Program

The document outlines a project schedule for the construction of a new factory building, detailing various tasks, their durations, start and finish dates. Key tasks include mobilization, civil construction, steel construction, and finishing works, with a total project duration of approximately 122 days. The project is set to begin on May 1, 2022, and conclude with the handing over on August 30, 2022.

Uploaded by

silotaeng
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
4 views

Program

The document outlines a project schedule for the construction of a new factory building, detailing various tasks, their durations, start and finish dates. Key tasks include mobilization, civil construction, steel construction, and finishing works, with a total project duration of approximately 122 days. The project is set to begin on May 1, 2022, and conclude with the handing over on August 30, 2022.

Uploaded by

silotaeng
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ID TaskTask Name Duration Start Finish

Mode
April 1 May 1 June 1 July 1 August 1 September
4/18 5/2 5/16 5/30 6/13 6/27 7/11 7/25 8/8 8/22 9
1 NEW FACTORY BUILDING 122 days Sun 5/1/22 Tue 8/30/22
2 BUILDING A 110 days Sun 5/1/22 Thu 8/18/22
3 Mobilisation Works 1 day Sun 5/1/22 Sun 5/1/22
4 Site Preporation 4 days Sun 5/1/22 Wed 5/4/22
5 Civil Construction Works 106 days Thu 5/5/22 Thu 8/18/22
6 Excavation works 10 days Thu 5/5/22 Sat 5/14/22
7 Column Footings 14 days Sun 5/8/22 Sat 5/21/22
8 Column Shafts 10 days Sun 5/15/22 Tue 5/24/22
9 Rubble Masonry 10 days Sun 5/22/22 Tue 5/31/22
10 Plinth Beams 10 days Mon 5/30/22 Wed 6/8/22
11 Floor Concrete 5 days Thu 6/9/22 Mon 6/13/22
12 Block Masonry 14 days Fri 7/22/22 Thu 8/4/22
13 Plastering Works 14 days Fri 7/29/22 Thu 8/11/22
14 Painting Works 7 days Fri 8/12/22 Thu 8/18/22
15 Steel Construction Works 110 days Sun 5/1/22 Thu 8/18/22
16 Fabrication Works 35 days Sun 5/1/22 Sat 6/4/22
17 Steel Erection Works 25 days Thu 6/9/22 Sun 7/3/22
18 Roofing Works 18 days Mon 7/4/22 Thu 7/21/22
19 Cladding Works 28 days Tue 7/12/22 Mon 8/8/22
20 Fixing Flashing 15 days Sat 7/30/22 Sat 8/13/22
21 Gutter and Down Pipes 15 days Thu 8/4/22 Thu 8/18/22
22 BUILDING C 122 days Sun 5/1/22 Tue 8/30/22
23 Civil Construction Works 101 days Thu 5/5/22 Sat 8/13/22
24 Excavation works 7 days Thu 5/5/22 Wed 5/11/22
25 Column Footings 10 days Thu 5/12/22 Sat 5/21/22
26 Column Shafts 10 days Sun 5/22/22 Tue 5/31/22
27 Rubble Masonry 10 days Mon 5/30/22 Wed 6/8/22
28 Plinth Beams 10 days Tue 6/7/22 Thu 6/16/22
29 Floor Concrete 4 days Fri 6/17/22 Mon 6/20/22
30 Block Masonry 10 days Fri 7/22/22 Sun 7/31/22
31 Plastering Works 10 days Sat 7/30/22 Mon 8/8/22
32 Painting Works 5 days Tue 8/9/22 Sat 8/13/22
33 Steel Construction Works 121 days Sun 5/1/22 Mon 8/29/22
34 Fabrication Works 35 days Sun 5/1/22 Sat 6/4/22
35 Steel Erection Works 20 days Fri 6/17/22 Wed 7/6/22
36 Roofing Works 15 days Thu 7/7/22 Thu 7/21/22
37 Cladding Works 20 days Sun 7/17/22 Fri 8/5/22
38 Fixing Flashing 17 days Mon 8/1/22 Wed 8/17/22
39 Gutter and Down Pipes 17 days Sat 8/13/22 Mon 8/29/22

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline Slack


Project: Program
Milestone Inactive Summary Start-only Critical
Date: Fri 4/29/22
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress

Page 1
ID TaskTask Name Duration Start Finish
Mode
April 1 May 1 June 1 July 1 August 1 September
4/18 5/2 5/16 5/30 6/13 6/27 7/11 7/25 8/8 8/22 9
40 Handing Over 1 day Tue 8/30/22 Tue 8/30/22

Task Inactive Task Manual Summary Rollup External Milestone Manual Progress

Split Inactive Milestone Manual Summary Deadline Slack


Project: Program
Milestone Inactive Summary Start-only Critical
Date: Fri 4/29/22
Summary Manual Task Finish-only Critical Split

Project Summary Duration-only External Tasks Progress