Process Design Ders Notlari
Process Design Ders Notlari
2025
PROCESS DESIGN
Prof. Dr. Mehtap Boroğlu
1
11.03.2025
2
11.03.2025
• The engineer must also have the ability to apply this knowledge to practical situations for
the purpose of accomplishing something that will be beneficial to society.
3
11.03.2025
exactly the same steps. for the proposed new venture, or developing a plant layout for
coordination of the overall operation.
Because of these many design duties, the chemical engineer is many times referred to here as a The development of the overall design project involves many different design
design engineer.
considerations.
On the other hand, a chemical engineer specializing in the economic aspects of the design is often
referred to as a cost engineer. • environmental protection,
In many instances, the term process engineering is used in connection with economic evaluation and • safety and health needs of plant personnel and the public,
general economic analyses of industrial processes, while process design refers to the actual design of
the equipment and facilities necessary for carrying out the process. • plant location, plant layout, plant operation and control,
Similarly, the meaning of plant design is limited by some engineers to items related directly to the • utility requirements, structural design, storage
complete plant, such as plant layout, general service facilities, and plant location.
• buildings, materials handling, and patent considerations.
4
11.03.2025
The development of a design project always starts with an initial idea or plan.
This initial idea must be stated as clearly and concisely as possible in order to define the
scope of the project.
Here, a general survey of the possibilities for a successful process is made by considering
the physical and chemical operations involved as well as the economic aspects.
same products). The computer-aided process simulator is also a useful tool in preparing material and energy
balances.
Chemical engineer must establish separate flowsheets or road maps for each
This software is especially useful for mass and energy balances, approximate sizing of equipment,
solution.
cost estimating, and economic analysis steps of process design.
Only those simplified flowsheets that provide a favorable gross profit are retained; The capabilities provided by computers for rapid calculations, large storage, and logical decisions
the others are rejected. plus the available technical and mathematical software permit design engineers to examine the effect
that various design variables will have on the process or plant design and to be able to do this more
The material and energy balances are generally performed with the use of a
rapidly than was required in the past to complete a single design by hand calculation.
computer-aided process simulator.
5
11.03.2025
As mentioned earlier, no design project should proceed to the final stages before A major function of the directors of a chemical or biochemical company
costs are considered, and cost estimates should be made throughout all the early
is to maximize the long-term profit to the owners or the stockholders.
stages of the design, even when complete specifications are not available.
The chemical engineer (or cost engineer) must be certain to consider all possible
A decision to invest in fixed facilities carries with it the burden of
factors when making a cost analysis. Fixed costs, direct production costs for raw continuing interest, insurance, taxes, depreciation, manufacturing costs,
materials, labor, maintenance, power, and utilities must all be included along with etc., and reduces the fluidity of the company' s future actions.
costs for plant and administrative overhead, distribution of the final products, and
other miscellaneous items.
In almost every case encountered by a chemical engineer, there are several alternative One typical example of an optimum economic design is determining the pipe
methods which can be used for any given process or operation. For example, formaldehyde diameter to use when pumping a given amount of fluid from one point to another.
can be produced by catalytic dehydrogenation of methanol, by controlled oxidation of Here the same final result (i.e., a set amount of fluid pumped between two given
natural gas, or by direct reaction between CO and H, under special conditions of catalyst,
points) can be accomplished by using an infinite number of different pipe diameters.
temperature, and pressure.
However, an economic balance will show that one particular pipe diameter gives
the least total cost.
If there are two or more methods for obtaining exactly equivalent final results, the preferred
The total cost includes the cost for pumping the liquid and the cost (i.e., fixed
method would be the one involving the least total cost. This is the basis of an optimum
economic design. charges) for the installed piping system.
6
11.03.2025
7
11.03.2025
CHAPTER 2
HEALTH AND SAFETY HAZARDS
General Design Considerations
The potential health hazard to an individual by a material used in any chemical or biochemical process is a
The development of a complete plant design involves consideration of many function of the inherent toxicity of the material and the frequency and duration of exposure. It is common
practice to distinguish between the short-term and long-term effects of a material.
different topics.
A highly toxic material that causes immediate injury is classified as a safety hazard while a material whose
• health, safety, loss prevention, and environmental considerations. effect is apparent only after long exposure at low concentrations is considered as an industrial health and
hygiene hazard.
Other aspects that will be discussed briefly include; Both the permissible limits and the precautions to be taken to ensure that such limits will not be exceeded are
quite different for these two classes of toxic materials.
• plant location, plant layout, plant operation and control, utility use,
Information on the effects of many chemicals and physical agents is accessible through a number of computer
structural design, materials handling and storage, and patent
databases, such as TOXLINE and TOXNET.
considerations.
Sources of Exposure
The main objective of health hazard control is to limit the chemical dosage of a chemical by
minimizing or preventing exposure.
The most common and most significant source of workplace exposure to chemicals—and the most
difficult to control—is inhalation. Workers become exposed when the contaminant is picked up by
the air they breathe. Thus, an understanding of the sources of contaminants to which workers are
exposed is important for the recognition, evaluation, and control of occupational health hazards.
For example, mechanical abrasions of solid materials by cutting, grinding, or drilling can produce
small particles that can form an airborne dust cloud or solid aerosol.
Gases are usually stored or processed in closed systems. Contamination of air with such gas occurs
from fugitive emissions (leaks) or from venting. Essentially all closed systems leak to some degree.
8
11.03.2025
9
11.03.2025
10
11.03.2025
11
11.03.2025
12
11.03.2025
HAZOP Study
Since a majority of the chemical process industry now uses some version of HAZOP
for all new facilities and selectively uses it on existing ones, an example of this
technique, as originally described by Ozog, is given in the following paragraphs.
Assume that a HAZOP study is to be conducted on a new flammable reagent storage
tank and feed pump, as presented by the piping and instrument diagram shown in
Fig. 2-1.
Since process and operating procedure changes are often made during or shortly
after plant start-up, it is strongly advised that hazard assessment not stop after
start-up.
Rather, periodic hazard assessment studies should be used to define the hazard
potential of such changes throughout the life of the facility.
The average time between reviews is about 3 years; more-hazardous facilities are
reviewed more frequently. Figure 2-1: Piping and instrumentation diagram used in HAZOP example
ENVIRONMENTAL PROTECTION
Because of the greater concern for the continued degradation of the
environment, the Environmental Protection Agency has systematically
been rewriting and tightening many policies and regulations.
Early effects of the agency designed to protect the environment focused
on the removal of pollutants from gas, liquid, and solid waste streams.
The effort through the passage of the Pollution Prevention Act of 1990
has now been shifted to waste minimization through waste reduction
and pollution prevention.
13
11.03.2025
14
11.03.2025
15
11.03.2025
16
11.03.2025
17
11.03.2025
18
11.03.2025
19
11.03.2025
20
11.03.2025
21
11.03.2025
22
11.03.2025
23
11.03.2025
Stream Information
• Since diagrams are small, not much stream information can be included
• Include important data – around reactors and towers, etc.
• Flags are used – see toluene HDA diagram
• Full stream data, as indicated in Table 1.4, are included in a separate flow
summary table – see Table 1.5
• It is divided into two groups—required information and optional
information—that may be important to specific processes.
24
11.03.2025
25
11.03.2025
Example 1.2
Check the overall material balance for the benzene process shown in Figure 1.3.
From the figure, we identify the input streams as Stream 1 (toluene feed) and Stream 3
(hydrogen feed) and the output streams as Stream 15 (product benzene) and Stream 16 (fuel
gas). From the flow summary table, these flows are listed as (units are in (103 kg)/h):
Input: Output:
Stream 3 - 0.82 Stream - 15 8.21
Stream 1 - 10.00 Stream - 16 2.61
Total - 10.82 ×103 kg/h Total - 10.82 ×103 kg/h
Figure 1.3 Skeleton Process Flow Diagram (PFD) for the Production of Benzene via the Hydrodealkylation of
Toluene
26
11.03.2025
Equipment Information
The final element of the PFD is the equipment summary.
The information presented in Table 1.6 is used in
This summary provides the information necessary to estimate the costs of preparing the equipment summary portion of the PFD
equipment and furnish the basis for the detailed design of equipment. for the benzene process.
Table 1.6 provides the information needed for the equipment summary for
most of the equipment encountered in fluid processes. The equipment summary for the benzene process is
presented in Table 1.7, and details of how we estimate
and choose various equipment parameters are discussed
in Chapter 11.
Table 1.7 Equipment Summary for Toluene Hydrodealkylation PFD (Benzene process )
Combining Topology, Stream Data, and Control Strategy to
Give a PFD
Up to this point, we have kept the amount of process information displayed on
the PFD to a minimum.
A more representative example of a PFD for the benzene process is shown in
Figure 1.5.
This diagram includes all of the elements found in Figure 1.3, some of the
information found in Table 1.5, plus additional information on the major
control loops used in the process.
27
11.03.2025
Figure 1.6 illustrates all the flags used in Flags are mounted on a staff connected to the appropriate
this text. process stream. More than one flag may be mounted on a
staff.
The units for each process variable are indicated in the key provided at the left-hand side of Figure 1.5. With the addition of the process control Example 1.7
loops and the information flags, the PFD starts to become cluttered.
The pressures of the streams to and from R-101 in the benzene process are also important. The difference in pressure
Therefore, in order to preserve clarity, it is necessary to limit what data are presented with these information flags. between the two streams gives the pressure drop across the reactor.
Fortunately, flags on a PFD are easy to add, remove, and change, and even temporary flags may be provided from time to time.
This, in turn, gives an indication of any maldistribution of gas through the catalyst beds. For this reason, pressure flags
The information provided on the flags is also included in the flow summary table. are also included on Streams 6 and 9.
However, often it is far more convenient when analyzing the PFD to have certain data directly on the diagram. Of secondary importance is the fact that flags are useful in reducing the size of the flow summary table.
Not all process information is of equal importance. General guidelines for what data should be included in information flags on the PFD are For pumps, compressors, and heat exchangers, the mass flows are the same for the input and output streams, and complete
difficult to define. entries in the stream table are not necessary.
However, at a minimum, information critical to the safety and operation of the plant should be given.
If the input (or output) stream is included in the stream table, and a flag is added to provide the temperature (in the case of
This includes temperatures and pressures associated with the reactor, flowrates of feed and product streams, and stream pressures and temperatures a heat exchanger) or the pressure (in the case of a pump) for the other stream, then there is no need to present this stream
that are substantially higher than the rest of the process. Additional needs are process specific. in the flow summary table. Example 1.8 illustrates this point.
28
11.03.2025
H2IN H2RCY
T = 120°F
P = 335 psi FEED-MIX REACT
Flow = 330 lbmol/hr HP-SEP
xH2 = 0.97
xN2 = 0.01
RXIN RXOUT T = 120°F
xCH4 = 0.02 P = 5 psi
T = 300°F T = 400°F
P = 330 psi P = 15 psi
benzene LIQ
conv. = 0.998
BZIN
T = 100°F 30% flow
CHRCY COLFD
P = 15 psi
100 lbmol /hr benzene LFLOW
LTENDS
Nstage = 12
RR = 1.2
Specify cyclohexane mole Mole-B = 99 lbmol /hr
recovery of 0.9999 by varying DV:D = 1
Mole-B from 97 to 101 lbmol /hr P = 200 psi COLUMN
Feed Stage = 8
PRODUCT
29
11.03.2025
cooling
water out process
condensate
propylene
• The piping and instrumentation diagram (P&ID), also known as mechanical flow
to treatment
cylinders
propylene recycle
toluene
diagram (MFD), provides information needed by engineers to begin planning for
the construction of the plant.
vent to flare
toluene tanker
cooling water in
T-200
K2CO3
• Support documents of the PFD used for planning for plant construction and
M cooling water out
PI
Na tank condensate
cw out
cw in
• The P&ID includes every mechanical aspect of the plant except the information
given in Table 1.8.
condensate
R-100 s.c.
T-100
• The general conventions used in drawing P&IDs are given in Table 1.9.
cooling water in intermediate
cooling water out storage
electric
steam
TI
condensate
• show where data is collected and/or recorded and how that information is
handled
30
11.03.2025
Figure 1.7 Piping and Instrumentation Diagram for Benzene Distillation (adapted from Kauffman, D,
“Flow Sheets and Diagrams,” AIChE Modular Instruction, Series G: Design of Equipment, series editor
J. Beckman, AIChE, New York, 1986, vol 1, Chapter G.1.5, AIChE copyright © 1986 AIChE, all rights Process & Instrumentation Diagram (P&ID)
reserved)
Process & Instrumentation Diagram (P&ID) Process & Instrumentation Diagram (P&ID)
31
11.03.2025
Process & Instrumentation Diagram (P&ID) Process & Instrumentation Diagram (P&ID)
Conventions Used for Identifying Instrumentation on P&IDs
All process information that can be measured in
Utility connections are the plant is shown on the P&ID by circular
identified by a numbered flags.
box in the P&ID.
This includes the information to be recorded and
The number within the used in process control loops.
box identifies the specific
utility. The circular flags on the diagram indicate where
the information is obtained in the process and
The key identifying the identify the measurements taken and how the
information is dealt with.
utility connections is
shown in a table on the Table 1.10 summarizes the conventions used to
P&ID. identify information related to instrumentation
and control.
32
11.03.2025
Process & Instrumentation Diagram (P&ID) Valve Symbols It is worth mentioning that in
virtually all cases of process control
in chemical processes, the final
control element is a valve.
Thus, all control logic is based on the
effect that a change in a given
flowrate has on a given variable.
The key to understanding the control
logic is to identify which flowrate is
being manipulated to control which
variable.
Once this has been done, it is a
relatively simple matter to see in
which direction the valve should
change in order to make the desired
change in the control variable.
33
11.03.2025
34
11.03.2025
35
11.03.2025
36
11.03.2025
The value of these diagrams does not end with the start-up of the plant. The design values on the diagram are
changed to represent the actual values determined under normal operating conditions. These conditions form a
“base case” and are used to compare operations throughout the life of the plant.
