Design of PSC T Bridge Abinash
Design of PSC T Bridge Abinash
INSTITUTE OF ENGINEERING
THAPATHALI CAMPUS
BY
HAMRO GROUP
Supervisor:
RAJAN SUWAL
April 2023
COPYRIGHT
The authors have agreed that the library, Department of Civil Engineering, Institute of
Engineering, Thapathali Campus, may make this report freely available for the inspection.
Moreover, the authors have agreed that permission for extensive copying of this report for the
scholarly purpose maybe guaranteed by the professors, who supervised the work herein or in his
recognition will be given to the authors of this report or the Department of Civil Engineering,
publishing for financial gain without permission of Department of Civil engineering, Institute of
Civil Engineering, Thapathali Campus, Thapathali and author’s written approval is prohibited.
Request for permission to copy or to make any other use of material in this report in whole or in
Head of Department
Thapathali Campus
Institute of Engineering
Thapathali, Kathmandu
i
TRIBHUVAN UNIVERSITY
INSTITUTE OF ENGINEERING
THAPATHALI CAMPUS
CERTIFICATE
This is to certify that this project work entitled “ANALYSIS AND DESIGN OF
PRESTRESSED CONCRETRE T-GIRDER BRIDGE OVER SISUWA KHOLA”
has been examined and declared successful for the fulfilment of academic requirement towards
the completion of Bachelor Degree in Civil Engineering.
…..………………………… …..…………………………
Er. Xyz
…..………………………… …..…………………………
Dr. Indra Narayan Yadav
External Examiner HOD, Department of Civil Engineering
ii
ACKNOWLEDGEMENT
We would like to sincerely thank everyone who assisted us in completing our final year project
on the topic of Analysis and Design of Prestressed T-girder bridge. The project could not have
been finished in this short amount of time without the tremendous support of all of you.
First of all, we would like to express our gratitude to Thapathali Campus for providing us with
oppurtunity to complete this project for our final year. We would like to specially thank Er.
Shakil Manandhar, our project supervisor, for leading us through our work and aiding in the
timely completion of our project.
Also, we are extremely thankful towards Dr. Indra Narayan Yadav (HOD), Er. Om Shanta
Maharjan (D-HOD) & other teachers, who laid foundations on structure during B.E. courses.
Finally, we would like to thank all the persons who helped us directly and indirectly in
completion of this report. We also acknowledge our gratitude towards each other for such a
united co- ordination amongst the group members during the project.
iii
ABSTRACT
The analysis and limit state design of the RCC T-Beam Bridge, its components and design of
superstructure of single span truss bridge has been incorporated in this report. Field observation
has verified the input data obtained from LRBSU. The data has been analyzed using a
combination of structural, hydraulic, geotechnical, and traffic engineering concepts. The bridge's
components have been designed according to relevant IRC codes of practice. According to the
limit-state design method, the superstructure components have been designed under dead load
and live loads considering IRC Class A and Class AA vehicles. The slab (cantilever and
restrained) has been analyzed using the effective width method, while the T-beam has been
analyzed using Courbon's method. The elastomeric bearing has been chosen and designed using
an Limit stress design method. Two similar abutments at each end and a hammer-headed pier
with Spread footing has been designed for basic and seismic load combinations. For the load
cases considered, the abutment's stability has also been examined. After the field visit, three span
bridge has been found suitable for the site according to the geometry of river flow. Architectural
and Structural drawings have all been used to display the final outcomes.
iv
SALIENT FEATURES
v
Contents
COPYRIGHT...................................................................................................................................i
CERTIFICATE................................................................................................................................ii
ACKNOWLEDGEMENT..............................................................................................................iii
ABSTRACT...................................................................................................................................iv
SALIENT FEATURES...................................................................................................................v
NOTATIONS...............................................................................................................................viii
ABBREVIATION.........................................................................................................................xii
1. Introduction..........................................................................................................................1
1.1 Background....................................................................................................................1
1.4 Objectives......................................................................................................................2
2. METHODOLOGY..............................................................................................................4
2.5 Drawing.........................................................................................................................6
3. ACQUISITION OF DATA...............................................................................................10
vi
3.1 Topographic Study and Engineering Survey...............................................................10
8.2 Analysis.....................................................................................................................148
8.3 Design........................................................................................................................159
vii
9.4 Foundation Shear Design..........................................................................................248
9.6 REFERENCES..........................................................................................................278
NOTATIONS
Op = Infiltration Coefficient
ui = index discharge
Qd = Design discharge
𝑆0 = Slope of River
Bed P = Wetted
Perimeter
R = Hydraulic Radius
viii
𝑞 = Discharge per unit effective
ix
dse = equilibrium scour below normal bed level
b = pier diameter
D = flow depth
α = opening ratio
µ = Poisson ratio
d’ = clear cover
S = Spacing
𝑟𝑢 = 𝑆ℎ𝑒𝑎𝑟 𝑆𝑡𝑟𝑒𝑠𝑠
𝑟𝑐 = 𝑠ℎ𝑒𝑎𝑟 𝑠𝑡𝑟𝑒𝑛𝑔𝑡ℎ
ɸ = Diameter of bar
x
B = Clear span of slab in transverse direction
xi
𝑚1, 𝑚2 = dead load
of vehicle
w = Intensity of loading
e = Eccentricity
xii
DLwc = Dead load of wearing coarse
xiii
DLas = Dead load of approach slab
direction
shrinkage
xiv
Fep(H) = Horizontal component of earth pressure force
xv
ABBREVIATION
xvi
QGIS: Quantum Geographic Information System
r.m.: Running Meter
RC: Reinforced Cement
RCC: Reinforced Cement Concrete
RL: Reduced Level
RM: Rural Municipality
RS: Restrained Slab
S.F.: Shear Force
S.N.: Serial Number
SP: Special Publication
Sq.: Square
SUM: Summation
TMT: Thermo-Mechanically Treated
UDL: Uniformly Distributed Load
WC: Wearing Course
WECS: Water and Energy Commission Secretariat
WSDM: Working Stress Design Method
TID: Transport Infrastructure Directorate
xvii
1. Introduction
1.1 Background
The bridge is an important element of land transportation system. A bridge is a structure that
conveys a service—such as traffic on a road or rail line, pedestrian traffic, or the use of public
utilities—over an obstruction, such as a river, a valley, or another road or rail line, and then
transfers the loads from the service to the foundations below. It is required to complete a real-
world project during the final year of the course in order to integrate the numerous civil
engineering topics covered during the undergraduate curriculum. The six membered team of
authors of this report have chosen the bridge design project for the fulfilment of degree to boost
all the knowledge area.
This report, which serves as the project's final deliverable, includes site selection based on
geotechnical data, bridge planning and design, type selection, hydrological and hydraulic design,
structural analysis and design of each component, preparation of working drawings, and a project
quantity estimate. The report was structured in accordance with the civil engineering
department's standard format. This report is also written in accordance with the fourth-year
second part syllabus for the Bachelor of Civil Engineering as part of the project work to
complete Project-II.
This project is under jurisdiction of Department of Local Infrastructure and consulted by Local
Roads Bridge Support Unit (LRBSU). With the help of LRBSU's financial and technical
assistance, this project was successfully completed. The funding source paid for every expense
incurred in finishing this project's work. Through LRBSU, the geotechnical investigation report,
topographical survey report, and geotechnical and hydrological guidelines were obtained. All
other data were used as provided, and the topographical data were validated by a short site
survey.
In this project, it was assigned to design a bridge over Sisuwa Khola which provides a link
between village Haripur left of the river with right to the river in Udayapur district. This bridge
is along Laalbazar Uchalne Road. As it is a local road, so a single lane bridge shall suffice. But
as per the provisions in Nepal Road Standards (a minimum of 6 m carriageway for bridges
1
longer than 50 m), the bridge will be designed as a two-lane bridge (intermediate lane). The
designers
2
were supposed to design the most economic bridge for this section as per the data provided by
LRBSU.
The key output of this project is the design of bridge and its working drawing. All of the bridge
components have been designed and verified using the limit state design method, as well as the
working drawing and details of the bridge across Sisuwa Khola, Udayapur is included in this
report. Therefore, this project is entitled as “Analysis and Design of PSC-T-Girder Bridge over
Sisuwa Khola Bridge”.
In this project, following assignments has been completed during the completion of the project.
1.4 Objectives
This project has been carried out towards the partial fulfilment of bachelor's degree in civil
engineering as final year project work mandated as per syllabus of Institute of Engineering.
This project has been carried out for achieving following objectives
3
▪ To select bridge site based on topographical, hydrological, and geotechnical data
▪ To select suitable bridge type and span arrangement
▪ To plan, analyze, design and detail each component of bridge
▪ To prepare working drawing of all components of bridge
▪ To prepare quantity estimate of various item of work
▪ To recommend any river training works or other site related works (their design is
not considered)
This project work includes acquisition of topographical, geotechnical, and hydrological data
from LRBSU, site visit and verification of bridge data by limited site works. The hydrological,
hydraulic, and geotechnical design are entirely based on these data. The structural planning,
design, and detailing are the key works of this project. Preparations of working drawing and
quantity estimate have been carried out based on the design.
The planning and design of river training, slope protection, or any other site related works are out
of the scope of this project and should be carried out separately.
4
2. METHODOLOGY
Topographic map, engineering features and geological state of river bed, river cross section, river
orientation and hydrological data are essential for bridge design and analysis. The topographic
and geological data used in subsequent stages of the report have been obtained from LRBP's
topographic and geotechnical report. DHM provided the rainfall data required in the hydrological
analysis of the bridge site. The project team has not been involved in any direct data
measurement. Important parameters such as the position of the bridge axis, the HFL, the width of
the stream along the HFL, and the cross section of the river have all been verified in the field.
Two alternative designs for the bridge superstructure have been designed. Taking into account
waterway requirements, geological conditions of the river-bed, and provisions in the codes
stated below, first alternative consists of three T-girder systems with three spans. Bearings and
sub- structures has been designed for T-girder superstructure only. Sub-structure has been
planned as two abutments at the river bank and an intermediate pier at mid-location. After a
thorough analysis and study of previous reports, existing design manuals, literature, and existing
codes, preliminary design of various bridge components has been completed. Various codes that
have been used for preliminary design of PSC bridge are listed below:
● IRC 5: 2015 General Features of Design
● IRC 6: 2014 Loads and Stresses
● IRC 21: 2000 Concrete Bridge
● Nepal Bridge Standards: 2067
● Standard Specification of Roads and Bridges, Government of Nepal, Ministry of Physical
Planning and works, Department of Roads
● IRC 83: 1987(Part II) Elastomeric Bearings
● IRC 78: 2000 Foundation and Sub-structures
5
● IRC 24: 2010 Steel Road Bridges
● IS 456: 2000 Plain and Reinforced Concrete - Code of Practice
● IS 800: 2007 General Construction In Steel
● IS 808: 1989 Dimensions For Hot Rolled Steel Beam, Column, Channel and Angle
Sections
● IS 2911: 1980 (Part 3) Code of Practice for Design and Construction of Pile Foundations
● IS 1367: 2002 (Part 3) Mechanical Properties of Fasteners Made of Carbon Steel and
Alloy Steel - Bolts, Screws and Studs
Initially, the idealization of loads, structural components, and support conditions has been done.
Following that, numerous bridge components like deck slab, girders, bearings, etc. has been
analyzed for the load combinations given in relevant IRC codes. The following responses have
been calculated: longitudinal and transverse bending moments, shear force, and axial forces.
The following approaches have been used to evaluate the bridge:
● Influence line diagram (longitudinal placement of live load for maximum response)
● Effective width method (analysis of cantilever slab)
● Pigeaud’s method (analysis of restrained slab)
● Courbon’s method (transverse distribution of load to main girder)
Limit state design method has been used in the design of structural components for bridges.
Working state design method has been used to design the elastomeric bearing, which has then
been checked for limit state design. For the design and detailing of bridge components, the
following codes has been used:
● “IRC 06:2017 (Section II) Loads and Load Combination” has been followed to compute
all the live and dead loads with load factors for different load combinations in different
components.
6
● "IRC 21: 2000 Standard Specifications and Code of Practice for Road Bridges,
Section: iii Cement Concrete (Plain and Reinforced)" and "IS 456:2000 Plain and
Reinforced Concrete - Code of Practice" have been used to design components of
superstructure.
● In addition, IS 456 (SP16) and IRC SP114:2018 have also been used.
● “IRC 78-2014 Substructure and Foundation" has been used to design substructure
components.
● "IRC 83:1987 Elastomeric Bearing" has been followed for working stress design of
elastomeric bearing which has then been checked by 2018 version of same code which is
based on limit state design method.
● Provisions in “IRC 112:2018” has been followed to comply the design with seismic
resistant design method. Moreover, detailing of pier has been specially considered to
localize the formation of plastic hinge at the base of pier.
● "IRC 112:2018 Code of Practice for Concrete Road Bridges" and "IRC SP114:2018
Guideline for Seismic Design of Road Bridges" have been followed for ductile detailing.
● “IRC 24:2010 Standard Specifications and Code of Practice for Road Bridges Section
V Steel Road Bridges (Limit State Method)” and “IS 800:2007 General Construction In
Steel – Code of Practice” have been followed for design of superstructure of truss.
2.5 Drawing
Plan, sectional and detailed drawings of various components of bridges have been prepared in
standard scale.
The detailed drawings prepared on standard sheet with dimensions have been used to determine
the quantities of the items of the bridge structure. The quantity of deformed bar required has
been estimated based on the bar bending schedule. Several jobs, such as earthworks and
concrete, have been assessed in cubic meter. Railing bars have been calculated in running meter.
Jobs that aren't directly related to the project, such as land acquisitions and site clearing, haven't
been estimated.
7
2.7 Project Work Report
This project work report has been created in accordance with the Department of Civil
Engineering's specifications. In the format specified below, this report includes all important
theories, methodologies, processes, data inputs, observations, calculations, and design outputs as
per the scope of our project work.
2.7.1 Introduction
This part of the report discusses nature of project work, project site, roles and responsibility of
designer, project assignment, project objectives and client requirements.
2.7.2 Methodology
This part is devoted to the principles, methods, theories, procedures, design basis, norms, and
standards, used for acquisition of design data, planning and preliminary design, idealization and
analysis of bridge structures, design, detailing, and drawing.
This part is concerned with topographical study and engineering survey, geological and
geotechnical study, hydrological study and traffic study carried out for acquisition of design data.
The field observation and data verification along with hydraulic and geotechnical design of
bridge is also included.
This part of report includes overall planning of bridge, selection of bridge deck, arrangement of
bridge component, preliminary sizing of slab, main beam and cross beam. It also contains
material selection and their properties.
8
2.7.5 Analysis and design of bridge components
In this part of the report, analysis, design, and detailing of slab (restrained and cantilever), main
beams (end and intermediate), cross beams (end and intermediate), bearing, substructures
(abutment, pier, seismic stopper, and foundation) for different load combination is presented.
At the last sections of the report, all the architectural drawings and structural drawings of each
component is presented.
9
Project Initiation
Data Acquisition
No
Is Yes
Field Visit & Data
Data
Verification
Sufficient?
Recommend Further
Original Data
Geotechnical Design
Selection of Bridge
Preliminary Sizing
Is
Original Size
Ok?
Design data provided by MLRBP have been adopted for the design of bridge. The topographical
survey was carried out by joint venture of Beam consultant Pvt. Ltd., Impulse consultants Pvt.
Ltd., and Smart engineering and design solutions Pvt. Ltd (BEAM-IMPULSE-SEDS JV).
10
Figure. Proposed Bridge axis (source: Google Earth)
3.1.2 Topography
The site is located at Belaka Municipality-6, Uchalne, Udayapur which is a part of Terai region
of Nepal which is also a part of the Gangetic plains. The geological formation of the Terai is
quaternary alluvial river deposits of boulders, gravels, sands, silts and clays. The project site is in
a plain area having alluvial deposits with silty sands in their textures with gravels, pebbles and
boulders traces in the vicinity of the site. The deposits are in medium denseness in state.
Cross section of the river was provided by the MLRBP. This flow depth and cross section of the
river was verified at site using various survey instruments and engineering techniques. So, this
verified cross section has been used for the design.
11
Reduced level
0
2.658
3.875
7.692
10.392
13.797
19.417
27.851
31.496
37.783
43.321
50.212
57.751
62.495
67.223
73.546
78.035
83.624
90.069
96.972
102.336
103.839
105.064
Distance
N.S. Engineering & Geo-technical Services Pvt. Ltd. carried out detailed subsurface
investigation studies at the proposed bridge site, and LRBSU provided the necessary data.
Boring, SPT tests, laboratory tests, and analysis of different test findings were used to
determine the allowable bearing capacity of existing soils at the bridge site. From the
results shown in the safe bearing capacity as well as test, it is recommended that:
i) The borehole log indicates the presence of Boulder and Gravel with little sands
throughout the drilled depth.
ii) The water table is found at the depth of 1m in BH-1, 1.5m in BH-2 and 1.8m in BH-3
from surface of the bank of the river during the drilling work, but may vary from season
to season.
iv) The allowable bearing capacity of various foundation at varying depths are mentioned
in this report. The recommended maximum allowable bearing capacity is limited to 400
KPa.
v) An average D50 value for BH-1 up to the depth of 1.5m is 5mm. Similarly, in BH-2,
average D50 value is 50mm up to depth of 1.5 m, and average D50 value is 22mm for
12
BH-
13
3 up to the depth of 1.5m. The actual dmean (for calculation of scour depth) should be
determined from pit excavation, which is not covered under the scope of the drilling
company. Hence, with reference to sieve data mentioned here and annex part if the report,
it is recommended that the hydrologist should use his own judgement to adopt a suitable
value.
vi) For backfill with a relative density greater than 70%, a friction angle of 30 degrees can
be adopted.
The hydrological data of the catchment area is in the form of annual precipitation data acquired
from DHM provided by MLRBP. Hypsometric data of the catchment has been deduced from
Google Earth. The design is primarily based on the provided data and relevant assumptions
wherever necessary. The site visit was done at early stage of the design and the field
observations data have been attached at the end of this part.
The bridge site in Sisuwa Khola is located at Latitude of 26°50'19” N and Longitude of 87°01'00”
E. The outlet elevation of Khola at bridge site is about 167 m (from Google Earth) and the
elevation of headwater (Highest Point) is about 1054 m. The catchment area up to bridge site
estimated by GIS and Google Earth is about 14.26 sq.km and main channel length is about 6.515
km. The catchment delineated by Google Earth is presented below in Photo 1(a) and that from
GIS in Photo 1(b).
14
(source: Google Earth)
Figure. Catchment of Sisuwa Khola at proposed bridge site from Google Earth
Stream
Catchment Highest Lowest
Length, Stream slope %Concentration Time tc, hours
Area, km2 Point, m Point, m
km
15
Catchment area under different land use
Coverage type
No any meteorological stations have been found to lie within the catchment of the bridge site.
However, according to the data available in the website of DHM, about 3 meteorological stations
have been found to be situated in the periphery of the catchment. Among the stations with
available data, only 2 stations have been found to have certain weightage in Thiessen Polygon
Method using GIS.
16
Figure. Thiessen Polygon Using GIS
Total A = 14.2609
Rational Method
Average (X)=
Triveni Chatara
(R1×A1+R2×A2)/ (Xi-µ)2
(R1) (R2)
A
169 203 186.110 2253.818
403 231 316.441 31614.681
100.1 286.4 193.855 3049.155
128.5 86.45 107.338 979.544
168.9 189.5 179.267 1650.867
140 151.2 145.636 49.005
113 141.8 127.494 124.155
84.9 200.2 142.925 18.391
17
123 147.2 135.179 11.954
50 130 90.260 2340.254
103 94.1 98.521 1609.211
100.4 113.2 106.842 1010.889
139 141.1 140.057 2.019
112 214.2 163.432 614.839
123 105 113.942 609.820
116 209.3 162.953 591.318
123 140.5 131.807 46.638
145 139.1 142.031 11.524
70 135.5 102.963 1272.583
168 170.5 169.258 937.710
100.1 252.9 176.996 1471.514
106.3 180.3 143.540 24.052
148 89.5 118.560 403.050
66 98.2 82.205 3184.509
165 116 140.341 2.906
90 147.8 119.088 382.136
102.2 115.3 108.793 890.635
92 140.1 116.206 503.096
95 141.4 118.351 411.495
61 123 92.201 2156.177
82.2 167.5 125.127 182.492
∑(Xi-µ)2 = 58410.438
∑(Xi) =
4297.718
n = 31
18
Standard Deviation ( ) = ∑(Xi-µ)2 /(n-1) = 58410.438/(31-1) = 44.125 mm
X100 = µ + K100 ×
= 138.636 + 3.6409 × 44.125
= 299.2907 mm
= 36.2805 min
= 0.6047 hrs
19
I = (X100 /24) × (24/tc)2/3
= (299.2907/24)×(24/0.6047)2/3
=145.098 mm/hr
Q= CIA/360
= (0.1196×145.098×14.2609×100)/360
= 68.74 m3/s
WECS Method
Water and Energy Commission Secretariat has published a regional hydrological analysis report
according to which the flood flows in any river of catchment area below 3000m of elevation, is
given by
Q100 = 14.63×(A3000+1)0.7342
Where the subscript 100 stands for the return periods in number of years
DHM 2004
The formula for 100-year return period is given by
Q100=20.7(A3000)0.72
where,
Q is design flood in (m3/s)
A3000 is basin area(km2) below 3000m
m3/s
20
Modified Dickens’s Method
Modified Dicken’s method is an empirical one where the peak discharge is given by:
Qpeak= CT × A 3/4
Where,
CT = 2.342×log10(0.6T) ×log10(1185/P) +4
P = 100(As+6)/(A+As)
Then,
P= 100(0+6)/(14.2609+0) = 42.073
CT=2.342×log10(0.6T) ×log10(1185/P) +4
= 2.342×log10(0.6×100) ×log10(1185/42.073) +4
= 10.037
Fuller’s method
Q = Cf ×A0.8(1+0.8log10T)
Where,
A = 14.2609 sq. km
Then,
Q = 1.45 × 14.26090.8(1+0.8log10(100))
= 31.598 m3/s
Ryves Formula
Qp = CR x A2/3
Where,
S.N
Method Used Calculated Discharge, Q (cumecs)
.
22
Among six methods, highest value of discharge obtained from DHM 2004 has been used as
design discharge.
Hydraulic Design
HFL Calculation
HFL has been calculated on trial and error basis using available cross-section and assuming HFL.
Assuming a numbers of HFLs and calculating discharge at those HFLs using AutoCAD, the
following curve has been obtained:
Stage n S A P R Q
0.03
149 0.02103 0.26364 3.47645 0.07584 0.207567318
3
0.03
149.1 0.02103 0.75096 6.64277 0.11305 0.771554479
3
0.03
149.2 0.02103 1.58279 10.0523 0.15746 2.028159713
3
0.03
149.3 0.02103 2.89751 15.2004 0.19062 4.217382433
3
0.03
149.4 0.02103 4.50907 17.7323 0.25429 7.953170465
3
0.03
149.5 0.02103 6.31636 19.1488 0.32986 13.25121595
3
0.03
149.6 0.02103 8.321 21.1491 0.39344 19.63377909
3
23
0.03
149.7 0.02103 10.5238 23.4751 0.4483 27.08862722
3
0.03
149.8 0.02103 12.9167 25.0055 0.51656 36.54296121
3
0.03
149.9 0.02103 15.4965 26.8895 0.5763 47.1600393
3
0.03
150 0.02103 18.2652 28.9079 0.63184 59.10220459
3
0.03
150.1 0.02103 21.2531 31.212 0.68093 72.28746893
3
0.03
150.2 0.02103 24.47 33.5162 0.73009 87.18825168
3
0.03
150.3 0.02103 28.0515 37.1612 0.75486 102.1974736
3
0.03
150.4 0.02103 31.8851 40.419 0.78886 119.6266631
3
0.03
150.5 0.02103 43.7021 78.1215 0.55941 130.3855581
3
0.03
150.527 0.02103 45.8122 78.7541 0.58171 140.2893676
3
0.03
150.6 0.02103 51.6018 80.4645 0.6413 168.6338136
3
0.03
150.7 0.02103 59.7338 82.8074 0.72136 211.1345417
3
0.03
150.8 0.02103 73.4004 108.91 0.67396 247.9468705
3
0.03
150.9 0.02103 84.3204 110.027 0.76636 310.3091842
3
0.03
151 0.02103 95.3255 110.872 0.85978 378.7667648
3
24
Rating Curve
151.5
151
150.5
Stage (m)
150
149.5
149
148.5
0 50 100 150 200 250 300 350 400
Discharge (cumecs)
Assuming HFL at 150.527 m and using AutoCAD, the following parameters has been
𝑃 78.7541
0
× (0.58171)3 × (0.02103)2 =
𝑛 0.03
= 3
3.062269317 m/s
However, surveying was carried out in site during site visit to check the provided data and
suitability of calculated HFL and the HFL in present condition was found to be 150.558 m. In
this scenario, as the observed HFL is more than that calculated above, observed HFL has been
taken as design HFL for the bridge design.
