Pre-Construction Plan the Work Activity: Description: Inputs: Tools: Develop the Work Breakdown Structure using the Master Deliverables List (MDL) On-Line Guide Process Revision July 1, 2005
Tailoring and completing the project-specific Work Breakdown Structure based on the Master Deliverables List. Completed Initiate and Align Worksheet What you need to know about the Master Deliverables List (MDL) Master Deliverables List (MDL)
Steps:
1. Refer to What you need to know about the Master Deliverables List (MDL) for a general briefing on the MDL and its role in the Project Delivery Information System (PDIS). 2. Review the MDL and delete the elements that are not applicable for this project and phase. 3. Identify your Project Phase and Sub-Phase (Levels 1 & 2), and eliminate the rest. The majority of the time in project development (design), we are in the Preliminary Engineering (PE) Phase (Level 1). Within PE, we are either in the Scoping or Design/PS&E SubPhase (Level 2). 4. Identify the categories of work or processes (Level 3) that will be a part of your project, and eliminate the rest. The processes in the MDL include subjects such as: Hydraulics, Right of Way, Traffic, Utilities, and Environmental Documentation. Consult with specialty groups to identify the specific processes required for the project. 5. Identify the deliverables to be produced (Level 4) for each category of work or process, and eliminate the rest. The deliverables in the MDL includes subjects such as: Type A Project, Right of Entry, Preliminary Traffic Analysis Report, and NEPA/SEPA Compliance. 6. Consult with specialty groups to identify project-specific deliverables, logical constraints, durations, and costs.
Products: Guidelines:
Build the WBS to the level at which you plan to manage the work. Specialty groups are a part of the project team, but they should identify their deliverables and be responsible for managing their tasks and reporting progress.
ow. In addition to presenting the scope, the project cost and schedule can be presented to the public. Why? Public meetings initiate active public involvement in the project. Obtaining public response to a project is critical to the state highway agency to avoid opposition to the project, which may delay project development. Further, the public may request changes to the project that would impact the projects scope. Delays and/or changes in scope have cost and schedule ramications.
What Does It Do? Meetings create public awareness of the project and hopefully public buy-in with respect to the approach for addressing the need that is driving the project scope. Through meetings, the public becomes part of the project. Meetings provide an opportunity for the state highway agency to gain public trust that the project is using their tax dollars wisely. When? Public involvement should occur early in project development, beginning at systems planning, continuing in program-
A-134
Project Status
January 2006 We hosted an open house to explain our plans and get public input on October 5, 2005. We recently received approval from state legislators to build a new flyover ramp from westbound SR 202 to westbound SR 520 three years ahead of schedule. The new ramp could be open to traffic by the end of 2007. We recently mailed a newsletter (pdf 759kb) to 40,000 Eastside households to keep them up-to-date on our progress.
Figure P3.1-1. Website clip of announcement for a Washington State DOT open house.
ming, then continuing through preliminary design and beyond. The timing of meetings to engage the public in the project should coincide with the availability of preliminary design information. The project team must have sufcient knowledge and understanding of the project to convey the projects purpose, need, and scope to the public in an effective manner. Examples An open house for a project informs the public about the details of the project and allows the public to ask questions. An illustration of this approach is shown in Figures P3.1-1 and P3.1-2. Tips The state highway agency should use public meetings and open house events to encourage public comments on the project. The information provided to the public should be simple and easy to understand. Graphics should be used to the fullest extent because a picture is worth a thousand words. State highway agency staff should actively engage the public during the meeting, so techniques should be used to encourage the public to ask questions. Costs and schedule information should be provided in a manner that helps the public understand the project costs and why it takes so long to design and construct the project. The state highway agency should have key project team personnel participate in these meetings so that the public gains condence that the project will be successful. Finally, the state highway agency should respond to any public comments and try to accommodate requests. Resources Howard/Stein-Hudson Associates, Inc., and Parsons Brinckerhoff Quade and Douglas (1996), Public Involvement Techniques for Transportation Decision-Making, Publication No. FHWA-PD-96-031 for the FHWA and the FTA. www. fhwa.dot.gov/reports/pittd/cover.htm.
FHWA (1997), Public Involvement at Oregon Department of Transportation, Publication No. FHWA-PD-94-021. This report describes how Oregon DOT uses a variety of public involvement techniques in both project development and statewide planning. Washington State DOT, Project SR520, Information can be found at: www.wsdot.wa.gov/Projects/SR520/WLakeSamPk_ SR202 and at www.wsdot.wa.gov/Projects/SR520/WLake SamPk_ SR202/ProjectPhotos.htm.
Figure P3.1-2. Members of the public reviewed project plans and asked Washington State DOT engineers questions about the plans at an open house.
A-135
ods and tools that an estimator uses to prepare and manage project cost estimates. Some agencies have found it useful to create a formal and standard denition for project complexity in order to communicate the issue to project team members and stakeholders. What Is It? A complexity denition is a formal classication of project complexity that can be applied to all projects. The complexity denition can also include a denition of project type (such as new or reconstruction, size, project setting, and rural or urban), project location, available level of design detail, and other extraordinary factors. The goal is to explicitly dene project complexity through the use of this classication system. Why? Providing a standard definition of project complexity promotes transparent communication of a projects characteristics. It can be used to assist in selecting an appropriate estimation method and tools or to invoke specic cost estimation management procedures. It helps to ensure that projects of varying complexity levels are subject to the appropriate reviews and attention. This allows for a common language between state highway agency employees for communication regarding project complexity. What Does It Do? This tool denes a project classication based on a specic set of complexity criteria. The classication in turn helps to identify the appropriate strategies, methods, and tools for approaching cost estimation practice and cost estimation management on the project. When? In terms of estimation, this tool is used to define the approach for preparing estimates during all phases of project development. It should be employed early in the project development process and revisited as design develops or if any major changes in scope are realized. Examples Several state highway agencies have created classications to dene the level of project complexity. Tables were created with the use of information from similar projects that have been fully evaluated to generate complexity factors for long-range planning estimates.
Pennsylvania DOT (PennDOT) has developed several tables that provide information regarding the PennDOT classication system of non-complex (i.e., minor), moderately complex, and the most complex (i.e., major) projects. These tables are shown in Figure R1.1. Tips Use the complexity denitions early in the project development process to select or invoke appropriate strategies, methods, and tools for project cost estimation practice and cost estimation management. Use the complexity denitions when developing estimation policies, guidelines, and training materials. In order to keep the tables accurately related to complexity, reassess project complexity at critical cost estimation management milestones. If the project becomes more or less complex as the design develops and more information becomes available, the denitions can be used to ensure that appropriate methods and tools are being applied. Resources PennDOT has established a system to dene the level of complexity. See PennDOTs Design Manual: Part 1A: Transportation Engineering Procedures, Publication 10A, available from PennDOT. Christine Fiori and Molly Kovaka identied ve key project characteristics common to construction megaprojects: cost, complexity, risk, ideals, and visibility. Fiori and Kovaka developed a descriptive and comparative tool for megaproject evaluation for future researchers. The tool consists of a 132-element questionnaire. Each element is numerically rated (0 to 4), and a ve-element composite project score is generated in the form CCRIV. For more information, see Fiori and Kovakas 2005 publication, Dening Megaprojects: Learning from Construction at the Edge of Experience, presented at the Construction Research Congress 2005: www. pubs.asce.org/WWWdisplay.cgi?0520069.
R2 Right-of-Way
Right-of-way administrators have reported a number of challenges routinely encountered in right-of-way cost estimation: (1) early estimates are typically based on planning-level maps, so the extent of takings must be anticipated based on limited information; (2) often there is limited time to prepare early estimates, thereby restricting the amount of research that can be undertaken for complex parcels; and (3) right-ofway estimates are usually prepared years in advance of actual right-of-way acquisition, and signicant ination in between estimation and acquisition results in property and damage appreciation.
A-136
NON-COMPLEX (MINOR) PROJECTS
Roadway
Maintenance betterment projects. Overlay projects, simple widening without right-of-way (or very minimum right-of-way take), little or no utility coordination. Non-complex enhancement projects without new bridges (e.g., bike trails).
Traffic Control
Structures
Bridge resurfacing or repairs which do not require re-analysis of bridge capacity. Pipes, box culverts or minor culvert replacements where design can be picked directly from design manual or standards or using simple software where detailed interpretation is not necessary. Sign structures for which the design can be picked up directly either from the standards or using design computer software. Noise walls or retaining walls for which the design can be picked up directly either from the standards or using design computer software.
Involve minor right-of-way acquisitions with no displacements, maintain existing access control. Minimal, if any. Categorical Exclusion (level 1A or 1B) Minimum interaction with environmental and permitting agencies. Minor environmental impacts as appropriate have a Statewide Wetland Finding. Do not involve cultural resources, hazardous waste, Section 4(f) evaluations or substantial flood plain encroachments.
Stakeholders
Roadway
3R and 4R projects which do not add capacity. Minor roadway relocations. Certain complex (non-trail enhancements) projects. Slides, subsidence. Non-ITS but major safety improvements. Interconnected traffic control/management projects. Non-complex (straight geometry with minimal skew; designs using AASHTO description factors; minimal seismic analysis; footings on rock or conventional piles and abutments) bridge replacements with minor (< 610 m [2,000 ft]) roadway approach work. Bridge rehabilitation which requires re-analysis of bridge capacity. Bridge mounted signs. Tie back walls. Noise walls. Proprietary/non-proprietary walls. Right-of-way plans needed with less than 20 moderate to significant claims and very few relocations or displacements. Some utility relocations, most of it prior to construction, but no major utility relocations. Categorical Exclusion level 2 or mitigated Environmental Assessment projects. Cultural resources (historical, archeological, etc.). Coordination with Museum Commission, FHWA, and/or Advisory Council. Wetland mitigation. Parkland involvement. Water and air pollution mitigation. Major coordination with Game or Fish and Boat commissions. Endangered species. Involvement of public and public officials is moderate due to noncontroversial project type. General communication about project progress is required.
Stakeholders
A-137
MOST COMPLEX (MAJOR) PROJECTS Roadway New highways; major relocations. New interchanges Capacity adding/major widening. Major reconstruction (4R; 3R with multi-phase traffic control). Congestion Management Studies are required. Traffic Control Multi-phased traffic control for highway or bridge construction that would mandate CPM during construction. Major ITS (Electronic surveillance, linkages) corridor project. Structures Replacement, new or rehabilitation of: Unusual (non-conventional like segmental, cable stayed, major arches or trusses, steel box girders, movable bridges, etc.) Complex (sharp skewed [less than 70 degree] superstructure, nonconventional piers or abutments, horizontally curved girders, three dimensional structural analysis, non-conventional piles or caisson foundations, complex seismic analysis, etc.) Major (bridge cost of $5 million or moreFederal definition). Unusual formations (caissons, uncommon piles, mines, Karst situation). Right-of-Way Right-of-way plans are needed and numerous relocations of residences or displacement of commercial and/or industrial properties are required. A few to over 20 property owners are involved. Major involvement of environmental clean-up. Before and after analysis. Major utility (transmission lines, substations) relocations or heavy multiutility coordination is involved. Environmental Impact Studies are required or complex Environmental Assessment without mitigated finding of no significant impact. Studies of multiple alternatives. Continued public and elected officials involvement in analyzing and selecting alternates. Other agencies (such as FHWA, COE, PHMC, Game Commission, Fish & Boat Commission, DEP, DCNR, EPA, Agricultural Board, etc.) are heavily involved to protect air; water; games; fish, threatened and endangered species; cultural resources (historical, archaeological, parks, wetlands, etc), etc. Stakeholders Controversial (lack of consensus) and high-profile projects. (Fast track design/construction, high public impact, high interaction of elected officials, etc.) Major coordination among numerous stakeholders is required.
Utilities Environmental
stand that average interchange acreage requirements are frequently not an appropriate methodology for estimating the cost of the necessary takings. When estimating an interchange acreage requirement, consideration must be given to effects on utilities (water, sewer, gas lines, electric, cable, and beroptic lines), the need for space to accommodate utility relocations, and, often times, space for noise walls. The concepts developed for each interchange should be evaluated to identify engineering issues, environmental concerns, construction requirements, and maintenance requirements. The concepts developed should be evaluated for:
Acquisition of developed properties Reconstruction of other facilities Trafc operation issues on or into private property
A-138
Signicant acquisition of right-of-way from the protected
mat could be used to establish interchange reality check gures for both acreage and land cost.
