Part 3 of 3 Vol II
Part 3 of 3 Vol II
Volume 2.4
May 2020
page
2.2.37 LCPs, EMP and Maintenance Switches for the FSTs ........................................ 46
2.2.38 LCPs, EMP and Maintenance Switches for the RAS and WAS pumping
stations......................................................................................................... 46
2.2.39 LCPs, EMP and Maintenance Switches for the Sludge Thickeners.................. 46
2.2.40 LCPs, EMP and Maintenance Switches for the Drainage Pumping Stations ... 46
2.3 Automation ........................................................................................................... 46
2.3.1 General Control Philosophy ................................................................................ 47
2.3.2 Fault and Faulty Value Handling ......................................................................... 47
2.3.3 Control of the screens station ............................................................................ 47
2.3.4 Control of the Return Pumping Station at the overflow tank ............................ 48
2.3.5 Control of the Grease and Grit Chambers.......................................................... 48
2.3.6 Control of the PSTs ............................................................................................. 49
2.3.7 Control of the ASTs ............................................................................................. 49
2.3.8 Controls of the FSTs ............................................................................................ 49
2.3.9 Control of the Return Activated Sludge Pumping Station ................................ 50
2.3.10 Control of the Waste Activated Sludge Pumping Station ................................. 50
2.3.11 Control of the Thickener...................................................................................... 50
2.3.12 Control of the Mechanical Dewatering Station .................................................. 50
2.3.13 Control of the Polymer Dosing ........................................................................... 50
2.3.14 Control of the Thickened Sludge Pumping Station ........................................... 50
2.3.15 Control of the Drainage Pumping Station .......................................................... 51
2.3.16 Control of the Sand Filter Station ....................................................................... 51
2.3.17 Control of the UV Disinfection Station ............................................................... 51
2.3.18 Wash water booster ............................................................................................. 51
2.4 Standby Stationary Diesel Generator ................................................................. 51
2.4.1 Scope of Works .................................................................................................... 51
2.4.2 Innovation............................................................................................................. 51
2.4.3 Electricity Supply ................................................................................................. 52
2.4.4 Configurations ..................................................................................................... 52
2.4.5 Generating Unit .................................................................................................... 52
2.4.6 Ambient Temperature .......................................................................................... 52
2.4.7 Generator.............................................................................................................. 52
2.4.8 Prime Mover ......................................................................................................... 53
2.4.9 Engine Type ......................................................................................................... 53
2.4.10 Engine Mounted Control Panel ........................................................................... 53
visible cable runs, the arrangement and alignment of apparatus and fittings. Conduit
shall be surface run with the exception of the control/office room where all fittings shall
be suitable for flush installation.
(2) The positions of all equipment are shown diagrammatically on the Contract Drawings,
but the exact locations shall be agreed with the Engineer before the commencement of
installation.
(3) There shall be included for the fixing of all switches, fuse boards, switchgear, cables,
fit-tings, cable trays, accessories and all other items comprising the electrical
installation.
(4) All holes for fixing shall be made by means of a rotary drill, not of the percussion type,
screws shall be secured with rawl plugs or similar approved devices.
(5) A single shot cartridge tool may be used only at the discretion of the Engineer.
(6) Should the installer propose to use junction boxes in auxiliary control cable circuit for
the purpose of marshalling a number of cables feeding to a common item of equipment
full de-tails shall be given to the Engineer. The installer shall only proceed after receipt
of the written approval of the Engineer. Any such junction boxes shall be of the wall
mounting pattern with double terminals. All cores shall be ferruled and identified in
accordance with the system schematic and cable diagrams.
(7) All electrical installations, other than lighting and socket outlets, mounted externally to
buildings shall be provided with a permanent sun-shade canopy.
1.7 Switchboards and Multi-Motor Control Boards
Switchboards and multi-motor control boards shall comply with the following requirements:
1.7.1 Construction
(1) Distribution switchboards and motor control boards shall consist of a number of
cubicles of equal height and depth mounted side by side to form a composite board of
uniform and pleasing appearance.
(2) The maximum height of any operating control shall not exceed 1,800 mm.
(3) All main cubicles shall be constructed from sheet steel of a minimum thickness of 2mm
and shall be totally enclosed welded construction arranged for wall mounting or floor
fixing with removable back covers and hinged front doors interlocked that the doors can
not be opened when the breaker or starter is in the “ON” position if so specified. All
cubicle doors shall be fitted with chromium plated key operated latches using a
triangular shaped key. The size and weight of any removable cover shall be such that it
can be handled easily by one person. The metal base of the cubicles shall be provided
with removable plates below the cable gland trays. All cubicles shall be dust and
corrosion and damp protected and be fully vermin proofed. The method of vermin
proofing shall be such that additional cables can be added or removed after the initial
installation has been completed. All steel parts shall receive corrosion protection
treatment before painting, except moving parts, which shall be greased. The outside of
the cubicles and the interior of the compartments shall be stove-enamelled to IEC
standard, enclosure protection to IP 54.
(4) Compartments shall be easily accessible for maintenance purposes. Barriers shall be
included between each compartment to contain an internal fault as defined in IEC
standards to ensure safe maintenance on any outgoing circuit when the remainder of
the board is live.
(5) Cubicles shall not rely on any removable portion for their rigidity.
(6) Boards shall be arranged for ready extension at each end.
(7) Particular specifications shall be as indicated in the Drawing and described hereafter.
1.7.2 Busbars
(1) Busbars and connections shall be identified by phase colour marking and adequately
supported by suitable insulators the whole to be mechanically and electrically designed
to withstand the full fault capacity as specified.
(2) All busbars and connections shall be rated for continuous operation. The mechanical
and dielectric strength of busbars and support shall be capable of withstanding the
worst conditions of electrical surge which can occur in the installation.
(3) Busbars and primary connections shall comply with BS 159 as appropriate and shall be
housed in air insulated enclosures with a time rating compatible with the switchgear.
(4) Busbars shall be of high conductivity tinned copper with PVC sleeving and moulded
PVC shrouds shall be provided over joints.
(5) Bolted copper busbar links shall be provided as necessary to allow a switchboard to be
manufactured in sections. These links shall only be used to allow the transportation
and erection on site of a modular switchboard. The links may also be used as
necessary for maintenance purposes. The link section shall be easily accessible from
the front or top of the board and shall have a lockable cover. Provision for storing the
links, nuts and bolts shall be made in the switchboard.
(6) Busbars for 400v switchboards and MCC’s shall be rated at least 50kA for 3 seconds.
1.7.3 Fuses
(1) All fuses shall be H.R.C. according to IEC 129,265 and 420 and one spare fuse for
each fuse fitted in the panel shall be supplied clipped adjacent to the position in which it
would be in service.
(2) A complete schedule of all fuses in the panel shall be affixed in convenient position in
the panel.
(3) Neutral links shall not be arranged in fuse holders but shall be separately bolted copper
links with one link for each fuse.
1.7.4 Terminals
(1) All terminals for outgoing connections shall be located at a low level in the
compartment adjacent to the cable gland trays.
(2) Provision for accommodation of rising armoured cables shall be provided with
adequate cable supports and a form of cable entry seal either of hardwood or similar
approved material shall be provided.
(3) Space shall be provided to accommodate cable glands of appropriate size for incoming
and outgoing circuits and non-ferrous gland plates shall be supplied where single core
cables are terminated. All glands and trays shall be adequately earthed.
(4) Cable disconnecting links shall be provided where specified and shall be used for
maintenance purposes only. The links shall be fitted to the busbar risers immediately
before the cable terminations and shall be easily accessible. The links shall be labelled
“ISOLATING LINK” and the circuit or cable reference shall be quoted.
1.7.6 Labels
(1) The Contractor shall supply and fit engraved labels to all items of system, etc.
throughout all installations. System reference numbers shall correspond to those used
in the operating and maintenance manuals. Labels shall be white laminated plastic with
engraved black letters and shall have chamfered edges using either stainless steel
nuts and bolts or permanent adhesive. Labels shall be engraved in English. The main
circuit label shall measure 150 x 60 mm. All door mounted instruments and controls
shall have labels of 40 x 15 mm. All devices installed inside the enclosure shall be
labelled.
(2) For electrical panels, switchgear etc. labelling shall be as follows:
(a) All external labels shall be white laminated plastic with engraved black letters in
English and Arabic. Edges shall be chamfered. The labels shall be affixed with
stainless steel nuts and bolts.
(b) All internal labels shall be engraved multi-layered plastic (Traffoloyte or similar)
affixed with stainless steel nuts and bolts.
(c) Each compartment door shall have a title label and each door mounted
component or control shall have a function label.
(d) Every internal component shall be identified and each fuse shall be labelled with
identification of fuse type or fuse current capacity.
(e) Compartments with doors or covers not interlocked at an isolator shall have an
external label affixed thereto as follows:
DANGER - LIVE TERMINALS
with flash and voltage in red letters on white background in English and Arabic.
(3) In addition to the above system identification labels the Contractor shall ensure each
item of machinery shall have manufacturers identification / rating plate detailing in
English the following:
Manufacturers name and address;
Model / type identification;
Serial number;
Year of manufacture;
Dorsch International Consultants GmbH 5
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP Technical Specifications
Part 4 Electrical Specifications
(5) Un-drilled gland plates shall be provided approximately 300 mm above floor level for
the reception of conduits and threaded glands. Boxes and glands shall be within the
cubicles except where otherwise approved.
(6) Prior to manufacture the Contractor shall confirm cabling termination requirements with
the Engineer.
1.7.11 Instruments
(1) All indicating instruments shall be of 90o scale type flush mounted and generally of the
same appearance throughout. They shall comply with IEC recommendation and be of
industrial grade accuracy. Instruments shall be hermetically sealed or tropicalised.
Instruments shall have external zero adjustment and have black bezels. They shall be
positioned such that they can be easily read and the dial centres shall be not less than
400mm and not more than 1800 mm above finished floor level. Meters shall be fitted
with an adjustable pointer or shall be inscribed on the scales to indicate the normal
circuit rating for the associated plant.
(2) Instruments shall have a square front appearance with width dimensions as follows:
72 mm Ammeters up to (1.2 x Full load current) A, voltmeters up to 600 V
96 mm All other instruments
(3) Ammeters fitted in a motor circuit shall have a suppressed scale to indicate the
maximum starting current.
(4) Kilowatt hours meters shall be arranged to register 3 phase 4 wire unbalanced loads
except as otherwise indicated.
(5) All instruments shall be mounted adjacent to the relevant circuit breaker switch or
starter unless separate panel suites are specified herein.
(6) At points of connection of potential circuits to LV busbars etc., HRC fuses shall be
provided to protect the auxiliary wiring. For cubical gear these fuses shall be housed
inside and readily accessible. Additional fuses to clear individual instrument faults shall
be provided and accessible from the front of the cubical where otherwise specified.
1.8 Current Transformers
(1) Current transformers shall comply with IEC 185 and should be suitably rated and de-
signed to carry out the desired appropriate function - viz. metering or protection.
(2) The short time current rating should not be less than 3 seconds.
(3) Identification labels giving type, ratios, accuracy limit factor, rating output and serial
numbers shall be fitted.
(4) Duplicate rating labels are to be fitted on the exterior of the mounting chambers
suitably located to enable reading without removal of any cover. Labels shall be
supplied for multi-ratio current transformers indicating the connection required for
alternative ratios.
(5) Bar type current transformers shall be supplied in preference to those with wound
primaries. Short time current factors shall relate to the full fault level for three seconds.
For over-current protection the product of VA rated burden and rated accuracy limit
factor shall be less than 150 unless otherwise agreed with the Engineer.
(6) One secondary terminal of each current transformer shall be earthed through a
removable link at the switchgear.
Dorsch International Consultants GmbH 7
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP Technical Specifications
Part 4 Electrical Specifications
(6) Closing and tripping batteries shall comply with these Specifications.
(7) Auxiliary contacts for the indication of breaker state for use at 230V AC shall be
provided.
(8) Slow closing of the circuit breakers to facilitate maintenance and contact adjustment
shall be provided. This operation shall be possible only with circuit breaker in the fully
withdrawn position. Any necessary handle or lever shall be included in the schedule of
spare parts.
(9) All circuit breakers shall be provided with interlocks to ensure that:
(a) Circuit breakers can not be plugged in or isolated when it is closed.
(b) The Circuit breaker can not be closed until it is fully plugged in or completely
isolated.
(c) The Circuit breaker can not be closed in the service position without completing
the auxiliary circuit between the fixed and moving positions.
(d) With the circuit breaker earthing device in position tripping may only be effected
by a manual device in the operating mechanism.
(10) The following flush mounting equipment shall be fitted to the front of each of incoming
circuit breaker panel (both mains and standby):
1 No. Under voltage relay
1 No. Phase sequence relay
1 No. Triple pole flush mounted over-current relay arranged for two poles over-
current and one pole earth protection with auxiliary relay for instantaneous
remote trip and indication.
1 No. Voltmeter (0-500V) with selector switch for phase/phase, phase/neutral and off
positions fitted to line side of incomer.
1 No. Kilowatt hour integrating meter
1 No. Kilovar integrating meter
1 No. Kilowatt meter
1 No. Pilot lamp of the transformer type with protection fuses, colour blue, for
“SUPPLY AVAILABLE” when illuminated.
1 No. Pilot lamp with protection fuses, colour white, for “Trip Circuit Healthy” when
illuminated.
1 No. Set of Test Blocks for C.T’s and P.T’s.
NOTE: Interlocks are required between mains, incomers and standby incomers such
that it shall be impossible to have both closed at the same time (except in the
with-drawn position). These shall be arranged such that all permissive and all
prohibitive signals are present before a circuit breaker may be closed.
(11) Any other interlocking shall be provided as necessary to ensure the safe operation and
maintenance of all electrical equipment provided under the Contract.
(12) Individual shutters which automatically operate as the truck is racked in and out, shall
be provided for busbar and circuit spouts. When closed the shutter shall effectively
prevent any contact with either the bus bar or circuit connections and also seal the
spouts against the ingress of dust. The shutters are to be coloured and painted in bold
Dorsch International Consultants GmbH 9
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP Technical Specifications
Part 4 Electrical Specifications
1.10.1 Enclosure
(1) The enclosure shall be so constructed that the cover can not be opened until the switch
is fully opened and the construction shall be such that when the cover is opened a
competent examiner can override the interlock and operate the switch. After such
operation the cover shall be prevented from closing with the switch position indicator in
a false position.
(2) Switch shall be provided with mechanical “ON/OFF” indicators and operating handles.
(3) Means shall be provided for locking the switch in the “OFF” position only.
1.10.2 Fuses
(1) The fuse shall either include a suitable fuse carrier or it shall be capable of isolation. If
the fuse carrier is included it shall be such that when it is being withdrawn normally or
when it is completely withdrawn the operator is completely protected from accidental
contact with any live metal of its fuse link, fuse contacts and fixed contacts.
(2) If the fuse is capable of isolation it shall be so interlocked with the switch that isolation
is complete before the fuse enclosure can be opened, further the switch shall be
prevented from closing while the fuse-cover is open.
1.11 Isolating Switches
The compartment isolating switch shall interrupt all supplies into the compartment to enable
safe maintenance to be undertaken. Isolators shall be of the fault break load make design.
Isolators shall have metal handles and a facility shall be provided to enable the isolator to be
padlocked in the “OFF” position only. One padlock with 4 keys shall be supplied for each
isolator on the board.
(5) The motors in some groups will be required to operate in a predetermined sequence
and starters should include suitable auxiliary relays and contacts.
(6) All starters shall contain a totally enclosed dustproof timer or the operation will be con-
trolled by a timer in the automatic section which shall have multiple contacts and also
be to-tally enclosed dustproof which shall prevent pump(s) starting after a power failure
until after a prudent time has elapsed. The timer(s) or contact shall be adjustable in the
range 50 percent to 200 percent of the anticipated maximum delay which shall be
taken as twice the total time required for all pumps to start and run steadily having
been started consecutively. The timer(s) or contacts shall be set to give individual
sequential start after a power failure with no drive starting until its predecessor has
reached full steady running.
1.14 Interlocking
(1) Mechanical interlocking shall be provided where possible. All electrical interlocking
shall be of the double type having separate permissive and prohibitive interlocks. Thus
to allow a device to operate there must be an absence of prohibitive signals and a
presence of permissive signals from the remaining devices in the interlocked system.
(2) Suitable equipment shall be provided mechanically to prevent a device being manually
operated when a prohibitive signal from another part of the interlocked system is
present.
1.15 Protection
(1) All protective relays shall conform to the latest edition of IEC Standard 157-1 and be
suit-able for the climatic site conditions fully sealed against ingress of moisture, or dirt
and tropicalised.
(2) The relay shall have automatic thermal compensation for variation in the temperature
between 0 to 55°C.
(3) All protective relays shall be supplied in flush mounted metal cases with glass
windows.
(4) Relays shall be mounted on a withdrawable chassis with plug-in facilities.
(5) Each individual element of the relay shall initiate a flag to indicate that the element has
operated. The element and flag shall be reset by operating an external reset button
mounted on the front of the relay case.
1.16 Motor Protection
For all motors up to 75 kW three single pole wound magnetic adjustable overloads high set
for starting and stalling protection and three single pole thermal overloads for overload and
single phasing prevention shall be provided.
grid will remain in operation. Subsequently relay setting schemes shall be furnished by
the Contractor for approval by the Engineer.
(3) The following relays and associated current transformers shall be applied for all 400 V
circuit breakers to be installed.
(a) Overload or overcurrent relays with either an inverse time delay overcurrent re-
lease or a definite time delay overcurrent release whichever type is more suitable
and interconnected to it.
(b) Short-circuit relay with instantaneous overcurrent release.
(c) Earth-fault relay or earth leakage relay with a three phase sum current trans-
former acting on a response current from 0.2 to 0.7 times the rated current which
can be set in several steps. The delay time of the release shall also be variable in
several steps between 100 and 500 millisec in order to attain the above
mentioned back-up protection.
(d) Undervoltage relays shall be installed only in circuit breakers used for feeders of
large motors in order to avoid automatic restarting of motors after voltage
recovery following a power failure.
(4) All relays shall be equipped with respective fault communicators and indicators for
audible and visible fault indication in the control room. A fault panel shall be part of the
supply. Connection works shall be included.
(5) Auxiliary switches to be actuated by the operating mechanism shall be available in
sufficient quantities to cover all control, indication, operation and protection
requirements.
(6) The Contractor shall submit circuit diagrams of all main, control and protection-circuits
of the circuit breakers to be used.
(7) Submersible pump motors because of inherent design are to generally comply with the
foregoing.
(8) Centrifugal pumps on unscreened sewage shall give at least 100% full load torque on
starting.
(9) All motors shall be suitable for operation on a 400 V, 50 Hz, 3 phase supply.
(10) All motor enclosures shall satisfy and be selected from:
IP55 for general purpose drives and for outdoor or machines subject to splashing
or washing down
IP68 for submersible machines
(11) The motors shall run in ball and/or roller bearings and the weight of the motor shall be
carried by thrust bearings incorporated in the motor body.
(12) The efficiency and power factor of the motors shall be high over a wide range of load
conditions and the motors shall be designed, manufactured and tested in accordance
with IEC 34 for continuously rated industrial electric motors with Class F insulation but
limited to Class B temperature rise. The maximum continuous rating (MCR) of each
motor shall be as set out below and shall be rated and designed for operation in
ambient temperatures up to 45°C and capable of prolonged operation in sand laden
atmospheres.
MCR RATINGS
Application Up to 75 kW drive Above 75 kW drive
All pump motors 10% above that 5% above that
(excluding positive required under all required under all
displacement type) conditions of conditions of
operation operation
NOTE:
(a) The reserve power requirements shall be added to the calculated power prior to any other
adjustments, e.g. high ambient temperatures at site.
(b) All motors shall have Classification “F” insulation but Classification “B” temperature rise limitations
shall apply. It should be noted, however, that this requirement is in addition to any adjustments
necessary for high ambient temperatures at site.
(18) All submersible pump motors shall be provided with slot temperature detection
(resistance thermometers) embedded in each phase of the stator winding, the leads of
which shall be brought to the terminal box.
(19) Out of these measurements, at least one maximum temperature contact shall be
derived either thermostatically or electronically and this thermal contact shall give alarm
and or trip its associated motor starter circuit breaker when the motor winding
temperature reaches its maximum allowable value.
(20) Motors with sleeve bearings shall be fitted with one dial type thermometer on each
bearing for local control and either thermo-couple or resistance thermometer for remote
indication, with oil level indicators marked for running and stand-still., oil flow indicators.
(21) Arrangements shall be made with the manufacturer so that the Engineer may witness
tests.
1.17 Reactive Power Compensation
(1) A "capacitor bank" for central reactive power compensation according to IEC
publication No. 70 shall be incorporated in each switchboard or MCC. The capacitor
bank shall consist of a definite number of parallel operated 400 V capacitors and their
associated feeders of individual fuse switch combinations.
(2) All this equipment shall be readily mounted inside suitable 400 V panels and shall be
connected ready for operation.
(3) Individual capacitor banks shall not exceed 150kVAr in rating. If a larger capacity
capacitor bank is required it shall comprise a number of banks of equal rating, each
bank not exceeding 150kVAr in rating.
(3) The power factor correction shall be permanently connected in circuit via the
associated fuse switch and shall be such as to keep the power factor to a figure not
more than 0.97 lagging.
(4) When dimensioning the total capacitance, as well as the number of parallel operated
capacitors, a design analysis shall be carried out based on the actual power factors of
motors as given by the manufacturer.
(5) Over compensation, i.e. self-excitation of the circuits shall be avoided in all cases.
1.18 Distribution Boards
(1) All distribution boards shall be of the totally enclosed metal clad pattern manufactured
in accordance with IEC standard publication No 28A5, 157,158,185,337,439,144 and
529.
(2) Fuses, MCB’s and MCCB’s as incorporated in distribution boards shall comply with the
relevant IEC standard and be fitted with thermal overload and instantaneous magnetic
short circuit protection. Earth leakage protection, when specified, shall be current
operated.
(3) The enclosure shall be made from zinc coated mild sheet steel formed to a clean line
and complete with a lockable hinged cover with gasket. Covers shall be fitted with
gaskets and shall be easily removable to preserve the finish and simplify installation.
Each distribution board shall be arranged for top and bottom cable entry and shall be
provided with an ample cable termination plate and chamber to enable cables to be
neatly glanded with tails grouped and terminated onto appropriate internal terminations.
(4) Distribution boards shall be wall or floor mounted and shall incorporate load break fault
make incoming isolators which shall be front of panel operated with “ON/OFF” indicator
and capable of being padlocked in the “OFF” position. Distribution boards shall
incorporate HRC cartridge fuses or combinations of single pole and neutral and triple
pole miniature circuit breakers (MCB) as specified. For DC circuits and power outlets
double pole shall be used.
(5) Each bank of MCB/fuses shall be clearly identified with its appropriate phase colour
code and the mounting framework for the banks of MCB/fuses shall be easily
removable to simplify installation. Adequate phase barriers and shields shall be fitted to
ensure that after installation and wiring, all bare terminals and wires are covered to
prevent accidental contact with live conductors during the normal procedure of fuse
changing and resetting of MCB.
(6) All fuse distribution boards shall be complete with HRC fuse cartridges manufactured in
accordance with IEC standards with fusing factor of 1.5 to afford ‘close’ overcurrent
protection to circuits as defined in the IEC No. 408.
(7) All neutral bars shall have a separate terminal for each fuse / MCB way within the
distribution boards.
(8) The termination of circuit cables at distribution boards shall be neat and slack left at
each fuse / MCB bank or neutral bar to enable the complete assembly to be removed
for inspection without disconnection. Neutral conductors shall be connected to the bar
in the same order as the phase conductor to the fuse / MCB way.
(9) Each distribution board shall be complete with a permanent circuit identification chart
preferably mounted within the front door. This chart shall be permanently and legibly
filled in as circuits are completed the circuit description including the fuse mcb rating.
The chart shall be in English.
1.19 Remote Control Push Button Station
(1) Adjacent to all motors and in the positions specified there shall be supplied, installed
and mounted on a suitable structure, a metal, weatherproof, heavy duty remote control
station.
(2) The support structure shall be a robust floor mounted mild steel hot dip galvanised
structure, comprising a tube mounted to a base plate with a mounting plate for the
remote controls positioned 1500mm above floor level. The base plate shall be
designed for bolting down to a concrete foundation and the tube shall provide the
conduit for the control cables from ground level to the position of the remote controls.
