Program
Program
Mode
April 1 May 1 June 1 July 1 August 1 September
4/18 5/2 5/16 5/30 6/13 6/27 7/11 7/25 8/8 8/22 9
1 NEW FACTORY BUILDING 122 days Sun 5/1/22 Tue 8/30/22
2 BUILDING A 110 days Sun 5/1/22 Thu 8/18/22
3 Mobilisation Works 1 day Sun 5/1/22 Sun 5/1/22
4 Site Preporation 4 days Sun 5/1/22 Wed 5/4/22
5 Civil Construction Works 106 days Thu 5/5/22 Thu 8/18/22
6 Excavation works 10 days Thu 5/5/22 Sat 5/14/22
7 Column Footings 14 days Sun 5/8/22 Sat 5/21/22
8 Column Shafts 10 days Sun 5/15/22 Tue 5/24/22
9 Rubble Masonry 10 days Sun 5/22/22 Tue 5/31/22
10 Plinth Beams 10 days Mon 5/30/22 Wed 6/8/22
11 Floor Concrete 5 days Thu 6/9/22 Mon 6/13/22
12 Block Masonry 14 days Fri 7/22/22 Thu 8/4/22
13 Plastering Works 14 days Fri 7/29/22 Thu 8/11/22
14 Painting Works 7 days Fri 8/12/22 Thu 8/18/22
15 Steel Construction Works 110 days Sun 5/1/22 Thu 8/18/22
16 Fabrication Works 35 days Sun 5/1/22 Sat 6/4/22
17 Steel Erection Works 25 days Thu 6/9/22 Sun 7/3/22
18 Roofing Works 18 days Mon 7/4/22 Thu 7/21/22
19 Cladding Works 28 days Tue 7/12/22 Mon 8/8/22
20 Fixing Flashing 15 days Sat 7/30/22 Sat 8/13/22
21 Gutter and Down Pipes 15 days Thu 8/4/22 Thu 8/18/22
22 BUILDING C 122 days Sun 5/1/22 Tue 8/30/22
23 Civil Construction Works 101 days Thu 5/5/22 Sat 8/13/22
24 Excavation works 7 days Thu 5/5/22 Wed 5/11/22
25 Column Footings 10 days Thu 5/12/22 Sat 5/21/22
26 Column Shafts 10 days Sun 5/22/22 Tue 5/31/22
27 Rubble Masonry 10 days Mon 5/30/22 Wed 6/8/22
28 Plinth Beams 10 days Tue 6/7/22 Thu 6/16/22
29 Floor Concrete 4 days Fri 6/17/22 Mon 6/20/22
30 Block Masonry 10 days Fri 7/22/22 Sun 7/31/22
31 Plastering Works 10 days Sat 7/30/22 Mon 8/8/22
32 Painting Works 5 days Tue 8/9/22 Sat 8/13/22
33 Steel Construction Works 121 days Sun 5/1/22 Mon 8/29/22
34 Fabrication Works 35 days Sun 5/1/22 Sat 6/4/22
35 Steel Erection Works 20 days Fri 6/17/22 Wed 7/6/22
36 Roofing Works 15 days Thu 7/7/22 Thu 7/21/22
37 Cladding Works 20 days Sun 7/17/22 Fri 8/5/22
38 Fixing Flashing 17 days Mon 8/1/22 Wed 8/17/22
39 Gutter and Down Pipes 17 days Sat 8/13/22 Mon 8/29/22
Task Inactive Task Manual Summary Rollup External Milestone Manual Progress
Page 1
ID TaskTask Name Duration Start Finish
Mode
April 1 May 1 June 1 July 1 August 1 September
4/18 5/2 5/16 5/30 6/13 6/27 7/11 7/25 8/8 8/22 9
40 Handing Over 1 day Tue 8/30/22 Tue 8/30/22