Works Programme

The document outlines a project schedule for construction tasks related to the Chuka AHP, detailing tasks, durations, start and finish dates, and dependencies. Key phases include site mobilization, foundations, and superstructures, with specific tasks assigned to various blocks. The timeline spans from December 2024 to May 2025, indicating a structured approach to project management.

Uploaded by

Shem Ayuka
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views4 pages

Works Programme

The document outlines a project schedule for construction tasks related to the Chuka AHP, detailing tasks, durations, start and finish dates, and dependencies. Key phases include site mobilization, foundations, and superstructures, with specific tasks assigned to various blocks. The timeline spans from December 2024 to May 2025, indicating a structured approach to project management.

Uploaded by

Shem Ayuka
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

ID Task Task Name Duration Start Finish Qtr 1, 2025 Qtr 2, 2025

Mode Nov Dec Jan Feb Mar Apr May


1

2 CHUKA AHP 86 days Fri 20/12/24 Fri 18/04/25

3 Mobilize on Site 42 days Fri 20/12/24 Mon 17/02/25

4 Site mobilization 14 days Fri 20/12/24 Wed 08/01/25

5 Prepare site - site hording 14 days Thu 09/01/25 Tue 28/01/25

6 Set up site offices 14 days Wed 29/01/25 Mon 17/02/25

7 Setting line and grade benchmarks 4 days Wed 29/01/25 Mon 03/02/25

8 Install temporary power 2 days Fri 20/12/24 Mon 23/12/24

9 Install temporary water service 2 days Tue 24/12/24 Wed 25/12/24

10 Site Grading and Utilities 7 days Tue 04/02/25 Wed 12/02/25

11 Clear and grub a site 4 days Tue 04/02/25 Fri 07/02/25

12 Site access and temporary parking areas 2 days Mon 10/02/25 Tue 11/02/25

13 Final site clearance 1 day Wed 12/02/25 Wed 12/02/25

14 Foundations 47 days Thu 13/02/25 Fri 18/04/25

15 Excavate raft foundations 40 days Thu 13/02/25 Wed 09/04/25

16 Blinding concrete 40 days Mon 24/02/25 Fri 18/04/25

17 SUPERSTRUCTURES

Task Project Summary Manual Task Start-only Deadline

Project: PRELIMINARIES Split Inactive Task Duration-only Finish-only Progress


Date: Thu 08/05/25 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Predecessors 24 Feb '25 03 Mar '25 10 Mar '25 17 Mar '25 24 Mar '25 31 Mar '25 07 Apr '25 14 Apr '25 21 Apr '25 28 Apr '25 05 May '25 12 May '25 19 May '25 26 May '25
Mode S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S
1 1 BLOCK- C 90 days Wed 26/02/25 Thu 29/05/25
2 1.1 REINFORCEMENT TO FOUNDATIONS RAFT,LIFT WALLS,SHEAR WALLS & 4 days Wed 26/02/25 Sat 01/03/25
COLUMNS
3 1.2 CONCRETE TO FOUNDATIONS RAFT ,LIFT WALLS,SHEAR WALLS & COLUMNS
3 days Wed 05/03/25 Fri 07/03/25 2
4 1.3 FORMWORKS & REINFORCEMENT TO FOUNDATION COLUMNS 3 days Fri 07/03/25 Tue 11/03/25 3
5 1.4 CASTING OF CONCRETE TO FOUNDATION COLUMNS 3 days Fri 07/03/25 Tue 11/03/25 4SS
6 1.5 FOUNDATION WALLINGS 4 days Sat 08/03/25 Thu 13/03/25 5SS+1 day
7 1.6 FORMWORK TO GROUND BEAMS 2 days Wed 12/03/25 Thu 13/03/25 6SS+3 days
8 1.7 REINFORCEMENT TO GROUND BEAMS 2 days Wed 12/03/25 Thu 13/03/25 7SS
9 1.8 CASTING OF GROUND BEAMS 2 days Thu 13/03/25 Fri 14/03/25 8SS+1 day
10 1.9 MAKE UP LEVELS USING APPROVED IMPORTED MATERIALS/SELECTED 4 days Fri 14/03/25 Tue 18/03/25 9SS+1 day
EXCAVATED MATERIALS-COMPACTED IN LAYERS NOT EXCEEDING 300MM
THICK WITH A ROLLER