(3) Each control station shall have an Emergency stop push button actuator of the auto
latch-turn to release type. The actuator head shall be red, mushroom shaped and
clearly labelled STOP in English. The Emergency stop button shall work in all modes of
control.
(4) Each control station shall have two, 2 position, rotary switch units. One switch unit shall
effect the manual operation of the associated drive and shall be labelled START and
STOP. The other switch unit shall effect the selection of automatic or manual control
and shall be labelled AUTO and MANUAL. In auto the function of the local start stop
switch shall be disabled.
(5) It is the responsibility of the Contractor to ensure that the pushbutton stations provided
are all from the same manufacturer.
1.20 Cables
(1) All cables shall comply with the requirements of the relevant BS/VDE standard for the
type of cable supplied.
(2) All cables shall be of a suitable voltage grade and stranded copper cored.
Manufacturer’s test certificates shall be submitted for all armoured cables 600/1000 V
and above to the Engineer, before the cables are despatched.
(3) The Contractor shall ensure that each cable is of sufficient rating for its normal and
fault conditions. To assess the rating and cross section required for each cable the
following factors shall be considered:
Fault level
Conditions of ambient temperature relevant to method of laying
Voltage drop
Voltage drop in motor circuits due to starting
Overcurrent settings of circuit breakers
Disposition of cabling whether in air ducts or ground
(4) The Contractor shall state the cable sizes in his quotation. The cable sizes are to be
approved by the Engineer before ordering. Cable rating shall be calculated in
accordance with VDE 0271 and IEC standards 502 and 228.
(5) The selection of cables shall be based on the following conditions:
Ground temperature 25°C
Air temperature 35°C
Thermal Resistivity 4.2.5°C m/w
For PVC insulated cables, circuit protection will normally be “Close” with fusing or
tripping at 1.5 times the cable rating within 4 hours.
(6) The Contractor shall prepare Technical Schedules showing all principal power and
control cables/wires to be supplied. All such cables and wires shall be numbered in the
Schedule, the same reference numbers being used in the contract drawings and
Specification. The following data shall be included for all cables in the schedule:
Cable identification number
Route from/to
Type of cable
Derating factor used
Cross sectional area (mm2)
Length (meters)
No. of cores (excluding earth conductor)
Number of spare cores
(7) All cables necessary for the complete operational installation shall be included.
(8) The Contractor shall be responsible for measuring from the contract drawings the
length of cables required. The cable size are to be approved by the Engineer before
ordering.
(9) Each cable shall be supplied in a suitable length and be continuous through its run.
Through joints will not be permitted without written permission from the Engineer.
(10) The earthing conductor shall be of adequate cross sectional area and shall either be
one core of a multicore cable or on a separately run single core cable. The use of cable
armouring, conduit, water or other service pipes in any part of the earth continuity
conductor is strictly prohibited.
(11) The Contractor shall supply and install all necessary cable glands and sealing boxes
required to complete the installation. All materials used in the manufacture of the
glands etc. shall have no deleterious effect on the cable core or armouring and shall be
non-corrodible.
1.21 Plastic Insulated Wire-armoured Cable (PVC SWA PVC)
(1) Thermoplastic insulated cables shall be Cross linked Polythene (XLPE) type and
comply with VDE 0271 and IEC 502 and IEC 228 class 1 and 2 respectively. They shall
be 600/1000 V and comprise of stranded copper conductor, XLPE insulation, suitable
bedding, steel wire armoured and PVC sheath.
(2) The cables shall be of approved manufacture.
(3) Aluminium armour shall be provided on single core cables.
(4) All such cables shall be terminated with mechanical glands in accordance with IEC
standards 502 and 540 which shall be of a type to provide adequate mechanical
support by locking on the armour and shall at the same time give high earth continuity.
1.22 PVC Insulated Cables
PVC insulated cables shall comply with VDE 0271 and IEC 228 class 1 and 2 and IEC 502
and shall be 600/1000V grade. The cable used shall not be less than 1.5 mm 2 cross
sectional area.
1.23 Building Services Wiring
(1) In general wiring for plant machinery shall be carried out in XLPE SWA PVC while the
building services shall be executed in PVC cable enclosed in heavy gauge screwed
galvanised conduit. The minimum copper conductor size used shall not be less than
1.5 m2. The use of junction boxes between fittings shall be kept to a minimum and
where practicable all connections shall be made at the fitting. When used, junction
boxes shall be rectangular pattern and where possible their position shall be hidden
from immediate view but not made inaccessible. Circuit wiring shall not be connected
directly on to the terminals of lighting fittings but shall made off in point boxes
consisting of standard BESA box containing shrouded pinch screw connectors to which
connections shall be made to the light fittings by flexible cables.
(2) The Contractor must ensure that the installation is installed so that not more than one
phase shall occur at switch lighting of power outlets where these outlets are less than
2.5 m apart unless guarded by a wall partition or other barrier. If this is impracticable
the Contractor shall obtain the advice of the Engineer before proceeding.
(3) The scheme of wiring shall conform to the colour code requirements of the IEC
Regulations.
Dorsch International Consultants GmbH 19
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP Technical Specifications
Part 4 Electrical Specifications
(4) A minimum length of 250 mm tails shall be left on all cables at outlet positions for
connection of the lighting fittings or other apparatus fed by the outlet.
(5) The installation of multi-core and single core cables or bunching of cables in conduit is
to be carried out on the assumption that such cables will carry alternating current.
(6) The excessive bunching of small cables in large conduits will not be permitted and the
Contractor shall not exceed the requirements of the regulations.
(7) The Contractor shall include for terminating each cable in excess of 30A current
carrying capacity in a pressure operated mechanically crimped leg terminal or terminal
socket.
1.24 Cable Installations
The electrical works shall include all cables and wiring necessary for the equipment including
supply and installation of cables and accessories, e.g. fastenings and mountings, screw
connections, cable lugs etc.
Power cables shall be separate from control and measuring cables.
Non-corroding materials shall be used exclusively. All cables shall be marked permanently
on both ends and at all separating and measuring points by way of durable marker labels.
The shielding of measuring and control cables shall be separately and adequately grounded
at the switch box.
Cable laying shall be effected by way of cable tray on walls and ceilings and ducts and
trenches in the floor or ground, duly executed in orderly fashion and sufficiently spaced
(especially power cables) in order to provide adequate ventilation. All cable tray installation
techniques shall not be used in excess of 60 % of their capacity.
On all cable trays, power transmission cables shall be installed in single layers, signal,
measuring and control cables may be installed in multiple layers. Separate cable trays shall
be provided for power cables and measuring and control cables. Accumulations and
crossings of cables shall be avoided.
The Contractor shall install standardised components only. Certificates of type acceptance
test shall be presented. Fastenings of all kinds shall be effected by way of wall plugs, dowels
etc. according to the building authorities' regulations. All fixings and fastenings shall be
stainless steel.
Where there is a possibility of aggressive substances (solvents), cables shall be designed
and/or protected accordingly (solvent-resistant). Also, areas of high ambient temperatures
shall be duly taken into account when choosing cables and wires.
Adequate measures shall be taken in design and construction to prevent water from entering
dry chambers through empty ducts.
Each cable duct shall be equipped with a 4 mm polypropylene pull rope. Where cable routes
pass through building walls or floors, suitable arrangements shall be provided to make good
the aperture when the cables have been installed.
1.25 Cabling Methods
(1) Every cable shall be installed in accordance with the relevant IEC Standards
Specification.
(2) Every cable shall be neatly run vertically, horizontally or parallel to adjacent walls,
beams or structural members.
(3) Suitable screens shall be provided to protect the cables, run on the external surface of
structures or above ground level, from the effect of the sun’s radiation. All screens used
to protect the cable shall be of an approved design, securely fixed to the structure or
ground and be fully ventilated.
(4) Where cables are terminated at a particular item of equipment care should be taken to
ensure that the cables finally approach the equipment from a common direction and
are individually terminated in an orderly and symmetrical fashion.
(5) All necessary materials for cable jointing and junction boxes required to complete the
installation shall be included. Cable ends shall be sealed in suitable chambers bolted to
terminals of circuit breakers and other equipment. Every cable shall be supported
where necessary by an approved method. All cable glands shall have a non-corrodible
finish and shall be supplied complete with PVC shroud.
(6) XLPE insulated cables shall be terminated in mechanical glands in accordance with
IEC standards No. 502 and 540, which shall be of a type to provide adequate
mechanical support by locking on the armour and give good earth continuity.
(7) Paper insulated cables with lead or lead alloy sheath shall be terminated in a suitable
wiping gland.
(8) All cable conductors shall be terminated in a suitable copper lug.
(9) Paper insulated cables shall only be joined or terminated by staff fully qualified to work
on this classification of cable. Before proceeding with the joint or termination the ability
of the staff employed on the work shall be demonstrated on site by making trial joints to
the satisfaction of the Engineer.
(10) Where cables enter or leave buildings the ducts shall be sealed at the points of entry
into the building. Caulking shall be carried out in fiberglass followed by not less than 40
mm of bitumen compound or a weak sand/cement mixture as directed by the Engineer.
Care must be taken to ensure that the PVC sheathing of cables is not damaged during
caulking due to excessive temperature if heated bituminous compound is employed.
(11) Wherever it is necessary to remove the PVC sheath of a cable e.g. at a joint, the mini-
mum length necessary shall be removed and the exposed copper conductor, sheath or
armouring shall be adequately covered by a PVC tape or sleeve or other suitable
means.
(12) All cables shall be delivered on robust cable drums with cable ends treated to form an
effective seal. When a cable is cut from a drum the cable end left on the drum shall be
immediately sealed in an approved manner to prevent the ingress of moisture. All
cables once they have been cut shall be either terminated in their final position
immediately or effectively sealed, paper insulated lead sheathed cables by sweating,
thermoplastic by taping in an approved manner.
(13) Every cable shall be permanently identified at each end by its cable number. Cable
markers shall be of adequate size and of a style approved by the Engineer. Cable
markers shall be securely fixed to the cable.
(14) Cable route marker posts shall also be installed at entry and exit points of buried ducts,
exits from buildings (if necessary wall mounted) and in such other position as are
necessary to identify and trace the route of any cable. All power cables shall be
connected to the main switchboard and other items of plant so that the correct phase
sequence and phase colour coding are preserved throughout the system. All such
cables shall be identified with phase colours for 3 and 4 wire systems and blue and
brown for single phase. On rotating plant where to achieve the required direction of
appropriately identified terminals then special core ferrules shall be fitted to identify
each core with the terminal to which it is finally connected.
(15) Control and instrument cables shall have individual cores identified by means of
suitable permanent ferrules bearing the same numbers or letters at both ends and
corresponding with terminals on equipment. Core identification shall be shown on the
wiring diagrams of the equipment at which the change is made.
(16) Numbering shall read from the terminals outwards on all cores. At those points of inter-
connection between wiring where a change of number can not be avoided, double
ferrules shall be provided on each wire. The change of numbering shall be shown on
the wiring diagrams of the equipment at which the change is made.
(17) If it is proposed to use junction boxes in auxiliary control cable circuits for the purpose
of marshalling a number of cables feeding to a common item of equipment full details
shall be given to the Engineer and he shall only proceed after receipt of the Engineer's
written approval. Any such junction box shall be the wall mounting pattern with double
terminal with cores ferruled and identified in accordance with the system schematic and
cable diagrams.
1.26 Cable Trench Work
(1) The Contractor shall prepare drawings showing his precise requirements for cable
trench work, detailing the width and depth of trenches utilising the road crossing cable
ducts shown in the Contract Drawings. These drawings shall be prepared in
consultation with the Engineer and be approved before issue and be based on Contract
Drawings showing proposed cable routes.
(2) The excavation and backfilling of trench work will be carried out by the Contractor.
(3) The Contractor shall be responsible for ensuring that the trench work is adequate for
his requirements and in accordance with his trench work drawings.
(4) The Contractor shall supply and lay the sand bedding, supply and lay the cables,
supply and lay sand blinding and supply and lay cable covers; he shall also supply and
lay cable route marker posts after the backfilling and top soiling has been carried out by
the Contractor.
(5) The sanding and laying of cables shall satisfy the following requirements:
(a) Cables shall be laid at a depth of 0.5 meter for LV and 1.0 meter for HV cables
according D1 of table A.52.3 of IEC 60364-5-52 . The depth shall be assessed
from finished ground level unless otherwise directed by the Engineer.
(b) Generally, LV and HV cables should not run in the same trench but should be
laid staggered. However, where necessary to pass through ducts it will be
necessary to lay one above the other and HV cables should be laid first and
cable cover tiles laid before laying the LV cables.
(c) Before laying cables the Contractor shall ensure that the bottom of each trench is
firm and of smooth contour and free from broken stones or rock.
(d) 75mm of sand shall be placed in the trench to form a bedding for the cables.
(e) Cables shall be laid with adequate separation and shall be gently ‘snaked’ to
avoid tension during backfilling and subsequent settlement.
(f) The Contractor shall provide all necessary plant for the installation including
feeding rollers, winches, draw-in stockings, etc. and all the necessary labour.
(g) The Contractor shall deal with or dispose of water to prevent risk to cables and
flooding of interconnected buildings.
(h) To this end the Contractor shall not unduly delay laying of cables once a trench
has been opened and temporary sealing of building entries shall be provided by
the Contractor if all cables are not laid in one session.
(i) Before sanding and backfilling all laid cables shall be inspected by the Engineer.
(j) A second inspection following sanding and tiling shall be made by the Engineer
before backfilling.
(k) After cables have been laid they shall be covered with a further 75 mm of sand
which shall be well tamped around the cables. Mechanical means shall not be
used for this work.
(l) After sanding cable covers shall be placed in position to overlap the cables by a
minimum of 50 mm either side of the cables.
(m) The Contractor shall carry out backfilling and ensure that tiles are not disturbed
and that no large rocks or stones are dropped on tiles or included in the backfill
material.
(n) After backfilling the Contractor shall reinstate to finished ground level and provide
and lay topsoil.
(o) There may be interval between the backfilling and topsoiling, if so the Contractor
shall provide temporary wooden route markers and erect these as directed by the
Engineer.
(6) The Contractor shall supply cable cover tiles. These shall be of the pre-cast concrete
type and engraved Electricity or other suitable symbol.
(7) Cable route marker posts shall be to approval of the Engineer and fitted with
permanently engraved label showing legend Danger Electric Cables, the appropriate
voltage and danger symbol of lightening stroke, legend to be in both English
languages.
(8) The general routing of cables is indicated on the Contract Drawings, but the final routes
shall be agreed with the Engineer before any work in connection with the cable
installation is commenced. All cables shall be installed in strict accordance with the
requirements of the Specification.
(9) All single core cables of the same circuit shall be grouped in trefoil and secured.
1.27 Cable Tray Work
(1) The Contractor shall supply and erect all required cable tray work.
(2) The following points are to be taken into account in selecting routes:
(a) Number of drive power and control cables to be located on each cable tray;
(b) The avoidance of existing pipe work and pipe work required for future extensions;
(c) The avoidance of maintenance areas of machinery pipes etc.;
(d) The avoidance of installation areas for the future extension to the system;
(6) Surface run conduits shall be supported at intervals in accordance with the following
schedule:
Size Interval
20 mm 1.2 m
25 mm 2.0 m
32 mm 2.5 m
(7) Where bends and sets occur in the conduit run, the conduit shall be securely fastened
at a distance of 225 mm either side of the diversion.
(8) Standard junction or adaptable boxes shall be provided at all junctions and at sharp
changes of direction in addition to any special positions where they are called for by the
Engineer.
(9) Only continuous lengths of buried conduit shall be installed between boxes, no joint
boxes being allowed in the floor screeds. Conduit crossing expansion joints shall be
fitted with couplings of approved manufacture with an earthing clip at each side of the
coupling connected by the correct size of tinned copper stranded wire.
(10) The ends of conduit laid or set in formwork prior to concreting shall be temporarily
sealed off with a coupler and a solid brass plug.
(11) No conduit shall be installed on the exterior surface of buildings without the written
approval of the Engineer. All exterior fittings shall be suitable for rear access.
(12) Fixing to surfaces of walls shall be by means of spacer bar saddles securely fixed by
screws. Where conduits are concealed or laid in construction floors, they shall be held
in position with substantial fixings of make and pattern to be approved by the Engineer.
(13) Conduit shall be of the screwed pattern galvanised by the hot process. All conduit fit-
tings not carrying accessories shall be supplied with flat covers fixed in position with
round head brass screws. Neoprene gaskets shall be supplied on all fittings.
(14) Adaptable boxes shall be constructed of minimum 3 millimetres sheet steel or best
quality cast iron finished as previously detailed for conduit bores and sized to prevent
the undue packing of cables in them.
(15) Weatherproof boxes and accessories shall be used outdoors and where indicated in
the Specifications or drawings.
(16) Conduit shall be installed such as to permit complete rewiring without the need to carry
out builders works.
(17) No Single conduit serving single phase socket outlets, lighting points and switches
shall contain more than one phase.
(18) Wiring shall be carried out on the looping-in system and no joints other than at looping-
in points will be allowed.
1.29 Flexible Conduit
(1) Where the conduit system terminates at any equipment requiring a non-rigid
connection, a flexible conduit shall be installed of the PVC or PVC sheathed metallic
type fully watertight with purpose made connection adaptors.
(2) Each flexible connection shall include not less than 400 mm length of flexible conduit
and a separate earth conductor shall be run within the conduit connected to the earth
terminals in the equipment and the fixed conduit run. The flexible conduit shall not be
used as an earth continuity conductor.
1.30 Cable Trunking
(1) The trunking shall be manufactured from heavy duty rigid unplasticised PVC which
shall be self extinguishing and shall be unaffected by sunlight or water. The material
shall be suitable for continuous ambient temperatures of 65°C. Each length shall be
supplied with the necessary connection sleeves and shall have joggled sides to allow
flush fitting.
(2) Each length trunking shall be fitted with easily removable covers attached to the
trunking by an efficient screw type fixing.
(3) The trunking system shall be complete with purpose made angle and set accessories
designed to afford easy installation of and to avoid tight right angle bends in the circuit
cables installed in the trunking. All trunking accessories shall be complete with
removable covers. No site made mitred joints shall be allowed.
(4) Where cable trunking is installed in vertical runs, efficient circuit cable clamps are to be
installed at not greater than 500 mm intervals.
(5) A continuous earth conductor shall be installed throughout the trunking system, with
provision for the connection of local circuits as necessary.
(6) All trunking shall be of adequate size to suit the number of cables passing through it
but as a minimum the size should be 50 mm by 50 mm. All bends, tees and
intersections to be of the gusset type and manufactured by the maker of the trunking
and to similar standard. The trunking shall be fixed to the walls and ceilings by means
of a secure and permanent fastening to be approved by the Engineer.
1.31 Socket Outlets
Socket outlets for installation throughout the Works covered by this Specification shall all be
of the waterproof corrosion resistant type and shall generally be mounted 1.30 m above floor
level as follows:
(a) 25 Volt, 5 A, 3 pin socket outlets complying with IEC 309-2/81 colour coded and
complete with matching colour coded plugs.
(b) 230 Volt, 16 A, 2 pin CEE 7/4 socket outlets.
(c) 400 Volt, 30 A, TP & N and E switched and mechanically interlocked. Each
socket outlet shall be supplied via current operated earth leakage circuit breaker
mounted within the distribution section of local switchgear/motor
control/distribution panel.
(3) The lighting systems shall comprise column mounted luminaries, typical fittings at hot dip
galvanized steel conical ribbed lighting pole 8m high.
(4) The lanterns shall incorporate changeable LED lamps ( Power : 100W, Lumen: 12000lm,
Light Efficiency: 120lm/W, IP Rating: IP66, Colour temperature: 3500K “Standard White” ,
Lifespan: 50,000 Hrs. Lantern shall be of the side entry inclined overhanging pattern with integral
lamp control gear, weatherproof die cast aluminium body, with hinged access cover and high
impact polycarbonate bowl.
(5) The columns shall be hot dipped galvanised steel with low level cable termination chamber
accessible through lockable front cover plates. The column cable terminations shall comprise a
fully insulated TP+N termination block for the loop-in termination of the main power cable
between columns, and insulated fused cut-out or MCB and neutral connection for the luminaries
circuit. Internal wiring shall be in PVC insulated and sheathed cable. Each column and lantern
shall be positively bonded to the main cable armour in an approved manner. Each column should
have its own earthing rod in addition to main earthing lead and earthing conductor
(6) The poles (columns) shall be mounted in concrete foundations with PVC lined cable entry
ducts.
(7) The lighting shall be fed on a single independent TP+N buried cable circuit, fed from the 400
V primary distribution switchboard located in the Administration building. The circuit shall be
controlled by a photo-cell switching circuit , timer circuit and manual control selector switch. The
photo-cell shall be wall mounted on the west face of Administration building.
moving parts are involved that they are earthed in any normal position e.g. circuit breaker
carriage, cubicle or sub-station door.
1.37 Earthing Systems
(1) The earthing system shall comply with the requirements of IEC Publication 364-5-54.
Earth tapes on 11 kV plant shall comprise a minimum of 50 mm x 6 mm copper tape
and on 400 V equipment 38 mm x 5 mm copper tape.
(2) The non-current carrying metal of electrical equipment provided under the Contract
shall be securely bonded to earth. Earthing shall be effected by means of the metal
sheath of cables which shall be securely bonded to the metalwork of the apparatus
concerned at each end or a separate earth conductor. A separate earth conductor shall
be provided for all items of plant rated 20 kW or greater.
(3) Armour wires on main cables shall be solidly bonded as additional earth path but
cables from the standby generators shall be insulated from the main earth system.
Particular care shall be taken on cable termination boxes bonded to the associated
item of plant. If continuity is adequate copper connections shall be made between the
apparatus frame and the cable sheath.
(4) Where the cable sheath and armour is used as the earth path return then it shall be
established that the resistance is less than 1.0 Ω. If not, a separate copper earth
conductor shall be installed.
(5) Particular care shall be taken to ensure earth continuity across items of equipment
situated within a cable run and should the design of such equipment not give adequate
and lasting continuity through its structural body then additional earthing clips and
conductors shall be provided to independently bond the cable sheaths together.
Similarly, additional earthing clips shall be provided to bond the cable sheaths to any
piece of apparatus fitted with a special earth terminal should the earth connection of
the termination gland prove inadequate. Any additional earthing clips shall be
contained within the apparatus wherever possible.
(6) The earth tapes shall be protected against corrosion and be complete with test links
and be run on walls held in position by saddles fixed by rawl plugs and screws.
(7) Connection shall be sweated and rivetted and shall be electrically and mechanically
continuous. Joints between the main conductor and the earth electrodes shall be
readily accessible for periodic inspection and shall be protected against damage and
corrosion.
(8) Where rigid or flexible conduit and/or trunking is incorporated into the Works, a
separate internal earth conductor shall be run which shall be securely bonded to the
terminating apparatus by means of a special earth terminal.
(9) The earth electrode system shall consist of two electrode beds or nest independently
arranged and each comprising a system of vertically mounted rods.
(10) On completion of the earth installation the Contractor shall demonstrate to the Engineer
that the resistance of the electrodes and the earth network is within the specified limits.
Test equipment shall be supplied by the Contractor.
1.38 Earthing Nests
(1) Each nest shall comprise of a number of interconnected earth rods, 25 mm in diameter
by 4.2.0 m long, driven vertically into the ground at intervals of not less than 3.0 m
apart with heads located at a depth to suit disconnecting chamber position.
Dorsch International Consultants GmbH 29
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP Technical Specifications
Part 4 Electrical Specifications
(2) Earth rods shall be copper or steel cored with a metallic bonded copper outer surface.
Rods shall be provided with special hardened tips and caps, to avoid distortion when
connecting the rod to the copper strip.
(3) Leads from each electrode shall be brought to concrete disconnection chambers to
enable each electrode to be disconnected for testing purposes.
(4) Concrete disconnecting chambers with removable cover and disconnecting lid, for test
purposes, shall be provided over each earth rod. The top of chamber shall be at
finished ground level.
(5) The test link shall be of copper and not be less than the connecting cables cross
sectional area and have a generous contact area.
(6) Disconnecting bolts, nuts, locknuts and washers shall be made from phosphor bronze.
(7) The copper strip connecting the earth rods to the test link shall be exothermically
welded at the test link and sweated to the top of the earth rod.
