PSOC
PSOC
REGULATION 2013
Dr. R. SELVARASU
Professor
Dept. of Electronics and Instrumentation Engineering,
Arunai Engineering College
Tiruvannamalai
D. PERIYAAZHAGAR
Assistant Professor
Dept. of Electrical and Electronics Engineering,
Arunai Engineering College
Tiruvannamalai
with U
s t S o lved A
Late s
t i o n Paper
Que s 16
t o J u ne 20
up
All rights reserved by the publisher.
This book or part thereof should not be reproduced in any form without the written permission of the
authors.
ISBN: 978-93-85364-32-7
` 280/-
The authors take great immense pleasure in introducing the text book
“Power System Operation and Control”. The book has been prepared
with the intention to help the VI - Semester EEE students of Anna University
(Regulation 2013) and to enable them to understand the fundamental concepts
of power system operation and control, Real power frequency control,
Reactive power voltage control, unit commitment, economic dispatch and
computer control of power system. The book has been presented in a simple
style to enable them to grasp the subject. This book is student friendly.
The authors extend their gratefulness to their family members for their
whole hearted encouragement.
Last but not least the authors shows their special thanks to the
publishers “Sri Krishna Hitech Publishing Company Pvt. Ltd.,” and their
team members for their efforts to bring out this book successfully at the
right time for the benefit of the students.
Authors
6<//$%86
UNIT I INTRODUCTION
An overview of power system operation and control - system load variation
- load characteristics - load curves and load-duration curve - load factor - diversity
factor - Importance of load forecasting and quadratic and exponential curve fitting
techniques of forecasting - plant level and system level controls.
UNIT I: INTRODUCTION
1.1 Overview of Power System Operation and Control.............................. 1.1
1.1.1 Overview of power system operation ........................................ 1.1
1.1.2 Overview of plant level and system level control ................... 1.4
1.2 System Load Variation ............................................................................. 1.7
1.2.1 Domestic (or) Residential load ................................................... 1.7
1.2.2 Industrial load ............................................................................... 1.8
1.2.3 Commercial load........................................................................... 1.8
1.2.4 Urban traction load ...................................................................... 1.8
1.2.5 Municipal load .............................................................................. 1.8
1.2.6 Irrigation load ............................................................................... 1.9
1.3 Load Characteristics .................................................................................. 1.9
1.3.1 Static characteristics ..................................................................... 1.9
1.4 Load Curves............................................................................................... 1.15
1.4.1 Daily Load curve ......................................................................... 1.15
1.4.2 Monthly Load curve .................................................................... 1.16
1.4.3 Annual load curve........................................................................ 1.16
1.4.4 Importance of Load curve........................................................... 1.16
1.5 Load Duration Curve ................................................................................ 1.17
1.6 Important Terms for Deciding the type and Ratings of Generating 1.17
Plant............................................................................................................
1.7 Load Factor (or) Demand Factor ............................................................ 1.19
1.8 Diversity Factor ......................................................................................... 1.20
1.9 Reserve Capacity And Requirements ...................................................... 1.20
1.10 Importance of Load Forecasting and Quadratic and Exponential Curve 1.22
Fitting Techniques Of Forecasting...........................................................
1.10.1 Load forecasting ........................................................................... 1.22
1.11 Basic P-f and Q-V Control Loops.......................................................... 1.25
1.11.1 AVR loop (or) Q-V control loop............................................... 1.25
1.11.2 ALFC loop (or) P-f control loop .............................................. 1.25
Worked Examples..................................................................................... 1.28
PART - A: Questions and Answers ...................................................... 1.50
PART - B: Questions .............................................................................. 1.54
UNIT II: REAL POWER – FREQUENCY CONTROL
2.1 Philosophy of Real And Reactive Power Control................................ 2.1
2.2 Basics of Speed Governing Mechanism and Modeling ....................... 2.2
2.3 Static Power Generation .......................................................................... 2.9
2.4 Speed Load Characteristics (Load Sharing Between Two Synchronous 2.11
Machines in Parallel) ...............................................................................
2.5 Control Area Concept .............................................................................. 2.14
2.6 Load Frequency Control of Single Area System (without Integral 2.14
Control) .....................................................................................................
2.6.1 Static Analysis (or) steady state response of uncontrolled case 2.15
2.6.2 Static Analysis of Controlled Case ........................................... 2.18
2.6.3 Static analysis when Pc PD ............................................. 2.19
2.6.4 Dynamic analysis of uncontrolled case (Single Area) ............ 2.20
2.6.5 Dynamic Analysis of Controlled Case...................................... 2.23
2.7 Load Frequency Control of Single Area System with Integral 2.23
Controller...................................................................................................
2.7.1 Static analysis (or) steady state response (Uncontrolled case) 2.24
2.7.2 Dynamic response of uncontrolled case.................................... 2.25
2.8 Two Area Load Frequency Control ....................................................... 2.29
2.8.1 Two Area Load Frequency Control System Modelling .......... 2.30
2.8.2 Static Analysis of Uncontrolled Case (Two Area System) .... 2.35
2.8.3 Dynamic response of uncontrolled case (Two area system) .. 2.37
2.9 Tie Line with Frequency Bias Control of Two Area System ............ 2.41
2.9.1 Determination of tie line with frequency bias control of two 2.42
area system...................................................................................