37
11.03.2025
1. Block Flow Diagram (BFD) (see Figure 1.1): The column was shown as a
part of one of the three process blocks.
38
11.03.2025
When accurate data are not available in the literature or when past experience does not give
an adequate design basis, pilot-plant tests may be necessary to design effective plant
equipment.
Equipment Specifications
If the equipment is standard, the manufacturer may have the desired size in stock.
In any case, the manufacturer can usually quote a lower price and give better
guarantees for standard equipment than for special equipment.
Before a manufacturer is contacted, the engineer should evaluate the design needs
and prepare a preliminary specification sheet for the equipment.
Preliminary specifications for equipment should show the following:
• 1. Identification
• 2. Function
• 3. Operation
• 4. Materials handled
• 5. Basic design data
• 6. Essential controls
• 7. Insulation requirements
• 8. Allowable tolerances
• 9. Special information and details pertinent to the particular equipment, such as materials of
construction including gaskets, installation, necessary delivery date, supports, and special
design details or comments
39
11.03.2025
Materials of Construction
The effects of corrosion and erosion must be considered in the design of chemical
plants and equipment.
Chemical resistance and physical properties of construction materials, therefore,
are important factors in the choice and design of equipment.
The materials of construction must be resistant to the corrosive action of any
chemicals that may contact the exposed surfaces.
Possible erosion caused by flowing fluids or other types of moving substances must
be considered, even though the materials of construction may have adequate
chemical resistance.
Structural strength, resistance to physical or thermal shock, cost, ease of
fabrication, necessary maintenance, and general type of service required,
including operating temperatures and pressures, are additional factors that
influence the final choice of construction materials.
Figure 3-7: Flow diagram for a conventional ethylene process using the front-end deethanizer process scheme
40
11.03.2025
• Design Data
The cracking yields for
feedstocks of either pure
ethane or pure propane are
listed in Table 3-2.
The yield distribution is based
on actual operating data of
present-day ethylene steam
crackers.
Design Data
The design bases and assumptions for the conventional base-case ethylene plant are
listed in Table 3-3.
All assumptions listed are those currently used in ethylene plants as verified by a
careful search of the literature.
41
11.03.2025
A more accurate product can only be determined by a simulation program that includes all the unit
operations.
The program includes the two hydrogenation steps and the loss of a small amount of ethylene with other
by-products.
For the base-case ethylene process, sensitivity calculations using the simulator are performed until
convergence matches the desired production capacity.
The material balance summary for the base-case
ethylene process.
42
11.03.2025
Equipment Design
For the preliminary design of the base-case ethylene process, this involves
The acetylene and ethylene hydrogenation reactions
are highly exothermic and are usually carried out in an Economic Assessment of Base-Case Design
adiabatic tubular reactor.
determining the size of the equipment normally selected in terms of An economic analysis of the base-case
Acetylene hydrogenation over Pd/Al2O3.
volume, surface area, or flow per unit time.
(palladium/alumina) catalyst in a fixedbed reactor is Capital Invesment ethylene process is necessary for
the favored industrial process since the acetylene
concentration can be reduced to less than 5 ppm while Production Costs comparing the profitability of this
process with the proposed design
undesirable hydrogenation of ethylene to ethane is
minimized. An adiabatic plug flow reactor model is Start-up Costs alternatives that utilize various
normally used to represent the operation of the
acetylene reactor. distillation/membrane hybrid
Based on this model, Fig. 3-17 shows the decrease in
configurations in the separation section
acetylene concentration as a function of reactor of the process.
volume.
Note for this adiabatic exothermic reaction in which The economic parameters and
the temperature increases along the length of the
reactor, the reaction virtually ceases when the reactor
conditions that are utilized in the base-
volume is increased beyond 2.5 m3 because of the case design and which are also used for
decrease in acetylene concentration. the modified process include
However, a volume of at least 5 m3 is required to lower plant location,
the desired acetylene concentration to about 2 ppm.
raw material costs,
This low acetylene concentration is only attained at
the endpoint of the reactor.
product costs,
utility costs,
The selectivity for the acetylene reaction is calculated
with the aid of Eq. (3-20) and is 89.1 percent. depreciation,
and tax rates.
Capital Investment
The estimated fixed-capital cost
tabulation is given in Table 3-9.
The probable error in this method of
estimating the fixed-capital investment
can be as much as ±20 percent.
However, since the probable error in
estimating the fixed-capital investment
associated with the proposed
modification in the separation section of
the ethylene process will be very similar,
this estimation procedure is acceptable
for making the economic comparison.
An example of such a tabulation is provided in Table 3-7, which lists design details and purchased cost of
individual pieces of equipment associated with the separation section of the ethylene process.
43
11.03.2025
Production Costs
Such costs include;
• direct costs - doğrudan maliyetler,
• indirect costs - dolaylı maliyetler, and
• general expenses - genel giderler.
Table 3-10 provides the cost in cents per kilogram for the raw materials, the utilities, and
the credit for the sale of by-products in the base-case ethylene process.
Direct costs for labor and maintenance in the conventional ethylene plant are generally
between 3 and 5 percent of the fixed-capital investment, with approximately one-half
of it for material replacements and one-half for maintenance labor.
For this preliminary design, 4 percent of the fixed-capital investment was designated for
maintenance charges.
The indirect costs include depreciation, taxes, insurance, and plant overhead charges.
For ethylene plants, the allowable depreciation rate typically ranges from 7 to 12 percent.
For the cost analysis, the depreciation rate was assumed to be 10 percent.
A production cost estimate for the One measure of profitability often used is the return on investment (ROI).
base-case ethylene design is
shown in Table 3-11.
The latter is defined as the annual profit before taxes, divided by the fixed-
capital investment.
The annual profit is the difference between the annual revenue and expenses.
Based on a price of 70.5 0/kg for the ethylene product, the ROI for the base-
case ethylene process before taxes is 25.1 percent.
44
11.03.2025
CHAPTER 4 As noted earlier, a schematic representation of a chemical process is made by the use
of a flowsheet.
Flowsheet Synthesis This chapter discusses two design procedures for flowsheet synthesis and design,
namely, the hierarchical and algorithmic methods.
and Development The former is based on heuristic rules derived from past experience, and the latter
utilizes mathematical programming procedures that include optimization
techniques.
A generalized hierarchical scheme for flowsheet Given a product that is to be manufactured, conduct a search of the technical and patent
synthesis and development is illustrated as a six- literature for information about the product.
step procedure in Fig. 4-1. Study market conditions and the pricing of the product.
These steps given below are not unique, but Key property data are obtained from the literature or must be estimated.
suggest an organized procedure to follow.
For a new product, there presumably may be laboratory and perhaps pilot-plant data plus a
market evaluation.
Figure 4-1. Flow diagram illustrating hierarchical process—flowsheet
synthesis, development, evaluation, and selection
45
11.03.2025
Figure 4-2
Development stages for sodium
dodecylbenzene sulfonate production; (a)
input/output diagram, (b) functions
diagram, (c) operations diagram, and (d)
final flowsheet.
46
11.03.2025
47
11.03.2025
All three of these require extensive research at the beginning of the design process, to Selection of appropriate reactions and reaction combinations usually proceeds by starting with the
determine the availability of existing designs or basic chemical processes that will enable desired product and working backward to the required feed materials.
production of the desired product.
The major chemically active functional groups in the target molecule are identified for this
procedure.
Functional groups are relatively stable groupings of atoms with potential external bonding sites.
The composition, structure, and bonding of many functional groups are fully identified and
available in ordered databases
Once the functional groups and their subassembly possibilities are known, the process of The ultimate decision is based largely on economic comparisons.
investigating functional-group assembly reactions produces a diagram of the molecular synthesis
train.
48
11.03.2025
EXAMPLE 4.2
Compare the product and raw material values for the five vinyl chloride reaction paths identified earlier based on a production
INPUT/OUTPUT STRUCTURE
of 1 kg of vinyl chloride.
The purpose of an investment in a chemical process is to produce a product and derive a It is clear from the results in the table that
reaction path 1 is not economical because of
profit.
the high price of acetylene and can therefore
The raw materials typically represent a substantial fraction of the total cost of producing a be eliminated.
product. Reaction paths 2 and 3 give the same result
because the net reaction is the same in both
Clearly, if the value of the products does not exceed the value of the raw materials, the cases. The literature makes it clear, however,
process cannot be economical. However, if the reverse is true, only further analysis can that when chlorine and ethylene react, the
find whether the process is truly economical. Any reaction path for which this is not true product is almost entirely EDC – 1,2-
can be eliminated from further consideration. Examination of the value of inputs relative to dichloroethane and not vinyl chloride.
outputs is therefore an important screening tool. Thus, reaction path 3 is chemically feasible,
For processes showing favorable economic potential, an input/output diagram can be but reaction path 2 is not and can also be
eliminated.
constructed that shows all the major material inputs and outputs as the basis for further
Reaction paths 4 and 5 show economic
analysis. potential although apparently less than that
Economic analysis of the vinyl chloride reactions, is described in Example 4-2. indicated for reaction path 3.
49
11.03.2025
The prices of the four species included have fluctuated over the 12-yr period shown.
It would be unwise to base the economics of a process on this unusually low price.
Therefore, the preliminary economic calculations for reaction paths 3, 4, and 5 have been recalculated using the average
A major factor that makes reaction path 3 price between 1990 and 2002 for ethylene, chlorine, vinyl chloride, and hydrogen chloride and the 8-year average for
oxygen as mentioned earlier.
appear attractive is the high price of the
The results are shown in the following table.
byproduct HCl coupled with the low price
of Cl2.
In fact, all the prices used should not be
just one-time values, but should be
examined over an extended period of time
when possible.
This has been done for the vinyl chloride
synthesis with the results presented in Fig.
4-3.
FUNCTIONS DIAGRAM
This step involves the identification of the major functions or subprocesses that must be achieved by the process
to produce the desired product.
A completed functions diagram is shown in Fig. 4-4.
The result is a diagram showing those functions with material flows for major products and raw materials.
50
11.03.2025
OPERATIONS DIAGRAM
Selection of the types of processing equipment, or unit operations, necessary to
accomplish the functions previously identified, along with specification of some of the
key conditions such as temperatures and pressures, is the next step. An operations
diagram is constructed indicating these choices.
Preprocessing
Reactors
Separations Methods
Heating and Cooling
Minimization of Processing
PROCESS FLOWSHEET
ALGORITHMIC FLOWSHEET GENERATION
The traditional approach to flowsheet synthesis employs a series of hierarchical steps to obtain a
The final steps in defining a flowsheet result.
are to estimate key equipment This is not a firm, concrete method, but rather the application of common sense, heuristics, and
performance parameters, improve the analysis.
mass balances, estimate approximate Therefore, flowsheets generated in this way are not necessarily even near optimal.
energy balances. An alternative method that involves an ordered, mathematical analysis is the algorithmic
approach.
Here mathematical tools are used to generate and evaluate all possible flowsheet arrangements to
possibly eliminate many of them as nonoptimal.
51
11.03.2025
The custom programs aimed at studying and implementing algorithms have demonstrated certain usefulness in a
limited number of studies. Software Use in Process
Design
They do, however, require human interaction at almost all stages of synthesis and are by definition customized to
specific study cases.
There are a number of commercial packages that are aimed at flowsheet synthesis.
The commercial packages are more widely applicable, but again usually require intensive human interaction and
constant supervision. Current software is therefore not sufficiently developed to allow completely autonomous
flowsheet synthesis and evaluation, although it does prove useful in analyzing very complex defined process systems
and in the generation of process arrangements once the processes have been defined.
As with all other aspects of engineering as well as those in everyday living, computer software use and utilization are now an
ingrained and indispensable part of process design and economic evaluation.
In the very first steps of the development process, computerized databases, research results, and electronic versions of
traditional publications aid in the selection of appropriate reactions and raw materials to determine potential chemical
processes that provide the desired product.
Computers are also useful whenever experimentation is required, to plan, run, and analyze the experiments.
Software can then be used to generate, evaluate, and select from the best process flow diagrams.
Computerized optimization of the process is then also possible using either dedicated optimization software or combinations of
non-optimization-specific software.
Once the process components and operating conditions are established, the physical arrangement of the process can also be
evaluated and optimized.
Finally, the schematics, drawings, and all the necessary planning aspects for constructing the process can be generated using
computers
52
11.03.2025
53
11.03.2025
CASH FLOW FOR INDUSTRIAL OPERATIONS CASH FLOW FOR INDUSTRIAL OPERATIONS
The flow of cash for the fixed-capital investment is usually spread over the entire construction period.
Depreciation is subtracted as a cost before income tax charges are calculated and paid, and net profits are
Because income from sales and the costs of operation may occur on an irregular time basis, a reservoir of reported to the stockholders.
working capital must be available to meet these requirements.
Consequently, removal of depreciation as a charge against profits is shown at the top of Fig. 6-1. The
The rectangular box in the Fig. 6-1 represents the operating phase for the complete project with working- depreciation charge dj is added to the net profit to make up the total cash flow for return to the capital reservoir.
capital funds maintained at a level acceptable for efficient operation.
The resulting gross profit of (sj — c0j — dj) that accounts for the depreciation charge is taxable. The income
Cash flows into the operations box as dollars of income sj from all sales while annual costs for operation, such tax charge-gelir vergisi is shown at the top of the diagram where it is removed in the amount (sj — c0j — dj)
as for raw materials and labor, but not including depreciation, are shown as outflow costs c0j. (Ф), where Ф is the fixed income tax rate-sabit gelir vergisi oranı designated as a fraction of the annual gross
These cash flows for income and operating expenses can be considered as continuous and represent rates of profits.
flow at a given time using the same time basis, such as dollars per day or dollars per year; the subscript j The remainder after income taxes are paid (sj — c0j — dj) (1 - Ф), is the net profit after taxes that is returned to
indicates the /th time period. the capital reservoir. When the depreciation charge dj is added to the net profit, the total project generated cash
Since, as discussed in Chap. 7, depreciation charges are in effect costs that are paid into the company capital flow returned to the capital reservoir on an annual basis is
reservoir, such charges are not included in the operation costs. Aj = (sj — c0j) (1 - Ф) + dj Ф
The difference between the income and operating costs sj — c0j is the gross profit before depreciation charge
and is represented by the vertical line rising out of the operations box.