(8) The earth rod interconnections shall be an electrically unbroken ring and
interconnections shall be PVC insulated stranded copper conductor earthing cable
sweated to the test links. The cable shall be of sufficient low resistance to carry the
maximum fault current for a period equivalent to the clearing time of the protective
equipment without undue temperature rise.
(9) Joints at the head of the earth rods shall be easily accessible for periodic inspection.
(10) Earth nests shall be connected to their station associated earthing system by 2 Nos.
PVC insulated stranded copper conductor earthing cables. The cable shall be sweated
to opposite ends of the earth nest and to two different spaced points on the station
earthing system.
(11) The earthing system shall be protected against damage by corrosion wherever
necessary.
1.39 Location of Nests
(1) An earth nest shall be installed at sub-stations where such forms part of this contract.
(2) Earth nests shall be located adjacent to the building housing the switchgear as
practical. Where two nests are specified, they shall be located at opposite ends of the
system.
1.40 Battery Units
(1) A battery and charger set shall be housed in a single sheet steel floor mounted
ventilated cabinet with batteries housed in the lower part of the cubicle.
(2) The unit shall be complete with a self adjusting constant potential trickle charger
suitable for operating from 230 Volt single phase AC supply. The charger shall be rated
to continuously energise relay coils and lamps as applicable. The charger shall be
designed to maintain a constant voltage with +/- 3% irrespective of mains voltage or
frequency variation. Booster charge facilities shall be included. The unit shall be fitted
with the following:
1 No. Supply “ON” Indicating Lamp
1 No “ON / OFF” Switch
1 No Charger Ammeter
The unaffected maximum environmental temperature is 45ºC. The supplier shall install at
critical switchgear rooms a ventilation or air conditioning system.
The supplier shall certify that the switchgears and the controlgears are constructed and
tested according to IEC 60439. The supplier shall submit the heat dissipation and
temperature rise calculations for review and approval.
2.2.5 Colour
The colour for the internal and external surfaces of the metalwork of the panels shall be RAL
7032.
Backplates shall be white.
Starting Methods
DOL Starter with Motor Protection by C.B. and Contactor "Direct On Line"
SD Starter with Motor Protection by C.B. and Controlled Star Delta
Contactor Combination
SC Starter with Cable Protection by C.B. and Contactor (PLC controlled)
C Starter with Cable Protection by C.B.
Dorsch International Consultants GmbH 35
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP Technical Specifications
Part 4 Electrical Specifications
ROS Starter with Motor Protection by C.B. and two Contactors for "Reversible
Direct On Line" start
RS Starter with Motor Protection by C.B. and two Contactors, reverse only
for jogging application
SS Static (Thyristor controlled) SS with integrated Motor Protection (Short
Circuit SS Protection by special fuses)
SSB like SS, but with SS controlled Contactor bypass
VSD Static Controlled Variable Speed Drive by F.C. with integrated Motor
Prot. (Short Circuit F.C. Prot. by special fuses)
DS Starter with Motor Protection by C.B. and two Contactor for two different
motor windings and speeds
All Synchronization instrument and control devices such as control unit, PLC, check
relays …etc which achieve Automatic Synchronization.
All Measurements meters and devices such as : Digital power meter (Current,
voltage, frequency, power, Volt-phase angle .. etc.), analogue Ammeters , analogue
Voltmeter, Volt-phase and angle–frequency meters to can achieve Manual
Synchronization.
2.2.20 MCC2A
The contractor shall install the MCC2A in the in MLVSB room.
MCC2-A in the MLVSB room
Rated Data Starter
Feeders No. Pn(kW) In(A) Type
Incomer (at the left side) from MLVSB 1 1250/1600
Aeration blowers 1 3 200 360/ 400 VFD
Ventilator 3 1.5 10/32
Anoxic mixer 1 4 1.5 20/32
Internal recirculation pumps 1 2 3.5 15/32 VFD
AST flow maker 1 4 5.5 20/32
Overhead crane in blowers room1 1 5.5 30/100
Overhead crane in generator room 1 3 30/100
Dorsch International Consultants GmbH 38
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP Technical Specifications
Part 4 Electrical Specifications
2.2.21 MCC2-B
The contractor shall install the MCC2A in the blower room 2.
2.2.22 MCC3
The contractor shall install the MCC3 in the building for the RAS and WAS pumping stations.
MCC3 near FSTs
Rated Data Starter
Feeders No. Pn(kW) In(A) Type
Incomer (at the left side) from MLVSB 1 1000/1250
RAS pumps (in RAS/WAS station 1) 3 18.5 63/100 VFD
2.2.23 MCC4
The contractor shall install the MCC4 in the building for the dewatering plants.
MCC4 in Digester Building
Rated Data Starter
Feeders No. Pn(kW) In(A) Type
Incomer (at the left side) from MLVSB 1 300/630
Gravity Thickener Control Panel 1 1 1 10/32
Gravity Thickener Control Panel 2 1 1 10/32
Thickened Prime Pump 3 4 10/32
Ventilator Thickened Prime 1 0.25 6/32
Scum pumps 2 2 6/32
Digester Feed Pumps 3 5.5 10/32
Gas Injection Compressor 2 30 40/63
Digester Circulation Pump 4 4 15/32
Digester Feed Macerator 3 2.2 10/32
Digester Building Lighting & Power 1 30/100
Building Power 1 32/63
Control & PLC 1 30/63
Odour Control Panel 1 37.5 40/100
Boiler Heat Pump 1 2.2 15/32
Boiler 1 3 15/32
Boiler Ventilator 2 1.5 15/32
Boiler Fuel pump 1 1.1 15/32
Condensate Pump 2 1.1 15/32
Dorsch International Consultants GmbH 40
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP Technical Specifications
Part 4 Electrical Specifications
2.2.24 MCC5
The contractor shall install the MCC5 in the building for the sand filters and UV disinfection
plants.
MCC5 in Sludge Treatment building
Rated Data Starter
Feeders No. Pn(kW) In(A) Type
Incomer (at the left side) from MLVSB 1 300/630
WAS Tank mixer 2 3 10/32
Ventilator 2 1.5 10/32
Overhead crane 1 5.5 30/63
Mechanical Thickening Control Panel 1 34 210/400 VFD+DOL
Polymer Preparation Unit 1 5 20/32
Building Power 1 30/63
Control & PLC 1 10/32
Mechanical Sludge Dewatering Control Panel 1 44 290/400
Ventilator 2 1.5 10/32
Overhead crane 1 5.5 30/63
Polymer Preparation Unit 1 5 20/32
Return Liquor Pump 3 15 25/63
SPARE 2 50/100
The “SS” starter is a static (thyristor controlled) Soft Starter with integrated Motor Protection
and with
Short Circuit SS Protection by special very fast fuses
Integrated monitoring and password protected manual control at the switchgear front
Interface to the PLC point-to-point or data-bus for monitoring, control and
parameterisation.
The soft starter shall have the features:
adjustable for the particular motor rating current.
adjustable current limitation.
Filters according to the EMC regulations Directive 2004/108/EC or equivalent
national regulations.
Voltage fault monitoring and tripping.
separately adjustable start and stop ramp using two time parameter.
temperature sensor with signalisation using two limits: alarm and tripping.
terminal for the EPB circuits for immediate stopping.
The “SSB” starter is a SS with contactor bypass for minimising temperature and losses of
the SS. The contactor shall be dimensioned minimum for the rated motor current, automatic
controlled by the SS electronic and direct by EPB circuits.
The “VSD(VFD)” starter is a starter for variable speed control by frequency converting
(F.C.) with integrated Motor Protection and with;
Short Circuit F.C. Protection by special very fast fuses.
Integrated monitoring and password protected manual control at the switchgear
front.
Interface to the PLC with point-to-point or data-bus for monitoring, control and
parameterisation.
The F.C. shall have the features:
adjustable for the particular motor rating current.
adjustable current limitation.
filters according to the EMC regulations Directive 2004/108/EC or equivalent
national regulations.
cable filters for long outgoing cables, if required.
voltage fault monitoring and tripping.
separately adjustable start and stop ramp with two time parameter.
possibility of adjusting the speed regulation by several regulating parameters.
temperature sensor with signalisation with two limits: alarm and tripping.
internal automatic controlled cooling system, if required.
terminal for the EPB circuits for immediate stopping.
2.2.34 LCPs, EMP and Maintenance Switches for the Grit Classifiers
A standard LPC with EPB shall be provided for the Grit Classifiers at the concrete of the grit
chamber wall, where there is a good overview upon the Classifier. Another EPB shall be
provided down at the drive. The maintenance switch shall be installed near the drive too.
2.2.38 LCPs, EMP and Maintenance Switches for the RAS and WAS pumping
stations
The RAS and WAS pumps do not need LCPs because all manual control shall be installed
on the front of the adjacent MCC. EPBs and Maintenance Switches shall be installed
adjacent the particular pump.
The EPBs shall be installed considering safety and ergonomic aspects, the Maintenance
Switches can be arranged together with or as alternative to the terminal box for the power
cable. One additional EPB for all pumps shall be installed at the top of stair to the pumps
room.
2.2.39 LCPs, EMP and Maintenance Switches for the Sludge Thickeners
A standard LPC with EPB and a Maintenance Switch shall be provided for the thickener
drive. The maintenance switch shall be installed near the drive.
2.2.40 LCPs, EMP and Maintenance Switches for the Drainage Pumping
Stations
The switches and pushbuttons of the two pumps according to the standard LCP shall be
combined to one common LCP together with one common EPB.
The Maintenance Switches shall be installed as alternative to the terminal box for the power
cables of each drive.
2.3 Automation
The automatic control and the management of the manual control of each electromechanical
equipment of the plant shall be implemented in the associated PLC. The automation
programs shall be generally as described here and shall include any further relevant
operational item described and included by the supplier. The RTU tasks of the PLCs and
data acquisition for SCADA are not described in this section.
The contractor shall submit a detailed program description and a PLC program flow chart for
the Engineers approval.
The contractor shall submit a complete I/O list for approval which shall include the SCADA
requirements.
and the other for the night with a shorter operation and longer pause time. The clock time
from day to night and night to day is part of the operational parameters.
If the selection switch is set to the MANUAL position, the screen shall be enabled to be
turned ON and OFF and also be pulsed in the reverse direction for a short time, this shall be
provided to enable the operator to easily free the screen from a blockage.
The conveyor shall start automatically after the starting of either one of the screens and
stops after a delay when the last of the two screens stops.
The general EPB at the general LCP shall stop all four screens and the two conveyors.
The compactor starts automatically after the starting of the conveyor and it stops after a
delay when the last of the two conveyors stops.
Automatic programs shall be stopped by switching to MANUAL at the LCP or by EPB which
shall not be possible at the switchgear and at SCADA. The operation of the main night/day
clock shall not be suspended.
The Grit Classifier shall start automatically after the starting of one of the two grit pumps. It
shall stop after a delay when the last of the two pumps stops. The two signals of the starting
of the pumps should be transmitted by wire from the Bridge Switchgear to the MCC1 PLC.
The automatic programs will be stopped by switching to MANUAL at the Classifier LCP
which shall not be possible at the switchgear and at SCADA or by the Classifier EPBs. The
two EPBs for the Grit Classifier shall be installed at the LCP and at the foot of the classifier
near the drive.
The position of the hydrostatic valves with modulating actuators at the sludge outflow of each
FST shall be automatically controlled by the separate sludge flow meters. The manual
control of the valve position shall be possible locally at the LCP and at SCADA.
2.4.2 Innovation
It is recognised that manufacturers will continue to develop new products, and improve
existing products, as part of the commercial and design processes. It is not the intention of
this specification to stifle improvement and innovation and new products incorporating
innovative features that enhance process performance and/or reduce whole life costs will be
considered. The generators shall be able to be practiced 8000 hours of operation within a 2-
year period without essential changes.
Dorsch International Consultants GmbH 51
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP Technical Specifications
Part 4 Electrical Specifications
2.4.4 Configurations
The diesel engine, generator, lubricating oil filters, fuel oil filter, lubrication oil strainers, fuel
oil strainers; lubrication oil coolers and other accessories deemed necessary by the
manufacturer shall be mounted on a common steel fabricated base. The common steel base
shall be sufficient strength to adequately support all equipment mounted on the base without
distortion either during operation or during shipment. If deemed necessary by the
manufacturer, the steel base shall be supported on steel spring vibration isolators or
sufficient size specifically designed for the weights and harmonics involved.
The isolators shall be furnished as part of the equipment. All spring connection from the
engine or accessories mounted on the steel base, such as air intake and exhaust, shall be
made by use of flexible connections. These flexible connectors shall be furnished as part of
the equipment.
All gauges shall be mounted in easily readable locations.
2.4.7 Generator
The alternator shall be a self-exciting, self-regulating brushless type to a degree of protection
not less than IP23, utilising CACA air cooling.
The excitation system shall be controlled by a semiconductor based automatic voltage
regulator (AVR) system and shall be self-exciting under all conditions, and capable of
producing at least twice full load machine current under short circuit conditions. The
machine’s output voltage shall remain stable when operating with all types of nonlinear
loads, such as large ac inverter variable speed drives.
The alternator and excitation equipment shall be of the quick response type suitable for the
starting of the largest load (ASTs).
The machine shall be constructed in accordance with BS 4999: Part 101, rated for type S8
duty, with loading requirements as detailed for each application.
Radio interference shall be suppressed to meet the requirements of BS 800.
The generator shall provide a 1100KVA, 400V, 3ph, 50Hz, 4-wire electrical output with power
factor of 0.8 lagging and the voltage shall be maintained within ± 2.5% at all load conditions
between no load and full load. When the generator operates at its full load, this ± 2.5%
tolerance shall apply with a power factor anyway between unity and 0.8 lagging.
The generator shall be air cooled and the output voltage, measured at its terminal box, shall
not be less than 87% of design output under any transient condition, in the specified ambient
conditions.
The generator must be capable of running at 110% full load for 1 hour in every 12 hours at
maximum ambient temperature.
The generator output frequency shall not be less than 45Hz under any condition.
The alternator terminal box shall be suitable for the termination of XLPE insulated armoured
cables.
To enable access to the highest parts of the engine for inspection and maintenance functions
a suitable access platform(s) and access ladder(s) shall be provided as fully integrated parts
of the generator set.
2.4.20 Spillages
Arrangements shall be provided to enable the collection of fuel and lubrication surpluses in
the form of a drip tray(s) or other discrete collection elements. Where such surpluses are
collected the collection point shall be in a position to enable the contents to be removed
easily by the operator.
Any interconnecting fuel or oil pipework which cannot be incorporated into the collection
elements shall be installed within a larger diameter pipe which shall only drain to a collection
element in the event of a spillage from the pipe.
2.4.21 Colour
The whole of the power unit comprising the engine, generator and bedplate is to be painted
the same colour. If no colour is specified for the application, the Supplier shall state in the
tender the standard colour normally supplied. The colour shall be approved in writing by the
Engineer.
A dump tank shall be provided complete with all associated pipe work to receive surplus fuel
from the engine injection system. The drain pipe work from the dump tank shall be piped to a
point common with the drains from the day tank.
A fire valve of the dead weight type in the supply line to the engine shall be provided to
operate by fusible links above the engine, and shall be complete with an interconnecting wire
and pulley system.
A ladder and platform access arrangement shall be provided to enable access to all parts of
the day tank and engine fuel supply system.
The day tank shall be fitted with a mechanically operated contents gauge mounted so as to
be easily read by the operator standing at floor level.
The day tank shall be fitted with a level measuring system to enable automatic operation of
the electric fuel transfer pump and the monitoring of the tank contents.
The fuel supply line from the day tank to the engine shall be fitted with a mechanical fuel
meter calibrated in litres. This flow meter shall be fitted with an electronic sender unit such
that the signal can be transmitted to the generator control panel.
All instrumentation shall be mounted such that the instrument information can be read by the
operator standing at floor level.
2.4.25 Earthing
The generator sets shall be connected to the earthing arrangements at the generator
building.
The Supplier shall be responsible for confirming the suitability of this earth for the connection
of the new generator set and for making recommendations for any necessary modifications.
The following components, as a minimum, shall be mounted on the front of the control panel:
Charger isolator OFF/ON switch to simultaneously isolate the battery charger from
the 240V supply, and isolate the battery charger from the battery,
Engine heater OFF/ON switch.
Fuel oil transfer pump Man / Automatic
Air blast cooler fan(s) Man / Automatic
Switch for engine control
Pushbuttons:
Battery charger boost
Manual start
Manual stop
Emergency stop
Alarm reset
Lamp test
Fuel oil transfer pump start
Fuel oil transfer pump stop
Air blast cooler fan start (for each fan)
Air blast cooler fan stop (for each fan)
Indicators-Back lighted enunciators
Mains failed Red
Generator failed Red
Engine heater on Yellow
Engine control on Blue
Boost charge in progress Red
Low air start pressure Red
Engine failed to start Red
Over speed shutdown Red
Earth leakage shutdown Red
Generator over current shutdown Red
High water temperature shutdown Red
Low lub oil pressure shutdown Red
High lub oil temperature shutdown Red
High charge air temperature Red
Low fuel level day tank Red
Each earth bar shall be connected to the earth conductor installation by two separate cable
connections, one from each end of the earth bar.
The earth bars shall be positioned inside buildings in the rooms with switchgears and in
rooms with metallic equipment. Maximum one busbar for one room shall be provided.
Concerning the outside bus bars each machinery or plant or group of engines shall be
equipped with one bus bar.
The bus bars shall be protected with suitable cover of rigid plastic.
The exact location of the earth bars will be advised during installation.
2.6.2 Innovation
It is recognised that manufacturers will continue to develop new products, and improve
existing products, as part of the commercial and design processes. It is not the intention of
this specification to stifle improvement and innovation and new products incorporating
innovative features that enhance process performance and/or reduce whole life costs will be
considered.
2.6.3 General
A computer based Supervisory Control and Data Acquisition System (SCADA) shall be
provided for monitoring and controlling the operation of the WWTP.
The SCADA system shall be located in the WWTP control room in the new administration
building.
The SCADA system shall be configured as a distributed system with programmable Logic
Controllers (PLC’s) as RTU installed in each MCC carrying out all control and monitoring of
the plant and equipment connected to the MCC. Each PLC shall work autonomously allowing
control to continue in the event of a communication network failure.
The system shall be designed to operate 24 hours a day without any necessity of attendance
from the personnel.
2.6.7 Hardware
The server and operator workstations shall be of the Personal Computer type, of a reputable
make and in the firm's professional series to the approval of the Engineer.
As a minimum the computer shall fulfil with the following requirements:
The Contractor shall design, supply, install and commission the SCADA centre with the
components:
Double (redundant) router system for the connection of the SCADA centre to the local
components.
DSL modem for connection to internet
2x 1Gb Ethernet interface for fibre cable
2 workstations (high quality standard PC).
1 programmer workstation (high quality standard notebook).
1 Alarm/Event printer
1 colour ink jet printer (A3) and 1 laser printer (A4) or better
Two (redundant) data recorder (may be incorporated in the workstations).
interfaces for exchange of information with GIS, MIS and accounting computers
Network (Ethernet LAN) for the interconnection of SCADA centre components
Acoustic alarm and alarm reset push button
Strip chart recorder for the five most important measured values (as redundancy)
The operating system software for the server PCs shall be newest Microsoft Windows
version for Advanced Server and for the workstation PCs should be newest Windows
Professional version..
The PCs shall have installed newest Microsoft Office Professional version.
The PCs shall have an updated virus protection system. The virus protection system shall be
with subscription in order to keep the system updated all the times.
All the Programs and Software shall be delivered with its original CD and its license.
• Store and handle the real-time data including performing arithmetic and logical
functions
• Undertake monitoring, alarm and fault handling
• Undertake self-diagnosis of the computer
The programming system shall collect, handle and store data while all other activities are on-
going.
A number of screen graphics to display the process shall be prepared. Each graphic shall
provide the facility, via overlay graphics, to select a number of detailed graphics which shall
include the composition and data of the parts of the process being viewed.
The following requirements are required for all mimics(graphics):
The background colour for all mimics(graphics) shall be subject to the approval of the
Engineer.
All flows shall be displayed in engineering units as specified in the I/O listing of the
agreed Functional Design Specification.
Each mimic(graphic) shall have navigation 'pushbutton' to the process overview, the
geographical overview and associated process mimics(graphics) .
The symbols used to describe the plant items shall be subject to the approval of the
Consultant.
Mimics(graphics) shall display process lines as colour dynamic with arrow indication
of flow direction.
Alarms indication shall be animated within the relevant mimic(graphic).
Trend pages (including historic and current information) and the alarm summary page
shall be available from every mimic(graphic).
The Contractor shall configure each on-site workstation such that a screen dump can
be printed by a single keyboard/on-screen action.
Control pages for all plant that can be controlled, overridden or plant data entered
manually shall be available from every mimic(graphic).
Operation of the system shall be based on an extensively use of the mouse to promote fast
and easy selections.
The operation shall be interactive and it shall be possible to display messages with
information that is helpful for the operator.
The internal clock shall be supplied with battery back-up or it shall automatically be adjusted.
2.6.12 Configuration
The SCADA software program shall allow the operator to extent and change the control and
monitoring, the reporting and the process configuration. The program shall be the interactive
type with explanatory messages to the operator.
The configuration shall be carried out via a well-documented standard program specifically
designed for configuration of the system (not via programming in a standard high level
programming language).
Changing or extension of the configuration shall include removing and/or adding of
components (motors, valves, instruments etc.), and it shall include all disciplines such as
addresses, conditions, alarms, reports, monitoring etc. Access shall be limited via password.
The program for configuration shall include a check program that will detect and disclose all
errors and allow only fault free configurations to be operational.
The contractor shall design following interactive pictures for the workstations.
The program to be installed at the routers and all workstations shall manage all acquired
data and shall enable the operator to monitor and control (supervisory control) the WWTP
and shall manage the automatic data storage and alarm printer output. The program shall be
a high quality standard program for waste water treatment plants.
All static structures (including buildings and mechanical objects) shall be represented in
brown outlines of varying thicknesses.
Process Colours
All process pipelines and associated text displays will follow these colour codes:
Raw Sewage Blue
Settled Sewage Green
Primary Sludge Dark Brown
Waste Activated Sludge Light Brown
Water Light Blue
Grit and Scum Red
All Plant items (MCCB, Motors, actuated weirs, etc.) shall follow these colour codes:
On, Running, Open Plant symbol is shown in Yellow
Off, Stopped, Closed Plant symbol is shown in Green
Failed & Unacknowledged Plant symbol is shown in Flashing Red
Failed & Acknowledged Plant symbol is shown in Steady Red
Under Maintenance / Isolated Plant symbol is shown in Yellow inside a
white outline Box'
Auto Selected Word AUTO Word ‘AUTO’
appears appears
on the right ofon
thethe right (for all Motors)
plant symbol
Manual Selected Word MANUAL Word ‘AUTO’onappears
appears the rightonofthe
theright (for all Motors)
plant symbol
Position Word ‘AUTO’
A numerical display appears the
field alongside on the right (for all Motors)
plant
symbol shall display the actual position in
the relevant units
2.6.17 Alarms
Alarm Generation
All alarms shall be generated in the respective PLC's and transferred to the SCADA system
as a discrete bit. Alarms shall be generated in the PLC as described below:
Discrete Digital Input - Generated by a field device i.e. pressure, level, temperature
switch and designated an alarm condition within the PLC.
Analogue Derived - An alarm derived within the PLC by configuring a point or points
from an analogue input
PLC Derived - An alarm derived from 2 or more discrete or derived signals
Alarm Display
All graphics shall have a three line banner at the bottom of the page which will display the
last three active alarms in descending order. The alarm banner shall be updated as new
alarms are generated, with the latest active alarm always being displayed on the top line.
The alarm summary page shall be accessed from any graphic via a function key or by
clicking on the screen poke point. The alarm summary page shall display all current alarms
and all cleared un-acknowledged alarms. The most recent alarm shall be shown at the top of
the display with date and time stamp.
An alarm condition shall be indicated on graphics by highlighting the equipment identification
label with a flashing border.
Alarm Processing
In the event of an alarm:
The relevant alarm message shall be inserted on the top line of both the graphic alarm
banner and the alarm summary page, an active alarm being indicated by a red square on the
left hand side of the alarm line.
The graphic symbol ID shall indicate an alarm.
An audible alarm shall be sounded.
An alarm message will be printed out on the dedicated alarm printer.
The alarm shall be muted via the dedicated function key.
