PERT-CPM Part II
PERT-CPM Part II
Now, based on the above earliest and latest event times, we can find out the project length or
project duration which is the length of the longest path. This longest path is known as
CRITICAL PATH. The critical path of a network is that path on which each of the events have
equal earliest and latest event times. In the above network, such event as observed are:
events 1, 3, 5, 6, 7, 8, 11, and 12. Thus the critical path of this network is:
B – D – F – G – H – K – N, as shown by the double arrow in the above network. The project
duration is the length of this path which is also equal to the latest time of the last event, that
is, 34 time units.
HOMEWORK
Calculate the earliest and latest event times of the above network.