Week 11 Earned Value Management
Week 11 Earned Value Management
Tutorial Week 12
180
Project management: from project
planning to project control
Plan
Project
Time Plan
Scheduling
Budget Control
Project
Cost Plan
Estimating
181
The S Curve
184
PV ( BVWS)
• Activity: “Trench excavation for utilities “ . (Critical)
0 7 10
Time
t
ES EF
• Activity duration 10 days; cost estimate $10K.
• Data date is 7, ( 7 days passing, by end of D7)
0 7 10
Time
t 10 d duration
$ 10 k cost
ES EF
= = $ 10k × 70% = $ 7 k
10k Vs.
Time
7d 10d
187
Plot PV vs. Time for the whole project
PV
Time
Budget at Completion
(BAC)
Time
(Project Duration)
189
PV ( BVWS)
• Activity: “Trench excavation for utilities “ . (Critical)
0 7 10
Time
t
ES EF
• Activity duration 10 days; cost estimate $10K.
• Data date is 7, ( 7 days passing, by end of D7)
(BVWC )
CPI = ( )
SPI = ( )
TCPI = ( )
At Data Date, which one do you need to forecast? Which ones are
given or derived.
195
Data Date
EAC
ETC
VAC
CV BAC
AC
SV
PV
EV
Time Line
TCPI vs. CPI
199
• At End of Day 3
TCPI
200
Dr. M. LU © 2015
1. Similar to variances, indexes help to compare planned progress with actual progress in project
control by applying EVM.
a) True
b) False
2. You have a project to be completed in 12 months. The budget for the project is $100,000. Six
months have passed, and $60,000 has been spent. On closer review, you find that only 40% of the
work has been completed to date. 50:50 credit rule applies as per the contract. What is the
project’s Earned Value (EV)?
a) EV = $30,000
b) EV = $50,000
c) EV = $40,000
d) None of the above
3. The amount of work that should have been done by a particular date is the --------------------.
a) PV
b) EV
c) ACWP
d) VAC
Prof. M. Lu copyright 2024 201
4. The ---------------------- specifies how much you are earning for each dollar spent on the
project.
a) SPI
b) CPI
c) TCPI
d) CV
5. Budgeted Cost of Work Performed (BCWP) and Earned Value are different.
a) True
b) False
6. What is the formula to calculate Earned Value?
a) EV = SV - PV
b) EV = AC + PV
c) EV = CPI*ACWP
d) EV = CV – AC
16 Which term represent the outstanding money required to finish the project?
a) EV
b) EAC
c) ETC
d) BAC
17 A project has EV = $500, AC = $550 and PV = $600. The overall project budget is $1,100.
Assume the project will continue to spend at the current CPI rate, what is the VAC?
a) -$160
b) $115
c) -$110
d) $110