25
Reduced level
0
2.658
3.875
7.692
10.392
13.797
19.417
27.851
31.496
37.783
43.321
50.212
57.751
62.495
67.223
73.546
78.035
83.624
90.069
96.972
102.336
103.839
105.064
Distance
Lacey's Formula
As per the clause 106.5.1.10, IRC 05: 2015, the waterway, as worked out from the formula or
decided otherwise, should be compared with linear waterway at HFL corresponding to the design
flood discharge. The linear waterway at HFL (150.558m) has been found to be 78.463m from
AutoCAD.
26
Check for afflux
The afflux is measured by difference in levels of water surfaces upstream and downstream of
bridge after the construction of structure, which can be calculated by following formula:
𝐷𝑖𝑠𝑐ℎ𝑎𝑟
𝑉 = 𝑣𝑒𝑙𝑜𝑐𝑖𝑡𝑦 𝑜𝑓 𝑛𝑜𝑟𝑚𝑎𝑙 𝑓𝑙𝑜𝑤 𝑖𝑛 𝑡ℎ𝑒 𝑔𝑒
𝑠𝑡𝑟𝑒𝑎𝑚 =
𝐶𝑟𝑜𝑠𝑠 − 𝑠𝑒𝑐𝑡𝑖𝑜𝑛𝑎𝑙 𝑎𝑟𝑒𝑎
140.26 𝑜𝑓 𝑓𝑙𝑜𝑤
7
=
45.812
2
= 3.062m/s
∴ Afflux, h= 0.2766m
Freeboard
As per Hydrological guidelines, minimum freeboard (vertical clearance) between the HFL and
the elevation of the lowermost part of the bridge superstructure is taken as 1.5m for Nepal.
Hence, freeboard of 1.5m has been provided.
28
i.e., d50 = 2mm
Laceys Formula
Maximum scour depth for abutment = 1.27 × dsm = 1.27 × 1.654 = 2.1006 m
2 HFL 150.558 m
4 Afflux 0.2766 m
5 Freeboard 1.5 m
29
3.4 Traffic study Data
The traffic statistics for the design have not been included during the planning of lane width and
any other traffic component of the bridge since the project site is a rural roadway without a
system for tracking traffic volume. The minimum carriageway width for agricultural roads
should be 6m, according to Nepal Rural Road Standard 2071. So, the bridge has been designed
to have a clear carriageway of 6.0m width.
As stated before, the site visit has been conducted at early stage of hydraulic design. As field
verification is mandatory for design, it has been possible to correlate the outcomes of the field
30
visit
31
data with the later design stages. And the assumed parameters have been checked with the out
comings of the site visit and everything seems as expected.
Observation over the upstream to 300m and downstream to 200m from the bridge axis was done.
The river has banks with boulder on both sides throughout the observed upstream and
downstream length of river. At the survey time, the streams from upstream were combined below
downstream near proposed bridge site to form single river course and the topography of the site
shows that there is no possibility of change in course of river. People travel through river during
dry season but during wet season transportation becomes very challenging. We could observe
boulder and gravel with little sands on the river.
The approach road, which is a part of Beltar-Besaha Road Alignment, is a bumpy earthen road.
At the time of survey, the approach road is not linked directly to the bridge axis. The existing
roads are connected across the river bed to allow the transportation of excavator and other
construction machines and equipment. The road connects Haripur and Uchalne in Udayapur
district.
32
4. SELECTION OF BRIDGE TYPE
The selection for the type of bridge is governed by the geography of site, loading, aesthetics and
the cost incorporated in its design and construction. Based on these main factors, following
alternatives have been developed:
The log of boreholes at both left and right banks of the river shows very dense sandy silty
Gravels and Boulders at depth below 8m from surface, which provides an unyielding foundation
for building the abutments for arch bridge on both banks. In addition, arch bridge is suitable for
major bridge of span 105m.
Construction of Steel Truss Bridge is also feasible in the location suitable for construction of
Arch Bridges. Since, no greater vertical clearance is possible below the bridge while selecting
deck type Truss Bridge, through-type Steel Truss Bridge can be one of the best alternatives.
The log of borehole at center of river cross section shows presence of very dense sandy silty
Gravels with Boulders at any depth below the surface, which provides appropriate foundation for
laying a pier at center. Also, simplicity and economy in design and construction of two span RC
T-girder bridge makes it one of the best alternatives.
Three Spans: Two spans of RC T-girder 15m each with middle span of Steel Truss type of
20m
Longer span of T-girder Bridge as mentioned above would exert larger loads on the pier and
make it unstable. So, introducing an additional pier and providing steel truss type span at middle
33
span of
34
20m will decrease the load on each pier and make it more stable. Also, this type of bridge and
span arrangement allows the operation of heavy loaded vehicles.
Although construction expenses are costlier than RCC type, it can be one of the alternatives as it
offers less construction time, higher durability, better rider serviceability, and higher strength-
weight ratio.
Being light in structure and offering higher stiffness, higher resistance to seismic and cycle
loading, it is also one of the possible alternatives as it reduces foundation depth and decreases
cost of construction.
Among the possible alternatives, PSC T-Beam Bridge of 35m span has been chosen for the
design considering economy and ease in construction.
35
5. BRIDGE TYPE AND PRELIMINARY DESIGN
PSC T-Beam Bridge of 70m with two span each of 35m has been proposed for the site.
Considering the overall economy and design requirements along with available construction
technologies, recent construction practices, and available and applicable literatures, following
materials have been selected for the design of super structure in this project:
Properties of Concrete
Permissible bearing stress = 0.25𝑓𝑐𝑘 (Working stress method) and 0.45𝑓𝑐𝑘 (Limit
state method) = 0.45 × 30 = 13.5 N/mm2
36
Properties of TMT steel
The preliminary sizing of various components of superstructure has been performed as per IRC
05: 2015, IRC 21: 2000, NRRS-2071, NBS-2067 and other standards as follows;
Wearing Coat:
Asphalt concrete type wearing coat with thickness 50mm@edge and 132mm@Crown resulting
2.5% camber has been provided.
Minimum height of railings above the adjacent roadway or kerb surface = 1.1m
Provide RC railing post of 175mm × 175mm × 1100mm @1750mm c/c spacing (i.e 21 in
numbers per span in each side)
Provide 3-48.5mm diameter GI heavy steel pipe rails @4.37kg/m, thickness 4.0mm.
37
Footpath:
Width of Footpath:
Width of Kerb = Projection + Width of railing post + Minimum clearance from post
= 0.475m
Adopt total width of Kerb = 0.85 m with clear Kerb width of 0.6m.
Height of Footpath:
Drainage Spout
Slab Deck
Depth at the tip of the cantilever part can be reduced up to 50.0mm than that of intermediate part.
So, minimum depth of slab at tip of cantilever part =200.0mm.
Provide deck slab depth of 250.0mm at intermediate part and 250.0mm at cantilever part.
Main Girder
Minimum thickness (width) of the web = 300 mm
Provide width of web, bw = 300 mm
Cross Girder
39
Number of cross girders: Provide 5 numbers of cross girders
𝑆𝑝𝑎𝑛
𝑁𝑜.𝑜𝑓 𝑐𝑟𝑜𝑠𝑠 𝑔𝑖𝑟𝑑𝑒𝑟𝑠 –1
Spacing of cross girders =
There are two cantilever slabs on either side of two main girders at the edge. Both of the
cantilever slabs are similar/identical in terms of support conditions, loadings, materials and
dimensions. For the analysis of cantilever slab, effective width method has been used. Design is
based on Limit State Design Methods of IRC 112:2000.
For unit width of cantilever slab, dead loads considering self-weight of slab, railing (GI pipe) and
RC post has been calculated and then moment due to these dead loads about the fixed end of
cantilever slab i.e., at the face of main girder has been computed.
40
Table Calculation of responses due to dead load on cantilever portion of bridge
For effective spans of over 30m, the intensity of load shall be determined by equation:
𝐿 15
= 3.90 kN/m2
where,
P’ =500kg/m2
Shear force at the face of rib = Intensity of load × Clear walking footpath width
41
Lever Arm=(𝑊𝑖𝑑𝑡ℎ 𝑜𝑓 𝑓𝑜𝑜𝑡𝑝𝑎𝑡ℎ− 𝑊𝑖𝑑𝑡ℎ 𝑜𝑓 𝑟𝑎𝑖𝑙𝑖𝑛𝑔)
2
+ Distance without considering footpath
Live load per unit width of slab is calculated placing a wheel of 114 KN Axle for class A
loading. Live load per unit width of slab is found by dividing live load by effective width of slab
‘beff’.
beff = 1.2a + b1 ≤ 𝑙 /3
Where, a= the distance of the centre of gravity of the concentrated load from the face of the
cantilever support = 0.0375 m
Breadth of concentration area of load (b1) = width of tire contact area+2 x Thickness of Wearing
Coat = 0.25+2 × 0.075 = 0.4 m
beff = 1.2a + b1 ≤ 𝑙 /3
4.5
Impact factor =
6+35
= 0.109
Moment due to loading = Live load per unit width with impact × 0.0375 =134.064 × 0.0375
= 5.028 KNm
42
Calculation of shear force and bending moment per unit width strip
Load Combinations
ULS ULS SLS SLS SLS
Basic Seismic Rare Freq. Quasi
1.35 1.35 1 1 1
1.75 1.75 1.2 1.2 1.2
1.5 0.2 1 0.75 0
1.15 0.2 0.75 0.2 0
Factored
Moment 27.446 20.91589 19.67296 17.33361 14.59306
Factored
Shear 33.96719 24.58471 24.26446 20.85648 16.96321
Flexure Design
43
Design of Slab
Ecu2 = 0.0035
Fck = 30 MPa
0.446×fck = 13.98
N/mm2 Xu = 115.63 mm
0.446×Xu =0.446*115.63=51.57 mm
Depth =250 mm
Clear cover =40 mm
Effective cover =Depth-Clear Cover-Diameter of rebar/2 = 46 mm
Effective depth(d)=Depth-Effective Cover = 204 mm
Breadth of slab (Bw) =1000 mm
β1 = 0.80952
β2= 0.41597
Compressive Force(C) = β1×0.446Fck×bw×Xu = 1252.43 kN
Cg from steel level =d-0.416Xu = 155.9mm
Mulim = C×CG from steel level/1000 = 195.25 kNm
Our design moment is 27.44 kN but we get limiting moment as 195.25 kN which is very high.
So, we have to increase tensile strain of steel in such a way that our neutral axis shifts upward
and Xu value then Mulim value is decreased respectively.
Ecu2 = 0.0035
Fck = 30 MPa
0.446×fck = 13.98
N/mm2 Xu = 12.78 mm
0.416×Xu = 5.32 mm
Depth = 250 mm
Clear cover = 40 mm
Effective cover =Depth-Clear Cover-Diameter of rebar/2 = 46 mm
Effective depth = Depth-Effective Cover = 204 mm
Bw = 1000 mm
44
β1 = 0.80952
45
β2 = 0.41597
C = β1×0.446Fck×bw×Xu = 138.425 kN
Cg from steel level =d-0.416Xu = 198.68 mm
Mulim = C×CG from steel level/1000 = 27.5kNm
(which is equal to our design moment)
Reinforcement:
Fe = 500 N/mm2
Fyd = 434.78 N/mm2
Steel Required = Compressive Force×1000/ Fyd = 318.38 mm2
Tensile steel as per code
Fctm= 0.259×fck2/3 = 2.501
Fyk = 500 N/mm2
0.26×Fctm/Fyk = 0.00130
Min. Asmin = min(0.26Fctm/Fyk,0.00130) = 0.00130
Minimum Area of steel = 0.0013×d×bw = 265.265
mm2 Area of concrete (Ac) = D×bw = 250000 mm2
Maximum Area of steel = 0.025Ac = 6250 mm2
Since, steel required is more than minimum area of steel, we are adapting required area of steel.
Required Ast = 318.38 mm2
=12mm Ф @ 355.22 mm c/c spacing
Provided Ast = 12mm Ф @ 150mm c/c spacing
Therefore, area of steel provided=753.980 mm2 (>318.18 mm2, <6250 mm2) (ok)
Distribution Reinforcement
Required Ast = 20% of 753.980 mm2
= 12mm Ф @ 750 mm c/c spacing
Provided Ast = 12mm Ф @ 300 mm c/c spacing
46
Check for Shear
Width = 1000 mm
Depth = 250
Fck = 30 MPa
ρl = Ast/(bw×d) = 0.0036<0.02
k =1+ (200/d)0.5 =1.9901 <2
γmin = 0.031k3/2 ck
f 1/2 = 0.4766
γRd, c, min = γmin +0.15 σcp = .4769
𝑣𝑅𝑑.𝑐 = [0.12(80𝜌1 ∗ 𝑓𝑐𝑘)0.33 + 0.15𝜎𝑐𝑝 ]= [0.12(80×0.0021×30)0.33+.15*.002]
=0.244 N/mm2
VRd,c = 0.244 × 1000× 204 = 168.800 kN > (167 kN)
47
= 250/2 = 125 mm
48
Ac, eff = min (Hc, eff) ×Bw
=79.07×1000
=79070mm2
c = 40mm
Sr, max = 3.4c+0.17×Φ/Ρ1, eff) =3.4×40+0.17×12/0.00953
= 350.1 mm
Crack width = Sr,max×(εsm-εcm)
= 350.1 × 0.000846
= 0.296mm < 0.3mm (ok for severe case)
50
spacing of Cross girder = 8.75 m
Wheel load(kN) = 57 kN
51
Distance of C.G. of concentrated load from the nearer support (a) =Size of slab along shoter
direction/2 = 1.1 m
(𝑎)
Effective width of slab on which load acts (beff) = α x a x (1 −
𝑆𝑖𝑧𝑒 𝑜𝑓 𝑠𝑙𝑎𝑏 𝑎𝑙𝑜𝑛𝑔 𝑠ℎ𝑜𝑡𝑒𝑟 𝑑𝑖𝑟𝑒𝑐𝑡𝑖𝑜𝑛) +b1
=1.813 m
Effective width (m) = beff + c/c spacing of load = 1.813 + 1.2 = 3.013 m
𝑤𝑖𝑑𝑡ℎ∗𝐸𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒 𝑙𝑒𝑛𝑔𝑡ℎ) 3)
Max. BM =
4.5
(6+𝑆𝑖𝑧𝑒 𝑜𝑓 𝑠𝑙𝑎𝑏 𝑎𝑙𝑜𝑛𝑔 𝑠ℎ𝑜𝑡𝑒𝑟
Impact factor=
𝑑𝑖𝑟𝑒𝑐𝑡𝑖𝑜𝑛)
= 0.549
Wheel load(kN)= 57 kN
52
Breadth of concentration area of load (b1) = width of tire contact area+2 x Thickness of Wearing
Coat
= 0.25+2×0.075 = 0.4m
Distance of C.G. of concentrated load from the nearer support (a) = 1.1 m
(𝑎)
Effective width of slab on which load acts (beff) = α x a x (1 −
𝑆𝑖𝑧𝑒 𝑜𝑓 𝑠𝑙𝑎𝑏 𝑎𝑙𝑜𝑛𝑔 𝑠ℎ𝑜𝑡𝑒𝑟 𝑑𝑖𝑟𝑒𝑐𝑡𝑖𝑜𝑛) +b1
=1.83m
Effective width (m) = beff + c/c spacing of load = 1.83 + 1.2 = 3.03 m
𝑤𝑖𝑑𝑡ℎ∗𝐸𝑓𝑓𝑒𝑐𝑡𝑖𝑣𝑒 𝑙𝑒𝑛𝑔𝑡ℎ) )
=27.79 kN/m
4.5
(6+𝑆𝑖𝑧𝑒 𝑜𝑓 𝑠𝑙𝑎𝑏 𝑎𝑙𝑜𝑛𝑔 𝑠ℎ𝑜𝑡𝑒𝑟
Impact factor =
𝑑𝑖𝑟𝑒𝑐𝑡𝑖𝑜𝑛)
= 0.548
53
For Bending Moment of Live Load
Distance of C.G. of
concentrated load from the 1.10 1.10 1.10 1.10
nearer support, a (m)
BM including CF and IF
18.46 19.27 24.50 23.51
(kNm/m)
54
For Shear Force due to live load
IRC 70R
Wheel Bogie
loading loading
wheel load (kN) 57 85 175 100
C/C spacing of load (m) 1.2 1.37 0 1.2
Breadth of
Concentration 0.4 0.4 4.72 0.4
area of load , b1 (m)
SF including IF (kN/m)
46.7861343 68.4198 85.5565 83.6359
55
Maximum Bending Moment and Shear Force due to live load
ULS SLS SLS
Mome Mome
Lo ULS Seismi SLS
nt Freq. Quasi Load nt
ad Basic c Rare
kNm kNm
Self-
4.8 1.35 1.35 1 1 1 Self-Weight 8.7
Weight
Factore
d 44.94 30.47 24.35
13.095 5.976
Mome 5 6 1
nt
Factore 146.0 98.36 76.97 12.80
34.842
d Shear 7 4 4 4
Flexure Design
Design of Slab
Ecu2 =0.0035
Fck =30 MPa
49
0.446×fck =13.98 N/mm2
Xu =126 mm
49
0.416×Xu = 52.340 mm
Depth = 250 mm
Clear cover = 40 mm
Effective cover = Depth-Clear Cover-Diameter of rebar/2 = 46 mm
Effective depth(d) = Depth-Effective Cover = 204 mm
Breadth of slab (Bw) = 1000 mm
β1 = 0.80952
β2 = 0.41597
Compressive Force(C) = β1×0.446Fck×bw×Xu = 1362.700 kN
Cg from steel level =d-0.416Xu = 151.700 mm
Mulim = C×CG from steel level/1000 = 206.680 kNm
Our design moment is 44.945 kN but we get limiting moment as 206.680 kN which is very high.
So, we have to increase tensile strain of steel in such a way that our neutral axis shifts upward
and Xu value then Mulim value is decreased respectively.
Ecu2 = 0.0035
Fck =30 MPa
0.446×fck = 13.98
N/mm2 Xu = 21.32 mm
0.416×Xu = 8.87 mm
Depth = 250 mm
Clear cover = 40 mm
Effective cover = Depth-Clear Cover-Diameter of rebar/2 = 46 mm
Effective depth = Depth-Effective Cover = 204 mm
Bw =1000 mm
β1 =0.80952
β2 =0.41597
C = β1×0.446Fck×bw×Xu = 230.92 kN
Cg from steel level =d-0.416Xu = 195.13 mm
Mulim =C×CG from steel level/1000 = 45.24 kNm (which is nearly equal to our design moment)
50
Reinforcement:
Fe = 500 N/mm2
Fyd = 434.78 N/mm2
Steel Required= Compressive Force×1000/ Fyd = 531.12 mm2
Tensile steel as per code
Fctm = 0.259×fck2/3 = 2.501
Fyk = 500 N/mm2
0.26×Fctm/Fyk = 0.00130
Min. Asmin = min(0.26Fctm/Fyk,0.00130) = 0.00130
Minimum Area of steel = 0.0013×d×bw = 265.265
mm2 Area of concrete (Ac) = D×bw = 250000 mm2
Maximum Area of steel = 0.025Ac = 6250 mm2
Since, steel required is more than minimum area of steel, we are adapting required area of steel.
Distribution Reinforcement
Required Ast =20% of 753.980 mm2
=12mm Ф @ 750 mm c/c spacing
Provided Ast =12mm Ф @ 300 mm c/c spacing
Width = 1000 mm
51
Fck = 30 MPa
ρl = Ast/(bw×d) = 0.0021 < 0.02
k = 1+ (200/d)0.5 = 1.9901 <2
γmin = 0.031k3/2 ck
f 1/2 = 0.4767
γRd, c, min = γmin +0.15 σcp = 0.477
𝑣𝑅𝑑.𝑐 = [0.12(80𝜌1 ∗ 𝑓𝑐𝑘)0.33 + 0.15𝜎𝑐𝑝 = (0.12×1.9901×(80×0.0021×30)0.33
=0.4092 N/mm2
VRd,c = 0.4092 × 1000× 354 = 168.800 kN > (146.07kN)
52
Fct, eff =0.259×(Fck)2/3
=0.259×(30)2/3 = 2.5
Ecm =22×(fcm/12.5)0.3×1000MPa(N/mm2)
=31187 MPa
ρ1, eff =As/Ac, eff =753.98/115000 = 0.0066
αe = Es/Ecm=200000/31187 = 6.413
𝑓𝑐𝑡,
𝜎 − ∗
𝛼 ∗ (1 + ∗ 𝜎𝑠𝑐
𝜀𝑠𝑚 − 𝜀𝑐𝑚 𝑠𝑐 𝑘𝑡 𝜌𝑝,𝑒𝑓𝑓 𝜌𝑝,𝑒𝑓𝑓) ≥ 0.6
𝑒
𝐸𝑠
=
𝐸
𝑠
53
6.1.2 Analysis and Design of Main Girders
There are three main girders, two at edge and one at the middle.
54
Bending Moment and Shear Force Due to Dead Loads:
Bending Moment and Shear Force Due to Dead Loads = Dead loads at mid-section of main girder
55
Load from cross girders:
Weight of one end cross girder = 1.7 × 0.45 × 3.3× 25 + 2 × 0.975 × 0.45 × 1.7 × 25
= 101.503 kN/m
Weight of one mid cross girder = 1.575 × 0.3 × 3.3 × 25+ 2 × 0.975 × 0.3 × 1.575 × 25
= 62.015 kN/m
Bending moment and shear force due to load from cross girder:
The self-weight of cross girders, in this case, acts at the center of main girder as concentrate load.
R1 R2
101.503*35+62.015*26.25+62.015*17.5+62.015*8.75
R = = 194.525 𝑘𝑁
35
1
BM at mid span:
BM at quarter span:
SF at mid span:
56
SF at quarter span:
SF at support(0 m) = 194.525 kN
SF at support(35 m) = -194.525kN
57
Further calculation in tabular form:
BM due to dead
load 0 0 4.375 8.75 13.125 17.5 21.875 26.25 30.625 35
406.971 813.942 1220.91 1627.88 2034.85 2441.82 2848.79 3255.7
93.022 0 0 0 3 5 4 5 6 8 9 7
-
- - - - - 1627.8
-62.015 8.75 0 0 0 0 271.316 542.631 813.947 1085.26 1356.58 9
-
- - - 1085.2
-62.015 17.5 0 0 0 0 0 0 271.316 542.631 813.947 6
-
- 542.63
-62.015 26.25 0 0 0 0 0 0 0 0 271.316 1
93.022 35 0 0 0 0 0 0 0 0 0 0
406.971 813.942 949.598 1085.25 949.593 813.933 406.958
0 3 5 1 4 8 8 1 -0.0175
SF just right
35 0 4.375 8.75 13.125 17.5 21.875 26.25 30.625 35
93.022 0 35 93.022 93.022 93.022 93.022 93.022 93.022 93.022 93.022 93.022
-62.015 8.75 35 -62.015 0 -62.015 -62.015 -62.015 -62.015 -62.015 -62.015 -62.015
-62.015 17.5 35 -62.015 0 0 0 -62.015 -62.015 -62.015 -62.015 -62.015
-62.015 26.25 35 -62.015 0 0 0 0 0 -62.015 -62.015 -62.015
58
93.022 35 35 93.022 0 0 0 0 0 0 0 93.022
-0.001 93.022 31.007 31.007 -31.008 -31.008 -93.023 -93.023 -0.001
58
Bending Moment summary from dead load:
At mid span:
10655.567 𝑘𝑁𝑚
2 2
14268.95𝑘𝑁𝑚
2 2
2 2
2 2
2 2
At quarter span:
𝑘𝑁𝑚
2 2
2 2
2 2
59
BM due to footpath = 18.75×35 × 8.75 − = 2153.32 𝑘Nm
18.75×8.752
2 2
60
BM due to surfacing = 12.375×35 × 8.75 – = 1421.191𝑘𝑁𝑚
12.375×8.752
2 2
BM due to load at support (one end) = 149.34×33.5 × 8.75 − 149.34 × 7.25 = 168
𝑘𝑁𝑚
35
At mid span:
SF due to slab and cross girder = 62.015×35 – 62.015× 17.5 + 30.001 = 30.001 𝑘𝑁
2
35
At 8.75m:
SF due to slab and cross girder = 62.015×35 – 62.015 × 8.75 + 93.02 = 635.65𝑘𝑁
2
35
At 26.25m:
62
Due to additional load at support:
35
At Support:
At 0 m:
35
63
At 35 m:
35
At mid span:
64
At quarter span:
SF due to railing = 0 kN
SF due to footpath = 0 kN
SF due to surfacing = 0 kN
At quarter span:
At 8.75 m:
65
At 26.25 m:
At support:
At 0 m:
SF due to railing = 35 kN
At 35 m:
66
Bending Moment summary from dead load:
cross girder 0 406.9713 813.9425 949.5981 1085.254 949.5938 813.9338 406.9581 -0.0175
67
Shear Force summary from dead load
shear
force
slab 62.5 1093.75 820.3125 546.875 273.4375 0 -273.438 -546.875 -820.313 -1093.75
footpath 18.75 328.125 246.0938 164.0625 82.03125 0 -82.0313 -164.063 -246.094 -328.125
surfacing 12.375 216.5625 162.4219 108.2813 54.14063 0 -54.1406 -108.281 -162.422 -216.563
cross girder 93.023 93.022 93.022 31.007 31.007 -31.008 -31.008 -93.023 -93.023
girder 93.022 1627.885 1220.914 813.9425 406.9713 0 -406.971 -813.943 -1220.91 -1627.89
Additional 1.5 142.9 -6.4 -6.4 -6.4 -6.4 -6.4 -6.4 -6.4 -6.4
33.5 6.4 6.4 6.4 6.4 6.4 6.4 6.4 6.4 -142.9
Sum 5124.06 2569.014 1743.683 856.3376 31.007 -856.339 -1681.67 -2569.01 -3543.65
68
Bending Moment and Shear Force Due to Pedestrian Loads:
No. of footpath = 2
Width of footpath = 1.025m
P’ = 500 kg/m2
(
16.5−1.025
𝐿 15 35 15
SF at 0 m = 161.79 kN
SF at 35 m = -161.79 kN
Reaction
0 4.38 8.75 13.13 17.5 21.88 26.25 30.63 35
@
69
Bending Moment and Shear Force Due To Live Loads:
Bending moment and shear force due to moving vehicles of various relevant classes from IRC 6-
2017 are determined using VBA programs/code.