11 1.10 300MM THICK HARDCORE BED: HAND PACKED: COMPACTED IN LAYERS 2 days Tue 18/03/25 Thu 20/03/25 10
NOT EXCEEDING 150MM THICK
12 1.11 50 MM STONE DUST/ MURRUM BLINDING TO SURFACES OF HARDCORE 1 day Wed 19/03/25 Thu 20/03/25 11FF
13 1.12 ANTI - TERMITE TREATMENT, DAMP-PROOF MEMBRANE 1 day Wed 19/03/25 Thu 20/03/25 12FF
14 1.13 ELECTRICAL 1ST FIX 2 days Thu 20/03/25 Sat 22/03/25 13
15 1.14 MECHANICAL 1ST FIX 2 days Thu 20/03/25 Sat 22/03/25 13
16 1.15 DPM & BRC A142 1 day Sat 22/03/25 Sat 22/03/25 15
17 1.16 CASTING OF GROUND FLOOR SLAB 1 day Tue 13/05/25 Tue 13/05/25
18 1.17 BLOCK- A 69.63 daysTue 04/03/25 Wed 14/05/25
19 1.17.1 REINFORCEMENT TO FOUNDATIONS RAFT,LIFT WALLS,SHEAR WALLS 4 days Tue 04/03/25 Fri 07/03/25 2
& COLUMNS
20 1.17.2 CONCRETE TO FOUNDATIONS RAFT ,LIFT WALLS,SHEAR WALLS & 3 days Fri 07/03/25 Tue 11/03/25 19
COLUMNS
21 1.17.3 FORMWORKS & REINFORCEMENT TO FOUNDATION COLUMNS 3 days Tue 11/03/25 Thu 13/03/25 20
22 1.17.4 CASTING OF CONCRETE TO FOUNDATION COLUMNS 3 days Wed 12/03/25 Fri 14/03/25 21SS+1 day
23 1.17.5 FOUNDATION WALLINGS 4 days Thu 13/03/25 Mon 17/03/25 22SS+1 day
24 1.17.6 FORMWORK TO GROUND BEAMS 2 days Sat 15/03/25 Tue 18/03/25 23SS+3 days
25 1.17.7 REINFORCEMENT TO GROUND BEAMS 2 days Sat 15/03/25 Tue 18/03/25 24SS
26 1.17.8 CASTING OF GROUND BEAMS 2 days Mon 17/03/25 Wed 19/03/25 25SS+1 day
27 1.17.9 MAKE UP LEVELS USING APPROVED IMPORTED 4 days Tue 18/03/25 Fri 21/03/25 26SS+1 day
MATERIALS/SELECTED EXCAVATED MATERIALS-COMPACTED IN LAYERS
NOT EXCEEDING 300MM THICK WITH A ROLLER