54
11.03.2025
55
11.03.2025
The capital required for construction overhead and for all plant components that are not directly (4) cash kept on hand for monthly payment of operating expenses, such as salaries, wages, and raw
material purchases;
related to the process operation is designated the nonmanufacturing fixed-capital investment.
These plant components include the land; processing buildings, administrative and other offices, (5) accounts payable; and
warehouses, laboratories, transportation, shipping, and receiving facilities, utility and waste disposal (6) taxes payable.
facilities, shops, and other permanent parts of the plant. The construction overhead cost includes
field office and supervision expenses, home office expenses, engineering expenses, miscellaneous The ratio of working capital to total capital investment varies with different companies, but most chemical
plants use an initial working capital amounting to 10 to 20 percent of the total capital investment. This
construction costs, contractors' fees, and contingencies.
percentage may increase to as much as 50 percent or more for companies producing products of seasonal
In some cases, construction overhead is proportioned between manufacturing and nonmanufacturing demand, because of the large inventories which must be maintained for appreciable periods.
fixed-capital investment.
56
11.03.2025
57
11.03.2025
COST INDEXES
Most cost data that are available for making a preliminary or predesign
estimate are only valid at the time they were developed.
Because prices may have changed considerably with time due to Cost indexes can be used to give a general estimate, but no index can take into account
changes in economic conditions, some method must be used for all factors, such as special technological advancements or local conditions.
updating cost data applicable at a past date to costs that are
representative of conditions at a later time. The common indexes permit fairly accurate estimates if the period involved is less than
This can be done by the use of cost indexes. 10 years. Indexes are frequently used to extrapolate costs into the near future.
For example, the cost estimator may project costs forward from the time a study is being
A cost index-maliyet endeksi is an index value for a given time showing the done until the expected start-up time of a plant.
cost at that time relative to a certain base time.
If the cost at some time in the past is known, the equivalent cost at present
can be determined by multiplying the original cost by the ratio of the present
index value to the index value applicable when the original cost was obtained,
namely.
58
11.03.2025
59
11.03.2025
Purchased Equipment
The cost of purchased equipment is the basis of several predesign methods for estimating capital
investment. Estimating Equipment Costs by
Scaling
The various types of equipment can often be divided conveniently into (1) processing equipment, (2)
raw materials handling and storage equipment, and (3) finished-products handling and storage It is often necessary to estimate the cost
equipment. of a piece of equipment when cost data
are not available for the particular size
The sizes and specifications of the equipment needed for a chemical process are determined from or capacity involved.
the equipment parameters fixed or calculated along with the material and energy balances. According to this rule, if the cost of a
The most accurate method for determining process equipment costs is to obtain firm bids from given unit b at one capacity is known,
the cost of a similar unit a with X times
fabricators or suppliers.
the capacity of the first is X0,6 times the
Often, fabricators can supply quick estimates that will be close to the bid price but will not take too cost of the initial unit.
much time.
Second-best in reliability are cost values from the file of past purchase orders.
60
11.03.2025
Purchased-Equipment Delivery
Purchased-equipment prices are usually quoted as f.o.b. (free
METHODS FOR ESTIMATING CAPITAL
on board, meaning that the purchaser pays the freight). INVESTMENT
Clearly freight-nakliye costs depend upon many factors,
such as the weight and size of the equipment, distance from
source to plant, and method of transport. Various methods can be employed for estimating capital investment. The choice of any one
For predesign estimates, a delivery allowance of 10 percent
of the purchased equipment cost is recommended.
method depends upon the amount of detailed information available and the accuracy
desired.
Purchased-Equipment Installation
Installation of process equipment involves costs for labor, 1. Method A: Detailed-Item Estimate: A detailed-item estimate requires careful
foundations, supports, platforms, construction expenses, and
other factors directly related to the erection of purchased determination of each individual item shown in Table 6-1. Equipment and material needs
equipment. are determined from completed drawings and specifications and are priced either from
Table 6-5 presents the general range of installation costs as a current cost data or preferably from firm delivered quotations. Estimates of installation
percentage of the purchased-equipment costs for various
costs are determined from accurate labor rates, efficiencies, and employee-hour
types of equipment.
calculations.
Installation labor cost as a function of equipment size shows
wide variations and is difficult to predict.
This method, which is frequently used for preparing definitive and The expected accuracy is in the ±20 to 30 percent range.
preliminary estimates, also requires detailed estimates of purchased price It yields more accurate results when applied to projects similar in configuration to recently
constructed plants.
obtained either from quotations or index-corrected cost records and published
For comparable plants of different capacity, this method sometimes has been reported to yield
data. definitive estimate accuracies, that is, close to ±10 percent.
61
11.03.2025
Solution: Use the ratio factors outlined in Table 6-9 with modifications
for instrumentation and outdoor operation. Take instrumentation as 10
percent of fixed-capital investment, that is, 0.1(428/100), or 43 percent,
of the purchased equipment delivered. Take buildings as 15 percent of
purchased equipment.
These factors vary depending upon the type of process plant being considered.
The percentages given in Table 6-10 are rough approximations that hold for the types of process
plants indicated.
These values may be used as Lang factors for estimating the fixed-capital investment or the total
capital investment.
62
11.03.2025
This power has been found to average between 0.6 and 0.7 for many process
facilities.
Table 6-11 gives the capacity power factor x for various kinds of processing plants
per unit of annual production capacity. The turnover ratio is defined as the ratio of gross annual sales to fixed-capital investment:
Such values may be obtained from Table 6-11 by dividing investment values
by the corresponding capacity in the preceding column. Although these values
depend to some extent on the capacity of the individual plants, it is possible
to determine the unit investment costs which apply for average conditions. The reciprocal of the turnover ratio is sometimes called the capital ratio or the investment
ratio.
63
11.03.2025
Revenue comes from sale of the product or products produced by the plant. uncertain, and the time of the year for the beginning of start-up is unknown.
The total annual revenue from product sales is the sum of the unit price of each product multiplied After the first year, it is common to use the design annual capacity of the plant as the production and
This is based on the usual practice of rating the annual capacity of chemical plants as the actual
Annual sales revenue, $/yr = Σ(sales of product, kg/yr)(product sales price, $/kg)
annual production, with an allowance for downtime.
The third major component of an economic analysis is the total of all costs of
operating the plant, selling the products, recovering the capital investment, and
contributing to corporate functions such as management and research and
development.
These costs usually are combined under the general heading of total product cost.
The latter, in turn, is generally divided into two categories: manufacturing costs and
general expenses. Manufacturing costs are also referred to as operating or
production costs. Figure 6-7: Costs involved in total product
cost for a typical chemical process plant
64
11.03.2025
Annual cost is probably the best choice for the purpose of economic analyses. Moreover, annual
estimates;
(3) permit more rapid calculation of operating costs at less than full capacity, and
(4) provide a convenient way of considering large expenses that occur infrequently such as annual
planned maintenance shutdowns.
Figure 6-8: Spreadsheet for first-year, annual total
product cost for 100 percent capacity
Manufacturing Costs
Manufacturing Costs
Fixed charges are expenses which are practically independent of production rate.
All expenses directly connected with the manufacturing operation or the physical equipment of a process plant itself are included in
the manufacturing costs. Expenditures for depreciation, property taxes, insurance, financing (loan interest), and rent are usually
classified as fixed charges.
These expenses, as considered here, are divided into three classifications:
These charges, except for depreciation, tend to change due to inflation. Because depreciation is on a
(1) variable production costs,
schedule established by tax regulations, it may differ from year to year, but it is not affected by inflation.
(2) fixed charges, and
Plant overhead costs are for hospital and medical services; general plant maintenance and overhead, safety
(3) plant overhead costs. services, payroll overhead including social security and other retirement plans, medical and life insurance,
Variable production costs include expenses directly associated with the manufacturing operation. This type of cost involves and vacation allowances, packaging, restaurant and recreation facilities, salvage services, control
expenditures for raw materials (including transportation, unloading, etc.), direct operating labor, supervisory and clerical labor directly laboratories, property protection, plant superintendence, warehouse and storage facilities, and special
applied to the manufacturing operation, utilities, plant maintenance and repairs, operating supplies, laboratory supplies, royalties, employee benefits.
catalysts, and solvents. These costs are similar to the basic fixed charges since they do not vary widely with changes in production
These costs are incurred for the most part only when the plant operates, hence the term variable costs. rate.
65
11.03.2025
66
11.03.2025
CHAPTER 7
Interest, Time Value
of Money, Taxes, and
Fixed Charges
In the decision-making process, a careful analysis of the time value of money will help establish the worth of
earnings and investments.
Consideration must also be given to the effect of taxes on the net profit of the proposed project.
In addition to income taxes, there are other fixed charges such as property taxes, depreciation, and insurance.
This chapter examines the various forms of interest available to the borrower or the lender.
INTEREST INTEREST
Simple Interest
Interest-faiz is the cost of borrowed money, or the earnings on money loaned.
The simplest form of interest requires compensation payment at a constant interest rate based only on the
original principal.
Principal-anapara refers to the original amount or the remaining unpaid amount of a loan.
Thus, if $1000 were loaned for a total time for 4 years at a constant interest rate of 10 percent per year, the
Interest rate-faiz oranı is defined as the amount of money earned by, or paid on, a unit of principal in a unit simple interest earned would be;
of time, expressed as a fraction or percentage per year.
($1000) (0.1) (4) = $400
If P represents the principal, N the number of time units or interest periods, and i the interest rate based on
Interest paid-ödenen faiz is an expense of business operation that must be included in the analysis of the length of one interest period, the amount of simple interest I accumulated during N interest periods is;
business profitability.
I = PiN
The principal must be repaid eventually; therefore, the entire amount of principal plus simple interest due
after N interest periods is;
F = P + I = P(l + iN)
where F is the total amount of principal and accumulated interest at time N.
67
11.03.2025
INTEREST INTEREST
Compound Interest-bileşik faiz is almost universally used in business transactions. The compound amount earned after any discrete number of interest periods can be determined as follows:
Compound interest is the interest earned on accumulated, reinvested interest as well as the principal amount.
This applies to payments on loans or interest on investments.
Thus, an investment of $1000 at an interest rate of 10 percent per year payable annually would earn $100 in
the first year.
If no principal were removed and the interest were left in the investment to earn at the same rate, then at the
end of the second year;
Therefore, the total amount of principal plus interest earned after N interest periods is;
($1000 + $100)(0.10) = $110
F = P(l + i)N
in interest would be earned and the total compound amount would be;
The term (1 + i)N is commonly referred to as the discrete single-payment compound amount factor - (Tek
$1000 + $100 + $110 = $1210 ödemeli akümüle değer faktörü), or the discrete single-payment future-worth-tek ödemeli gelecek değer
faktörü factor. -
It is represented by the functional form (F/P, i, N), and;
(F/P, i, N) = (1 + i) N or
F = P (F/P, i, N)
INTEREST
Nominal and Effective Interest Rates
In common industrial practice, the length of the discrete interest period is taken to be 1 year, and the fixed
interest rate i is based on 1 year.
However, there are cases where other time periods are employed.
Even though the actual interest period is not 1 year, the interest rate is often expressed on an annual basis.
Consider an example in which the interest rate is 3 percent per period and the interest is compounded at
half-year periods.
A rate of this type is referred to as 6 percent per year compounded semiannually, or just 6 percent
compounded semiannually for simplification.
An interest rate stated as an annual rate but compounded other than annually is designated a nominal
interest rate.
The actual annual return (the effective interest rate) would not be 6 percent, but would be higher because of
the effect of compounding twice per year.
Whenever no period for interest is stated or obvious, assume it to be per year.
68
11.03.2025
INTEREST INTEREST
Nominal and Effective Interest Rates Nominal and Effective Interest Rates
The nominal interest rate does not take into account the compounding period. The effective interest rate The effective interest rate ieff is the rate which, when compounded once per year, gives the same amount of
does take the compounding period into account and thus is a more accurate measure of interest charges. money at the end of 1 year, as does the nominal rate r compounded m times per year.
The interest rate per period is r/m, and the amount at the end of the year, using Eq. (7-3), is;
A statement that the "interest rate is 10%" means that interest is 10% per year, compounded annually. In this
case, the nominal annual interest rate is 10%, and the effective annual interest rate is also 10%. However, if
compounding is more frequent than once per year, then the effective interest rate will be greater than 10%.
The more often compounding occurs, the higher the effective interest rate.
69
11.03.2025
In determining income taxes, interest on loans and bonds can be considered as a cost, while the A very common type, used for nearly all home mortgages and many business loans, calls for
return of both preferred and common stock cannot be included as a cost. constant periodic payments for a fixed period.
If the incremental annual income tax rate is 35 percent, every $1 spent for interest on loans or Each payment covers the current interest due and repays some of the remaining principal
bonds has a true cost after taxes of only $0.65. balance.
Thus, after income taxes are taken into consideration, a bond issued at an annual interest rate of 5 The total payment is constant, but the principal balance decreases, so that the interest portion of
percent actually has an interest rate of only (5)(65/100) = 3.25 percent. each payment is smaller than the previous one and the principal portion of each payment is larger
than the previous one.
70
11.03.2025
This earning power of money can be included in the analysis of business profitability.
71
11.03.2025
72
11.03.2025
The results show that the present and future worths are the same for both cash flows; therefore, the two cash
flows are equivalent at the specified interest rate.