2.9.2 The line bias control of multi area systems ............................ 2.44
2.10 Types of Automatic Load Frequency Controls for Interconnected 2.45
Power System ...........................................................................................
2.10.1 Flat frequency control................................................................. 2.45
2.10.2 Flat tie line load control ............................................................ 2.45
2.10.3 Tie line load bias control........................................................... 2.46
2.11 Economic Dispatch Control With LFC.................................................. 2.49
Worked Example ...................................................................................... 2.50
PART - A: Questions And Answers ..................................................... 2.81
PART - B: Questions .............................................................................. 2.86
UNIT III: REACTIVE POWER – VOLTAGE CONTROL
3.1 Generation And Absorption of Reactive Power.................................... 3.1
3.2 Basics of Reactive Power Control ......................................................... 3.5
3.2.1 Definition of Reactive power..................................................... 3.5
3.2.2 Positive and Negative Reactive power...................................... 3.6
3.2.3 System losses due to reactive power flow............................... 3.7
3.2.4 Causes of Low power factor ..................................................... 3.8
3.2.5 Effects of Low power factor ..................................................... 3.8
3.2.6 Advantages of power factor Improvement................................ 3.8
3.3 Excitation System ..................................................................................... 3.9
3.3.1 Requirements ................................................................................ 3.9
3.3.2 Classification ................................................................................ 3.9
3.4 Modeling of Typical Excitation System (or) Modeling of Automatic 3.15
Voltage Regulator.....................................................................................
3.5 Static And Dynamic Analysis of AVR ................................................. 3.21
3.5.1 Static analysis of AVR............................................................... 3.21
3.5.2 Steady state response for a closed loop transfer function...... 3.23
3.5.3 Dynamic Analysis of AVR loop ............................................... 3.24
3.6 Stability Compensation............................................................................. 3.25
3.7 Methods of Voltage Control and Secondary Voltage Control ............ 3.27
3.8 Tap Changing Transformer...................................................................... 3.27
3.9 SVC (TCR + TSC).................................................................................. 3.29
3.10 Static Synchronous Compensator (STATCOM)..................................... 3.30
Worked Examples..................................................................................... 3.32
PART - A: Questions and Answers....................................................... 3.55
PART - B: Questions .............................................................................. 3.61
UNIT IV: UNIT COMMITMENT AND ECONOMIC DISPATCH
4.1 Economic Dispatch ................................................................................... 4.1
4.1.1 Optimal operation of Generators on a busbar.......................... 4.1
4.1.2 Economic Dispatch Problem....................................................... 4.4
4.2 Input - Output Cost Characteristics ........................................................ 4.5
4.3 Incremental Cost Curve ........................................................................... 4.6
4.3.1 Cost Function ............................................................................... 4.6
4.3.2 Incremental cost curve of Received Power (or) System 4.7
Incremental Cost (or) Incremental fuel cost (IC).....................
4.4 Co-ordination Equations ........................................................................... 4.10
4.5 Coordination Equation Without Loss...................................................... 4.12
4.6 Coordination Equation With Loss (or) Exact Coordination Equation. 4.15
4.7 Solution By Direct Method ..................................................................... 4.17
4.8 Solution By Iteration Method Without Loss (Computer Approach) 4.17
4.8.1 Computational Approach for optimum Allocation of 4.21
Generation (Including losses) .....................................................
4.9 Statement of Unit Commitment Problem............................................... 4.24
4.9.1 Need for unit commitment ......................................................... 4.24
4.9.2 Difficulties to find unit commitment solution .......................... 4.25
4.9.3 Constraints on unit commitment problem ................................. 4.25
4.10 Methods Available for Unit Commitment.............................................. 4.26
4.10.1 Priority List Method.................................................................... 4.26
4.10.2 Solution of unit commitment problem by Forward Dynamic 4.31
Programming ................................................................................
Worked Examples..................................................................................... 4.33
PART - A: Questions and Answers....................................................... 4.62
PART - B: Questions .............................................................................. 4.68
UNIT V: COMPUTER CONTROL OF POWER SYSTEMS
5.1 Need for Computer Control of Power Systems.................................... 5.1
5.2 Concept of Energy Control Centre ........................................................ 5.1
5.3 SCADA (Supervisory Control And Data Acquisition System) ........... 5.6
5.3.1 Functions of SCADA.................................................................. 5.6
5.3.2 Need for SCADA........................................................................ 5.7
5.3.3 Components of SCADA ............................................................. 5.7
5.3.4 Configurations .............................................................................. 5.7
5.3.5 Master unit ................................................................................... 5.9
5.3.6 Remote Terminal Units (RTU) .................................................. 5.10
5.3.7 Communication channels in SCADA system ........................... 5.10
5.4 Energy Management System (EMS) ...................................................... 5.11
5.4.1 Energy management system for utilities ................................... 5.11
5.4.2 Energy management system for users....................................... 5.12
5.5 Network Topology.................................................................................... 5.13
5.6 State Estimation........................................................................................ 5.14
5.6.1 Maximum Likelihood Weighted Least Squares Estimation..... 5.14
5.6.2 Power system state estimation ................................................... 5.19
5.7 Contingency Analysis............................................................................... 5.20
5.8 System States Transition Diagram.......................................................... 5.22
5.9 Hardware Requirements for Computer Control of Power System...... 5.23
5.10 Software for Computer Control of Power System ............................... 5.24
PART - A: Questions and Answers ...................................................... 5.25
PART - B: Questions .............................................................................. 5.29
Anna University Solved Question Papers.............................................. 1-34
UNIT - I
8=CA>3D2C8>=
running at different times of the day. To run a generating unit means to start the
auxiliaries, bring the unit to full speed, synchronise it with the system and load it.