28 1.17.10 300MM THICK HARDCORE BED: HAND PACKED: COMPACTED IN 2 days Sat 22/03/25 Mon 24/03/25 27
LAYERS NOT EXCEEDING 150MM THICK
29 1.17.11 50 MM STONE DUST/ MURRUM BLINDING TO SURFACES OF HARDCORE1 day Sat 22/03/25 Mon 24/03/25 28FF
30 1.17.12 ANTI - TERMITE TREATMENT, DAMP-PROOF MEMBRANE 1 day Sat 22/03/25 Mon 24/03/25 28FF
31 1.17.13 ELECTRICAL 1ST FIX 2 days Mon 24/03/25 Wed 26/03/25 30
32 1.17.14 MECHANICAL 1ST FIX 2 days Wed 26/03/25 Fri 28/03/25 31
33 1.17.15 DPM & BRC A142 1 day Fri 28/03/25 Sat 29/03/25 32
34 1.17.16 CASTING OF GROUND FLOOR SLAB 1 day Wed 14/05/25 Wed 14/05/25
35 1.18 BLOCK- B1 24.75 daysMon 10/03/25 Thu 03/04/25
36 1.18.1 REINFORCEMENT TO FOUNDATIONS RAFT,LIFT WALLS,SHEAR WALLS 4 days Mon 10/03/25 Thu 13/03/25 19
& COLUMNS
37 1.18.2 CONCRETE TO FOUNDATIONS RAFT ,LIFT WALLS,SHEAR WALLS & 3 days Thu 13/03/25 Mon 17/03/25 36
COLUMNS
38 1.18.3 FORMWORKS & REINFORCEMENT TO FOUNDATION COLUMNS 3 days Mon 17/03/25 Wed 19/03/25 37
39 1.18.4 CASTING OF CONCRETE TO FOUNDATION COLUMNS 3 days Tue 18/03/25 Thu 20/03/25 38SS+1 day
40 1.18.5 FOUNDATION WALLINGS 4 days Wed 19/03/25 Sat 22/03/25 39SS+1 day
41 1.18.6 FORMWORK TO GROUND BEAMS 2 days Fri 21/03/25 Mon 24/03/25 40SS+3 days
42 1.18.7 REINFORCEMENT TO GROUND BEAMS 2 days Fri 21/03/25 Mon 24/03/25 41SS
43 1.18.8 CASTING OF GROUND BEAMS 2 days Sat 22/03/25 Tue 25/03/25 42SS+1 day
44 1.18.9 MAKE UP LEVELS USING APPROVED IMPORTED 4 days Mon 24/03/25 Thu 27/03/25 43SS+1 day
MATERIALS/SELECTED EXCAVATED MATERIALS-COMPACTED IN LAYERS
NOT EXCEEDING 300MM THICK WITH A ROLLER

45 1.18.10 300MM THICK HARDCORE BED: HAND PACKED: COMPACTED IN 2 days Fri 28/03/25 Sat 29/03/25 44
LAYERS NOT EXCEEDING 150MM THICK
46 1.18.11 50 MM STONE DUST/ MURRUM BLINDING TO SURFACES OF HARDCORE1 day Fri 28/03/25 Sat 29/03/25 45FF
47 1.18.12 ANTI - TERMITE TREATMENT, DAMP-PROOF MEMBRANE 1 day Fri 28/03/25 Sat 29/03/25 45FF
48 1.18.13 ELECTRICAL 1ST FIX 2 days Sat 29/03/25 Tue 01/04/25 47
49 1.18.14 MECHANICAL 1ST FIX 2 days Sat 29/03/25 Tue 01/04/25 47
50 1.18.15 DPM & BRC A142 1 day Tue 01/04/25 Wed 02/04/25 49
51 1.18.16 CASTING OF GROUND FLOOR SLAB 1 day Sat 17/05/25 Sat 17/05/25
52 1.18.17 BLOCK- B2 21.38 daysThu 08/05/25 Thu 29/05/25
53 1.18.17.1 REINFORCEMENT TO FOUNDATIONS RAFT,LIFT WALLS,SHEAR 4 days Thu 08/05/25 Mon 12/05/25 36SS
WALLS & COLUMNS
54 1.18.17.2 CONCRETE TO FOUNDATIONS RAFT ,LIFT WALLS,SHEAR WALLS 3 days Thu 08/05/25 Sat 10/05/25 37
& COLUMNS
55 1.18.17.3 FORMWORKS & REINFORCEMENT TO FOUNDATION COLUMNS 3 days Sat 10/05/25 Wed 14/05/25 54
56 1.18.17.4 CASTING OF CONCRETE TO FOUNDATION COLUMNS 3 days Sat 10/05/25 Wed 14/05/25 55SS
57 1.18.17.5 FOUNDATION WALLINGS 4 days Mon 12/05/25 Fri 16/05/25 56SS+1 day
58 1.18.17.6 FORMWORK TO GROUND BEAMS 2 days Thu 15/05/25 Fri 16/05/25 57SS+3 days
59 1.18.17.7 REINFORCEMENT TO GROUND BEAMS 2 days Thu 15/05/25 Fri 16/05/25 58SS
60 1.18.17.8 CASTING OF GROUND BEAMS 2 days Fri 16/05/25 Sat 17/05/25 59SS+1 day
61 1.18.17.9 MAKE UP LEVELS USING APPROVED IMPORTED 4 days Sat 17/05/25 Wed 21/05/25 60SS+1 day
MATERIALS/SELECTED EXCAVATED MATERIALS-COMPACTED IN LAYERS
NOT EXCEEDING 300MM THICK WITH A ROLLER