FindBM = 0
Exit Function
End If
LocalLen = SS - bmat
LocalR = (uLoadAt) / SS
Else
LocalLen = bmat
End If
End Function
70
Program to find Shear Force using ILD:
FindSF = 0
Exit Function
End If
If SFAt = 0 Then
Exit Function
FindSF = -uLoadAt / SS
Exit Function
FindSF = -uLoadAt / SS
Else
End If
End Function
71
Program to find Left support reaction using ILD:
FindRL = 0
FindRL = ULat / S1
FindRL = 0.5
Else
FindRL = 0
End If
End Function
FindRR = 0
FindRR = 0.5
72
FindRR = (S1 + CC + S2 - ULat) / S2
Else
FindRR = 0
End If
End Function
Sub MoveVehBM35()
For m = 1 To 4
For n = 1 To 4
A = 20 × m - 12
B=3×n+3
C = 20 × m + 4
D=3×n+4
E = m + 251
F=n+4
L = 0: bm = 0: BmX = 0
Sheet3.Cells(A, B) = L
73
bm = Sheet3.Cells(C, D)
BmX = bm
LmX = L
End If
L = L + 0.1
Loop
Sheet3.Cells(E, F) = BmX
Sheet2.Cells(E, F + 5) = LmX
Next n
Next m
End Sub
Sub MoveVehSF35()
For m = 1 To 4
For n = 1 To 4
74
A = 20 × m + 70
B=3×n+3
C = 20 × m + 86
D=3×n+4
E = 2 × m + 256
F=n+4
L = 0: SF = 0: SFmax = 0: SFmin = 0
Sheet3.Cells(A, B) = L
SF = Sheet3.Cells(C, D)
SFmax = SF
Lmax = L
End If
SFmin = SF
Lmin = L
End If
L = L + 0.1
Loop
Sheet3.Cells(E, F) = SFmax
Sheet3.Cells(E, F + 5) = Lmax
Sheet3.Cells(E + 1, F) = SFmin
75
Sheet3.Cells(E + 1, F + 5) = Lmin
Next n
Next m
End Sub
Sub MoveVehRXN35()
For m = 1 To 4
For n = 1 To 2
A = 20 × m + 152
B=3×n+3
C = 20 × m + 168
D=3×n+4
E = 2 × m + 267
F=n+4
Sheet3.Cells(A, B) = L
RXN = Sheet3.Cells(C, D)
76
If RXN > RXNmax Then RXNmax = RXN Lmax = L
End If
End If L = L + 0.1
Loop
Next n Next m
End Sub
position section SF
79
Class A 53.7 35
27 0 53.7 35 0
27 1.1 52.6 35 0
114 3.2 49.4 35 0
114 1.2 48.2 35 0
68 4.3 43.9 35 0
68 3 40.9 35 0
68 3 37.9 35 0
-
68 3 34.9 35 67.8057
-
18.8 67.8057
81
120 3.96 44.44 26.25 0 120 3.96 44.44 30.625 0
120 1.52 42.92 26.25 0 120 1.52 42.92 30.625 0
170 2.13 40.79 26.25 0 170 2.13 40.79 30.625 0
170 1.377 39.413 26.25 0 170 1.377 39.413 30.625 0
170 3.05 36.363 26.25 0 170 3.05 36.363 30.625 0
170 1.37 34.993 26.25 0.034 170 1.37 34.993 30.625 0.034
13.407 0.034 13.407 0.034
position section SF
Class
70R 48.4 35
80 0 48.4 35 0
120 3.96 44.44 35 0
120 1.52 42.92 35 0
170 2.13 40.79 35 0
170 1.377 39.413 35 0
170 3.05 36.363 35 0
-
170 1.37 34.993 35 169.966
-
13.407 169.966
82
100 0.653 38.194 0 0 100 0.653 38.194 4.375 0
100 0.653 37.541 0 0 100 0.653 37.541 4.375 0
100 0.653 36.888 0 0 100 0.653 36.888 4.375 0
100 0.653 36.235 0 0 100 0.653 36.235 4.375 0
100 0.653 35.582 0 0 100 0.653 35.582 4.375 0
0.10142 0.10142
50 0.653 34.929 0 9 50 0.653 34.929 4.375 9
0.10142 0.10142
4.571 9 4.571 9
83
50 0 39.5 17.5 0 50 0 39.5 21.875 0
100 0.653 38.847 17.5 0 100 0.653 38.847 21.875 0
100 0.653 38.194 17.5 0 100 0.653 38.194 21.875 0
100 0.653 37.541 17.5 0 100 0.653 37.541 21.875 0
100 0.653 36.888 17.5 0 100 0.653 36.888 21.875 0
100 0.653 36.235 17.5 0 100 0.653 36.235 21.875 0
100 0.653 35.582 17.5 0 100 0.653 35.582 21.875 0
0.10142 0.10142
50 0.653 34.929 17.5 9 50 0.653 34.929 21.875 9
0.10142 0.10142
4.571 9 4.571 9
position section SF
84
Class
70RT 39.5 35
50 0 39.5 35 0
100 0.653 38.847 35 0
100 0.653 38.194 35 0
100 0.653 37.541 35 0
100 0.653 36.888 35 0
100 0.653 36.235 35 0
100 0.653 35.582 35 0
-
50 0.653 34.929 35 49.8986
-
4.571 49.8986
85
BM section
SF section
Class AA min 0 -5.78571 -37.3286 -80.2371 -145.58 -215.226 -284.871 -354.517 -416.949
Class AA max 398.74 330.6771 261.0314 191.3857 124.48 66.83429 33.22286 10.88 0
70R min 0 -10.9943 -52.4714 -169.149 -294.864 -420.578 -546.292 -669.149 -785.949
70R max 850.8506 727.9934 602.2791 476.5649 350.8506 228.6791 115.5591 35.18514 0
70RT min 0 -40.6771 -128.29 -216.29 -304.29 -390.29 -478.29 -566.29 -652.29
70Rt max 653.71 565.71 477.71 391.71 303.71 215.71 127.71 41.99571 0
86
Unfactored Reactions (without
IF)
Max Min
87
Summary Table
Max BM s section
0 4.375 8.75 13.125 17.5 26.25 26.25 30.625 35 ImpF Lane
Max SF section
Class AA min 0 -2.60665 -16.8177 -36.1494 -65.5884 -96.966 -128.344 -159.721 -187.849 0.1098 2
Class AA
max 179.645 148.9805 117.6029 86.22532 56.08218 30.11096 14.96795 4.901784 0 0.1098 2
70R min 0 -9.90655 -47.2801 -152.414 -265.691 -378.967 -492.244 -602.946 -708.19 0.1098 1
70R max 766.6702 655.9681 542.6916 429.4151 316.1386 206.0544 104.1261 31.70404 0 0.1098 1
70RT min 0 -36.9792 -116.627 -196.627 -276.627 -354.809 -434.809 -514.809 -592.991 0.1 1
70Rt max 594.2818 514.2818 434.2818 356.1 276.1 196.1 116.1 38.17792 0 0.1 1
88
TRANSVERSE DISTRIBUTION OF LIVE LOAD
Class
Distribution Factor A
Eccentricty= 0.700 m
CG = 4.300 m
Moment = 2.800 KNm
Sum= 25.313
89
Distribution Factor 70R Track
Load positions from left
edge -> 2.870 4.930
Loads 1.000 1.000
Eccentricty= 1.100 m
CG= 3.900 m
Moment = 2.200 KNm
Sum= 25.313
Reactions on the
beams ( L) 0.500 0.500 0.500 0.500
Reactions on the -
beams ( M) 0.293 0.098 0.098 -0.293
0.793 0.598 0.402 0.207
0.29 0.20
Distribution Factor 0.397 9 1 0.103
90
70R
Distribution Factor Wheel
91
Load positions from left edge -> 2.880 4.810
Loads 1.000 1.000
CG of
Loads 1.000 1.000 KN
Sum= 2.000 KN
2.880 4.810 m
Load x Distance = 2.880 4.810 KNm
Eccentricty= 1.155 m
CG= 3.845 m
Moment = 2.310 KNm
25.31
Sum= 3
Distribution Factor
Summary
0.21888 0.15666
Class A 0.343333 0.281111 9 7
70R 0.20111 0.10333
Track 0.396667 0.298889 1 3
70R 0.19866
Wheel 0.404 0.301333 7 0.096
92
Design of T-Beam
Grade of concrete=M45
Reinforcement=Fe500
Class II 7 ply19K13
Diameter of strand=12.7mm
93
A. Calculation of Moment
Bm
udl 0 4.375 8.75 13.125 17.5
slab 62.5 0 4187.012 7177.734 8972.168 9570.313
railing 2 0 133.9844 229.6875 287.1094 306.25
footpath 18.75 0 1256.104 2153.32 2691.65 2871.094
surfacing 12.375 0 829.0283 1421.191 1776.489 1894.922
cross girder 0 406.9713 813.9425 949.5981 1085.254
girder 161.25 0 10802.49 18518.55 23148.19 24691.41
Pedestrian 0 618.5 1060.3 1325.4 1413.2
BM section
0 4.375 8.75 13.125 17.5
BM ClassAA 0 617.2875 2509.825 3172.988 3448.65
BM 70R 0 3184.971 5389.253 6666.394 7125.615
BM 70RT 0 2503.931 4290.613 5361.844 5716.875
At mid:
beff,1 = 0.2 × b1 + 0.1 × span = 0.2 × 1.294 + 0.1 × 35 = 3.759 m <(0.2lo = 7) and > (bi = 1.294)
beff,2 = 0.2 ×b2 + 0.1 × span = 0.2 × 1.430 + 0.1 × 35 = 3.785 m < (0.2lo = 7) and > (bi = 1.294)
94
95
The effective flange width beff for a T beam is given by,
beff = ∑ beff,i + bw ≤ b
with beff,i = 0.2bi +0.1lo ≤ 0.2lo
and beff,i ≤ bi
Now,
At support:
beff,1 = 0.2 × b1 + 0.1 × span = 0.2 × 1.069 + 0.1 × 35 = 3.714 m <(0.2lo = 7) and > (bi = 1.069)
beff,2 = 0.2 ×b2 + 0.1 × span = 0.2 × 1.200 + 0.1 × 35 = 3.740 m < (0.2lo = 7) and > (bi = 1.069)
beff = ∑ beff,i + bw ≤ b
and beff,i ≤ bi
Now,
96
B. Calculation of moment due to prestressing force
At mid
CG from Moment
Sections Breadth Height Area
bottom of Area
Slab 2.45 0.25 0.6125 2.275 1.39344
Fillet 0.9 0.15 0.0675 2.1 0.14175
Web 0.3 1.55 0.465 1.375 0.63938
Bulb-
0.3 0.15 0.0788 0.514 0.0405
Trapezium
Rectangle 0.75 0.45 0.3375 0.225 0.07594
Depth 2.4 1.5613 sum 2.291003
CG from
1.46736899 m
bottom=
CG from
0.93263101 m
top=
Moment of Inertia
97
At support
CG from Area
Sections Breadth Height Area
bottom moment
Slab 2.45 0.25 0.6125 2.275 1.39344
Web 0.3 1.55 0.465 1.375 0.63938
Depth = 2.4 1.0775 sum= 2.03281
Moment of Inertia
Nos of Angle of
End Mid 4.375 8.750 13.125 17.500
cables emergence
3.15 1.590 2.468 1.980 1.688 1.590 0 10.21 C10
2.85 1.410 2.220 1.770 1.500 1.410 0 9.44 C9
2.55 1.230 1.973 1.560 1.313 1.230 0 8.66 C8
2.25 1.050 1.725 1.350 1.125 1.050 0 7.89 C7
1.95 0.870 1.478 1.140 0.938 0.870 0 7.11 C6
1.65 0.690 1.230 0.930 0.750 0.690 1 6.32 C5
1.35 0.510 0.983 0.720 0.563 0.510 0 5.54 C4
1.05 0.330 0.735 0.510 0.375 0.330 1 4.75 C3
0.75 0.150 0.488 0.300 0.188 0.150 1 3.96 C2
0.45 0.150 0.319 0.225 0.169 0.150 2 1.98 C1
5
98
Cable Profile
1.750
1.500
1.250
1.000
0.750
0.500
0.250
0.000
0.000 5.000 10.000 15.000 20.000 25.000 30.000 35.000 40.000
Calculation of eccentricity
0.00 4.38 8.75 13.13 17.50
C10 1.704 0.947 0.460 0.167 0.070
C9 1.404 0.700 0.250 -0.020 -0.110
C8 1.104 0.452 0.040 -0.208 -0.290
C7 0.804 0.205 -0.170 -0.395 -0.470
C6 0.504 -0.043 -0.380 -0.583 -0.650
C5 0.204 -0.290 -0.590 -0.770 -0.830
C4 -0.096 -0.538 -0.800 -0.958 -1.010
C3 -0.396 -0.785 -1.010 -1.145 -1.190
C2 -0.696 -1.033 -1.220 -1.333 -1.370
C1 -0.996 -1.202 -1.295 -1.352 -1.370
99
C2 0.750 0.488 0.300 0.188 0.150
C1 0.900 0.638 0.450 0.338 0.300
sum 4.350 3.090 2.190 1.650 1.470
CG of cable from bottom 0.870 0.618 0.438 0.330 0.294
deff 1.530 1.782 1.962 2.070 2.106
Calculation of average eccentricity
0.00 0.00 0.00 0.00 0.00
C10 0.000 0.000 0.000 0.000 0.000
C9 0.000 0.000 0.000 0.000 0.000
C8 0.000 0.000 0.000 0.000 0.000
C7 0.000 0.000 0.000 0.000 0.000
C6 0.000 0.000 0.000 0.000 0.000
C5 0.204 -0.290 -0.590 -0.770 -0.830
C4 0.000 0.000 0.000 0.000 0.000
C3 -0.396 -0.785 -1.010 -1.145 -1.190
C2 -0.696 -1.033 -1.220 -1.333 -1.370
C1 -1.992 -2.403 -2.591 -2.703 -2.741
-2.880 -4.511 -5.411 -5.951 -6.131
Average eccentricity -0.576 -0.902 -1.082 -1.190 -1.226
100
Calculation of moment due to pre-stressing:
Limiting force = 0.783 × No. of strands per cable × fpk × area of one tendon
= 0.783 × 19 × 1860 × 98.7 .
=2731.1 kN
Force applied = 2730.0 kN
Force in each cable = (1 – 0.3) × 2730.0
= 1911.0 kN
Total force applied = 1911 × total no of cable
= 1911 × 5
= 9555 kN
101
2. Taking no loss
Maximum force in each cable = 2730.0 kN
Loss = 0%
Force applied in each cable = 2730.0 kN
Total force applied = 2730 × 5
= 13650.0 kN
Moment @ 0.000 4.375 8.750 13.125 17.500
C10 - - - - -
C9 - - - - -
C8 - - - - -
C7 - - - - -
C6 - - - - -
C5 556.7 - 792.5 - 1,611.5 - 2,102.9 - 2,266.7
C4 0.0 0.0 0.0 0.0 0.0
C3 -1081.3 -2143.8 -2758.1 -3126.6 -3249.5
C2 -1900.3 -2819.5 -3331.4 -3638.5 -3740.9
C1 -5438.6 -6560.4 -7072.3 -7379.4 -7481.8
-7863.6 -12316.2 -14773.2 -16247.4 -16738.8
102
Unfactored moment due to DL & LL Factors
103
Factored Moment summary:
104
Case 2: Quasi Permanent combination
Axial Force= 9555 KN
105
D. Ultimate strength check
Live Loads DF LF
106
Factored bending moment
DEAD
LOADS
UDL 0 4.375 8.75 13.125 17.5 DF LF
slab & CG 62.5 0 2065.225 3592.658 4460.33 4790.21 0.333 1.35
Barrier 0 0 0 0 0 0 0.333 1.35
girder 161.25 0 4856.259 8325.014 10406.27 11100.02 0.333 1.35
railing 2 0 90.43947 155.0391 193.7988 206.7188 0.5 1.35
footpath 18.75 0 847.8702 1453.491 1816.864 1937.988 0.5 1.35
surfacing 12.375 0 483.1162 828.1991 1035.249 1104.266 0.333 1.75
Pedestrian 0 463.875 795.225 994.05 1059.9 0.5 1.5
Live Loads DF LF
e𝑐
[1 − (1 −
e𝑐
= 𝑛 ≤ e𝑐2
𝑓𝑐𝑑 ] e𝑐
for 0 ≤
e
)
𝑐2
𝛼 𝑓𝑐𝑑
fcd =
e𝑚
107
fck= 45.00 N/mm2 εcu2 = 0.0035
fcd= 20.10 N/mm2 εc2= 0.0020
n= 2
Stress of concrete for different values of strain
25.00
Concrete 20.00
0.0020 20.10
0.0025 20.10
0.0030 20.10
0.0035 20.10
fpk= 1860.0 N/mm2 Es = 195000 N/mm2
fp0.1= 1618.2 N/mm2 εuk = 0.0222
fpd = 1407.1 N/mm2 εud= 0.02000
Design strain (ε) = 0.00722
-0.0222 1653.94077 0
-0.03 -0.02 -0.01 0.00 0.01 0.02 0.03
-0.0200 -1617.4
-1000
-0.0072 -1407.1
-2000
0.0000 0.0
0.0072 1407.1
0.0200 1617.4
108
Strain distribution at mid
Check
actual limiting
xu 411.32 687.85 OK
εbottom cable 0.01565 0.02000 OK
Moment 17781 28303 OK
tensile stress 1545.8 1617.4 OK for bottom cable
Check
actual limiting
xu 409.27 676.09 OK
εbottom cable 0.01558 0.02000 OK
Moment 16640 27733 OK
tensile stress 1544.7 1617.4 OK for bottom cable
Check
actual limiting
xu 403.20 640.81 OK
εbottom cable 0.01538 0.02000 OK
Moment 13391 26037 OK
tensile stress 1541.4 1617.4 OK for bottom cable
109
Strain Distribution at L/8
Check
actual limiting
xu 390.40 582.02 OK
εbottom cable 0.01516 0.02000 OK
Moment 7854 23216 OK
tensile stress 1537.8 1617.4 OK for bottom cable
Strain Distribution at 0
Check
actual limiting
xu 347.20 499.72 OK
εbottom cable 0.01616 0.02000 OK
Moment 0 19172 OK
tensile stress 1554.2 1617.4 OK for bottom cable
110
Shear Check for Main Beam:
Sections SF DF LF Factored SF
Dead Load KN
Slab & CG 1095.8109 0.333 1.350 493.1
Barriers 0 0.333 1.350 0.0
Girder 1394.5781 0.333 1.350 627.6
Railing 35 0.500 1.350 23.6
Footpath 288.75 0.500 1.350 194.9
Surfacing 173.25 0.333 1.750 101.1
Pedestrain 161.568 0.500 1.500 121.2
1561.4
Live Loads inculding impact
Class A 929.45 0.333 1.500 464.7
70 R Wheel 947.29 0.410 1.500 583.3
70R Boogie 436.29 0.410 1.500 268.6
70 R Track 719.73 0.398 1.500 429.8
583.3
Total 2144.7
N/mm2
111
Design for cracked section
fck = 45 N/mm2
0.67∗45
fcd = = 20.1 N/mm2
1.5
Z = 1386.95 mm
𝑁𝑒𝑑 0.67
σcp= = 4.02 N/mm2 < (0.2fcd=0.22×45× = 4.02N/mm2)
𝐴𝑐 1.5
k =1 + √ ≤ 2=1.3615 ≤ 2.0
200
𝑉𝑅 750
𝑑.𝑐 1000
= 0.95 × 1530 × = 1094.00 kN
112
for σcp values (in between) αcw
0.00 1
0.00 5.03 1.2
10.05
5.03 1.25
10.05 20.10 2
N/mm2
Max. allowable shear stress for (ϑ)=45° = αcw×0.225× v1× fck= 6.2318 < 2.262 (ok)
Provided 20 mm diameter of bar and with 2 legged along with spacing of 100 mm .
fy = 500.00 N/mm2
𝑓𝑦𝑘
= = 434.78 N/mm2
fywd = fyd =
500
1.15 1.1
5
bf =2887.5mm
113
Df = 250mm
bw = 300 mm
114
bw/8 = 37.5 mm
bwc=bw,nom= 300mm
k1 = 1
VRd.c = 1727.399 kN
115
D. Shear Design at support (I- 8)
Sections SF DF LF Factored SF
Dead Load KN
Slab & CG 771.45 0.333 1.350 347.2
Barriers 0.00 0.333 1.350 0.0
Girder 933.93 0.333 1.350 420.3
Railing 26.25 0.500 1.350 17.7
Footpath 216.56 0.500 1.350 146.2
Surfacing 129.94 0.333 1.750 75.8
Pedestrain 121.18 0.500 1.500 90.9
1098.0
Live Loads inculding impact
Class A 786.86 0.333 1.500 393.4
70 R Wheel 807.78 0.410 1.500 497.4
70R Boogie 380.49 0.410 1.500 234.3
70 R Track 622.93 0.398 1.500 372.0
497.4
Total 1595.4
N/mm2
116
Design for cracked section
fck = 45 N/mm2
0.67∗45
fcd = = 20.1 N/mm2
1.5
Z = 1621.16 mm
𝑁𝑒𝑑 0.67
σcp = = 4.02 N/mm2 < (0.2fcd=0.22×45× = 4.02N/mm2)
𝐴𝑐 1.5
k =1 + √ ≤ 2=1.335 ≤ 2.0
200
𝑉𝑅
= 1.05 × 300 × 1782 = 558.67 kN
𝑑.𝑐 1000
117
for σcp values (in between) αcw
0.00 1
0.00 5.03 1.2
5.03 10.5 1.25
10.05 20.10 2
N/mm2
Max. allowable shear stress for (ϑ)=45° = αcw×0.225× v1× fck= 6.2318 < 2.262 (ok)
Provided 20 mm diameter of bar and with 2 legged along with spacing of 100 mm.
fy = 500.00 N/mm2
𝑓𝑦𝑘
= = 434.78 N/mm2
fywd = fyd =
500
1.15 1.1
5
bf =2887.5mm
Df = 250mm
118
bw = 300 mm
bw/8 = 37.5 mm
119
Dia. of duct (Ф) = 90mm
bwc=bw,nom= 300 mm
k1 = 1
VRd.c = 1727.399 kN
Reinforcement =Fe500
N/mm2
Geometric Properties
Wearing Course = 75 mm
Cross Girder
120
Size of Fillets = 0 mm
121
Spacing of girders = 0 kN/m
Each cross girder will receive triangular load from deck slab panels on its either side.