Different types of generating units have different start up time and characteristics.
In big houses, the demand factor may be only around 0.5. During summer the
major part of domestic load may consists of refrigerator load, fan load during day
and light and fan load during evenings. During winter, the major load is light load
during evenings and early mornings and some heater load and refrigerator load. Fig.
2 (a) shows the curve for domestic load.
The load for water supply is for pumping water to the overhead tanks. It is
generally possible to fit this load during system off peak hours, usually occurring
during night.
The heating load maintains constant resistance with voltage change and hence
the power varies with (voltage)2, where as, lighting load is independent of frequency
and power consumed varies as V1.6 rather than V2. From the electrical point of view
the magnitude of devices are characterized by vast differences with regard to
Size
P P |V| ...(1.1)
Q Q |V| ...(1.2)
|V|2
P with R constant
R
|V|2
P with R V
R
V2 R j XL
R j XL R j XL
V2
2 [R j XL]
R X2L
V2
P jQ 2 R j XL
R X2L
V2 V2 ...(1.4)
P 2 R R
R X2L R2 2 fL2
V2 V2 ...(1.5)
Q 2 XL 2 fL
R X2L R2 2 fL2
Real power
From the equivalent circuit, the real power P per phase consumed by the motor
is given by
R2 |V|2 R2 ...(1.8)
P |I|2 s
s 2
R
2
X2
s
Where,
R2 = Rotor resistance
X1 = Stator leakage reactance
X2 = Rotor leakage reactance referred to stator
Xm = Phase voltage
s = Slip
X X1 X2
Reactive power
The reactive power consumed by the motor consists of two components, namely,
the magnetizing component Q associated with magnetizing current I and the
component Qs depending upon stator and rotor leakage. Thus the reactive power Q
per phase as
Q Q Qs ...(1.9)
Where,
|V|2 ...(1.10)
Q I |V|
Xm
Qs |I|2 Xs (1.11)
Fig. 1.5 (a) Variation of I and Xm with Fig. 1.5 (b) Reactive power Q as a
applied voltage function of voltage
|V|2 R2 ...(1.12)
P
2 s
R
2 X2
s
dp
The critical point occurs when is equal to zero.
ds
Differentiating P with respect to s, we get
dp 1
|V|2 R2
ds
2
R2 2
s s X
2
2
R 2R2 R2 R
s 2 X2 0 1 s 2 2 2
X
s s s
2
|V| R2 s
2 2
2 R2 2
s X
s
2
2R2 R
2 2
X2
s s
|V|2 R2 2 2
2 R2 2
s X
s
2
R
2
|V|2 R2 X2
s 2
R22 sX2
2 2
|V| R2
R R22 sx2
2
s2 X2
s
dp
Equating 0, we get
ds
R22 sX2 0
R22 s2 X2, R2 sX
R2 ...(1.13)
s scr
X
Introduction 1.15
where,
scr= critical slip
|V|2 sX
Pmax 2
s
sX X2
s
|V|2 ...(1.14)
Pmax per phase
2X
# ;>03 2DAE4B
The curve showing the variation of load on the power station with reference to
time is known as a load curve.
It is clear that load on the power station is varying and being maximum at 6
pm in this case.
When the load elements of a load curve are arranged in the order of descending
magnitudes, the curve thus obtained is called a load duration curve.
The load duration curve is obtained from the same data as the load curve but
the ordinates are arranged in the order of descending magnitudes. In otherwords, the
maximum load is represented to the left and decreasing loads are represented to the
right in the descending order. Hence the area under the load duration curve and the
area under the load curve are equal. Fig 1.8 (a) shows the daily load curve. The
daily load duration curve can be readily obtained from it. It is clear from daily load
curve that load elements in order of descending magnitude are: 20 MW for 8 hours,
15 MW for 4 hours and 5 MW for 12 hours. Plotting these loads in the order of
descending magnitudes the daily load duration curve can be obtained as shown in
Fig. 1.8 (b).
Fig. 1.8 (a) Load curve Fig. 1.8 (b) Load duration curve
Maximum demand
Demand factor
Connected load
Load factor is defined as the ratio of average load to the maximum demand
during a certain period of time such as a day (or) a month (or) a year.
Average load
Load factor
Maximum demand
If the plant is operated for T hours.
Average load T
Load factor
Maximum demand T
The ratio of sum of the individual maximum demands of all the consumers
supplied by the power station to the maximum demand of the power station is called
the diversity factor.
Sum of individual maximum demands
Diversity factor
Maximum demand of power station
It is always greater than the unity.
Because maximum demand of different consumers do not occur at same time. Therefore
Maximum demand on Sum of individual
the power station maximum demands
If diversity factor is more, the cost of generation of power is low.
Each of the above methodologies have its own advantages and limitations. No
one approach is used by all the utilities consistently. Choosing the best method for
a given system requires good judgement of the planner.