If an ROW [right-of-way] acreage estimate is provided, that number is used. Otherwise, estimate ROW [is] needed according to type of project. For the regional Transportation Plan, two methods have been used in the past to estimate the ROW costs. The simplied method generally assumes a project is in a high (A), medium (B) or low (C-default) cost per acre area. A more complex method based on actual county auditor valuations for the adjacent parcels has also been used. For this study the simplied approach will be used. The three cost-per-acre categories are $620,000/ac, $235,000/ac and $75,000/ac. Other costs like utility relocation vary depending upon the individual project and are not included. The following ROW acreage assumptions are made based on the improvement type. ... Intersection Improvement:
facilities Why? Many state highway agencies have design guidelines that describe the elements of a typical highway interchange and required land area. Right-of-way estimates (including those for interchanges) that are prepared based on both typical acreage requirements and an average per-acre price are often inaccurate because they fail to consider impacting cost drivers and the fact that interchanges, while following standard designs, must almost always be tted into the unique physical setting of their locations. What Does It Do? This is a tool to help project managers and estimators appreciate the fact that as projects become more complex, there is a greater need for coordination and communication between the disciplines participating in the development of the projects design and estimate. This is particularly important in the case of initial right-of-way estimates for interchanges. In such a case, many more supporting groupsmultiple utility companies, agencies that grant environmental permits, construction, and maintenancemust be consulted before the area required for the interchange can be determined and the right-of-way cost estimated. When? This tool supports the estimate process for projects (new alignment or reconstruction) involving interchanges, either interchange-only projects or projects where interchanges are part of a large total scope. This tool should even be applied to projects where, during early planning, it is believed that no additional right-of-way will be required, because consultation with supporting sections (utilities relocation, environmental, and construction) may lead to a different conclusion. Examples The Mid-Ohio Regional Planning Commission issued a report, Historical and Projected Transportation Funding in Central Ohio, in 2004 (available online at http://transportation. morpc.org/tplan/nalTPlan04Funding.pdf). Section 5 of the report, Right-of-Way Costs, provides the following guidance for that region of the country. While the cost data are most likely not appropriate to state highway agencies, the for-
a) Turn lane 2 approaches Major Intersection: Minor Intersection: b) Turn lane 4 approaches Major Intersection: Minor Intersection: Interchange Upgrade: a) Basic Diamond/Partial Clover b) Complex with directional Ramp New Interchange: a) Basic Diamond or Partial Clover b) Complex with directional Ramp
5 acre 10 acre
30 acre 70 acre
For the right-of-way cost, project specic estimates are made. First, for each project the parcel(s) are identied through which ROW is needed. Second, using the county auditors data set, the cost per acre for each parcel is determined. The total ROW cost is calculated by multiplying the estimated ROW acreage and the cost per acre of the parcel. The minimum cost per acre is xed at $75,000.
Tips Based on a project description detailing the limits of all alternatives, a primary impact area should be established. This primary impact area identication should include work done during concept development, scoping, public involvement, and interagency coordination. Secondary impact areas, where applicable, should also be identied and discussed. A graphic detailing the primary and secondary impact corridor and proposed ROW limits should be developed. Another graphic should be developed mapping the existing land use and zoning within the primary impact area of each alternative. The graph-
A-139
ics should delineate industrial, commercial, single-family residential, multifamily residential, public and quasi-public uses, and vacant land. Pursuant to the Farmland Protection Policy Act of 1984 (FPPA) (Public Law 9798Subtitle I of Title XV, Section 15391549), all agricultural lands, dened as agricultural soils considered prime farmland soils, soils of statewide or local importance and unique soils, affected by the proposed action must be identied and quantied. The acreage of agricultural soils acquired by the proposed right-of-way must be determined. Additionally, it should be noted if this total exceeds 3 acres per mile of roadway improvements or 10 acres per interchange or intersection. The results of these calculations will be forwarded to the State Soil Conservation Service. Do not show proposed right-of-way during early project development. Look at the typical section width under the worst-case scenario with maximum right-of-way needed. In the conceptual plans, look at the existing constraints so that alternatives that limit right-of-way requirements (e.g., retaining walls or steeper side slopes) can be explored. Resources Florida DOT right-of-way estimation guidance can be found at www.dot.state..us/rightofway/documents/ROWmanual/ Acrobat%20les/ch06s03.pdf. Computer-aided design and drafting (CADD) systems use computer graphic technologies to design and map projects and to quickly consolidate many different design aspects, such as right-of-way maps, into a common database or base map. A 1999 U.S. General Accounting Ofce study found that 43 state highway agencies use CADD systems on more than half their projects. CADD-generated project right-of-way maps present an opportunity to enhance knowledge concerning required right-of-way requirements and to improve rightof-way estimation. Global positing systems (GPS) are used for mapping purposes. A 1999 U.S. General Accounting Ofce study found that 15 state highway agencies use these systems on more than half their projects. GPS-generated project right-of-way maps present an opportunity to enhance knowledge concerning required right-of-way requirements and to improve right-ofway estimation. The FHWAs Ofce of Real Estate Services has a Project Development Guide that contains a practical approach to project right-of-way. This document presents best practices of state and local agencies and others in the right-of-way eld. The guide can be found on the Internet at www.fhwa.dot.gov/ realestate/pdg.htm. Wisconsin DOTs document Design, Real Estate and Construction Delivery Estimates identies the portion of dollars that should be set aside for design, real estate, and con-
struction delivery. The document can be found at www. dot.wisconsin.gov/localgov/highways/docs/delivery.pdf. Estimates are derived by taking a certain percentage of actual real estate acquisition costs for real estate delivery or an actual percentage of total construction costs for design and construction delivery.
A-140
When? This tool should be used in the earliest stages of project development in order to avoid ination and escalating property values caused by development within the alignment of a corridor or project. It is a good tool for a limited number of parcels. However, in the case of a long corridor, its application is limited. Examples The Texas legislature has given the Texas DOT (TxDOT) the authority to acquire right-of-way to preserve a corridor. Both TxDOT and the FHWA understand that such an acquisition would not negate the requirement to complete NEPA. The I-69/Trans-Texas Corridor Project in Texas will be evaluated using a tiered approach. At Tier 1, corridor-level decisions will be made. After the Tier 1 right-of-way acquisition, TxDOT can acquire right-of-way at its own risk, knowing that when the Tier 2 NEPA evaluations are initiated, the ownership of the previously acquired right-of-way cannot and will not inuence the Tier 2 alternative location decision. Since the I-69/TTC corridor will be approximately 1,000 miles long, common sense would lead one to believe that only the parcels in eminent danger of being developed would be acquired. See the FHWAs March 2004 Environmental Streamlining Newsletter for more information on the I-69 project. Minnesota DOT (Mn/DOT) policy requires environmental documentation prior to purchase. Additional information can be found in Appendix J of Mn/DOTs Interregional Corridors: A Guide for Plan Development and Corridor Management (available online at http://www.oim.dot.state.mn.us/IRC-Guide. html). Also included is information on the environmental review and documentation process as it relates to right-of-way preservation. Mn/DOT also conducted a research project to identify circumstances under which it is optional to purchase right-ofway in advance and those in which it is not. The nal report of this research project, titled The Final Benefits of Early Acquisition of Transportation Right of Way, is available at http://www.research.dot.state.mn.us/detail.cfm?productID =1998. Improvements to Floridas Strategic Intermodal System (SIS), a statewide network of high-priority transportation facilities, envisions:
Acquisition of right-of-way for the future widening of I-595 Acquisition of right-of-way for the widening of I-4 Acquisition of right-of-way for future improvements to
Florida DOTs Right of Way Manual (effective April 15, 1999; acquisition revised December 11, 2000), Section 8.1 Advance Acquisition, can be found at www.dot.state.fl. us/rightofway/documents/ROWmanual/Acrobat%20files/ ch08s01.pdf. Tips Brief summary of the process. To use the protective purchase option (advance purchase), there must be at least a draft environmental document (which means that the initial public hearings must have been held). An individual categorical exclusion (CE) document will be required for the protective purchase. The state highway agency will ask the FHWA division ofce to review and approve a protective purchase package. The package will include (but may not be limited to) a CE document, copies of property valuation appraisals, preliminary design maps, and written justication for the protective purchase. If the FHWA division ofce concurs with the protective purchase, the approval will indicate that the state highway agency may incur costs that will be eligible for reimbursement at such time as a nal environmental document is approved. The state highway agency may use its own funds to make the purchase and request reimbursement from the FHWA after the nal environmental document is approved. There is the potential for a decrease in the value of abutting parcels (e.g., who would want to purchase a home in an area knowing that there is a major highway project planned?). Adjacent property owners could also demand compensation at this time, and there really is no appropriate way to compensate properties not within the corridor for a property value stigma associated with a nearby project. However, limited studies at Illinois DOT (IDOT) looking at the effect of highway improvements on adjacent property did not show evidence of property value decreases. IDOT often got comments from property owners who were not directly affected by right-of-way acquisition that the highway would damage them even though no right-of-way was taken from them. When sales prices of properties next to and away from a major highway were examined, it did not appear that the highway was a negative impact on property values. When using this tool, the agency may want to look at some examples in its area to see if properties next to major roadways sell for less than comparable properties a block or two away. A study conducted by a national realtors organization that surveyed 2000 homebuyers nationwide on what issues were most important in choosing a home location found that access to transportation infrastructure was cited most often (43%). Transfer of development rights. Some agencies have negotiated with property owners to transfer right-of-way dedi-
SR 79
Acquisition of right-of-way for future US 331 reconstruc-
A-141
cation for future roadways for increased development densities on remaining portions of the parcel. This enables the developer to get the same number of lots or units and also enables the agency to obtain the needed right-of-way. Resources The FHWAs Ofce of Real Estate Services has a Project Development Guide that contains a practical approach to project right of way. This document presents best practices of state and local agencies and others in the right-of-way eld. The guide can be found on the Internet at www.fhwa.dot.gov/ realestate/pdg.htm. The chapter covering advance purchases, 14 Specialized Acquisition Functions, is located at www. fhwa.dot.gov/realestate/specacq.pdf. Computer-aided design and drafting (CADD) systems use computer graphic technologies to design and map projects. They provide an expedient way to consolidate many different design aspects, such as right-of-way maps, into a common database or base map. A 1999 U.S. General Accounting Ofce study found that 43 state highway agencies use CADD systems on more than half their projects. CADD-generated project right-of-way maps present an opportunity to enhance knowledge concerning right-of-way requirements and to improve right-of-way estimation. Global positing systems (GPS) are used for mapping purposes. A 1999 U.S. General Accounting Ofce study found that 15 state highway agencies use these systems on more than half their projects. GPS-generated project right-of-way maps present another opportunity to enhance knowledge concerning right-of-way requirements and to improve right-of-way estimation. Also see the hardship/protective purchasing sections of the 23 Code of Federal Regulations. Specically, refer to Sections 23 CFR 630.106(c)(3), 23 CFR 710.503, and 23 CFR 771. 117(d)(12). See Texas DOTs Project Development Process Manual, 4410: Perform Advance Acquisition for Qualied Parcels, at http://manuals.dot.state.tx.us/dynaweb/coldesig/pdp/ @Generic_ BookTextView/18357;cs=default;ts=default.
What Is It? This is a tool to educate project managers and estimators as to the schedule impacts, which can affect the overall project estimate, and the direct right-of-way cost impacts of using condemnation to acquire right-of-way. When right-of-way must be secured by condemnation through eminent domain procedures, it typically involves the transition of control of the settlement from the agencys right-of-way department to its legal department. At that point, issues of time, cost, and jury process are relevant to establishing the estimated cost of the right-of-way parcel. Why? Because of the high costs and the potential for project delays, most right-of-way ofces make it a high priority to resolve and settle right-of-way parcel disputes before resorting to litigation, and a majority of the cases where condemnation proceedings have been initiated are settled before actually going to court. However, estimators must have an understanding of the potential necessity of resorting to condemnation proceeding to acquire right-of-way and of the cost consequences of such procedures. What Does It Do? This tool educates estimators about the direct and indirect cost of right-of-way acquisition, particularly the cost associated with condemnation proceedings, and the effect that condemnation proceedings can have on a projects time line. If a state highway agency is unable to agree with the owner on a price for a parcel of property, the agency les a condemnation suit and the court determines the propertys value. Other costs in many cases can include the landowners attorney fees, appraiser fees, technical expert fees, and relocation expenses if necessary. If the state takes a portion of a business property, it may also have to pay business damages for permanently lost prots and the reduced prot-making capacity of the business. Estimators need to understand these ramications of right-of-way cost in order to prepare accurate project estimates. When?
R2.3 Condemnation
Typically, right-of-way acquisition, especially in urbanized areas, includes other costs besides land purchase, such as costs related to takings, condemnations, relocations, damages, and courts. As a result, it is necessary to estimate these additional costs associated with actual acquisition of land needed for projects. From FY 91/92 to FY 94/95, Florida DOT had to initiate condemnation proceedings in 42.9% of its right-of-way parcel acquisition actions.