Factored loads
122
BM due to WC = 41.051 kNm
123
CG T beam
Reinforcement =Fe500
N/mm2
b = 8.75 m
bw = 0.3 m
bi = 4.225 m
beff1 = beff2 = 0.2 × 4.225 + 0.1 × 2.625 = 1.1075 ≤ 0.2lo = 0.2 × 2.625 = 0.525
≤ bi = 4.225
beff = 1.35 mm
124
Area of stress block = b1× fcd × Xu
125
Web only = 1575 mm
Cover = 80 mm
Xu = 1076.21 mm
fck = 45 N/mm2
fy = 500
fcd = 20.10
fyd = 434.78 MPa
CG @ =447.70 mm from top
C z(mm) C×z
Web 5253.4 1297.30 6,815
Flange 5276.3 1620.00 8,548
Total C= 10529.7 Total M 15,363
So, Mu,lim = 15362.77 kNm CG of C is @ 1459.00 mm from bottom
Ast = 24218.25 mm2
20 mm dia = 𝜋 ∗ 202 =314mm2 = 77.09 nos.
4
So,this section can take 15362.8 kNm with 78 nos. of 20mm dia bars
126
Design of Cross Girder:
127
Provided reinforcement:
Ast=832.25
mm2 Required:
∗ 252=491mm2=1.70nos Ast=832.25mm2
𝜋
4
25 mm dia =
Provided:
(Asmin) = 0.26 ×
3.3
= 0.001716
500
Minimum Area of steel (AS.min) = 0.001716, if (Asmin <0.0013) then adopt that greater value.
BM =95.19kNm
Load Factor =1
128
Factored BM =95.19×0.5×1 =47.6kNm
Live Load
70R Tracked
BM =738.59kNm
Distribution Factor =1
Load Factor =1
Crack width
Actual Stress(σsc) =
184.29N/mm2 bw =300mm
Case I:
Case II:
Hc,eff = (h-xu)/3 =
= 1820 mm
Case III:
129
Hc,eff = h/2= 913 mm
Es = 200000 Mpa(N/mm2)
Kt = 0.50
fcm= fck+10 = 55
= 0.6 ×
𝜎𝑠𝑐
= .0006 (εsm - εcm > 0.6 σsc/Es, safe)
𝐸𝑠
Srmax = 265.870
= 0.1652 mm, (IF Crack width <0.3 then given value is safe).
Shear check
fck = 45 N/mm2
0.67∗45
fcd = = 20.1 N/mm2
1.5
Z = 1738.1 mm
ρl = 𝑏𝑤×
𝐴𝑠𝑡 =0.0038 ≤ 0.02
𝑑
k =1 + √ ≤ 2=1.338 ≤ 2.0
200
𝑉𝑅 300
𝑑.𝑐 1000
= 0.38 × 1745 × = 198.50 kN
N/mm2
Max. allowable shear stress for (ϑ)=45° = αcw×0.225× v1× fck= 5.193 > 0.171 (ok)
132
Asw = × 102 × 2 = 157.08 mm2
𝜋
fy = 500.00 N/mm2
𝑓𝑦𝑘
= = 434.78 N/mm2
fywd = fyd =
500
1.15 1.1
5
133
Design Of End Block
Number of Cable = 5
Side of end block ( 2Yo) = 0.75 m
Side of loaded area ( 2Yp) = 0.244 m
Load in tendon (Pk) = 2730 KN
Yeild strength of steel (fy) = 500 N/m2
Height of girder = 2.4 m
Table for Design brusting tensile strength (Fbst) according to IRC 112
Ypo/Yo 0.3 0.4 0.5 0.6 0.7
Fbst/Pk 0.26 0.23 0.19 0.16 0.12
134
Table for individual square end block design brusting tensile strength
Cable1 Cable 3
For Vertical direction
Yo 0.15 0.15
Ypo 0.122 0.122
Ypo/Yo 0.81333 0.81333
3 3
Fbst/Pk 0.12 0.12
Fbst 327.6 327.6
For Horizontal direction
Yo 0.225 0.375
Ypo 0.122 0.122
Ypo/Yo 0.54222 0.32533
2 3
Fbst/Pk 0.17733 0.2524
3
Fbst 484.12 689.052
Table for overall group rectangle end block design brusting tensile strength
Equivalent 2Ypo = √5 ∗ 0.244 ∗ 0.244 = 0.5456
135
For V For H
Yo 1.2 0.375
Ypo 0.2728 0.2728
Ypo/Yo 0.22733 0.72746
4 7
Fbst/Pk 0.26 0.12
Fbst 709.8 327.6
Maximum bursting force = 709.8 kN
Tensile Strength = 0.87*500 = 435 N/ mm2
Required Ast = 709.8 * 1000/435=1631.7241
mm2 Provide 16 mm, 6-legged bar @ 3 nos
Area of steel provided = π*162*6*3 = 3619.115 mm2
4
136
Maximum bursting force = 709.8 kN
Tensile Strength = 0.87*500 = 435 N/ mm2
Required Ast = 709.8 * 1000/435=1631.7241
mm2 Provide 16 mm, 6-legged bar @ 3 nos
Area of steel provided = π*162*6*3 = 3619.115 mm2
4
π
Ast Provided = 16 mm @ 2 nos
*162*2 = 402.12 mm2 > 393.12 mm2 (ok)
4
=
Spiral Reinforcement
Spiral reinforcement is provided as per M/S Dynamic Prestress
Provide 16 mm dia. bar @ 16 mm = π*162*9 = 1809.5573 mm2
4
137
7. Design of Elastomeric Bearing
Different loads of the bridge superstructure have been calculated and bearings have been
designed for the critical combinations of the calculated loads
Weight of Cross girder End Cross Girder = 97.45 kN (load calculation in girder)
Total Reaction due to Dead Load from Superstructure without Wearing Coat (Wu) = DL of slab
+ DL of railing + DL of Cross Girder + DL of Longitudinal girder + DL of Footpath
= 52.5 × 35/6 +2 × 35/2 + 179.8 + (1.6875 + 11.625 + 2.625 +7.5 +8.25) × 35/2 + 50.625×3/3
= 1108.75 kN
138
3.Braking Load
4.Wind Load
Wind load in transverse direction of bridge (𝐹𝑊𝑇) = PZ × A × G ×
CD Height of bridge < 10.0 m
For plain terrain and basic wind 33.0 m/s,
Vz = 27.8 m/s
Pz= 463.7 N/𝑚2
Basic Design wind speed = 47 m/s
Then,
Vz = 47 × 27.8 = 33.5939 m/s
33
33
33
139
Gust factor, G = 2 for span up to 150 m
𝑊𝑖𝑑𝑡ℎ 𝑜𝑓
𝑏𝑟𝑖𝑑𝑔𝑒 = 8.4 = 3.5
𝐷𝑒𝑝𝑡ℎ 𝑜𝑓 𝑠𝑢𝑝𝑒𝑟 2.4
B/D =
𝑠𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒
= 3.5
Area in transverse direction of bridge (A) = 35 × 2.4 + 21 × 1.1 × 0.15 + 0.11 × (35-21×0.15) =
90.9685 𝑚2
Wind load in Transverse direction of (𝐹𝑊𝑇) each bearing = 0.25Max (𝐹𝑊𝑇)/6 = 0.25 × 352.995/3
= 79.399 kN
Wind load in Vertical direction of bridge (𝐹𝑊𝑇) = PZ × A × G ×
CL CL = 0.75
Plan Area (A) = 8.4 × 35 = 294 𝑚2
𝐹𝑊𝑉 = Pz × A × G × CD = (294× 940.6 ×2 × 0.75)
1000
= 414.805 kN
2 𝑅 𝑔
𝑆𝑎
𝑔
= average response acceleration coefficient,
141
W = Total Dead load along the longitudinal and sum of appropriate live load in transverse
direction.
W along longitudinal direction = 6999.01 kN
W along transverse direction =6999.01 + 0.2 × (853.6057+161.57) = 7202.04 kNF𝑠𝐿
× × 2.5 ×
𝑇 0.36
1
7202.04
= 3240.92 kN
2 1
F𝑠 =
∆
2ℎ0
Maximum horizontal force on a bearing (Fcst) =
×G×A
For common reinforced concrete bridge deck, the longitudinal strain due to temperature
variation,creep and shrinkage is 5 × 10−4.
Horizontal load due to creep, shrinkage and temperature has been distributed to expansion
bearing only.
Horizontal deformation of bearing, ∆ = 5×10-4 × 25300 = 12.65 mm
142
Summary of Loads on bearing
a) Basic Combination
Total vertical load (Carriageway live load as leading) = 1.35DL + 1.75WC + 1.5LL + 0.9𝐹�𝑉 +
1.15𝐹𝑏𝑉
�
= 2532.58 kN
Total horizontal load along longitudinal direction = 0.9 𝐹𝐶𝑆𝑇 + 0.9𝐹𝑉 + 1.5𝐹𝐻
𝑊 𝑏𝑟
= 150.927 kN
143
b) Seismic Combination
= 2078.03 kN
Total horizontal load along longitudinal direction = 0.5 𝐹𝐶𝑆𝑇 + 0.2 𝑏𝐹𝐻
𝑟
= 26.9198 kN
Design of Bearing
Nmin = 1496.815 kN
Nmax=2532.58kN
Hmax = 150.927kN
Length, l = 600 mm
Width, b = 400 mm
𝑙 60
𝑖) 0 = 1.5 < 2 (𝑂𝐾)
�=
� 40
0
40
0 = 80 > ℎ = 76 𝑚𝑚 (𝑂𝐾)
�
𝑖𝑖) =
�
5 5
𝑏 30
𝑖𝑖𝑖) 0 = 30 < ℎ = 76 𝑚𝑚 (𝑂𝐾)
1 =
0 10
𝐴1
𝑖𝑣) 𝑆ℎ𝑎𝑝𝑒
𝑓𝑎𝑐𝑡𝑜𝑟, 𝑆 = 𝑙𝑃 × 𝑡𝑒
𝑡𝑒
=ℎ𝑖 = = 12.32 mm
2 × 1.4 × ℎ 𝑒+ 4 2 × 1.4 × 7+ 4 × 14
× 5
𝑡𝑜𝑡𝑎𝑙 𝑛𝑢𝑚𝑏𝑒𝑟 𝑜𝑓
𝑙𝑎𝑦𝑒𝑟𝑠
232064
𝑆 = 9.5713 > 6 & < 12 (𝑂𝐾)
= 1968 ×
12.32
𝐴
√ 𝑖𝑠 𝑙𝑖𝑚𝑖𝑡𝑒𝑑 𝑡𝑜 2)
𝐴2
1
146
Here, Allowable bearing pressure > Bearing pressure. Hence, OK.
𝜀𝑢,
= 7.0
⸫
𝜀𝑢,𝑑
7
= =
𝛾𝑚 1
S = Shape factor
Ar = Reduced effective plan area due to the loading effects given by,
= 1 × (1 − 𝑉𝑥,𝑑 𝑉𝑦,𝑑
)
𝑎′ 𝑏′
−
𝑉𝑥,𝑑 =
147
� 𝑥𝑖𝑚𝑢𝑚 ℎ𝑜𝑟𝑖𝑧𝑜𝑛𝑡𝑎𝑙 𝑙𝑜𝑎𝑑 𝑖𝑛 𝑡ℎ𝑒
𝑑𝑖𝑟𝑒𝑐𝑡𝑖𝑜𝑛 𝑜𝑓 𝑎
�
� ×ℎ
�
𝐺 × 𝐴1
150.927 ×
1000 × 76
=
1 × 232064
148
= 36.4207 𝑚𝑚
Similarly, 𝑉𝑦, = 0
36.420
𝐴 7 − 0) = 210502.96 𝑚𝑚2
= 232064 × (1 −
𝑟
392
1.5 × 2532.58 × 1000
𝜀𝑐,𝑑 = 1.885 𝑚𝑚
1 × 210502.96 × 9.5713
=
= 0.008665
So,
𝜀𝛼,𝑑 =
149
3922 × 5 + 4922 × 0
0.00866 × 14 = 1.598
2 × (4 × 143 + 2 × 73 )
Now,
150
𝜀𝑡,𝑑 = 𝐾𝐿 (𝜀𝑐,𝑑 + 𝜀𝑞,𝑑 + 𝜀𝛼,𝑑)
b. Reinforcing plate thickness (Clause 5.1.3.5, IRC 83: 2018 (part II))
𝐾𝑝 × × (𝑡1 + 𝑡2) × 𝐾ℎ ×
𝑡𝑠
,
𝛾𝑚
=
𝐴𝑟 × 𝑓𝑦
Kh = factor for induced tensile stresses in reinforcing plate whose value is given as,
Without holes: Kh = 1
With holes: Kh = 2
c. Limiting conditions
151
i. Rotational limitation condition
152
𝑎′ × 𝖺𝑎,𝑑 + 𝑏′ × 𝖺𝑏,𝑑
∑ 𝑉𝑍,𝑑 ≥0
𝐾𝑟,𝑑
−
where,
𝐾𝑟, = 3)
∑ 𝐹𝑍, × 𝑡𝑖 1
∑ 𝑉𝑍,𝑑 × ( 1 )
𝐴
=
1 5 × 𝐺 × 𝑆2
𝐸𝑏𝑒𝑎𝑟𝑖𝑛𝑔
+
2532.58 × 1000 × 1 )
∑ 𝑉𝑍,𝑑 76 1
= 213085.2 × (
5 × 1 × 9.57132
2000
+
= 1.3342 mm
Now,
i. Buckling stability
𝐹𝑍 2 × 𝑎′ × 𝐺 × 𝑆
<
3 × 𝑇𝑒
,𝑑
𝐴
𝑟
153
2532.58 × 2 × 392 × 1 × 9.57
1000 <
3 × 76
213085.2
154
ii. Non sliding condition
Fz, d Min is the minimum value of dead load from superstructure. As rubber has the unique
property that it behaves differently below certain minimum load, F z, d Min has been taken as DL
without considering wearing course, i.e.,
𝐾𝑓
𝜇𝑒 = 0.1 +
1.5 × 𝜎𝑚
𝐹𝑜𝑟𝑐𝑒 1496.815 ×
1000 = 11.851 𝑁/𝑚𝑚2
𝜎 = =
𝑚
𝐴𝑟𝑒 213085.2
𝑎
Then,
0.6
𝜇𝑒 = 0.1 + = 0.1759
11.851
1.5 ×
Here,
Hence, OK.
155
8. Analysis and Design of Pier
For the design of pier, following data has been obtained from hydrological and geotechnical
investigation report.
Bridge span = 35 m
Lane width = 6 m
Depth of pier = Difference between depth of HFL from bed level + scour depth +free Board height
=2.447+2+2.5+1.5 = 8.447 m
RL of HFL = 150.558 m
Material
Concrete: M30 for pier cap and M30 for pier stem (as minimum grade of concrete specified in
IRC SP114-2018)
Rebar: TMT500D
156
Type of Pier
RCC single column hammer headed pier has been selected. As the length of pier is more than 5m
so wall pier system will not be economical. Moreover, for 35m span, strength is also not
sufficient. Also, carriage way is only 6m so single column may be sufficient.
Diameter of stem=2.2m
Length of pier cap = c/c spacing of main girder × 2 + bearing length + 2 × clearance
Case I:
Case II:
Length of one edge of pier cap excluding stem portion = (6.85 – 2.85)/2 =2.325m
=1364.698 kN
157
Figure: Preliminary sizing of pier cap
KcTc = 0.3030
158
8.2 Analysis
Option Explicit
Sub Maximize ()
Dim i As Integer
For i = 1 To 4
LeL = 0
MaxP = 0: MaxBM = 0
Cells(13, 5 × i) = LeL
159
'If Cells(49, 5 × i - 2) > MaxRL Then
'End If
'End If
MaxP = Cells(50, 5 × i - 1)
LL(i, 3) = LeL
PMaxRL = Cells(49, 5 × i - 2)
PMaxRR = Cells(49, 5 × i - 1)
PMaxBM = Cells(52, 5 × i - 1)
End If
MaxBM = Cells(52, 5 × i - 1)
LL(i, 4) = LeL
BMMaxRL = Cells(49, 5 × i - 2)
BMMaxRR = Cells(49, 5 × i - 1)
End If
160
Loop
Next i
End Sub
Class A Loading:
MaxP RL 429.09
RR 103.38 244.28
MaxBM RL 421.18
RR 0.00
MaxP 78.85 532.5
MaxBM 35.70 315.9
MaxP RL 484.21
RR 444.53 29.76
MaxBM RL 10.88
RR 873.61
MaxP 44.70 928.7
MaxBM 49.20 647.0
161
Class 70R Track load:
MaxP RL 310.46
RR 381.66 53.40
MaxBM RL 0.00
RR 668.70
MaxP 38.05 692.1
MaxBM 40.35 501.5
MaxP RL 287.4
RR 401.7 85.71
MaxBM RL 0.0
RR 674.3
MaxP 37.0 689.1
MaxBM 48.2 505.7
=234.168 kN
162
4. Due to Temperature & Shrinkage:
Temperature variation = 30 ˚C
Length = 35 m
No of bearing = 6
.27
.096
Force on pier = 1.1 × (1000 ×
×.0196) × 6
= 363.825 kN
163
Then,
47
Vz = × 27.8 = 33.5939 m/s
33
33
33
Gust factor, G = 2 for span up to 150 m (Clause 209.3.3, IRC 06: 2014)
𝑊𝑖𝑑𝑡ℎ 𝑜𝑓
𝑏𝑟𝑖𝑑𝑔𝑒 = 8.4 = 3.5
𝐷𝑒𝑝𝑡ℎ 𝑜𝑓 𝑠𝑢𝑝𝑒𝑟 2.4
B/D =
𝑠𝑡𝑟𝑢𝑐𝑡𝑢𝑟𝑒
Area in transverse direction of bridge (A)= 35 × 2.4 + 21 × 1.1 × 0.15 + 0.11 × (35-21×0.15) =
93.845 m2
×551.841)
1000
= 275.85 kN
Wind load in Transverse direction of (𝐹𝑊𝑇) each bearing = 0.25Max (𝐹𝑊𝑇)/6 = 0.25 × 417.129/6
= 17.3804 kN
Wind load in Vertical direction of bridge (𝐹𝑊𝑇) = PZ × A × G × CL
164
CL = 0.75
165
Plan Area (A) = 8.4 × 35 = 294 𝑚2
𝐹𝑊𝑉 = Pz × A × G × CD
(294× 940.6 ×2 × 0.75)
= 1000
= 414.805 kN
Vertical Wind Load in each bearing = 414.805/6 = 69.1341 kN
Total Load = 2 × (0.78 × 30.885+0.824 × 30.885+0.952 × 130.425+1 × 130.425+
77.805 × (0.828+0.708+0.588+0.468))
This load is taken by pier only. Braking load on pier is given by:
FH br= 291.6kN
291.6 × 3.345
𝐹𝑏 = = 19.508𝑘𝑁
𝑉
𝑟
25 × 2
Seismic load = 𝑍 × × ×W
𝐼 𝑆𝑎
2 𝑅 𝑔
For 5% damping of RCC structure, 𝑆𝑎 = 2.5 (Clause 219.5.1, IRC 06: 2014)
𝑔
W = Total Dead load along the longitudinal and sum of appropriate live load in transverse
direction.
166
W along longitudinal direction =4102.28 kN
W along transverse direction 4102.28 + 0.2 × (928.74 + 689.14) = 4347.58 kN
×
× 2.5 ×
(Total Seismic Load in longitudinal) F𝑠𝐿 = 0.36
1
1 4102.28
= 615.3412 kN
2
×
× 2.5 ×
(Seismic Load in transverse) F𝑠𝑇 = 0.36
1
1 4347.58
= 652.1367 kN
2
3 6
= 144.919 kN
Horizontal Horizontal
Moment in Moment in
Cases Force Force in Force
Longitudinal Transverse
longitudinal Transverse
Longitudinal 0.0 615.3 0.0 6859.2 0.0
Transverse 0.0 0.0 652.1 0.0 7269.4
167
Vertical Up /
434.8 0.0 0.0 1489.0 543.4
Down
168
Horizontal
Horizontal Force Moment in Moment in
Seismic cases Force Force
in longitudinal Longitudinal Transverse
Transverse
rl + 0.3rt + 0.3rv 130.4 615.3 195.6 7305.9 2343.8
rl + 0.3rt - 0.3rv -130.4 615.3 195.6 6412.5 2017.8
0.3 rl + rt +0.3rv 130.4 184.6 652.1 2504.5 7432.4
0.3 rl + rt -0.3rv -130.4 184.6 652.1 1611.0 7106.3
0.3 rl + 0.3 rt + rv 434.8 184.6 195.6 3546.8 2724.3
0.3 rl + 0.3 rt - rv -434.8 184.6 195.6 568.7 1637.4
Seismic load = 𝑍 × × ×W
𝐼 𝑆𝑎
2 𝑅 𝑔
For 5% damping of RCC structure, 𝑆𝑎 = 2.5 (Clause 219.5.1, IRC 06: 2014)
𝑔
W = Total Dead load along the longitudinal and sum of appropriate live load in transverse
direction.
W along longitudinal direction = 2063.295 kN
W along transverse direction = 2063.295 kN
×
× 2.5 ×
Seismic Load in transverse (F𝑠𝑇)= 0.36
1
1 2063.295
= 928.483 kN
2
169
Vertical Seismic load = 2 ×
217.3789
3 6
= 144.919 kN
170
Total Seismic load in longitudinal direction (𝐹𝐿𝑆)= 309.49
kN Seismic load in Transverse direction 𝐹𝑇𝑆 = 928.48 kN
Horizontal Horizontal
Moment in Moment in
cases Force Force in Force
Longitudinal Transverse
longitudinal Transverse
Longitudinal 0.0 309.5 0.0 1771.4 0.0
Transverse 0.0 0.0 928.5 0.0 5314.2
Vertical Up /
Down 619.0 0.0 0.0 0.0 0.0
Horizontal
Horizontal Force Moment in Moment in
Seismic cases Force Force
in longitudinal Longitudinal Transverse
Transverse
rl + 0.3rt + 0.3rv 185.7 309.5 278.5 1771.4 1594.3
rl + 0.3rt - 0.3rv -185.7 309.5 278.5 1771.4 1594.3
0.3 rl + rt +0.3rv 185.7 92.8 928.5 531.4 5314.2
0.3 rl + rt -0.3rv -185.7 92.8 928.5 531.4 5314.2
0.3 rl + 0.3 rt + rv 619.0 92.8 278.5 531.4 1594.3
0.3 rl + 0.3 rt - rv -619.0 92.8 278.5 531.4 1594.3
171
Load due to water current:
𝐹𝑇𝑊𝐶 = 𝑃×𝐴
V = 3.0623 m/s
Width at HFL= 3 m
𝐸𝑥𝑖𝑠𝑡𝑖𝑛𝑔 𝑑𝑖𝑟𝑒𝑐𝑡𝑖𝑜𝑛 𝑜𝑓 𝑓𝑙𝑜𝑤 𝑎𝑛𝑔𝑙𝑒 𝑤𝑖𝑡ℎ 𝑝𝑖𝑒𝑟 𝑎𝑥𝑖𝑠 𝑖𝑛 𝑟𝑖𝑣𝑒𝑟 𝜃 = 0° (𝑓𝑜𝑟𝑚 𝑡𝑜𝑝𝑜
𝑚𝑎𝑝)
5o
∴𝐹
𝑤 = 52 × 0.66 × (3.0623 × 𝑐𝑜𝑠15)^2 × 14.841 × 9.81/1000 = 44.883𝑘𝑁
𝑇
∴𝐹
𝑤 = 52 × 0.66 × (3.0623 × 𝑠𝑖𝑛25)^2 × 14.841 × 9.81/1000 = 16.336𝑘𝑁
𝐿
172
Scour Depth = 4.947m
173
Height of submerged portion of pier(H) = 6.947m
H/re = 4.4972
H/Re=3, Ce=.675
H/Re=4, Ce=0.73
𝐹𝑏𝑢𝑜𝑦 = 𝑉𝑠𝑢𝑏𝑚𝑒𝑟𝑔𝑒𝑑 × 𝛾𝑤
8.3 Design
Pier cap has been designed as cantilever beam and detailed as per IRC-112
174
Figure. Pier cap (section and plan) showing critical sections
Load Combinations
a) Basic Combination
Case I:
Case II:
175
Case III:
Case IV:
b) Seismic Combination
176
Depth of Triangle = 750 mm
Width = 2325 mm
Cover = 0.075 m
177
Finding Area Of the given Geometry
Area CG of
SNo of C C Area of C
. Depth Width Stripe stripe Strain Stress Stress CG Force Moment
1 1250 2325 0.0035 13.4
11625 1557.7
2 1200 2325 0 1225 0.0023 13.4 670.000 1225 5 1908.244
11625 10.49 1176. 1388.7
3 1150 2325 0 1175 0.0011 3 597.315 014 58 1633.199
11625 1133. 609.88
4 1100 2325 0 1125 -1E-04 0 262.315 333 28 691.2005
11625
0 0 0
5 1050 2325 0 1075 -0.001 0 0.000
11625
0 0 0
6 1000 2325 0 1025 -0.003 0 0.000
11625
0 0 0
7 950 2325 0 975 -0.004 0 0.000
11625
0 0 0
8 900 2325 0 925 -0.005 0 0.000
11625
0 0 0
9 850 2325 0 875 -0.006 0 0.000
11625
0 0 0
10 800 2325 0 825 -0.007 0 0.000
11625
0 0 0
11 750 2325 0 775 -0.009 0 0.000
11237 725.2
0 0 0
12 700 2170 5 874 -0.01 0 0.000
10462 675.3
0 0 0
13 650 2015 5 086 -0.011 0 0.000
178
625.3
0 0 0
14 600 1860 96875 333 -0.012 0 0.000
575.3
0 0 0
15 550 1705 89125 623 -0.014 0 0.000
525.3
0 0 0
16 500 1550 81375 968 -0.015 0 0.000
475.4
0 0 0
17 450 1395 73625 386 -0.016 0 0.000
425.4
0 0 0
18 400 1240 65875 902 -0.017 0 0.000
375.5
0 0 0
19 350 1085 58125 556 -0.018 0 0.000
325.6
0 0 0
20 300 930 50375 41 -0.02 0 0.000
275.7
0 0 0
21 250 775 42625 576 -0.021 0 0.000
225.9
0 0 0
22 200 620 34875 259 -0.022 0 0.000
176.1
0 0 0
23 150 465 27125 905 -0.023 0 0.000
126.6
0 0 0
24 100 310 19375 667 -0.024 0 0.000
77.77
0 0 0
25 50 155 11625 778 -0.026 0 0.000
33.33
0 0 0
26 0 0 3875 333 -0.027 0 0.000
0.115
xu/d= 151 Moment 4232.643
179
Check For Provided Depth
Taking M25 concrete and diameter of Bars 32mm and average depth 875 mm. characteristics
strength of concrete is 30 MPa. Clear cover of concrete is 40mm.