One method, used by many utilities, for long range load forecasting is
extrapolation. Extrapolation technique involves filling trend curves to basic historical
data adjusted to reflect the growth trend itself. Once the trend curve is known, the
forecast is found by evaluation the trend curve function at the desired future point.
Some of the functions used in Trend curve filling are:
Straight line Y A Bx
Parabola Y A Bx Cx2
S curve Y A Bx Cx2 Dx3
Exponential Y CDx
e
Gompertz Y ln 1 A CDx
e
Combination Y A Bx CDx
e
Where Y is the load in year x (with base year zero) and A, B, C, D are constants
computed, generally, by the method of least squares.
If the uncertainty of extrapolated results is to be quantified using statistical
entities like mean and variance, the basic technique become probabilities extrapolation.
The use of stochastic models to generate a forecast from random inputs derived from
historical data has also been suggested but is not used in actual practice.
Another technique for load forecasting is correlation. This technique relates
system loads to various demographic and economic factors. Typically factors like
population, employment, industrial licenses, appliance saturation, weather data etc are
used in correlation techniques. However the forecasting of the demographic and
economic factors is rather difficult.
Many digital computer programs for load decomposition and forecasting have
been developed by many utilities.
1. Static changes in Pi in the real power affect the bus phase angle and not
the bus voltage magnitude. This change affects the real power line flows
and not the reactive power line flows.
2. Static changes Qi in the reactive power affect the bus voltage magnitudes
and the phase angle. This change affects the reactive power line flows and
not the real power line flows.
3. Static changes in the reactive power affects the bus voltage at the particular
bus and has little effect on the magnitude of voltage.
In order to perform voltage and frequency control a basic generator will have
two control loops namely,
(i) Automatic voltage control loops (or) Q-V control loop
(ii) Automatic load frequency control (ALFC) loop (or) P-f control loop.
Fig. 1.9 Automatic load frequency and Voltage regulator control loops
Introduction 1.27
After this part of the circuit is the introduction of the primary ALFC loop whose
functions has already been described.
Thus, the two loops together help in controlling speed which in turns controls
the frequency, since N f.
120f
Using the speed relation, N
P
Where
f = Frequency in Hz
p = Number of poles
1.28 Power System Operation and Control
WORKED EXAMPLES
4G0<?;4 1.1
A generating station has a maximum demand of 400 MW. The annual load factor
is 60% and capacity factor is 50%. Find the reserve capacity of the plant.
(April/May 2010)
Given data
Load factor 0.6
Solution
Energy generated per annum
2102.4 103
0.5 8760
480 MW
480 400
80 MW
Introduction 1.29
4G0<?;4 1.2
A generating station has a maximum demand of 25 MW. Load factor is 60%, plant
capacity factor is 50% and plant use factor is 72%. Find the reserve capacity and
daily energy produced.
Solution
60
Load factor 0.6
100
50
Plant capacity factor 0.5
100
Maximum demand 25 MW
25 0.6 15 kW
Average load
Plant capacity factor
Installed capacity
Average load
Installed capacity (or) Plant capacity
Plant capacity factor
15
30 MW
0.5
Fr om aver age load,
Ener gy pr oduced per day 15 24
360 kW/day
72
Plant use factor 0.72
100
Energy produced per day
Maximum energy produced
Plant use factor
360
500 kW
0.72
Reserve capacity Plant capacity Maximum demand
30 25 5 kW
1.30 Power System Operation and Control
4G0<?;4 1.3
Solution
(a) Total maximum demand of loads
10000 30000 50000
90000 kW
System Diversity factor = 1.5
Total maximum demand
Maximum demand
System diversity factor
90000
60000 kW
1.5
Commercial load
Maximum Diversity
Maximum commercial
commercial factor of
load demand demand commercial load
Industrial load
Maximum Diversity
Maximum Industrial
Industrial factor of
load demand demand Industrial load
50000 1.35
67500 kW
Maximum demand Industrial
Connected Industr ial load
Demand factor of industrial load
67500
0.95
71052.63 kW
4G0<?;4 1.4
Solution
Time (hrs)/Group 0-6 6-8 8-10 10-18 18-24
A – – 200 kW 200 kW –
B – 100 kW 100 kW – –
C – 50 kW 50 kW – –
D 100 kW – – 100 kW 100 kW
Total load on power 100 kW 150 kW 350 kW 300 kW 100 kW
station
Fig. 1.10
Average load
(c) Load factor
Maximum demand
Units generated per day
Average load
Hour’s in a day
4600
191.666 kW
24
191.666
Load factor 0.5476 54.7%
350
4G0<?;4 1.5
A generating station has the following daily loads. (Dec 2012, 2013)
0 - 6 hrs 4500 kW
6 - 8 hrs 3500 kW
8 - 12 hrs 7500 kW
12 - 14 hrs 2000 kW
14 - 18 hrs 8000 kW
18 - 20 hrs 2500 kW
20 - 24 hrs 5000 kW
Sketch the load duration curve and determine the load factor and plant capacity
factor if the capacity of the plant is 12 MW.