The alarm shall be acknowledged at the alarm summary page, access to this page being
gained via the dedicated function key from any screen.
The alarm indicator square on the banner and the summary page shall change colour from
red to blue when the alarm is acknowledged.
The acknowledged message is printed out.
When the alarm is returned to normal, i.e. the fault is cleared, the alarm message shall be
removed from the alarm banner and the summary page, the mimic(graphic)(graphic)
indicator shall clear and an alarm clear message shall be printed out.
If an alarm clears before it is acknowledged the alarm active condition shall be indicated on
the alarm banner and the summary page with a green square until it is acknowledged. When
acknowledged the alarm message shall be removed from the alarm banner and the summary
page.
It shall be possible to carry out changes to RTU/PLC programs and changes to program
parameters from the operator station in the SCADA centre under the password protected
access arrangements.
Changing of parameters shall be easy and by using interactive messages.
The license shall be valid for all RTUs and the SCADA workstations and laptop.
The system shall include two SCADA server and three SCADA client software licenses. The
system shall include an A3 colour printer Ink Jet or laser and a laser A4 printer. The
complete SCADA hardware and the two printers shall to be connected together with one high
speed LAN.
2.6.22 Visualization
The clients shall be able to view all of the WWTP parameters, status and commands. The
client shall include a hierarchy of security levels. All visualization screens shall be designed
in accordance to standard ISA symbols.
2.6.24 Reporting
Daily, weekly and monthly reports shall be printed automatically on the report printer. The
operator shall be able to select any historical period and request a report to be printed. All
trends shall be printed on the colour printer. The contractor is advised that a major
requirement of the SCADA system is the ability to produce maintenance reports and facility
performance monitoring reports. The contractor shall submit his proposal to the Engineer for
approval while noting that the contractor is obliged to deliver the reports required by the
Engineer.
2.6.25 Equipment
One portable PC (laptop) shall be provided for easily programming in the site and shall be
latest version and international brand name type to be approved by the Engineer.
The SCADA system shall be equipped with all suitable furniture (desks) for use and
operation, separate stations shall be provided for each system.
The turnkey construction of the PV Plant and its Operation Services, shall briefly include:
EPC
Complete PV System and Project Design and Construction. All work shall be in
accordance with the relevant local and international standards
Mobilization
Hydrogeological works
Supply of all the components to be installed in the PV plant premises.
Civil & Infrastructure Design & Construction
Mechanical Design & installations
Electrical Design & installations
Supply and installation of the Monitoring and SCADA systems
Supply and installation of the Security and CCTV systems
Testing, Commissioning, Operation Service the PV System and Project as specified and
for the defined period as described herein in this contract.
De-mobilization after completion of the Works as per the contract
.
OPERATION & MAINTENANCE SERVICES
The scope of work of the Operation Services will be the proper functioning of the system as a
whole during the Defect Notification Period, by ensuring:
The preventive maintenance activities to be carried out in accordance with the Operation
& Maintenance plan;
The corrective maintenance including all the necessary components and labour to repair
or replace any defective parts, and in general to ensure the correct operation of the PV
Plant according to the reaction plan;
The supply of all the components necessary for the proper maintenance of the PV plant;
The supervision and control of the system through remote monitoring and the reporting
activity;
The landscaping maintenance;
The cleaning of the PV modules, at least 18 times per year;
The assistance to the Employer in relation to any possible insurance and warranty
claims.
IMPORTANT. The Contractor shall be responsible for the complete design, supply and
installation of the MV equipment (transformer station, MV cables) to be compliant with the
Jordanian Electric Power Company (JEPCO). No deviations from the requirements of the
Grid Operator will be accepted. In case the requirements of the Grid Operator shall differ
from the technical specification as defined in this section, the Grid Operator’s instructions
shall prevail. The Contractor shall prepare the documents, submit them to the Grid Operator
and obtain their validation in order to avoid any problem or delay to the commissioning.
3.5 PV Modules
General Requirements
It is required to select a module manufacturer between the recognised Tier 1 suppliers for, at
least, 5 consecutive years. without any restrictions on where the PV modules are
manufactured. In terms of quality and warranty, the selected PV modules must fulfil the
requirements, as described in the subsequent sections of this document. Furthermore, prior
to or during the process of a module manufacturer selection, a comprehensive technical due
diligence to assess the manufacturing practice and quality systems of the manufacturers
under consideration has to be provided.
Full details of the PV modules shall be submitted to confirm compliance with the
Specifications for approval by the Engineer.
The objective is to evaluate the ability of such manufacturers to produce PV modules of the
same quality to those that have been submitted and passed certification and compliance
tests. The Contractor will provide an attestation by an independent third party that such an
assessment is or was performed, at a maximum of 12 months prior to the prospective
delivery date of the modules.
The PV plant supply or purchase agreements (e.g. contract documents) shall contain
detailed technical specifications and agreed warranty terms and conditions. The Contractor
will be requested to provide evidence of such specifications and warranties. Upon delivery of
the modules to Site, the Contractor shall submit the flash data for each PV module at STC
(flash reports) in electronic format (Excel files). The Contractor shall provide a summary
spreadsheet, containing the summary of all the spreadsheets and the full installed capacity.
Modules are expected to be packed vertically to avoid micro-crack damage, during
transportation.
The active electrical components within each PV module shall be electrically insulated
from the frame, the rear cover, and the front glass surface. The insulation must
withstand 1000 Volts DC between the short-circuited module output leads, the metal
frame and the rear and front covers.
Mechanical resistance: PV modules must be certified for resistance to a suction
pressure of 2400 Pa (Wind speed 140 km/h with safety factor 3) and an increased
distributed mechanical load of 5400 Pa on the front glass surface (wind and snow).
Junction box: shall include 3 by-pass diodes to protect against partial shading and
module overheating. IP67 protection required.
Cables: factory fitted module cables shall be long enough to allow the modules to be
interconnected electrically in series, to form strings and shall indicate clearly the
polarity. Connectors certified BS EN 62852:2015. compatible with MC4.
Encapsulation: EVA-Solar Cells-EVA. Back material: Tedlar-Polyester-Tedlar, white
colour.
Glass: front surface of the modules shall be protected with at least a 3.2 mm tempered
glass of low iron content and may have a manufacturer-applied anti-reflective coating.
The glass cover shall have strong resistance to heavy shocks, thermal stress and high
wind loads including wind with high content of particulates.
Frame: the PV laminate (glass / encapsulant / solar cells / rear side) shall be
surrounded with a metal frame made of aluminium or aluminium alloy. The frame shall
be placed to protect the edges of the glass cover of the PV modules and to facilitate
support and mounting. The construction of the frame of each PV module shall be
adequate to allow for thermal contractions and expansions of the glass cover of the PV
module. To avoid galvanic corrosion due to electrolytic action between different
materials, any contact between different metals in the PV module frame, must be fully
electrically isolated.
Dimensions: approximately 100x160 cm for the 60 cells modules and approximately
200x100 cm for the 72 cells modules
Certifications: PV module components are only considered to be approved when they
are used to fabricate the modules that were submitted to and passed various standard
certification and compliance tests such as IEC. Therefore, as the manufacturer goes
through the process of qualifying new suppliers, the test certificates must continuously
be updated to include additional component providers. Therefore, as part of the module
agreement, the Contractor shall include a requirement that the PV modules intended
for the PV projects under consideration shall be made with only approved module
components.
Nameplate: each module shall permanently display a technical characteristics
nameplate carrying the following information as a minimum:
- Name of manufacturer (or monogram or symbol)
- Type or model number
- Serial number
- Polarity of terminals or leads
- Max system voltage which module is suitable for
- Safety class
- Application class
Dorsch International Consultants GmbH 76
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP Technical Specifications
Part 4 Electrical Specifications
3.10 Inverters
3.10.1 Determination of the inverter
The Contractor shall select and supply the photovoltaic inverters required to realize the PV
plants considering the PV installation design and functional requirements and including the
integration requirements into the PV system and the compatibility to the selected PV
modules for the installations.
The Contractor shall submit full details of the inverters to demonstrate compliance with the
Specifications mentioned in the following section, for approval by the Engineer.
There are no restrictions where the PV inverters are manufactured; however, it shall be
noted that the inverter specifications shall comply with all the requirements of the grid
operator, including the capability to produce the reactive power that the grid operator could
require.
Inverters shall be three-phase decentralised.
The string configuration defined for the Works needs to be verified with the specific software
provided by the inverter manufacturer.
Technical specifications of inverters
The minimum technical parameters for the inverters are:
One (or more) MPP tracker;
A system to allow performance control;
Maximum efficiency at least 98,6%;
Remote monitoring and control capabilities (PC connection…);
Isolation fault detection;
Ability to start and stop function automatically;
The ratio of the input power over the output power has to be between 90% and 100%
and, in any case such to deliver the needed reactive power;
The MPP voltages of the strings are to be verified to lie in the MPP voltage range of the
inverter for temperatures between -10°C and 70°C.
IP protection class of at least 54 is required for outdoor inverters. Noting the possible
presence of dust in the selected areas, a boxed installation is recommended even for
outdoor inverters.
Even when the technical characteristics of the inverter clearly contemplate an outdoor
installation, a protection is to be designed in any case against direct sunlight and rain
(e.g. sunshield, beneath the arrays, etc.);
The inverter requires a DC switch.
Inverters have to be protected from overload and short-circuit internally and shall be
equipped with disconnection devices following the local requirements.
In some cases, special requirements for inverters (grounding, with or without transformer
etc.) are requested by the PV module manufacturers. If such a case occurs, the Contractor
shall be responsible to include these requirements in the design and carry out such
measures at his own cost. Inverters shall comply with international standards and safety
regulations or any other local requirement. Inverters can sustain a given temperature range
defined in the related datasheet; this range shall be respected by the Contractor. If the
inverters are positioned inside a shelter, it implies designing an adequate ventilation system.
A thermal study shall be carried out to verify the inverters temperature specifications will be
respected. The inverters’ shelters shall be waterproof. The compatibility with the transformer
size is to be safeguarded.
3.14 Cables
3.14.1 General
All cabling shall be installed in accordance with its manufacturer’s requirements and to meet
the design conditions used in the sizing calculations. The combined cable losses shall not
exceed 3% (DC and AC cable losses combined). A shop drawing will be prepared to define
in detail the arrangement of the cables in the trenches, the AC/DC boxes and the inverters.
3.14.2 DC cables
The cables of the PV installation shall have the following characteristics:
Solar cables shall be in copper with a minimum cross section of 6mm².
Cables used outside shall be UV resistant (according to HD 605/A1) and ozone
protected
Class II rating for insulation
Rated for temperatures from -40°C to +90°C. This requirement is also applicable to all
materials used in the installation of PV (such as cable conduits).
Made of double insulated component and shall have a minimal life span of 25 years.
Cable bending radius shall be at minimum four times the cable diameter or as specified
by manufacturer, if different.
Sized to allow a current up to 1.25 Isc and up to 1.2 Voc typically observed for
crystalline-silicon modules
Installed in conduits and hooded cable trays. The cable return path shall follow the
same way to avoid induction loops.
Cables shall be dimensioned according to CEI 20-40 and CEI 20-67. Norm CEI 64-8 shall be
followed to prevent short-circuit-induced current. Norm CEI 82-25 shall be followed regarding
arrangement of cables and cables trays. In terms of certifications, DC cables shall be
compliant with the requirements described in 2Pfg 1169/08.07 (“Requirements for cables for
use in photovoltaic-systems”). Combined DC cable losses shall be less than 1% at 80% Isc.
3.14.4 AC cables
All AC cables shall be suitable for direct buried or ducted installation. In case of direct buried
installation, the Contractor shall install armoured cables and add one spare conduit from
each AC box to the transformer.
The LV cables shall be compliant to the following standards:
General Services: Steel Wire Armoured (SWA) on tray or ladder, NYM-J within steel
conduit/trunking.
CT/VT secondary and control cables: NYCY
Cables between generators and external unit substations: NYY-O (double insulated
and suitable for outdoor use), minimum Voltage rating 1000V and suitable for the
generating Voltage.
LV cables shall be terminated using proprietary crimped lugs
The MV cables shall be XLPE or EPR insulated with aluminium or copper stranded wire
conductors and PE or PVC outer sheath. The cable construction shall be according to
IEC60502 and shall employ longitudinal water blocking. All joints and terminations shall be
completed and tested in accordance with the manufacturer’s recommendations. MV cables
shall have a cross section of at least 150 mm2.
The combined AC (both LV as MV) power losses shall be below 2%. The MV cables shall
comply with the requirements of the Grid Operator.
3.16 Transformers
Refer to Section 1.81.8 “Current Transformers” and Section 2.2.18 “Automatic
Synchronization Panel”.
Fault finding.
Safety features of the power plant.
Safe operation of power plant.
Protection equipment.
Theory and practice of electrical power system.
Operational activity that is permissible by the Employer’s personnel, during the
warranty period.
Safe methods of isolation of equipment for maintenance.
Description of the electrical system including details of MV, LV and data cable
routes.
Location of plant and equipment including points of isolation and earthing.
Identification of protection relays and equipment.
Review of protection relay settings.
Description of interface with any existing substation equipment and with the utility
grid.
Safe operation, safe access, maintenance of nominal and safe performance
where special procedures are required which would not be familiar to
experienced, qualified/registered personnel.
The Contractor shall provide comprehensive course notes and shall include ‘hands-on’
practical sessions on the Works. Operating and technical manuals, including drawings shall
also be provided to accompany the training. Training manuals shall be provided to all
delegates attending training courses. The manuals shall be developed specifically for the
Works and shall be specific to the level of training provided to the course delegate. The
training manuals shall be developed in sections, reflecting the course structure and shall be
developed in a manner that will provide the delegate with a quick reference guide to the
various aspects of the system following the course. The Contractor shall provide written
certification for personnel who complete the course to the required standard.
3.19.1 PV Modules
The PV module manufacturers at the present day, generally, offer two types of standard
warranties: product and power warranty.
Product warranty shall warrant that the modules are free from defects in materials or
workmanship. The definition of defects in materials or workmanships shall be clearly defined.
The compensation for defective products shall be clearly defined (replacement, repair or
financial compensations). The warranty shall also include the factory-assembled DC
connector and cables. A warranty period of at least 12 years is required. A longer warranty
period is preferred.
Power warranties guarantee certain percentage of initial power output during certain period
of time. The definition of a reference output power must be clearly defined. The
measurement shall be conducted under Standard Test Conditions (25°C, 1000W sqm). A
power output warranty, being at least 90% after 12 years and 80% after 25 years with a
linear/yearly degradation. The warranties shall start from the certified date of Contractual
Handover.
The involvement of an independent test party such as Fraunhofer ISE (Freiburg, Germany),
TUV Rheinland (Cologne, Germany), or other international institution in case of technical
disputes during the warranty claim is required. The warranties offered by the module
manufacturers shall be in the name of the Employer. Other terms and conditions for
warranties transferability must be defined clearly. The contract sales agreement with the
module manufacturer is expected to define clearly the claiming procedure of defect modules,
the required additional specific independent party involvement and any other conditions that
might influence the honouring of the warranties. Finally, the conditions which void the
warranties shall be clearly stated (e.g. mishandling of modules, etc.) for approval by the
Engineer.
3.19.2 Inverters
Inverters shall have at least a 5 years standard warranty. The contract sales agreement with
the inverter manufacturer shall clearly define the claiming procedure of defected inverters or
parts, the required additional specific independent party involvement and any other
conditions that might influence the honouring of the warranties. Any extension and the full
scope of that extension to the standard limited warranty - included in the price - shall be
indicated. The Contractor must provide proof that the inverter manufacturers have sufficient
financial backup that covers manufacturers in case of bankruptcy or that are filing for Chapter
11 protection. Finally, the conditions which void the warranties shall be clearly stated (e.g.
mishandling of inverters, installation in extreme salt conditions etc.) for the Engineer.
source must be able to provide an average expected yearly irradiation value and the yearly
climate variation or year to year values. The system has to be simulated using software or a
method that are widely accepted in the photovoltaic industry (e.g. PVSyst, PVSOL).
The Contractor is requested to certificate the estimated production forecast for the first year
and for the 24 following years, taking into account degradation and availability (both) as
guaranteed in the Contract.
The following losses shall be taken into consideration for the Yield simulation:
Far shading loss (horizon line) -0.1%
Soiling losses -4.0%
Near shading losses (obstacles, buildings, trees, etc.) -1.6%
IAM factor on global -1.5%
Irradiance dependencies -0.1%
Quality related losses (related to product variance) +0.5%
Temperature dependencies -7.8%
AC Ohmic loss -0.8%
Mismatching -1.1%
Cabling (DC as well as AC) -1.4%
Inverter losses -1.8%
Transformer losses -0.7%
Additionally, in the Simulation a Cos(Phi) for the Reactive Power of 0.85 shall be considered.
The real value to be applied to the system will be defined by the Grid Operator. The analysis
shall contain also the calculation of the Performance Ratio (PR) of the PV plant. Production
and PR estimated for the first year shall be split by single months.
3.20.1 Degradation
The value of the degradation shall be not more than 0.7% per year.
Production
Performance Ratio
Availability
At any relevant test, possible Performance Shortfalls (SHFPROD, SHFPR, SHFAV) will be
calculated and will be >0 when an Effective Performance for any of the indicators will prove
lower than the related minimum guaranteed value. All performance shortfalls will initially be
expressed in kWh, resulting from the formulas described in the relevant paragraphs of this
chapter.
The value of the Liquidated Damages will be calculated considering only the highest between
SHFPROD, SHFPR, SHFAVL and associating an economic value to each kWh equal to the
Dorsch International Consultants GmbH 86
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP Technical Specifications
Part 4 Electrical Specifications
electricity tariff paid by the Employer at the moment of the test or the cost of generating the
same amount of energy with the diesel generator installed at site, depending which of these
2 sources will actually deliver the missing energy.
3.21.2 Production
Definition
The Production is defined as the total amount of energy delivered to the grid/water facility in
1 year, expressed in kWh, as recorded by the “comparison” MV meter (after the
Transformer).
YF
PR = YR
The value for Yf is calculated by the equation:
YF= E (kWh/kWp)
PN
where: =
YF = final PV System yield
E = System net AC energy output in kWh as measured by the MV meter after the
transformer (if this last is provided by the Contractor)
PN = System nominal power in kWp
and:
H
Yr =
where: = G
Yr = reference yield
H = total in-plane irradiance in kWh/m2 being the average of the solar irradiance as
measured by the pyranometers installed for each PV Plant.
G = reference irradiance (1 kW/m2)
PR guaranteed at Year 1 shall be not more than 1.5% less than the PR defined by the Yield
analysis
At any relevant PR Test, the Guaranteed Performance Ratio (PRguarYn) will be calculated
according to the following formula:
During the Trial Period Tests, the effective PR will be measured during a period of
consecutive 14 days, subject to:
at least 9 out of the 14 days resulting in a daily irradiation level > 3000 Wh/m2
no interruption in the regular system functioning
Shall the above conditions not be satisfied; the period will be extended to the next days
satisfying the conditions until a total of 14 test days will be achieved. The PR at PAC will be
computed as follows:
Yf
PREFFPAC Yr (kWh/m2)/(kW/m2)
= the reference PR of the month when the test has been
The PREFFPAC must be higher than
performed, according to the PVSyst included in the Contractor’s Tender. In case the average
temperature during the test will differ more than 15% from the temperature of the
correspondent month as defined in PVSyst, a temperature coefficient to adjust the
PREFFPAC shall be introduced.
Effective PR at Intermediate 1, Intermediate 2 and Final Performance Tests (PREFFIAC
and PREFFFAC)
The effective PR at the Intermediate and Final Performance tests shall be calculated in a 15-
minute resolution.
The effective PR at the Intermediate and at Final Performance tests is defined as follows:
E
PN
PREFF =
IRRAVG
G
Where:
IRRAVG = the average value of the solar irradiation measured by the pyranometers
installed in each PV Plant during respectively the 1st, 2nd and 3rd year after Take
Over Certificate. If data from different pyranometers differ >3%, then only the
highest value will be considered.
3.21.4 Availability
Definition
An inverter is considered as not available when it shows no production, while irradiance is
higher than 50 W/m² at the same time.
Minimum Guaranteed Availability
The Minimum Guaranteed Availability shall be 99,0%.
Effective Availability
The effective PV Plant availability (AVeff) is calculated as follows:
Where:
AVeff Technical availability of PV plant
Hm: Number of hours with a solar irradiance of >50 W/m²
Pc: Impaired installed power of the affected inverter/s [kWp,DC,STC]
Pt: Total installed power of PV plant [kWp,DC,STC]
Hi: Incident duration in hours when inverter power is equal to 0 kW. Excluding times
when:
such inverter is not operative due to a Force Majeure Event;
grid outages, continuous overvoltage or undervoltage incidents and
permanent or temporary limitation by DNO not attributable to the Contractor
or its Subcontractors or delays in supply of the following missing Component
Parts: Medium Voltage Components and whole inverter or parts leading to
downtime of a whole inverter, on the basis that the Contractor has placed the
order for the required component part;
solar irradiance is below 50 W/m²;
Performance shortfall
Production shortfall (SHFPROD)
Possible performance shortfalls related to Production will be evaluated at the Intermediate
Performance Test 1 and 2 and at the Final Performance Test. The value of the Shortfall is
calculated in kWh according to the formula shown below:
The formulas for the calculation of Liquidated Damages at Intermediate Performance Test 1
and 2 and at Performance Test is:
LD = SHFHI*EP
Where:
SHFHI = the highest SHF (PROD, PR, AV)
EP = Price of Electricity supplied by the local Utility in the reference period and/or price
of the energy produced by the diesel generator installed at site
In case of shortfalls in PR at the Provisional and at the Performance Tests (in this last
case as an additional liquidated damage), the formula below will apply:
At Provisional Performance Test:
LDPR25Y = SHFPR*EPAVG*25/2
At Performance Test:
LDPR22Y = SHFPR*EPAVG*22/2
Where:
EPAVG = Average of the Electricity Price in the remaining years to get 25 years from
Take Over Certificate, calculated with an inflation of 3% (starting from the actual
electricity price)
/2 = Actualization
As an alternative to the payment of these last Liquidated Damages, the Employer and the
Contractor may agree that additional capacity is installed – sized as deemed necessary to
cover the Performance Shortfall – at the expense of the Contractor.
TABLE OF CONTENTS
List of Tables
Table 1: Measure values to be used for units and dimensions............................................... 3
Table 2: Measurement and indication of chemical parameters .............................................. 4
Table 3: Totalizer precision for regulatory purposes .............................................................. 4
Table 4: IP ratings and materials/coatings ............................................................................. 6
Table 5: Minimum time between maintenance....................................................................... 6
Table 6: Turbidity – application and performance requirements............................................18
Table 7: pH measurement and control types ........................................................................19
Table 8: Performance overview on other instruments and devices .......................................20
5.1.1.Innovation
It is recognised that manufacturers will continue to develop new products, and improve
existing products, as part of the commercial and design processes. It is not the intention of
this specification to stifle improvement and innovation and new products incorporating
innovative features that enhance process performance and/or reduce whole life costs will be
considered. However it is also recognised that standardisation on particular instruments or
manufacturer has operational and maintenance advantages. Staff training costs associated
with the introduction of new technology or equipment must be taken into account. The end
user must always be consulted and his/her agreement obtained before a new product is
specified or accepted.
pH pH Units
5.1.3.General
The design, construction, inspection and testing of the equipment and component(s) shall
comply with all relevant Statutory Regulations, and the latest editions (current at the time of
Tender) of all relevant British and Harmonised European Standards, including:
a) The Electrical Equipment (Safety) Regulations 1994;
b) The Electromagnetic Compatibility Regulations 1992/1994;
c) The Low Voltage and Electromagnetic Compatibility Directives;
d) BS EN 50081-1 1992 for emissions - EMC;
e) BS EN 50082-2 1995 for immunity – EMC;
f) BS EN 61010-1 1993 low voltage directive;
g) BS EN 60529 Specification for Degrees of Protection Provided by Enclosures (IP
rating);
h) Equipment shall be CE marked to demonstrate compliance with:
Electrical installation works shall generally comply with BS 7671 and Part 5 General
Electrical Specification.
Mechanical installation works shall generally comply with Part 2 General Mechanical
Specification.
The performance of instrumentation, shall not be affected by:
- Fouling of sensors and sampling systems with biological slimes along with organic
and mineral deposits.