Design of reinforcement
fy =500 N/mm2
Provide bar of = 32 mm
Transverse reinforcement
Spacing = 612.760 mm
180
Spacing adopted =200 mm c/c
mm2
fctm = 2.5
(Asmin) = 0.26 ×
2.5
= 0.0013
500
Minimum Area of steel (AS.min) = 0.00130, if (Asmin >0.0013) then adopt that greater value.
Total 1996.742
181
Total Moment = 2851.130 kNm
182
Crack width
Case I:
Case II:
Hc,eff = (h-x)/3 =
= 352 mm
CG Factor β2 = 0.41597
Case III:
Es = 200000 Mpa(N/mm2)
Kt = 0.05
fcm= fck+10 = 40
183
N/mm2 Fct,eff = 2.50
184
ρ1, eff = 0.0593
𝐸𝑠
α e= = 6.413
𝐸𝑐𝑚
= 0.6 ×
𝜎𝑠𝑐
= .0005 (εsm - εcm > 0.6 σsc/Es, safe)
𝐸𝑠
Srmax = 227.738
= 0.1685 mm, (IF Crack width <0.3 then given value is safe).
Shear check
Diameter of Bars = 32 mm
500
𝑓𝑦𝑘
fyd =
1.15
= = 434.8 N/mm2
1.15
Es = 2000000 N/mm2
0.200
εuk = = 0.0222
.9
εud = 0.200
185
434.8
ε = 200000 = 0.00022
0
Steel
Strain Stress, σcd
-0.02222 -483.0917874
-0.02000 -434.78261
0.00000 0.00000
0.02000 434.78261
500
𝑓𝑦𝑘
Design stress, fpd=
1.15
= = 434.8 N/mm2
1.15
fck = 30 N/mm2
0.67∗30
fcd = = 13.4 N/mm2
1.5
N/mm2 Z = 833.09 mm
𝑁𝑒𝑑 0.67
σcp= = 0 < (0.2fcd=0.22×30× = 2.68 N/mm2)
𝐴𝑐 1.5
bw = 2350 mm
lever arm factor j= 0.95
186
𝐴𝑠𝑡
ρl = 𝑏𝑤× =0.0095 ≤ 0.02
𝑑
187
k =1 + √ ≤ 2=1.47809 ≤ 2.0
200
𝑉𝑅 875
𝑑.𝑐 1000
= 0.50 × 2325 × = 1012.16 kN
0.00 1
0.00 3.35 1
3.35 6.70 1.25
6.70 20.10 2.5
N/mm2
Max. allowable shear stress for (ϑ)=45° = αcw×0.225× v1× fck= 3.6581 < 2.262 (ok)
Provided 20 mm diameter of bar and with 2 legged along with spacing of 100 mm.
188
Asw = × 202 × 2 = 628.32 mm2
𝜋
4
fy = 500.00 N/mm2
189
𝑓𝑦𝑘
= = 434.78 N/mm2
fywd = fyd =
500
1.1
1.15 5
190
Analysis And Design of pier Stem
Point of
Load Type Unfactor load Unit application from
bottom(m)
Vertical Combination
DL, super (DLss) 2814.14 kN 0
DL, wearing coat (DLwc) 173.25 kN 0
Braking Load -25.10 kN 0.75
Live Load on span (LLs) 3256.75 kN 0.75
Seismic Vertical Super (FvS) 434.757855 kN 0.75
Seismic Vertical Sub (FvSu) 618.988661 kN 0.75
Wind Vertical 414.80 kN 0.75
Pedestal 48.00 kN 0
Pier (Wpier) 1364.70 kN 0
Horizontal Combination
Check Transverse
Water current (Fwa) 44.88 kN 3.298
Wind super (Fwi) 430.32 kN 7.723
Wind sub (Fwi) 20.01 kN 3.2235
Seismic super (Fse) 184.60 kN 7.723
Seismic sub (Fse) 92.85 kN 3.2235
Hydrodynamic (Fhyd) 58.72 kN 3.298
Buoyancy (Fbuoy) 259.16 kN 4.2235
Horizontal Temperature (Ftem) 363.83 kN 8.485
Check Longitudinal
Water Current (Fwa) 16.3361265 kN 3.298
Wind Super (Fwi) 107.579792 kN 7.723
Wind sub (Fwi) 5.00283928 kN 3.2235
Seismic Super (Fse) 615.341285 kN 7.723
Seismic Sub (Fse) 92.8482991 kN 3.2235
Braking (Fba) 234.168286 kN 12.198
Long Temperature (Ftem) 363.825 kN 8.485
191
Load combination for ultimate state:
192
Load combination for serviceability state:
SERVICEABILITY STATE
Quasi
Rare Load Combinations Frequent Load Combinations Combination
Live Live wind wind Thermal Thermal Braking Braking Live Live wind wind Thermal Thermal Braking Braking
Quasi Quasi
Load Type leading leading leading leading leading leading leading leading leading leading leading leading leading leading leading leading
while while
while while while while while while while while while while while while while while while while
dead dead
Dead Dead Dead Dead Dead Dead Dead Dead Dead Dead Dead Dead Dead Dead Dead Dead
leading relieving
Adding relieving Adding relieving Adding relieving Adding relieving Adding relieving Adding relieving Adding relieving Adding relieving
Vertical Combination LF1 LF2 LF3 LF4 LF5 LF7 LF8 LF9 LF1 LF2 LF3 LF4 LF5 LF7 LF8 LF9 LF1 LF2
DL, super (DLss)
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
DL, wearing coat (DLwc)
1.2 1 1.2 1 1.2 1 1.2 1 1.2 1 1.2 1 1.2 1 1.2 1 1.2 1
Braking Load 0.75 0.75 0.75 0.75 0.75 0.75 1 1 0.2 0.2 0.2 0.2 0.2 0.2 0.75 0.75 0 0
Live Load on span (LLs) 1 1 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.2 0.2 0.2 0.2 0.2 0.2 0 0
Seismic Vertical Super (FvS)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Seismic Vertical Sub (FvSu)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Wind Vertical 0.6 0.6 1 1 0.6 0.6 0.6 0.6 0.5 0.5 0.6 0.6 0.5 0.5 0.5 0.5 0 0
Pedestal 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Pier (Wpier) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Water current (Fwa)
1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0
Wind super (Fwi)
0.6 0.6 1 1 0.6 0.6 0.6 0.6 0.5 0.5 0.6 0.6 0.5 0.5 0.5 0.5 0 0
Wind sub (Fwi)
0.6 0.6 1 1 0.6 0.6 0.6 0.6 0.5 0.5 0.6 0.6 0.5 0.5 0.5 0.5 0 0
Seismic super (Fse)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Seismic sub (Fse)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Hydrodynamic (Fhyd)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Buoyancy (Fbuoy)
0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15
Horizontal Temperature (Ftem)
0.6 0.6 0.6 0.6 1 1 0.6 0.6 0.6 0.6 0.5 0.5 0.6 0.6 0.6 0.6 0.5 0.5
Water Current (Fwa) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0
Wind Super (Fwi)
0.6 0.6 1 1 0.6 0.6 0.6 0.6 0.5 0.5 0.6 0.6 0.5 0.5 0.5 0.5 0 0
Wind sub (Fwi)
0.6 0.6 1 1 0.6 0.6 0.6 0.6 0.5 0.5 0.6 0.6 0.5 0.5 0.5 0.5 0 0
Seismic Super (Fse)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Seismic Sub (Fse)
0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Braking (Fba)
0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.2 0.2 0.2 0.2 0.2 0.2 0.75 0.75 0 0
Long Temperature (Ftem)
0.6 0.6 0.6 0.6 1 1 0.6 0.6 0.5 0.5 0.5 0.5 0.6 0.6 0.5 0.5 0.5 0.5
174
Ultimate Shear and Bending moment:
175
Serviceability Shear and Bending moment:
Resultant
Resultant
Cases PZ HL HT ML MT Mpz shear
moment(kNm)
force(kN)
Case 1 8112.084 572.2512 477.8069 4197.1621 4556.577 2615.1116 8810.1554 745.5004
Case 2 8077.434 572.2512 477.8069 4197.1621 4556.577 2615.1116 8810.1554 745.5004
Case 3 7463.817 752.3834 522.84 5552.3067 4895.364 2128.9115 9531.1202 916.2109
Case 4 7429.167 752.3834 522.84 5552.3067 4895.364 2128.9115 9531.1202 916.2109
Case 5 7297.895 717.7812 623.3369 5431.9841 5791.399 2004.4701 9944.6691 950.6623
Case 6 7263.245 717.7812 623.3369 5431.9841 5791.399 2004.4701 9944.6691 950.6623
Case 7 7291.621 572.2512 477.8069 4197.1621 4556.577 1999.7646 8194.8083 745.5004
Case 8 7256.971 572.2512 477.8069 4197.1621 4556.577 1999.7646 8194.8083 745.5004
Case 9 7270.217 527.2181 301.3736 3858.3759 2592.164 1983.7119 6631.978 607.2767
Case 10 7235.567 527.2181 301.3736 3858.3759 2592.164 1983.7119 6631.978 607.2767
Case 11 5520.483 535.8687 312.6319 3888.4566 2676.86 671.41087 5392.1815 620.3982
Case 12 5485.833 535.8687 312.6319 3888.4566 2676.86 671.41087 5392.1815 620.3982
Case 13 5479.002 527.2181 337.7561 3858.3759 2900.869 640.30052 5467.5262 626.1295
Case 14 5444.352 527.2181 337.7561 3858.3759 2900.869 640.30052 5467.5262 626.1295
Case 15 5465.199 527.2181 430.1662 3858.3759 4163.175 629.94836 6306.1349 680.4424
Case 16 5430.549 527.2181 430.1662 3858.3759 4163.175 629.94836 6306.1349 680.4424
Case 17 4625.268 220.7872 181.9125 1707.7151 1543.528 0 2301.9053 286.0755
Case 18 4590.618 220.7872 181.9125 1707.7151 1543.528 0 2301.9053 286.0755
Maximum Resultant 9944.6691 950.6623
176
Design of pier stem:
1. Slenderness ratio
which became bottom end rigidly fixed with foundation & top end is free to translate as well as
rotate.
2. Minimum Eccentricities
𝐿 𝐷 8447 2200
emin = + = + = 90.227 mm
500 30 500 30
e = 0.05d = 110 mm
Hence, column must be designed by taking moments and forces due to external loads only.
3. Longitudinal Reinforcement:
fy = 500 N/m2
fck = 30
N/mm2
Effective cover = 60 mm
Clear cover = 44 mm
Diameter of bar = 32 mm
177
p/fck from area of
cases pu/fckd2 mu/fckd3 graph p% steel
1 0.0791751 0.04114 0.0075 0.225 8552.99
2 0.0730389 0.04467 0.0105 0.315 11974.2
3 0.0730389 0.04724 0.012 0.36 13684.8
4 0.0712643 0.04085 0.01 0.3 11404
5 0.0530834 0.0382 0.035 1.05 39913.9
Maximum P % = 1.05 %
Adopted P % = 1.4 % (If adopted pier > 0.8 % “ok”, “Not ok”)
= 53218.579 m2
fctm = 2.2
178
Minimum Area of steel (Amin) = 0.0013 (If 0.001144 > 0.0013)
Transverse Reinforcement:
Shear Design:
Diameter of bars = 32 mm
fck = 30 N/mm2
Clear cover = 40 mm
f𝑓𝑦𝑘 500
yd =
1.15
= = 434.8 N/mm2
1.15
εud = 0.200
434.8
ε = 200000 = 0.00022
0
180
k =1 + √ ≤ 2 = 1.302 ≤ 2.0
200
VRd.c,min = (0.031k3/2 ck
f 1/2 + 0.15 σcp ) × bw × d = 1220.224 kN
The column withstand a shear is 1928.930 kN, so, 1220.224 kN is lesser than 1928.930 kN .
So, shear design not required due to 1928.930 kN is greater than 1574.554 kN.
Crack width
2.325 m
Case I:
Case II:
CG Factor β2 = 0.41597
181
Case III:
182
Ac,eff = 308000 mm2
Es = 200000 Mpa(N/mm2)
Kt= 0.05
fcm= fck+10 = 40
= 0.6 ×
𝜎𝑠𝑐
𝐸𝑠
= .0005 (εsm - εcm >0.6 σsc/Es, safe)
Srmax = 136.00
Confinement Of Pier
α = 0.67
fyd = fyk/γs
183
γs is taken as 1.15 for basic and seismic combination, and 1.0 for accidental combination.
γs = 1.15
𝑓𝑦𝑘
= = 434.78 N/mm2
fyd =
500
1.15 1.1
5
Clear cover = 50 mm
ωwd = 0.2157
ωw,min = 0.2157
Required d = 17.9389 m
184
Designed ωwd = 0.215
185
8.4 Analysis and Design of Spread Footing
Table: Response of footing at its base in basic and seismic combination of loads.
Point of Point of
application application
Load Type Unfactored load Unit
from bottom for from bottom
stability for design
Vertical Combination
DL, super (DLss) 2814.14 KN 4.70115 0
DL, wearing coat (DLwc) 173.25 KN 4.70115 0
Braking Load -25.10 4.70115 0.75
Live Load on span (LLs) 3256.75 KN 4.70115 0.75
Seismic Vertical Super (FvS) 434.76 KN 4.70115 0.75
Seismic Vertical Sub (FvSu) 466.57 KN 4.70115 0.75
Wind Vertical 414.80 KN 4.70115 0.75
Pedestal 48.00 KN 4.70115 0
Pier (Wpier) 1555.23 KN 4.70115 0
Foundation 3290.81 KN 4.70115 0
Check Transverse
Water current (Fwa) 44.88 KN 5.298 5.298
Wind super (Fwi) 430.32 KN 9.723 9.723
Wind sub (Fwi) 20.01 KN 5.2235 5.2235
Seismic super (Fse) 184.60 KN 9.723 9.723
Seismic sub (Fse) 69.99 KN 5.2235 5.2235
Hydrodynamic (Fhyd) 58.72 KN 5.298 5.298
Buoyancy (Fbuoy) 259.16 KN 6.2235 6.2235
HZ Temprature(Ftem) 363.83 KN 10.485 10.485
186
Check Longitudinal
Water Current(Fwa) 16.34 KN 5.298 5.298
Wind Super(Fwi) 107.58 KN 9.723 9.723
Wind sub(Fwi) 5.00 KN 5.2235 5.2235
Seismic Super(Fse) 615.34 KN 9.723 9.723
Seismic Sub(Fse) 69.99 KN 5.2235 5.2235
Braking(Fba) 234.17 KN 14.198 14.198
Long Temprature(Ftem) 363.83 KN 10.485 10.485
187
Seismic Load
Load Type Basic Load Combinations
Combinations
Check Longitudinal
Water Current(Fwa) 1 1 1 1 1
Wind Super(Fwi) 0.9 1.5 0.9 0.9 0
Wind sub(Fwi) 0.9 1.5 0.9 0.9 0
Seismic Super(Fse) 0 0 0 0 1.5
Seismic Sub(Fse) 0 0 0 0 1.5
Braking(Fba) 1.15 1.15 1.15 1.5 0.2
Long Temprature(Ftem) 0.9 0.9 1.5 0.9 0.5
188
Load combination for ultimate state:
Check Longitudinal
Water Current (Fwa) 1 1 1 1 1 1 1 1
Wind Super (Fwi) 0.9 1.5 0.9 0.8 1.3 0.8 0 0
Wind sub (Fwi) 0.9 1.5 0.9 0.8 1.3 0.8 0 0
Seismic Super (Fse) 0 0 0 0 0 0 1.5 1.5
Seismic Sub (Fse) 0 0 0 0 0 0 1.5 1.5
Braking (Fba) 1.15 1.15 1.5 1 1 1.3 0.2 0.75
Long Temprature
0.9 0.9 0.9 0.8 0.8 0.8 0.5 0.5
(Ftem)
189
Load Type Load Combinations
190
Quasi
Load Type RareLoad Combinations Frequent Load Combinations
Combination
wind Therma Thermal Brakin braking Live wind Therma Thermal Brakin braking
Live Live wind Live wind Quasi
leading l leading g leading leading leading l leading g leading Quasi
leading leading leading leading leading while
while leading while leading while while while leading while leading while while
Vertical Combination while while while while while dead
Dead while Dead while Dead Dead Dead while Dead while Dead dead
Dead Dead Dead Dead Dead relievin
relievin Dead relievin Dead relievin relievin relievin Dead relievin Dead relievin leading
Adding relieving Adding Adding Adding g
g Adding g Adding g g g Adding g Adding g
DL, super(DLss) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
DL, wearing coat(DLwc) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Braking Load 1.2 1 1.2 1 1.2 1 1.2 1 1.2 1 1.2 1 1.2 1 1.2 1 1.2 1
Live Load on span(LLs) 0.75 0.75 0.75 0.75 0.75 0.75 1 1 0.2 0.2 0.2 0.2 0.2 0.2 0.75 0.75 0 0
Seismic Vertical Super(FvS) 1 1 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.2 0.2 0.2 0.2 0.2 0.2 0 0
Seismic Vertical Sub(FvSu) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Wind Vertical 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Pedestal 0.6 0.6 1 1 0.6 0.6 0.6 0.6 0.5 0.5 0.6 0.6 0.5 0.5 0.5 0.5 0 0
Pier(Wpier) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Foundation 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
Check Transverse
Water current (Fwa) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0
Wind super(Fwi) 0.6 0.6 1 1 0.6 0.6 0.6 0.6 0.5 0.5 0.6 0.6 0.5 0.5 0.5 0.5 0 0
Wind sub(Fwi) 0.6 0.6 1 1 0.6 0.6 0.6 0.6 0.5 0.5 0.6 0.6 0.5 0.5 0.5 0.5 0 0
Seismic super(Fse) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Seismic sub(Fse) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Hydrodynamic (Fhyd) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Buoyancy(Fbuoy) 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15 0.15
HZ Temprature(Ftem) 0.6 0.6 0.6 0.6 1 1 0.6 0.6 0.6 0.6 0.5 0.5 0.6 0.6 0.6 0.6 0.5 0.5
Check Longitudinal
Water Current(Fwa) 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 0 0
Wind Super(Fwi) 0.6 0.6 1 1 0.6 0.6 0.6 0.6 0.5 0.5 0.6 0.6 0.5 0.5 0.5 0.5 0 0
Wind sub(Fwi) 0.6 0.6 1 1 0.6 0.6 0.6 0.6 0.5 0.5 0.6 0.6 0.5 0.5 0.5 0.5 0 0
Seismic Super(Fse) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Seismic Sub(Fse) 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0
Braking(Fba) 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.75 0.2 0.2 0.2 0.2 0.2 0.2 0.75 0.75 0 0
Long Temprature(Ftem) 0.6 0.6 0.6 0.6 1 1 0.6 0.6 0.5 0.5 0.5 0.5 0.6 0.6 0.5 0.5 0.5 0.5
188
Moment at toe due to different load for stability analysis:
Resultant Resultant
Cases PZ HL HT ML MT MPZ
MHZ((kNm)) HZ(kN)
Live Leading 7081.7 816.5 714.4 7772.6 8308.1 33292.3 11377.1 1084.9
10345.
Wind Leading 7081.7 1086.7 781.9 7 8951.4 33292.3 13680.7 1338.8
Temperature 10061. 10597.
Leading 7099.1 1034.8 932.7 5 0 33373.8 14612.6 1393.1
Braking Leading 7081.7 816.5 796.4 7772.6 9471.8 33292.3 12252.7 1140.5
12181.
Seismic Leading 2706.0 926.6 1273.1 7309.9 6 12721.2 14206.6 1574.6
189
Moment at base centre of foundation due to serviceability condition:
Resultant Resultant
Cases PZ HL HT ML MT Mpz
Moment(kNm) SF(kN)
Case
1 10676.6 572.3 477.8 3227.4 3020.9 2615.0 7035.6 745.5
Case
10642.0 572.3 477.8 3227.4 3020.9 2615.0 7035.6 745.5
2
Case
3 10028.4 752.4 522.8 4948.3 3451.1 2128.8 8161.7 916.2
Case
9993.7 752.4 522.8 4948.3 3451.1 2128.8 8161.7 916.2
4
Case
5 9862.4 717.8 623.3 3227.4 3926.6 2004.3 7087.1 950.7
Case
9827.8 717.8 623.3 3227.4 3926.6 2004.3 7087.1 950.7
6
Case
7 9856.1 572.3 477.8 3227.4 3020.9 1999.6 6420.2 745.5
Case
9821.5 572.3 477.8 3227.4 3020.9 1999.6 6420.2 745.5
8
Case
9 9834.9 527.2 301.4 2797.2 2004.6 1983.7 5425.0 607.3
Case
9800.2 527.2 301.4 2797.2 2004.6 1983.7 5425.0 607.3
10
Case
11 8085.1 535.9 312.6 3227.4 2112.1 671.4 4528.5 620.4
Case
8050.5 535.9 312.6 3227.4 2112.1 671.4 4528.5 620.4
12
Case
13 8043.7 527.2 337.8 2797.2 2231.0 640.3 4218.2 626.1
Case
8009.0 527.2 337.8 2797.2 2231.0 640.3 4218.2 626.1
14
Case
15 8029.7 527.2 430.2 2797.2 2686.9 629.8 4508.5 680.4
Case
7995.1 527.2 430.2 2797.2 2686.9 629.8 4508.5 680.4
16
Case
17 7190.0 220.8 181.9 408.2 1132.1 0.0 1203.5 286.1
Case
7155.3 220.8 181.9 408.2 1132.1 0.0 1203.5 286.1
18
190
Check for stability of Pier:
Seismic case:
= 33373.58/14612
= 33373.58/14612.6
= V tanΦ/H
191
= 7099.1×0.8/1574.6
= V tanΦ/H
= 7099.1×0.8/1393.1
Resultan
Cases PZ HL HT ML MT MPZ Resultan
t Hz
t MHz
Case 1 11113.1 623.0 614.3 5427.6 7226.0 2423.7 9037.4 874.9
Case 2 11527.9 1073.3 726.9 9716.1 8298.1 2734.8 12777.4 1296.3
Case 3 8782.7 877.6 1049.2 7588.1 10163.2 676.0 12683.5 1367.8
Case 4 8296.2 1073.3 476.4 9716.1 4886.8 311.1 10875.9 1174.3
192
y = 9.4/2 = 4.7 m
Footing Analysis
fck = 30 N/mm2
Clear cover = 75 mm
Fy = 500 N/mm2
Length = 9400 mm
Breadth = 7000 mm
Resultant Resultant
Cases PZ HL HT ML MT MPZ
Moment Hz
Case 1 15565.5 1036.8 714.4 9143.6 8308.1 1821.1 14175.5 1259.1
Case 2 14425.6 1307.0 781.9 11716.7 8951.4 1393.7 16138.5 1523.0
Case 3 12214.5 1036.8 796.4 9143.6 9471.8 1390.4 14555.5 1307.3
Case 4 12090.1 955.4 631.6 8333.3 7320.7 1578.3 12670.5 1145.3
Case 5 13940.9 1180.5 687.9 10477.5 7856.8 1211.9 14308.0 1366.3
Case 6 12220.4 955.4 701.9 8333.3 8318.2 1209.0 12983.4 1185.5
Case 7 14498.8 926.6 1273.1 7309.9 12181.6 1421.1 15627.6 1574.6
Case 8 12693.7 926.6 1401.9 7309.9 14010.2 744.2 16546.8 1680.4
193
Calculation of stress for different cases :
Wind as leading combination has maximum stress and braking as leading has minimum stress.