This is true even though the patterns are very different and the actual totals of the two cash flows are somewhat
Figure 7-4: Series of unequal end-of-monlh cash flows different.
Therefore, in the case of a continuous cash flow, the cash flow is invested continuously as it is received. The most common choices are a compounding period of 1 year and the year-end convention for cash flow.
These two choices will be used for discrete times and cash flows throughout the rest of this chapter, unless
otherwise indicated.
If interest is compounded continuously, the rate of earning at any instant consists of two terms:
For simple cash flow patterns, such as a single amount as shown in Fig. 7-5 or equal flows for a period of years as
(1) a continuous, constant rate of cash flow P in dollars per period (usually 1 year) and presented in Fig. 7-6, it is possible to derive compounding and discount factors.
(2) the compound rate of earning on the accumulated amount M that has been invested at the rate r. Some of these were derived earlier in this chapter.
The rest of these factors will be presented without derivation and are available from many sources.
Table 7-3 shows the common compounding and discounting factors for case 1, discrete interest and discrete cash
flow.
These same factors are also applicable to case 3 since the final result is independent of the pattern of cash flow
over the year when interest for a year is calculated based on the amount of principal at the beginning of the year.
73
11.03.2025
INCOME TAXES
Corporate income taxes are levied by the governments and by some of the states as well.
State income taxes are often calculated by closely following federal policies.
Federal Income Taxes: Because the federal corporate income tax rate is as high as 39 percent of net profit,
it is an extremely important component in corporate planning.
To estimate corporate income tax for a new project, the actual incremental, or marginal, tax rate associated
with the taxable income added to corporate earnings should be used, if known.
For convenience, a rate of 35 percent will be used here, unless stated otherwise.
74
11.03.2025
The capital gain on items held for less than 1 year is designated as a short-term capital gain.
Land is not depreciable.
Under current income tax laws, the tax rate on a long-term capital gain is 20 percent, while that on a short-
For depreciable assets, such as buildings and equipment, profit is the selling price less the costs of selling, term capital gain is equal to the incremental income tax rate.
and less the cost of acquisition reduced by the amount of depreciation that has already been charged. Normally, a 35 percent rate can be used for estimates.
If total corporate operations show a loss within a given year, that loss can be carried back for up to 3 years These are considered part of the total employee benefits package which includes medical
to offset past profits; or they may be carried forward for up to 5 years to offset future profits.
insurance and retirement plans that are usually combined with wages to obtain labor costs.
A particular project may be profitable overall, but show losses in one or more years.
In such cases, the question arises as to whether the losses should be used to reduce overall corporate income
Such benefits depend upon individual corporate benefits plans, but a typical value is 40 percent of
taxes or whether these reductions should be used as a "negative income tax" in the evaluation of the process. wages.
Even though it may be realistic to do so, it is unwise to use this argument for justifying the economic
viability of a project. Here, again, company policy determines the decision.
75
11.03.2025
In addition to income taxes, property and excise taxes may be levied by federal, state, or local Excise taxes (Tüketim vergileri) are levied by federal and state governments.
governments. Excise taxes include charges for import customs duties, transfer of stocks and bonds, and a large number of
similar items.
Taxes of this type are referred to as direct since they must be paid directly by the particular
business and cannot be passed on as such to the consumer. Manufacturers and retailers excise taxes are levied on the sale of many products such as gasoline and
alcoholic beverages.
Property taxes may vary widely from one locality to another, but the average annual amount of
these charges is 1 to 4 percent of the assessed valuation. Taxes of this type are often referred to as indirect since they can be passed on to the consumer.
For economic evaluation purposes, 2 percent of the fixed-capital investment in a project is a Many businesses must also pay excise taxes for the privilege of carrying on a business or manufacturing
typical property tax rate charge. enterprise in their particular localities.
Excise taxes are included in economic evaluations only when they are known to apply specifically to the
project under consideration.
FIXED CHARGES
Among the many costs included in the total product cost, as listed in Fig. 6-7, are a group of fixed charges.
The first three of these charges — depreciation, property taxes (discussed above), and insurance — are
costs related to the capital investment in a project.
Once the facility for the project has been built, these charges are fixed.
The other fixed charge, rent, is also fixed if there has been a contractual agreement for the rental of space.
These charges are fixed in that they are not related to the activity level of the plant and continue even if the
plant does not operate.
Interest is sometimes included as a fixed charge, but because of its importance has been treated separately in
this chapter.
76
11.03.2025
Depreciation is an unusual charge in that it is paid into the corporate treasury. One common type of functional depreciation is obsolescence.
Depreciation, has a significant effect on corporate cash flow. This is caused by technological advances which make an existing property obsolete.
The concept of depreciation is based upon the fact that physical facilities deteriorate and decline in Other causes of functional depreciation could be;
usefulness with time; thus, the value of a facility decreases.
(1) decrease in demand for the service rendered by the property,
Physical depreciation is the term given to the measure of the decrease in value of a facility due to changes
(2) shifts in population,
in the physical aspects of a property.
(3) changes in requirements of public authority,
Wear and tear, corrosion, accidents, and deterioration due to age or the elements are all causes of physical
depreciation. (4) inadequacy or insufficient capacity, and
With this type of depreciation, the serviceability of a property is reduced because of the physical changes. (5) abandonment of the enterprise.
Depreciation due to all other causes is known as functional depreciation.
Depreciation is more than an artifact, however, because of the effect it has on the amount of income tax that For example, patents and copyrights are amortizable.
a corporation must pay.
77
11.03.2025
FIXED CHARGES
Depreciable Investments:
In general, all property with a limited useful life of more than 1 year that is used in a trade or business, or held for the
production of income, is depreciable.
Physical facilities, including such costs as design and engineering, shipping, and field erection, are depreciable.
Land is not depreciable, but improvements to the land, such as grading and adding utility services, are depreciable.
Working capital and start-up costs are not depreciable. Inventories held for sale are not depreciable.
Amortisman Ayırma Şartları:
In project terminology, the fixed-capital investment, not including land, is depreciable. •İşletmede bir yıldan fazla kullanılabilir olması
Maintenance is necessary for keeping a property in good condition; repairs connote the mending or replacing of broken •Yıpranmaya, aşınmaya veya kıymetten düşmeye maruz bulunması
or worn parts of a property.
•Değerleme gününde envantere dahil ve kullanıma hazır olması
The costs of maintenance and repairs are direct operating expenses and thus are not depreciable. •İktisadi kıymetin değerinin 900 TL’yi (2017 yılı için) aşması
The total amount of depreciation that may be charged is equal to the amount of the original investment in a property—
no more and no less.
The method of determining depreciation may be different for purposes of obtaining the book value than that which is If the property is not useful, it can often be sold for material recovery. Income obtainable from this type of disposal is
used for income tax puiposes, depending on corporate policy. known as scrap value.
The price that could be obtained for an asset if it were sold on the open market is designated the market value. As of 2002, tax laws do not permit considering salvage or scrap value in the calculation of depreciation.
It may be quite different from the book value and clearly is important for determining the true asset value of the Income from the sale of used property, to the extent that it exceeds the undepreciated value of the property, is therefore
company. taxed as a capital gain.
If the net sale price is less than the undepreciated value, it is not taxable but it is included as an income to the project at
the time of the sale.
78
11.03.2025
FIXED CHARGES
Recovery Period:
The period over which the use of a property is economically feasible is known as the service life
of the property.
The period over which depreciation is charged is the recovery period, and this is established by tax
codes.
While originally the recovery period was at least approximately related to the service life, the
reality now is that there is little relationship between the two.
Recovery periods for some chemical- and process-industries related depreciation are shown in
Table 7-8.
79
11.03.2025
• A proposed investment must be evaluated for its economic feasibility. When a new
technical project is proposed, a design study must be carried out.
CHAPTER 8 The design study produces specifications from which cost estimates can be made.
These cost estimates, in turn, become the data for evaluating the economic
Profitability, Alternative consequences of the project.
This chapter introduces principles and methods for carrying out economic evaluations.
Investments, and • In the economic evaluation of a particular project, there are always alternative uses
for the resources.
Replacements For example, the available capital can be invested in another project or projects, or
invested in various financial instruments such as stocks, bonds, and savings accounts.
Since economic evaluation is always performed in the context of these alternatives,
evaluation methods must permit rational comparisons of these alternatives.
Several such methods are discussed in this chapter.
• Equipment replacement strategy also is reviewed in the light of these economic
evaluation criteria.
A profitability standard is a quantitative measure of profit with respect to the investment required to generate that profit. The cost of capital based upon corporate experience is often used as a basic profitability standard.
Profit is the goal of any investment, but maximizing profit is an inadequate profitability standard. Cost of capital is the amount paid for the use of capital from such sources as bonds, common and preferred stock, and
loans.
The profit must be judged relative to the investment. For example, suppose two equally sound investment opportunities
are available. The cost of capital after income taxes is found by weighting the cost of each of these outside sources according to its
fraction of the total capital from these sources.
One of these requires a $ 100,000 capital investment and will yield a profit of $ 10,000 per year, while the second
requires $1 million of capital investment and will yield a profit of $25,000 per year. Bond dividends and loan interest are contractual amounts and as such are charged as an expense of doing business.
While the second investment provides a greater yearly profit than the first, the annual rate of return on that investment The argument for using the cost of capital as a basic profitability standard is that any project must earn at least that
is only ($25,000/$l,000,000)(100), or 2.5 percent, while it is 10 percent for the first investment. If one had $1 million rate just to repay these external capital sources.
to invest and there were no alternative uses for these funds, then one might select the second investment.
However, because there are numerous reliable alternatives, such as bonds, that will yield annual returns greater than 2.5
percent, the second investment is not attractive.
In this case, it would be thadvisable to invest $100,000 in the first alternative, assuming that it is not significantly more
risky than the second alternative, and invest e remaining $900,000 in other reliable alternatives that provide higher
annual returns.
80
11.03.2025
A commonly used profitability standard is the minimum acceptable rate of return (also known as the minimum attractive The basic, safe value selected for mar is then normally adjusted to account for the uncertainties associated with a new
rate of return, or MARR). project.
The minimum acceptable rate of return is a rate of earning that must be achieved by an investment in order for it to be From the unknown future behavior of the overall economy to the uncertain future of price and demand for a particular
acceptable to the investor. product, there are risks associated with investing in a project.
The symbol mar will be used for the minimum acceptable annual rate of return, and it is used as a fraction per year but The risk is further increased whenever most of the capital is invested in equipment and plant construction, because that
often expressed as a percentage per year. capital is not liquid; that is, it is not easily recoverable on demand.
The mar generally is based on the highest rate of earning on safe investments that is available to the investor, such as Therefore, the practice is to adjust the safe cost of capital or earning rate in order to make the minimum acceptable rate
corporate bonds, government bonds, and loans. of return commensurate with the risk.
The argument for this choice is that any investment in a project must show earnings at a rate that is at least equal to the There is no given formula for doing this.
highest safe alternative opportunity available to a company or corporation.
The compensation for risk is largely a judgment call established for each corporation by upper management. Some
The cost of capital can be used as an alternative basis from which to establish a minimum acceptable rate of return. guidance for establishing this level of risk compensation is suggested below.
Suppose that a corporation has a weighted cost of capital, based on Table 7-1, of 8 percent per year after taxes.
PROFITABILITY STANDARDS
Minimum Acceptable Rate of Return
This rate of return on safe investments available to the company likewise could be used as the value for mar.
If 8 percent per year is used as the after-tax rate of earning on all the investment in the project, including that
from corporate funds as well as from outside sources, then just enough funds are available to pay the
dividends and interest on the outside capital sources and provide earnings at that same rate on the corporate
investment. Such a rate of earnings on the corporate investment is not likely to be considered satisfactory to
either management or shareholders.
Rather, the basic rate is increased sufficiently to make it attractive in the face of risk, thereby arriving at a
mar value that can be used in project evaluations.
The cost of capital and the rate of earnings on alternative investments are generally expressed as a single,
end-of-the-year amount after income taxes, calculated as a percentage per year of the capital obtained or
invested.
This is equivalent, in project terms, to the net profit divided by the total capital investment (Net Profit/Total
Capital Investment).
81
11.03.2025
PROFITABILITY STANDARDS
Minimum Acceptable Rate of Return
Various degrees of risk and corresponding mar values are presented in Table 8-1.
These are suggestions, for use when no other guidance is supplied, inferred from rates of return used in numerous
sources.
For new products that require large investments in research, development, and testing before their future is determined,
such as biotechnology products, the minimum acceptable return may be even higher than those listed in the table,
especially for the earlier stages of the project study.
82
11.03.2025
• The methods that do not consider the time value of money include; Table 8-2 shows the results of a recent survey on the use of these methods in economic analyses.
rate of return on investment, Table 8-2 notes that there are methodology differences between small and large companies and also indicates that large
companies often use more than one method.
payback period, and
net return.
Where;
ROI: the annual return on investment expressed as a fraction or percentage per year, (Yatırım Getirisi)
This definition agrees with the way in which the m ar values in Table 8-1 are defined.
Gross profit, before income taxes, or cash flow is sometimes used in place of net profit. Fixed-capital investment can
be used rather than total investment. Corporate policy or the preference of the resource analyst determines the choice.
83
11.03.2025
Net profit usually is not constant from year to year for a project; total investment also changes if additional An ROI calculated from any of these three prior equations can be compared directly with a mar value supplied or
investments are made during project operation. In such a case, no one year is necessarily likely to be representative of selected from Table 8-1.
the entire project life; therefore, it becomes a question of what value to use for the net profit in Eq. (8-la).
If the ROI equals or exceeds the minimum acceptable rate of return m ar then the project offers an acceptable rate of
The recommended procedure is to take the average ROI over the entire project life as given by return.
If it does not, then the conclusion is that the project is not desirable for the investment of either borrowed or corporate
funds.
where N is the evaluation period, Np,j the net profit in year j, —b the year in which the first investment is made in the
project with respect to zero as the start-up time, and F the total capital investment in year j.
