Topic 5 Tutorial Questions
Topic 5 Tutorial Questions
Discussion questions
1 In the operation of a certain 15-station transfer line, the ideal cycle time is 0.58 min.
Breakdowns occur at a rate of once every 10 cycles, and the average downtime per
breakdown ranges between 2 and 9 min, with an average of 4.2 min. The plant in which
the transfer line is located works an 8-h day, 5 days per week. How many parts will the
line be capable of producing during an average week?
3 Solve Problem 2 using the lower-bound approach. What proportion of workparts are
removed from the transfer line?
The time to transfer between stations = 0.28 min. If the part stops due to a jam in the
line, it is removed as defective. It takes an average of 8 min to determine the fault and
6 In Problem 5 the cost of operating the transfer machine is $60/h, as estimated by the
accounting department of the company. It is proposed that a computer and sensors be
installed to aid in diagnosing breakdowns when they occur. The anticipated savings are
2 min off the 8 min to identify and correct the fault when it occurs. The computer will
have no effect on tool changes. The estimated cost of installing the monitoring system
is $11,000. How many units must the system produce to pay for the computer?
7 An eight-station transfer line has the following operations at each station; also given are
the processing time and the frequency of line stops for each station. During the
observation period there were 2000 parts completed.
____________________________________________________________________
____
Station Process Process time (min) Breakdown
____________________________________________________________________
____
1 Load part 0.40 0
2 Mill top 0.85 22
3 Mill sides 1.10 31
4 Drill two holes 0.60 47
5 Ream two holes 0.40 8
6 Drill six holes 0.90 58
7 Tap six holes 0.75 84
8 Unload part 0.50 0
____________________________________________________________________
____
Also influencing the cycle time is the operation of the transfer mechanism, which takes
0.15 min each cycle. When breakdowns occur, it takes an average of 7.00 min to
make repairs and get the line operating again. Assume that the upper-bound
approach is operative in your analysis for the following:
a) Determine the average production time per piece and the hourly
production rate for the transfer line.
b) What is the uptime efficiency of the line and the proportion downtime?
c) How many hours were required to produce the 2000 parts?
a) How many raw workparts would have started on the line to complete the
2000 parts?
b) How many parts would have been removed from the line as damaged due
to breakdown if 2000 parts were completed?
c) How many hours would have been required to produce the 2000
completed parts?
9 The APSCIM Machine & Foundry operates an automated transfer line with 12 stations.
The line is considered to have an efficiency that is unacceptably low. Below is a report
of a study on the current line operations. APSCIM would like to improve the efficiency
by making the following changes in the line:
This will document our two-week study of the APSCIM transfer line. The transfer
line was observed for a total of 80 hours (one shift per day). During this period, the
line was down for a total of 42 hours, and a total of 1689 parts were machined. The
following table lists the operation, the process time (in minutes), and the number of
downtime occurrences for each stations.
__________________________________________________________________________
Station Operation Process time (min) Number of downtimes
___________________________________________________________________________
1 Load (manual) 0.50 0
2 Rough mill top 1.10 15
3 Finish mill top 1.25 18
4 Rough mill sides 0.65 23
5 Finish mill sides 1.05 31
6 Mill surfaces for drill 0.80 9
7 Drill two holes 0.75 27
Second, divide the current line consisting of 12 stations into two stages, each
consisting of six stations. An in-process storage buffer would be used between the
stages so that each stage could operate as an independent transfer line. This is
expected to improve the overall production rate and line efficiency.
Determine the following:
a) The parameters of the line performance as it currently operates (without the improvements).
These should include the ideal cycle time, the frequency of line stops, the line efficiency,
and the average hourly production rate.
b) The effect of the two changes in the line operation described above. Determine the effect of
both changes together rather than each change separately. Your analysis should result in
an assessment of the line performance for each stage (ideal cycle time, the frequency of line
stops, the line efficiency, and the average hourly production rate). Also, determine the overall
performance of the two-stage system. In your analysis, assume the upper-bound approach.
Make any other additional assumptions necessary to solve the problem.
10 A partially automated flow line has a mixture of mechanized and manual workstations.
There are a total of six stations and the overall theoretical cycle time is 1.0 min. This
includes a transfer time of 6 s. The six stations possess characteristics as follows:
_______________________________________________________________________
Station Type Process time (s) Pi
_______________________________________________________________________
_
1 Manual 30 0
2 Automatic 15 0.01
3 Automatic 20 0.02
4 Automatic 25 0.01
5 Manual 54 0
6 Manual 30 0
____________________________________________________________________
12 The total work content time of a certain assembly job is 7.8 min. The estimated
downtime of the line is D = 5%, and the required production rate of Rp = 80 units/h.
13 A moving belt assembly line is to be designed for an assembly job that has a total
work content of 21 min. From consideration of human factors, the length of each
station will be 6.0ft. The belt speed is variable and can be set between 1.1 and 2.0
ft./min. The required production rate for the line must be 30,000 units/yr. (assume
2000 h of operation per year). From past experience on similar lines, the uptime
proportion of this assembly line (line efficiency), E is expected to be 95%. Production
management demands that the line be designed so that the balance delay d is
between 0.06 and 0.10, and the line must be designed for a balance delay within this
range.
a) Determine the number of stations that should be designed on the assembly line.
b) With good design practice in mind, determine the belt speed, spacing between
parts on the line, and the tolerance time to be used.
15 Solve Problem 14 using the Kilbridge and Wester method in part (c).