- Ingress of moisture into sensitive electronic circuits
- Sensitivity to electrical interference
- Poor accuracy due to variability of sample or presence of interferents
- Sensors sensitive to variations in sample flow rate, pressure or other measured
parameters
- Long response times due either to the instrument or its installation
- Changing environmental factors
- Unrepresentative sample due to change occurring in the sampling system or
unsatisfactory sample point location
- Instruments shall be protected against unauthorised operations of all controls
- Instruments shall have readily available supplies of spares and consumables
including reagents and standard solution
- Instruments and their measuring capability shall be unaffected by changes in
ambient temperature or pressure.
f) All cable glands used shall have the same IP rating as the enclosure or greater and
any unused cable entry holes shall be sealed or be fitted with suitable blanking plugs to
maintain the IP rating.
g) Enclosures shall only be affixed to structures and supports by means of any integral
mounting facilities or special brackets provided by the manufacturer for the purpose.
Additional holes shall NOT be drilled in the enclosure.
5.1.5.Performance
a) ‘Warm up time’ or performance following a power failure shall not unduly affect the
operation of the instrument and its associated plant.
b) The instrument shall operate within the performance specification for periods detailed
below without manual calibration or scheduled maintenance.
c) Minimum Time Between Maintenance shall be as specified in the below table.
Conductivity 6 months
Turbidity, dissolved oxygen, pH Nitrate and 30 days
suspended solids Phosphate, Iron, ammonia
Other analytical instruments 7 days
All other instruments 6 months
d) Routine maintenance and re-calibration shall not require the instrument to be off-line
more than 1 hour with the exception of flowmeters.
e) The instrument shall be designed for a minimum operating life of ten years providing it
has been maintained and operated according to the manufacturer’s instructions.
f) Instrumentation shall be in accordance with the relevant British Standard
Specifications.
5.1.6.Identification
g) Every instrument shall be clearly identified as to it’s purpose and function by means of
durable, permanently engraved label securely fixed on or immediately adjacent to the
instrument.
h) Where an instrument is contained within another enclosure the presence of the
instrument within that enclosure shall also be indicated by means of durable,
permanently engraved label securely fixed on or immediately adjacent to the enclosure.
i) Sample pumps shall be clearly identified. The label should also indicate the instrument
or meter with which it is associated.
Insulating gaskets shall be fitted between both meter flanges and the pipe flanges and all
flange connecting bolts shall be fitted with insulating sleeves and washers.
An insulated, adequately rated, bonding cable shall be connected between the outermost
pipeline flanges to maintain the electrical continuity of the pipeline. The bonding cable
connections and terminals shall be adequately protected against corrosion.
The body of the meter must be earthed in compliance with BS 7671.
Upon completion of the meter installation any existing Cathodic Protection system must be
tested to ascertain that it is functioning correctly. Ref BS 7367
Location underground
All below-ground meters shall be installed in a water tight chamber.
Where meters are installed in pipelines and within underground chambers or directly buried
in ground the precise location of the meter shall be indicated by means of marker posts and
indicator plates.
Environment & Accessibility
Where meters are installed in chambers or buried directly in ground remote mounted
transmitters shall be provided and which shall be mounted in readily accessible positions
without the need to enter confined spaces and the like.
All pipeline mounted electrical equipment enclosures including sensors, integral transmitters
and the like shall be IP68 suitable for continuous submergence to 10 metres head of water in
accordance with BS EN 60529.
Where meters are installed in readily accessible positions and without the need to enter
confined spaces and the like, transmitter units may be integral with the sensor.
Outputs
The transmitter shall provide, as a minimum, a 4-20mA dc analogue output scaled directly
proportional to flow, programmable pulsed outputs for forward and reverse flows and an
alarm contact to indicate a fault/failure condition.
Accuracy
The accuracy of the proposed flow meters and the flow range to which these accuracy
figures relate shall be provided by the Contractor to the Engineer for information and
acceptance.
Cabling & Termination
Where remote mounting transmitters are to be used the interconnecting cable is typically a
special type specified and supplied by the meter manufacturer and must be ordered to the
correct length. Where the sensor/transmitter combination is matched to the length of cable
supplied the length of cable shall not be reduced or extended under any circumstances, any
excess must be coiled neatly and properly secured at one or both ends. Intermediate joints in
the cable are not permitted.
Termination of the cable shall be carried out strictly in accordance with the meter
manufacturers’ instructions and recommendations.
Where the interconnecting cable is to be buried in ground and/or in ducts it shall be steel wire
armoured with a PVC oversheath.
Turbine meters shall be constructed from stainless steel with carbon steel or stainless steel
flanges. Rotors shall generate pulses within pick-up coils fitted to the outside of the meter
housing. Rotor bearings shall be tungsten carbide construction.
Turndown ratio shall not exceed 10:1
e) Thin plate weirs shall be in accordance with BS3680 part 4A. Weir plates shall be fixed
in position, of sufficient thickness as to ensure rigidity under all flow conditions and
installed true vertical and horizontal. Plates shall be fabricated from either stainless
steel or a plastic polymer that is not affected or degraded by exposure to sunlight/UV.
f) For sewage applications flumes shall normally be flat bottomed rectangular or U-
throated in accordance with BS3680 Part 4C.
g) The flume primary element may be a factory built prefabricated assembly to be
incorporated and installed true and level without distortion into the overall hydraulic
structure.
Be suitable for rack, panel and/or wall mounted applications as required for the
particular application.
g) The control unit shall also automatically self-monitor for correct operation and provide a
common alarm for system faults, memory failure and loss of echo. This common alarm
shall be connected to telemetry.
h) A plate, mounted and set to simulate known head of water and corresponding flow rate
shall be provided such that it may readily be temporarily rotated under the transducer
to provide a reference level to aid calibration and routine checking. A latch or retaining
device shall be provided to enable the plate to be locked in either position.
i) For general process flow measurement applications the control unit shall be mounted
on the main control panel unless the distance between the transducer and the control
unit exceeds the maximum stated by the manufacturer. If the maximum distance would
be exceeded the control unit may be mounted externally within a vandal proof lockable
enclosure with viewing window and providing protection to IP55 BS EN 60529. Such
enclosure to have a anti-condensation heater operating at 220 volts.
j) Where the instrument is to be used for Regulatory purposes the control unit shall
either:
be mounted externally within a vandal proof lockable enclosure with a viewing
window and providing protection to IP55 BS EN 60529 installed in such a position
as to be readily and safely accessible to the Regulatory Authority for flow reading
purposes without it’s staff requiring access to any building, control room etc.
or
a remote readout be provided for such purpose.
k) Where the instrument is to be used both for Regulatory purposes and process control
particular care shall be taken to ensure that the there are no adverse effects upon the
correct functioning of the meter by the process control connections or interface. Signal
isolators shall be used in the analogue circuits.
c) The type of transducer chosen shall be located such that the emitted beam covers an
area that avoids obstacles and reflections to prevent spurious readings.
d) Any separate temperature sensor shall be located adjacent to the transducer but shall
not be positioned such that it may receive direct sunlight.
g) Where required by the particular application e.g. pump control the controller shall
provide additional features e.g.:
Be configurable to operate around at least two sets of time dependant control
set points to allow peak lopping event and one time related low level pump
down event;
Provide volumetric conversion of tank/sump level into volume and the
capability to gather total pumped volume data.
h) The control unit shall also automatically self-monitor for correct operation and provide a
common alarm for system faults, memory failure and loss of echo. This common alarm
shall be connected to telemetry.
i) The control unit shall normally be mounted on the main control panel unless the
distance between the transducer and the control unit exceeds the maximum stated by
the manufacturer. If the maximum distance would be exceeded the control unit may be
mounted externally within a vandal proof lockable enclosure with viewing window and
providing protection to IP55 BS EN 60529. Such enclosure to have a anti-condensation
heater operating at 220 volts.
Inaccuracy Range
Type I + 5 mg/l or + 10% of 0-100 mg/l suspended solids
reading whichever is
greater
3. Sensors - For dip and insertion sensors, the sensor shall be safely and easily removed
from the process stream without shutting down the process. Self cleaning and integral
automatic calibration facilities shall be included
The total response time, including all sampling lags, shall not exceed 3 minutes (T 90) for type
I analysis
Range - The range shall be capable of selection by the user and shall be suitable for the
application.
Repeatability - Repeatability shall not exceed + 1% of span or + 0.1 FTU, whichever is
greater.
c) Sensor Cleaning – self-cleaning integral automatic calibration and manual cleaning
facilities shall be included if required to achieve the required time between
maintenance.. Incorporation of these systems shall not affect the availability of the
instrument for a period greater than 1 minute in any one hour for type I instruments and
15 minutes in any one hour (maximum aggregate of 2 hours in 24 hours). For type II
instruments
d) Entrainment of Air - the instrument shall incorporate a facility for ensuring that
inaccurate readings due to entrained air will be minimised.
e) Sensors - For dip and insertion sensors, the sensor shall be safely and easily removed
from the process stream without shutting down the process.
f) Calibration shall be by the use of a Dry Secondary Calibration Standards designed and
supplied for the instrument. The standards shall be traceable to an FTU standard. One
number of standards appropriate for each specific model and range of instrument are
required on any one site.
c) The instrument shall meet the performance requirements of this specification when
operated continuously and without manual intervention for a minimum period of
30days. Auto-calibration, auto-cleaning or multi-sensor techniques may be used to
maintain this stability.
If self-cleaning and/or auto-calibration is incorporated the accuracy of the instrument
shall not be affected for a period greater than 10 minutes in any 1 hour period. The
aggregate of the off-line periods shall not exceed 2 hours in a 24 hour period.
d) Sampling systems should make provision for:
- Clean water flush and/or air purge (i.e. avoid deposition of suspended
material);
- Chemical cleaning with acids or biocides;
- Mechanical cleaning arrangements;
- Ultrasonic cleaners (NB: Control output to be inhibited during cleaning until
re-stabilisation achieved);
- Sample take-off point at a position that is representative;
- Care in avoidance of aeration of the sample on the release of dissolved
gases;
- Avoidance of change in temperature of the sample;
- Short sample time, achieved by fast bypass loops where necessary.
Operating
Inaccuracy:
Long Term range, all
Combined effect Temperature
Stability components
of non-linearity, effect all
Device unless
hysterisis and components 12 Months otherwise
repeatability % FSD/ C
0
% Span specified
% FSD 0
C
Operating
Inaccuracy:
Long Term range, all
Combined effect Temperature
Stability components
of non-linearity, effect all
Device unless
hysterisis and components 12 Months otherwise
repeatability % FSD/ C
0
% Span specified
% FSD 0
C
measurement
± 0.25 or 6mm,
Level Measurement by
which ever is - - -15 to +55
ultrasonic methods
greater
Differential Pressure
± 0.5 ± 0.02 ± 0.02 -
Transmitter
Panel Indicator
±1 - - -15 to +55
(analogue)
Flowmeter,
± 1.0 % of reading - - -15 to +50
Turbine
Flowmeter
± 5.0 - - -15 to +50
Variable Area
1 to 50 mg/l ±
1.0mg/l
Nitrate Analyser + 5 to +45
50 to 100 mg/l ± - -
2% of reading
Organic Pollution
± 0.5 ± ± +0 to +40
analyser
-10 to +50,
o
Temperature transmitter ± 0.5 C ± 0.02 ± 0.02 transmitter
only
m) 13. Motors fitted to sample pumps shall operate at the most suitable voltage appropriate
to the installation and type/size of pump being utilised. Motors shall be capable of long
term continuous running without maintenance e.g. 3ph 400Vac 50Hz. Single phase
230V or 110V ac 50Hz motors shall be of the capacitor start/run type.
1 110-IL-01 in the Inlet chamber Analogue (4-20 mA) Level Ultrasonic Acc. to installation Ex 2
2 121-IL-01 Coarse screen 1 channel Analogue (4-20 mA) Differantial Level Ultrasonic Acc. to installation Ex 2
3 121-IL-02 Coarse screen 2 channel Analogue (4-20 mA) Differantial Level Ultrasonic Acc. to installation Ex 2
4 122-IL-01 Fine screen 1 channel Analogue (4-20 mA) Differantial Level Ultrasonic Acc. to installation Ex 2
5 122-IL-02 Fine screen 2 channel Analogue (4-20 mA) Differantial Level Ultrasonic Acc. to installation Ex 2
6 120-IQ-01 in screening building Analogue (4-20 mA) Gas (CH4 & H2S) incl. visual and audible alarm 0-100% LEL and 0-50 ppm H2S Ex 2
7 120-IP-01 Service water supply pipe in screening building Digital Pressure Manometer + switch 0-10 bar Ex 2
8 121-IL-03 Coarse Wash press inlet hopper Digital Level 2x Point Acc. to installation Ex 2
9 122-IL-03 Fine Wash press inlet hopper Digital Level 2x Point Acc. to installation Ex 2
10 123-IP-01 outlet of the grit blower Digital Pressure Manometer + switch 0-500 mbar Ex 2
11 123-IQ-01 in the Inlet work's effluent chamber Analogue (4-20 mA) pH, Temp 1-14 Ex 2
12 123-IQ-02 in the Inlet work's effluent chamber Analogue (4-20 mA) conductivity 0-500 mS/m Ex 2
13 124-IL-01 stormwater pump sump Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
14 126-IL-01 waterline drainaige pump sump Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
15 126-IL-02 waterline drainaige pump sump Digital Level Float Sensor Acc. to installation -
Flow Meter
16 125-IF-01 in the flow metering chamber Analogue (4-20 mA) Flow Electromagnetic 0-3000 m3/h -
17 200-IT-01 in Primary sludge pump 1 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
18 200-IT-02 in Primary sludge pump 2 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
19 200-IT-03 in Primary sludge pump 3 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
20 200-IP-01 discharge pipe of Primary sludge pump 1 Digital Pressure Manometer + switch 0-10 bar -
21 200-IP-02 discharge pipe of Primary sludge pump 2 Digital Pressure Manometer + switch 0-10 bar -
22 200-IP-03 discharge pipe of Primary sludge pump 3 Digital Pressure Manometer + switch 0-10 bar -
23 200-IF-01 on the common discharge pipe of primary sludge pumps Analogue (4-20 mA) Flow Electromagnetic 0-40 m3/h -
# Tag Number Location Signal Type Measured Parameter Instrument Type Measuring Range EX Category
24 200-IT-04 in Primary sludge pump 1 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
25 200-IT-05 in Primary sludge pump 2 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
26 200-IT-06 in Primary sludge pump 3 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
27 200-IP-04 discharge pipe of Primary sludge pump 1 Digital Pressure Manometer + switch 0-10 bar -
28 200-IP-05 discharge pipe of Primary sludge pump 2 Digital Pressure Manometer + switch 0-10 bar -
29 200-IP-06 discharge pipe of Primary sludge pump 3 Digital Pressure Manometer + switch 0-10 bar -
30 200-IF-02 on the common discharge pipe of primary sludge pumps Analogue (4-20 mA) Flow Electromagnetic 0-40 m3/h -
31 201-IL-01 in the pump station Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
201-IL-03 in the pump station Digital Level Float Sensor Acc. to installation -
32 201-IL-02 in the pump station Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
33 201-IL-04 in the pump station Digital Level Float Sensor Acc. to installation -
34 210-IL-01 in the thickener tank Analogue (4-20 mA) Sludge-blanket level Ultrasonic Acc. to installation Ex 2
35 210-IL-02 in the thickener tank Analogue (4-20 mA) Sludge-blanket level Ultrasonic Acc. to installation Ex 2
36 210-IL-03 in the scum pump station Analogue (4-20 mA) Level Ultrasonic Acc. to installation Ex 2
37 210-IL-04 in the scum pump station Digital Level Float Sensor Acc. to installation Ex 2
38 210-IT-01 Temperature sensor for Primary sludge pump 1 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
39 210-IT-02 Temperature sensor for Primary sludge pump 2 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
40 210-IT-03 Temperature sensor for Primary sludge pump 3 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
41 210-IP-01 Pressure sensor on the pipe after Primary sludge pump 1 Digital Pressure Manometer + switch 0-10 bar -
42 210-IP-02 Pressure sensor on the pipe after Primary sludge pump 2 Digital Pressure Manometer + switch 0-10 bar -
43 210-IP-03 Pressure sensor on the pipe after Primary sludge pump 3 Digital Pressure Manometer + switch 0-10 bar -
Dorsch International Consultants GmbH 25
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP
Part 5 Instrument Specifications
# Tag Number Location Signal Type Measured Parameter Instrument Type Measuring Range EX Category
44 140-IQ-01 in the anoxic zone 1.1 Analogue (4-20 mA) Nitrate (NO3-N) UV absorbtion 0-10 mg NO3-N/l -
45 140-IQ-04 in the anoxic zone 1.2 Analogue (4-20 mA) Nitrate (NO3-N) UV absorbtion 0-10 mg NO3-N/l -
46 140-IQ-02 in aeration tank 1.1 Analogue (4-20 mA) Redox -500 … +500 mV -
47 140-IQ-03 in aeration tank 1.1 Analogue (4-20 mA) Dissolved Oxygen Optical 0-10 mg O2/l -
48 140-IQ-05 in aeration tank 1.2 Analogue (4-20 mA) Redox -500 … +500 mV -
49 140-IQ-06 in aeration tank 1.2 Analogue (4-20 mA) Dissolved Oxygen Optical 0-10 mg O2/l -
50 140-IF-01 on air pipe to AST 1.1 Analogue (4-20 mA) Flow 0-6000 m3/h -
51 140-IF-02 on air pipe to AST 1.2 Analogue (4-20 mA) Flow 0-6000 m3/h -
Blower Station 1
54 140-IQ-07 in the anoxic zone 2.1 Analogue (4-20 mA) Nitrate (NO3-N) UV absorbtion 0-10 mg NO3-N/l -
55 140-IQ-10 in the anoxic zone 2.2 Analogue (4-20 mA) Nitrate (NO3-N) UV absorbtion 0-10 mg NO3-N/l -
56 140-IQ-08 in aeration tank 2.1 Analogue (4-20 mA) Redox -500 - 500 mV -
57 140-IQ-09 in aeration tank 2.1 Analogue (4-20 mA) Dissolved Oxygen Optical 0-10 mg O2/l -
58 140-IQ-12 in aeration tank 2.2 Analogue (4-20 mA) Redox -500 … +500 mV -
59 140-IQ-11 in aeration tank 2.2 Analogue (4-20 mA) Dissolved Oxygen Optical 0-10 mg O2/l -
60 140-IF-03 on air pipe to AST 2.1 Analogue (4-20 mA) Flow 0-6000 m3/h -
61 140-IF-04 on air pipe to AST 2.2 Analogue (4-20 mA) Flow 0-6000 m3/h -
Blower Station 2
64 205-IF-02 in the inlet chamber from FST 1.2 Analogue (4-20 mA) Flow Ultrasonic 0-700 m3/h -
65 205-IF-03 in the inlet chamber from FST 1.1 Analogue (4-20 mA) Flow Ultrasonic 0-700 m3/h -
66 205-IL-01 in the RAS/WAS pump chamber Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
67 205-IL-02 in the RAS/WAS pump chamber Digital Level Float Sensor Acc. to installation -
68 205-IF-01 on common discharge main from RAS pumps Analogue (4-20 mA) Flow Electromagnetic 0-1200 m3/h -
69 205-IF-04 on common dischrage main from WAS pumps Analogue (4-20 mA) Flow Electromagnetic 0-80 m3/h -
# Tag Number Location Signal Type Measured Parameter Instrument Type Measuring Range EX Category
RAS/WAS Pumping station 2
70 205-IF-06 in the inlet chamber from FST 2.2 Analogue (4-20 mA) Flow Ultrasonic 0-700 m3/h -
71 205-IF-07 in the inlet chamber from FST 2.1 Analogue (4-20 mA) Flow Ultrasonic 0-700 m3/h -
72 205-IL-03 in the RAS/WAS pump chamber Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
73 205-IL-04 in the RAS/WAS pump chamber Digital Level Float Sensor Acc. to installation -
74 205-IF-05 on common discharge main from RAS pumps Analogue (4-20 mA) Flow Electromagnetic 0-1200 m3/h -
75 205-IF-08 on common dischrage main from WAS pumps Analogue (4-20 mA) Flow Electromagnetic 0-80 m3/h -
76 152-IL-01 in the scum pump station Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
77 152-IL-01 in the scum pump station Digital Level Float Sensor Acc. to installation -
Sand Filter
78 160-IL-01 in the Inlet chamber of the sand filter Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
79 160-IL-02 wash water pump sump Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
80 160-IP-01 pressure main of air compressors Digital Pressure Manometer + switch 0-1 bar -
UV Disinfection
81 170-IL-01 in the UV channel after disinfection Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
82 190-IP-01 on the common pressure main of service water pumps Analogue (4-20 mA) Pressure Pressure transducer 0-10 bar -
83 211-IL-01 in the WAS storage tank Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
84 212-IT-01 in GBT feed pump 1 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
85 212-IT-02 in GBT feed pump 2 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
86 212-IT-03 in GBT feed pump 3 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
87 212-IP-02 discharge pipe of GBT feed pump 1 Digital Pressure Manometer + switch 0-10 bar -
88 212-IP-03 discharge pipe of GBT feed pump 2 Digital Pressure Manometer + switch 0-10 bar -
89 212-IP-04 discharge pipe of GBT feed pump 3 Digital Pressure Manometer + switch 0-10 bar -
90 212-IF-01 discharge pipe of GBT feed pump 1 Analogue (4-20 mA) Flow Electromagnetic 0-100 m3/h -
91 212-IF-02 discharge pipe of GBT feed pump 2 Analogue (4-20 mA) Flow Electromagnetic 0-100 m3/h -
92 212-IF-03 discharge pipe of GBT feed pump 3 Analogue (4-20 mA) Flow Electromagnetic 0-100 m3/h -
93 212-IL-03 suction pipe of GBT 1 outlet pipe Digital Level 2x Point Acc. to installation -
Dorsch International Consultants GmbH 27
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP
Part 5 Instrument Specifications
# Tag Number Location Signal Type Measured Parameter Instrument Type Measuring Range EX Category
94 212-IL-04 suction pipe of GBT 2 outlet pipe Digital Level 2x Point Acc. to installation -
95 212-IL-05 suction pipe of GBT 3 outlet pipe Digital Level 2x Point Acc. to installation -
96 212-IT-07 in GBT 1 outlet pump Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
97 212-IT-08 in GBT 2 outlet pump Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
98 212-IT-09 in GBT 3 outlet pump Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
99 212-IP-12 discharge pipe of pump after GBT 1 Digital Pressure Manometer + switch 0-10 bar -
100 212-IP-13 discharge pipe of pump after GBT 2 Digital Pressure Manometer + switch 0-10 bar -
101 212-IP-14 discharge pipe of pump after GBT 1 Digital Pressure Manometer + switch 0-10 bar -
102 212-IP-01 Service water supply pipe in Sludge Treatment Building Digital Pressure Manometer + switch 0-10 bar -
103 212-IT-04 in Polymer Preperation unit pump 1 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
104 212-IT-05 in Polymer Preperation unit pump 2 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
105 212-IT-06 in Polymer Preperation unit pump 3 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
106 212-IP-07 Discharge pipe of Polymer Preperation unit pump 1 Digital Pressure Manometer + switch 0-10 bar -
107 212-IP-08 Discharge pipe of Polymer Preperation unit pump 2 Digital Pressure Manometer + switch 0-10 bar -
108 212-IP-09 Discharge pipe of Polymer Preperation unit pump 3 Digital Pressure Manometer + switch 0-10 bar -
109 212-IF-06 Discharge pipe of Polymer Preperation unit pump 1 Analogue (4-20 mA) Flow Electromagnetic 0-1 m3/h -
110 212-IF-07 Discharge pipe of Polymer Preperation unit pump 2 Analogue (4-20 mA) Flow Electromagnetic 0-1 m3/h -
111 212-IF-08 Discharge pipe of Polymer Preperation unit pump 3 Analogue (4-20 mA) Flow Electromagnetic 0-1 m3/h -
112 212-IP-05 service water pipe to PPU inline mixer 1 going to GBT 2 Digital Pressure Manometer + switch 0-10 bar -
113 212-IP-06 service water pipe to PPU inline mixer 2 going to GBT 3 Digital Pressure Manometer + switch 0-10 bar -
114 212-IP-10 service water pipe to PPU inline mixer 3 going to GBT 1 Digital Pressure Manometer + switch 0-10 bar -
115 212-IF-04 service water pipe to PPU inline mixer 1 going to GBT 2 Digital Flow Rotameter + 2x switch 0-3 m3/h -
116 212-IF-05 service water pipe to PPU inline mixer 2 going to GBT 3 Digital Flow Rotameter + 2x switch 0-3 m3/h -
117 212-IF-09 service water pipe to PPU inline mixer 3 going to GBT 1 Digital Flow Rotameter + 2x switch 0-3 m3/h -
118 270-IL-01 in the return liquor pump sump Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
119 270-IL-02 in the return liquor pump sump Digital Level Float Sensor Acc. to installation -
120 270-IF-01 common discharge pipe of return liquor pumps Analogue (4-20 mA) Flow Electromagnetic 0-300 m3/h -
121 215-IL-01 in the sludge blending tank Analogue (4-20 mA) Level Ultrasonic Acc. to installation Ex 2
Digester Building
122 220-IT-07 in the Digester feed pump 1 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
123 220-IT-08 in the Digester feed pump 2 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
124 220-IT-09 in the Digester feed pump 3 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
125 220-IP-09 discharge pipe of the Digester feed pump1 Digital Pressure Manometer + switch 0-10 bar -
Dorsch International Consultants GmbH 28
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP
Part 5 Instrument Specifications
# Tag Number Location Signal Type Measured Parameter Instrument Type Measuring Range EX Category
126 220-IP-10 discharge pipe of the Digester feed pump2 Digital Pressure Manometer + switch 0-10 bar -
127 220-IP-11 discharge pipe of the Digester feed pump3 Digital Pressure Manometer + switch 0-10 bar -
128 220-IF-01 on infeed sludge going to heat exchanger 1 Analogue (4-20 mA) Flow Electromagnetic 0-100 m3/h -
129 220-IF-02 on infeed sludge going to heat exchanger 2 Analogue (4-20 mA) Flow Electromagnetic 0-100 m3/h -