This tool should be a continuous estimator education process for all estimators who are involved in estimating the cost of right-of-way. The tool particularly supports early estimates developed when the exact project alignment is imprecise and right-of-way issues lack focus. Examples Oregon DOT (ODOT) holds statewide right-of-way meetings every 18 months, where all right-of-way staff meet for
A-142
training sessions and to share best practices with each other. In addition to formal training programs, individual training plans are prepared at the regional level and approved by central ofce as part of its business plan. Portions of the right-ofway manual are available online on a shared directory, and policy memos, clarications, and relocation meeting minutes called Andy-grams are frequently circulated and stored electronically. Something like this could be expanded to include training for right-of-way estimators. The AASHTO Right-of-Way and Utilities Subcommittee sponsors conferences addressing many of the subjects that right-of-way estimators need knowledge about. Tips Most areas of dispute involve severance damages to the remainder of the property, and business damages. Therefore, these issues must be fully understood when estimating rightof-way cost. Consider the effect that relocation has on a business. Does the business have specific requirements that may hinder relocation? When the right-of-way land requirement does not require all of an owners business property, other facts should be considered:
Will the proximity of the proposed facility affect the oper-
on more than half their projects. CADD-generated project right-of-way maps present an opportunity to enhance knowledge concerning right-of-way requirements and to improve right-of-way estimation. Global positing systems (GPS) are used for mapping purposes. A 1999 U.S. General Accounting Ofce study found that 15 state highway agencies use these systems on more than half their projects. GPS-generated project right-of-way maps also present an opportunity to enhance knowledge concerning right-of-way requirements and to improve right-of-way estimation. The FHWAs Ofce of Real Estate Services has a Project Development Guide that contains a practical approach to project right-of-way. This document presents best practices of state and local agencies and others in the right-of-way eld. The guide can be found on the Internet at www.fhwa.dot.gov/ realestate/pdg.htm. Also read Costs of Right-of-Way Acquisition: Methods and Models for Estimation, by Jared D. Heiner and Kara M. Kockelman, Journal Transportation Engineering, American Society of Civil Engineers, Vol. 131, No. 3, pp. 193204 (March 2005). Also see the American Association of Sate Highway and Transportation Ofcials, Standing Committee on Highways, Strategic Plan 4-4, Right-of-Way and Utilities Guidelines and Best Practices, Jan. 2004, http://cms.transportation.org/sites/ rightofway/docs/aabp%20report%20nal.pdf.
ations of any businesses, in terms of access disruption, or parking loss, which could result in loss of business? Will the proposed action disrupt current accessibility to businesses, thereby having a potential for loss of clientele? Resources The FHWA report, Evaluation of State Condemnation Process, summarizes the legal and procedural framework for acquiring real property for right-of-way, focusing on ve specic states. It provides information on the statutory authority and case law that is relevant to the acquisition of real property in each of those ve states. It reviews each states approach to negotiations and valuation, the use of alternative dispute resolution or other administrative procedures used to establish value, and the payment of the property owners attorney fees and related expenses. This FHWA report can be found at www.fhwa.dot.gov/realestate/cndmst.htm. Computer-aided design and drafting (CADD) systems use computer graphic technologies to design and map projects and provide an expedient way to consolidate many different design aspects, such as right-of-way maps, into a common database or base map. A 1999 U.S. General Accounting Ofce study found that 43 state highway agencies use CADD systems
A-143
acquisition to include relocation costs. The Uniform Act provides relocation payments for residential occupants and for businesses, farms, and nonprot organizations. These payments include moving expense payments and certain supplementary payments for replacement housing for residential occupants. In addition, the Uniform Act requires the availability of replacement housing for displaced persons, sets minimum standards for such housing, and requires notices and information to be provided to all property occupants. The law also requires that advisory services be provided to occupants so as to help them relocate successfully. Why? It is important to understand that the project schedule can be impacted by relocation actions and that there are indirect costs associated with securing right-of-way. Without the relocation of those occupying the project site, the project cannot proceed to actual construction and the schedule will be extended, thereby adding cost to the project. Estimators must understand the timing effects of relocation actions, particularly in relation to construction timing (midpoint of construction for estimation purposes), and the cost of relocation actions must be included in a project right-of-way cost estimate. What Does It Do? This tool seeks to educate estimators and project managers about the legal requirements that impact the right-of-way cost and the impact that relocation actions have on project schedule so that estimators and project managers can estimate project cost based on realistic schedules and can include all subsidiary (i.e., indirect) right-of-way costs in the estimate. When? This tool should be used when projects involve the relocation of individuals in residential properties or nonresidential relocations, businesses, farms, and nonprot organizations. One of the main purposes of the Uniform Act is to prevent affected persons from bearing an unfair share of the burden of public projects. The act provides relocation assistance payments in addition to relocation assistance advisory services. Relocation assistance payments are designed to compensate displaced persons for costs that result from acquisition of the property on which they reside. Examples Residential relocation payments are intended for persons who move (or move personal property) from a dwelling as a
result of a highway project receiving federal nancial assistance. These payments may be subdivided into three types:
Moving expense payments are designed to compensate for
the moving and related costs that a person incurs as a result of having to move from his or her dwelling or to move personal property for a project. Replacement housing payments are designed to help eligible displaced persons occupy housing that is decent, safe, sanitary, adequate for their needs, and comparable to what they had before the project required their move. There are three categories of replacement housing payments: purchase supplements, rental assistance, and down payment assistance. Housing-of-last-resort payments are payments in excess of statutory maximums or payments involving other, unusual methods of providing comparable housing. See the Caltrans brochure, Your Rights and Benets as a Displaced Business, Farm or Nonprot Organization Under the Uniform Relocation Assistance Program, on the Internet at www.dot.ca.gov/hq/row/pubs/business_ farm.pdf. Tips Consider the effect that relocation has on a business and answer the question, Does the business have specic requirements that may hinder relocation? Resources See the Uniform Relocation Assistance and Real Property Acquisition Policies Act of 1970 (Public Law 91-646), as amended (42 U.S.C. 4601 et seq.). Also see the Uniform Relocation Assistance and Real Property Acquisition for Federal and Federally Assisted Programs (49 CFR 24). Computer-aided design and drafting (CADD) systems use computer graphic technologies to design and map projects. They provide an expedient way to consolidate many different design aspects, such as right-of-way maps, into a common database or base map. A 1999 U.S. General Accounting Ofce study found that 43 state highway agencies use CADD systems on more than half their projects. CADD-generated project right-of-way maps present an opportunity to enhance knowledge concerning right-of-way requirements and to improve right-of-way estimation. Global positing systems (GPS) are used for mapping purposes. A 1999 U.S. General Accounting Ofce study found that 15 state highway agencies use these systems on more than half their projects. GPS-generated project right-of-way maps
A-144
also present an opportunity to enhance knowledge concerning right-of-way requirements and to improve right-of-way estimation. The FHWAs Ofce of Real Estate Services has a Project Development Guide that contains a practical approach to project right-of-way. This document presents best practices of state and local agencies and others in the right-of-way eld. The guide can be found on the Internet at www.fhwa.dot. gov/realestate/pdg.htm. The section on relocation is found at www.fhwa.dot.gov/realestate/relasst.pdf.
tor training tool should be standard practice to every state highway agency. However, it has been found that court costs are highly variable and are particularly high for projects in highly developed commercial corridors, where condemnation proceedings are common. Thus, the tool may be of greater benet to state highway agencies that regularly engage in urban commercial corridor projects. Examples An example of right-of-way estimation guidance can be found at www.dot.state.fl.us/rightofway/documents/ ROWmanual/Acrobat%20les/ch06s03.pdf. The FHWAs Ofce of Real Estate Services has a Right-ofWay Outreach and Program Research website (www.fhwa. dot.gov/realestate/research.htm), which lists available professional training and technical assistance. Tips Train estimators to red ag areas in proposed corridors (major streams, Federal Emergency Management Agency (FEMA) ood zones, residential and commercial structures, cemeteries, wetlands, historic properties, hazardous waste sites, parks, etc.) that can impact right-of-way cost. Also train estimators to recognize removal items that will impact right-of-way cost (trees, buildings, abandoned slabs, etc.). Revisit the right-of-way estimate as design proceeds and the construction limits are rened. Each time, identify total takes, relocations, and noise wall locations, and then check the cost estimate. Understand whether the acquisition process for compensating renters differs from the process for compensating property owners. Real estate sales prices along a corridor of several individual projects are affected by the order in which projects are accomplished. A study of residential property prices from 1979 to 1997 along an urban corridor in Texas revealed signicant price effects of the corridor improvement phases. During the pre-planning phase, housing prices in the immediate vicinity of the freeway were negatively affected, while those farther away were positively affected. During the planning phase, houses in the corridor appreciated at twice the rate of other Dallas properties. Prices declined more rapidly in the corridor than elsewhere in Dallas during the early construction phases. However, prices again improved during the nal construction phase, as sections of the freeway began to reopen and access improved. During the early phase of a project development, the rightof-way needs may not be dened clearly enough to differentiate between what will be a whole take and what will be a partial
and speculation that can occur between the time when the estimate is initially prepared (typically several years in advance of actual right-of-way acquisition) and when the parcels are purchased. Right-of-way estimates are prepared based on year of parcel purchase, not midpoint of construction. Account for the uncertainties associated with damages and court costs that result from condemnation proceedings. When? Because all state highway agencies are continually involved with projects requiring right-of-way, the right-of-way estima-
A-145
take. If it is helpful, cost estimates may be limited to whole parcel acquisition. Costs of partial acquisitions, including damages to the remaining properties and project overhead, can be factored into an estimate. Resources The Florida DOT right-of-way estimation guidance can be found at www.dot.state.fl.us/rightofway/documents/ ROWmanual/Acrobat%20les/ch06s03.pdf. Computer-aided design and drafting (CADD) systems use computer graphic technologies to design and map projects and provide an expedient way to consolidate many different design aspects, such as right-of-way maps, into a common database or base map. A 1999 U.S. General Accounting Ofce study found that 43 state highway agencies use CADD systems on more than half their projects. CADD-generated project right-of-way maps present an opportunity to enhance knowledge concerning right-of-way requirements and to improve right-of-way estimation. Global positing systems (GPS) are used for mapping purposes. A 1999 U.S. General Accounting Ofce study found that 15 state highway agencies use these systems on more than half their projects. GPS-generated project right-of-way maps also present an opportunity to enhance knowledge concerning right-of-way requirements and to improve right-of-way estimation. Executive Order (EO) No. 12898 (1994), Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations, requires that federal agencies be responsible for reviewing their programs and other activities to determine and prohibit any disproportionately high adverse effects on the human environments in low-income or minority communities. In the case of transportation projects, EO 12898 is implemented through the U.S. DOT and the FHWA. The U.S. DOT strategy ensures that the provisions of EO 12898 are integrated into the relevant existing guidelines used in the project planning and public participation processes. The FHWAs order requires that specic research and related data collection be conducted to provide information on environmental justice concerns. The FHWAs Ofce of Real Estate Services has a Project Development Guide that contains a practical approach to project right-of-way. This document presents best practices of state and local agencies and others in the right-of-way eld. The guide can be found on the Internet at www.fhwa.dot.gov/ realestate/pdg.htm. The Costs of Right of Way Acquisition: Methods and Models for Estimation is a paper presented at the 83rd Annual Meeting of the Transportation Research Board, January 2004. The paper reviews the literature related to right-of-way acquisition and property valuation. It describes the appraisal process
and the inuence of federal law on acquisition practices. It provides price models for estimation of costs associated with taking property using recent acquisition data from several Texas corridors and full-parcel commercial sales transactions in Texass largest regions. Results indicate that damages depend heavily on parking, access, and location. The size of the taking is not as important as the value of improvements, and utility costs are highly variable. This paper can be found at www.ce.utexas.edu/prof/kockelman/public _ html/ TRB04ROW.pdf. See the following federal laws governing acquisition:
The Uniform Relocation and Real Property Acquisition
et seq.)
