The document discusses the concepts of PERT-CPM, focusing on finding the earliest and latest event times in a project network using forward and backward pass methods. It provides a detailed example of a network with various activities, their durations, and how to calculate the earliest and latest times for each event. The critical path is identified, which determines the project duration, and a homework assignment is given to calculate these times for the provided network.

Uploaded by

cpqcjbq9rk
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views9 pages

PERT-CPM Part II

The document discusses the concepts of PERT-CPM, focusing on finding the earliest and latest event times in a project network using forward and backward pass methods. It provides a detailed example of a network with various activities, their durations, and how to calculate the earliest and latest times for each event. The critical path is identified, which determines the project duration, and a homework assignment is given to calculate these times for the provided network.

Uploaded by

cpqcjbq9rk
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 9

PERT-CPM CONTINUED

The concepts that you will learn next are:

• Finding the earliest and latest event times of a network


• We will find the Earliest Start times, Earliest Finish times,
Latest Start times, Latest Finish times and various float
times for all the activities.
• Using concept of probability in order to apply a sort of
sensitivity analysis for a network
Consider the following network:

Activity Immediate Predecessor Duration (Days)


A -- 2
B -- 3
C A 1
D B 2
E C 4
F D 3
G E, F 5
H G 4
I G 6
J G 2
K H 7
L I 2
M J 8
N K, L, M 10
The event times are found in this way: Each of the events has been divided into 2
halves – upper circle and lower circle. The lower circle has been further subdivided
into 2 halves. The left half will show the earliest times of events and the right half will
show the latest time of the event. The earliest times of the events will be found out in
the forward direction, that is, starting from event 1 and ending at the last event, event
12. This way of finding the earliest times of the events is known as the forward Pass
method. The latest event times will found out in the backward direction, that is,
starting from the last event, event 12 and finishing at the first event, event 1. This way
of finding the latest time is called Backward Pass method.
At first, event 1 starts at time 0. Time 0 may represent any starting time such as , 10 AM, for
example. However, activity A takes 2 time units and thus the earliest time when event 2 can
start is (0+2)=2 time units, as shown in the left half of the lower circle of event 2. Similarly,
activity B takes 3 time units and thus the earliest time for event 3 is (0+3) = 3 time units.
Activity C takes 1 unit of time. Thus, the earliest event time for event 4 = earliest time of its
previous event, event 2 + duration of activity C = 2+1=3 time units. Duration of activity D is 2
time units and thus the earliest time for event 5 is = earliest time for event 3 + duration of
activity D = 3+2=5 time units. For event 6, it can be observed that, two different paths are
reaching event 6 – one is through event 4 and another is through event 5. Event 6 cannot start
unless both the activities E and F finish. Thus the earliest time for event 6 = maximum of time
through activity E and time through activity F = maximum(earliest time of event 4 + duration
of activity E, earliest time of event 5 + duration of activity F) = maximum(3+4,5+3)
=maximum(7,8) = 8 time units.
Next, duration of activity G is 5 time units. Thus, earliest time of event 7 = earliest time of
previous event 6 + duration of activity G = 8+5 = 13 time units. Durations of activities H, I, and
J are 4 time units, 6 time units, and 2 time units respectively. Thus the earliest time of event 8
= earliest time of event 7 + duration of activity H = 13+4=17 time units. The earliest time of
event 9 = earliest time of event 7 + duration of activity I = 13+6=19 time units. The earliest
time of event 10= earliest time of event 7 + duration of activity J = 13+2=15 time units. For
event 11, it can be observed that, 3 different paths are reaching event 11– first one is through
event 8, 2nd one is through event 9 and 3rd one is through event 10. Event 11 cannot start
unless the activities K, L and M finish. Thus the earliest time for event 11 = maximum of time
through activity K, time through activity L and time through activity M = maximum(earliest
time of event 8 + duration of activity K, earliest time of event 9 + duration of activity L, earliest
time for event 10 + duration of activity M) = maximum(17+7,19+2,15+8) =maximum(24,21,23)
= 24 time units. Duration of activity N is 10 time units. Thus, earliest time for event 12 is =
earliest time of previous event 11 + duration of activity N = 24+10 = 34 time units. Thus now,
all the earliest times for all the events have been calculated.
Next, the event times will be calculated by Backward Pass method, starting from event 12. The
latest time for the last event 12 = earliest time of the event = 34 time units. Instead of adding
the activity duration to the earliest time as in forward pass method, this time, the duration of
the previous activity will be subtracted from the latest event time of an event in order to find
the latest time of the previous event. Thus, the latest time of event 11 = latest time of event
12 – duration of activity N = 34 – 10 = 24 time units, as shown on the lower right half of the
lower half circle of event 11. Duration of activity K is 7 time units. Thus, latest time of event 8
= latest time of event 11 – duration of activity K = 24 – 7 = 17 time units. Similarly, latest time
of event 9 = latest time of event 11 – duration of activity L = 24 – 2 = 22 time units and latest
time of event 10 = latest time of event 11 – duration of activity M = 24 – 8 = 16 time units.
For event 7, we can reach event 7 in backward pass method, through 3 different paths –
through event 8, through event 9 and through event 10. Unlike before for forward pas s
method, we will take minimum of the times through these 3 paths, not the maximum one as
we did in forward pass method. Thus the latest time for event 7 = minimum(latest time of
event 8 + duration of activity H, latest time of event 9 + duration of activity I, latest time of
event 10 + duration of activity J) = minimum(17 – 4, 22 – 6, 16 – 2) = minimum(13,16,14) =13
time units. Duration of activity G is 5 time units. Thus, latest time of event 6 = latest time of
event 7 – duration of activity G = 13 – 5 =8 time units. Duration of activity E is 4 time units.
Thus, latest time of event 4 = latest time of event 6 – duration of activity E = 8 – 4 =4 time
units. Duration of activity F is 3 time units. Thus, latest time of event 5 = latest time of event 6
– duration of activity F = 8 – 3 =5 time units. Again, duration of activity C is 1 time unit. Thus,
latest time of event 2 = latest time of event 4 – duration of activity C = 4 – 1 =3 time units.
Duration of activity D is 2 time units. Thus, latest time of event 3 = latest time of event 5 –
duration of activity D = 5 – 2 =3 time units.
For event 1, we can reach event 1 in backward pass method, through 2 different paths –
through event 2, and through event 3. Thus the latest time of event 1 = minimum(latest time
of event 2 – duration of activity A, latest time of event 3 – duration of activity B)
= minimum(3 – 2, 3 – 3) = minimum(1,0) =0 time unit, as shown in the right half of the lower
half circle of event 1.

Now, based on the above earliest and latest event times, we can find out the project length or
project duration which is the length of the longest path. This longest path is known as
CRITICAL PATH. The critical path of a network is that path on which each of the events have
equal earliest and latest event times. In the above network, such event as observed are:
events 1, 3, 5, 6, 7, 8, 11, and 12. Thus the critical path of this network is:
B – D – F – G – H – K – N, as shown by the double arrow in the above network. The project
duration is the length of this path which is also equal to the latest time of the last event, that
is, 34 time units.
HOMEWORK

Calculate the earliest and latest event times of the above network.

PLEASE COMPLETE THE HOMEWORK AS GIVEN ON THE NEXT


SLIDE AND SEND THE ANSWER TO ME BY MAY 25, 2020