Method Statement For Temporary Facilities
Method Statement For Temporary Facilities
Client:
Consultant:
Contractor:
Subcontractor:
Reference No:
FORM OF SUBMITTAL Date:
To: Attn:
To: Attn:
FOR
☐ Review and comments ☐ Approval ☐ Record
P a g e 1 | 36
METHOD STATEMENT FOR
THE TEMPORARY FACILITIES
CONSTRUCTION WORKS.
FOR
MAY, 2025
P a g e 2 | 36
Contents
1. GENERAL OVERVIEW .................................................................................................................................. 5
2. EQUIPMENT AND MANPOWER FOR CONSTRUCTION (TABULATED) ..................................... 6
3. ALL QUANTITIES USED FOR TEMPORARY WORK CONSTRUCTION (TABULATED)........... 7
4. WORKING TIME ............................................................................................................................................. 8
5. SITE CONDITION AFFECTING CONSTRUCTION PROCESS ......................................................... 10
5.1 Soil Conditions ..................................................................................................................................... 10
5.2 Water Table and Surface Water ..................................................................................................... 10
5.3 Accessibility........................................................................................................................................... 10
5.4 Weather Conditions............................................................................................................................ 10
5.5 Proximity to Sensitive Structures ................................................................................................. 10
6. CONSTRUCTION PROCESS CHART ...................................................................................................... 11
7. MATERIAL FOR CONSTRUCTION ......................................................................................................... 12
7.1 Civil Works ............................................................................................................................................. 12
7.2 Structural Steel & Metal .................................................................................................................... 12
7.3 Fixtures and Fitments ....................................................................................................................... 12
7.4 MEP & Monitoring .............................................................................................................................. 12
7.5 Sanitary & Plumbing .......................................................................................................................... 13
8. CONSTRUCTION METHOD ...................................................................................................................... 14
8.1 Yard Preparation ................................................................................................................................. 14
8.2 Drainage System with Neat Cement Finishing ......................................................................... 15
8.3 Silt Trap Construction ....................................................................................................................... 16
8.4 Washing Bay Construction .............................................................................................................. 17
8.5 Sump Pit Construction ...................................................................................................................... 19
8.6 Project Signboard, Traf ic Signboard & Safety Statistics Board Installation ................ 20
8.7 Noise & Vibration Monitoring System......................................................................................... 21
8.8 Temporary Site Of ice Installation (Container System + Furniture) ............................... 22
8.9 Electrical System and Site Illumination ...................................................................................... 23
8.10 Temporary Toilet Facilities ........................................................................................................... 25
8.11 Temporary Guard House Construction .................................................................................... 26
8.12 Temporary Fence Installation ...................................................................................................... 26
P a g e 3 | 36
8.13 CC Camera Security System Installation .................................................................................. 28
9. QUALITY CONTROL ................................................................................................................................... 30
9.1 Quality Objectives ............................................................................................................................... 30
9.2 Quality Control Measures by Work Scope ................................................................................. 30
9.3 Inspection & Documentation .......................................................................................................... 30
9.4 Records to be Maintained ................................................................................................................ 30
10. SAFETY CONTROL ................................................................................................................................... 31
10.1 Safety Objectives ............................................................................................................................... 31
10.2 General Safety Measures ................................................................................................................ 31
10.3 Activity-Speci ic Safety Precautions .......................................................................................... 31
11. ENVIRONMENT CONTROL ................................................................................................................... 32
11.1 Environmental Objectives ............................................................................................................. 32
11.2 Control Measures by Activity ....................................................................................................... 32
11.3 Materials Handling ........................................................................................................................... 32
12. RISK ASSESSMENT (RA) ....................................................................................................................... 33
12.1 (5x5) Risk Matrix .............................................................................................................................. 33
12.2 Key Risk Items and Mitigation Measures (Quanti ied Risk Table) ................................ 35
P a g e 4 | 36
1. GENERAL OVERVIEW
This Method Statement outlines the temporary facilities construction works necessary for the
execution and support of the main project titled:
-------------------------------------------------------------------------------------------------------------------------------
--------------------
The temporary works are essential for ensuring safe, efficient, and systematic project execution and
include the following scopes:
The works shall be carried out in accordance with the approved drawings, technical specifications,
applicable codes and standards, and with strict adherence to quality, safety, and environmental
requirements.