Solution
Fig. 1.11
1.34 Power System Operation and Control
Fig. 1.12
1,25,000 kWhr
Introduction 1.35
4G0<?;4 1.6
250 106
28.54 kW
365 24
Average load
Annual load factor 100
Maximum demand
28.54
100
40 103
0.071%
Maximum demand
Demand factor
Connected load
40
0.533 or 53.33%
75
1.36 Power System Operation and Control
4G0<?;4 1.7
(Dec 2008)
Solution
Maximum demand = 2500 kW
1.1
Average load
(b) Average load factor
Maximum demand
45 105 45 105
24 365 8760
513.69
Load factor
2500
20.54%
Introduction 1.37
4G0<?;4 1.8
The annual load duration curve of a certain power station can be considered as a
straight line from 20 MW to 4 MW. To meet this load, three turbine generator
units, two rated at 10 MW each and one rated at 5 MW are installed. Determine
(i) Installed capacity
(ii) Plant factor
(iii) Units generated per annum
(iv) Load factor and
(v) Utilization factor
Solution
Fig. 1.13
Average demand
(iv) Load factor
Maximum demand
12000
60%
20000
Maximum demand
(v) Utilization factor
Plant capacity
20
0.8
25
4G0<?;4 1.9
(May 2011)
Solution
Sum of all individual maximum demands
Diversity factor
Maximum demand on power station
95 5 8 12
92
1.3043
3 108
34246 kW
24 365
Introduction 1.39
Average load
Load factor
Maximum demand
34246
0.372
92 103
37.2%
4G0<?;4 1.10
A generating station supplied the following loads 15000 kW, 12000 kW, 8500 kW,
6000 kW and 450 kW. The station has a maximum demand of 22000 kW. The
annual load factor of the station is 48% calculate
(i) the number of units supplied
(ii) the diversity factor
(iii) the demand factor (Dec 2009)
Solution
M.D = 22000 kW
Average load
Annual load factor
Maximum demand
Average load
0.48
22000
Average load 22000 0.48 10,560 kW
kWhr generated per annum
Average load
Hours in a year
kWhr generated per annum 10560 8760
92 106
Average load
Demand factor
Maximum demand
10,560
0.48
22,000
4G0<?;4 1.11
Given data
Maximum demand 20 MW
0.6 20,000
12,000 kW
Average demand
Plant capacity factor
Installed capacity
Average demand
Installed capacity
Plant capacity factor
12000
25000 kW
0.48
Introduction 1.41
4G0<?;4 1.12
A generating station has a maximum demand of 50,000 kW. Calculate the cost per
unit generated from the following data.
Capital cost Rs.95 106
Annual load factor 40%
Annual cost of fuel and oil Rs. 9 106
Taxes, wages and salaries, etc. Rs. 7.5 106
Interest and depreciation 12% (Dec 2011, 2013)
Solution
Annual Hours
Units generated/annum { Maximum demand } Load in a
factor year
0.12 95 106
27.9 106
Rs. 0.16
17.52 107
16 paise
4G0<?;4 1.13
The maximum demand of a power plant is 40 MW. The capacity factor is 0.5 and
the utilisation factor is 0.8. Find
(a) Load factor
(b) Plant capacity
(c) Reserve capacity
(d) Annual energy production
Solution
Capacity factor 0.5
(a) Load factor 0.625
Utilisation factor 0.8
Introduction 1.43
Maximum demand 40
(b) Plant capacity
Utilisation factor 0.8
50 MW
(c) Reserve capacity 50 40 10 MW
(d) Annual energy production 40 0.625 8760
219000 MWhr
4G0<?;4 1.14
The load curve of an electrical system is linear with the following values at different
times of the day:
Time 0 5 AM 9 6 8 PM 10 12
Load (MW) 50 50 100 100 150 80 50
Plot chronological load curve. Find the energy required by the system in one day
and the system daily load factor.
Solution
Fig. 1.14
2060
Daily load factor 0.5722
150 24
57.22%
4G0<?;4 1.15
Consider an inductive load of type Z R jX. By how many percent will be the
real power load drop if the voltage is reduced by 5%. (Nov, 2004)
Solution
1
P j Q |V|2 Y |V|2
R jX
1 1
Multiplying by complex Y
Z R jX
Conjugate of denominator and numerator, we get
|V|2 R jX R jX
|V|2 2
R jX R jX R X2
Equating real and imaginary parts, we get
R
P |V|2 2
R X2
X
Q |V|2 2
R X2
4G0<?;4 1.16
The maximum demand on a power station is 100 MW. If the annual load factor
is 40%. Calculate the total energy generated in a year. (Dec 2008)
Solution
Maximum Annual Hours in a
Units generated/annum
demand load factor year
350400 MWhr
4G0<?;4 1.17
5200 MW
5.2 kWhr
1.46 Power System Operation and Control
Fig. 1.15
21.7%
4G0<?;4 1.18
The yearly load - duration curve of a power plant is a straight line (Fig. 1.16)
The maximum demand (load) is 30 MW and the minimum load is 20 MW. The
capacity of the plant is 35 MW. Calculate the plant capacity factor, the load factor,
and the utilization factor.
Solution
No. of units generated per year = Area OACD Area OBCD Area BAC
Introduction 1.47
1
20 8760 30 20 8760
2
1
8760 20 10
2
8760 25 2,19,000 MWhr
No. of units generated per year
Average annual load
8760
2,19,000
25 MW
8760
Average annual load 25
Load factor 0.833
Maximum load 30
Average annual load
Plant capacity factor
Rated plant capacity
25
0.714
35
Maximum demand 30
Utilization 0.857
Rated capacity 35
Alternatively
Capacity factor
Utilization factor
Load factor
0.714
0.857
0.833
4G0<?;4 1.19
A generating station supplies four feeders with the maximum demands (in MW) of
16, 10, 12 and 7 MW. The overall maximum demand on the station is 20 MW
and the annual load factor is 45%. Calculate the diversity factor and the number
of units generated annually.