194
Bending Moment at different position :
Design of Foundation:
= 0.80952×30×1909×0.62
= 189972.5 kN
195
Reinforcement Detailing
Mu = β1×fck×b×xu×d×(d-β2xu)
Xu actual = 11.098 mm
= 0.80952×30×11.098 × 9400
= 1129.8 kN
= 1129.8/(500/1.15)
= 2598.59 mm2
= 23333.74207 mm2
= 470000 mm2
Spacing = 23333.74207/(804.25)
= 335.56 mm
196
Provide bar of 32 mm @ 220 mm c/c
Transverse Reinforcement
= 0.0012×9400×1909
= 2290.8 mm2
= 2290.8/490.87
= 214.28 mm
197
Resultant Resultant
Cases PZ HL HT ML MT Mpz
moment SF
2615.11164 745.500428
Case 1 7921.552413 572.2512 477.806919 3218.5061 3018.854 7027.850034
7 3
2615.11164 745.500428
Case 2 7886.902413 572.2512 477.806919 3218.5061 3018.854 7027.850034
7 3
916.210910
Case 3 7273.285511 752.38341 522.839972 4933.9152 3447.706 2128.91147 8148.063907
2
916.210910
Case 4 7238.635511 752.38341 522.839972 4933.9152 3447.706 2128.91147 8148.063907
2
2004.47010
Case 5 7107.363687 717.7812 623.336919 3218.5061 3924.56 7079.994812 950.662278
2
2004.47010
Case 6 7072.713687 717.7812 623.336919 3218.5061 3924.56 7079.994812 950.662278
2
1999.76457 745.500428
Case 7 7101.08965 572.2512 477.806919 3218.5061 3018.854 6412.502961
4 3
1999.76457 745.500428
Case 8 7066.43965 572.2512 477.806919 3218.5061 3018.854 6412.502961
4 3
1983.71192 607.276725
Case 9 7079.686113 527.218148 301.373599 2789.6539 2002.871 5417.902098
2 9
198
527.218147 301.373599 2789.65388 1983.71192 607.276725
Case 10 7045.036113 2002.8713 5417.902098
9 2 5 2 9
535.868700 312.631862 3218.50614 671.410865 620.398215
Case 11 5329.951371 2110.0843 4519.947956
4 3 4 2 1
535.868700 312.631862 3218.50614 671.410865 620.398215
Case 12 5295.301371 2110.0843 4519.947956
4 3 4 2 1
527.218147 337.756099 2789.65388 640.300523 626.129505
Case 13 5288.470915 2229.2978 4211.28601
9 2 5 3 8
527.218147 337.756099 2789.65388 640.300523 626.129505
Case 14 5253.820915 2229.2978 4211.28601
9 2 5 3 8
527.218147 430.166156 2789.65388 629.948361 680.442427
Case 15 5274.668033 2685.2142 4501.969069
9 3 5 5 8
527.218147 430.166156 2789.65388 629.948361 680.442427
Case 16 5240.018033 2685.2142 4501.969069
9 3 5 5 8
220.787247 407.601723 286.075455
Case 17 4434.736884 181.9125 1132.1324 0 1203.271804
1 1 3
220.787247 407.601723 286.075455
Case 18 4400.086884 181.9125 1132.1324 0 1203.271804
1 1 3
Maximum
8148.063907 950.662278
Resultant
199
Crack Width:
σmax = 189.511
N/mm2
200
Point Position From left σmax
M 0 30.98050329
A 1.69215 59.511624
B 3.60115 91.69902431
O 4.70115 110.245981
C 5.80115 128.7929377
D 7.71015 160.980338
N 9.4023 189.5114587
At M, σmax = 30.9805
kN/m2 At M, σmin =
189.511 kN/m2
201
Maximum SF at A = (309805+59.511)/2 × (1.69215 − 0) × 1= 76.53 KN
202
Maximum SF at D = (189.511+160.98)/𝟐 × (9.4-7.71) × 1 = 296.51 KN
Case I:
Case II:
Hc,eff = (h-x)/3 =
=636 mm
CG Factor β2 =0 0.41597
Case III:
= 2139023 mm2
Es = 200000 Mpa(N/mm2)
Kt=0 0.05
fcm= fck+10 = 40
203
N/mm2 Fct,eff=2.50
204
Ecm = 31187 Mpa(N/mm2)
ρ1,eff= 0.0161
𝐸𝑠
𝐸𝑐
αe= = 6.413
𝑚
= 0.6 ×
𝜎𝑠𝑐
= 0.0004 (εsm - εcm >0.6 σsc/Es , 0.0004,Take)
𝐸𝑠
Srmax = 473.262
= 0.0237 mm <0.3mm
Shear check
Diameter of Bars = 32 mm
f𝑓𝑦𝑘 500
yd =
1.15
= = 434.8 N/mm2
1.15
Es = 2000000 N/mm2
0.200
εuk = = 0.0222
0.9
εud = 0.200
434.8
ε = 200000 = 0.00022
0
500
𝑓𝑦𝑘
Design stress, fpd=
1.15
= = 434.8 N/mm2
1.15
205
Flexural tensile stress, σp = 599.782 N/mm2
206
Width of the foundation = 1000 mm
k =1 + √ ≤ 2=1.324 ≤ 2.0
200
207
9. Analysis and Design of Abutments
Load at mid-section
Weight of slab =8.4×0.25×1×25 = 52.5 kN/m
Weight of girder=70.32kN/m
Where, weight of girder consists of
a. Fillet=0.45×0.15×6×25=5.06kN/m
b. Middle Web=0.3×1.550×3×25=34.875kN/m
c. Bottom trap.= (0.5× (0.3+0.75)) ×0.2×3×25 = 7.88kN/m
d. Bottom =0.75×0.4×3×25 =22.5kN/m
Railing =2kN/m
Footpath =1.2×0.275×2×25 =16.5kN/m
Surfacing =6×0.075×1×22 =9.9kN/m
Load at end-section
Weight of slab = 8.4×0.25×1×25 = 52.5 kN/m
Weight of girder = 0.75×2.15×3×25= 120.94kN/m
Railing =2kN/m
Footpath =1.2×0.275×2×25 =16.5kN/m
Surfacing =6×0.075×1×22=9.9kN/m
Load from cross girder,
End CG = (1.75×0.45×3.75×25+2×0.5×1.75×0.45×1.2×25) ×2
=194.9kN
Mid CG= (1.575×0.3×4.65×25) ×3
=164.78kN
Total CG=359.68kN
208
70.32 ∗ 29 + 120.94 ∗ 3 + 0.5 ∗ (70.32 + 120.94) ∗ 3
Taking average of load of girder loads,
=76.83kN/m
Summary Dead Load
Slab and CG = (52.5×35+359.68)=2197.18kN
Girder=35×76.83=2689.05kN
Railing=2×35=70kN
Footpath=16.5×35=577.5kN
Surfacing=9.9×35=346.5kN
Total= 5880.23kN
Impact factor=0.1
Lane factor=1
209
Reaction at A due to Class70R(Wheeled) vehicle
=170×1+170×0.961+170×0.874+170×0.835+120×0.774+120×0.73+80×0.617
=853.74kN
4.5
6+𝐿 4.5
Impact factor =
= 6+3 = 0.1098
5
Lane factor =1
4.5
6+𝐿 4.5
Impact factor =
= 6+3 = 0.1098
5
Lane factor = 2
4.5
6+𝐿 4.5
Impact factor =
= 6+3 = 0.1098
5
Lane factor =1
210
Reaction = 387.4×1.1098×1= 429.94kN
211
Pedestrian Load
For effective spans of over 30m, the intensity of load shall be determined by equation:
𝑃 = (𝑃′ − 260 + )( )
4800 16.5−𝑊
𝐿 15
𝑃 = (500 − 260 + )
4800
) = 384.685kg/m2 = 384.685/100×1.2×35
(
16.5−1.2
35 15
= 161.567kN
where,
P’ = 500kg/m2
Design of Abutment
Material and Properties:
Grade of Concrete =M30 Characteristic strength(fck) =30N/mm2
Reinforcement =Fe500 Yield stress of steel(fy) =500N/mm2
212
Unit weight of materials as per IRC:6-2017:
Concrete (Reinforced)=25kN/m3
Backfill = 20kN/m3
Bridge Geometry
Abutment Geometry
213
Total Height = maximum scour depth for abutment foundation below HFL + grip length +
free board + depth of main girder + thickness of bearing
= (2.5+1.97) +2+1.5+2.4+0.072
= 10.442m (10.5m is adopted)
Wearing Course Height =0.075m
Height of Backwall =Height of superstructure + Wearing Course Height +Bearing Height
=2.4+0.576+0.075
=3.051m
Width of abutment =8.4m
Backwall Width =0.3m
Cap Height =0.7m
Stem Height =Total Height-Height of Backwall-Cap Height
=10.5-3.051-0.7
=0.7m
Stem Width =3.1m
Hunch detail,
Hunch
b (m) h (m)
detail
Stem
0.45 0.3
hunch
Back wall rectangl
0.25 0.25
front e
hunch 0.25 0.25 triangle
rectangl
Approach 0.25 0.25
e
slab hunch
0.25 0.25 triangle
214
Cap Width =Stem Width +Stem Hunch +Projection(0.1m)
=3.45+0.45+0.1
=3.75m
Distance from backwall to bearing center =0.65m
Distance from edge to bearing center =Cap Width - Backwall Width - Distance
from backwall to bearing center
=3.75-0.65-0.3=2.8m
A. Calculation of Loads
1. Load from self-weight of abutment and moment at base of stem
Stem = Stem Height×Stem Width×Width of abutment×Unit weight of concrete
=6.749×3.2×8.4×25
= 4535.33
Lever Arm = 0
Cap = Cap Height×Cap Width×Width of abutment×Unit weight of concrete
=0.7×3.65×8.4×25
=536.55
Lever Arm = -(3.2/2+0.45) +3.75/2 =-0.175
Backwall = Backwall Height×Backwall Width×Width of abutment×Unit weight of
concrete
=3.051×0.3×8.4×25
=192.213
Lever Arm = -(3.1/2+0.45) +0.3/2 = -1.85m
Stem Hunch = 0.5× Stem Hunch Height×Stem Hunch Width×Width of
abutment×Unit weight of concrete
=0.5×0.3×0.45×8.4×25
=14.18
Lever Arm = -(3.2/2+0.45) +2/3×0.45 =-1.75
Backwall front Hunch rectangle = Height×Width×Width of abutment×Unit weight
of concrete
= 0.25×0.25×8.4×25
= 13.125
215
Lever Arm = -(0.45+3.1/2) +(0.3+0.25/2) = -1.575
Backwall front Hunch triangle = 0.5×Height×Width×Width of abutment×Unit
weight of concrete
= 0.5×0.25×0.25×8.4×25
= 6.56
Lever Arm =-(0.45+3.1/2) +(0.3+0.25/3) = -1.617 m
Approach slab Hunch rectangle = Height×Width×Width of abutment×Unit weight
of concrete
= 0.25×0.25×8.4×25
= 13.125
Lever Arm = -(0.45+3.1/2)-0.25/2 = -2.125 m
Approach Slab Hunch triangle = 0.5×Height×Width×Width of abutment×Unit
weight of concrete
= 0.5×0.25×0.25×8.4×25
= 6.56
Lever Arm = -(0.45+3.1/2)-0.25/3 = -2.083 m
Distance from center of Moment
Component Wt. (kN)
base(m) (kNm)
Stem(rectangle) 4535.33 0.000 0.00
stem(triangle) 0.00 1.600 0.00
Cap 536.55 -0.175 -93.90
Backwall 192.213 -1.850 -355.59
Stem hunch 14.18 -1.750 -24.81
13.13 -1.575 -20.67
Back wall front hunch
6.56 -1.617 -10.61
13.13 -2.125 -27.89
Approach slab hunch
6.56 -2.083 -13.67
5175.9 -546.4
216
2. Load from superstructure
Dead Load = Weight of slab/Cross girder +Weight of Girder+Weight of railing+Weight
of footpath
=1098.6+1344.5+35+288.8
=2766.9
Lever Arm=-(0.45+3.1/2) +(0.3+0.65) = -1.05 m
Surface Load = 173.3
Lever Arm= -(0.45+3.1/2) +(0.3+0.65) = -1.05 m
Live load =Maximum load among all vehicles+Pedestrian load
=947.48+161.57 =1109
Lever Arm= -(0.45+3.1/2) +(0.3+0.65) = -1.05 m
DL 2766.9 -1.050 -2905.21
Surface 173.3 -1.050 -181.91
LL 1109.0 -1.050 -1164.50
3. Earth Pressure
Ф =35°
β =0°
α =0°
δ =22.50° (2/3 of Ф)
ɣ =20 kN/m3
Term1 =cos2(Ф - α) =0.671
Term2 =cos2(α)cos(δ+α) =0.924
Term3 =sin (Ф+ δ) sin (Ф- β)=0.484
Term4 =cos (α- β) cos (δ+ α) =0.924
𝑘𝑎 = ∗ ( 𝑇𝑒𝑟𝑚3 )2
𝑇𝑒𝑟𝑚1 1
𝑇𝑒𝑟𝑚2
1+√𝑇𝑒𝑟𝑚4
Ka=0.2445
h =Total Height-Approach Slab depth
=10.5-0.325
=10.175m
217
Earth pressure = ɣ× Ka×h
=20×0.2445×10.175
=49.755kN/m2
Total Force =0.5×Pressure×Height×Width of abutment
=0.5×49.755×10.175×8.4
=2126.2kN acts @0.42h i.e. 4.274m for dry soil from base
Horizontal Force = 2126.2×cos(δ) = 2126.2×cos (22.5) = 1964.3kN
acts @ 0.42h i.e. 4.274m for dry soil from base
Vertical Force = 2126.2×sin(δ) = 2126.2×sin (22.5) = 1964.3kN
acts @ (-3.1/2=-1.55m from stem center)
Force
LA (m) M (KNm)
(KN)
EP h = 1964.3 4.274 8394.6 KNm
FP v = 813.66 -1.55 -1261.2 KNm
4. Braking
Weight of 70R wheeled vehicle = 1000kN
Weight of Class A train of vehicle = 554kN
Point of application of load = 1.2m above deck
Lane Factor Force
1 0.2 200.0 KN
1 0.2 221.6 KN
Braking Load = 200 kN
Lever arm = Total height – 1.2 – height of bridge deck – bearing height
= 10.5 – 1.2 -2.4 – 0.576
= 6.32 m
Braking L 200 KN 6.32 m (LA) 1264.8 KNm
Here total length of class A vehicle is 20.3m and minimum spacing between two is 18.5m.
(38.6>35) m. So, factor of 10%is not taken only 20% taken.
218
5. Temperature
Temperature variation=30 ˚C
Coefficient Of thermal expansion(α) =0.0000120 m/ ˚C / m
Length =35m
Strain due to shrinkage = 0.00020 (IRC6)
Thermal Elongation = 30×0.0000120×35
=0.0126000m
6. LL Surcharge
Ka = 0.244
Height(h) =1.2m
ɣ =20kN/m3
Pressure = ɣ× Ka×h
=20×0.244×1.2 = 5.868kN/m2
Force = Pressure×(Total Height-Approach Slab Depth) ×Width of abutment
= 5.868×(10.5-0.325) ×8.4
= 501.51kN
219
Lever arm = Total Height/2 = 10.5/2 = 5.25m
Vertical surcharge = ɣ× h×Width of abutment×Approach slab length
=20×1.2×8.4×3.5
=705.6 kN
Lever arm = Approach slab length/2+Stem Hunch width +Stem Width/2
= 3.5/2+0.45+3.1/2
= 3.75 m
Force 501.51 KN 5.25 m (LA) 2632.93 KNm
Vertical
705.60 KN 3.75 m (LA) 2646.00 KNm
Surcharge
7. Seismic Loads
Zone Factor = 0.36
Imp Factor =1
Response Reduction Factor = 3
Sa/g = 2.5
Z/2/I×Sa/g = 0.36/2×1×2.5 = 0.45
Ah = 0.45/3 = 0.15
This term ‘Ah’ is multiplied with the weight and horizontal seismic force is
determined. Lever arm is taken in the direction of height of abutment accordingly
moment is determined. Calculation is tabulated below:
220
Back wall front 13.13 1.97 10.38 20.4
hunch 6.56 0.98 10.17 10.0
Approach slab 13.13 1.97 10.05 19.8
hunch 6.56 0.98 9.84 9.7
776.39 3128.0
Due to backfill
Ф = 35°
β = 0°
α = 0°
δ = 22.50° (2/3 of Ф)
ɣ =20 kN/m3
Ah =0.15
Av =2/3×0.15 =0.1
𝐴ℎ
Λ = 1±𝐴 0.15
= 1±0. = 0.1651rad
𝑣
1
(1 ± 𝐴𝑣)𝑐𝑜𝑠2(∅ − 𝜆 − 1
𝐶𝑎 ∗( )2
𝛼) 𝑠𝑖𝑛 𝑠𝑖𝑛 (∅ 𝛿) 𝑠𝑖𝑛 (∅ − 𝛽 −
=
1+( 𝜆)+0.5
𝑐𝑜𝑠𝜆𝑐𝑜𝑠2(𝛼)𝑐𝑜𝑠 (𝛿 + )
𝛼 + 𝜆) 𝑐𝑜𝑠 𝑐𝑜𝑠 (𝛼 − 𝛽) 𝑐𝑜𝑠 (𝛿 + 𝛼 + 𝜆
Ca = 0.391
Ca-Ka =0.391-0.244 = 0.4164
Height(h) = 10.175m
221
Width of abutment(B) = 8.4m
Earth Pressure Seismic = ɣ×(Ca-Ka) ×h
222
= 20×0.4164×10.175 = 29.79 kN/m2
Seismic force due to backfill = 0.5×29.79×10.175×8.4 =1273.19 kN
Lever arm = 10.175/2 = 5.088m
Seismic force due to backfill = 1273.19 KN 5.088 m (LA) 6477.36 KNm
Dynamic Surcharge
Force = ɣ×(Ca-Ka) ×h(1.2m) ×Height of abutment×Width of abutment
=20×0.4164×1.2×10.175×8.4
=300.310 kN
Lever arm = Height of abutment/2 =10.5/2 =5.25m
Force= 300.310 KN 5.250 m (LA) 1576.62 kNm
Summary of Loads
Unfactored
Forces (KN) Factors
Moment
Vertica
Horizontal (KNm) Basic Seismic
l
Abutment Self 5175.9 -546.4 1.00 1
SS DL 2766.9 -2905.2 1.00 1
SS Surface 173.3 -181.9 1.00 1
SS LL 1109.0 -1164.5 0.00 0.00
EPH 1964.3 8394.6 1.50 1.00
EPV 813.7 -1261.2 1.00 1.00
LL Surcharge (H) 501.5 2632.9 1.20 0.20
Braking 200 1264.2 1.15 0.00
Temperature 102.1 819.6 1.50 0.50
Seismic Loads
Superstructure DL 441.0 4244.8 0.00 1.50
223
Abutment DL 776.4 3128.0 0.00 1.50
Earth pressure 1273.2 6477.4 0.00 1.50
Dynamic Surcharge 300.3 1576.6 0.00 1.50
Forces(KN) Forces(KN)
Vertica Horizonta Momen Vertica Horizonta Moment
l l t l l (KNm)
(KNm)
Abutment Self 5175.9 0.0 -546.4 5175.9 0.0 -546.4
SS DL 2766.9 0.0 -2905.2 2766.9 0.0 -2905.2
SS Surface 173.3 0.0 -181.9 173.3 0.0 -181.9
SS LL 0.0 0.0 0.0 0.0 0.0 0.0
EPH 0.0 2946.5 12592.0 0.0 1964.3 8394.6
EPV 813.7 0.0 -1261.2 813.7 0.0 -1261.2
LL Surcharge (H) 0.0 601.8 3159.5 0.0 100.3 526.6
Braking 0.0 230.0 1454.5 0.0 0.0 0.0
Temperature 0.0 153.2 1229.3 0.0 51.1 409.8
Seismic Loads
Superstr. DL 0.0 0.0 0.0 0.0 661.5 6367.2
Abutment DL 0.0 0.0 0.0 0.0 1164.6 4691.9
Earth pressure 0.0 0.0 0.0 0.0 1909.8 9716.0
Surcharge 0.0 0.0 0.0 0.0 450.5 2364.9
8929.7 3931.5 13540.6 8930 6302 27576
Structural Design
Width of abutment = 8.4m
Total Stem Base Width = 3.1m
Area (Ac) = 26.04 m2
Fcd = 0.446× fck =13.38 N/mm2
Axial Load = 0.1×fcd×Ac = 34841.52 kN
Max Axial Load = 8929.7 kN (Vertical load becomes axial load here)
224
Since, max axial load is less than 0.1×fcd×Ac, abutment stem is designed as cantilever slab
where foundation is treated as fixed support and stem is treated as slab.
Our design moment is 27576.40 kN but we get limiting moment as 377714.80 kN which is
very high. So, we have to increase tensile strain of steel in such a way that our neutral axis
shifts upward and Xu value then Mulim value is decreased respectively.
Ecu2 = 0.0035
Fck = 30 MPa
0.446×fck = 13.98
N/mm2 Xu = 102 mm
0.416×Xu = 42.50 mm
Depth = Width of abutment = 3100mm
Clear cover = 75mm
225
Effective cover = Depth-Clear Cover-Diameter of rebar/2 =91mm
Effective depth = Depth-Effective Cover =3009mm
Bw = 8400mm
β1 = 0.80952
β2 = 0.41597
C = β1×0.446Fck×bw×Xu = 9295.9 kN
Cg from steel level = d-0.416Xu = 2966.5 mm
Mulim = C×CG from steel level/1000 = 27576.4 kNm (which is equal to our design moment)
Reinforcement:
Fe = 500 N/mm2
Fyd = 434.78 N/mm2
Steel Required = Compressive Force×1000/ Fyd = 21380.66
mm2 Tensile steel as per code
Fctm = 0.259×fck2/3 = 2.501
Fyk = 500 N/mm2
0.26×Fctm/Fyk = 0.00130
Min. Asmin = min(0.26Fctm/Fyk,0.00130) = 0.00130
Minimum Area of steel = 0.0013×d×bw = 32866.4
mm2 Area of concrete (Ac) = D×bw = 26040000 mm2
Maximum Area of steel = 0.025Ac = 651000 mm2
Since, steel required is less than area of steel, we are adapting minimum area of steel.
226
Check for shear:
Minimum Axial (NED) = Abutment self-load+Superstructure Dead load+Superstructure
Surface load
= 5175.9+2766.9+173.3
= 8116 kN
Breadth of abutment stem (bw) = 8400mm
Effective Depth of abutment stem(d) = 3009 mm
Area of Concrete (Ac) = bw×d = 25275600 mm2
Area of Steel Provided (Ast) = 44866 mm2
Fck = 30 MPa
σcp = NED /Ac = 0.327<(0.2fcd=0.22×30=6)
ρl = Ast/(bw×d) = 0.0018 <= 0.02
k =1+ (200/d)0.5 =1.2578 <=2
γmin = 0.031k3/2 ck
f 1/2 = 0.2395
γRd, c, min = γmin +0.15 σcp = 0.288
𝑉𝑅𝑑.𝑐 = [0.12(80𝜌1 ∗ 𝑓𝑐𝑘)0.33 + 0.15𝜎𝑐𝑝
=(0.12×1.2578×(80×0.0018×30)0.33+0.15×0.327 = 0.2917
Γ = max (γRd, c, min, 𝑉𝑅𝑑.𝑐) = max (0.288,0.2917) =
0.2917 VRd.c = 0.2917×bw×d = 7372.2 kN > 6302 kN
(ok)
Crack Width:
Rare Quasi-
Frequent
combinatio permanent
Vertica Horizonta Momen Combination
Normal n Combination
l l t (KNm)
Abutment
5175.9 0.0 -546.4 1 1 1
Self
SS DL 2766.9 0.0 -2905.2 1 1 1
227
SS Surface 173.3 0.0 -181.9 1.2 1.2 1.2
SS LL 1109.0 0.0 -1164.5 1 0.75 0
EPH 0.0 1964.3 8394.6 1 1 1
EPV 813.7 0.0 -1261.2 1 1 1
LL
Surcharge 0.0 501.5 2632.9 0.8 0 0
(H)
Braking 0.0 200.0 1264.8 1 0.75 0
Temperatur
0.0 102.1 819.6 0.6 0.5 0.5
e
Seismic
Loads
Superstr.
