0% found this document useful (0 votes)
5 views3 pages

User Guide Cost To Complete Module

The document outlines the steps to work with the Cost To Complete module, including creating a job, entering estimated costs, and freezing the document for approval. It describes the functionalities of the Create Page, which includes tabs for Draft/Insert and Freeze, and the View Page, which provides access to CTC View and CTC Details. Users can track and manage cost estimates and actual costs associated with projects through this module.

Uploaded by

sanjukta2011
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
5 views3 pages

User Guide Cost To Complete Module

The document outlines the steps to work with the Cost To Complete module, including creating a job, entering estimated costs, and freezing the document for approval. It describes the functionalities of the Create Page, which includes tabs for Draft/Insert and Freeze, and the View Page, which provides access to CTC View and CTC Details. Users can track and manage cost estimates and actual costs associated with projects through this module.

Uploaded by

sanjukta2011
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 3

Module Path:

Document » Estimation » Cost To Complete

To start to work with the module

• Click on create.
• Give the Job code, Order Number.
• By default the month will be Last month (if required change the Month).
• Click on GO.

It will show the products with details

In Create Page there are 3 Tabs

• Draft / Insert: Here it will show the parameter wise estimated cost vs actual cost. And allow
to enter the expected cost to complete values against each parameter. Once the value is
entered click on Draft.

Sensitivity: LNT Construction Internal Use


• Draft / Insert: Once the required Cost to complete value inserted and drafted it will be
available for edit/update under Draft / Insert Tab for edit if required. Once the value entered
has been checked click on Update.

• Freeze: Once cost to complete Value entered and verified we need to Freeze the document
for approval. NOTE: once the document is freeze it cannot be edited.

In View Page we have 2 Tabs

• CTC View: With this Tab we can view the status of submitted document and print the
document.
• CTC Details: With this Tab we can view Order→ Product wise Estimated cost vs Actual
Cost , Accepted Cost, Sales against order, Margin .

Sensitivity: LNT Construction Internal Use