Solution
Sum of maximum demands 16 10 12 7
45 MW
45
2.25
20
20 0.45 9 MW
78840 MWhr
Alternatively
No. of units generated annually
Annual load factor
Maximum demand 8760
78,840 MWhr
Introduction 1.49
4G0<?;4 1.20
Calculate the annual load factor of 120 MW power station which delivers 110 MW
for 4 hrs, 60 MW for 10 hrs and is shut down for the rest of each day. For
general maintenance, it is shut down for 60 days per annum.
Solution
Capacity of power station = 120 MW
60 MW for 10 hrs
And for general maintenance, it is shut down for 60 days per annum.
1,040 MWhr
305
3,17,200 MWhr
MWhr supplied/annum
Annual load factor
Maximum demand in MW Working hours
3,17,200
100
120 305 24
36.11%
1.50 Power System Operation and Control
2. What are the advantages of computer control in power system? What are
the types of computer control? (May 2015)
Advantages
1. Maintaining frequency within limits.
2. Maintaining bus voltage within limits.
3. Maintaining current flows within limits.
4. Transformers and generators operating within their ratings.
3. Define Load?
Load is a device that taps energy from the network.
5. What are the various types of loads connected to the system? (Dec 2008)
1. Residential load
2. Commercial load
3. Industrial load
4. Agricultural load
5. Municipal load
Introduction 1.51
8. What is the difference between load curve and load duration curve?
(Dec. 2009, Dec 2014)
Load curve
The curve drawn between the variations of load on the power station with
reference to time is known as load curve. There are three types, Daily load curve,
Monthly load curve and Yearly load curve.
13. What is the need for load forecasting? (Nov/Dec 2008), (Dec 2015)
1. To meet out the future demand.
2. Planning for future expansion of the system.
3. Maintaining the required spinning reserve.
4. Allocating spinning reserve.
14. What is meant by load frequency control? (Dec 2007, 2008)
In interconnected systems with two or more independently controlled areas, in
addition to control of frequency, generation within each area has to be controlled to
maintain scheduled power interchange.
15. What are the advantages of pool operation with respect to LFC?
(May 2008)
1. 50% of the added load in area 2 will be supplied by area 1 through the
tie line.
2. Frequency drop will be only half compared with that of single area.
16. What are plant level controls?
1. Prime mover control
2. Excitation control
17. What is meant by system voltage control? (Nov/Dec 2009) (June 2007)
System voltage control is the process of controlling the system voltage within
tolerable limits. The task of voltage control is closely associated with fluctuating load
and corresponding requirement of reactive power compensation under steady state and
transient state.
18. Define utilization factor?
Maximum demand on the power station
Utilization factor
Rated capacity of the power station
19. What happens to frequency if the load on the generator increases?
When the load on the generator increases, the speed of the generator decreases.
Introduction 1.53
120f
N
P
Nf
21. Give the two major control loop for large generators. (May 2005)
1. P - f control loops
2. Q - V control loops
23. What are the various need for frequency and voltage to be regulated in
power system?
(Nov/Dec 2013) (April/May 2009) (April/May 2008) (Dec 2007) (June 2007)
(May 2005)
1. In any power system, if the frequency changes there won’t be required
voltage at the receiving end. If we connected two systems in parallel, it
will spoil the system.
2. The generator turbines are designed to operate at a very precise speed that
can be maintained by regulating frequency.
Fig. 1.17
PART - B QUESTIONS
1. Explain an overview of power system operation and control and the role of
computer in the implementation with the help of block diagram. (Dec/AU/14)
2. (i) Explain the need for voltage and frequency regulation in power system.
(8) (April/May 2010)
(ii) A generating station has a maximum demand of 400 MW. The annual load
factor is 65% and capacity factor is 50%. Find the reserve capacity of the plant.
(8) (April/May 2010)
3. Why is the load on a power station variable? What are the effects of variable
load on the operation of the power station? (8) (April/May 2008)
4. Explain the important objectives of power system and various control strategies
during its operation. (16) (Nov/Dec 2012)
5. Highlight briefly the importance of regulating frequency and voltage of the power
system. (8) (April/May 2011)
Introduction 1.55
6. Consider an inductive load of type Z R jX. By how many percent will the
real load drop if the voltage is reduced by 1%?
(8) (April/May 2010)
7. (i) Draw the load curve and load duration curve. Explain the Importance of
these curves in connection with economic operation of power system.
Industries 92 MW
Domestic lighting load 8 MW
Domestic power load 9 MW
Commercial load 11 MW
The maximum demand on the station is 90 MW. Calculate the load factor and
diversity factor if the total numbers of units generated in a year are 3 108
(16)
10. A generating station has the following daily load cycle: (10) (Nov/Dec 2012)
1. Maximum demand
2. Units generated per day
3. Average load
4. Load factor
1.56 Power System Operation and Control
15. A generating station has a maximum demand of 50,000 kW. Calculate the cost
per unit generated from the following data:
Capital cost = Rs. 95 106.