0.0 441.0 4244.8 0 0 0
DL
Abutment
0.0 776.4 3128.0 0 0 0
DL
Earth
0.0 1273.2 6477.4 0 0 0
pressure
228
Rare Combination Frequent Combination Quasi-permanent Combination
V H M V H M V H M
Abutment Self 5175.9 0.0 -546.4 5175.9 0.0 -546.4 5175.9 0.0 -546.4
SS DL 2766.9 0.0 -2905.2 2766.9 0.0 -2905.2 2766.9 0.0 -2905.2
SS Surface 207.9 0.0 -218.3 207.9 0.0 -218.3 207.9 0.0 -218.3
SS LL 1109.0 0.0 -1164.5 831.8 0.0 -873.4 0.0 0.0 0.0
EPH 0.0 1964.3 8394.6 0.0 1964.3 8394.6 0.0 1964.3 8394.6
EPV 813.7 0.0 -1261.2 813.7 0.0 -1261.2 813.7 0.0 -1261.2
LL Surcharge (H) 0.0 401.2 2106.3 0.0 0.0 0.0 0.0 0.0 0.0
Braking 0.0 200.0 1264.8 0.0 150.0 948.6 0.0 0.0 0.0
Temperature 0.0 61.3 491.7 0.0 51.1 409.8 0.0 51.1 409.8
Seismic Loads
Superstr. DL 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Abutment DL 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
Earth pressure 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0
6161.9 3948.5 3873.3
224
Bending Moment for crack width check (Mc)=6161.92 kNm (From Rare Combination)
Horizontal Reinforcement
Vertical main = 32mm Φ @150mm c/c spacing
Ast provided =5361.65m2 /m
Stem width =3100mm
Stem Height =1000mm
Ac = 3100×1000 =3100000mm2
Horizontal reinforcement = 25% Ast =1340.41 mm2
= 0.001Ac =3100 mm2
Half =3100/2 =1550mm2(For both directions)
Using 20mm Φ bar
Area of 20mm Φ bar =π×202/4 =314.16 mm^2
Then spacing =1000/ (1550/314.16) =203 mm
Provide Ast = 20mm Φ bar @ 150mm c/c spacing
Ast provided = 2094.4 mm2(For both directions)
Vertical Reinforcement
Stem Width (W) = 3100mm
Stem L= 1000mm
Ac = 3100×1000=3100000 mm2
0.0012×Ac = 0.0012×3100000=3720
mm2
Using 28mm Φ bar
Area of 28mm Φ bar = π×282/4=615.752 mm2
Then spacing =1000/ (3720/615.752) =166 mm
Provide Ast = 28mm Φ bar @ 150mm c/c spacing
226
Ast provided = 4105.01 mm2
227
Check:
Ast provided at rear face = 44866.30
mm2 Ast provided at front face = 4105.01
mm2
Allowable maximum reinforcement = 0.04×Ac=124000 mm2 (ok)
Allowable minimum reinforcement = 3720 mm2 (ok)
Bridge Geometry
228
A. Calculation of Loads and moments from toe edge
1. Load from self-weight of abutment
Stem = Stem Height×Stem Width×Width of abutment×Unit weight of concrete
= 6.749×3.1×8.4×25
= 4393.6kN
Lever Arm = Length of foundation-Heel-Stem Width/2
= 9.2-3.1-3.1/2 = 4.55m
Cap = Cap Height×Cap Width×Width of abutment×Unit weight of concrete
= 0.7×3.65×8.4×25
= 536.55kN
Lever Arm = Length of foundation-Heel+Stem Hunch-Cap Width/2
= 9.2-3.1+0.45-3.65/2 = 4.725m
Backwall = Backwall Height×Backwall Width×Width of abutment×Unit weight of concrete
= 3.051×0.3×8.4×25
= 192.213kN
Lever Arm = Length of foundation-Heel+Stem Hunch-Backwall width/2
= 9.2-3.1+0.45-0.3/2 = 6.4m
Stem Hunch = 0.5× Stem Hunch Height×Stem Hunch Width×Width of abutment×Unit weight
of concrete
= 0.5×0.3×0.45×8.4×25
= 14.18kN
Lever Arm = Length of foundation-Heel+Stem Hunch/3
= 9.2-3.1+0.45/3 = 6.25m
Backwall front Hunch rectangle = Height×Width×Width of abutment×Unit weight of concrete
= 0.25×0.25×8.4×25
= 13.125
Lever Arm = Length of foundation-Heel+Stem Hunch-BW Width-Front Hunch/2
= 9.2-3.1+0.45-0.3-0.25/2 = 6.125m
Backwall front Hunch triangle = 0.5×Height×Width×Width of abutment×Unit weight of
concrete
=0.5×0.25×0.25×8.4×25
229
=6.56
Lever Arm = Length of foundation-Heel+Stem Hunch-BW Width-Front Hunch/3
= 9.2-3.1+0.45-0.3-0.25/3 = 6.167m
Approach slab Hunch rectangle = Height×Width×Width of abutment×Unit weight of concrete
= 0.25×0.25×8.4×25
=13.125
Lever Arm = Length of foundation-Heel+Stem Hunch -Approach Slab Hunch/2
= 9.2-3.1+0.45+0.25/2 = 6.675m
Approach Slab Hunch triangle = 0.5×Height×Width×Width of abutment×Unit weight of
concrete
= 0.5×0.25×0.25×8.4×25
= 6.56
Lever Arm = Length of foundation-Heel+Stem Hunch- Approach Slab Hunch/3
= 9.2-3.1+0.45-0.25/3 = 6.633m
Distance
from Moment
Component Wt. (kN)
center of (kNm)
base(m)
Stem(rectangle) 4393.6 4.55 19990.88
stem(triangle) 0.00 3 0
Cap 536.55 4.725 2535.20
Backwall 192.213 6.4 1230.16
Stem hunch 14.18 6.25 88.59
Back wall front 13.13 6.125 80.39
hunch 6.56 6.167 40.47
Approach slab 13.13 6.675 87.61
hunch 6.56 6.633 43.53
5175.9 23043.24
230
Lever arm = Length of foundation/2
= 9.2/2 = 4.6m
Foundation Pad 5009.40 4.600 23043.24
3. Earth
Pressure Ф =
35°
β =0°
α =0°
δ =22.50° (2/3 of Ф)
ɣ =20 kN/m3
𝑘𝑎
∗( )2
1
= 𝑐𝑜𝑠2(𝛼)𝑐𝑜𝑠(𝛿
𝑐𝑜𝑠2(Ф − 𝛼)
𝑠𝑖𝑛 (Ф+ 𝛿) 𝑠𝑖𝑛 (Ф− 𝛽)
+𝛼) 1+√ 𝑐𝑜𝑠 (𝛼− 𝛽) 𝑐𝑜𝑠 (𝛿+ 𝛼)
Ka = 0.2445
231
Height(h) = Total Height-Approach Slab depth+ Foundation Depth
= 10.5-0.325+2.2
= 12.375m
Earth pressure = ɣ× Ka×h
=20×0.2445×12.375
=60.51kN/m2
Total Force =0.5×Pressure×Height×Width of abutment
=0.5×60.51×12.375×8.4
=3145kN acts @0.42h i.e. 4.274m for dry soil from base
Horizontal Force = 3145×cos(δ) = 3145×cos (22.5) = 2905.6kN
acts @ 0.42h i.e. -5.2m for dry soil from base
Vertical Force =3145×sin(δ) = 3145×sin (22.5) =1203.55kN
acts @ (9.2-3.1=6.1 m from stem center)
Force (KN) LA (m) M (KNm)
EP h = 2905.6 -5.198 8394.6 KNm
FP v = 1203.55 6.1 7341.7 KNm
4. Braking
Weight of 70R wheeled vehicle =1000kN
Weight of Class A train of vehicle =554kN
Point of application of load =1.2m above deck
Lane Factor Force
1 0.2 200.0 KN
1 0.2 110.8 KN
Braking Load = 200kN
Lever arm = Foundation Height+Stem Height+Cap Height
= 2.2+6.749+0.7
= 9.65m
232
Here total length of class A vehicle is 20.3m and minimum spacing between two is 18.5m. (38.6>35)
m. So, factor of 10%is not taken only 20% taken.
Moment due to braking = Braking Load×(1.2+Depth of superstructure+Bearing Ht.)
= -200×(1.2+2.4+0.6) = -840kNm
Braking Vertical reaction = Moment/spam
=-840/35 = -23.9kN
Braking vertical
-23.9 KN 5.60 -133.84 KNm
reaction=
5. Temperature
Temperature variation = 30 ˚C
Coefficient Of thermal expansion(α) =0.0000120 m/ ˚C / m
Length =35m
Strain due to shrinkage = 0.00020 (IRC6)
Thermal Elongation = 30×0.0000120×35
= 0.0126000m
233
Force on each abutment 102.13 KN 8.025 m (LA) -1044.24 KNm
6. LL Surcharge
Ka =0.244
Height(h) =1.2m
ɣ =20kN/m3
Pressure = ɣ× Ka×h
= 20×0.244×1.2 = 5.868kN/m2
Force = Pressure×(Total Height-Approach Slab Depth) ×Width of abutment
= 5.868×(10.5-0.325) ×8.4
= 501.51kN
Lever arm = Total Height/2+Height of Foundation
= 10.5/2+2.2 = 7.45m
Vertical surcharge = ɣ× h×Width of foundation×Heel
= 20×1.2×9.9×3.1
= 736.56kN
Lever arm = Toe+Stem Hunch+Heel/2
= 3+3.1+3.1/2
= 7.65m
Force 501.51 KN 7.45 m (LA) -3736.3 KNm
Vertical 5634.68
736.56 KN 7.65 m (LA) KNm
Surcharge 4
7. Backfill
Height(h) = Total Height-Approach Slab Depth
= 10.5-0.325 = 10.175m
Heel = 3.1m
Width of abutment = 9.9m
Weight of Backfill = ɣ×h×Heel×Width of abutment = 20×10.175×3.1×9.9
= 6245.415kN
234
Lever arm = Length of foundation-Heel/2
= 9.2-3.1/2
= 7.65m
Moment = 47777.425kNm
8. Seismic Loads
Zone Factor =0.36
Imp Factor =1
Response Reduction Factor(R) =3
Sa/g = 2.5
Z/2×I×Sa/g = 0.36/2×1×2.5 =0.45
Ah = (Z/2) ×(I/R) ×(Sa/g) = 0.45/3 = 0.15
This term ‘Ah’ is multiplied with the weight and horizontal seismic force is determined. Lever
arm is taken in the direction of height of abutment accordingly moment is determined.
Calculation is tabulated below:
235
i. Superstructure Dead Load
Weight = 2940kN
Horizontal Force = 2940×0.15 = 441.02
Lever arm =Total Height-Wearing Course Height+Height of foundation-Height of bridge
deck/3
=10.5-0.075+2.2-2.4/3 =11.825m
Moment = 5215kNm
Here, live load is not taken according to Clause 219.5.2(i) of IRC:6-2017
ii. Due to backfill
Ф = 35°
β = 0°
α = 0°
δ = 22.50° (2/3 of Ф)
ɣ = 20 kN/m3
Ah = 0.15
Av = 2/3×0.15 =0.1
𝐴
Λ =1±𝐴ℎ𝑣 0.15
= 1±0. = 0.1651rad = 9.46°
1
(1 ± 𝐴𝑣)𝑐𝑜𝑠2(∅ − 𝜆 − 1
𝐶𝑎 = ∗( )2
𝛼) 𝑠𝑖𝑛 𝑠𝑖𝑛 (∅ 𝛿) 𝑠𝑖𝑛 (∅ − 𝛽 −
1+( 𝜆)+0.5
𝑐𝑜𝑠𝜆𝑐𝑜𝑠2(𝛼)𝑐𝑜𝑠 (𝛿 + )
𝛼 + 𝜆) 𝑐𝑜𝑠 𝑐𝑜𝑠 (𝛼 − 𝛽) 𝑐𝑜𝑠 (𝛿 + 𝛼 + 𝜆
Ca = 0.391
Ca-Ka =0.391-0.244 = 0.147
Height(h) = Total Height+Height of foundation-Approach slab depth
=10.5+2.2-0.325 = 12.375m
Width of foundation(B) = 9.9m
Earth Pressure Seismic = ɣ×(Ca) ×h
= 20×0.391×12.375 = 96.74kN/m2
Seismic force due to backfill = 0.5×96.74×12.375×9.9 = 5926.2kN
236
Earth Pressure Normal = 3145kN
Difference = 5926.2-3145 = 2781.2kN
Lever arm = h/2 = 12.375/2 = 6.188m
Difference= 2781.2 KN 6.188 m (LA) -17208.63 kNm
B. Summary of Loads
Unfactored
Forces(KN) Moment (KNm)(at toe) Basic Seismic
Vertica Horizonta Resistin Overturnin
R O R O
l l g g
Abutment 5175.9 24096.8 0.9 1.1 0.9 1.1
Foundation 5009.4 23043.2 0.9 1.1 0.9 1.1
SS DL 2766.9 15494.4 0.9 1.1 0.9 1.1
1.3 1.3
SS Surface 173.3 970.2 1 1
5 5
SS LL 1109.0 6210.7 0 1.5 0 0
EPH 2905.6 -15102.0 1 1.5 1 1
EPV 1203.6 7341.7 1 1.5 1 1
LL
501.5 -3736.3 0 1.2 0 0
Surcharge(H)
LL Surcharge 5634.68
736.6 0 1.2 0 0
(V) 4
237
Braking 200.0 -1929.8 0 1.5 0 0
Temperature 102.1 -1044.2 0 0.9 0 0.5
Backfill 6245.4 47777.4 0.9 1.1 0.9 1.1
Breaking 1.1
-23.9 -133.632 0 0 0.2
uplift 5
Seismic
Seismic DL
776.4 -4836.1 0 0 0 1.5
abut.
Seismic
751.4 -826.6 0 0 0 1.5
foundation
Seismic DLSS 441.0 -5215.0 0 0 0 1.5
Seismic Earth
2781.2 -17208.6 0 0 0 1.5
pressure
Surcharge
365.2 -1917.5 0 0 0 1.5
dynamic
Basic combination
Forces(KN) Moment (KNm)
Horizonta Overturni
Vertical l Resisting ng
Abutment 4658.32 0.00 21687.15 0.00
Foundation 4508.46 0.00 20738.92 0.00
SS DL 2490.18 0.00 13945.00 0.00
SS Surface 173.25 0.00 970.20 0.00
SS LL 0.00 0.00 0.00 0.00
EPH 0.00 4358.44 0.00 -22653.02
EPV 1203.55 0.00 7341.66 0.00
LL
Surcharge(H) 0.00 601.81 0.00 -4483.51
238
LL Surcharge
(V) 0.00 0.00 0.00 0.00
Braking 0.00 300.00 0.00 -2894.70
Temperature 0.00 91.91 0.00 -939.82
Backfill 5620.87 0.00 42999.68 0.00
Breaking
uplift -27.44 0.00 0.00 -153.68
Seismic 0.00 0.00 0.00 0.00
Seismic DL
abt 0.00 0.00 0.00 0.00
Seismic
foundation 0.00 0.00 0.00 0.00
Seismic DLSS 0.00 0.00 0.00 0.00
Seismic Earth
pressure 0.00 0.00 0.00 0.00
Surcharge
dynamic 0.00 0.00 0.00 0.00
Total 18627.19 5352.17 107682.61 -31124.72
Seismic combination
Forces(KN) Moment (KNm)
Overturni
Vertical Horizontal Resisting ng
Abutment 4658.3208 0 21687.148 0
Foundation 4508.46 0 20738.916 0
SS DL 2490.1785 0 13944.9996 0
SS Surface 173.25 0 970.2 0
SS LL 0 0 0 0
239
-
EPH
0 2905.62976 0 15102.011
1203.55125
EPV
4 0 7341.66265 0
LL
Surcharge(H) 0 0 0 0
LL Surcharge
(V) 0 0 0 0
Braking 0 0 0 0
-
Temperature
0 51.0631579 0 522.12079
Backfill 5620.8735 0 42999.6823 0
-
Breaking
4.77257142
uplift
9 0 0 -26.7264
Seismic 0 0 0 0
Seismic DL -
abt 0 1164.5802 0 7254.1851
Seismic -
foundation 0 1127.115 0 1239.8265
-
Seismic DLSS
0 661.525875 0 7822.5435
Seismic Earth -
pressure 0 4171.78932 0 25812.946
Surcharge -
dynamic 0 547.863323 0 2876.2824
18649.86 10629.57 107682.61 -60656.64
240
Summary of loads basic Seismic
Vertical load 18627.19 18649.86
Horizontal loads 5352.17 10629.57
107682.6 107682.6
Resisting moment 1 1
Overturning
moment -31124.72 -60656.64
Frictional
coefficient 0.70 0.70
Overturning = 3.46 1.78
Sliding = 2.44 1.23
Here,
=−𝑂𝑣𝑒𝑟𝑡𝑢𝑟𝑛𝑖𝑛𝑔 𝑀𝑜𝑚𝑒𝑛𝑡> 1
𝑅𝑒𝑠𝑖𝑠𝑡𝑖𝑛𝑔 𝑀𝑜𝑚𝑒𝑛𝑡
Overturning
𝜇∑ 𝑉
>1
∑
Sliding =
𝐻
V H M
Abutment 5175.9 0.0 24096.8
Foundation 5009.4 0.0 23043.2
SS DL 2766.9 0.0 15494.4
SS Surface 173.3 0.0 970.2
SS LL 1109.0 0.0 6210.7
EPH 0.0 2905.6 -15102.0
241
EPV 1203.6 0.0 7341.7
LL Surcharge(H) 0.0 501.5 -3736.3
LL Surcharge (V) 736.6 0.0 5634.7
Braking 0.0 200.0 -1929.8
Temperature 0.0 102.1 -1044.2
Backfill 6245.4 0.0 47777.4
Breaking uplift -23.9 0.0 -133.6
Seismi 108623.
c 2
Seismic DL abt. 0.0 776.4 -4836.1
Seismic
foundation 0.0 751.4 -826.6
Seismic DLSS 0.0 441.0 -5215.0
Seismic Earth
pressure 0.0 2781.2 -17208.6
surcharge dynamic 0.0 365.2 -1917.5
78619.4
242
243
Horizontal force, vertical force and moment due to horizontal force remains same. Only moment due
to vertical force changes.
Calculation of moments due to vertical forces,
i. Abutment
= 24096.8-4.6×5175.9 = 287.6kNm
ii. Foundation
=23043.2-4.6×5009.4 = 0kNm
iii. Superstructure Dead Load
=15494.4-4.6×2766.9 =2766.66kNm
iv. Superstructure surface
=970.2-4.6×173.3 =173.02kNm
v. Superstructure Live load
=6210.7-4.6×1109 =1109.3kNm
vi. Earth Pressure Horizontal
=-15102-4.6×0 = -15102kNm
vii. Earth Pressure Vertical
=7341.7-4.6×1203.6 =1805.14kNm
viii. Liveload surcharge(H)
=-3736.3-4.6×0 = -3736.3kNm
ix. Liveload surcharge(V)
=5634.7-4.6×736.6 = 2246.34kNm
x. Braking
=-1929.8-4.6×0 = -1929.8kNm
xi. Temperature
=-1044.2-4.6×0 = -1044.2kNm
xii. Backfill
=47777.4-4.6×6245.4 =19048.56kNm
xiii. Breaking uplift
=-133.6-4.6×(-23.9) = -23.66kNm
244
Seismic
i. Seismic Dead Load abutment
=-4836.1-4.6×0 =-4836.1kNm
ii. Seismic foundation
=-826.6-4.6×0 =-826.6kNm
iii. Seismic Dead load Superstructure
=-5215-4.6×0 =-5215kNm
iv. Seismic Earth Pressure
=-17208.6-4.6×0 =-17208.6kNm
v. Surcharge Dynamic
=-1917.5-4.6×0 =-1917.5kNm
245
Seismic foundation 751.4 -826.6 0 0 1.5
Seismic DLSS 441.0 -5215.0 0 0 1.5
Seismic Earth -
pressure 2781.2 17208.6 0 0 1.5
surcharge dynamic 365.2 -1917.5 0 0 1.5
For C1
Abutment 6987.5 0.0 388.3
Foundation 6762.7 0.0 0.0
SS DL 3735.3 0.0 3735.3
SS Surface 303.2 0.0 303.2
SS LL 1663.6 0.0 1663.6
-
EPH
0.0 4358.4 22653.0
EPV 1805.3 0.0 2708.0
LL Surcharge(H) 0.0 601.8 -4483.5
LL Surcharge (V) 883.9 0.0 2695.8
Braking 0.0 300.0 -2894.7
Temperature 0.0 91.9 -939.8
Backfill 8431.3 0.0 25715.5
Breaking uplift -35.8 0.0 -35.8
Seismic
246
Seismic DL abt 0.0 0.0 0.0
Seismic foundation 0.0 0.0 0.0
Seismic DLSS 0.0 0.0 0.0
Seismic Earth pressure 0.0 0.0 0.0
surcharge dynamic 0.0 0.0 0.0
30536.9 5352.2 6202.8
For C2
Abutment 5175.9 0.0 287.6
Foundation 5009.4 0.0 0.0
SS DL 2766.9 0.0 2766.9
SS Surface 173.3 0.0 173.3
SS LL 1441.8 0.0 1441.8
-
EPH
0.0 3777.3 19632.6
EPV 1564.6 0.0 2346.9
LL Surcharge(H) 0.0 501.5 -3736.3
LL Surcharge (V) 736.6 0.0 2246.5
Braking 0.0 260.0 -2508.7
Temperature 0.0 81.7 -835.4
Backfill 6245.4 0.0 19048.5
Breaking uplift -31.0 0.0 -31.0
Seismic
Seismic DL abt 0.0 0.0 0.0
Seismic foundation 0.0 0.0 0.0
Seismic DLSS 0.0 0.0 0.0
Seismic Earth pressure 0.0 0.0 0.0
surcharge dynamic 0.0 0.0 0.0
23082.8 4620.5 1567.4
247
For C3
Abutment 6987.5 0.0 388.3
Foundation 6762.7 0.0 0.0
SS DL 3735.3 0.0 3735.3
SS Surface 233.9 0.0 233.9
SS LL 831.8 0.0 831.8
EPH 0.0 2905.6 -15102.0
EPV 1203.6 0.0 1805.3
LL Surcharge(H) 0.0 100.3 -747.3
LL Surcharge (V) 147.3 0.0 449.3
Braking 0.0 150.0 -1447.4
Temperature 0.0 51.1 -522.1
Backfill 8431.3 0.0 25715.5
Breaking uplift -17.9 0.0 -17.9
Seismic
Seismic DL abt 0.0 1164.6 -7254.2
Seismic
foundation 0.0 1127.1 -1239.8
Seismic DLSS 0.0 661.5 -7822.5
Seismic Earth
pressure 0.0 4171.8 -25812.9
surcharge dynamic 0.0 547.9 -2876.3
28315.4 10879.9 -29683.0
248
V H M
Combi
1 30536.9 5352.2 6202.8
Combi
2 23082.8 4620.5 1567.4
Combi
3 28315.4 10879.9 29683.0
= 9.9×9.23/12
= 642.42m4(For the base of raft)
For Combination 1,
= 9.9∗9.2 ±642.42∗2
30536.9 6202.8∗9.2
=335.275 ± 44.414
=290.86 kN/m2 (For -ve)
=379.69 kN/m2 (For +ve)
For Combination 2,
= 9.9∗9.2 ±642.42∗2
23082.8 1567.4∗9.2
=253.434 ± 11.223
=242.21 kN/m2 (For -ve)
=264.66 kN/m2 (For +ve)
For Combination 3,
= 9.9∗9.2 ± 642.42∗2
28315.4 29683.0∗9.2
249
=310.884 ± 212.543
250
=98.34 kN/m2 (For -ve)
=523.43 kN/m2 (For +ve)
Bearing Capacity of Soil = 400kN/m2(From Geotech report)
Combi1 290.86 379.69 <400.0 KN/m2
Combi2 242.21 264.66 <600.0 KN/m2
Combi3 98.34 523.43 <600.0 KN/m2
Seismic
0.0 751.4 -826.6 0.00 0 1.50
foundation
251
Seismic DLSS 0.0 441.0 -5215.0 0 0 1.5
Seismic Earth
0.0 2781.2 -17208.6 0.00 0 1.50
pressure
surcharge
0.0 365.2 -1917.5 0.00 0 1.50
dynamic
For Seismic
For Basic I combination
Combination
V H M H M V H M
252
Surcharge
0.0 0.0 0.0 0.0 0.0 0.0 547.9 -2876.3
dynamic
Total 29970.