Note that for j > 0, that is, anytime after the original investment, Fj may often be zero or at most small compared to the
original investment, and the denominator can be replaced by the initial total capital investment to simplify Eq. (8-1b) to
The profitability measure of payback period, or payout period, is the length of time necessary for the total return to It is subject to the fact that the cash flow usually changes from year to year, thereby raising the question of which
equal the capital investment. annual values to use. A particular year can be selected, or the average of the Aj values may be used to give;
The initial fixed-capital investment and annual cash flow are usually used in this calculation, so the equation is;
PBP is the payback period in years, A PBP calculated from either Eq. (8-2a) or (8-2b) should be compared to a PBP obtained from the minimum acceptable
rate of return.
V the manufacturing fixed-capital investment,
Because V + Ax is approximately equal to 0.85F and (Aj)ave is equal to Np,ave + dj,ave = marF + 0.85F/N,
Ax the nonmanufacturing fixed-capital investment,
(8-2c)
V + Ax the fixed-capital investment, and
It is subject to the fact that the cash flow usually changes from year to year, thereby raising the question of which
annual values to use.
84
11.03.2025
Another profitability measure is the amount of cash flow over and above that required to meet the minimum acceptable
rate of return and recover the total capital investment.
This quantity is calculated by subtracting the total amount earned at the minimum acceptable rate of return, as well as
the total capital investment, from the total cash flow .
Each of these quantities represents the total amount obtained over the length of the evaluation period. where Rn is the net return in dollars and recj the dollars recovered from the working capital and the sale of physical
assets (equipment, buildings, land, etc.) in year j.
The net return is given by;
By noting that the sum of dj plus the sum of the recovered amounts is equal to the total capital investment or the sum
of F, the equation simplifies to
EXAMPLE 8-1: Calculation of Profitability Measures Not Considering Time Value of Money – Page:325
85
11.03.2025
The net present worth (NPW) is the total of the present worth of all cash flows minus the present worth of all The appropriate discount rate to use for discrete compounding is the minimum acceptable rate of return or m ar
capital investments, as defined by; originally selected as the evaluation standard. For continuous compounding the nominal interest rate is used, as given
by;
where rma is the minimum acceptable nominal rate for continuous compounding.
The net present worth is the time value of money equivalent of the net return defined in Eq. (8-3).
where NPW is the net present worth, PWFcf,j the selected present worth factor (from Table 7-3, 7-4, or 7-5) for the cash
flows in year j, sj the value of sales in year j, coj the total product cost not including depreciation in year j, PWFv,j the If the net present worth is positive, then the project provides a return at a rate greater than the discount (earning) rate
appropriate present worth factor for investments occurring in year j, and Fj the total investment in year j. used in the calculations.
An earning rate is incorporated into the present worth factors by the discount rate used. In making comparisons of investments, the larger the net present worth, the more favorable is the investment.
Thus, the net present worth is the amount of money earned over and above the repayment of all the investments and the If the net present worth is equal to zero, then the project provides a return that matches the discount rate.
earnings on the investments at the discount (earning) rate used in the present worth factor calculations.
In either of these cases, the project is judged as favorable compared to the mar selected.
If the net present worth is less than zero, then the project rates unfavorably with respect to the mar standard.
The discounted cash flow rate of return, or DCFR, is the return obtained from an investment in which all investments
and cash flows are discounted. It is determined by setting the NPW given by Eq. (8-4) equal to zero and solving for the
discount rate that satisfies the resulting relation. Thus,
The DCFR is only of concern when the project rates favorably compared to the value of m ar used in calculating the net
present worth. Clearly, if the NPW that is calculated equals zero, then the mar or ram used is the DCFR. However, if the
NPW is greater than zero, then the DCFR must be calculated from Eq. (8-6). Since the discount rate appears in
377.45
numerous exponents, it is generally impossible to solve for the discount rate analytically and an iterative solution is
required.
As guidance, the discounted cash flow rate of return will be greater than the mar or ram used. Thus, the mar or ram
value used is a good starting point. When the NPW is favorable, the DCFR will necessarily be favorable and will be the
actual earning rate of the investment. The two methods—net present worth and DCFR—are nearly always used
together.
86
11.03.2025
EBITDA
It is an acronym for
FAVÖK
which is a shorthand notation for
87
11.03.2025
The net present worth method, combined with the discounted cash flow rate of return method,
is strongly recommended for making economic decisions.
These methods not only include all the pertinent information of the other methods, but also take
into account the time value of money. In that way they give a more realistic picture of the value of
the earnings in relationship to the investment than do those methods that do not include the time
value of money.
Income tax effects can be included in all the evaluation methods, and there is no good reason not
to include them. Income taxes affect the net profit and cash flow into the corporate treasury, but
not the capital investment.
Thus, taxes impact all measures of return with respect to investment, and that includes all five
profitability measures considered here. Table 8-3 reviews the quantities involved in order to
emphasize and clarify many of these income tax effects.
It is recommended that all investment opportunities that are being analyzed be compared using the
same profitability methods.
Since each of the methods discussed has advantages and disadvantages, it is reasonable to apply
and examine the results obtained from each one in the course of any economic analysis. However,
it is quite possible to compare a series of alternative investments by any one of the profitability
methods discussed and find that different alternatives could be recommended depending on the
evaluation technique used.
If there is any question as to which method should be used for a final determination, the net
present worth method should be chosen, since this specific method best accounts for the factors
affecting the profitability of the investment.
88
11.03.2025
89
11.03.2025
90
11.03.2025
After plant construction has been completed, there is a start-up period during which all units are tested for operational During start-up, it sometimes becomes apparent that equipment changes have to be made before the plant can operate at
characteristics and safety. The start-up period process is continued until the desired operating conditions with proper maximum design conditions.
control have been achieved. Depending on the complexity of the plant and the experience of the engineering and
operating personnel, this period may last from a few weeks to as long as a year with little acceptable product being These changes involve expenditures for materials and equipment that become part of the capital investment.
produced.
It is usually expected that such investments will be relatively small and are to be covered from the contingency
In the overall cost analysis, start-up expenses over and above normal operating expenses are represented as a one-time allowance; but a separate investment entry for these items may be included in the estimate if it is desired to monitor
only expenditure in the first year of the plant operation. These start-up expenses can vary from 5 to 20 percent of the their expense.
fixed-capital investment. A typical value is 10 percent.
Losses in product revenue due to such changes are usually included in the capacity allowance mentioned in the previous
The production rate for the first year of operation of a new plant is usually estimated as a fraction of the annual design paragraph.
capacity because of unproductive time at start-up, and because start-up may begin at any time of year. In preliminary
economic estimates, it is common to use a fraction of one-half of annual capacity for the first year. This fraction, of
course, has a profound impact on the sales revenue and variable expenses for that period, and it may be changed as a
start-up date becomes more accurately known.
Figure 8-1 shows the structure of a model spreadsheet for performing the economic evaluation calculations
described above. The user of the spreadsheet inputs basic data from, for example, the spreadsheets in Figs.
6-7 and 6-8.
Minimal required user inputs are at the top of Fig. 8-1 and in items 1, 9, and 11. The user may modify
default values and relations as needed for a particular project. The five profitability measures considered
here are calculated and tabulated near the bottom of the spreadsheet.
91
11.03.2025
92
11.03.2025
ALTERNATIVE INVESTMENTS
Alternatives When an Investment Must Be Made
The alternatives should then be compared with the base plan, and an additional investment would be
recommended only if it gave a definite advantage.
When investment comparisons are made, alternatives requiring more initial capital are compared only with
lower investments that have been found to be acceptable.
Consider an example in which an investment of $50,000 will give a desired result, while alternative
investments of $60,000 and $70,000 will give the same result with less annual expense. Suppose that
comparison between the $60,000 and the $50,000 cases shows the $60,000 investment to be unacceptable.
Certainly, there would be no reason to give further consideration to the $60,000 investment, and the next
comparison should be between the $70,000 and the $50,000 cases. In making a choice among various
alternative investments, it is necessary to recognize the need to compare one investment to another on a
mutually exclusive basis in such a manner that the return on the incremental investment is satisfactory.
Example 8-6 illustrates this principle.
93
11.03.2025
Because the indicated percent return for each of the first three designs is above the minimum of 15 percent
required by the company, any one of these three designs would be acceptable. Now it becomes necessary to
choose one of the three alternatives. One way to do this is by using the method of return on incremental
investment.
Analysis by means of return on incremental investment is accomplished by a logical step-by-step
comparison of an acceptable investment to another investment that might be better.
If design 1 is taken as the starting basis, comparison of design 2 to design 1 shows that an annual saving of
$3000 — $2000 = $1000 is obtained with an additional investment of $6000.
Thus, the percent return on the incremental investment is (1000/6000)(100) = 16.7 percent. Design 2 is
acceptable by company policy in preference to design 1.
Comparing design 2 to design 3, the annual percent return is (200/4000)(100) = 5 percent.
Thus, design 3 compared to design 2 shows that the incremental return is unacceptable, and design 2 is the
preferred alternative.
REPLACEMENTS REPLACEMENTS
The term replacement, as used in this chapter, refers to a special type of alternative in which facilities are 2. The existing property is capable of yielding the necessary product or service, but more efficient
currently in existence and it may be desirable to replace these facilities with different ones. Although equipment or property is available which can operate with lower expenses.
intangible factors may have a strong influence on decisions relative to replacements, the design engineer When the reason for a replacement is of the first general type, the only alternatives are to make the
must understand the tangible economic implications when a recommendation is made as to whether existing necessary changes or else go out of business. Under these conditions, the final economic analysis is usually
equipment or facilities should be replaced. The reasons for making replacements can be divided into two
reduced to a comparison of alternative investments.
general classes, as follows:
The correct decision as to the desirability of replacing an existing property that is capable of yielding the
1. An existing property in order to continue operation and meet the required demands for service or
necessary product or service depends on a clear understanding of theoretical replacement policies plus a
production must be replaced or changed. Some examples of reasons for this type of necessary replacement
careful consideration of many practical factors. To determine whether a change is advisable, the operating
are that
expenses with the present equipment must be compared with those that would exist if the change were
a. The property is worn out and can give no further useful service. made.
h. The property does not have sufficient capacity to meet the demand placed upon it. Practical considerations, such as amount of capital available or benefits to be gained by meeting a
competitor's standards, may also have an important effect on the final decision.
c. Operation of the property is no longer economically feasible because changes in design or product
requirements have caused the property to become obsolete.
94
11.03.2025
EXAMPLE 8-9: An Extreme Situation to Illustrate Result of Replacement Economic Analysis EXAMPLE 8-9: An Extreme Situation to Illustrate Result of Replacement Economic Analysis
A new manufacturing unit has just been constructed and put into operation by a midwestern company. The Solution
basis of the manufacturing process is a special computer for control (designated as the OVT computer) as The before-tax annual cost of continuing to operate the OVT computer is the cash expense plus
developed by the research department. The plant has now been in operation for less than one week and is depreciation, or 250,000 + 2,000,000/10 = $450,000.
performing according to expectations.
The total capital investment for the OVT computer is completely lost if the NTR computer is installed; thus,
However, a new computer (designated as the NTR computer) has just become available on the market. This the total investment in the NTR is $1,000,000.
new computer can easily be installed to replace the present computer and will provide the same process The after-tax savings based on a 35 percent tax rate will be (450,000)(0.65) - [50,000 + (1,000,000/10)]0.65.
control at considerably less annual cash expense because of reduced maintenance and personnel costs. or $195,000. The rate of return on this investment is (195,000/1,000,000)( 100), or 19.5 percent.
However, if the new computer is installed, the present computer is essentially worthless because there is no This after-tax return is most likely satisfactory to the company for a safe, though unnecessary, investment. If
other use for it. The pertinent economic information relative to the two computers is shown here: so, then the replacement should be recommended. If the return is not satisfactory, then the possibility of a
corporate capital gains tax reduction on the capital loss for the OVT computer should be investigated and
factored into the calculation.
Because of the reduced costs for the NTR computer, a profitability evaluation method that includes the time
value of money will tend to favor the replacement even more than the rate of return method on ivestment
used in the solution of this example.
What recommendation should be made relative to replacing the present $2,000,000 computer with the new
computer?
Optimum Design •
•
processing equipment used,
arrangement and sequencing of the processing equipment used in the design, and
and Design Strategy • the actual physical parameters for the equipment.
The optimum for a process design is the most cost-effective selection, arrangement, sequencing of
processing equipment, and operating conditions for the design.
95
11.03.2025
When a design variable is changed, often some costs increase and others decrease.
Under these conditions, the total cost may go through a minimum at one value of the particular design
variable, and this value is the optimum value of that variable.
An example illustrating the principles of an optimum economic design is presented in Fig. 9-1. In this
simple case, the problem is to determine the optimum thickness of insulation for a given steam pipe
installation.
As the insulation thickness is increased, the annual fixed costs increase, the cost of heat loss decreases, and
all other costs remain constant.
Therefore, as shown in Fig. 9-1, the sum of the costs goes through a minimum, and this determines the
optimum insulation thickness.
Although profitability or cost is generally the basis for optimization, practical and intangible factors usually
need to be included as well in the final investment decision.
Examples of process decision variables, and dependent variables include operating conditions such as
temperature and pressure as well as equipment specification variables such as the number of trays in a
distillation column.
96
11.03.2025
Further simplification may also be possible through suboptimization of sections of the overall design, either On the basis of the profitability analysis discussed earlier, it is proposed that the best strategy is one that
as a basis for subsequent overall design optimization or for direct analysis. favors those investments that meet or exceed an established minimum acceptable rate of return for each
investment, but that also ensures that no investment is made which does not meet that acceptable return
standard.
When several discrete investment alternatives are being compared, an effort should be made first to identify optimization.
the smallest investment that meets the minimum acceptable rate of return standard. This should be followed Structural optimization consists in finding one or more "best" flowsheets for a process.
by comparing the return on the incremental investment for each alternative to the best previous alternative
Selection of one or several "best" flowsheets is done by economic comparisons of these candidates.
to determine whether the incremental investment meets the prescribed standard.
