Lecture Note 2 - Field and Office Computations
Lecture Note 2 - Field and Office Computations
Field computation in surveying involves calculating and processing data collected during
fieldwork to determine spatial measurements, coordinates, distances, elevations, and other
relevant information. These computations are critical for mapping, construction, and engineering
projects. Below is an overview of the key aspects of field computation in surveying.
Office computation in surveying involves processing, analyzing, and interpreting the data
collected during fieldwork to create accurate maps, plans, and reports. This step transforms raw
field data into meaningful outputs for construction, engineering, and land management projects.
1
Coordinate Method: Use point coordinates and formulas like the
Shoelace formula.
Trapezoidal Rule: Estimate area based on irregular shapes divided into
trapezoids.
Planimeter: Measure area directly on a plotted map.
4. Distance and Bearing Computations:
o Objective: Compute distances and bearings between two points.
o Steps:
Use Pythagoras' theorem to calculate horizontal distances:
2
Problem 1: A surveyor measures the angle of a line relative to the north-south axis using a
theodolite. Determine the WCB for each quadrant.
1.
Reduced bearings (RB) are expressed as angles from the north or south direction, followed by
east or west.
Steps to Convert:
Worked Example:
WCB = 50∘
3
WCB = 150°
WCB = 230°
WCB = 300°
Given coordinates of two points, A(x 1 , y 1)∧B( x 2 , y 2), the bearing can be computed using the
formula for the angle of a line:
−1 y2 − y1
θ=tan ( )
x2 − x1
Worked Example:
∆ y = y 2 − y 1=500 −200=300
−1 y2 − y1
θ=tan ( )
x2 − x1
−1 300
θ=tan ( )
200
−1
θ=tan (1.5)
= 56.31°
Since the line lies in the first quadrant (NE), the bearing is:
WCB = 56.31°
RB = N56.31° E
4
Problem:
A(100m, 200m)
B(300m, 500m)
Solution:
∆ y = y 2 − y 1=500 −200=300
Distance=√(200)2+(300)2
Distance=√ 40000+90000
Distance=√130000
Distance = 360.56m
When elevation (height) differences are considered, the 3D distance can be calculated using:
Problem:
Solution:
5
∆ x=x 2 − x 1=300 −100=200
∆ y = y 2 − y 1=500 −200=300
Distance=√132,500
Distance = 364.01m
If you are given a slope distance (S) and a vertical angle (θ), the horizontal distance ( Dℎ) can be
calculated as:
Dℎ =S × cos θ
Problem:
Solution:
Dℎ =200 m× cos30°
¿ 200 m× 0.8660
= 173.2m
5. Area Computations:
o Objective: Estimate earthwork volumes (e.g., cut and fill).
o Methods:
6
Cross-Section Method: Use cross-section profiles at regular intervals.
Grid Method: Subdivide the site into grids, calculate elevations, and
estimate volumes.
Volume computation in surveying is crucial for tasks like earthwork, excavation, embankments,
and land development. The volume is typically calculated based on the topographic data of the
area. Below are the most common methods used for volume computation, along with worked
examples.
This method assumes that the area between two sections forms a trapezoid.
Formula:
L
A= ( A1 + A2 )
2
Where:
Solution:
L
Area= ( A1 + A2 )
2
20 m
Area= ¿
2
Area=10. m׿ )
Area=10 m× ¿)
7
3
Area=800 m
2. Mid-Ordinate Rule
This method is commonly used when the boundary line is curved. It divides the area into strips
and measures the mid-ordinates.
Formula:
8
9
10
11
12
13
14
15
Summary of Methods and Applications
∆ x (Y 0 +4 Y 1+2 Y 2 +...+Y n )
Simpson’s Rule Irregular boundaries
❑
A= × Base ×Height
Division into 1 Triangular plots,
Triangles 2 irregular shapes
16
Elevation and Leveling
HI = BM + BS
Use: Calculate the height of the instrument based on the benchmark (BM) and back sight
(BS).
RL = HI − FS
Use: Determine the reduced level by subtracting the foresight (FS) from the height of the
instrument.
Manipulation: Rearrange to find missing values, e.g., HI=RL+FSHI = RL +
FSHI=RL+FS.
A surveyor is tasked with determining the elevations of several points (A, B, and C) in a field.
The elevation of a known benchmark (BM) is 100.000 m. Using a leveling instrument, the
surveyor records the following readings:
A - 2.000
B - 1.800
C - 2.200
Solution
17
1. Elevation of A = HI - Fore Sight (FS)
2. Elevation of A = 101.500 - 2.000 = 99.500 m
Results
BM 100.000
A 99.500
B 99.700
C 99.300
Key Points:
The Height of Instrument (HI) is the elevation of the instrument's line of sight.
The Back Sight (BS) is always taken on a point with a known or assumed elevation (like
a benchmark).
The Fore Sight (FS) is taken on the points to calculate their elevation relative to the HI.
A surveyor is tasked with determining the reduced levels (RLs) of points P, Q, R, and S using a
leveling instrument. The RL of a known benchmark (BM) is 100.000 m, and the following
readings are recorded:
Station Back Sight (BS) Intermediate Sight (IS) Fore Sight (FS) Remarks
BM 1.500 - - RL = 100.000 m
P - 2.000 -
Q - 1.800 -
18
Station Back Sight (BS) Intermediate Sight (IS) Fore Sight (FS) Remarks
R - 2.200 -
S - - 2.500
Solution
Using the collimation method, the Height of Instrument (HI) is first calculated and then used
to determine the RLs of the points.
HI =RLBM + BS=100.00+1.50=101.50
Results
Station BS IS FS HI RL Remarks
19
Key Points
Collimation Method:
Volume Computations
Volume of Earthwork
L
V = ( A 1 +4 A m + A2 )
6
Use: Calculate volume of cut/fill between two cross-sections, where L is the distance, A1
and A2 are end areas, and Am is the mid-area.
The formula for volume calculation using the trapezoidal rule is:
L
V = ( A 1 +2 A 2+ A 3)
2
Where:
V = Volume
L = Distance between the sections (50 m in this case)
A1 , A 2 , A3 =Cross Sectional Area
20
50
V= (25+2( 30)+28)
2
V =25(25+60+ 28)
V =25(113)
V = 2825m3
Final Answer:
Notes:
If the intervals between sections are irregular, the formula for the volume between two
sections is:
( A 1+ A 2)
V=A ×L
2
For more complex calculations, methods like the Prismoidal Rule can be applied if
cross-sectional areas vary significantly.
Given cross-sectional areas (in square meters) at regular intervals of 50 meters along a road
alignment:
Cross-section 1: A1=25 m2
Cross-section 2: A2=30 m2
Cross-section 3: A3 =28 m2
Use Prismoidal Rule to compute the volume of the section along the road alignment.
Solution:
L
V = ( A 1 +4 A m + A2 )
6
Where:
21
Am : Mid-section area (calculated as the average of A1 and A2 )
L: Distance between the sections (length of the prismoid)
(A 1 + A2 )
Am =A
2
(25+30)
Am =A =27.5m2
2
L
V = ( A 1 +4 A m + A2 )
6
50
V= (25+ 4(27.5)+30)
6
V =8.33(25+ 4(27.5)+30)
V =8.33(25+110 +30)
V =8.33(165)
V =¿1,374.45
V =¿1,375m 3
In surveying, calculating the rectangular (Cartesian) coordinates of a new station from a known
station involves using the known coordinates, the bearing (or azimuth), and the horizontal
distance between the two points. This process is fundamental in traverse computations, where a
series of connected lines form a framework for mapping and measurement.
22
2. Bearing or Azimuth (θ): The direction from Point A to Point B, typically measured
clockwise from the north direction.
3. Horizontal Distance (D): The straight-line distance between Point A and Point B.
∆ Y = Cos(θ)
∆ X = Sin(θ)
Note: Ensure that the bearing or azimuth (θ) is converted to radians if your calculator or
software uses radian mode.
1. Bearing Quadrants:
X B= X A +∆ X
Y B=Y A + ∆Y
Example Calculation:
Suppose you have a known station A with coordinates (200,300) meters. Determine the
coordinates of station B, which is 300 meters away from A at a bearing of N 42°30' E.
23
Convert Degrees to Decimal:
42°30' = 42.5°
π
θ=42.5 ° × =0.718radians
180
Additional Considerations:
Coordinate Transformations:
o Transform field coordinates to fit different systems or projections, often using
affine transformations or least-squares adjustments.
Example Problem:
24
Transform a point from a local coordinate system to a global coordinate system. The
transformation involves the following:
We need to compute the new coordinates (X′,Y′)(X', Y')(X′,Y′) in the global coordinate system.
25
o Least-Squares Adjustment: Minimizes the sum of squared errors for complex
networks.
o Check Measurements: Ensure accuracy by cross-verifying readings.
Applications
Mapping: Creating topographic or cadastral maps.
Construction: Ensuring accurate placement of structures.
Boundary Surveys: Determining legal land boundaries.
Engineering Design: Providing data for road, bridge, or building design.
26