5282.2 6011.4 4560.5 1365.0 28402.6 10769.9 -28534.5
9
stem
13893.
5282.2 -22399.9 4560.5 -19930.0 13061.3 3097.0 -9693.5
base 1
Here,
V H M
Basic I 29970.9 5282.2 6011.4
Basic II 22572.2 4560.5 1365.0
Seismic 28402.6 10769.9 28534.5
= 9.9×9.23/12
= 642.42m4(For the base of raft)
= 9.9∗9.2 ±642.42∗2
29970.9 6011.4∗9.2
=329.06 ± 43.044
=286.02 kN/m2 (For -ve)
=372.11 kN/m2 (For +ve)
= 9.9∗9.2 ±642.42∗2
22572.2 1365.0∗9.2
=247.828 ± 9.77
=238.05 kN/m2 (For -ve)
=257.60 kN/m2 (For +ve)
For Seismic,
= 9.9∗9.2 ± 642.42∗2
28402.6 28534.5∗9.2
=311.842 ± 204.319
=107.52 kN/m2 (For -ve)
=516.16 kN/m2 (For +ve)
BP=286.02kN/mm2 At x2=9.2m
𝑦2 − 𝑦1
BP=372.11kN/mm2
𝑦 − 𝑦1 = ∗ (𝑥 − 𝑥1)
−
𝑥2
𝑥1
372.11 −
𝑦 = 286.02 + 286.02 ∗ (𝑥 − 0)
9.2 − 0
254
At x=(3.1-2.109=0.991m) BP=295.3 kN/mm2
At x=(3.1m) BP=315.0 kN/mm2
At x=(6.2m) BP=344.0 kN/mm2
At x=(8.31m) BP=363.8 kN/mm2
255
Pressure due to concrete+soil
= - (Unit weight of concrete×Depth of foundation×γf+ Unit weight of soil×Height of abutment×γf)
= -(25×2.2×1.35+20×10.175×1.35) = -348.975kN/mm2
Pressure due to concrete
= - (Unit weight of concrete×Depth of foundation×γf)
= -(25×2.2×1.35) = -74.25kN/mm2
BP=238.05kN/mm2 At x2=9.2m 𝑦2 − 𝑦1
∗ (𝑥 − 𝑥1)
BP=257.60kN/mm2
𝑦 − 𝑦1 = −
𝑥2
𝑥1
257.6 −
𝑦 = 238.05 + 238.05 ∗ (𝑥 − 0)
9.2 − 0
256
𝑦2 − 𝑦1
At x2=9.2m BP=516.6kN/mm2
𝑦 − 𝑦1 = ∗ (𝑥 − 𝑥1)
−
𝑥2
𝑥1
257
516.16 −
𝑦 = 107.52 + 107.52 ∗ (𝑥 − 0)
9.2 − 0
Design of toe
Flexure Check (per meter)
Basic I
344.0 372.1
Basic II
251.23 257.6
Seismic
382.91 516.16
259
Seismi
Basic I Basic II
c
1723.0
Mrec = 1548.15 1130.52
9
Mtri = 84.22 19.12 399.76
-
Mfooting -334.13 -247.50
334.13
1788.7
Mtotal= 1298.24 902.15
2
260
= (1778.72×106/434.78/2075.9 =1982mm2
Tensile steel as per code
Fctm =0.259×fck2/3 =2.501
Fyk =500 N/mm2
0.26×Fctm/Fyk =0.00130
Min. Asmin =min(0.26Fctm/Fyk,0.00130) =0.00130
Minimum Area of steel =0.0013×d×bw
=0.0013×2200×1000 =2860 mm2
Area of concrete (Ac) =D×bw=2200×2860=6292000
mm2 Maximum Area of steel =0.025Ac=157300 mm2
261
Basic I At d,
SFrec=Stress×Length
=363.8×(9.2-8.3)=324.12kN
SFtri=0.5×(372.1-363.8) ×(9.2-8.3)=3.71kN
SFfooting=-γc×Depth×Length×γf
=-25×2.2×(9.2-8.3) ×1.35=-66.16kN
TotalSF =324.12+3.71-66.16=261.68kN
At face,
SFrec=Stress×Length
=344×(9.2-6.2)=1032.1kN
SFtri =0.5×(372.1-344.0) ×(9.2-6.2)=42.11kN
SFfooting =-γc×Depth×Length×γf
=-25×2.2×(9.2-6.2) ×1.35 =-222.75kN
TotalSF=1032.1+42.11-222.75=851.46kN
SF=261.68kN
Basic II
At d,
SFrec=Stress×Length
=255.7×(9.2-8.3) =227.84kN
SFtri =0.5×(257.6-255.7) ×(9.2-8.3)=0.84kN
SFfooting=-γc×Depth×Length×γf
=-25×2.2×(9.2-8.3) ×1=-49kN
TotalSF=227.84+0.84-49=179.68kN
At face,
SFrec=Stress×Length
=255.7×(9.2-6.2)=753.68kN
SFtri=0.5×(257.6-255.7) ×(9.2-6.2)=9.56kN
SFfooting=-γc×Depth×Length×γf
=-25×2.2×(9.2-6.2) ×1=-165kN
TotalSF=753.68+9.56-165 =598.24kN
262
SF=179.68kN
Seismic
At d,
SFrec=Stress×Length
=476.6×(9.2-8.3)=424.64kN
SFtri=0.5×(516.2-476.6) ×(9.2-8.3)=17.63kN
SFfooting=-γc×Depth×Length×γf
=-25×2.2×(9.2-8.3) ×1.35=-66.16kN
TotalSF=424.64+17.63-66.16=376.11kN
At face,
SFrec=Stress×Length
=476.6×(9.2-6.2) =1148.73kN
SFtri=0.5×(516.2-476.6) ×(9.2-6.2)=199.88kN
SFfooting=-γc×Depth×Length×γf
=-25×2.2×(9.2-6.2) ×1.35=-222.75kN
TotalSF=1148.73+199.88-222.75=851.46kN
SF=376.11kN
Design SF,VR,dc=376.11kN
Basic I Basic II Seismic
At d At face At d At face At d At face
324.1
SFrec = 1032.10 227.84 753.68 424.64 1148.73
2
SFtri = 3.71 42.11 0.84 9.56 17.63 199.88
SFfooting= 66.16 222.75 49.00 165.00 66.16 222.75
261.6
Total SF = 851.46 179.68 598.24 376.11 1125.86
8
SF 261.68 179.68 376.11
Tension at
Tension at bottom Tension at bottom
bottom
Design SF,VR,dc 376.11
263
Breadth of abutment stem (bw) = 1000mm
Effective Depth of abutment stem(d) = 2109 mm
Area of Concrete (Ac) = bw×d =2109000 mm2
Area of Steel Provided (Ast) =5362 mm2(Main
reinforcement)
Fck =30 MPa
σcp = NED /Ac =0 <(0.2fcd=0.22×30=6)
ρl =Ast/(bw×d) =0.0025 <=0.02
k =1+ (200/d)0.5 =1.31 <=2
γmin =0.031k3/2 fck1/2 =0.255
γRd, c, min = γmin +0.15 σcp =0.255
𝑉𝑅𝑑.𝑐 = [0.12(80𝜌1 ∗ 𝑓𝑐𝑘)0.33 + 0.15𝜎𝑐𝑝 = (0.12×1.31×(80×0.0025×30)0.33+0.15×0
=0.284
Design of Heel
Flexure Check (per meter)
Basic I
286.02 315
265
Mtotal =1374.31+46.46-1676.82 =-256.05kNm
Basic II
238.05 244.64
Seismic
107.52 245.22
266
Design Moment =Maximum among three cases
=939.64kNm
Fck =30 MPa
Fe =500MPa
0.446×fck =13.98 N/mm2
Xu =40.79mm
0.416×Xu =16.97 mm
Depth =Depth of foundation =2200mm
Clear cover =75mm
Effective cover =Depth-Clear Cover-Diameter of rebar/2=91mm
Effective depth =Depth-Effective Cover =2109mm
Bw =1000mm
β1 =0.80952
β2 =0.41597
C = β1×0.446Fck×bw×Xu =441.8 kN
Cg from steel level =d-0.416Xu =2092.0 mm
Mulim =C×CG from steel level/1000 =924.18 kNm
(which is equal to our design moment)
Shear Design
Design shear force:
Load at: 0.0 1.0 3.1 6.2 8.3 9.2
Basic I 286.0 295.3 315.0 344.0 363.8 372.1
Basic II 238.1 240.2 244.6 251.2 255.7 257.6
Seismic 107.5 151.5 245.2 382.9 476.6 516.2
Basic I
At d,
SFrec =Stress×Length
=286×(0.991-0) =283.44kN
SFtri =0.5×(295.3-286.0) ×(0.991-0) =4.59kN
SFfooting =-Stressconcrete×Length
=-348.975×(0.991-0) =-345.83kN
TotalSF =283.44+4.59-345.83 =-57.80kN
At face,
SFrec =Stress×Length
=286×(3.1-0) =886.65kN
268
SFtri =0.5×(315-286) ×(3.1-0) =44.96kN
SFfooting =-Stressconcrete×Length
=-348.975×(3.1-0) =-1081.82kN
TotalSF =886.65+44.96-1081.82 =-150.21kN
SF =-150.21kN
Basic II
At d,
SFrec =Stress×Length
=238.1×(0.991-0) =235.91kN
SFtri =0.5×(240.2-238.1) ×(0.991-0) =1.04kN
SFfooting =-Stressconcrete×Length
=-258.5×(0.991-0) =-256.17kN
TotalSF =235.91+1.04-256.17 =-19.22kN
At face,
SFrec =Stress×Length
=238.1×(3.1-0) =737.97kN
SFtri =0.5×(244.6-238.1) ×(3.1-0) =10.21kN
SFfooting =-Stressconcrete×Length
=-258.5×(3.1-0) =-801.35kN
TotalSF =737.97+10.21-801.35 =-53.17kN
SF =-53.17kN
Seismic
At d,
SFrec =Stress×Length
=107.5×(0.991-0) =106.55kN
SFtri =0.5×(151.5-107.5) ×(0.991-0) =21.81kN
SFfooting =-Stressconcrete×Length
=-348.975×(0.991-0) =-345.83kN
TotalSF =106.55+21.81-345.83 =-217.47kN
269
At face,
SFrec =Stress×Length
=107.5×(3.1-0) =333.32kN
SFtri =0.5×(245.2-107.5) ×(3.1-0) =213.43kN
SFfooting =-Stressconcrete×Length
=-348.975×(3.1-0) =-1081.82kN
TotalSF =333.32+213.43-1081.82 =-535.08kN
SF =535.08kN
Design SF,VR,dc =535.08kN
Basic I Basic II Seismic
At d At face At d At face At d At face
283.4
SFrec = 886.65 235.91 753.68 106.55 333.32
4
SFtri = 4.59 44.96 1.04 9.56 21.81 213.43
-
SFfooting - - -
345.8 -1081.82 165.00
= 256.17 345.83 1081.82
3
-
Total SF = -57.8 -150.21 -19.22 598.24 -535.08
217.47
SF -150.21 -53.17 -535.08
Tension at bottom Tension at bottom Tension at bottom
Design SF,VR,dc 535.08
270
k =1+ (200/d)0.5 =1.31 <=2
271
γmin =0.031k3/2 fck1/2 =0.255
γRd, c, min = γmin +0.15 σcp =0.255
𝑉𝑅𝑑.𝑐 = [0.12(80𝜌1 ∗ 𝑓𝑐𝑘)0.33 + 0.15𝜎𝑐𝑝 = (0.12×1.31×(80×0.0025×30)0.33+0.15×0
=0.284
BP=286.02kN/mm2 At x2=9.2m
𝑦2 − 𝑦1
BP=372.11kN/mm2
𝑦 − 𝑦1 = ∗ (𝑥 − 𝑥1)
−
𝑥2
𝑥1
272
372.11 −
𝑦 = 286.02 + 286.02 ∗ (𝑥 − 0)
9.2 − 0
273
At x=(2.05m) BP=305.2 kN/mm2
At x=(3.1m) BP=315.0 kN/mm2
At x=(6.2m) BP=344.0 kN/mm2
At x=(7.25m) BP=353.9 kN/mm2
At x=(8.31m) BP=363.8 kN/mm2
BP=238.05kN/mm2 At x2=9.2m 𝑦2 − 𝑦1
∗ (𝑥 − 𝑥1)
BP=257.60kN/mm2
𝑦 − 𝑦1 = −
𝑥2
𝑥1
257.6 −
𝑦 = 238.05 + 238.05 ∗ (𝑥 − 0)
9.2 − 0
Seismic,
At x1=0 BP=107.52kN/mm2
At x2=9.2m BP=516.6kN/mm2
𝑦2 − 𝑦1
𝑦 − 𝑦1 = ∗ (𝑥 − 𝑥1)
−
𝑥2
𝑥1
516.16 − 9.2 − 0
𝑦 = 107.52 + 107.52
274
∗ (𝑥 − 0)
275
At x=(7.25m) BP=429.75 kN/mm2
At x=(8.31m) BP=476.59 kN/mm2
𝑑
K =1.31 <2.0
For Basic I
Upward Pressure=0.5×(Stress at d/2 from left face +Stress at d/2 from right face of column)×
(Distance at d/2 of left from left -Distance at d/2 of right from left)×Increased Width
=0.5×(305.2+353.9)×(7.25-2.05)×9.9 =16993.54kN
Self Weight=(Distance at d/2 of left from left -Distance at d/2 of right from left)×Effective
depth(d)×Increased Width×γc×γf
=(7.25-2.05)×2.1×9.9×25×1.35 =3670.62kN
VED =Vstembase =13893.1kN
VED,red = Self Weight+ VED- Upward Pressure
=3670.62+13893.1-16993.54
=570.14kN
M/V =6011.4/29970.9 =0.201
Eccentricity of CP(ei) = Distance at d/2 of right from left-0.5×(Front face+Back face)
=7.25-0.5×(6.2+3.1) =2.6m
Wi =∑ (𝑒𝑖 ∗ 𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝑝𝑒𝑟𝑖𝑚𝑒𝑡𝑒𝑟)
=2.6×19.8 =51.569
𝐶𝑃∗(
𝑀
𝑉
β) =1 + 𝑘 ∗ =1+0.45×19.8×0.201/51.569 =1.0347
𝑊𝑖
ved = β× VED,red/CP/d
=1.0347×570.14/19.8/2109 =0.0141
Since, ved< VRd (OK)
For Basic II
Upward Pressure=0.5×(Stress at d/2 from left face +Stress at d/2 from right face of column)×
(Distance at d/2 of left from left -Distance at d/2 of right from left)×Increased Width
277
=0.5×(242.4+253.5)×(7.25-2.05)×9.9 =12785.75kN
278
Self Weight=(Distance at d/2 of left from left -Distance at d/2 of right from left)×Effective
depth(d)×Increased Width×γc×γf
=(7.25-2.05)×2.1×9.9×25×1 =2718.98kN
VED =Vstembase =10580.8kN
VED,red = Self Weight+ VED- Upward Pressure
=2718.98+10580.8-12785.75
=514.04kN
M/V =1365.0/22572.2 =0.06
Eccentricity of CP(ei) = Distance at d/2 of right from left-0.5×(Front face+Back face)
=7.25-0.5×(6.2+3.1) =2.6m
Wi =∑ (𝑒𝑖 ∗ 𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝑝𝑒𝑟𝑖𝑚𝑒𝑡𝑒𝑟)
=2.6×19.8 =51.569
𝐶𝑃∗(
𝑀
𝑉
β) =1 + 𝑘 ∗ =1+0.45×19.8×0.06/51.569 =1.0104
𝑊𝑖
ved = β× VED,red/CP/d
=1.0104×514.04/19.8/2109 =0.0124
Since, ved< VRd (OK)
For Seismic
Upward Pressure=0.5×(Stress at d/2 from left face +Stress at d/2 from right face of column)×
(Distance at d/2 of left from left -Distance at d/2 of right from left)×Increased Width
=0.5×(429.75+198.38)×(7.25-2.05)×9.9 =13742.02kN
Self Weight=(Distance at d/2 of left from left -Distance at d/2 of right from left)×Effective
depth(d)×Increased Width×γc×γf
=(7.25-2.05)×2.1×9.9×25×1.35 =3670.62kN
VED =Vstembase =13061.3kN
VED,red = Self Weight+ VED- Upward Pressure
=3670.62+13061.3-13742.02
=2989.88kN
M/V =-28534.5/28402.6 =-1.005
Eccentricity of CP(ei) = Distance at d/2 of right from left-0.5×(Front face+Back face)
279
=7.25-0.5×(6.2+3.1) =2.6m
Wi =∑ (𝑒𝑖 ∗ 𝐶𝑜𝑛𝑡𝑟𝑜𝑙 𝑝𝑒𝑟𝑖𝑚𝑒𝑡𝑒𝑟)
=2.6×19.8 =51.569
𝐶𝑃∗(
𝑀
𝑉
β) =1 + 𝑘 ∗ =1+0.45×19.8×0.201/51.569 =1.0347
𝑊𝑖
ved = β× VED,red/CP/d
=1.0347×2989.88/19.8/2109 =0.0141
Since, ved< VRd (OK)
=
51.5691 51.5691 51.5691
β=
1.0347 1.0104 1.0347
So, ved =
0.0141 0.0124 0.0741
OK OK OK
280
9.5 Foundation Crack
281
Factored loads at foundation
base
Abutment 5175.9 0.0 287.6
Foundation 5009.4 0.0 0.0
SS DL 2766.9 0.0 2766.9
SS Surface 207.9 0.0 207.9
SS LL 1109.0 0.0 1109.0
EPH 0.0 2905.6 -15102.0
EPV 1203.6 0.0 1805.3
LL Surcharge(H) 0.0 401.2 -2989.0
LL Surcharge (V) 589.2 0.0 1797.2
Braking 0.0 150.0 -1447.4
Temperature 0.0 102.1 -1044.2
Backfill 6245.4 0.0 19048.5
Breaking uplift -17.9 0.0 -17.9
Seismic
Seismic DL abt 0.0 776.4 -4836.1
Seismic foundation 0.0 751.4 -826.6
Seismic DLSS 0.0 441.0 -5215.0
Seismic Earth
pressure 0.0 2781.2 -17208.6
Surcharge dynamic 0.0 365.2 -1917.5
22289.
4 8674.2 23581.9
282
𝑉𝑒𝑟𝑡𝑖𝑐𝑎𝑙 𝑀𝑜𝑚𝑒𝑛𝑡 ∗ 𝐿𝑒𝑛𝑔𝑡ℎ
𝐵𝑒𝑎𝑟𝑖𝑛𝑔 ±
𝑓𝑜𝑟𝑐𝑒(𝑉) 𝑀𝑂𝐼 ∗ 2
𝑃𝑟𝑒𝑠𝑠𝑢𝑟𝑒 =
𝑊𝑖𝑑𝑡ℎ ∗
𝐿𝑒𝑛𝑔𝑡ℎ
= 9.9∗9.2 ± 642.42∗2
22289.4 23581.9∗9.2
=244.723 ± 168.856
=75.87 kN/m2 (For -ve)
=413.58 kN/m2 (For +ve)
𝑦2 − 𝑦1
BP=413.58kN/mm2
𝑦 − 𝑦1 = ∗ (𝑥 − 𝑥1)
−
𝑥2
𝑥1
413.58 −
𝑦 = 75.87 + 75.87 ∗ (𝑥 − 0)
9.2 − 0
283
Stress
Distribution conc+soil concrete
Distance 0 3.1 6.2 9.2 Heel Toe kN/m2
Rare 75.9 189.66 303.46 413.58 -258.5 -55
Crack Check
Moment at column face of toe
303.46 413.58
75.9 189.66
284
Toe Heel
Mrec = 1365.55 364.54
Mtri = 330.37 182.26
Mfooting= -247.50 -1242.09
Mtotal= 1448.43 -695.29
285
=31187 MPa
ρ1, eff =As/Ac, eff =5362/227500 =0.0236
αe =Es/Ecm =200000/31187 =6.413
𝑓𝑐𝑡,
𝜎 − ∗
𝛼 ∗ (1 + ∗ 𝜎𝑠𝑐
𝜀𝑠𝑚 − 𝜀𝑐𝑚 𝑠𝑐 𝑘𝑡 𝜌𝑝,𝑒𝑓𝑓 𝜌𝑝,𝑒𝑓𝑓) ≥ 0.6
𝑒
𝐸𝑠
=
𝐸
𝑠
εsm-εcm =0.000390
c =75mm
Sr, max =3.4c+0.17×Φ/Ρ1, eff) =3.4×75+0.17×32/0.0236
=485.8mm
Crack width = Sr, max ×(εsm-εcm)
=485.8×0.000390
=0.1897mm >0.3mm (ok for severe case)
287
Es =200000MPa(N/mm2)
Actual Stress(σsc) = Mc ×106/ (As× z)
=-695×106/(5362×2076) =-61.99N/mm2
Kt =0.5
Fcm =fck+10 =40MPa
Fct, eff =0.259×(Fck)2/3
=0.259×(30)2/3 =2.5
Ecm =22×(fcm/12.5)0.3×1000MPa(N/mm2)
=31187 MPa
ρ1, eff =As/Ac, eff =5362/227500 =0.0236
αe =Es/Ecm =200000/31187 =6.413
𝑓𝑐𝑡,
𝜎 − ∗
𝛼 ∗ (1 + ∗ 𝜎𝑠𝑐
𝜀𝑠𝑚 − 𝜀𝑐𝑚 𝑠𝑐 𝑘𝑡 𝜌𝑝,𝑒𝑓𝑓 𝜌𝑝,𝑒𝑓𝑓) ≥ 0.6
𝑒 𝐸𝑠
=
𝐸
𝑠
εsm-εcm =0.000390
c =75mm
Sr, max =3.4c+0.17×Φ/Ρ1, eff) =3.4×75+0.17×32/0.0236
=485.8mm
Crack width = Sr, max ×(εsm-εcm)
=485.8×0.000390
=0.1897mm >0.3mm (ok for severe case)
288
9.6 REFERENCES
1. B.C. Punmia, A. J. (2007). Limit State Design of Reinforced Concrete (First ed.). New Delhi:
Laxmi Publication (P) Ltd.
2. Duggal, S. K. (2008). Design of Steel Structures (Third ed.). New Delhi: Tata McGraw-Hill
Publishing Company Ltd.
3. Raju, N. K. Design of Bridges (Fourth ed.). New Delhi: Oxford & IBH Publishing Co Pvt. Ltd.
4. S Unikrishna Pillai, D. M. (2014). Reinforced Concrete Design (Third ed.). New Delhi: Tata
McGraw-Hill Publishing Company Ltd.
5. Sairam, D. K. (2015). Design of Steel Structures (Revised Second ed.). New Delhi: Pearson
Education India.
6. Subramanian, N. (2010). Steel Structures: Design and Practice (First ed.). New Delhi: Oxford
University Press.
7. Dr. Suwal, R. (2019). Design of Bridges (First ed.). Kathmandu: Mark Line Publication.
8. Victor, D. J. (2017). Essentials of Bridge Engineering (Sixth ed.). New Delhi: CBS Publishers
and Distributors Pvt. Ltd.
1. ‘IRC: 5-2015 Standard specification and code of practices for road bridges, section-I General
Features of Design’, Indian Road Congress, 2015.
2. ‘IRC: 6-2017 Standard specification and code of practices for road bridges, section-II Loads and
Stresses’, Indian Road Congress, 2017.
3. ‘IRC: 21-2000 Standard specification and code of practices for road bridges, section-III –Cement
concrete (plain and reinforced)’, Indian Road Congress, 2000.
4. ‘IRC: 78-2014 Standard specification and code of practices for road bridges, section-VII –
Foundation and substructure’, Indian Road Congress, 2000.
5. ‘IRC: 83-2018 Standard specification and code of practices for road bridges, section-IX –
Bearings- part II: Elastomeric bearings’, Indian Road Congress, 2018.
6. ‘IRC: 112-2020 Code of practices for concrete road bridges’, Indian Road Congress, 2020.
7. ‘IRC: SP: 114- 2018 Guidelines for seismic design of road bridges’, Indian Road Congress,
289
8. ‘SP 105:2015 ‘Hand book on Code of practices for concrete road bridges’, Indian Road
Congress.
9. ‘Nepal Bridge Standards-2067’, GON, Ministry of Physical Planning and works, Department of
Roads
10. ‘Nepal Rural Road Standard (2055) 2nd Revision, 2071’, Department of Local Infrastructure, 2014
290