Title VI of the Civil Rights Act of 1966 (42 U.S.C. 2000d
et seq.) Title VIII of the Civil Rights Act of 1968 (42 U.S.C. 3601 et seq.) as amended The National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) The Comprehensive Environmental Response, Compensation and Liability Act of 1980 (CERCLA or Superfund) as amended by the Superfund Amendments and Reauthorization The Superfund Amendments and Reauthorization Act of 1986 (SARA) (42 U.S.C. Section 9601 et seq.) Section 504 of the Rehabilitation Act of 1973 (29 U.S.C. 790 et seq.) The Flood Disaster Protection Act of 1973 (Public Law. 93-234) The Age Discrimination Act of 1975 (42 U.S.C. 6101 et seq.) Executive Order 11063: Equal Opportunity and Housing, as amended by Executive Order 12259 Executive Order 11246: Equal Employment Opportunity Executive Order 11625: Minority Business Enterprise Executive Order 11988: Floodplain Management Executive Order 11990: Protection of Wetlands Executive Order 12250: Leadership and Coordination of Non-Discrimination Laws Executive Order 12259: Leadership and Coordination of Fair Housing in Federal Programs Executive Order 12630: Governmental Actions and Interference with Constitutionally Protected Property Rights
A-146
with obtaining parcels and the details of acquisition law has led some agencies to establish a separate group of right-of-way estimators. What Is It? This tool is a group of individuals within the state highway agency who are specically trained in techniques for estimating right-of-way cost, who construct and maintain rightof-way cost models, and who have sole responsibility for estimating the right-of-way cost portion of a project estimate. This group of right-of-way estimators could be located in the agencys right-of-way, design, or estimation sections. Location in the agency structure is not as important as developing a group having the unique skills needed to accurately estimate right-of-way costs and who can mentor and support one another in this important task. Why? It is extremely important that individuals attempting to estimate the cost of right-of-way acquisition be intimately familiar with the applicable state laws and implementation regulations. Over the years, states have enacted eminent domain laws governing public acquisitions under their jurisdiction. Since the enactment of the Federal Uniform Relocation Assistance and Real Property Policies Act of 1970 (Uniform Act) and passage of the various state consent laws, basic public acquisition policy has become more uniform. However, a number of states have enacted laws and regulations that go beyond federal law and provide property owners with entitlements not considered generally compensatable under federal law. Therefore, those responsible for estimating the cost of right-of-way must possess knowledge concerning a unique set of rules and regulations and understand the lead time requirements that accompany the rules and regulations. Aside from property acquisition costs, estimators must also estimate the cost of utility relocations. These costs can run very high and may even exceed property acquisition costs. The current cost estimates for utility relocations required in the expansion of Interstate 10 in Houston, Texas, exceed $200 million. This represents a unit cost of $10 million per mile for this 20-mile project, or 30% of the right-of-way budget. What Does It Do? This tool ensures that the agency has individuals who are knowledgeable and specifically trained to prepare right-ofway cost estimates. Additionally, the tool provides the
agency with the staff personnel having the competencies to evaluate right-of-way cost estimates prepared by outside consultants. When? The establishment of separate right-of-way estimators could be of great benet to state highway agencies that regularly engage in urban commercial corridor projects. It has been found that court costs associated with acquiring right-of-way vary greatly and are particularly high for projects in highly developed commercial corridors. Examples Virginia DOT is currently doing right-of-way estimates through the right-of-way department, but is looking into making this task part of the in-house computer program. However, there has been some resistance because the right-of-way people feel that the computer cannot match the expert judgment that is required. Caltrans has realized that right-of-way funds to acquire parcels needed to construct the project are typically expended during the design phase. For this reason, it is the agencys policy to have close coordination with the right-of-way branch during the design phase of project development. Florida DOT has recommended the use of right-of-way cost estimation teams for certain projects. Guidance Document 2: Right of Way Cost Estimates (revised April 2004) states: It is suggested that the district consider appointment of a team to participate in the preparation of the estimate on large or complex projects. The document is available online at www. dot.state.fl.us/rightofway/documents/ROWmanual/ Acrobat%20les/guide2.pdf. Tips Real estate sales prices along a corridor of several individual projects are affected by the order in which projects are accomplished. A study of residential property prices from 1979 to 1997 along an urban corridor in Texas revealed signicant price effects of the corridor improvement phases. During the pre-planning phase, housing prices in the immediate vicinity of the freeway were negatively affected, while those farther away were positively affected. During the planning phase, houses in the corridor appreciated at twice the rate of other Dallas properties. Prices declined in the corridor more rapidly than elsewhere in Dallas during the early construction phases. However, prices again improved during the nal construction phase, as sections of the freeway began to reopen and access
A-147
improved. Right-of-way estimators need to be engaged in construction data based on such information to use as aids in preparing estimates. Resources Computer-aided design and drafting (CADD) systems use computer graphic technologies to design and map projects. They provide an expedient way to consolidate many different design aspects, such as right-of-way maps, into a common database or base map. A 1999 U.S. General Accounting Ofce study found that 43 state highway agencies use CADD systems on more than half their projects. CADD-generated project right-of-way maps present an opportunity to enhance knowledge concerning right-of-way requirements and to improve right-of-way estimation. Global positing systems (GPS) are used for mapping purposes. A 1999 U.S. General Accounting Ofce study found that 15 state highway agencies use these systems on more than half their projects. GPS-generated project right-of-way maps also present an opportunity to enhance knowledge concerning right-of-way requirements and to improve right-of-way estimation. Executive Order (EO) No. 12898 of 1994, Federal Actions to Address Environmental Justice in Minority Populations and Low-Income Populations, requires that federal agencies be responsible for reviewing their programs and other activities to determine and prohibit any disproportionately high adverse effects on the human environments in low-income or minority communities. In the case of transportation projects, EO 12898 is implemented through the U.S. DOT and the FHWA. The U.S. DOT strategy ensures that the provisions of EO 12898 are integrated into the relevant existing guidelines used in the project planning and public participation processes. The FHWAs order requires that specic research and related data collection be conducted to provide information on environmental justice concerns. The FHWAs Ofce of Real Estate Services has a Project Development Guide that contains a practical approach to project right-of-way. This document presents best practices of state and local agencies and others in the right-of-way eld. The guide can be found on the Internet at www.fhwa.dot.gov/ realestate/pdg.htm. The Costs of Right of Way Acquisition: Methods and Models for Estimation is a paper presented at the 83rd Annual Meeting of the Transportation Research Board, January 2004. The paper reviews the literature related to rightof-way acquisition and property valuation. It describes the appraisal process and the inuence of federal law on acquisition practices. It provides price models for estimation of costs associated with taking property using recent acquisition data
from several Texas corridors and full-parcel commercial sales transactions in Texas largest regions. Results indicate that damages depend heavily on parking, access, and location. The size of the taking is not as important as the value of improvements, and utility costs are highly variable. See also the following research:
Bufngton, J. L., M. K. Chui, J. L. Memmott, and F. Saad
(1995). Characteristics of Remainders of Partial Takings Significantly Affecting Right-of-Way Costs. TXDOT Research Report. FHWA/TX-95/1390-2F. Carey, J. (2001). Impact of Highways on Property Values: Case Study of the Superstition Freeway Corridor. FHWA Report No. FHWA-AZ-01-516. Gallego, A. V. (1996). Interrelation of Land Use and Trafc Demand in the Estimation of the Value of Property Access Rights. Thesis for Masters of Science in Civil Engineering, the University of Texas at Austin. See also the following federal laws governing acquisition:
The Uniform Relocation and Real Property Acquisition
Policies Act of 1970 (42 U.S.C. 4801 et seq.) Section I of the Civil Rights Act of 1866 (42 U.S.C. 1982, et seq.) Title VI of the Civil Rights Act of 1966 (42 U.S.C. 2000d et seq.) Title VIII of the Civil Rights Act of 1968 (42 U.S.C. 3601 et seq.) as amended The National Environmental Policy Act of 1969 (42 U.S.C. 4321 et seq.) The Comprehensive Environmental Response, Compensation and Liability Act of 1980 (CERCLA or Superfund) as amended by the Superfund Amendments and Reauthorization The Superfunds Amendment and Reauthorization Act of 1986 (SARA) (42 U.S.C. Section 9601 et seq.) Section 504 of the Rehabilitation Act of 1973 (29 U.S.C. 790 et seq.) The Flood Disaster Protection Act of 1973 (Public Law. 93-234) The Age Discrimination Act of 1975 (42 U.S.C. 6101 et seq.) Executive Order 11063: Equal Opportunity and Housing, as amended by Executive Order 12259 Executive Order 11246: Equal Employment Opportunity Executive Order 11625: Minority Business Enterprise Executive Order 11988: Floodplain Management Executive Order 11990: Protection of Wetlands Executive Order 12250: Leadership and Coordination of Non-Discrimination Laws
A-148
Executive Order 12259: Leadership and Coordination of
What Is It? In the context of cost estimation, this tool quanties project risk and uncertainty to provide a better understanding of contingency and the ultimate project cost. It involves evaluation of risks in terms of their likelihood of occurrence and their probable consequences. Likelihood of occurrence and the associated consequences can be expressed qualitatively or quantitatively. If risks can be quantied, they can provide for a better understanding of project uncertainty and assist in the cost estimation management process. Risk analysis can be done through qualitative or quantitative procedures. In a qualitative analysis process, the project team assesses each identied risk (see also Tools I2.1 and I2.2) for its probability of occurrence and its relative magnitude of impact on project objectives. Quite often, experts or functional unit staff assess the risks in their respective elds and share these assessments with the project team. The risks are then sorted into high, moderate, and low risk categories (in terms of time, cost, and scope). The objective is to rank each risk by degree of probability and impact. The rationale for the decision should be documented for future updates, monitoring, and control. Quantitative risk analysis procedures employ numeric estimates of the probability that a project will meet its cost and time objectives. It is common to simplify a risk analysis by calculating the expected value or average of a risk. The expected value provides a single quantity for each risk that is easier to use for comparisons. While this is helpful for comparisons and ranking of risks, estimators must take care when using the expected value to calculate project costs or contingencies. For example, if there is a 20% chance that a project will need a $1 million storm water upgrade, the estimator will include $200,000 in contingency using the expected value. If the storm water upgrade is required, this value will not be enough. Unfortunately, a great deal of information is lost in this oversimplied contingency analysis. More comprehensive quantitative analysis is based on a simultaneous evaluation of the impact of all identied and quantied risks. The result is a probability distribution of the projects cost and completion date based on the risks in the project. Quantitative risk analysis involves statistical simulations and other techniques from the decision sciences. Tools commonly employed for these analyses include rst-order second-moment (FOSM) methods, decision trees, and/or Monte Carlo simulations. Why? Highway project delivery is a complex task that is fraught with uncertainty. Traditional methods of cost estimation often overlook risks or deal with them in a deterministic manner. Using the analysis of uncertainty and other risk tools in the cost
Risk identication Risk analysis (qualitative and/or quantitative) Risk mitigation planning Risk monitoring and control
Risk identication and risk mitigation planning are discussed in the Tools I2.1 and I2.2. Risk analysis and risk monitoring and control are discussed in Tools R3.1, R3.2, R3.3, R3.4, and R3.5. Additionally, communication of risk analysis results is discussed in Tool C1.2. When used together, these eight tools support a comprehensive risk management process. The tools presented in this section provide a better understanding of project uncertainty and application of contingency. The process can also assist in the contingency resolution process as the project scope, design, and delivery methods become fully dened.
R3.1 Analysis of Risk and Uncertainty (Also See C1.2 and I2)
Analysis of risk and uncertainty involves the quantication of identied risks. In a comprehensive risk management process, risk analysis is used to prioritize the identied risks for mitigation, monitoring, and control purposes. In the context of cost estimation, risk analysis can be extremely helpful for understanding project uncertainty and setting appropriate contingencies. Risk analysis can be done through qualitative or quantitative methods.
A-149
estimation process has many advantages. Federal Transit Administrations 2004 Risk Assessment Methodologies and Procedures mentioned several advantages:
Better understanding of the project delivery process, includ-
ing timelines and phasing, procedural requirements, and potential obstacles. More realistic estimates of individual component costs and durations, thereby allowing more reasonable expectations of total project cost and duration. Better understanding of what the project contingency is, whether it is sufcient, and for what it may need to be used. Information support to other project or agency activities, such as value engineering and strategic planning. Potential to improve the project budget and scheduling processes, possibly for the immediate project in development but certainly for future projects.