62 1.18.17.10 300MM THICK HARDCORE BED: HAND PACKED: COMPACTED IN 2 days Wed 21/05/25 Fri 23/05/25 61
LAYERS NOT EXCEEDING 150MM THICK
63 1.18.17.11 50 MM STONE DUST/ MURRUM BLINDING TO SURFACES OF 1 day Thu 22/05/25 Fri 23/05/25 62FF
HARDCORE
64 1.18.17.12 ANTI - TERMITE TREATMENT, DAMP-PROOF MEMBRANE 1 day Thu 22/05/25 Fri 23/05/25 63FF
65 1.18.17.13 ELECTRICAL 1ST FIX 2 days Fri 23/05/25 Mon 26/05/25 64
66 1.18.17.14 MECHANICAL 1ST FIX 2 days Mon 26/05/25 Tue 27/05/25 65
67 1.18.17.15 DPM & BRC A142 1 day Tue 27/05/25 Wed 28/05/25 66
68 1.18.17.16 CASTING OF GROUND FLOOR SLAB 1 day Wed 28/05/25 Thu 29/05/25 67

Project: SUBSTRUCTURES-CHU Task Milestone Project Summary Inactive Milestone Manual Task Manual Summary Rollup Start-only External Tasks Deadline Manual Progress
Date: Thu 08/05/25 Split Summary Inactive Task Inactive Summary Duration-only Manual Summary Finish-only External Milestone Progress