130 220-IQ-01 on inlet of reciprocation pumps 1&2 Analogue (4-20 mA) pH 1-14 -
131 220-IQ-02 on inlet of reciprocation pumps 3&4 Analogue (4-20 mA) pH 1-14 -
132 220-IT-01 at the bottom of digester 1 Analogue (4-20 mA) Temperature PT100 0-50 oC -
133 220-IL-01 at the bottom of digester 1 Analogue (4-20 mA) Level Hydrostatic 0-20 m -
o
134 220-IT-02 at the middle of digester 1 Analogue (4-20 mA) Temperature PT100 0-50 C -
135 220-IL-02 at the top of digester 1 Digital Level Point Acc. to installation Ex 1
136 220-IP-01 at the top of digester 1 Analogue (4-20 mA) Pressure Pressure transducer 0-100 mbar Ex 1
137 220-IT-03 at the top of digester 1 Analogue (4-20 mA) Temperature PT100 0-50 oC -
138 220-IT-06 at the bottom of digester 2 Analogue (4-20 mA) Temperature PT100 0-50 oC -
139 220-IL-04 at the bottom of digester 2 Analogue (4-20 mA) Level Hydrostatic 0-20 m -
140 220-IT-05 at the middle of digester 2 Analogue (4-20 mA) Temperature PT100 0-50 oC -
141 220-IL-03 at the top of digester 2 Digital Level Point Acc. to installation Ex 1
142 220-IP-02 at the top of digester 2 Analogue (4-20 mA) Pressure Pressure transducer 0-100 mbar Ex 1
143 220-IT-04 at the top of digester 2 Analogue (4-20 mA) Temperature PT100 0-50 oC -
144 230-IL-01 in the digested sludge tank Analogue (4-20 mA) Level Ultrasonic Acc. to installation Ex 2
145 240-IT-01 in BFP feed pump 1 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
146 240-IT-02 in BFP feed pump 2 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
147 240-IT-03 in BFP feed pump 3 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
148 240-IP-01 discharge pipe of BFP feed pump 1 Digital Pressure Manometer + switch 0-10 bar -
149 240-IP-02 discharge pipe of BFP feed pump 2 Digital Pressure Manometer + switch 0-10 bar -
150 240-IP-03 discharge pipe of BFP feed pump 3 Digital Pressure Manometer + switch 0-10 bar -
151 240-IF-03 discharge pipe of BFP feed pump 1 Analogue (4-20 mA) Flow Electromagnetic 0-40 m3/h -
152 240-IF-02 discharge pipe of BFP feed pump 2 Analogue (4-20 mA) Flow Electromagnetic 0-40 m3/h -
153 240-IF-01 discharge pipe of BFP feed pump 3 Analogue (4-20 mA) Flow Electromagnetic 0-40 m3/h -
154 240-IT-04 in Polymer Preperation unit pump 1 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
155 240-IT-05 in Polymer Preperation unit pump 2 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
156 240-IT-06 in Polymer Preperation unit pump 3 Analogue (4-20 mA) Temperature Acc. to pump manufacturer -
157 240-IP-13 discharge pipe of Polymer Preperation unit pump 1 Digital Pressure Manometer + switch 0-10 bar -
158 240-IP-14 discharge pipe of Polymer Preperation unit pump 2 Digital Pressure Manometer + switch 0-10 bar -
159 240-IP-15 discharge pipe of Polymer Preperation unit pump 3 Digital Pressure Manometer + switch 0-10 bar -
Dorsch International Consultants GmbH 29
On behalf of JV Nexus
Sanitation Programme: NEXUS and Resource Protection Tender Documents – Vol.2
Component 3 Salt WWTP
Part 5 Instrument Specifications
# Tag Number Location Signal Type Measured Parameter Instrument Type Measuring Range EX Category
160 240-IF-07 discharge pipe of Polymer Preperation unit pump 1 Analogue (4-20 mA) Flow Electromagnetic 0-1.5 m3/h -
161 240-IF-08 discharge pipe of Polymer Preperation unit pump 2 Analogue (4-20 mA) Flow Electromagnetic 0-1.5 m3/h -
162 240-IF-09 discharge pipe of Polymer Preperation unit pump 3 Analogue (4-20 mA) Flow Electromagnetic 0-1.5 m3/h -
163 240-IP-10 service water pipe to PPU inline mixer 1 going to BFP 3 Digital Pressure Manometer + switch 0-10 bar -
164 240-IP-11 service water pipe to PPU inline mixer 2 going to BFP 2 Digital Pressure Manometer + switch 0-10 bar -
165 240-IP-12 service water pipe to PPU inline mixer 3 going to BFP 1 Digital Pressure Manometer + switch 0-10 bar -
166 240-IF-04 service water pipe to PPU inline mixer 1 going to BFP 3 Digital Flow Rotameter + 2x switch 0-6 m3/h -
167 240-IF-05 service water pipe to PPU inline mixer 2 going to BFP 2 Digital Flow Rotameter + 2x switch 0-6 m3/h -
168 240-IF-06 service water pipe to PPU inline mixer 3 going to BFP 1 Digital Flow Rotameter + 2x switch 0-6 m3/h -
169 240-IQ-01 in the BFP room in sludge treatment building Analogue (4-20 mA) Gas (CH4 & H2S) incl. visual and audible alarm 0-100% LEL and 0-50 ppm H2S -
170 250-IL-01 in the drying area pump station Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
171 250-IL-02 in the drying area pump station Digital Level Float Sensor Acc. to installation -
172 241-IL-01 in the equalization tank Analogue (4-20 mA) Level Ultrasonic Acc. to installation -
173 241-IL-02 in the equalization tank Digital Level Float Sensor Acc. to installation -
Gas Holder
174 320-IL-02 in the condensate chamber Digital Level 2x Point Acc. to installation Ex 1
175 320-IQ-02 in the condensate chamber Analogue (4-20 mA) Gas (CH4 & H2S) incl. visual and audible alarm 0-100% LEL and 0-50 ppm H2S Ex 1
176 325-IF-01 discharge pipe of gravel filter 1 Analogue (4-20 mA) Flow Thermal mass 0-400 m3/h Ex 2
177 325-IF-02 discharge pipe of gravel filter 2 Analogue (4-20 mA) Flow Thermal mass 0-400 m3/h Ex 2
178 325-IP-09 common suction pipe of gas booster blowers Analogue (4-20 mA) Pressure Pressure transducer -50 … +50 mbar Ex 2
179 325-IT-01 discharge of biogas booster 1 Analogue (4-20 mA) Temperature PT100 0-100 oC Ex 2
180 325-IT-02 discharge of biogas booster 2 Analogue (4-20 mA) Temperature PT100 0-100 oC Ex 2
181 325-IP-10 common discharge pipe of gas booster blowers Analogue (4-20 mA) Pressure Pressure transducer 0-200 mbar Ex 2
182 325-IF-03 at the outlet to CHP units Analogue (4-20 mA) Flow Thermal mass 0-400 m3/h Ex 2
183 325-IF-04 at the outlet to Boiler units Analogue (4-20 mA) Flow Thermal mass 0-200 m3/h Ex 2
184 325-IQ-03 in Gas room Analogue (4-20 mA) Gas (CH4 & H2S) incl. visual and audible alarm 0-100% LEL and 0-50 ppm H2S Ex 2
CHP Room
185 340-IT-01 heating water return pipe heat exchanger 2 Analogue (4-20 mA) Temperature PT100 0-100 oC Ex 2
# Tag Number Location Signal Type Measured Parameter Instrument Type Measuring Range EX Category
o
186 340-IT-02 heating water return pipe heat exchanger 1 Analogue (4-20 mA) Temperature PT100 0-100 C Ex 2
o
187 221-IT-09 on the hydraulic switch Analogue (4-20 mA) Temperature PT100 0-100 C Ex 2
188 350-IL-01 in the Fuel oil tank Analogue (4-20 mA) Level Ultrasonic Acc. to installation Ex 2
189 340-IQ-01 in CHP room Analogue (4-20 mA) Gas (CH4 & H2S) incl. visual and audible alarm 0-100% LEL and 0-50 ppm H2S Ex 2
190 340-IT-01 in CHP room Analogue (4-20 mA) Temperature PT100 0-50 oC Ex 2
Part 6 - Documentation
Table of Contents
page
6 DOCUMENTATION .................................................................................................. 1
6.1 General............................................................................................................ 1
6.2 Tender documentation ..................................................................................... 1
6.3 Documentation after Award of Contract and before Employer's
Taking-Over ..................................................................................................... 1
6.3.1 General ..................................................................................................... 1
6.3.2 Obtaining of relevant approvals and certificates ........................................ 3
6.4 Final Documentation ........................................................................................ 3
6.4.1 As-Built Drawings ..................................................................................... 3
6.4.2 Operation, Maintenance and Repair Manuals ........................................... 3
ANNEX A: MODEL OF OPERATIONS MANUAL FOR WWTP................................... 6
6 DOCUMENTATION
6.1 General
The documentation is divided into three categories:
Tender documentation to be submitted as part of the tender
Documentation after Award of Contract and before Tests on Completion (Working
documentation).
Final documentation to be submitted at the Tests on Completion.
6.3.1 General
Detailed drawings, descriptions and calculations required for the Contractor’s Temporary
Works and to provide additional details for the Contractor to construct the Permanent Works
as shown on the Contract Drawings and specified, shall be prepared by the Contractor and
submitted to Engineer for review. Drawings and calculations shall be submitted in four (4)
copies. Two (2) copies shall be returned to the Contractor with the Engineer's comments.
Drawings are to be submitted in time for incorporation of comments without delaying the
programme and the completion of the work. The Contractor shall within 2 weeks from the
Order to Commence submit a programme for submittal of all drawings and design
calculations requiring approval.
Any drawings and documents submitted for approval will be inspected, stamped and
protected for return to the Contractor normally within 14 days from receipt of the drawings by
the Engineer. When large quantities of documents are submitted at one time, the Engineer
may, at his discretion, advise the Contractor of the expected return date.
Drawings from sub-contractors shall be checked signed by the Contractor before being
forwarded to the Engineer, who shall deal in all respects exclusively with the Contractor.
When the Engineer has approved a working drawing, he shall return a copy marked
"Approved" to the Contractor, who shall then insert the date of approval on the tracing and
furnish the Engineer with three prints of the working drawings as approved.
Approval of a working drawing by the Engineer will only signify his general approval of the
design and shall not make him liable for any error of the Contractor in detail or lack of
strength or efficiency of any part. Where errors, deviations and / or omissions are discovered
later, they shall be made good by the Contractor irrespective of any approval by the
Engineer.
Any modifications to the approved drawings found necessary on the Site shall be agreed with
the Engineer and confirmed in writing as record, by Site Instruction or other means. If any
approved drawing needs to be amended later, the amended drawing shall be submitted for
approval in accordance with the aforesaid.
The Engineer may require the Contractor to submit for approval drawings, samples, patterns,
models and technical details of items additional to those mentioned above to the extent
reasonably necessary for him to satisfy himself that the items are suitable for their intended
purpose.
During the construction period, the Contractor shall prepare a set of drawings marked with
changes and additions. Upon completion of the work, this set of drawings shall be submitted
to the Engineer for approval.
(1) Numbering system
The Contractor shall design a document numbering system for all documentation. The
system shall include all documents, manuals and drawings and shall be comprehensive.
Issue and submittal of all subcontractor’s documentation shall be in accordance with the
approved system.
The Contractor shall design the tag numbering system for all equipment, processes and
locations.
All documents and manuals
All drawings
All electrical and mechanical components
All cables
All pipes.
The Engineer shall approve the numbering / tag systems.
(2) QA system
Not more than thirty (30) days after the Commencement Date, the Contractor shall submit
a detailed Quality Plan for review by the Engineer. The Plan shall cover the quality
assurance of all aspects of the Works, and contain, as a minimum, the following items:
Organisation chart for quality control
List of Contractor’s staff to be engaged in quality control and materials testing
together with de-tails of their relevant experience
List of facilities which will be inspected and tested by the Contractor at stages during
implementation of the Works as part of his quality control, together with inspection
procedures and test types
Welding Procedure Specifications (WPS)
Welders Certificates
Results of welds testing
Certificates of materials
Test results from pressure test on pressure pipes
Documentation of surface treatment (corrosion protection)
Test results of capacity tests
Specifications of equipment and work
Tests
loose-leaf binders of DIN A4 size. Copies of these manuals shall be used during the training
courses for operation and maintenance.
For all installations, the manuals shall include:
A general part comprising contents, description of the installation and relevant
addresses and phone numbers,
Documentation - as built,
Functional description,
List of components indicating manufacturer, type, component numbers, ordering
numbers, other data and position,
Maintenance instructions stating maintenance routines and intervals,
Fault finding instructions,
Calibration reports for analogue signal circuits,
Data leaflets,
Manufacturer’s recommended spare parts lists for 2 years, according to the O&M
manuals, and sources of supply for the parts.
List of tools, and
List of lubricants.
Written explanations of all safety considerations relating to operation and
maintenance procedures.
For mechanical installations the manual shall further as a minimum contain:
Machinery Type and Serial No. (all in one chart),
Operating instructions,
Lubrication charts and maintenance instructions (all equipment included in one
chart),
Fault finding details for rectification of basic faults,
List of spare parts giving part numbers in relation to a drawing preferably of the
exploded view type. The list shall be appropriate for correct reordering of the
complete component and its spare parts as well as repair kits,
Brochures including all components accompanied with names and addresses of
suppliers,
Performance curves, diagrams, test certificates etc.
Specification of corrosion protection,
Specifications for repair of all painted / coated surfaces, and
Guidelines for repair.
For all electrical components the manual shall be divided into separate sections for the
following installations:
Control panels,
Instruments,
Control and measuring components (signalling system), and
Other components.
For electrical equipment the manual shall further include but not be limited to:
Layout drawings,
Schematic and wiring diagrams,
Detailed description,
Specific operation instructions,
Specific maintenance instructions,
Component list for all equipment,
Fault-finding chart,
Emergency procedure,
A transcription of each application program with explanatory comments (source text)
for sub stations and the master station, which explains the function and operation
mode, including all potential documentation presenting the programming software
(Cross reference schedules etc.)
Manual for sub-station and master station
Backup copy of data, application program and potential updated PLC program on
flash memory or similar.
All electrical drawings shall also be delivered in electronic version on CD-ROM together with
a licensed version of the standard software tools used for designing the plant.
All information in the manuals shall apply specifically to the equipment being supplied, and
shall be free from such irrelevant matters as might be contained in the manufacturer’s
general literature. Other types of machines and options not included in the Contract are not
allowed in the instructions.
Immediately after the Test on Completion, the suitable corrected manuals shall be compiled
into its final form and be submitted to the Engineer for approval.
The final version of the Operation, Maintenance and Repair Manuals shall be submitted with
six (6) copies in both English and Arabic. Each of the Operation Maintenance and Repair
Manuals shall be submitted in both hard copy and in electronic form as approved by the
Engineer.
Any additions, alterations or deletions, which may be required following the experience
gained during the Defects Notification Period shall be incorporated into the final versions in
the form of additional pages or complete replacement of sections as specified by the
Engineer. All costs of these amendments shall be deemed to be included in the Contract
Price.
The Taking-Over Certificate will not be issued until all copies of the final Operation,
Maintenance and Repair Manuals have been handed over.
7 Testing..................................................................................................................... 1
7.1 General ................................................................................................................ 1
7.2 Testing Method Statement and Work Programme ................................................ 2
7.3 Inspection and Testing Requirements .................................................................. 2
7.4 Testing General.................................................................................................... 2
7.4.1 Provision of Equipment, Materials, Power and Consumables for
Testing ............................................................................................................ 2
7.4.2 Works Testing and Inspection Costs ................................................................ 2
7.4.3 Test Instruments .............................................................................................. 3
7.4.4 Test Certificates............................................................................................... 3
7.5 Works Hydraulic Test ........................................................................................... 3
7.6 Works Inspection Tests and Guarantees .............................................................. 4
7.7 Pumps .................................................................................................................. 4
7.8 Motors .................................................................................................................. 5
7.9 Control Panels...................................................................................................... 5
7.10 Pressure Switches and Gauges ........................................................................... 5
7.11 Mechanical ........................................................................................................... 5
7.12 Electrical and Automation ..................................................................................... 6
7.12.1 Electrical .......................................................................................................... 6
7.12.2 Automation ...................................................................................................... 6
7.13 Performance Testing of Specific Equipment ....................................................... 10
7.14 Civil and Builders Works .................................................................................... 10
7.14.1 Materials ........................................................................................................ 10
7.14.1.1 Samples.................................................................................................. 10
7.14.1.2 Tests....................................................................................................... 11
7.14.2 Test Certificates............................................................................................. 11
7.14.3 Testing and Inspection................................................................................... 11
7.14.3.1 General ................................................................................................... 11
7.14.3.2 Gravity Sewers ....................................................................................... 12
7.14.3.3 Pressure Mains ....................................................................................... 13
7.14.3.4 Manholes and Inspection Chambers ....................................................... 13
7 Testing
7.1 General
The tests shall be carried out in accordance with the Conditions of Contract prior to hand
over of the Works on Completion as follows:
Tests before Taking Over
Pre commissioning,
Commissioning,
Tests after Taking Over
Monitoring of performance parameters and other tests to be carried out after
Taking Over during the O&M period
This Part 7 covers testing before Taking Over. Tests after Taking Over are specified in
Specification Part 8.
The objective of the testing is to verify that all equipment and systems work in accordance
with the Contract and the detailed design so that the whole Works or Section of Works can
be put into operation immediately following Taking over. Wet tests before Taking Over shall
generally be done with clean water. Where it is approved by the Engineer to carry out such
tests with wastewater, then adequate measures shall be taken for environmentally sound
disposal of the test water and it shall not be considered as Taking Over.
All tests of equipment and of the complete system shall be performed in accordance with the
Contractor's approved Quality Assurance system.
All tests have to be documented in test forms defined as part of Quality Assurance system
covering:
Date of test,
Description of test,
Actual method of test,
Output of test,
Remarks regarding deviations from the expected output,
Accepted / rejected,
Supervisor's signature,
Comments.
Handling of Deviations
Before the report is completed and can be approved, all significant deviations have to be
corrected.
In case of deviations, the following issues have to be decided:
What are the consequences of the deviation? Which part of the installations will
be influenced by a revision, and which tests already accepted will have to be
done over again (if any)?
Date of a new test of the revised system included repetition of already accepted
tests.
The acceptance test report shall be approved when significant deviations have been
corrected and tested.
All tests have to be planned so the Engineer has the possibility to comment on the tests
planned and to supervise the tests. That means that all tests shall be announced at least two
weeks in advance. This goes also for any repetition of tests.
(3) The Contractor shall provide adequate means on site to identify the materials or goods
with their respective test certificates.
(4) Test Certificates shall be provided giving detailed records of all electrical and
mechanical tests carried out on the equipment and material including lifting equipment,
tanks, pressure vessels, cables and cabling both in the manufacturer’s works and on
site.
(5) Copies of certificates for the hydraulic tests carried out in all works shall be provided.
(6) The Contractor shall obtain and submit to the Engineer and to other parties as may be
directed, test certificates for all items, certifying that they have been satisfactorily tested
and describing and giving full particulars of such tests.
(7) Copies of test certificates of major items shall be included in the operating and
maintenance instructions.
7.7 Pumps
(1) The witnessed test shall obtain the guarantees of pump delivery, head, kW input,
overall efficiency and other figures in accordance with the guarantees given in the
Schedule of Particulars and shall satisfy the inspector as to the mechanical reliability of
the plant and its capability of fulfilling the whole of the conditions.
(2) The guarantee duty is subject to a tolerance of ±5%.
(3) It is preferable that the pumps be tested with their own motors, but if this is not
attainable the pumps shall be tested in conjunction with the pump manufacturer’s
standard or calibrated motor, but the manufacturer shall satisfy the Engineer as to the
performance of the test motor so that the kW absorbed by the pumps may be
accurately determined.
7.8 Motors
(1) All motors shall be subject to full performance tests on site, which shall be witnessed
by the Engineer. Motors > 100 kW and their associated equipment subject to factory
performance tests may be witnessed by the Engineer and Employer. The Engineer will
nominate which tests are to be witnessed.
(2) Motor tests shall be carried out in accordance with the requirements of British
Standards or DIN as applicable. Tests shall gauge the overall level of efficiency and
other figures in accordance with the guarantees given in the Schedule of Particulars.
Test Certificates shall be provided for all sized motors.
7.11 Mechanical
Before Taking-Over can take place, the Contractor shall test - as installed - all mechanical
installations to prove that the capacity, power consumption and general efficiency and
functionality complies with the Employer's Requirements.
The tests shall be carried out in the presence of the Engineer.
The results of the testing shall be compiled in a report for approval by the Engineer.
For pumps the tests shall include:
Flow (measured at operating levels).
Pressure in pressure main, if applicable.
Power consumption.
For other mechanical installations the tests shall include:
Test of correct functions.
Power consumption, if motor-operated.
The tests shall be carried out as well before as after the equipment has been put into normal
service (dry and wet testing).
The testing shall also include testing of all automatic functions as described in the Employer's
Requirements.
7.12.1 Electrical
The following electrical functions shall be tested, and shall be verified to be in accordance
with the Employer's Requirements:
Earth resistance and boundary system.
Function of all emergency stop circuits.
Function of all safety circuits.
Lightning systems.
Emergency power supply system. The external power supply shall be switched
off and it shall be verified, that the emergency power supply system starts up
automatically. Furthermore it shall be verified, that all emergency control
functions start up automatically (automatically by-pass of waste water, handling
of alarms etc.).
Signal test of all signals according to signal lists. All signals shall be tested from
source to software. For analogue signals range and scale shall be verified. For
level transmitters offset and range shall be related to fix points in the
construction.
7.12.2 Automation
The automation system covers the PLC system and the SCADA system. The test shall cover
a number of different issues:
Usability (general operation of the automation and SCADA system).
Efficiency (performance).
Accuracy (correct handling of values and calculations).
Security (protection against unauthorised use of the SCADA system).
Flexibility (verification that the automation system is suitable for upgrading).
Below, each issue is described. At the end of each item, a number of criteria for passing test
are described.
(1) Usability
This section describes the tasks to be performed to test the usability of the program.
(2) Installation and start up
The purpose of this test is to make sure that the installation and start-up procedure
functions well and is described correctly in the Operation and Maintenance Manual.
The test shall:
Perform an installation procedure in accordance with the O&M Manual.
Check if the procedure is in accordance with instructions.
Check if the program can start up normally.
Perform a normal removal of program.
The on-line help function provides relevant help to the operator in most situations,
and the terminology is clear and consistent.