The Caltrans example demonstrates a sound process for qualitative risk analysis. The outcome of the qualitative analysis is typically a ranked list of risks that can be used as red ag items or in a risk charter. Quantitative analysis typically begins with a process that is similar to the quantitative analysis shown above, but then applies a direct and more accurate assessment of probability and impact and incorporates these assessments into a probabilistic cost-risk model. The goal of the quantitative risk analysis is to create a probabilistic cost-risk model to represent the uncertainties affecting project cost and schedule. It ultimately identies a likely range of costs or durations that bracket potential risk cost or schedule impacts. Examples of range estimates are provided in Tools R3.4 and R3.5. Tips Conduct the risk analysis early in the project development process. Involve a multidisciplinary team to conduct the risk analysis. The team may benet from outside experts to generate the list of risks and assist in the analysis. If a project requires a quantitative risk analysis, consult expert modelers. Most state highway agencies do not have in-house capabilities for performing quantitative risk analyses. Resources Caltrans Ofce of Project Management Process Improvement (2003). Project Risk Management Handbook. www.dot. ca.gov/hq/projmgmt/documents/prmhb/project _ risk_ management_handbook.pdf. Federal Transit Authority (2004). Risk Assessment Methodologies and Procedures. Project Management Oversight under Contract No. DTFT60-98-D-41013. Federal Highway Administration (2004). Major Project Program Cost Estimating Guidance. http://www.fhwa.dot.gov/ programadmin/mega/cenal.htm. Grey, S. (1995). Practical Risk Assessment for Project Managers. John Wiley and Sons, Chichester, England. Molenaar, K. R. (2005). Programmatic Cost Risk Analysis for Highway Mega-Projects, Journal of Construction Engineering and Management, Vol. 131, No. 3. Project Management Institute (2004). A Guide to Project Management Body of Knowledge (PMBOK Guide). Washington State DOTs Cost Estimating Validation Process (CEVP) website: www.wsdot.wa.gov/Projects/ ProjectMgmt/RiskAssessment.
What Does It Do? This tool quanties the impact of potential risks in terms of their consequences to cost and schedule estimates. It provides a systematic evaluation of project uncertainty. It assists estimators in setting appropriate contingencies and assists project managers in controlling project cost, schedule, and scope issues that can arise from uncertain or risky events. When? Risk analysis can be used throughout the project development process. At the earliest stages of project development, risk analysis will be helpful in developing an understanding of project uncertainty and in developing an appropriate project contingency. As the project progresses through the development process, risk analysis can be used in a comprehensive risk management monitoring and control process to assist in managing cost escalation resulting from either scope growth or the realization of risk events. Examples California DOT (Caltrans) has documented a qualitative risk analysis procedure in its 2003 Project Risk Management Handbook. The Caltrans process is largely based on the Project Management Institutes 2004 A Guide to Project Management Body of Knowledge (PMBOK Guide). The Caltrans handbook calls for a quantitative assessment of project risk items representing the highest degree of exposure. This quantication is important for updating the contingency amount to be included in the project estimate. Figure R3.1 shows the Caltrans process, published as Appendix C of the handbook, as an example of a qualitative risk analysis method.
R3.2 ContingencyIdentied
The standard state highway agency method for assigning contingency has been to either follow standard percentages for
A-150
A-151
A-152
the varying stages of project development or to rely solely on the project estimators experience. The enumeration and qualitative assessment of a projects contributor risks offers a more effective method for determining project contingency than does the standard state highway agency practice of broad-based percent add-on contingency amounts. Attention to technical complexities, construction execution, and the macroenvironment focuses estimator attention on project risks. What Is It? This tool creates a process whereby the contingency amount included in an estimate is set on the basis of identied risks and the probability of their occurrence. This tool should ideally be used in conjunction with a comprehensive risk management process. When this tool is used in conjunction with a qualitative risk assessment, the contingency is set using the cost estimators judgment and the information generated from the risk identication and analysis process, and the contingency is in compliance with state highway agency policy. When this tool is used in conjunction with a quantitative risk analysis, the contingency is set using an acceptable condence interval for the project (i.e., the difference between the 50% and 80% condence intervals of a range estimate). Cost estimation methods and tools must be understood in terms of the design denition (i.e., detail) available during the various phases of project development. More generally, at any stage in the development of a highway project, cost estimates
will be composed of three components for which there are different amounts of information: Known/Knowns (known and quantiable costs), Known/Unknowns (known but not quantied costs), and Unknown/Unknowns (as yet unrecognized costs); these concepts are illustrated in Figure R3.2-1. Note that in this gure the contingency cost component extends into the known/known cost percentage. Also note that in this gure, at the Advertise & Bid point, there still will be the potential for unrecognized costs (a very small gap) and known but not quantied costs (a small gap). Only when construction is completed are all costs known. All too often, if the cost of an item is not known, it is not included in early project cost estimates. There is also opportunity for other items (e.g., environmental or construction inspection costs) to be entirely left out of early estimates. The costs associated with the three componentsknown/knowns, known/unknowns, and unknown/unknownsrequire different methods and tools to dene and quantify their possible contribution to the estimate at any particular time in the project development process. Figure R3.2-2 illustrates how identifying, quantifying, and managing cost and schedule uncertainty relates to rening the cost estimate (i.e., managing the nal project cost). This gure illustrates two crucial points that apply to situations where the scope is unchanged and where an estimate, at some early stage in the design process, has included uncertainty. The rst point is that the range of cost or schedule uncertainty should
A-153
decrease as a project proceeds from concept to nal design. Estimate accuracy improves as design develops, cost variables are better dened, and uncertainty is eliminated. The second point is that if the uncertainties included in the estimate, as a contingency amount, in the early stages of project design materialize, then the estimated total will still be as expected. However, as risk management and other cost control processes are applied to the identied uncertainties, it is often possible to mitigate risks (i.e., contingency costs) and deliver the project at a lower cost. The Association for the Advancement of Cost Engineering International (AACEI) has developed a cost estimate classication system that denes ve estimate classications. This system, shown in Table R3.2, provides an expected range of accuracy for each project development phase. A Class 5 estimate is prepared at the earliest stage of project denition, and a Class 1 estimate is prepared closest to complete project definition and nal design. Table R3.2 also describes the methodological approach to the estimate as either stochastic or deterministic, depending upon the level of design and information available. A deterministic estimate contains no random variables, while a stochastic estimate contains one or more random variables. The result of a deterministic estimate is a single point of total cost, while the result of a stochastic estimate is a range of total cost. The AACEI recommends that Class 1 through 3 estimates be developed primarily as sto-
chastic estimates, which are not commonly employed by state highway agencies, but are being described in this section on risk analysis. Why? The identication of project risks gives the estimator a much rmer basis for developing a reliable contingency amount than the typical top-down assignment of a percentage based on the estimated direct cost of the project. What Does It Do? Because risks are specically delineated as a project is developed, specic strategies can be implemented to mitigate, transfer, or avoid signicant risks. In addition, with the risks identied and quantied, control and tracking procedures can be implemented to monitor risk items on an ongoing basis. These concepts are more fully explained in Section R3.5. When? The tool should be employed early, and risks should be tracked throughout the project development process. Projects of an unusual or complex nature require a more in-depth evaluation of potential risks and their effect on estimated cost.
Methodology
Typical estimation method
Screening or Feasibility Concept Study or Feasibility Budget, Authorization, or Control Control or Bid/ Tender Check Estimate or Bid/Tender
Stochastic or Judgment Primarily Stochastic Mixed, but Primarily Stochastic Primarily Deterministic Deterministic
Class 2 Class 1
Adapted from the Association for the Advancement of Cost Engineering Internationals AACE International Recommended Practice No. 17R-97: Cost Estimate Classification System, 1997.
The opportunities to expand the identication and quantication of risks should be pursued as design progresses and as more is known about potential exogenous risk factors. Examples The Cost Estimating Validation Procedure (CEVP) developed by the Washington State DOT (WSDOT) is a peer-level review on the scope, schedule, and cost estimate for transportation projects throughout the state of Washington. The objective of the CEVP is to evaluate the quality and completeness, including anticipated uncertainty and variability, of the projected cost and schedule. The outcomes of the CEVP include:
An estimate validation statement in the form of a CEVP
The Federal Transit Administration commissioned a report on risk assessment technologies and procedures that discusses the application of risk-based contingency. The report is titled Risk Assessment Methodologies and Procedures. The Regional Transportation District (RTD) in Denver, Colorado, is also employing a risk-based contingency process to its Fastracks transit program. See Denver RTDs 2006 Risk Assessment Quantification, available online at www.rtd-denver.com/ fastracks/documents/SB_208_Submittal/Risk_Analysis.doc. Tips To successfully attack the effects of project risk, risk analysis must take a broad view of risk; concentrating on only the technical risks can lead to oversights in other project dimensions. The analysis should consider local authority/agency impacts, industry and market risks, elements of political uncertainty, and public and/or permit approval processes that might impact timing. Scope changes must also be considered from a broad perspective. Identication of risk goes beyond the internal project risks (such as pile driving depth) and includes exogenous factors (such as market conditions, business environment, global construction activities/demand, the macroeconomic environment, and weather). Namely, any major uncertainties that might inuence the primary project outcomes of cost, schedule, or quality should be included. Resources Association for the Advancement of Cost Engineering International (2004). AACE International Recommended Practice No. 10S-90: Cost Engineering Terminology. http:// www.aacei.org/resources/rp.shtml.
project summary sheet that represents the project cost ranges and the uncertainty involved (see Section C1.2). Findings and recommendations that allow WSDOT project teams and senior management to better understand the basis, content, and variability of cost estimates. Identication and characterization of the high-risk project elements (this outcome will allow project teams to address appropriate mitigation strategies). The CEVP is also discussed in Sections C1.2, I2.2, R3.4, and R3.5. The Caltrans Risk Management Handbook calls for a quantitative assessment of project risk items representing the highest degree of exposure. This quantication is important for updating the contingency amount to be included in the project estimate. The handbook is available online at www.dot.ca.gov/ hq/projmgmt/documents/prmhb/project_risk_management _ handbook.pdf.
A-155
Caltrans Ofce of Project Management Process Improvement (2003). Project Risk Management Handbook. www.dot. ca.gov/hq/projmgmt/documents/prmhb/project_risk_ management_handbook.pdf. Denver Regional Transportation District (2006). Risk Assessment Quantication. www.rtd-denver.com/fastracks/ documents/SB_ 208_ Submittal/Risk_ Analysis.doc. Federal Transit Administration (2004). Risk Assessment Methodologies and Procedures, Report for Contract No. DTFT60-98-D-41013. Federal Highway Administration (2006). Price Trends for Federal-Aid Highway Construction. www.fhwa.dot.gov/ programadmin/pricetrends.htm. Federal Highway Administration (2004). Major Project Program Cost Estimating Guidance. http://www.fhwa.dot. gov/programadmin/mega/cenal.htm. Owen, P. A., and J. K. Nabors (1983). Quantifying Risks in Capital Estimates, AACE Transactions, B.5.1-B.5.7. Stevenson, J. J. (1984). Determining Meaningful Estimate Contingency, Cost Engineering, AACE International, Vol. 26, No. 1. Washington State DOT (2006). Cost Estimating Validation Process (CEVP) website, www.wsdot.wa.gov/Projects/ ProjectMgmt/RiskAssessment.
direct cost with the percentage being established by analysis of historical cost experience from past projects. Why? At any stage in the development of a project, cost estimates will be composed of three components for which there are differing amounts of information: Known/Knowns (known and quantiable costs), Known/Unknowns (known but not quantied costs), and Unknown/Unknowns (as yet unrecognized costs). These components are illustrated in Figure R3.2-1. What the contingency amount is supposed to account for is the total of the Known/Unknowns and Unknown/ Unknowns of the estimate. What Does It Do? A contingency allowance included in an estimate is meant to provide funds for cost growth resulting from necessary but unforeseeable project scope changes, underestimation of real project costs, or errors in projecting the rate of ination. Increases in the prices for construction servicesination are not to be considered covered by the contingency amount. Ination should be handled by applying an appropriate ination rate to the calculated project cost (see Section E3.5). When? Contingency amounts, added to an estimate, are a valid means of reflecting the uncertainties that remain to be defined as design progresses. A contingency amount should be included in every project estimate from the earliest planning stage of project development to the final PS&E; however, as shown in Figure R3.2-1, the magnitude of the contingency amount decreases as the scope is defined and the design progresses. Examples Many state highway agencies use standard percentages, such as the percentages in Table R3.3-1, to develop estimate continTable R3.3-1. One state highway agencys graduated conceptual estimate contingency scale.