Page 1
ID Task Task Name Duration Start Finish Predecessors Mar '25 Apr '25 May '25 Jun '25 Jul '25 Aug '25 Sep '25 Oct '25
Mode 17 24 03 10 17 24 31 07 14 21 28 05 12 19 26 02 09 16 23 30 07 14 21 28 04 11 18 25 01 08 15 22 29 06
0 SUPERSTRUCTURES-AHP 100 days Tue 13/05/25 Mon 29/09/25
1
2 1 SUPERSTRUCTURES-[BLOCK C,A,B1 & B2] 100 days Tue 13/05/25 Mon 29/09/25
3 1.1 Column-Beam- Floor Slab (GF-1st floor) 10 days Tue 13/05/25 Mon 26/05/25
[Reinforcement, Shuttering, Concreting,
4 1.2 External & internal walling 3 days Wed 14/05/25 Fri 16/05/25 3SS+1 day
5 1.3 Staircase (CONST: LVL1 & LVL2) 4 days Wed 14/05/25 Mon 19/05/25 4SS
6 1.4 Construction of Lift Area 5 days Tue 13/05/25 Mon 19/05/25 3SS
7 1.5 Column-Beam- Floor Slab (1st floor -2nd floor) 10 days Tue 27/05/25 Mon 09/06/25 3
[Reinforcement, Shuttering, Concreting,
8 1.6 External & internal walling 3 days Wed 28/05/25 Fri 30/05/25 7SS+1 day
9 1.7 Staircase (CONST: LVL2 & LVL3) 4 days Wed 28/05/25 Mon 02/06/25 8SS
10 1.8 Construction of Lift Area 5 days Wed 28/05/25 Tue 03/06/25 9SS
11 1.9 Column-Beam- Floor Slab (2nd floor -3rd 10 days Tue 10/06/25 Mon 23/06/25 7
floor) [Reinforcement, Shuttering, Concreting,
12 1.10 External & internal walling 3 days Wed 11/06/25 Fri 13/06/25 11SS+1 day
13 1.11 Staircase (CONST: LVL3 & LVL4) 4 days Wed 11/06/25 Mon 16/06/25 12SS
14 1.12 Construction of Lift Area 4 days Wed 11/06/25 Mon 16/06/25 13SS
15 1.13 Column-Beam- Floor Slab (3rd floor -4TH 10 days Tue 24/06/25 Mon 07/07/25 11
floor) [Reinforcement, Shuttering, Concreting,
16 1.14 External & internal walling 3 days Wed 25/06/25 Fri 27/06/25 15SS+1 day
17 1.15 Staircase (CONST: LVL4 & LVL5) 4 days Wed 25/06/25 Mon 30/06/25 16SS
18 1.16 Construction of Lift Area 4 days Wed 25/06/25 Mon 30/06/25 17SS
19 1.17 Column-Beam- Floor Slab (4th floor -5th 10 days Tue 08/07/25 Mon 21/07/25 15
floor) [Reinforcement, Shuttering, Concreting,
20 1.18 External & internal walling 3 days Wed 09/07/25 Fri 11/07/25 19SS+1 day
21 1.19 Staircase (CONST: LVL5 & LVL6) 4 days Wed 09/07/25 Mon 14/07/25 20SS
22 1.20 Construction of Lift Area 5 days Wed 09/07/25 Tue 15/07/25 21SS
23 1.21 Column-Beam- Floor Slab (5th floor -6th 10 days Tue 22/07/25 Mon 04/08/25 19
floor) [Reinforcement, Shuttering, Concreting,
24 1.22 External & internal walling 3 days Wed 23/07/25 Fri 25/07/25 23SS+1 day
25 1.23 Staircase (CONST: LVL6& LVL7) 4 days Wed 23/07/25 Mon 28/07/25 24SS
26 1.24 Construction of Lift Area 5 days Wed 23/07/25 Tue 29/07/25 25SS
27 1.25 Column-Beam- Floor Slab (6th floor -7th 10 days Tue 05/08/25 Mon 18/08/25 23
floor) [Reinforcement, Shuttering, Concreting,
28 1.26 External & internal walling 3 days Wed 06/08/25 Fri 08/08/25 27SS+1 day
29 1.27 Staircase (CONST: LVL7 & LVL8) 4 days Wed 06/08/25 Mon 11/08/25 28SS
30 1.28 Construction of Lift Area 5 days Wed 06/08/25 Tue 12/08/25 29SS
31 1.29 Column-Beam- Floor Slab (7th floor -8th 10 days Tue 19/08/25 Mon 01/09/25 27
floor) [Reinforcement, Shuttering, Concreting,
32 1.30 External & internal walling 3 days Tue 19/08/25 Thu 21/08/25 31SS
33 1.31 Staircase (CONST: LVL8 & LVL9) 4 days Tue 19/08/25 Fri 22/08/25 32SS
34 1.32 Construction of Lift Area 5 days Tue 19/08/25 Mon 25/08/25 33SS
35 1.33 Column-Beam- Floor Slab (8th floor -9th 10 days Tue 02/09/25 Mon 15/09/25 31
floor) [Reinforcement, Shuttering, Concreting,
36 1.34 External & internal walling 3 days Wed 03/09/25 Fri 05/09/25 35SS+1 day
37 1.35 Staircase (CONST: LVL9 & LVL10) 4 days Wed 03/09/25 Mon 08/09/25 36SS
38 1.36 Construction of Lift Area 5 days Wed 03/09/25 Tue 09/09/25 37SS
39 1.37 Column-Beam- Floor Slab (9th floor -ROOF 10 days Tue 16/09/25 Mon 29/09/25 35
floor) [Reinforcement, Shuttering, Concreting,
40 1.38 External & internal walling 3 days Wed 17/09/25 Fri 19/09/25 39SS+1 day
41 1.39 Staircase (CONST: LVL11) 4 days Wed 17/09/25 Mon 22/09/25 40SS
42 1.40 Construction of Lift Area 5 days Wed 17/09/25 Tue 23/09/25 41SS
Task Summary Inactive Milestone Duration-only Start-only External Milestone Manual Progress
Project: SUPERSTRUCTURES-AH
Split Project Summary Inactive Summary Manual Summary Rollup Finish-only Deadline
Date: Thu 08/05/25
Milestone Inactive Task Manual Task Manual Summary External Tasks Progress