P a g e 5 | 36
2. EQUIPMENT AND MANPOWER FOR CONSTRUCTION (TABULATED)
Drainage System with Shovel, Pickaxe, Cement Mixer, Trowel Mason, Helper, Labors
Cement Finishing
Washing Bay Construction Concrete Mixer, Steel Cutter, Welding Mason, Welder, Labors,
Machine Carpenter
Sump Pit Construction Manual Tools, Vibrator, Concrete Mixer Labors, Mason, Carpenter
Signboard & Board Steel Frame, Drill Machine, Ladder, Fabricator, Painter,
Installation Shovel, Concrete Mixer Labors
Noise & Vibration Vibration Meter, Sound Level Meter Monitoring Technician
Monitoring System
Temporary Toilet Facilities Masonry Tools, Plumbing Equipment Plumber, Mason, Labors
CC Camera Security System Drill, Conduit Bender, Laptop for Electrician, Technician
configuration
P a g e 6 | 36
3. ALL QUANTITIES USED FOR TEMPORARY WORK CONSTRUCTION (TABULATED)
CODE : 101 - PREPARATION AND TESTING
JDC-KONOIKE JV
CODE DESCRIPTION QTY UNIT REMARK
P a g e 7 | 36
4. WORKING TIME
The temporary works for this project shall be executed in accordance with the approved
project timeline, ensuring alignment with site access and safety protocols. The proposed
working hours are as follows:
Key Points:
Overtime or night work may be carried out for critical temporary work items,
subject to client approval.
All work during holidays or outside regular hours shall be carried out with the
client approval.
Site lighting shall be installed for low-light or evening work (especially for
electrical and security installation).
Specific working hours may vary slightly depending on site conditions, weather,
or coordination with other subcontractors.
P a g e 8 | 36
Construction Work Schedule
P a g e 9 | 36
5. SITE CONDITION AFFECTING CONSTRUCTION PROCESS
The construction of temporary works is influenced by several on-site conditions that
must be considered for effective planning and execution. Key conditions identified at the
PKPL project site include:
The site is located near the riverbank, consisting of a soft to medium-stiff clayey
soil layer.
5.3 Accessibility
Limited space in some sections for equipment movement and material storage.
Shared access points with other ongoing construction activities may cause traffic
or congestion.
Coordination with main contractor and logistics team is essential for safe
equipment mobilization.
P a g e 10 | 36
Noise, vibration, and dust control measures must be implemented during fence
erection, excavation, and concreting works.
P a g e 11 | 36
7. MATERIAL FOR CONSTRUCTION
The construction of temporary facilities requires a range of civil, structural, mechanical,
and electrical materials. Below is a categorized list of materials proposed for each scope
of work:
Brick Chips (for sub-base): 1st class, broken from well-burnt bricks
Filling Sand: Clean, locally available river sand for filling and bedding
Concrete Mix: Nominal mix M15–M24 (for pits, washing bay, drainage)
Project Signboards / Safety Boards: self-adhesive eco solvent vinyl print with
matte laminated weatherproof backing
Furniture: Office tables, chairs, file racks, beds (for site office)
P a g e 12 | 36
Site Illumination Lights: LED flood lights and area lighting
Noise & Vibration Meters: Calibrated digital sensors with data loggers
PVC Pipes and Fittings: Ø100 mm for toilet and soak pit
Toilet Fixtures: High Commode or Squat pan, tap, basin, soap holder
P a g e 13 | 36
8. CONSTRUCTION METHOD
Work Description:
Prepare the working yard using a sub-base layer
comprising compacted brick chips mixed with
sand to create a firm, stable, and dry surface for
vehicle and pedestrian movement.
Procedure:
Quality Control:
Safety:
P a g e 14 | 36
8.2 Drainage System with Neat Cement Finishing
Work Description:
Construct surface water drains along the yard and
project perimeter using mortar plastered with neat
cement finish to control water runoff.
Procedure:
Quality Control:
Safety:
P a g e 15 | 36
8.3 Silt Trap Construction
Work Description:
Build a silt trap to collect sediment-laden runoff before it enters the main drainage
system, reducing clogging and environmental contamination.
Procedure:
1. Layout and Excavation: Mark and excavate as per the approved silt trap section
(depth and dimensions).
2. Base Preparation: Compact the base and place 50mm lean concrete (1:4:8).
3. Reinforcement & Formwork: Fix rebar and formwork for RCC side walls and
base slab.
5. Filter: Install filter as shown in the drawing using pipes and brick chips of
different sizes, so it can reduce clogging and environmental contamination.
6. Connection: Integrate with site drain via inlet and outlet pipes.
7. Cleaning & Inspection: Clean internally and check for free flow.
Quality Control:
Safety:
P a g e 16 | 36
8.4 Washing Bay Construction
Work Description:
A concrete washing bay to remove mud from construction area.
Procedure:
1. Excavation & Grading: Mark and excavate to required depth as per drawing.
2. Sub-base Preparation: Compacted the soil layer and place lean concrete or
brick soling.
3. Formwork & Steel Fixing: Place shuttering and lay mesh or bar reinforcement.
4. Concrete Pouring: Cast RCC slab (C18) with support as shown in the drawing.
Quality Control:
P a g e 17 | 36
Finish surface with broom finish for anti-slip.
Safety:
P a g e 18 | 36
8.5 Sump Pit Construction
Work Description:
A sump pit will serve as a water collection point for pumped drainage or vehicle wash
runoff, facilitating temporary water control during construction.
Procedure:
Quality Control:
Safety:
P a g e 19 | 36
8.6 Project Signboard, Traffic Signboard & Safety Statistics Board Installation
Work Description:
Install fixed visual aids for site identification, traffic
management, and safety awareness near the
entrance and site boundary.
Procedure:
Quality Control:
Safety:
P a g e 20 | 36
8.7 Noise & Vibration Monitoring System
Work Description:
Install noise and vibration monitoring equipment to ensure compliance with
environmental and occupational safety standards, especially near sensitive areas or
inhabited zones.
Procedure:
1. Site Selection: Identify monitoring points near the site boundary, heavy
equipment zones, and nearby structures.
3. Power Supply: Ensure solar or battery backup; where applicable, connect to site
electrical supply.
Quality Control:
Safety:
P a g e 21 | 36
8.8 Temporary Site Office Installation (Container System + Furniture)
Work Description:
Install prefabricated container-based offices complete with electrical, furniture, and
work zones for the contractor’s site management team.
Procedure:
1. Site Preparation: Level and compact the base area for container placement.
2. Foundation Pads: Lay precast concrete blocks or steel sleepers to elevate the
container.
4. Connection Works: Join containers (if modular), seal gaps, and insulate if
necessary.
5. Interior Setup: Install desks, chairs, filing cabinets, lighting, fans, and power
outlets.
6. External Works: Provide ramp access, roof shade and canopies, drainage, and
fire extinguisher points.
Quality Control:
Safety:
Follow lifting protocol during crane work (no personnel on top of container).
P a g e 22 | 36
8.9 Electrical System and Site Illumination
Work Description:
Install a temporary electrical system to supply power to the site office, lighting, tools,
and equipment. Include site-wide illumination for safety and night work.
Procedure:
3. Wiring Installation: Use PVC insulated wires with conduit for indoor; armored
cables for outdoor.
4. Light Fixtures: Mount LED flood lights on poles at key zones (entry, office, toilet,
washing bay).
6. Testing & Labelling: Test all outlets, label circuits, and maintain logs.
Quality Control:
P a g e 23 | 36
Test continuity and insulation resistance.
Safety:
P a g e 24 | 36
8.10 Temporary Toilet Facilities
Work Description:
Construct temporary toilet units with basic sanitary fittings and proper waste disposal
system to serve site personnel.
Procedure:
1. Site Selection: Choose location with easy access and away from food/prep
areas.
4. Sanitary Fittings: Fix WBC or squat pans, tap, handwash basin with plumbing.
5. Water Supply & Waste: Connect with overhead water tank and soak pit or
septic tank.
Quality Control:
Non-slip floor.
P a g e 25 | 36
8.11 Temporary Guard House Construction
Work Description:
Construct a small temporary shelter for on-site security personnel, near the entry/exit
gate or location identified by the client, providing basic shade, rest space, and
surveillance point.
Procedure:
6. Painting and Finishing: Paint exterior and interior for durability and visibility.
Quality Control:
Safety:
Work Description:
Install 2.0m high solid fencing around the site using vertically ribbed steel wall cladding
sheets fixed to steel posts for safety, security, and privacy.
Procedure:
2. Post Installation: Dig holes, insert MS angle posts, and encase in concrete.
P a g e 26 | 36
5. Stiffening & Finish: Add bracing where needed; paint or coat if uncoated.
Quality Control:
Safety:
P a g e 27 | 36
8.13 CC Camera Security System Installation
Work Description:
Install a Closed-Circuit Television (CCTV) system to monitor the project’s temporary
facilities and entry/exit activities, enhancing overall site security.
Procedure:
3. Cable Routing: Use conduits or raceways to route data and power cables to each
camera.
Quality Control:
Safety:
P a g e 28 | 36
P a g e 29 | 36
9. QUALITY CONTROL
Quality control for temporary works is essential to ensure they are constructed to
specification, are safe, and serve their intended purpose throughout the duration of the
project.
Photographic records
Handover checklists
P a g e 30 | 36
10. SAFETY CONTROL
The temporary works shall be executed with strict adherence to project-specific Health,
Safety, and Environmental (HSE) policies. The primary goal is Zero Incident Execution
through proactive safety management.
Ensure all workers use proper PPE and follow safe work procedures.
Barricading and warning signs around all excavations and equipment operation
zones.
Excavation (Sump/Silt
Edge protection, standby watch.
Trap)
Crane Operation (Site Use experienced rigging crew, exclusion zone during lifting,
Office) no overhead personnel.
Welding
Fire blanket, fire extinguisher, welding shield.
(Fence/Signboards)
P a g e 31 | 36
11. ENVIRONMENT CONTROL
Environmental control measures are integrated into the temporary works to minimize
adverse impacts on the surrounding environment and to comply with environmental
regulations and JV/client requirements.
Drainage and Washing Ensure drains are not connected to natural water bodies.
Bay Install silt traps.
Site Illumination and Avoid light pollution with directional lighting. Prevent oil
Electrical leakage from generators.
Waste Generation (All Segregate solid waste, store in bins, and dispose outside of
Items) the site.
P a g e 32 | 36
12. RISK ASSESSMENT (RA)
A formal risk assessment has been conducted for all temporary work activities to
identify potential hazards, evaluate associated risks, and implement mitigation
measures. The goal is to reduce all risks to an acceptable or negligible level.
Risk Matrix
SEVERITY
Minor 2 Injury or ill-health requiring first-aid only (includes minor cuts and
bruises, irritation, ill-health with temporary discomfort)
P a g e 33 | 36
LIKELIHOOD
P a g e 34 | 36
12.2 Key Risk Items and Mitigation Measures (Quantified Risk Table)
Work Scope Potential Hazards Likelihood Severity Risk Level Control Measures / Mitigation
(L × S)
Yard Preparation Trip hazards, dust inhalation, 3– 3 – Moderate 9 – Medium Water spraying, defined
equipment movement Possible walkways, PPE, trained operators.
Drainage System Excavation collapse, cement 3– 4 – Major 12 – High Trench support, gloves & goggles,
Construction burns, hand injuries Possible excavation permit system.
Silt Trap Construction Rebar injuries, fall into pit, 3– 4 – Major 12 – High Pit barricades, ventilation,
poor ventilation Possible confined space procedures.
Washing Bay Slips on wet concrete, 2– 3 – Moderate 6 – Medium Anti-slip finish, secured
Construction formwork collapse Unlikely formwork, signage, check mixer &
tools.
Sump Pit Construction Fall into pit, water 4 – Likely 3 – Moderate 12 – High Secure cover, pump system, daily
accumulation, mosquito inspection, apply larvicide.
breeding
Signboards / Safety Overhead injury, falling 2– 3 – Moderate 6 – Medium Use of PPE, erect in calm weather,
Board Installation board, welding sparks Unlikely fire extinguisher at work area.
Noise & Vibration Equipment fall, tampering, 2– 2 – Minor 4 – Low Secure units on pole or mount,
Monitoring Setup low-voltage issues Unlikely signage, sealed systems.
Temporary Site Office Crane lifting failure, tipping, 3– 5– 15 – High Level foundation, fire
(Containers) fire hazard Possible Catastrophic extinguishers, supervised
installation.
Electrical System & Electrical shock, fire, short 3– 5– 15 – High Earthing, experienced
Illumination circuit Possible Catastrophic electricians.
Toilet Facilities Odor, hygiene issues, pit 2– 3 – Moderate 6 – Medium Daily cleaning, soak pit
failure Unlikely construction, water connection.
Temporary Guard Overcrowding, poor lighting, 2– 2 – Minor 4 – Low Fan/vent installation, low-load
House electrical overload Unlikely DB design, first aid access.
Temporary Fence Cuts, wind damage, unstable 3– 3 – Moderate 9 – Medium Edge protection gloves, bracing,
(Cladding Sheet) erection Possible schedule work during low winds.
CCTV Security System Ladder fall, poor cable 2– 4 – Major 8 – Medium Use secured ladders, isolate
Installation routing, power overload Unlikely power, concealed conduit routing.
P a g e 35 | 36
Risk Level Scale:
>15: Critical Risk (none in this scope due to temporary nature and controls)
P a g e 36 | 36