Project Value
$0 - $1,000,000 $1,000,000 - $5,000,000 $5,000,000 - $25,000,000 $25,000,000 +
R3.3 ContingencyPercentage
As depicted in Figures R3.2-1 and R3.2-2 and Table R3.2, contingency percentages should decrease from the early stages of project development through final design. This theoretical idea of contingency has led some state highway agencies to apply fixed contingencies that decrease with project development milestones. However, it is poor policy to use fixed allowances for contingencies without good reasons. So even if the contingency amounts included in an estimate are justified based on published tables of practice, they still should be documented in writing. This requirement for documentation becomes even more important when fixed allowances or guide ranges for contingency are not followed. If extraordinary conditions exist that call for higher contingencies, the rationale and basis must be documented in the estimate. What Is It? Recognizing that cost estimation is inherently difcult because estimators are trying to predict the future, it is prudent to provide contingency allowances in the estimate. These contingency allowances represent the typical cost escalation experienced on similar projects as design progresses. The contingency amount can be set as a percentage of the projects
Conceptual Contingency
11.0% 9.5% 7.0% 6.0%
A-156
gency amounts. Historical experience shows that state highway agencies can establish contingency percentages to be applied to an estimates direct cost, but research shows that, in many cases, the applied percentages do not reect actual conditions. State highway agencies should only use the percentage contingency approach for projects that are similar in character to a large number of past projects for which good cost data are available. Table R3.3-2 is a summary of guidance on contingency in Chapter 20 of the Caltrans Project Development Procedures Manual (available online at http://www.dot.ca.gov/hq/oppd/ pdpm/pdpmn.htm). The table is offered as guidance for a graduated contingency. However, it should be noted that Caltrans also offers guidance on applying risk-based contingency when appropriate, as described in Sections R3.1 and R3.2. Tips When a state highway agency chooses to establish an estimate contingency by means of the relationship between contingency amount and project direct cost, two steps are needed to make the process work effectively: 1. The purpose of the contingency amount needs to be carefully dened. Estimators and management must understand that the contingency is intended to account for very specic unforeseen, unexpected, unidentied, or undened costs. The project risks that cause the occurrence of these costs must be delineated in the state highway agencys estimation manual with the percentages. Examples of risk factors early in design are provided in Sections I2.1 and I2.2. Examples of possible risk factors near the nal design period include: Number of bidders: The availability of contractors willing to bid the work will affect the bid prices. Caltrans has found that, for projects in the $1 million to $10 million range, if there is only one bidder, the price will on average be 5% above the engineers estimate, and the effect of each additional bidder is a 2% reduction in bid price compared with the state highway agency estimate.
Table R3.3-2. Caltrans graduated conceptual estimate contingency scale.
Design/Estimation Milestone Project Feasibility Cost Estimate Project Study Report Cost Estimate Draft Project Report Cost Estimate Project Report Cost Estimate Preliminary Engineers Cost Estimate Final Engineers Cost Estimate Percent Contingency 30% to 50% 25% 20% 15% 10% 5% or less
of risk by contractors vary widely, but underground work will normally increase a contractors bid because of geotechnical unknowns. For one-of-a-kind projects, contractors will apply more risk to their bid. Construction unknowns: This risk factor might be addressed with a reserve to cover construction change orders due to differing site conditions and other construction issues. Quality of construction documents (plans and specications): Incomplete or inadequate construction documents add to project management difculties and usually result in an increased number of change orders. Contracting method: A range of risk management strategies affect project cost, risk transfer, risk reduction, and even nancial treatments. Using lump sum or even unit price contracts to transfer risk to a contractor when project complexities exist that cannot be completely addressed until construction commences will add cost to the project. The constructor will add higher overhead and prot markup to the bid, and there will still be difcult-to-resolve change orders. Material price escalation: Sometimes material price escalation is carried in the individual items of the estimate, and sometimes it is supposed to be part of the estimate contingency. The proper accounting should be dened in the state highway agencys estimation manual. 2. The established contingency percentages should be based on actual experience (i.e., historical data). It is important for both the state highway agency estimators and state highway agency management to know the level of accuracy achieved with the prescribed contingency percentages. Statistical analysis of past projects provides a means for measuring that accuracy and adjusting the employed percentages. Resources FHWA (2004). Contingency Fund Management for Major Projects. www.fhwa.dot.gov/programadmin/mega/ contingency.htm. FHWA (2004). Major Project Program Cost Estimating Guidance. www.fhwa.dot.gov/programadmin/mega/ cefinal.htm. Chapter 20 of the Caltrans Project Development Procedures Manual, http://www.dot.ca.gov/hq/oppd/pdpm/pdpmn.htm. Caltrans Ofce of Project Management Process Improvement (2003). Project Risk Management Handbook. www.dot. ca.gov/hq/projmgmt/documents/prmhb/project_risk_ management_handbook.pdf. Caltrans (1998). State Administrative Manual, Chapter 6000, Section 6854: CONSTRUCTION. http://sam.dgs.ca.gov/TOC/ 6000/6854.htm.
Adapted from Chapter 20 of the Caltrans Project Development Procedures Manual (available online at http://www.dot.ca.gov/hq/oppd/pdpm/pdpmn.htm).
A-157
U.S. Army Corps of Engineers. Military Program-Specic InformationREF8011G, http://bp.usace.army.mil/robo/ projects/pmbp_manual/PMBP_Manual/REF8011G.htm. Uppal, Kul B. (Ed.) (2005). Professional Practice Guide #8: Contingency (CD), Association for the Advancement of Cost Engineering (AACE) International. http://www.aacei.org/ technical/ppg.shtml.
are appropriate given the estimates precision. A range estimate can help to convey the uncertainty of an estimate. Estimates derived from probabilistic methods (i.e., range cost estimates) better convey the uncertain nature of project costs at the conceptual phase of project development and even during later project development phases. What Does It Do?
The communication of a range of values representing the possible array of ultimate project costs creates a better understanding of estimate precision. The range does not necessarily represent the very least or the very most that the project will cost, but typically the most probable range of project costs. The size of the range will be determined by the identied uncertainties and the modeling method. The interpretation of the range depends on how aggressive the agency is with the results. For example, the agency can set the budget conservatively at a 90% condence interval, meaning that the nal project cost should be less than the budget nine out of ten times. Currently, many agencies communicate project costs in a single-point value that includes a contingency. The use of a point estimate early in the project development process can lead to a false sense of precision and accuracy because even the best engineers cannot predict all future events that can and will impact a projects cost. The inability to provide a 100% accurate estimate can, in turn, be negatively viewed by opponents to the agency or project. Through use of an estimate range, the agency can convey the uncertainty that is inherent in the project and educate other parties about cost variability. This is also helpful within the agency to demonstrate the uncertainty about the project to other personnel who may not be intimately familiar with the project. When? Ranges may be considered throughout project development, but they should be used on projects in earlier stages of development to communicate the level of project knowns and unknowns about the project. Examples The Washington State DOT (WSDOT) has developed a risk-based approach to cost estimation in its Cost Estimating Validation Process (CEVP). The CEVP is used to convey project cost through estimate ranges. Figure R3.4-2 provides an example of how CEVP is used to convey an estimate range in the form of probability densities. The project represented has a 10% chance of being completed for $651 million or less, while there is a 90% chance that the project will cost $693 million or less. However, there is a chance that the project will cost as little as $640 million and as much as $720 million.
x, Project Cost
A-158
Figure R3.4-2. Estimate range (presented as a probability density function) generated through WSDOTs Cost Estimating Validation Process (CEVP).
WSDOT also uses the CEVP to present cost estimate ranges in a tabular fashion rather than a probability density function. Figure R3.4-3 is an example of how WSDOT is communicating the ranges of possible project costs for the Alaskan Way Viaduct and Seawall Replacement Project. The tabular presentation is used to present multiple ranges for multiple design
options. Figure R3.4-3 also conveys how the estimates have changed during 2 years of project development. California DOT (Caltrans) uses three-point estimates for some elements of project costs and is planning to make wider use of this technique. Figure R3.4-4 shows the type of estimate generated by this technique. Although the math may appear
Figure R3.4-3. Estimate range (presented as a table) generated through WSDOTs Cost Estimating Validation Process (CEVP).
A-159
Most Probable Cost (m)
Tips While estimate ranges transparently convey the uncertainty involved in a project, they can be misunderstood. The range theoretically shows the highest possible cost for a project. If people focus on the high end of the range, the project can be slowed or stopped. The range should be used as part of a comprehensive risk management plan. If the risks and uncertainties that are driving the range can be understood, they can likely be mitigated and the project can be completed at a cost that is substantially less than the lower end of the range. Resources Federal Transit Administration (2004). Risk Assessment Methodologies and Procedures, Report for Contract No. DTFT60-98-D-41013. FHWA (2004). Major Project Program Cost Estimating Guidance. http://www.fhwa.dot.gov/programadmin/mega/ cenal.htm. Molenaar, K. R. (2005). Programmatic Cost Risk Analysis for Highway Mega-Projects, Journal of Construction Engineering and Management, Vol. 131, No. 3, American Society of Civil Engineers. Project Management Institute (2004). A Guide to Project Management Body of Knowledge (PMBOK Guide). Washington State DOT (2006). Cost Estimating Validation Process (CEVP) website, www.wsdot.wa.gov/Projects/ ProjectMgmt/RiskAssessment.
complex at rst glance, it is easy to implement with a simple spreadsheet. The three-point estimation process uses the following steps: 1. Have subject matter experts develop three estimates for each item of work: a) An optimistic estimate (o): The lowest credible cost assuming that everything goes right. b) A most-likely estimate (m): The experts best guess of the cost. c) A pessimistic estimate (p): The highest credible cost, assuming that virtually everything goes wrong. 2. The average cost of the item is (o + 4m + p)/6. The average is always greater than the most likely estimate. This is because there is a nite lowest-possible cost. Even in the most optimistic situation, the work package will have a cost that is greater than zero. At the other end of the scale, there is no highest possible cost. It is always possible to spend more money. 3. The standard deviation for the item, derived from the principle that 95% of events occur within two standard deviations of the mean, is: i = ( p o) 4 4. The standard deviation for the combination of all items in the project is:
2 2 2 2 project = ( i1 + i2 + i3 + . . . in ) 0.5
5. The cost estimate for the project is the sum of the average costs for the items. Caltrans gives the highest credible cost as the cost estimate plus three standard deviations (3 project). Using three standard deviations rather than two allows for the skewed nature of the probability density function.
A-160
It involves risk identication, risk analysis, risk mitigation and planning, and risk monitoring and control. It systematically combines all of the risk identication, analysis, and communication tools described in this guide (see Sections C1.2, I2.1, I2.2, R3.1, R3.2, R3.3, and R3.4). A successful cost risk analysis program has the following characteristics:
Feasible, stable, and well-understood user requirements A close relationship with user, industry, and other appro-
development, the tool supports the contingency resolution process though active monitoring and control. Examples California DOT (Caltrans) has developed a comprehensive risk management process and documented it in Caltranss 2003 Project Management Risk Management Handbook. The Caltrans process is largely based on the Project Management Institutes Guide to Project Management Body of Knowledge (PMBOK Guide). In the Caltrans process, the project team completes the risk management plan before the project initiation document (PID) component ends. The team updates the plan in each subsequent lifecycle component and continues to monitor and control risks throughout the life of the project. Figure R3.5 shows the process owchart. Table R3.5-1 shows the two main process tasks, the four subtasks, and all of the deliverables associated with project risk management. Table R3.5-2 shows all of the process tasks and the roles associated with each task. Caltrans has summarized its process into a risk management plan worksheet. The worksheet is available in Microsoft Excel format. It is intended to act as a risk charter for the process (see Section I2.2). The worksheet provides a tool to organize risks from the risk identication process. It provides a color-coded function for conducting qualitative risk assessments. It also provides space for inputting the results of a quantitative risk assessment. Additionally, the risk management planning worksheet provides tracking mechanisms for risk mitigation strategies as well as risk monitoring and control. An electronic version of this sample spreadsheet is available on the project management guidance website at www.dot.ca.gov/hq/ projmgmt/guidance_prmhb.htm. Washington State DOT (WSDOT) developed the Cost Estimating Validation Process (CEVP) to assist in evaluating the quality and completeness of project estimates, including the anticipated uncertainty and variability of the projected cost and schedule. The CEVP uses systematic project review and risk assessment methods, including statistics and probability theory, to evaluate the quality of the information at hand and to identify and describe cost and schedule uncertainties. The CEVP recognizes that every project cost estimate will be a mix of the very likely, the probable, and the possible. Importantly, the process examines, from the very beginning, how risks can be communicated and lowered and cost vulnerabilities managed or reduced. In other words, a dividend of the CEVP is to promote the activities that will improve end-ofproject cost and schedule results. The CEVP process integrates into the entire project development process in a way similar to that of the Caltrans method previously described. The CEVP process begins with a workshop to facilitate the risk identication and quantitative risk analysis phases of the process. A rigorous peer review and uncertainty analysis is
priate participants
A planned and structured risk management process, integral
performance elements
Metrics to monitor effectiveness of risk-handling strategies Formal documentation
Why? Programmatic cost risk analysis can be used to change an agencys culture and to combat systemic cost escalation. It allows cost estimates to be transparently conveyed to management. It reveals risk and uncertainty involved with the project at each stage of the process. It provides a tool to model both the technical and nontechnical nature of the challenges in quantifying capital costs early in the project life cycle. What Does It Do? Programmatic cost risk analysis can help to create a culture of risk management that is forward looking, structured, informative, and continuous. Through the generation of riskbased probabilistic cost and schedule estimates, the process can assist agencies in anticipating and mitigating potential cost escalation. The process can produce prioritized lists of cost and schedule risks. It can provide estimates of these individual risk costs and their potential effects on project component schedules. Ultimately, the process can produce prioritized risk mitigation strategies, including their estimated implementation costs and cost/schedule savings, which can be incorporated into a comprehensive risk management plan. When? A programmatic cost risk analysis should be applied in all phases of the project development process. In the earliest phases of project development, the tool focuses on risk identication and risk analysis to produce meaning contingencies and prioritized rankings of risks. As project development progresses, the process supports risk mitigation and is managed though an active risk charter. In the nal stages of project
A-161
Source: Project Risk Management Handbook, Caltrans Office of Project Management Process Improvement, 2003. PT = Project development team EIS = Environmental impact statement ND = Negative declaration FONSI = Finding of no significant impact EIR = Environmental impact report
Source: Project Risk Management Handbook, Caltrans Office of Project Management Process Improvement, 2003.
the foundation of the CEVP process. A multidisciplinary team of professionals from both the public and private sectors examines the project. Table R3.5-3 presents the seven phases in the WSDOT CEVP process. While the workshop is a key component of the CEVP process, the CEVP process involves many other components
that are integrated into the cost estimation, risk management, and project management processes at WSDOT. Other elements of the CEVP process are described in Sections C1.2, I2.2, R3.1, and R3.4 in this guide. More information can be found on the WSDOT CEVP and Cost Risk Analysis website at www.wsdot.wa.gov/Projects/ProjectMgmt/RiskAssessment.