Typically, a few near optimal flowsheets are obtained by establishing several feasible flowsheets and then
For optimization purposes, the methods of return on investment, payback period, and discounted cash flow
comparing their net present worths or annualized costs.
rate of return are not ideal, since it may be possible to invest more than indicated at the maximum or
One or more of these is then subjected to parametric optimization, and the most economically attractive one
minimum of these measures and still earn a rate that is equal to or above the return standard.
is selected.
The other two profitability methods — net return and net present worth —are recommended as the basis
for the objective function in optimization problems. Of these two, the net present worth method is more
strongly recommended because it includes the time value of money.
97
11.03.2025
Some of the more obvious examples of such decisions are operating conditions, recycle ratios, and stream However, this type of selection is qualitative and therefore can lead to overlooking influential variables or
properties such as flow rates and compositions. including unnecessary variables and thus needlessly complicating the optimization requirements.
In addition to the decision variables common to most processing equipment, every type and variant of A more quantitative selection is possible if process models are available.
process equipment may have from one to several unique decision variables. Thus, parametric optimization
The model analysis variable selection route is more involved and time consuming, but it does lead to
problems often involve hundreds of decision variables, including many that are common to multiple pieces quantifiable results.
of equipment such as operating pressure and temperature. In this way a balance is struck between the
increased difficulty of high-variable number optimization and optimization accuracy.
Practical considerations are realities and uncertainties that may be difficult to include in an optimization procedure Application programming is the practice of assembling the mathematical relationships that describe a
or that require special treatment or judgment. design process and its economic behavior and then using these relationships to explore and optimize the
Other realities, such as the benefits of early entry of a product into a market, financing windows of opportunity design.
and limitations, and fabrication and construction lead times may be difficult to program, but can be very important There are no generalized systematic programming practices that can be applied to all designs. Instead, a
to the success of a project. number of programming methods have been developed for the various kinds of optimization situations most
Uncertainties include such factors as future economic and market conditions, dependability of raw material and commonly encountered.
intermediate supplies, and unproven technologies. This categorization yields two optimization situations, linear integer programming (LIP) and mixed-
Intangible considerations are factors that are not quantifiable. Some examples are corporate image, investors' integer linear programming (MILP).
perceptions, community and labor relations, and compatibility with corporate product lines and policies. Such
factors may be important in corporate planning and decision making, and the inclusion of such considerations in
investment decisions is one of the main responsibilities of top corporate officers.
98
11.03.2025
Another widely used continuous constrained optimization type is linear programming. Linear programming is
widely used because of both its relative simplicity and wide availability of good general-purpose linear
optimization algorithms and practices, and because many real-world situations can be converted to linear behavior
without too much difficulty or loss of accuracy. Further, the reduction to linear programming often does not result
in acuity losses, especially in cases where model and data accuracy is inexact or not well known.
Linear Programming
One strategy for simplifying the approach to a programming problem is based on expressing the constraints
and the objective function in a linear mathematical form.
where the coefficients a,... ,n and b are known values and V1,..., Vn are unknown variables.
As an example to illustrate the basic methods involved in linear programming for determining optimum
conditions, consider the following simplified problem.
99
11.03.2025
Water (W) can be added to the blend at no cost. What volume combination of the two beers in stock with
water, including at least 40 liters of beer A, will give the minimum ingredient cost for the 400 liters of 4
percent beer?
This example is greatly simplified because only a few constraints are involved and there are only three
independent variables, that is, volume of beer A (VA), volume of beer B (VB), and volume of water (Vw).
100
11.03.2025
Linear Programming
Intuitive Approach to Problems Involving Linear Programming
It can be seen intuitively, from Eqs. (9-6) and (9-7), that the minimum value of the objective function C
occurs when Vw is zero. Therefore, the optimum value of VA from Eq. (9-6) is 150 liters, and the optimum
value of VB from Eq. (9-2) is 250 liters.
Figure 9-3 is the graphical representation of this problem. Line OE represents the overall constraint placed
on the problem by Eqs. (9-2), (9-3), and (9-4). The parallel dashed lines represent possible conditions of
cost. The goal of the program is to minimize cost (i.e., minimize C) while still remaining within the
constraints of the problem. The minimum value of C that still meets the constraints occurs for the line OD,
and the optimum must be at point O. Thus, the recommended blend is no water, 150 liters of A, 250 liters of
B, for a total cost C of $31.00 for 400 liters of blend.
Although the simplicity of this problem makes it trivial to use a computer for solution, the following is presented to The basic problem in linear programming is to maximize or minimize a linear function of a form shown in
illustrate the basic type of reasoning involved in developing a computer program for the linearized system.
Eq. (9-1).
An iterative procedure must be used for the computer solution to permit the computer to make calculations for repeated
possibilities until the minimum objective function C is attained. In this case, there are four variables (VA, VB, VW and S)
and three nonzero constraints (total volume, final alcohol content, and VA = 40 + S). Because the number of real
variables cannot e0XFFGI6xceed the number of nonzero constraints, one of the four variables must be zero. Thus, one There are various strategies that can be developed to simplify the methods of solution, some of which can
approach for a computer solution merely involves solving a 4 x 3 matrix with each variable alternatively being set equal
lead to algorithms that allow rote or pure number-plugging methods of solution that are well adapted for
to zero, followed by instruction that the desired combination is the one giving the least total cost.
machine solution.
The structure and implementation of the many computerized procedures for linear programming solutions are beyond
In linear programming, the variables vi,..., vj are usually restricted (or can be transformed) to values of zero
the scope of this text. However, there are many such procedures, or algorithms, available today, some of which are
or greater. This is known as a nonnegativity restriction on vj; that is,
described later in the chapter.
101
11.03.2025
Linear programming is concerned with solutions to simultaneous linear equations where the equations are
developed on the basis of restrictions on the variables. Because these restrictions are often expressed as
inequalities, it is necessary to convert these inequalities to equalities. This can be accomplished by the
Again, f' is generally nonlinear, and h and g may also be nonlinear. All are usually assumed to be smooth,
inclusion of a new variable designated as a slack variable.
typically twice differentiable.
For a restriction of the form;
The programming approaches to solving these types of problems are more varied than those for linear
problems, and a combination of methods is common.
However, a number of major approaches account for most nonlinear programming and are representative of
the methodologies employed in nonlinear programming.
The major approaches are successive linear programming (SLP), successive quadratic programming
(SQP), augmented Lagrangian methods or method of multipliers, and generalized reduced gradient
(GRG) methods.
102
11.03.2025
When two or more independent variables affect the objective function, the procedure for determining the
optimum conditions may become rather tedious; however, the general approach is the same as when only
one variable is involved.
Consider the case in which the total cost for a given operation is a function of the two independent variables
x and y, or;
By analyzing all the costs involved and reducing the resulting relationships to a simple form, the following
function might be found for Eq. (9-35):
103
11.03.2025
Graphical Procedure
The relationship among CT, x, and y could be shown as a curved surface in a three-dimensional plot, with a
minimum value of CT occurring at the optimum values of x and y. However, the use of a three-dimensional plot is
not practical for most engineering determinations.
The optimum values of x and y in Eq. (9-36) can be obtained graphically on a two-dimensional plot by using the
method indicated in Fig. 9-6.
In this figure, the objective function is plotted against one of the independent variables x, with the second variable
y held at a constant value.
A series of such plots is made with each dashed curve representing a different constant value of the second
variable.
As shown in Fig. 9-6, each of the curves (A, B, C, D, and E) gives one value of the first variable x at the point
where the total cost is a minimum.
The solid curve NM represents the locus of all these minimum points, and the optimum value of x and y occurs at
the minimum point on curve NM.
There is a close relationship between operating time, rate of production, and selling price. It is desirable to
operate at a schedule that will permit maximum utilization of fixed costs while simultaneously meeting market
sales demand and using the capacity of the plant production to give the best economic results. Figure 9-7 shows
graphically how production rate affects costs and profits.
The fixed costs remain constant while the total product cost, as well as the profit, increases with increased rate of
production. The point where total product cost equals total income represents the breakeven point, and the
optimum production schedule must be at a production rate higher than that corresponding to the breakeven point.
104
11.03.2025
An algorithm is simply an objective mathematical method for solving a problem and is purely mechanical so that
it can be programmed for a computer.
Solution of programming problems generally requires a series of actions that are iterated to a solution, based on a
programming method and various numerical calculation methods. The input to the algorithm can be manual,
where the relations governing the design behavior are added to the algorithm. They can also be integrated or set to
interface with rigorous computer simulations that describe the design.
Use of algorithms thus requires the selection of an appropriate programming method, methods, or combination of
methods as the basic principals for the algorithm function.
It also requires the provision of the objective functions and constraints, either as directly provided relations or
from computer simulation models.
The algorithm then uses the basic programming approach to solve the optimization problem set by the objective
function and constraints. Table 9-2 gives a brief summary of some of the more commonly used algorithms.
OPTIMIZATION APPLICATIONS
Optimization Application: Optimum Production Rates in Plant Operation
The same principles used for developing an optimum design can be applied to determine the most favorable
conditions in the operation of a manufacturing plant.
One of the most important variables in any plant operation is the amount of product produced per unit of
time.
From an analysis of the costs involved under different situations and consideration of other factors affecting
the particular plant, it is possible to determine an optimum rate of production or an economic lot size.
When a design engineer submits a complete plant design, the study ordinarily is based on a given production
capacity for the plant. After the plant is put into operation, however, some of the original design factors will
have changed, and the optimum rate of production may vary considerably from the original design capacity.
105
11.03.2025
The total product cost per unit of time may be divided into the classifications of operating costs and It is convenient to consider operating costs on the basis of one unit of production. When this is done, the
organization costs. operating costs can be divided into two types of expenses as follows:
Operating costs depend on the rate of production and include expenses for direct labor, raw materials, (1) minimum expenses for raw materials, labor, power, etc., that remain constant and must be paid for each
power, heat, supplies, and similar items which are a function of the amount of material produced. unit of production as long as any material is produced; and
Organization costs, on the other hand, are due to expenses for directive personnel, physical equipment, (2) extra expenses due to increasing the rate of production.
and other services or facilities which must be maintained irrespective of the amount of material produced.
These extra expenses are known as superproduction costs.
Organization costs are independent of the rate of production.
They become particularly important at high rates of production. Examples of superproduction costs are extra
expenses caused by overload on power facilities, additional labor requirements, or decreased efficiency of
conversion. Superproduction costs can often be represented in the following manner:
OPTIMIZATION APPLICATIONS
Optimum Production Rate for Minimum Cost per Unit of Production
Quite often there is a need to know the rate of production which will give the least cost on the basis of one
unit of material produced.
At this particular optimum rate, a plot of the total product cost per unit of production versus the
production rate shows a minimum product cost; therefore, the optimum production rate must occur where
dCT/dP0 = 0.
106
11.03.2025
Many processes are carried out by the use of cyclic operations that involve periodic shutdowns for
discharging, cleanout, or reactivation.
This type of operation occurs when the product is produced by a batch process or when the rate of
production decreases with time, as in the operation of a plate-and-frame filtration unit.
In a true batch operation, no product is obtained until the unit is shut down for discharging. In
semicontinuous cyclic operations, product is delivered continuously while the unit is in operation, but the
rate of delivery decreases with time. Thus, in batch or semicontinuous cyclic operations, the variable of
total time required per cycle must be considered when determining optimum conditions.
107
11.03.2025
The investment for piping and pipe fittings can amount to an important part of the total investment for a The value of this optimum diameter can be determined by combining the principles of fluid dynamics with
It is necessary, therefore, to choose pipe sizes that provide a minimum total cost for pumping and fixed The optimum economic pipe diameter is found at the point at which the sum of pumping costs and fixed
108
11.03.2025
CHAPTER 10
Materials and
Fabrication Selection
109
11.03.2025
110
11.03.2025
Reduction in temperature is often beneficial with a reduction in corrosion. Cathodic protection is widely used in the protection of underground pipes and tanks from
external soil corrosion and in water systems to protect water storage tanks and offshore
Modification of pH values to less acidic conditions also can result in less corrosion. structures.
111
11.03.2025
PROPERTIES OF MATERIALS
Ferrous Metals and Alloys
Steel
Carbon steel is the most commonly used material in the chemical process industry despite its
somewhat limited corrosion resistance. This type of steel is routinely used with most organic
chemicals and neutral or basic aqueous solutions at moderate temperatures. Because of its
availability, low cost, and ease of fabrication, carbon steel is used even in situations with corrosion
rates of 0.13 to 0.5 mm/yr by specifying an added thickness to ensure achievement of the desired
service life.
Low-alloy steels contain one or more alloying components to improve the mechanical and
corrosion-resistant properties over those of carbon steel. Nickel increases toughness and improves
low-temperature properties and corrosion resistance.
Chromium and silicon improve hardness, abrasion resistance, corrosion resistance, and resistance
to oxidation.
Molybdenum provides added strength for higher-temperature operation.
112
11.03.2025
PROPERTIES OF MATERIALS
Stainless Steel
A preliminary approach to the selection of the stainless steel required for a specific
application is to classify the various types according to alloy content, microstructure, and
major characteristics.
Table 10-3 outlines the information according to the classes of stainless steels—austenitic,
martensitic, and ferritic.
Table 10-4 presents characteristics and typical applications of various types of stainless
steel while Table 10-5 indicates resistance of stainless steels to oxidation in air.
113
11.03.2025
114
11.03.2025
115
11.03.2025
116
11.03.2025
117
11.03.2025
The chemical resistance of polypropylene is about the same as that of polyethylene, but it Polyphenylene oxide displays good resistance to aliphatic solvents, acids, and bases, but
can be used at 120C. poor resistance to esters, ketones, and aromatic or chlorinated solvents.
