Interview Questions Civil
Interview Questions Civil
PART II
QA/QC
Civil Engineering
Interview Questions
Complete Study Notes
by D. Sourish
M.E. Construction Tech & Management
Civil Engineer | Educator | Encourager
Answer:
A chemical applied to the concrete surface to retain moisture and
prevent rapid drying. Alternative to water curing.
Answer:
Answer:
Damp Proof Course is a layer in building construction that
prevents moisture rising through walls and floors.
Answer:
Ground Granulated Blast-furnace Slag is a cement substitute
that improves durability, workability, and reduces heat of
hydration.
Answer:
To test and validate the compressive strength of the concrete
used in actual work.
59. How many samples are required for a concrete mix design?
Answer:
At least 15 cubes are typically prepared for various ages (7, 14,
28 days) as per IS 10262.
Answer:
A lab-produced concrete batch used to determine the right
proportions of mix ingredients before actual site use.
Answer:
Should not exceed 8% by volume (IS 2386 – Part II).
Answer:
Using a silt test bottle filled with salt water and sand. Let it
settle and measure silt as a percentage.
Answer:
Cubes should be cured in water at 27 ± 2°C as per IS 516.
Answer:
Answer:
Temporary structure to Mold concrete. Quality is checked for
alignment, leakage, surface finish, and tightness.
72. How do you test the bond between steel and concrete?
Answer:
By pull-out test or beam test to assess bond strength and
anchorage.
Answer:
The distance between reinforcement and the concrete surface,
protecting steel from corrosion and fire.
74. What is the minimum cover required for various elements (as
per IS 456)?
Answer:
• Slab: 15–20 mm
• Beam: 25 mm
• Column: 40 mm
• Footing: 50 mm
Answer:
Request for Inspection – A formal document submitted to
request inspection of completed activities before proceeding.
Answer:
A document listing minor pending works or defects to be rectified
before final project handover.
Answer:
Voids or gaps in concrete caused by improper compaction, leading
to weak zones and poor finish.
Answer:
• Vibrating adequately.
Answer:
Answer:
Non-Conformance Report – Issued when construction does not
meet specified requirements or standards.
Answer:
A method to identify the underlying cause of a defect or non-
conformance and implement corrective action.
Answer:
Answer:
Field Density Test (FDT) using sand replacement or core cutter
method to check soil compaction during backfilling.
Answer:
Answer:
To visually inspect and understand sub-surface soil and utilities
before excavation.
Answer:
As per IS codes, up to 6 mm per 3 m height is generally
acceptable.
Answer:
Water rising to the surface. Controlled by:
• Finer cement
• Use of admixtures
• Adequate compaction
Answer:
Limited by spacing — should allow proper compaction and cover;
IS 456 recommends minimum clear spacing = bar diameter or 25
mm.
Answer:
Answer:
A document that defines when inspections are to occur, their
methods, and acceptance criteria during each construction stage.
Answer:
A detailed document describing how specific construction
Answer:
A planned joint between two concrete pours, typically after a
work stoppage exceeding the initial set time.
Answer:
An unplanned discontinuity between two concrete pours due to
delayed placement, leading to weak bonding.
Answer:
Curing ensures proper hydration of cement, critical for strength
gain and crack prevention. Minimum 7 days (OPC), 10 days
(PPC).
Answer:
150 mm × 150 mm × 150 mm cube is standard for compressive
strength testing.
Answer:
A document outlining the quality management system, including
company policy, processes, and responsibilities.
Answer:
A by-product from thermal power plants used as a pozzolanic
material to enhance durability and reduce heat of hydration.
Answer:
99. What are the common QA/QC tests for fresh concrete?
Answer:
• Slump test
• Temperature test
• Air content
• Unit weight
• Setting time
Answer:
• Proper curing.
• Quality materials.
s
our
ish-
das
-0810
@The
Civ
il
Tal
es