Project data compilation CEVP training and education Establishment of the workshop goals, workshop scope, and project alternatives being explored Project team presentation of: 1) scope and assumptions for each decision alternative; 2) cost and schedule estimate; and 3) major issues and concerns Development of project flow chart or schedule (the basis for the cost and schedule risk and uncertainty model)
Cost validation team breakout activities Risk team breakout activities Environmental costing team breakout activities Modeling team breakout activities
Breakout team reports Reconciliation of breakout assumptions Construction of cost and schedule risk and uncertainty model Oral presentation of workshop results Written presentation of workshop results Project and CEVP teams validate workshop results Alternative project scenarios are explored and evaluated Development of risk mitigation planning and integration into project management Reviewing and updating of workshop results and predictions as compared with actual project results
Phase V Presentation of Results Phase VI Validation of Results and Generation of Alternatives Phase VII Implementation and Auditing
Tips Implementation of a programmatic cost risk analysis tool will involve signicant changes to most state highway agencies cost estimation and project management procedures. In fact, the process will likely require a cultural change within the organization. To be successful, this tool will require managements full support and commitment of resources. Resources Caltrans Ofce of Project Management Process Improvement (2003). Project Risk Management Handbook. www.dot.ca. gov/hq/projmgmt/documents/prmhb/project_risk_manage ment_handbook.pdf. Federal Transit Authority (2004). Risk Assessment Methodologies and Procedures, report under Contract No. DTFT6098-D-41013. Federal Highway Administration (2004). Major Project Program Cost Estimating Guidance. Molenaar, K. R. (2005). Programmatic Cost Risk Analysis for Highway Mega-Projects, Journal of Construction Engineering and Management, Vol. 131, No. 3, American Society of Civil Engineers.
Project Management Institute (2004). A Guide to Project Management Body of Knowledge (PMBOK Guide). Washington State DOT (2006). Cost Estimating Validation Process (CEVP) website: www.wsdot.wa.gov/Projects/ ProjectMgmt/RiskAssessment.
V1 Validate Costs
Constant project cost evaluation is a means to better manage projects and respond to public skepticism and concern about project estimates and actual costs. Validation processes appraise the reasonableness and completeness of the assumptions, procedures, and calculations used in developing an estimate.
A-164
What Is It? Estimation software is the computer program that assists the state highway agencies in developing cost estimates. Most estimation software, be it agency developed or a commercial product, has preloaded templates that help the state highway agency project teams dene the project scope, cost, and schedule. The software provides a means to track project development, and it can assist in project review, particularly if it includes features that ag costs that do not fall within preset historical cost ranges. Why? One of the advantages of using estimation software to calculate project cost is that it can provide rapid search features that detect errors or anomalies in an estimate. Estimates on large projects and even on many small urban projects are very complex, and computer software is the only efficient method of checking the many small details that support the cost calculations. What Does It Do? The estimation software will direct the estimators attention to input data or costs that the software detects as not being appropriate. The software does not tell the estimator what is wrong, but it focuses attention on those areas of the estimate that should be carefully reviewed. When? Cost validation is an ongoing process that should be occurring during all project development stages. By using estimation software with built-in anomaly detection features, the validation checks take place as the estimate is created. This means that problem identication is continuous. Examples The Heavy Construction Systems Specialists, Inc. (HCSS), software, HeavyBid, has a feature that checks the estimate and takes the estimator to each questionable location so that corrections can easily be made as necessary. The AASHTO CES and Estimator software have a feature that allows the estimator to spot unit costs that are outside the range of unit cost data included in the database. There is a statistical regression option that provides a best-fit curve with condence intervals. This feature can be used to determine if a unit price that was input by the estimator is within the range of expected unit prices as deleted through the regression analysis.
Tips The effectiveness of any estimation software is directly related to product support and training. When selecting software, always ensure that product support will be available and that training and training material will be provided. Resources For more information about Trnsport Estimator, contact the AASHTOWare contractor: Info Tech, 5700 SW 34th Street, Suite 1235, Gainesville, FL 32608. Phone (352) 381-4400; Fax (352) 381-4444; E-mail [email protected]; Internet www.infotech.com. Heavy Construction Systems Specialists, Inc. (HCSS), 6200 Savoy, Suite 1100, Houston, TX 77036. Phone (800) 683-3196 or (713) 270-4000; Fax (713) 270-0185; E-mail [email protected]; Internet www.hcss.com.
V2 Value Engineering
Value engineering can be dened as a systematic method to improve the value of goods and services by examining function. Value is the ratio of function to cost. Value can therefore be increased by either improving the function or reducing the cost. It is a primary tenet of value engineering that quality not be reduced as a consequence of pursuing value improvements. In the United States, value engineering is specifically addressed in Public Law 104-106, which states, Each executive agency shall establish and maintain cost-effective Value Engineering procedures and processes. Value engineering is sometimes taught within the industrial engineering body of knowledge as a technique in which the value of a systems outputs is optimized by crafting a mix of performance (i.e., function) and costs. In most cases, this practice identies and removes unnecessary expenditures, thereby increasing the value for the manufacturer and/or their customers. In late 1995, Congress passed the National Highway System (NHS) Designation Act, which included a provision requiring the U.S. Secretary of Transportation to establish a program that would require states to carry out a value engineering analysis for all federal-aid highway projects on the NHS with an estimated total cost of $25 million or more. On February 14, 1997, the FHWA published its value engineering regulation establishing such a program.
A-165
What Is It? Value engineering is the systematic review of a project, product, or process to improve performance, quality, and/or life cycle cost by an independent multidisciplinary team of specialists. The value engineering process, referred to as the job plan, denes a sequence of activities that are undertaken during a value engineering study before, during, and following a workshop. During the value engineering workshop, the value engineering team learns about the background issues; denes and classies the project (or product or process) functions; identies creative approaches to providing the functions; and then evaluates, develops, and presents the value engineering proposals to key decision makers. The focus on the functions that the project, product, or process must perform sets value engineering apart from other quality improvement or cost reduction approaches. Why? When value engineers talk about reducing costs, they are usually referring to either total life cycle costs or the direct costs of production. Total life cycle costs are the total expenditures over the whole life span of the highway. This measure of cost is most applicable to expensive capital equipment and includes engineering, procurement, construction, maintenance, and decommissioning costs. Individual expenditures must be discounted to reect the time value of money, which translates to a more accurate estimate. The main objectives that the value engineering process seeks include improving project quality, reducing project costs, fostering innovation, eliminating unnecessary and costly design elements, ensuring efcient investment in projects, and developing implementation procedures. What Does It Do? Value engineering uses intuitive logic (a unique how/ why questioning technique) and analysis to identify relationships that increase value. Value engineering is a quantitative method similar to the scientic method (which focuses on hypothesis and conclusion to test relationships) and operations research (which uses model building to identify predictive relationships). The value engineering process follows a general framework commonly referred to as an eight-phase job plan, with the following phases: 1. Selection Phase: Select the right projects, timing, team, and project processes and elements. 2. Investigation Phase: Investigate the background information, technical input reports, eld data, function analysis, and team focus and objectives.
3. Speculation Phase: Be creative and brainstorm alternative proposals and solutions. 4. Evaluation Phase: Analyze design alternatives, technical processes, life cycle costs, documentation of logic, and rationale. 5. Development Phase: Develop technical and economic supporting data to prove the feasibility of the desirable concepts. Develop team recommendations. Recommend long-term as well as interim solutions. 6. Presentation Phase: Present the recommendations of the value engineering team in an oral presentation and in a written report and workbook. 7. Implementation Phase: Evaluate the recommendations. Prepare an implementation plan, including response of the managers and a schedule for accomplishing the decisions based on the recommendations. 8. Audit Phase: Maintain a records system to track the results and accomplishments of the value engineering program on a statewide basis. Compile appropriate statistical analyses as requested. The duration and assessment for these phases depend on the complexity of the project. By performing the steps in these phases, the value engineering team will evaluate several components of a project, such as designs, topographical implications, and environmental impacts, and make recommendations for several feasible options along with the cost differences and their impact on total project cost and schedule. These details are compiled into a value engineering decision document for appraisal from concerned authorities. When? Value engineering is most successful when it is performed early in project development. A value engineering study should be performed within the rst 2530% of the design effort prior to selecting the nal design alternative. Value engineering is compulsorily performed on federal aid projects greater than $25 million and should be performed on highcost projects. The process can provide a justied logic for alleviating cost escalations while not compromising quality. Examples Figure V2.1, the value analysis owchart for Nevada DOT, shows how the value engineering process is incorporated into practice. Tips Often, value engineering reduces costs by eliminating wasteful practices. This can be done in several areas:
Material substitutions: Unnecessarily expensive inputs can
A-166
just as well. If a product has a life span of 10 years, then using a material that lasts 30 years is wasteful. In a perfectly value-engineered product, every component of a highway will function perfectly until the product is no longer useful, at which time all components will deteriorate. Process efciency and producibility: More efcient processes can be used, and the highway can be redesigned so
that it is easier to construct. Reducing unnecessary design elements, unnecessary precision, and unnecessary construction operations can lower costs and increase the speed of construction and reliability. Modularity: Many highway project design elements are identical and can be mass produced to reduce costs. Such designs are developed once and reused in many slightly dif-
A-167
ferent products, thereby reducing a projects engineering and design costs. For example, precast concrete slabs have proven to be a quick and efcient solution to time-constrained construction operations. These slabs can be factory cast for different sizes and transported and assembled at the sites by modern construction practices, such as posttensioned concrete structures. Also, these slabs can be produced to a desired quality as they are manufactured under controlled conditions. Energy efciency: In an environmentally conscious society, value can be created by making a product or process more energy efcient for the user. For example, development and usage of customized equipment, such as slip form pavers, ensure that a single piece of equipment performs several operations that would require several resources traditionally. Additionally, agencies must
Ensure they have adequate training facilities or trained staff Identify and train value engineering team member in-house Share knowledge gained or results derived during value
which cause the estimator to review the scope for completeness, will yield comprehensive and improved cost estimates. What Is It? This tool is the employment of checklists or templates that estimators and managers use to ensure that the project scope is complete. These checklists guide the estimator through an inventory of items and questions that address both the design elements of the project and other things that drive project cost, such as environmental permits, purchase of right-of-way, and utility interference. Why? Estimators are generally very familiar and procient with assembling cost data and developing item costs, but for the estimate to be of value, it must match what will actually be built and the build environment conditions. Thus, one of the rst steps to achieving estimate accuracy is verifying that the project scope is complete, in terms of both the physical structures to be built and the environment where the construction will take place. What Does It Do?
engineering studies to continuously improve the process Resources Wilson, David C. (2005), NCHRP Synthesis of Highway Practice 352: Value Engineering Applications in Transportation, Transportation Research Board. http://www.trb.org/news/ blurb_detail.asp?id=5705. Washington State DOT (1998), Design Manual, Section 315. http://www.wsdot.wa.gov/EESC/Design/DesignManual/ desEnglish/315-E.pdf.