Annual load factor 40%.
Annual, cost of fuel and oil = Rs. 9 106
Taxes, wages and salaries, etc. Rs. 7.5 106
Interest and depreciation = 12% (12) (Nov/Dec 2013)
(ii) 1. Define Diversity factor 2. Define Plant use factor.
(4)
16. A generating station has the following daily load cycle:
1. Maximum demand
3. Average load
4. Load factor
(10)
17. A diesel station supplies the following loads to various consumers:
(Nov/Dec 2008)
Industries 1500 kW
Domestic lighting load 450 kW
Domestic power load 100 kW
Commercial load 750 kW
The maximum demand on the station is 2500 kW and the number of kWhr generated
per year is 45 106, determine (i) the annual load factor (ii) diversity factor.
1.58 Power System Operation and Control
Maximum
Type of load Diversity factor Demand factor
demand (kW)
Domestic 10,000 1.2 0.8
Commercial 30,000 1.3 0.9
Industrial 50,000 1.35 0.95
19. Define load factor and diversity factor. Explain the importance of these factor in
connection with economic operation of a power system. (8) (April/May 2008)
20. Explain the following 1. Load forecasting 2. Economic dispatch control
(8) (April/May 2008)
21. (i) Write short notes on load forecasting?
(4) (Nov/Dec 2008) (May 2015)
(ii) Define diversity factor. Discuss the practical ways to improve the diversity
factor. (4) (Nov/Dec 2008)
22. Explain the types of load forecasting.
(6) (April/May 2011)
23. What is load forecasting? Also state its classification and importance.
(8) (April/May 2011)
24. Explain the following:
(i) Hot reserve and cold reserve
(ii) Load curve and duration curve
(iii) Governor control
(iv) Security control (16) (Nov/Dec 2010)
25. (i) Define the following:
1. Hot reserve
2. Cold reserve
3. Spinning reserve (6) (Nov/Dec 2013)
Introduction 1.59
(April/May 2008)
29. (i) Discuss the various reserve requirements in power system operation.
(May 2015)
UNIT - II
Power system load flow studies bring out the following properties of power
system networks.
1. The changes in real power at buses mainly affect the bus voltage phase
angles (and therefore real power line flows) and have negligible effect on
bus voltage magnitudes and reactive power line flows.
2. The changes in reactive powers at buses mainly affect the bus voltage
magnitudes (and reactive power line flows) and have negligible effect on
bus voltage phase angles and real power line flows.
3. The changes in reactive powers at a bus have a very strong effect on the
voltage magnitude at that bus. But have a mild effect on voltage magnitudes
at distant buses.
The above system properties lead us to the following two methods of real and
reactive power control in power system.
The above two control channels operate more (or) less independent of each other.
Moreover the power factor loop is rather flow in action due to inertia of mechanical
parts whereas the Q-V loop is very fast. Fig 2.1 shows the two controls channels for
maintaining the real and reactive power balance in the system.
Fig. 2.1 Load frequency and Automatic voltage control channels of a turbo alternator
The real power in a power system is being controlled by controlling the driving
torque of the individual turbines of the system. The speed governor is the main primary
tool for the load frequency control. Whether the machine is used alone to feed a
smaller system or it is a part of the most elaborate arrangement. Fig. 2.2 shows
schematically the speed governing system of the steam turbine. By controlling the
position of the control valve or gate, we can exert control over the flow of high
pressure steam (or water) through the turbine.
Speed changer
It is a sort of bias applied to the governing system and usually takes the form
of an adjustment of spring tension. It enables the adjustment of speed governing system
to change the speed load characteristics of the machine. As shown in Fig. 2.2 an
adjustment of speed changer shifts the speed load characteristics parallel to itself up
or down.
Hydraulic amplifier
It consists of Pilot valve and main piston. With this arrangement a low Power
Pilot valve movement is converted into high power level movement of the oil
servomotor piston. The input to this amplifier is the position XD of the pilot valve.
The output is the position XE of the main piston. Hydraulic amplification is necessary,
so that the steam valve or gate could be operated against high pressure steam.
Linkage mechanism
ABC is a rigid link pivoted at B and CDE is another rigid link pivoted at D.
The function of the link mechanism is to control the steam valve or gate. Feedback
can be obtained from the movement of the steam valve Via link CD.
Working
As load increases the speed of the turbine decreasing, the speed changer gives
raise command and the fly balls move outwards and the point B moves downwards
and D moves upwards and high pressure oil enters into the upper pilot valves and
presses the main piston downwards and opens the valve (or) gate increases the flow
of steam to the turbine. Thereby speed of the turbine increases while maintaing
constant frequency.
XA Kc Pc
Movement of C
l2
XA Contributes XA K1 XA K1 Kc Pc
l1
Xc K1 Kc Pc K2 f ...(2.1)
Movement of D
Contributed by Xc and XE
l4 l3
XD Xc XE
l3 l4 l3 l4
K3 Xc K4 XE ...(2.2)
Movement of XD opens pilot valve, there by moving the main piston and
opening the steam valve by XE
Movement of XE
XE is proportional to the line integral of XD.
t ...(2.3)
XE K5 XD dt
0
k5 ...(2.6)
XE s XD s
s
Substitute equ. (2.5) in (2.6), we get
k5
XE s [k3 Xc s k4 XE s]
s
k4 k5 k5 k3 ...(2.7)
XE s 1 Xc s
s s
Substitute equ. (2.4) in equ. (2.7), we get
2.6 Power System Operation and Control
k4 k5 k5 k3
XE s 1 [ k1kc Pc s k2 F s]
s s
KG
XE s Pc s Fs
1 ...(2.8)
R 1 sTG
Where,
K1 Kc
R = = Speed regulation of the governor in Hz/MW
K2
K3 K1 Kc
KG = = Gain of speed governor
K4
1
TG = = Time constant of speed governor.
