Lecture 4-Work Breakdown Structure
Lecture 4-Work Breakdown Structure
and Entrepreneurship
WORK BREAKDOWN
GEME 321 STTRUCTURE
LECTURE 4
POSITIONING the WBS
Project Title-
objective
Clear
Prepare site Purchase Materials Construct Deck
site
Dig
Buy footin Build
Level Source Lay Seal
Remove wooden gs frame
site quotat wood wood
litter boards
ions
Approaches in Developing WBS
ii. List format
❑ BUILD WOODEN DECK
1.Prepare the site
1.1. Remove litter
1.2 level the site
2. Purchase material
2.1 Source quotations
2.2 Buy wooden boards
3. Construct Deck
3.1 Dig Footings
3.2 Build frame
3.3 Lay the wood
3.4. Seal the wood
4. Clear site
Guidelines for Creating a WBS
1. Identify and analyse outputs/major project elements-
from Scope statement- major deliverables
2. Decomposition- breakdown top-tier project elements
into smaller components parts.
i. To move down you should answer “what should
be done to complete this task?”e.g. What should
be done to clear site (task)?- Remove litter, Level
site
ii. 100% rule- adding up all work packages into
summary activities, and when summary activities
are all incorporated, the WBS should = work to be
done to meet deliverables.
• WPs should also not add up to >100% of the scope
of summary activities- shows off scope work
Decomposition continued
iii. WBS Components of the WBS are not necessarily
decomposed to same degree
iv. WBS components must always be broken down
into at least 2 or more subcomponents.
• Avoid “single-child” WPs- i.e. one WP under
one summary activity: Sum Activity = WP
• Shows excessive decomposition,
micromanaging team members.
v. Names of WBS components- clear, unambiguous
indicating outcome/action to be performed
• “single verb-noun” naming rule e.g. Prepare Site;
Purchase Materials VS Site, Materials– vague
• Verb = work to be done, noun = the deliverable.
Decomposition continued
vi. WP must not be too large /require lots of time to
complete
a. “8-80”rule- level of work should not be less than
8 hours (1 day) & not more than 80 hrs (10 days).
b. WP completion time mustn’t be longer than a
single reporting period e.g. team meets
weekly/monthly- so should WPs -monitoring easy
viii.WP completion criteria : clear, measurable & defined
by deliverables- provide std for measuring
completion
Guidelines for Creating WBS
3. Allocate unique codes to each WBS component
e.g. 1, 1.1, 1.2. … = WBS ID
• Easy to identify and manage components
4. Create a WBS Dictionary – provides info on WBS
components:
▪ Description of work - deliverable/task
▪ Details of who is responsible (person/orgn/
contractor) for delivery; Completion criteria
▪ Costs, and Resources to be used and or skills
required
▪ List of schedule milestones
▪ Quality requirements; Cross references to
related activities
Example….WBS Dictionary
Level WBS Task (element Description Work product Owners Estimated level
Code name) of Effort
1 1 Prepare site All the work necessary to Site prepared Project 40 hours
clear the site in preparation and ready for manager
for construction construction
2 1.1 Remove litter All work required to remove Clear site Team leader 6 hours
litter from site ready for
construction
• Statement of
Work: Scope
Process • Scope Baseline:
statement etc. WBS, WBS
• Decomposition Dictionary,
• Requirements Scope statement
list.
Inputs Outputs
WBS: PHASE-BASED APPROACH
Work can be broken down according to the life cycle components/ phases of
the project- phase based decomposition
Brainstorm Ideas
Concept
Generation
Identify needs
Competitor
analysis
Product Analysis
Ingredient
Formula selection
Development Create specific
recipe
Prototyping
Laboratory testing
Production Scaling Product Testing
Customer testing
Promotion