(4) Efficiency
The purpose of the efficiency test is to verify that the operation and response times are
at an acceptable level.
The verification of efficiency values shall be based on well-defined situations. The
operator shall perform different kind of situations:
Changing a set-point / sending a command.
Open a new diagram.
Open a graph.
Require a report based on historical data's.
Five different types of response times have to be taken into account:
Response time for a transaction, which is the time interval from sending a
command until the result is visible and the user can send a new command.
Sending a command can be executed by the "Enter"-button, by a mouse click
etc. This type of transaction is defined as typing data in an input data field with no
calculations, change of diagram etc. related to the transaction.
Response time for opening a new part of the program, such as a new diagram.
Opening a diagram for the first time after start of the program may take longer
time.
Response time for opening a graph showing curves for 24 hours. In this case, the
response time is the time interval from sending an "open graph" command until
the result is visible.
Response time for opening a report showing values for 1 month. In this case, the
response time is the time interval from sending an "open report" command until
the result is visible.
Response time for creating a background job such as a printing command.
The criteria for passing the final acceptance test will be:
The response time for sending a command is almost negligible (less than 1
second). Return of the value from the PLC shall be fulfilled within 2 seconds.
The response time for opening a new diagram is less than 2 seconds.
The response time for opening a graph is less than 10 seconds.
The response time for opening a report is less than 20 seconds.
All tests shall take place from the secondary operator station (not the server).
(5) Accuracy
The purpose of the accuracy test is to verify that the system generates correct output
results.
Based on the detailed project for automation the functionality described here shall be
verified.
All functions shall be simulated so electrical connections the software and correct
parameter settings can be verified.
The real check of the results will be done manually. A selection of output data will be
made, and manual recalculation of this output data will be performed. The
documentation will include all the intermediate results.
The system has to be designed in a structure with well-defined modules or classes.
The classes shall be defined with interfaces where inputs and outputs are available for
investigation. A complete test is divided into several accounts. The number of accounts
shall be sufficiently high to allow verification of the sequence between two accounts by
use of a pocket calculator.
The criteria for passing the final test will be:
Manual calculation proving correct relations between all generated accounts.
(6) Security
The purpose of this test is to verify correct security functions in accordance with the
requirements. A number of security levels have been specified.
For each security level, the following has to be verified:
A person at each level (if defined) shall be able to log into the system and have
access to the system in accordance with their status. It shall also be verified that
the user does not have access to part of the system not covered by their rights.
This test shall be performed for a person at each level.
Each person defined shall be able to change their own password.
The administrator shall be able to define and remove users and to change a
user's password. If specified, the administrator shall be able to look into database
structures, as well.
The designer shall be able to look into database structures and source codes.
The test of access to source code can be carried out on the development system,
only.
The criteria for passing the final acceptance test will be:
The number of users has been successfully defined at different levels.
A user has successfully logged in and out.
A user successfully changed their own password.
The administrator has successfully changed the password of a user.
The system has been successfully accessed at the different levels.
(7) Flexibility
The purpose of this task is to verify that the structure of the system is suitable for
upgrading to additional functionality. The source code and programmers'
documentation shall be investigated.
The test shall verify that:
The program and database structure of the program developed have well defined
interfaces in order to add new modules and new technical solutions under
existing SCADA systems.
The source code is well documented with comments and descriptions in the code
and variables are described in a logical way.
The compilation and installation of the software are well described.
The criteria for passing the final acceptance test will be:
The structure of the documentation is in accordance with the specifications.
Investigation of several classes, selected arbitrarily proves a comprehensive
amount of relevant code line comments so that the source code is
understandable.
The compilation and installation of the software are adequately described in the
documentation.
7.14.1 Materials
7.14.1.1 Samples
(1) In addition to specific provisions in the specifications for sampling and testing of
materials, the Contractor shall submit to the Engineer, as he may require, samples of
all materials which he proposes to use in the works. When approved, these will be
retained by the Engineer.
(2) Samples to be submitted shall be accompanied by an approved form on which all
information about specifications, description, location of use, manufacturer etc. are
stated.
(3) The Contractor shall submit a “Materials Procurement Programme” for all materials and
equipment which are deemed to be used in the permanent works indicating dates for
sampling, approval, ordering, and delivery to site.
(4) The Engineer may reject any materials or goods which in his opinion are inferior to the
samples submitted.
(5) The Engineer's approval of manufacturers or material for the works, whenever required
by the specifications, shall not relieve the Contractor of his responsibilities under the
Contract.
7.14.1.2 Tests
(1) The Engineer may examine and may require testing of any materials or goods to be
used in the works at any place inside or outside Jordan. The Contractor shall give the
Engineer unrestricted access to his sub-contractors' and suppliers' premises for such
purposes at all times.
(2) The Contractor shall afford the Engineer all facilities, assistance, labour and appliances
necessary for the convenient examination, testing, weighing or analysis of all materials
and goods. The Contractor shall prepare all test samples the Engineer may require.
(3) Tests carried out off the site shall not relieve the Contractor of the responsibility of
ensuring that the materials pass any required tests on site and when they are
incorporated in the permanent works.
(4) The costs for all tests as prescribed in the Specifications and as directed by the
Engineer shall be borne by the Contractor and are deemed to be included in his
contract prices.
7.14.3.1 General
(1) All pipelines and associated chambers shall be inspected and tested as described and
the Contractor shall include in his rates for all costs thus incurred. Any defects found
shall be made good and the test shall be repeated at the expense of the Contractor
until a satisfactory result is obtained.
(2) All tests shall be witnessed by the Engineer. Test results shall be recorded on an
approved test data sheet, countersigned by the Contractor and the Engineer, and
copies shall be provided for the Engineer's use.
as video, either on VHS tape or digital format. If the recording is provided in digital
format, then the viewing software shall be provided for the use of the Engineer.
(8) An inspection report shall be prepared, stating the date of inspection, sections
inspected, description of the inspection equipment, procedures and problems
encountered, inspector’s report sheets for each section and a summary of defects
observed.
(9) The inspection video record and report shall be submitted to the Engineer in two copies
before final Taking Over.
7.14.4.1 General
(1) The approval of the Engineer of any materials, proportions or results given under this
section shall not relieve the Contractor from his obligations in connection with the
requirements for permanent works concrete.
(2) Concrete for testing shall be taken from the point of placing. Sampling shall be carried
out and tests made in accordance with an approved procedure.
(3) The Contractor is responsible for the provision of the moulds and assisting the
Engineer in taking concrete samples for the execution of the tests and for taking into
account the results of such tests in the execution of the Works.
Contractor's rates for concrete and no additional payment for such assistance
shall be made.
(2) Preliminary Test Cubes shall be taken from the proposed mixes as follows:
(a) For each class a set of 6 cubes shall be made from each of 3 consecutive trial
batches. 3 from each set of 6 shall be tested at an age of 7 days and 3 at an age
of 28 days.
(b) The cubes shall be made, cured, stored, transported, and tested in accordance
with approved standards.
(c) At each age of test no cube strength shall fall below the appropriate specified
minimum for preliminary strength tests.
(3) Works Test Cubes:
(a) These cubes shall be made from works concrete samples taken from the point of
placing as and when directed by the Engineer. Normally for each grade of
concrete, 6 cubes shall be made from concrete taken at random, 3 cubes from
each set shall be tested at an age of 7 days and 3 at an age of 28 days.
(b) Cubes will generally be required at least as follows:
− For every 25 m3 of concrete placed;
− For each important structural member;
− As otherwise directed by the Engineer.
(c) The cubes shall be made, cured, stored, transported, and tested as specified.
(d) A record of such tests identifying the test cubes with the part of the work
executed shall be kept on the Site by the Engineer and made available to the
Contractor.
(e) The appropriate strength requirement shall be considered to be satisfactory if
none of the strengths of the three cubes tested at each age is below the specified
cube strength, or if the average strength of the three cubes is not less than the
specified cube strength and the difference between the greatest and the least
strengths is not more than 20 % of that average.
(f) If the expected 28 day cube strength ßw28 is to be estimated from the 7 day cube
strength ßw7 in preliminary tests and quality control tests, this may in general be
done by applying the factors given in the table below, to the values of the 7 day
cube strength:
28-Day Cube
Cement Strength
Compressive
Class
Strength ßw28
Z 25 1.4 x ßw7
Z 35 L 1.3 x ßw7
Z 35 F; Z 45 L 1.2 x ßw7
Z 45 F; Z 55 1.1 x ßw7
(according to DIN 1045 Section 7.4.3)
or:
(g) The hardening test gives an indication of the strength of the concrete in the
structure at a particular time and thus also gives guidance as to the formwork
stripping time as determined in the following table extracted from DIN 1045,
Clause 12.3:
For the For Lateral
Lateral Formwork For the
Formwork of Formwork of
of Beams and Formwork
Cement Beams, Frames Walls for Water
Formwork of Walls of Ceiling
Strength Class and Wide Spread Retaining
and Columns Slabs
Slabs Structures *
[days] [days]
[days] [days]
Z 25 4 10 28 28
Z 35 L 3 8 20 20
Z 35 F, Z 45 L 2 5 10 10
Z 45 F, Z 55 1 3 6 6
* For design requirement, walls of closed tanks should not be subjected to any
lateral forces before the final hardening of the roof slab due to the propping
action induced by the slab.
(h) The hardening can be determined, in accordance with approved standards, on
test specimens or by non-destructive means.
(i) The specimens for these tests shall be made from the concrete intended for the
structural components in question and be stored directly beside or on these
components and be cured in the same manner (influence of temperature and
humidity). At least three specimens shall be made for the hardening test, but it is
advisable to make more specimens so that if the strength determined in the test
is found to be inadequate the test can be repeated.
(j) Components whose dimensions vary significantly from those of the test
specimens may attain a different degree of hardening from that of the specimens,
e.g. due to differences in heat evolution in the concrete. Due account should be
taken of such factors when assessing test results.
(k) If, due to lack of compressive strength test results, or in the event that there is
reason to doubt the strength of concrete in any particular section, it may be
7.14.4.4 Laboratory
(1) The Contractor shall provide and maintain on site for the duration of the Contract a
concrete testing laboratory. It shall be equipped with at least one concrete cube
crushing machine, weighing scales, a set of sieves for determining particle size
distribution of aggregate, apparatus for testing the chemical content of cement provided
for the Works, all equipment required to perform all concrete tests, staffed by personnel
experienced in the use of such equipment who will be employed by the Contractor to
work under the direction of the Engineer when required. The equipment described
above will remain the property of the Contractor, also after conclusion of the works.
(2) The Contractor shall provide a locked and insulated curing tank for concrete test cubes.
(3) All equipment to be provided shall be tested, calibrated and certificates provided to
confirm its suitability for the required tests.
(4) The Contractor shall supply, install and maintain testing equipment and material
required to perform soil tests and quality control of asphalt.
(5) With the Engineer’s approval the Contractor may use testing laboratories / facilities
established elsewhere in the Employer’s country, provided that these laboratories /
facilities are recognized by the responsible Government Authorities. All costs involved
using these laboratories / facilities shall be borne by the Contractor.
no damp patches are visible, then the structure shall be deemed to have passed the
test.
(6) Should the structure be deemed by the Engineer to have failed the test, the Contractor
shall be responsible for and bear the expense of locating the source of leakage and
carrying out all necessary remedial work as required by the Engineer to make the
structure water tight. A further test shall then be carried out as before and the
procedure shall be repeated until the structure is deemed by the Engineer to have
passed the test.
(7) Incidental expenses to cover all the costs associated with carrying out this test to the
satisfaction of the Engineer are to be included in the respective Items. Payment will be
made for the successful structure only, and the rates entered by the Contractor shall be
deemed to cover all costs incurred in complying with the requirements of this Clause
including the cost of labour, equipment, supply and disposal of the water used in
testing.
7.15.1 PV Modules
For each PV module delivered for the project, a comprehensive IV flash test data collected
during the module fabrication (in excel format) must be provided. The data must have the
following information:
Serial number of the tested module, including which modules are in which shipping
containers and pallets.
Power at maximum power point (Pmpp).
Voltage at MPP (Vmpp).
This information shall be provided the latest 2 weeks prior to the arrival of PV modules on the
site, in order to enable the Contractor to plan or change the program development and
assembly based on the type and quantity of modules, in the containers they are delivered in.
7.15.2 Inverters
The Factory Acceptance test for the inverters shall include as a minimum the following tests:
Ingress protection (IP) testing. The test shall detect the ability of the inverter casing and
seal to prevent moisture, dust ingress and foreign particles from entering and harming
the electrical components.
Built quality check. During this procedure the build quality of the inverters is checked.
This basically involves an assessment of the quality and assembly of the
components on the electrical circuit board (resistors, diodes, capacitors, transistors
etc.) and wiring used in the system.
Hot spots and temperature distribution. During this test procedure, the temperature
inside an inverter and its distribution is checked.
Functions test. The functions test assesses the operational functioning and power
conversion characteristics of the particular inverter with a simulated PV array.
7.15.4 VT’s
Factory testing on VTs shall include:
Pressure and tightness test
Power frequency withstand test
Partial discharge test (<5pC)
Verification of terminal marking
Determination of Errors
7.15.5 CT’s
Factory testing on CTs shall include:
Pressure and tightness test
Power frequency withstand test
Partial discharge test (<5pC)
Capacitance Measurement on Capacitive Tap
Measurement of Dielectric Dissipation Factor
Secondary Resistance Measurement
Inter-turn Overvoltage test
Verification of terminal marking and turns ratio test
Determination of Errors
Verification of secondary EMF
Secondary magnetizing current characteristic
Routine tests for all CTs and VTs including confirmation that ratio and errors are within
IEC tolerances.
Primary injection of all CTs and VTs to confirm ratio and polarity.
Magnetisation curve tests for all CTs.
The overvoltage and secondary injection tests shall be repeated once the switchboard
has been installed at site.
7.15.9 Transformers
The following factory tests shall be undertaken on each of the following type of transformers
supplied by the Contractor as part of the Works:
Low resistance conductor test on the switchgear including circuit-breakers in the test
circuit.
Visual inspection.
Once the Taking Over Certificate has been issued, the Defects Notification Period starts. The
period ends with the issue of the Performance Certificate. During this period 2 different Tests
will be carried out:
The Intermediate Performance Test will start after the issue of the Taking Over
Certificate and will end 12 months after (see par. 8 for performance measurement
and acceptance procedures). Upon positive completion, an Intermediate
Performance Certificate is released by the Employer.
The Performance Test will start after the issue of the Intermediate Performance
Certificate and will end 12 months after (see par. 8 for performance measurement
and acceptance procedures). Upon positive completion, a final Performance
Certificate is released by the Employer.
8.10.1 General.......................................................................................................... 17
8.10.2 Sampling Equipment........................................................................................ 1
8.10.3 Laboratory and Analytical Equipment .............................................................. 1
8.10.4 Laboratory Information Management System .................................................. 1
8.10.5 Analytical Methodology .................................................................................... 1
8.10.6 Independent Analysis ...................................................................................... 1
8.10.7 Remedy on Compliance Failure ....................................................................... 1
8.10.8 Sampling by the Engineer ................................................................................ 1
8.10.9 Weather Data .................................................................................................. 2
8.11 Tests after Take Over........................................................................................... 2
8.12 Solid Waste Management .................................................................................... 3
8.12.1 Sludge Management........................................................................................ 3
8.12.2 Screenings, Grit and other Wastes .................................................................. 3
8.13 Third Party Discharges ......................................................................................... 3
8.13.1 Continuous Discharges to Sewer ..................................................................... 3
8.13.2 Intermittent Imported Discharges ..................................................................... 4
8.13.3 Procedures for Management of Third Party Discharges ................................... 4
8.13.4 Right to Refuse Third Party Discharges ........................................................... 4
8.14 Odour Control ...................................................................................................... 5
8.15 Noise Control ....................................................................................................... 5
8.16 Vermin Control ..................................................................................................... 5
8.17 Failure to Comply with the Environmental Requirements ..................................... 5
8.18 Management of Consumables.............................................................................. 6
8.18.1 Chemicals Management .................................................................................. 6
8.18.2 Energy Management ....................................................................................... 6
8.19 Maintenance of the Works .................................................................................... 6
8.19.1 General............................................................................................................ 6
8.19.2 Maintenance Programme ................................................................................ 6
8.19.3 Maintenance Outsourcing ................................................................................ 7
8.19.4 Building Maintenance ...................................................................................... 7
8.19.5 Site Infrastructural Maintenance ...................................................................... 8
8.19.6 Lifting Mechanisms .......................................................................................... 8
8.19.7 Tank and Pump Sump Inspection .................................................................... 8
8.19.8 Spare Parts ..................................................................................................... 9
8.19.9 Auditing of the Maintenance Programme ......................................................... 9
List of Tables
Table 1: Wastewater Influent Quality ...................................................................................... 2
Table 2: Treated Effluent Standard [Ref. JS 893/2006]........................................................... 2
Table 2: Staffing list for As Salt WWTP .................................................................................. 5
Table 3: O&M Staff Minimum Experience & Qualifications ..................................................... 8
Table 4: Sampling and Analysis Programme – Wastewater Treatment ................................ 19
Table 5: Sampling and Analysis Programme – Sludge Treatment ........................................ 20
Table 6: Sampling and Analysis Programme – Power Management..................................... 20
List of Figures
Figure 1: Organisation of Operations Staff.............................................................................. 4
7. Achieve satisfactory sanitary handling and disposal of screenings, grit and sludge; and
8. Minimise the generation of obnoxious odours and mitigate potential complaints due to
odours.
Training of WAJ staff shall be integrated into the O&M, commencing with the Tests on
Completion for both Section 1 and Section 2, as specified.
DO (mg/l) >2
TSS (mg/l 50
NH4+ (mg/l) -
Total-N (mg/l) 45
FOG (mg/l 8
Contractor’s Operations Staff shall be assigned to the works as specified until completion of
the O&M i.e. Section 3, and WAJ has assumed full operations responsibility and the Defects
Notification Period for both Section 1 and Section 2 is completed.
The O&M shall include all civil, mechanical, electrical, telemetry, SCADA and infrastructure
items comprising the complete project operating unit, including but not necessarily limited to
the following:
- Salt WWTP in its entirety, from the Inlet Manhole in the adjacent road to the effluent
discharge downstream of the lagoon and dam.
- Sludge treatment, from removal of sludge from the settling tanks to removal of treated
sludge from the WWTP at minimum 50% ds, including the digesters, gas treatment &
handling and CHP units.
- Solar PV installation.
- Complete smart power system, integrating power from the following sources:
Main power connection.
Power generation from digestor sludge gas at Salt WWTP.
Solar PV installation at Salt WWTP.
- All off site support or ancillary services needed for the functioning of the Salt WWTP as
an operating entity.
Operations Manager
Security
The Plant Manager will be responsible for the overall day to day management of the project,
including the operation and control of the different units for power supply, wastewater
treatment and sludge handling. Reporting directly to the Employer, the Plant Manager should
have a good technical background, with a sound understanding of operation and
management of wastewater treatment plants. Suitable candidates should have at least 15
years appropriate experience, with an international background.
A chemist/biologist/chemical engineer will be in charge of the laboratory and the monitoring
of wastewater and sludge quality. He will advise the Plant Manager on the operation of
treatment processes to achieve the optimum performance and compliance with proposed
wastewater standards. Concerning treatment efficiency, he will report independently to WAJ.
He will be assisted by several lab assistants and will be nominated as Deputy Plant
Manager.
An Electrical Engineer will be responsible for the “Smart Power System” to ensure adequate
power for the project at all times from the three main supply sources; mains power, digester
gas generation and solar PV, including the emergency standby diesel generators. Suitable
candidates should have at least 10 years appropriate experience, preferably with an
international background.
An IT/SCADA Engineer will be responsible for the SCADA, PLCs and all instrumentation
included in the controls at the WWTP to ensure proper monitoring and control facilities and to
carry out any programming needed for the SCADA system. Suitable candidates should have
at least 10 years appropriate experience, preferably with an international background.
It is proposed that a total of about 36 employees work at the plant as shown in Table 3
below.
Category Grade Shift Nos. Nos. Cat 1 Nos. Cat 2 Nos. Cat 3 Nos. Cat 4 Nos. Cat 5 Nos. Cat 6
Management
Plant Manager 1 1 shift 1 1
Planning/Process Control/Administration
Engineers 2 2 shift 1 1
Technicians 3 1 shift 1 1
Secretary 4 1 shift 1 1
Stores & Inventory 4 1 shift 1 1
O&M Power Supply/SCADA
Electrical Engineers 2 1 shift 1 1
IT/Instrumentation Engineers 2 1 shift 1 1
Technicians 3 2 shift 2 2
Skilled Workers 4 2 shift 2 2
O&M Water Treatment
Engineers 2 2 shift 2 2
Technicians 3 2 shift 2 2
Skilled Workers 4 2 shift 3 3
Unskilled Workers 5 1 shift 2 2
O&M Sludge Treatment & Gas Utilisation
Engineers 2 1 shift 1 1
Technicians 3 2 shift 2 2
Skilled Workers 4 2 shift 2 2
Unskilled Workers 5 1 shift 4 4
Laboratory
Manager/Deputy Plant Manager 1 1 shift 1 1
Technicians 3 1 shift 1 1
Skilled Workers 4 1 shift 1 1
Security
Security staff 6 2 shift 4 4
Total Staff 36 2 6 8 10 6 4
Category 1: plant manager Category 4: skilled workers
Category 2: Engineers Category 5: unskilled workers
Note:
1. If handover of the Works is delayed at the Contractor’s responsibility, Phase 1 manmonths shall be extended at no
additional cost.
2. If Defects Notification completion is delayed at the Contractor’s responsibility, Phase 3 manmonths shall be extended
at no additional cost.
Table 3: Staffing list for As Salt WWTP
8.5 Phasing
The O&M shall be provided in three phases as follows:
Phase 1 Prior to Taking Over of Section 1
For a period of at least 2 months during testing and commissioning of the Works
Section 1 Line 1 until formal Taking Over
Phase 1 shall apply to both Line 1 and Line 2. In the case of Line 2, the staff already
mobilised for the O&M and who are working on O&M shall provide these Phase 1 services.
Phase 2 After Taking Over of Section 1
For a period of at least eighteen calendar months from the date of takeover of the
works for Section 1“Part 1 Construction Stage 1”
The Contractor’s staff shall then carry out full operations and maintenance of the WWTP Line
1 and associated works until end of the Contractor’s O&M period. These staff shall work
initially on Line 1 and then concurrently on WWTP Line 2 once the Taking–Over Certificate
for Section 2 “Part 1 Construction Stage 2” has been issued.
Phase 3 Prior to Completion of the O&M
For the final 6 months of the O&M until issue of the Performance Certificate at the completion
of the O&M Period, the Contractor shall provide the ongoing services of the specified
operations staff.
The Contractor shall arrange that at least 50% of his staff will transfer to employment with the
organisation designated by the Employer to take over operation of the WWTP.
The staff that will transfer shall sign a letter of intent confirming that they will work at least 12
months with the new operator. The content of the letter of Intent shall be submitted to the
Engineer for approval. Against signing of this letter of intent, the transferred staff will be paid
a bonus equivalent to 10% of their net salary (after deduction of tax and social security) for
the first 12 months following completion of the Contractor’s O&M and transfer to the new
operator. This bonus shall be paid from the Provisional Sum provided in Bill No. 7
Operations.
The Contractor shall provide full and comprehensive training during the 6 months of Phase 3
for the additional operations staff that will be assigned to take over on completion of the
Contractor’s O&M services. If 100% of the Contractor’s O&M staff agree to transfer to the
incoming operator, then no training will be required.
Phase 4 After Completion of the O&M
The Contractor shall provide a bank guarantee in value of 10% of the last year of the O&M.
This guarantee shall be valid for 12 months following completion of the O&M services and
shall guarantee that the Contractor shall rectify any defects in the Works caused by the O&M
services notified during the 12 month period.
Provisional sums are provided for spare parts and expert support. These may be used at any
time during the O&M for services outside the Contractor’s specified scope, subject to the
approval of the Engineer.
The Contractor’s staff shall have the experience and background specified in Table 4 below.
Position Experience Qualifications
Operations Manager 15 years relevant experience in wastewater BSc or equivalent in
(Chief of Party) treatment, including 5 years responsible as engineering or process
manager in charge of the operation of a science.
WWTP of comparable size.
Process / Operations 10 years relevant experience in wastewater BSc or equivalent in
Engineer treatment operations, including 5 years in engineering or process
operation of a WWTP of comparable size. science.