Checklists serve to delineate the large number of factors that must be considered during scope development. Therefore, they are an excellent means of avoiding omissions and calling attention to the interaction between factors that can impact scope and cost. The answers to the checklist questions will provide an overview of scope completeness and focus the estimator and project management teams attention on critical issues that need to be considered. When? Scope checklists can support estimate creation at all stages of project development. The purpose of a checklist is to assist the project team in developing a complete description of project scope. Checklists should be as inclusive as possible, with questions that specically probe the scope at the different stages in project development. Examples A scope checklist for bridge construction might review the following topics: 1. 2. 3. 4. Maintenance of trafc Removals Foundation Wetland mitigation
A-168
Garbage dump removal Toxic waste removal Utilities (relocation companies/owners) Unusual conditions, such as power stations, sewerage plants, high-tension lines, and pumping stations Railroad engineering Right-of-way summary Mitigation for wetland sites Sidewalks on bridge Maintenance operations, such as cleaning existing pipes, drainage structures, and ditches Noise barriers
project development, but they should all include questions about third-party requirements. The project scope must be monitored as the project proceeds through the development phases to ensure that any and all changes are properly managed. Resources Sturgis, Robert P. (1967). For Big SavingsControl Costs while Dening Scope. AACE 11th National Meeting, AACE International, Vol. 67-C.3, pp. 4952. Though it is not strictly for transportation work, a scope development checklist can be found on the Construction Industry Cooperative Alliance (CICA) web page at www.ces. clemson.edu/cica/Toolbox/files/SD1_Scope%20Develop ment%20Checklist.doc. CICA is a cooperative alliance between member rms from the construction industry in the eastern United States and Clemson Universitys Department of Civil Engineering.
Tips The project scope should clearly dene each deliverable, including exactly what will be produced and what will not be produced. Get approval from all stakeholders. There can be many individual checklists to support the different phases of
APPENDIX B
Implementation Framework
B-1
APPENDIX B
Implementation Framework
ManagementManage the estimation process and costs through all stages of project development. Scope/ScheduleFormulate denitive processes for controlling project scope and schedule changes. Off-PrismUse proactive methods for engaging external participants and conditions that can inuence project costs. RiskIdentify risks, quantify their impact on cost, and take actions to mitigate the impact of risks as the project scope is developed. Delivery and Procurement MethodApply appropriate delivery methods to better manage cost, as project delivery inuences both project risk and cost Document QualityPromote cost estimate accuracy and consistency through improved project documents Estimate QualityUse qualied personnel and uniform approaches to achieve improved estimate accuracy IntegrityEnsure checks and balances are in place to maintain estimate accuracy and minimize the impact of outside pressures that can cause optimistic biases in estimates
APPENDIX C
Denitions
C-1
APPENDIX C
Denitions
Acquisition: The act or process of acquiring fee title or some interest therein other than fee title of real prioperty (real estate). Allowance: Additional resources included in an estimate to cover the cost of known but undened requirements for an activity or work item. An allowance is a normal cost. Appraisal: A written statement independently and impartially prepared by a qualied appraiser setting forth an opinion of dened value of an adequately described property as of a specic date, supported by the presentation and analysis of relevant market information. Competitive Bidding: The process whereby construction projects are required to be advertised and awarded to the lowest responsible and responsive bidder through open bidding, unless use of an eligible force account is more cost-effective. Conceptual Estimate (Initial Estimate): A project cost estimate prepared prior to the NEPA decision document. Usually, quantities have not been determined at this time. The estimates are prepared for the range of alternatives evaluated under NEPA. In some cases, the relative dollar amount is expressed as a range used for decision making to proceed with project development. Condemnation: The legal process of acquiring private property for public use or purpose through the acquiring agencys power of eminent domain. Condemnation is usually not used until all attempts to reach a mutually satisfactory agreement through negotiations have failed. An acquiring agency then goes to court to acquire the needed property. Condence Level: The probability that a range will contain the value under consideration. For example: there is a 90% probability that the ultimate project cost will be less than $(number). Condence Range: The difference between the upper and lower values of a set of numbers or results within specic condence levels. Construction Administration Cost: The normal cost of administration, management, reporting, design services in construction, and community outreach required in the construction phase of a project. Construction Allowance: An amount of additional resources included in an estimate to cover the cost of known but undened requirements for a construction activity or work item. A construction allowance is a normal cost. Construction Contingency: An additional markup applied to cover the cost of undened and asyet unknown construction requirements that are expected to be zero at completion of construction. Construction contingency is a risk cost. Construction Phase: The project development phase that includes advertising the project, awarding the contract, and performing the actual construction.
C-2
Contingency: A markup applied to account for substantial uncertainties in quantities and unit costs and the possibility of currently unforeseen risk events related to quantities, work elements, or other project requirements. Contingency is a risk cost. Cost Estimate Validation Process (CEVP) Schedule: The schedule assessed by the CEVP team, including consideration of all normal costs, allowances, contingency, risk, and opportunity events. Cost Team: The CEVP team members plus project team members who reviewed all elements of normal cost (including allowances) for the particular project under consideration. Cost Validation: A detailed examination of normal costs (including allowances) for the particular project under consideration to assess validity, reasonableness, consistency, and accuracy of these costs. Damages: A loss in value of the remaining property caused by the acquisition, planned use, or construction. Normally, the value of the damage is based on the before-and-after appraisal or cost to cure. An owner is entitled to payment of damages and receives this payment as a part of just compensation. Design Allowance: Additional resources included in an estimate to cover the cost of known but undened requirements for a design element. A design allowance is a normal cost. Design Contingency: A markup applied to cover the cost of undened and as-yet unknown design requirements. The design contingency is expected to be zero at completion of design. Design contingency is a risk cost. Eminent Domain: The right of a government to take private property for public use. In the United States, just compensation must be paid for private property acquired for federally funded programs or projects. Environmental Clearance: The process whereby a project must conform to the National Environmental Policy Act (NEPA), the National Historic Preservation Act (Section 106), and Section 4(f) of the U.S. DOT Act, and other relevant federal and state environmental laws. Estimate: The most probable cost for a project, consisting of normal costs, contingencies, and the probable cost of risk events. Fair Market Value: The price that a willing buyer will pay a willing seller for a piece of real estate. Federal Share: The portion of the project cost funded by the federal government. These federal funds are normally matched with state and/or local government funds to make up the total cost of the project. The federal portion, or share, is 80% for most projects; however, in states with large amounts of federal lands, a higher federal share is authorized. See Matching Funds. Final Estimate: The estimate developed when design is approximately complete and all quantities are known. Highest and Best Use: The legal use (or development or redevelopment) of a property that makes the property most valuable to a buyer or the market. Just Compensation: The price an agency must pay to acquire real property. The price offered by the agency is considered to be fair and equitable to both the property owner and the public. The agencys offer to the owner is just compensation and may not be less than the amount established in the approved appraisal report as the fair market value for the property. If it becomes necessary for the acquiring agency to use the condemnation process, the amount paid through the court will be just compensation for the acquisition of the property. Matching Funds (Local Funding Share): The percentage of nonfederal funds required for almost all TEA-21 programs on a project-by-project basis to match a federal contribution. The standard ratio is a 20% match from state and local sources, with a federal share of 80%. See Federal Share. Monte Carlo Simulation: A technique using multiple simulations incorporating the variability of individual elements to produce a range of potential results.
C-3
National Environmental Policy Act (NEPA): The federal law that requires every federal agency, prior to approving a major federal action that could signicantly affect the quality of the human environment, to prepare a detailed report evaluating both environmental impacts and alternatives to the proposed action. The environmental clearance required of federal-aid projects may take a variety of forms: environmental impact statement (EIS), environmental assessment (EA), nding of no signicant impact (FONSI), and categorical exclusion (CE). Negotiation: The process used by acquiring agencies to reach amicable agreements with property owners for the acquisition of needed property. An offer is made for the purchase of property in person or by mail, and the offer is discussed with the property owner. Nomination: The process by which a public or private entity submits an application for a candidate project to the state DOT for consideration. In most states, the nominating entity must be a public agency with tax-bearing authority. Normal Cost: The most probable cost for a unit or element of the project. The normal cost represents the cost that can most reasonably be expected if no signicant problems occur. The normal cost typically has small uncertainty or variance. Obligation: The second step in the funding process; the formal commitment by the FHWA of a specied amount of funding for a particular project, usually made when project or project phase is ready to begin billable work. Overmatch: The share of state or local matching funds (or in-kind value) brought to a project that is over and above the required state/local share. Parcel: Any plot of land. For the purposes of this report, parcel generally refers to the part being acquired, but it may also be used in association with original or remainder parcels. Partial Taking: Acquisition in which the original property is severed to form two parcels, leaving a remainder. Damages are most often associated with partial takings, which may require the removal of access, parking, buildings, or other improvements. Plans, Specications and Estimates (PS&E): The documentation submitted by the project sponsor that must receive state DOT approval before federal funds can be obligated to proceed with contract letting and project construction. Preliminary Engineering Phase: The project development phase that includes preparation of environmental and construction documentation, such as plans, specications, and cost estimates. Preliminary right-of-way work, appraisal maps, and estimates may also be reimbursed with federal-aid funding for the preliminary engineering phase. Probability: The chance of an event occurring, measured as a percentage or fraction, where 100% or 1 represents certainty. Programming Estimate: The estimate for the selected alternative. This estimate can be based on some quantities. This estimated project cost begins with NEPA approval and continues up to the PS&E. Project: An undertaking to develop, implement, or construct a particular transportation enhancement at a specic location or locations. Project Schedule: The schedule, as presented by the project team, corresponding to the project team estimate. Project Team: The team representing the particular project under consideration. Range: The difference between the upper and lower values of a set of numbers or results, either absolutely or related to condence levels. Range Cost Estimate: A cost estimate that shows a range of costs related to a specic condence level. Rehabilitation: The act or process of returning a property to a state of utility through repair or alteration that makes possible an efcient contemporary use while preserving those portions
C-4
or features of the property that are signicant to the propertys historical, architectural, and cultural values. Restoration: The act or process of accurately recovering the form and details of a property and its setting as it appeared at a particular period of time by means of the removal of later work or by the replacement of missing earlier work. Right-of-Way (ROW): A linear corridor of land used for transportation or other facilities, such as highways, roads, streets, railroads, trails, light-rail, and utilities. Risk: The combination of the probability of an adverse event and its consequences. Risk Assessment: A systematic evaluation of possible risk events in order to quantify risk to the project. Risk Events: Potential adverse events that negatively affect the dened project (resulting in impacts to cost, schedule, safety, performance, or other characteristics), but do not include the minor variance inherent in normal costs. Examples include political and/or management changes, changes in regulations and laws, earthquakes, res, oods, and unknown archeological sites. Risk Team: The CEVP team members plus project team members who reviewed all elements of risk (including contingency) for the particular project under consideration. Selected Project: A project or project phase contained in an approved statewide transportation improvement program (STIP) that has been advanced for implementation by the state highway agency in cooperation with the metropolitan planning organization or public transportation operator, as appropriate. Soft Match: The value of activities outside the project scope, but directly related to the project, that are credited toward the nonfederal share of a project. Sponsors: Individuals, partnerships, associations, private corporations, or public authorities recommending a particular project and committed to its development, implementation, construction, maintenance, management, or nancing. In most states, an enhancement project sponsor must be a public entity with tax-bearing authority. Surface Transportation: All elements of the intermodal transportation system, exclusive of aviation but inclusive of water. Variance (Variability): Inherent uctuations due to random events that result in a range of potential values for a quantity. Whole Taking: An acquisition that involves the taking of the original parcel in its entirety.
Abbreviations and acronyms used without denitions in TRB publications: AASHO AASHTO ACRP ADA APTA ASCE ASME ASTM ATA CTAA CTBSSP DHS DOE EPA FAA FHWA FMCSA FRA FTA IEEE ISTEA ITE NASA NCFRP NCHRP NHTSA NTSB SAE SAFETEA-LU TCRP TEA-21 TRB TSA U.S.DOT American Association of State Highway Officials American Association of State Highway and Transportation Officials Airport Cooperative Research Program Americans with Disabilities Act American Public Transportation Association American Society of Civil Engineers American Society of Mechanical Engineers American Society for Testing and Materials American Trucking Associations Community Transportation Association of America Commercial Truck and Bus Safety Synthesis Program Department of Homeland Security Department of Energy Environmental Protection Agency Federal Aviation Administration Federal Highway Administration Federal Motor Carrier Safety Administration Federal Railroad Administration Federal Transit Administration Institute of Electrical and Electronics Engineers Intermodal Surface Transportation Efficiency Act of 1991 Institute of Transportation Engineers National Aeronautics and Space Administration National Cooperative Freight Research Program National Cooperative Highway Research Program National Highway Traffic Safety Administration National Transportation Safety Board Society of Automotive Engineers Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (2005) Transit Cooperative Research Program Transportation Equity Act for the 21st Century (1998) Transportation Research Board Transportation Security Administration United States Department of Transportation