Polycarbonate is a relatively high-temperature plastic. It can be used up to 150C. Polyamide or polyimide polymers are resistant to aliphatic, aromatic, and chlorinated or
Resistance to mineral acids is good. Strong alkalies slowly decompose it, but mild alkalies florinated hydrocarbons as well as to many acidic and basic systems, but are degraded by
do not. It is partially soluble in aromatic solvents and soluble in chlorinated hydrocarbons. high-temperature caustic exposures.
General-purpose polyester resins, reinforced with fiberglass, have good strength and
good chemical resistance, except to alkalies. Some special materials in this class, based on
bisphenol, are more alkali-resistant. Temperature limit for polyesters is 95C.
Epoxies reinforced with fiberglass have very high strengths and resistance to heat.
118
11.03.2025
119
11.03.2025
120
11.03.2025
121
11.03.2025
FABRICATION OF EQUIPMENT
Fabrication expenses account for a large fraction of the purchased cost for equipment.
A chemical engineer, therefore, should be acquainted with the methods for fabricating equipment,
and the problems involved in the fabrication should be considered when equipment specifications
are prepared.
Many of the design and fabrication details for equipment are governed by various codes, such as
the ASME codes. These codes can be used to indicate definite specifications or tolerance limits
without including a large amount of descriptive restrictions.
For example, fastening requirements can often be indicated satisfactorily by merely stating that all
welding should be in accordance with the ASME code.
3. Forming into desired shape For example, fastening requirements can often be indicated satisfactorily by merely stating that all
welding should be in accordance with the ASME code.
4. Fastening
5. Testing
6. Heat-treating
7. Finishing
122
11.03.2025
123
11.03.2025
FABRICATION OF EQUIPMENT
Finishing CHAPTER 11
The finishing operation involves preparing the equipment for final shipment.
Sandblasting, polishing, and painting may be necessary. Final pressure tests at 1 ^ to 2 or more
times the design pressure are conducted together with other tests as demanded by the specihed
Written and Oral
code or requested by the inspector.
Design Reports
Written and Oral Design Reports Written and Oral Design Reports
A successful engineer not only must be able to apply theoretical and practical principles in the development Some questions that each design engineer should ask before starting, preparing, or finalizing such a
of ideas and methods, but also must have the ability to express the results clearly and convincingly in communication are listed here:
written and oral presentations. What is the purpose of this communication?
During the course of a design project, the engineer may be requested to prepare numerous written and oral
What audience will read or listen to this communication?
reports. These may involve feasibility investigations, environmental impact studies, progress reports, and
project conclusions and recommendations. What is the function of this audience?
The decision on the advisability of continuing the design project will often be made on the basis of the What background information does the audience have?
material presented in the written and oral communications. What is the technical level that the audience will understand?
The value of the engineer's work is measured to a large extent by the results given in these various reports What response is desired from this audience?
covering the design study and the manner in which these results are presented.
The answers to these questions indicate the type of information that should be presented,
the quantity of detail required, and the most satisfactory method of presentation.
124
11.03.2025
WRITTEN REPORTS
Organization of a Written Report
A design report, generally, presents the results of a design effort to decision makers in an organization and The organization of a formal report requires careful sectioning and the use of subheadings in order to
aids them in their assigned responsibilities. maintain a clear and effective presentation.
Similar to the design process, design reports are of varying scope, detail, and complexity. To a lesser extent, the same type of sectioning is valuable for informal reports. The following discussion
applies to formal reports, but by deleting or combining appropriate sections, the same principles can be
Reports can be designated us formal and informal. Formal reports are often prepared as research,
applied to the organization of any type of report.
development, or design reports. These reports present results in considerable detail, and the design engineer
is generally allowed considerable leeway in selecting the type of presentation to be made. Informal reports
include memoranda, letters, progress notes, survey-type results, and similar items in which the major
A complete design report consists of several independent parts, with each succeeding part giving greater
purpose is to present a result without including detailed information. Stereotyped forms are often used for
detail on the design and its development. A covering letter of transmittal is usually the first item in any
informal reports, such as those for sales, production, calculations, progress, analyses, or summary of report. After this come the title page, the table of contents, and an abstract or summary of the report.
economic relations.
The body of the report is next and includes essential information, presented in the form of discussion,
graphs, tables, and figures. The appendix at the end of the report gives detailed information which permits
complete verification of the results shown in the body of the report.
Tables of data, sample calculations, and other supplementary material are included in the appendix. A typical
outline for a design report is given in Table 11-1.
WRITTEN REPORTS
A design report, generally, presents the results of a design effort to decision makers in an organization and
aids them in their assigned responsibilities.
Similar to the design process, design reports are of varying scope, detail, and complexity.
Reports can be designated us formal and informal. Formal reports are often prepared as research,
development, or design reports. These reports present results in considerable detail, and the design engineer
is generally allowed considerable leeway in selecting the type of presentation to be made. Informal reports
include memoranda, letters, progress notes, survey-type results, and similar items in which the major
purpose is to present a result without including detailed information. Stereotyped forms are often used for
informal reports, such as those for sales, production, calculations, progress, analyses, or summary of
economic relations.
125
11.03.2025
Materials-Handling The most common process for transferring liquid materials uses pumps and piping systems.
Compressors, fans, blowers, conveyors, chutes, and hoists are examples of other types of equipment used
extensively to handle and transfer gaseous and solid materials.
Equipment—Design Other types of special equipment may further change the characteristics of the materials with the use of
blenders, mixers, kneaders, crushers, and grinders.
and Costs Collection and storage of these materials are still another phase of this materials-handling process.
In all these cases the design engineer must decide which type of equipment is best suited for achieving the
objectives of the process design to prepare equipment specifications that will satisfy the operational
demands of the process under reasonable cost conditions.
Therefore, design principles, practical problems of operation, and cost effects are all involved in the final
choice of materials transfer, handling, and treatment equipment.
126
11.03.2025
Newtonian Fluids
For a Newtonian fluid in a smooth pipe, dimensional analysis relates the friction drop per unit length of
pipe to the pipe diameter, density of the fluid, and average fluid velocity through two dimensionless groups,
namely, the Fanning friction factor (Fanning sürtünme faktörü), given by;
The friction factor in smooth pipes is a function of the Reynolds number. However, in rough pipes, the
relative roughness (bağıl pürüzlülük) ε /D also affects the friction factor.
Figure 12-1 presents a plot of the friction factor as a function of the Reynolds number and ε/D.
Representative values for the surface roughness factor ε associated with various materials are indicated in
the figure.
127
11.03.2025
Newtonian Fluids
Many pipe flow problems either include determination of the pressure drop given the flow rate (or
velocity) or the calculation of the flow rate (or velocity) for a given pressure drop.
When the flow rate is given, the Reynolds number is determined to identify the flow regime and the
appropriate friction factor relation that needs to be used.
When the pressure drop is given and the velocity is unknown, the flow regime will have to be assumed and
later verified by checking the Reynolds number.
When Eq. (12-6) is solved for velocity when the pressure drop is given, note that the right-hand side of the
equation is independent of velocity since
Re(f )1/2 = (D3/2 /μ)(ρΔp/2L)
If the velocity, density, and viscosity of the flowing fluid remain constant and the pipe diameter is uniform
over the total pipe length, the mechanical energy loss due to friction may be obtained from:
(12-7)
Newtonian Fluids
Non-Newtonian and Bingham Fluids
(12-7) For flow of non-Newtonian fluids, the Fanning friction factor design chart (Fig. 12-2) developed by
Dodge and Metzner is often used. In this chart, n' is the slope of a plot of D p/(4L) versus 8V/D on
logarithmic coordinates, and γ is a general relationship for the shear rate (kesme hızı) of the fluid given
In a strict sense, Eq. (12-7) is limited to conditions in which the flowing fluid is noncompressible and the by:
temperature of the fluid is constant.
When one is dealing with compressible fluids, such as air, steam, or any gas, it is good engineering practice
to use Equation (12-7) only if the pressure drop over the system is less than 10 percent of the initial
pressure.
If a change in the fluid temperature occurs, Eq. (12-7) should not be used in the form indicated unless the By plotting capillary viscometry information in this manner, the data can be used directly for pressure drop
total change in the fluid viscosity is less than approximately 50 percent based on the maximum viscosity. calculations. For such calculations, the flow rate and diameter determine the fluid velocity from which
8V/D is determined and D p/(4L) is read from the plot.
If Equation (12-7) is used when pressure changes or temperature changes are involved, the best accuracy is
obtained by using the linear velocity, density, and viscosity of the fluid as determined at the average For Bingham plastic materials in turbulent flow, it is generally assumed that the wall stresses greatly
temperature and pressure. exceed the yield stress (akma gerilimi), so that the friction factor-Reynolds number relationship for
Newtonian fluids applies. This is equivalent to setting n' = 1 in the Dodge-Metzner method.
Exact results for compressible fluids or nonisothermal flow can be obtained from the Fanning equation by
integrating the differential expression, taking all changes into consideration.
128
11.03.2025
Vacuum Flow
For gas flows under high vacuum conditions, the continuum hypothesis used in previous flow calculations Frictional Losses Encountered in Pipelines
is no longer appropriate. Accordingly, vacuum flow is generally described with such flow variables as S
and Q, the pumping speed and throughput, respectively. The pumping speed is the actual volumetric flow If the cross-sectional area of a pipe changes gradually to a new cross-sectional area, the
rate of the gas through a flow cross section, and throughput is the product of the pumping speed and the disturbances to the flow pattern can be so small that the amount of mechanical energy lost
absolute pressure. The mass flow rate (m) is directly related to the throughput, using the ideal gas law, as: as friction due to the change in cross section is negligible.
However, if the change is sudden, an appreciable amount of mechanical energy can be
lost as friction.
where M is the molecular weight of the gas. For a given mass flow rate, throughput is independent of Similarly, the presence of bends, fittings, valves, orifices, or other installations that
pressure. The relation between throughput and pressure drop across a flow element is designated in terms
disturb the flow pattern can cause frictional losses.
of the conductance Cc. Conductance has dimensions of volume per time and is defined as:
All these effects must be included in the friction term appearing in the total mechanical
energy balance.
Recommended expressions for evaluating the important types of frictional losses are
presented in Table 12-1.
Since the individual terms in Eq. (12-12) can be evaluated directly from the physical properties of the
system and the associated flow conditions, the design engineer can apply this equation to many liquid-flow
systems without making any major assumptions.
Example 12-1 illustrates the application of Eq. (12-12) to determine the power requirements for the given
pumping operation.
129
11.03.2025
Example 12 – 1 Solution:
EXAMPLE 12-1: Application of Mechanical Energy Balance to
Noncompressible Flow Systems
Water is pumped from a large reservoir into an open tank using a standard steel pipe with an inside diameter
of 0.0525 m.
The reservoir and the tank are open to the atmosphere.
The difference in vertical elevation between the water surface in the reservoir and the discharge point at the
top of the tank is 21.3 m.
The length of the pipeline is 305 m. Two gate valves and three standard 90° elbows are part of the piping
system.
The efficiency of the pump is 40 percent and includes the losses at the entrance and exit of the pump.
If the flow rate of the water is to be maintained at 3.15 x 10-3 m3/s and the water temperature remains
constant at 16 °C, estimate the power rating of the motor required to drive the pump.
130
11.03.2025
Power Requirements for Transport of Liquids and Gases EXAMPLE 12-2: Application of the Total Energy Balance to a
Compressible Flow System
The use of the mechanical energy balance is not recommended for compressible fluids when large pressure Nitrogen gas is flowing under turbulent conditions at a constant rate through a long, straight, and horizontal
drops in the flow are involved. In such cases, the total energy balance should be used if the required data are pipe with an inside diameter of 0.0525 m.
available. A rearrangement of the total energy balance given in Eq. (12-1) for the work involved in the fluid At the upstream location (point 1), the temperature of the nitrogen gas is 21 °C, the pressure is 103 kPa, and
system is given by the linear velocity of the gas is 15 m/s.
At the downstream location (point 2), the temperature of the nitrogen gas is 60°C and the pressure is 345
kPa.
An external heater is located between points 1 and 2, and 23.2 kJ is transferred from the heater to each
kilogram of the flowing gas.
where h is the enthalpy and is equal to u + pv. When Eq. (12-13) is applied in design calculations,
information must be available for determining the change in enthalpy over the range of temperature and No other heat sources or losses occur between the gas and the surroundings.
pressure involved. Estimate the work input to the gas in kJ/kg supplied by the compressor located between points 1 and 2.
Example 12-2 shows how Eq. (12-13) can be used to calculate the pumping requirement when a
compressible fluid is involved.
Example 12 – 2 Solution:
PIPING IN FLUID TRANSPORT PROCESSES
The American National Standards Institute (ANSI) and the American Petroleum Institute (API) have
established detailed standards for the most widely used components of piping systems. Lists of these
standards as well as specifications for pipe and fitting materials can be found in the ANSI B31 code
sections. Many of these standards contain pressure-temperature ratings that will be of assistance to
engineers in their design function. Even though safety is the basic consideration of the code, design
engineers are cautioned that the code is not a design handbook and does not eliminate the need for
engineering judgment.
Some of the specific requirements for pumping systems have been included in the Occupational Safety and
Health Administration (OSHA) requirements. A few of the more significant requirements of ANSI B31.3
have been summarized and are included in this section since they relate directly to the minimum
requirements for the selection and design of piping systems.
131
11.03.2025
132
11.03.2025
133
11.03.2025
134
11.03.2025
135
11.03.2025
PUMPING OF FLUIDS
Centrifugal Pumps
The major advantages of a centrifugal pump are simplicity, low initial cost, low maintenance
expense, uniform (nonpulsating) flow, quiet operation, and adaptability to use either motor or
turbine drivers.
This type of pump also can handle liquids with large amounts of solids since there are no close
metal-to-metal fits within the pump and there are no valves involved in the pump operation.