Mechanical Engineer 10 years relevant experience in wastewater BSc or equivalent in
treatment operations, including sludge mechanical engineering
digestion.
Electrical Engineer 10 years relevant experience in operation of BSc or equivalent in
low and medium voltage power systems, electrical engineering
including generation, synchronisation and
networks
Laboratory Technician 5 years relevant experience in wastewater BSc in chemistry,
sampling and analysis. biochemistry or equivalent
Operations Technician 5 years relevant experience in wastewater Relevant vocational training
treatment and diploma or equivalent
certification
Mechanical 5 years relevant experience in wastewater Relevant vocational training
Technician treatment and diploma or equivalent
certification
Electrical Technician 5 years relevant experience in wastewater Relevant vocational training
treatment and diploma or equivalent
certification
The CVs of each of the above staff shall be submitted to the Engineer for approval at least
one month before the start of assignment. The Engineer will require that the Operations
Manager and Process / Operations engineer attend an interview in Jordan prior to giving
approval. These interviews shall be done at no additional cost.
In the event that any proposed staff member is rejected, it shall be the Contractor’s
responsibility to propose a replacement for approval within the Contract Programme.
Electricity costs will be paid for according to the items provided in the Contract O&M Bill for
the WWTP is based on the Tariff Rate in effect at the time of tender.
Escalation of the electricity costs will be paid according to the actual tariff rates at the time of
consumption and the actual metered consumption based on the following formula:
EE=Pc x Ta x 1.1 / Tt
Where:
EE = Electricity escalation to be paid quarterly in addition to the BoQ rate
Pc = Actual power consumption over the invoiced period in kWhr
Ta = Actual electricity tariff applicable over the invoice period
Tt = Electricity tariff applicable at the time of tender
The escalation costs will be paid from Provisional Sum included in Contract O&M Bills.
- Provide all authorisations and payment of tipping charges for screenings, grit and
sludge from the WWTP. Transport to the place of disposal shall be the responsibility
of the Contractor.
- Provide temporary release of WAJ staff as agreed to work with the Contractor
All other obligations shall be the responsibility of the Contractor and the associated costs
shall be included in the Contract rates.
- Installed on at least 3 PCs with Windows operating system, located in the Control
Room, in the maintenance workshop and the Operations Manger’s Office.
- Track, schedule and document predictive, preventive and corrective maintenance
activities.
- Identify any potential maintenance problems.
- Issue of work orders.
- Show the status of spare parts inventory.
- Issue of Periodic status report.
The Contractor shall provide any special training required in the MMS use to his and WAJ
staff and shall ensure that all relevant data is regularly feed and updated into the system.
The plan shall identify the hazards that could have consequential impacts on human and
animal health and the surrounding environment resulting in an emergency response. It shall
also specify methods and procedures for:
Dealing with emergencies
Testing of the EOP
The training for dealing with emergencies at the works, which shall be provided to
personnel.
Notifying the Engineer, his representative, other relevant public and private bodies,
and the general public
Dealing with the consequential impacts of the emergency
Communication with those notified regarding plans for remediation of any damage
done and actions to minimise re-occurrence.
The EOP should extend to tasks related to the operation and maintenance that may be
carried out beyond the boundaries of the Site. These may include sludge, screenings, and
solid waste disposal, chemical deliveries, and transportation of plant and equipment to and
from the works. The Contractor shall issue a copy of his EOP to all personnel, contractors,
and subcontractors, and shall ensure that they comply with its conditions at all times.
the EMS is fully in place and operating to the satisfaction of the Engineer. The Contractor
shall not be responsible for auditing the EMS for certification purposes; this may be arranged
by the WAJ within the duration of the O&M.
The EMS shall include the following:
Environmental policy;
Schedule of Environmental Objectives and Targets;
Environmental Management Programme;
The Operational Management Plan (as described in Clause 8.8.1);
Environmental review and audit procedures.
Protection of the Archaeological Site.
The report shall be submitted to the Engineer, one copy in electronic format and three copies
in paper format, within the first 14 days of each month following the month covered in the
Report.
The Engineer may request information, relating to the operation and maintenance of the
Plant, from the Contractor at any stage during the O&M.
8.9.1 General
The daily management and operation tasks will be under the control of the Operations
Manager (OM), reporting directly to the WAJ. The OM will be responsible for the overall day
to day management of the plant, including the operation and control of the different treatment
units for wastewater and sludge.
In Phase 2 of the O&M, the Contractor shall effectively manage operation of the works,
assisted by the WAJ personnel, on a continuous 24 hour, 7 day week basis. This will then be
taken over by WAJ in Phase 3 of the O&M.
8.10.1 General
Regular sampling and analyses of the wastewater, effluent and sludge shall be commenced with the Tests at Completion and shall be
carried out throughout the O&M. The minimum parameters, locations and frequency of analyses for wastewater treatment are as
specified in
Outlet Outlet Sand
Parameter Unit Inlet WWTP Inlet AST AST FSTs RAS Filters Outlet UV Outlet WWTP
3
Flow m /hr online Online Online
pH Daily/FPS online Daily/FPS
Conductivity µS/cm Daily/FPS Daily/FPS
o
Temperature C online online
Turbidity l/m Daily/FPS Daily Daily/FPS
O2 mg/l Online Daily
RedOx V Online
COD mg/l Daily/FPS Daily/FPS Daily/FPS
BOD mg/l Daily/FPS Weekly/FPS Daily/FPS
TSS mg/l Daily/FPS Weekly/FPS Daily/FPS
NH4-N mg/l Weekly/FPS Weekly/FPS Weekly/FPS
NO3-N mg/l Weekly/FPS Weekly/FPS Weekly/FPS
TN-N mg/l Weekly/FPS Weekly/FPS Weekly/FPS
PO4 mg/l Weekly/FPS Weekly/FPS
H2S mg/l Handheld
Alkalinity mg/l Weekly/FPS Weekly/FPS
MLSS mg/l Daily/GS
MLVSS mg/l Daily/GS
Table 5 below.
Outlet Outlet Sand
Parameter Unit Inlet WWTP Inlet AST AST FSTs RAS Filters Outlet UV Outlet WWTP
3
Flow m /hr online Online Online
pH Daily/FPS online Daily/FPS
Conductivity µS/cm Daily/FPS Daily/FPS
o
Temperature C online online
Turbidity l/m Daily/FPS Daily Daily/FPS
O2 mg/l Online Daily
RedOx V Online
COD mg/l Daily/FPS Daily/FPS Daily/FPS
BOD mg/l Daily/FPS Weekly/FPS Daily/FPS
TSS mg/l Daily/FPS Weekly/FPS Daily/FPS
NH4-N mg/l Weekly/FPS Weekly/FPS Weekly/FPS
NO3-N mg/l Weekly/FPS Weekly/FPS Weekly/FPS
TN-N mg/l Weekly/FPS Weekly/FPS Weekly/FPS
PO4 mg/l Weekly/FPS Weekly/FPS
H2S mg/l Handheld
Alkalinity mg/l Weekly/FPS Weekly/FPS
MLSS mg/l Daily/GS
MLVSS mg/l Daily/GS
The minimum parameters, locations and frequency of analyses for sludge treatment are as specified in Table 6 below.
Sludge Sludge Dried
Dewateri. Dewateri. Gas
Parameter Unit WAS Thicken. Thickn. Digesters Sludge to Return PS
Inlet Outlet Treatment
inlet Outlet Disposal
Sludge Flow m3/hr Online Online Online Online Online
3
Decant Flow m /hr Online
3
Gas flow m /hr @ Online
atmos
Dried Sludge m3/d Daily
o
Temperature C Online
COD mg/l Daily/GS
BOD mg/l Daily/GS
TSS mg/l Daily/GS
TN-N mg/l Weekly/GS
Sludge acidity pH Daily
ds % Daily/GS Daily/GS Daily/GS Daily/GS Daily/GS Daily/GS Daily/GS
Arsenic (As) mg/kg Monthly
Cadmium (Cd) mg/kg Monthly
Chromium (Cr) mg/kg Monthly
Copper (Cu) mg/kg Monthly
Mercury (Hg) mg/kg Monthly
Salmonella - Monthly
(4) - Monthly
Helminthes eggs
(5) - Monthly
Viruses
The minimum parameters, locations and frequency of analyses for power management are as specified in Table 7 below.
Parameter Unit Digesters Wastewater Sludge Treatment CHPs PV Diesel Generators
Treatment
Gas Flow @ atmos m3/hr Online Online
Power Production kWhr Daily Daily Daily
Power Consumption µS/cm Daily Daily
Diesel Fuel Consumption l/d Daily Daily
Other sampling and analyses required, either on a regular or from time to time, for the proper
control of the process shall be defined by the Contractor or carried out in close cooperation
with the WAJ staff.
Analysis that is capable of being carried out with the analytical equipment provided under the
Contract shall be performed at the Plant by the operational staff. All other analysis shall be
carried out by a recognised independent laboratory, as agreed with the Engineer.
Procedures and methods for the monitoring, sampling, and analysis for the wastewater and
sludge shall be provided as part of the Contractor’s OMP.
The Contractor shall carry out monitoring, sampling, and analysis in accordance with all
relevant regulations.
The Contractor shall ensure that all on site analysis is carried out in a safe manner, and that
all waste chemicals and containers are disposed of in a proper fashion.
This sampling shall be separate from the control sampling that will be carried out with the
Engineer every quarter, refer Clause 8.23.
- RAS pumps
- Sludge pumps
- Dewatering units
- CHPs
Operate the WWTP under emergency conditions on Diesel Generator power only
for 6 hours
highlighting changes that may be necessary to the physical plant, any operational
adjustments, and associated additional costs.
The Contractor during O&M may also be required to carry out monitoring, sampling, and
analysis of the particular industrial discharge. The mechanism for this activity, and the costs
associated with it, would be agreed between the parties at the appropriate time.
8.19.1 General
The Contractor during O&M shall provide for the routine, planned, breakdown, and repair
maintenance of all assets relating to civil, mechanical, electrical, and electronic plant,
equipment and infrastructure at the works.
occurs. The buildings shall be kept in such a state that they do not, in the opinion of the
Engineer, post any risk to the health, safety, and welfare of any person.
8.21.1 General
The Contractor during O&M shall comply with all aspects of current International Safety
Standards. The O&M shall also fully comply with the requirements of “Volume 2.0, Part 2
Employer’s Requirements, Section VII. Works Requirements, 1. Specifications, b)
Specifications of Environmental, Social, Health and Safety Management (ESHS) of the
Works”. The Contractor during O&M shall maintain and update the Safety File on an ongoing
basis.
The Contractor shall incorporate, into the OMP, procedures for the management, operation,
and maintenance of the works to be put in place in the event of a “no flow” occurrence. The
procedures shall cater for such an event should it occur without prior warning, i.e. as a result
of an emergency.
An inspection of the Plant, building structures, external works etc. shall be conducted jointly
by the Engineer at both times and the Contractor to establish the overall condition of the
facilities.
A functional test of all mechanical and electrical plant shall be carried out as part of the
inspection prior to completion of the Defects Notification Period. The tests shall be carried
out by the Contractor and witnessed by the Engineer.
A protocol shall be made containing all shortcomings found during the inspection and tests.
Responsibility for all shortcomings at the end of the Defects Notification Period shall be
determined in accordance with the Contract. The Contractor shall be required to remedy the
Defects under his liability within a predetermined time according to Conditions of Contract.
The Contractor shall, by the end of the Defects Notification Period, provide spare parts for
the Plant to an extent equivalent to the range of spare parts provided prior to Taking-Over
and agreed with the Engineer, paid from the Provisional Sum provided for this purpose.
8.25 Training
The Contractor shall be required to provide an on-site training programme in two phases.
Note that Phase 1 shall apply to both Section 1 “Part 1 Construction Stage 1” for Line 1 and
Section 2 “Part 1 Construction Stage 2” for Line 2. This training shall involve the following:
Phase 1: The Contractor shall be responsible for all dry and wet testing prior to Taking Over.
Phase 2: The Contractor shall be responsible for start-up, commissioning, performance
testing and operation of the WWTP over a period of 18 months. The date for commencement
of Stage 2 will normally be the date of Taking Over but may be delayed in agreement with
the Employer. During this Phase, the Contractor shall be responsible for any training needed
of his operations staff. However, no training of Waj staff is included in this Phase.
Phase 3: During the final 6 months of the O&M, the Contractor shall remain fully responsible
for the O&M of the WWTP as in Phase 2. In addition, the Employer shall assign O&M staff to
take over from the Contractor on completion of the O&M. During this period, the Employer’s
assigned staff shall be trained by the Contractor so that they will be able to take over
responsibility for operation of the plant at the end of the O&M.
The specified objectives shall be:
Achieving for the Employer an adequate human resource base through recognised
practices, skills, and incentives
Improving the skills base of the Employer’s assigned staff in the required areas of
expertise for the WWTP operations.
Achieving good operational performance through better management activity,
scheduling, and resource planning
Providing specific training in specialised equipment new to the Employer’s
assigned staff, including but not limited to the following:
- Aeration blowers
- Diffused air aeration systems
- Sludge digestion and gas production
- Gas storage and treatment
- CHP units
- Solar PV
- Energy production and management
Achieving reliable operation through scheduled procedures for:
- Preventive maintenance and monitoring
- Reactive maintenance
- Emergency procedures
Provide a basis to respond to organisational change
Establish procedures for procurement and stores handling for spares and
consumables.
Training programme:
Training shall be provided on site, both as formal instruction and “on the job” practice to
strengthen the following specific areas:
Personnel management
Wastewater treatment
Wastewater monitoring
Maintenance of pumps and mechanical equipment
Electrical maintenance
O&M Procedures
SCADA systems
Safe systems of work
Budgeting
Stores and handling
Database development
This on-site training programme shall be coordinated with off-site training to be arranged
through the WAJ.
Water Line
Structure-No. Description
Irrigation Water Storage Tank (Former Chlorine Contact
171 Tank)
180 Odour control unit of Waterline
185 Chlorination system
190 Service Water Station
The treated wastewater will be either reused for irrigation purposes or discharged into the wadi.
Sludge Treatment as anaerobic sludge digestion with mechanical sludge dewatering (sludge
line);
Sludge Line
Structure-No. Description
200 Primary Sludge Pumping Station
205 RAS/WAS Pumping Station
210 Gravity Sludge Thickener
211 WAS Storage Tank
212 Mechanical Thickening
215 Sludge blending tank
220 Anaerobic digester
230 Digested Sludge Tank
Sludge Treatment Building(Mechanical Thickening and
240 Dewatering)
241 Return Liquor Equalisation Tank
250 Sludge Drying Beds
260 Odour control unit for Sludge Treatment
270 Return Liquor Pumping Station
Digester Gas treatment and utilization by combined heat power generation (CHP) (Power and
Gas lines);
Gas/ Power Line
Structure-No. Description
310 Desulphurisation Unit
320 Gas holder
330 Gas Flare
340 CHP Generator
350 Boiler
Infrastructure with Public Utilities and Buildings.
Buildings
Structure-No. Description
400 Administration Building and Workshop
420 Standby Generator
430 Power Station
Sand filters
UV disinfection,Service Water Pumping Station
Emergency chlorination dosing
The sand filters are required for the removal of fine suspended solids which would otherwise disturb the
process of disinfection. The treated effluent is then collected by the effluent control manhole for effluent
quality monitoring and finally discharged to the Storage Tank.
The hydraulic calculations take into account the most unfavourable scenarios in each treatment unit:
The night flow velocity is calculated in all units to check minimum velocities;
The wet peak flow of at design horizon 2035isconsidered to check maximum velocities
The emergency case (one of the parallel units is taken out of operation) is simulated, as this
increases the hydraulic load on the other lines. In that case, flooding is to be prevented.
In the start-up phase, minimum velocities in pipes and channel are expected to be in the range of 0.3 to
0.5 m/s for the night or average flow. These velocities are low but are in the range of acceptable velocities
and the hourly peak flow will assure that all potential deposits are carried away once a day, especially
between the mechanical units (screens, grit chamber and primary settling tanks).
At peak flow, maximum velocities will not exceed 1.8 m/s in pipes and channels, thus minimizing hydraulic
losses.Inemergency cases (if one unit is taken out of operation), velocities of up to 2 m/s are considered to
be acceptable. On the water line, the water flows per gravity from the inlet to the outlet of the WWTP. No
intermediate pumping station is required, except for the RAS recirculation and the nitrate internal
recirculation. Downstream of the inlet works, the primary settling tanks, activated sludge tanks and
secondary sedimentations tanks are implemented in 2 distinct lines (Line 1 and Line 2). The elevations of
all units in Line 2 are set approximately 50 cm higher than the elevations of the units of Line 2.
Installed
Standby
Active
Rated power, Operating Operating Operating
Total
Duty
Active power Active power power
per unit factor factor hours
TAG Nr. Equipment consumption
Inlet Chamber
Overhead crane 1 1 0 5.00 0.90 4.50 1.00 4.50 365 1,643
Stormwater Tank
Stormwater return pumps 2 1 1 15.00 0.90 13.50 1.00 13.50 720 9,720
Screening Plant
Coarse screening conveyor 1 1 0 0.55 0.90 0.50 1.00 0.50 2,920 1,445
Screenings wash press 2 2 0 2.20 0.90 3.96 1.00 3.96 2,920 11,563
Fine screen conveyor 1 1 0 0.55 0.90 0.50 1.00 0.50 4,380 2,168
Screenings wash press 1 1 0 2.20 0.90 1.98 1.00 1.98 4,380 8,672
Grit and grease scraper 2 2 0 1.10 0.90 1.98 1.00 1.98 8,760 17,345
Installed
Standby
Active
Rated power, Operating Operating Operating
Total
Duty
Active power Active power power
per unit factor factor hours
TAG Nr. Equipment consumption
Inlet Measurement
Automatic sampler 1 1 0 1.00 0.90 0.90 1.00 0.90 365 329
PST scum pump 2 1 1 5.00 0.90 4.50 1.00 4.50 730 3,285
Installed
Standby
Active
Rated power, Operating Operating Operating
Total
Duty
Active power Active power power
per unit factor factor hours
TAG Nr. Equipment consumption
Primary sludge pump 3 2 1 3.00 0.90 5.40 1.00 5.40 1,460 7,884
Primary sludge pump 3 2 1 5.00 0.90 9.00 1.00 9.00 1,460 13,140
Anoxic tank mixer 8 8 0 1.50 0.90 10.80 1.00 10.80 8,760 94,608
İnternal recirculation pump 6 4 2 3.50 0.90 12.60 1.00 12.60 8,760 110,376
Modulating air control valve 4 4 0 0.37 0.90 1.33 1.00 1.33 730 972
FST channel cleaning brush 4 4 0 0.55 0.9 1.98 1 1.98 730 1,445
Filter Station
Filter backwash pumps 3 2 1 16.00 0.90 28.80 1.00 28.80 1,460 42,048
Air supply valve 4 4 0 0.25 0.90 0.90 1.00 0.90 730 657
UV Disinfection
Installed
Standby
Active
Rated power, Operating Operating Operating
Total
Duty
Active power Active power power
per unit factor factor hours
TAG Nr. Equipment consumption
Effluent Measurement
Automatic sampler 1 1 0 1.00 0.90 0.90 1.00 0.90 365 329
Installed
Standby
Active
Rated power, Operating Operating Operating
Total
Duty
Active power Active power power
per unit factor factor hours
TAG Nr. Equipment consumption
Odour Control Unit 1 (preliminary treatment) 1 1 0 0.75 0.90 0.68 1.00 0.68 8,760 5,913
Water circulation pumps 2 1 1 3.00 0.90 2.70 1.00 2.70 8,760 23,652
Gravity thickener scraper 2 2 0 0.55 0.90 0.99 1.00 0.99 8,760 8,672
Thickened primary sludge pump 3 2 1 4.00 0.90 7.20 1.00 7.20 2,920 21,024
WAS tank mixer 2 2 0 3.00 0.90 5.40 1.00 5.40 8,760 47,304
GBT feed pump 3 2 1 7.50 0.90 13.50 1.00 13.50 2,503 33,789
Gravity belt thickener 3 2 1 0.75 0.90 1.35 1.00 1.35 2,503 3,379
Polymer preparation unit (mechanical thickening) 1 1 0 0.10 0.90 0.09 1.00 0.09 2,503 225
Installed
Standby
Active
Rated power, Operating Operating Operating
Total
Duty
Active power Active power power
per unit factor factor hours
TAG Nr. Equipment consumption
Polymer suction blower 1 1 0 0.55 0.90 0.50 1.00 0.50 313 155
Polymer dosing pump (mechanical thickening) 3 2 1 0.05 0.90 0.09 1.00 0.09 2,503 225
Thickened WAS pump 3 2 1 3.00 0.90 5.40 1.00 5.40 2,503 13,515
Thickened sludge tank mixer 1 1 0 3.00 0.90 2.70 1.00 2.70 8,760 23,652
Anaerobic Digesters
Digester feed macerator 3 2 1 2.20 0.90 3.96 1.00 3.96 2,920 11,563
Digester feed pump 3 2 1 5.50 0.90 9.90 1.00 9.90 2,920 28,908
Digester mixing system 2 2 0 0.05 0.90 0.09 1.00 0.09 5,840 526
Gas injection compressors 4 2 2 30.00 0.90 54.00 1.00 54.00 5,840 315,360
Digester recirculation pump 3 2 1 4.00 0.90 7.20 1.00 7.20 7,300 52,560
Biogas desulphurisation system 1 1 0 6.00 0.90 5.40 1.00 5.40 8,760 47,304
Installed
Standby
Active
Rated power, Operating Operating Operating
Total
Duty
Active power Active power power
per unit factor factor hours
TAG Nr. Equipment consumption
Biogas booster blower 2 1 1 3.00 0.90 2.70 1.00 2.70 8,760 23,652
Siloxane removal system (future provision) 1 1 0 5.50 0.90 4.95 1.00 4.95 8,760 43,362
Cogeneration Station
Combined Heat & Power unit (CHP) 3 2 1 4.00 0.90 7.20 1.00 7.20 8,760 63,072
Emergency cooling fans 2 1 1 6.00 0.90 5.40 1.00 5.40 4,380 23,652
CHP heating pumps 3 2 1 2.20 0.90 3.96 1.00 3.96 8,760 34,690
Digester heating pumps 4 2 2 1.50 0.90 2.70 1.00 2.70 7,300 19,710
Desulphurisation heating pumps 1 1 0 0.55 0.90 0.50 1.00 0.50 1,460 723
Boiler Station
Boiler heating pumps 1 1 0 2.20 0.90 1.98 1.00 1.98 365 723
Digested sludge tank mixer 1 1 0 7.50 0.90 6.75 1.00 6.75 8,760 59,130
Belt filter press 3 2 1 4.00 0.90 7.20 1.00 7.20 2,920 21,024
Installed
Standby
Active
Rated power, Operating Operating Operating
Total
Duty
Active power Active power power
per unit factor factor hours
TAG Nr. Equipment consumption
Polymer preparation unit (mechanical dewatering) 2 1 1 0.20 0.90 0.18 1.00 0.18 2,920 526
Polymer suction blower 2 1 1 1.10 0.90 0.99 1.00 0.99 730 723
Polymer dosing pump (mechanical dewatering) 3 2 1 0.25 0.90 0.45 1.00 0.45 2,920 1,314
Sludge collection conveyor 1 1 0 5.50 0.90 4.95 1.00 4.95 2,920 14,454
Sludge distribution conveyor 1 1 0 5.50 0.90 4.95 1.00 4.95 2,920 14,454
Potable water booster pumps 2 1 1 4.50 0.90 4.05 1.00 4.05 2,920 11,826
Odour control unit 2 1 1 0 0.75 0.90 0.68 1.00 0.68 8,760 5,913
Water circulation pumps 2 1 1 3.00 0.90 2.70 1.00 2.70 8,760 23,652
3 CHP Calculations
Biogas (64%
Average Peak
CHP system CH4)
Loads Loads
Medium
Daily calorific energy load kWh/d 27268 34156
Total number of CHP units units 3 3
Number of duty CHP units units 2 2
Electrical efficiency selected % 40 40
Required operation time h/d 24 24
Electrical capacity required kW elec. 227 285
Electrical capacity selected kW elec. 300 300
Effective operation time h/d 18 23
Total biogas flow to CHP units Nm3/h 234 234
Thermal efficiency % 45 45
Heat generated kW therm. 675 675