Page 1
ID Task Task Name Duration Start Finish Qtr 2, 2025 Qtr 3, 2025 Qtr 4, 2025 Qtr 1, 2026 Qtr 2, 2026 Qtr 3, 2026
Mode Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug
1

2 SUMMARY 260 days Mon 07/07/25 Fri 03/07/26 03/07

3 HARDWARE INSTALLATIONS 160 days Mon 07/07/25 Fri 13/02/26


4 WINDOW INSTALLATION 120 days Mon 07/07/25 Fri 19/12/25
5 DOOR INSTALLATION 120 days Mon 07/07/25 Fri 19/12/25
6 ELECTRICAL WORK FIXING 160 days Mon 07/07/25 Fri 13/02/26
7 PLUMBING WORK FIXING 160 days Mon 07/07/25 Fri 13/02/26
8 INTERIOR WORK 167 days Mon 18/08/25 Tue 07/04/26
9 FLOORING (ALL LEVELS) 160 days Mon 18/08/25 Fri 27/03/26
10 PAINT (ALL LEVELS) 160 days Wed 27/08/25 Tue 07/04/26
11 CEILING WORK (ALL LEVELS) 160 days Wed 27/08/25 Tue 07/04/26
12 STAIRCASE RAILING & BALUSTRADE 160 days Wed 27/08/25 Tue 07/04/26
13 JOINERY AND FITTINGS 160 days Wed 27/08/25 Tue 07/04/26
14 EXTERIOR FINISHING 160 days Wed 27/08/25 Tue 07/04/26
15 PAINT (ALL LEVELS) 160 days Wed 27/08/25 Tue 07/04/26
16 EXTERNAL WORKS 45 days Wed 08/04/26 Tue 09/06/26
17 GARBAGE RECEPTACLE 21 days Wed 08/04/26 Wed 06/05/26
18 GUARD HOUSE 28 days Wed 08/04/26 Fri 15/05/26
19 BOUNDARY WALLING 30 days Wed 08/04/26 Tue 19/05/26
20 BASKETBALL PITCH 45 days Wed 08/04/26 Tue 09/06/26
21 POWER HOUSE 21 days Wed 08/04/26 Wed 06/05/26
22 UNDERGROUND WATER TANK 45 days Wed 08/04/26 Tue 09/06/26
23 CIVIL WORKS - ROADS 30 days Wed 29/04/26 Tue 09/06/26
24 CIVIL WORKS - SEWER 30 days Wed 29/04/26 Tue 09/06/26
25 PERFORMANCE AND MONITORING 18 days Wed 10/06/26 Fri 03/07/26
26 QUALITY CHECKS 7 days Wed 10/06/26 Thu 18/06/26
27 CLEANING OF ENTIRE SITE 7 days Fri 19/06/26 Mon 29/06/26
(INTERNAL AND EXTERNAL)
28 FINAL DOCUMENTATION 3 days Tue 30/06/26 Thu 02/07/26
29 HANDING OVER TO CLIENT 1 day Fri 03/07/26 Fri 03/07/26
30

Task Project Summary Manual Task Start-only Deadline

Project: HARDWARES & EXTERN Split Inactive Task Duration-only Finish-only Progress
Date: Thu 08/05/25 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone