Main+Clauses+and+SubMain+Clauses+and+Sub Clauses+of+FIDIC+Red+Book+ (1999+edition) +With+Examples
Main+Clauses+and+SubMain+Clauses+and+Sub Clauses+of+FIDIC+Red+Book+ (1999+edition) +With+Examples
1.1 Definitions
Purpose: Defines key terms used throughout the contract to ensure clarity.
Example: "Works" refers to the entire scope of construction works specified in the
contract.
1.2 Interpretation
Purpose: Rules for interpreting the contract. Defines the usage of singular/plural terms,
gender references, and language rules.
Example: The term “Engineer” is considered singular or plural depending on context,
meaning both an individual and a team of engineers.
Purpose: Identifies the official name and legal standing of the Employer.
Example: "The Employer is XYZ Construction Ltd., incorporated in the UK."
Purpose: Describes the Employer’s duties, such as providing access to the site, relevant
information, and approvals.
Example: The Employer must provide the Contractor with all necessary documents
related to the site’s existing conditions.
www.ipmtedu.com
2.3 Employer’s Representative
Purpose: Details how the Employer issues instructions to the Contractor, typically in
writing.
Example: The Employer issues an instruction via email requiring the Contractor to
change the material specifications.
Purpose: Specifies the Engineer’s role in overseeing the construction and their authority
to issue instructions and make decisions.
Example: The Engineer is authorized to approve drawings, inspect work, and provide
directions regarding the project’s progress.
Purpose: The Engineer may appoint a representative to assist in overseeing the project
on their behalf.
Example: The Engineer assigns an assistant engineer to conduct daily inspections and
report back on progress.
Purpose: Outlines the Contractor’s obligation to carry out the work as per the contract.
Example: The Contractor must execute the project in compliance with the Employer’s
design and schedule.
Purpose: Requires the Contractor to provide security for performance in case of default.
Example: The Contractor submits a bank guarantee of 10% of the contract price to
ensure performance.
www.ipmtedu.com
4.3 Subcontracting
Purpose: Specifies conditions for subcontracting part of the work, including Employer
approval.
Example: The Contractor subcontracts electrical works but seeks prior approval from
the Employer before proceeding.
5. Design (Clause 5)
Purpose: Specifies when the Contractor is responsible for designing parts of the work.
Example: In a design-build contract, the Contractor is responsible for designing the
structural elements of the building.
Purpose: Ensures the Contractor complies with local labor laws and provides fair wages
and benefits.
Example: The Contractor must pay employees in accordance with the local minimum
wage laws and provide health benefits.
www.ipmtedu.com
Purpose: The Contractor is responsible for maintaining a safe working environment.
Example: The Contractor installs proper scaffolding and provides safety helmets and
protective gear to all workers.
Purpose: The Contractor must ensure the quality of materials and plant used for the
project.
Example: The Contractor uses high-quality concrete and steel as per the project
specifications.
Purpose: The Engineer has the right to inspect materials before they are used.
Example: The Engineer inspects the steel beams delivered to the site to ensure they
meet specifications.
7.3 Workmanship
Purpose: Work must be carried out with proper craftsmanship and in line with the
contract’s requirements.
Example: The Contractor must ensure that all masonry is laid perfectly to specifications.
www.ipmtedu.com
8.4 Suspension
Purpose: The Employer may suspend the works under certain circumstances.
Example: The Employer suspends work for two weeks due to a safety concern.
Purpose: Specifies that the work must pass tests before final completion.
Example: The electrical system is tested to ensure it complies with safety and
functionality standards before the final handover.
www.ipmtedu.com
12.1 Definition of Force Majeure
Purpose: Defines events outside the control of both parties (e.g., natural disasters, war)
that can delay or prevent work.
Example: The Contractor can claim an extension of time if work is delayed due to a
natural disaster like a flood.
Purpose: Details the types of insurance the Employer and Contractor must obtain.
Example: The Contractor must maintain insurance against damage to the work, personal
injury, and worker’s compensation.
Purpose: Allows the Employer to terminate the contract under certain circumstances,
such as default by the Contractor.
Example: The Employer may terminate the contract if the Contractor fails to complete
the work within the agreed period, after giving appropriate notice.
Purpose: Allows the Contractor to terminate the contract under specific circumstances,
such as non-payment by the Employer.
www.ipmtedu.com
Example: The Contractor can terminate the contract if the Employer has failed to pay a
due amount within a certain period.
Purpose: Defines the situation where the Employer is in default, including failure to give
possession of the site, or failure to make payments.
Example: If the Employer does not provide the Contractor with access to the site, this
constitutes a default, entitling the Contractor to terminate the contract.
Purpose: Provides the Contractor with the right to suspend work if the Employer fails to
fulfill certain obligations.
Example: The Contractor has the right to suspend work if the Employer does not pay for
the work completed within the agreed time.
Purpose: Details the process for suspending work, including notification and
justification.
Example: The Contractor sends a written notice to the Employer explaining the reason
for suspension due to a delay in payments.
Purpose: The Contractor is entitled to payment for work carried out prior to suspension.
Example: If the suspension lasts more than 30 days, the Contractor can request
payment for work completed until the suspension was implemented.
Purpose: Specifies the process for resuming work once the suspension cause is rectified.
www.ipmtedu.com
Example: Upon payment, the Employer requests the Contractor to resume work within
7 days, after which work resumes as per the original schedule.
Purpose: Defines the method by which the work will be measured for payment
purposes.
Example: Work will be measured according to the "Standard Method of Measurement
for Building Works," which outlines how quantities and work quality are determined.
Purpose: Allows for adjustments in the contract sum based on changes in quantities of
work.
Example: If the Employer requires additional excavation, the contract price will be
adjusted based on the new quantity of work.
Purpose: Specifies that the Engineer will measure the work as it progresses.
Example: The Engineer measures the amount of concrete poured on-site and agrees on
the quantities for invoicing.
Purpose: Provides rules for evaluating work that is not measured in quantities, such as
lump-sum items.
Example: The Engineer evaluates the value of additional work, not previously priced,
and agrees on a rate with the Contractor.
Purpose: Allows the Employer to instruct the Contractor to make changes to the scope
of work.
Example: The Employer orders a variation to change the layout of the building, which
requires additional work and materials.
www.ipmtedu.com
Purpose: Outlines the procedure for valuing variations to the contract.
Example: The Engineer values the variation at a rate agreed upon for similar work, and
the Contractor is paid accordingly.
Purpose: The contract may include provisional sums for items not fully defined at the
time of the contract signing.
Example: A provisional sum of $50,000 is set aside for unforeseen works that may arise
during the construction process.
Purpose: Requires parties to provide timely notice of claims related to delays, additional
work, or other issues.
Example: The Contractor submits a notice of claim for additional time due to delays
caused by adverse weather conditions.
19.4 Arbitration
www.ipmtedu.com
Example: If a dispute over the contract price is unresolved through mediation, both
parties agree to submit the matter to arbitration as per the FIDIC rules.
Purpose: Specifies the law that governs the contract, typically the law of the country
where the project is located or the law agreed by the parties.
Example: The contract is governed by the laws of the United Kingdom.
Purpose: Specifies the language for the contract and how notices should be
communicated.
Example: The contract is written in English, and all notices must be sent via registered
mail or email to the addresses provided in the contract.
Purpose: States that the contract represents the entire agreement between the parties.
Example: Any previous discussions or agreements not included in the contract
documents are not legally binding.
21.1 Severability
Purpose: Ensures that if one part of the contract is found to be unenforceable, the rest
of the contract remains valid.
Example: If a specific clause is deemed unenforceable by a court, the remaining clauses
of the contract still apply.
21.2 Waiver
Purpose: Specifies that the failure of either party to enforce a provision of the contract
does not waive their right to enforce it later.
Example: If the Employer delays in issuing a notice but does so later, they can still
enforce the clause without losing the right to do so.
www.ipmtedu.com