On the other hand, centrifugal pumps generally cannot be operated at high heads and have
efficiency problems with handling highly viscous fluids.
The maximum efficiency for a given pump is only available over a fairly narrow range of
operating conditions
136
11.03.2025
Güç Bağlantılar
Akışkan sıcaklığı T -15...+120 °C Oval flanş nominal çapı G 1¼
Nominal basınç PN PN 16
Maksimum işletme pmax 16 bar kademesi (basınç
basıncı tarafı)
Minimum verimlilik endeksi (MEI) Nominal basınç PN PN 16
Minimum verimlilik endeksi ≥ 0,40 kademesi (emiş tarafı)
(MEI) Malzemeler
Motor Çark 1.4301 [AISI304]
Yalıtım sınıfı F
Pompa gövdesi 1.4301 [AISI304]
Koruma sınıfı IP 55
Pompa mili 1.4301 [AISI304]
137
11.03.2025
Figure 12-25 provides operating boundaries using these parameters for the four types of compressors Centrifugal compressors, in general, are used for higher pressure ratios and lower flow rates compared to
discussed in this section, namely, lower-stage pressure ratios and higher flow rates in axial compressors. The pressure ratio in a single-stage
centrifugal compressor used in the petrochemical industry is about 1.2:1. The pressure ratio of axial flow
Centrifugal, compressors is between 1.05:1 and 1.15:1.
Axial, Axial-flow compressors are mainly used as compressors for turbines. The use of multiple stages permits
Reciprocating, and overall pressure increases up to 30:1. The efficiency of an axial compressor is higher than that of a
centrifugal compressor.
Rotary.
The selection process must also recognize process problems with certain gases at elevated temperatures that
could create a potential explosion hazard or with the admission of small amounts of lubricating oil or water
that would contaminate the process gas stream.
Finally, for continuous process operation, a high degree of equipment reliability will be required since
frequent shutdowns cannot be tolerated.
138
11.03.2025
139
11.03.2025
The addition of an average compressibility factor Zc in Equations (12-24) and (12-25) attempts
to account for any deviations from the ideal gas law that are present during the compression
process.
For adiabatic multistage compression, assuming equal division of compression work between
the stages and intercooling of the gas after each stage back to the original inlet temperature, Eq.
(12-22b) is modified to:
Table 12-8 provides typical adiabatic efficiencies observed for some of the
compressors discussed in this section.
140
11.03.2025
141
11.03.2025
142
11.03.2025
143
11.03.2025
144
11.03.2025
145
11.03.2025
146
11.03.2025
147
11.03.2025
STORAGE AND CONTAINMENT OF FLUIDS Table 12-10 Design equations and data for pressure vessels based on the
ASME Boiler and Pressure Vessel Code.
Costs for Tanks, Pressure Vessels, and Storage Equipment
Steel density can be assumed to be 7833 kg/m3.
The weight of the formed head of such tanks can be approximated by calculating the area of the
blank disk of metal used for forming the heads.
The required diameter of the blank disk can be obtained by multiplying the actual outside
diameter of the shell by the appropriate factor given in Table 12-11.
These factors include an allowance for the flange that is necessary for welding purposes.
Cost for pressure vessels in January 2002 (including nozzles, manholes, saddles or skirts, but no
internals such as trays or agitators) as dollars per kilogram weight of the fabricated unit f.o.b. with
carbon steel as the cost basis is given by:
where Wv is the total calculated weight of the vessel in kg. This relation is applicable over a
weight range from 400 to 50,000 kg.
Table 12-10 Design equations and data for pressure vessels based on the STORAGE AND CONTAINMENT OF FLUIDS
ASME Boiler and Pressure Vessel Code.
If weight information on tanks and pressure vessels is not available, preliminary cost estimates
can be based on the volumetric capacity for small mixing and storage tanks in Fig. 12-52 and for
shop-fabricated tanks with a wall thickness of 6.35 mm in Fig. 12-53.
An adjustment factor can be used for other wall thicknesses.
Purchased cost for horizontal storage vessels is provided in Fig. 12-54. Figures 12-55 and 12-56
provide cost data on small and large field-erected tanks for liquid storage.
Figure 12-57 presents cost data for large-volume gas storage tanks operating at atmospheric
pressure.
In determining the total cost for the tanks in these figures, allowances must be made for nozzles,
supports and foundations, platforms, labor, and indirect costs as well as for all the internals
required in the tank or vessel. Table 12-13 gives costs for selected small containers.
148
11.03.2025
149
11.03.2025
Design and Cost • Reactor geometry: flow pattern and manner of contacting the phases:
• Stirred tank reactor;
• Tubular reactor;
• Packed bed, fixed and moving;
• Fluidized bed.
150
11.03.2025
REACTOR PRINCIPLES
The basic mathematical model for a reactor system is developed from
(1) reaction rate expressions incorporating mechanism definition and temperature functionality;
(2) material balances including inflow, outflow, reaction rates, mixing effects, and diffusion
effects;
(3) energy balances including heats of reaction, heat transfer, and latent and sensible heat
effects;
(4) economic evaluations; and
(5) special constraints on the design system.
The material and energy balances, shown graphically in Fig. 13-2, are developed from the
fundamental conservation equations based on a differentia] volume of the reacting system.
The material balance is given by
151
11.03.2025
152
11.03.2025
Catalytic Reactions
For fluid-phase reactions, solid catalysts are most frequently used, because solids are convenient for
contacting gases and liquids, easy to fabricate, place in a reactor, and separate from the reaction
Few guidelines in selecting a reactor
mixture. The Langmuir-Hinshelwood (L-H) concept of such reactions is that molecules of at least
one reactant must be adsorbed on the catalyst surface, there to react with another reactant either
gaseous or adsorbed, and then the reaction product(s) must desorb from the catalyst surface back to
the gas phase.' Any one of these three steps can be much slower than the others and is therefore called
the rate-limiting or rate-controlling step. A general form of rate expression for such reactions is
153
11.03.2025
154
11.03.2025
Types of Reactors
Chemical reactors come in the form of vessels or tanks for batch reactors or back-
mix flow reactors, as cylinders for fluidized-bed reactors, or as single or multiple
tubes inside a cylindrical container for plug-flow reactors, particularly when special
needs exist for temperature control. High pressure and extreme temperatures as well
as corrosive action of the materials involved can introduce complications in the
design of such systems. Tank reactors must be designed with closed ends that can
withstand the operating conditions. Cooling or heating can be provided either by
internal or external coils or pipes, or by jacketing, as shown in Fig. 13-5.
155
11.03.2025
156
11.03.2025
157
11.03.2025
158
11.03.2025
159
11.03.2025
160
11.03.2025
161
11.03.2025
SUMMARY
Chemical reaction process design is generally encountered in most chemical
processes. The complexity of some chemical reactions and their dependence on
mass and energy transport can lead to considerable difficulties in the design of
reactive chemical processes. These complexities make a simple optimization routine
impossible, although a general approach to designing and optimizing chemical
CHAPTER 15
reaction processes greatly helps in establishing the possible designs that fulfill the
process requirements, the optimal design, and the best operating conditions.
Idealized reactor models can be adapted for use in most situations. While these basic
designs are idealized and often are not accurate enough for proper design, there are
ways of increasing their usefulness through careful analysis and the use of software.
At the same time, the kinetics of the reaction drive the operational requirements of
the design to maximize the required reaction and discourage any unwanted
reactions. This requires careful study of the reaction kinetics and mechanism, Separation Equipment—
followed by the selection of temperature, pressure, concentration, and material
contact operating conditions. Further improvement of reactions is often possible
through the utilization of catalytic substances. These often improve the economics Design and Costs
of a reaction, but require additional equipment design and investigation of operating
conditions to fulfill catalytic requirements and thus achieve an optimal design.
The selection of the best separation process often must be made from several
possible separation processes. The important factors to be considered in making the
selection include exploitable property differences, feed and product conditions, and
characteristics of the separation process. The most important feed conditions are
flow rate and composition, particularly of the key components to be recovered or
separated.
Generally, the more dilute the key components are in the feed mixture, the greater is
the cost of separation. However, some separation operations, such as those based on
the use of barriers or solid agents, perform very well even when feeds are dilute in
the component that is to be recovered. The most important product condition is the
product purity of the component or components that are recovered.
162
11.03.2025
Tables 15-2 and 15-3 present some guidelines to assist the design engineer in
identifying one or more feasible processes that would be appropriate for the
separation of homogeneous and heterogeneous mixtures, respectively.
The tables outline the normal feed conditions and the separating agent, force field,
or gradient that will be involved in the separation process under consideration.
Additional information in the table indicates the approximate concentration range of
key components that may be encountered in the feed for each of the listed separation
processes as well as an estimate of the range in flow capacity of the equipment
available for laboratory to commercial use associated with these processes.
Finally, advantages and disadvantages listed for each of the separation processes can
provide insights for recognizing whether such alternative processes could be utilized
to perform the required separation.
163
11.03.2025
Distillation: The creation or addition of another phase in distillation is obtained by the repeated vaporization and condensation of the fluid. The separation
process exploits the differences in vapor pressure of the key components in the mixture to initiate the separation. The advantages of distillation are its simple
flowsheet, low capital investment, and low risk. The separation process has the ability to handle wide ranges of feed concentrations and throughputs while
producing a high-purity product.
This separation process can easily be staged. It is possible to have more than 100 theoretical stages in one distillation column. Accordingly, relative volatilities
between key components to be separated can be as low as 1.2, and the separation can still be achieved. In addition, mass-transfer rates between phases are
generally quite high, and phase contacting and disengaging are easily accomplished so that equipment dimensions needed to obtain high degrees of separation
are usually not excessive.
The equipment requirements for distillation are small compared to those for most other separation processes. All that is generally required is a column, a
reboiler, a condenser, and some relatively small ancillary equipment. By comparison, separation processes based on the use of mass-separating agents typically
involve two or more separate mass-transfer zones, or require semibatch operation, or do both to perform the same separation.
Absorption: A widely used alternative to distillation for the separation of a solute from a gas stream is absolution. In this separation process, the gas mixture is
contacted with a liquid solvent which preferentially absorbs one or more components from the gas stream. Liquid flw rate, temperature, and pressure are the
variables that must be set in this separation process.
164
11.03.2025
Reflux considerations
165
11.03.2025
166
11.03.2025
The second variable that needs to be set for the distillation process is the reflux
ratio. With an increase in reflux ratio from its minimum, the capital cost decreases
initially because of a reduction in the number of plates required for the separation.
However, the utility costs increase as more reboiling and condensation duties are
required.
If the capital costs involved in the separation process are annualized and combined
with the annual cost of the utilities, an optimal reflux ratio can be obtained. Most
designers select a ratio of actual reflux to minimum reflux of at least 1.2 or above,
except in special cases such as ultralow-temperature separation, since a small error
in the design data or a small change in the operating conditions might lead to a
process that does not meet the original design specifications.
A design variable of lesser importance is the vapor/liquid condition of the feed. If
the feed is subcooled, the number of trays in the rectifying section is decreased and
the number of trays in the stripping section is increased. This feed condition requires
more heat in the reboiler and less cooling in the condenser. Partially vaporized feed
reverses these effects. For a given separation, the feed conditions can be optimized.
167
11.03.2025
Column Shells
168
11.03.2025
169
11.03.2025
170
11.03.2025
171
11.03.2025
172
11.03.2025
173
11.03.2025
Continuous Contactors
Continuous Contactors
• Packed Column Design Factors
• pressure drop
• flow capacities
• foundation load
• Satisfactory packing should result in;
• low pressure drop
• high throughput (capacity)
• low weight and liquid holdup
• large active surface area per unit volume
• large free (void) volume per unit total volume
• high durability, corrosion resistance
• low side thrust on tower walls
Continuous Contactors
Column Packing
• Types of Packing
• random (dumped)
• stacked (structured)
• Critical Packing Physical Characteristics
• nominal size (in)
• average weight per ft3 of tower volume (lb/ft3)
• average surface area per tower volume (ft2/ft3)
• % free-gas space,
• packing factor ap/3, effective surface area/(void fraction)3, (ft2/ft3)
174
11.03.2025
Column Packing
Column Packing
175
11.03.2025
Feed Distributor
Liquid Distribution
• To provide max amount of active liquid vapor contact, packing should
be completely wetted during operation.
• Re-distributors are used within a column to reduce the loss of active
surface area due to channeling or improper liquid distribution.
176
11.03.2025
177
11.03.2025
Mist Eliminator
Pressure Drop
• Factors Affecting P
• fluid flow rates
• and of fluids
• packing size, shape, orientation & surface
• Estimation of P
• use data from similar equipment operating under equivalent conditions
• correlations when unavailable
{
Loading Point - beginning of • countercurrent liquid/gas flow
liquid build-up on packing.
• p = pressure drop (psf)
Pre-loading Range - • h = packed height (ft)
log G vs. log DP about linear • , = packing dependent constants
desired operating range • L, G = superficial liquid/gas mass velocity (lb/h/ft2)
• L, G = density of liquid/gas (lb/ft3)
log G, superficial gas rate (lb/h/ft2)
178
11.03.2025
179
11.03.2025
Effect of Operating Pressure on Flooding Velocity Effect of Operating Pressure on Flooding Velocity
• Write eqns for Vm & Gm at each average operating condition (1&2), • if vapor acts ideally, G = MGP/RT
eliminate Kp; 0 .5 0 .5 0 .5 0 .5
G2 L1 P L1
T1 MG2
Vm1 Vm2 Vm1 Vm2 2
P1 L T2 MG
G1 L2 2 1
0.5 0 .5 0.5 0 .5
G1 L1 P L1 T2 M G1
Gm1 Gm2 1
Gm1 Gm2 L T MG
G2 L2 P2 2 1 2
180
11.03.2025
181
11.03.2025
Jacketted
Thermo-
Kettle
Syphon
Reboiler
Reboiler
182
11.03.2025
Reboiler Configurations
Kettle
Reboiler
183