K4 K5
Value of TG 100 msec
Turbine model
Where,
Tt = Time constant of turbin
Kt = Gain constant
PV = Per unit change in valve position from nominal valve.
H Inertia constant
J2w ...(2.9)
WK E f20
0
WK E 0 0
2
2 f f2
WK E 1
0 2
f0 f0
2f [Neglecting Second order term]
WK E0 1
f0
2.8 Power System Operation and Control
Substituting WK E0
2Hs
PG s PD s F s B
f
0
PG s PD s
F s
2Hs
B1
Bf0
Kp ...(2.14)
F s PG s PD s
1 sTP
Real Power - Frequency Control 2.9
Where,
1
KP = Power system gain
B
2H
TP = Power system time constant
Bf0
Combining Fig. 2.3, 2.4 and 2.5 we get block diagram for load frequency control.
Apply block diagram reduction technique for the Fig. 2.6, we get
KG Kt 1
PG s [ PC s F s]
1 sTG 1 sTt R
F s 0
KG Kt ...(2.15)
PG s Pc s
1 sTG 1 sTt
2.10 Power System Operation and Control
KG Kt
s PG s Pc
1 sTG 1 sTt
KG Kt Pc
If we take KG Kt 1
PG stat Pc ...(2.17)
1 F s
PG s
1 sTG 1 sTt R
f
For a step change, F s
S
1 f 1 f
PG s , S PG s R
1 sTG 1 sTt sR 1 sTG 1 sTt
f
PG stat Lt s PG s
s0
R
f ...(2.18)
R Hz/MW
PG stat
R Speed regulation.
Real Power - Frequency Control 2.11
The per unit drop (or) speed regulation ‘R’ of the generating unit is defined as
the magnitude of the change in steady state speed, expressed in per unit of rated
speed when the output of the unit is gradually reduced from 1.0 p.u rated power to
zero.
Where,
f2 = Frequency at no load in Hz
f1 = Frequency at rated megawatt output PGr
fr = Rated frequency (Base)
Pr = Megawatt base
fr
Multiplying by in equation (2.19)
Pr
fr
Regulation (slope) Rp.u
pr
2.12 Power System Operation and Control
f2 f1 ...(2.20)
R Hz/MW
PGr
Suppose the unit is supplying output power PG0 at frequency f0 when the load
is increased to PG PG0 PG as shown in Fig.2.8.
fr
f R PG Rp.u PG Hz
pr
Due to supplementary control action of the speed changer, speed control
mechanism can parallel shift the regulation characteristics to the final position.
When two generating units are operating in parallel the changes in the outputs
of the units are given by.
Pr1 f ...(2.21)
Unit 1, PG1 MW
Rp.u fr
Pr2 f ...(2.22)
Unit 2, PG2 MW
Rp.u fr
Two different controls are carried out on the governor characteristics. The
parameters ‘R’ is adjusted during off-line condition of the unit to ensure its proper
co-ordination with the other units. The second control shifts the straight line
characteristics parallel to itself to change the load distribution among the generators
connected in parallel as well as to maintain the system frequency. The second control
also known as supplementary control is explained in Fig.2.9.
2.14 Power System Operation and Control
Suppose initially the total load is P and it is to be shared by the two units
P P1 P2 and the frequency is f0. Now if the load is increased to P, the frequency
falls to fn as the units can increase their output by giving away some of its kinetic
energy i.e., by reducing the speed in order to restore the system frequency,
characteristics of both the units (Fig. 2.8) (or) one of two units can be raised as
shown by the dotted line, so that the total load ‘P’ is shared by both the units keeping
the system frequency to fn. The power supplied here is P P1 P2. The raising
or lowering of governor characteristics is carried out with a device known as speed
changer which is operated either manually (or) by a speeder motor.
Load Frequency Control (LFC) deals with the control mechanism needed to
maintain the system frequency. The topic of maintaining the system frequency constant
is commonly known as Automatic Load Frequency Control (ALFC).
Let,
PC Incremental control input
PD Incremental disturbance input
The incremental control input is due to the change in the speed changer settings,
while the incremental disturbance input is due to the change in load demand.
There are two responses:
(i) Steady state (or) Static response
(ii) Dynamic state response.
Real Power - Frequency Control 2.15
Let Pc s 0
Fig. 2.11
Fig. 2.12
2.16 Power System Operation and Control
Kp
1 sTp
F s [ PD s]
Kp KG Kt
1
1 sTp R 1 sTG 1 sTt
Kp
F s [ PD s]
Kp KG Kt
1 sTp
R 1 sTG 1 sTt
PD
For a step load change PD s
s
Kp PD
F s
Kp KG Kt s
1 sTp
R 1 sTG 1 sTt
f stat Lt s F s
s0
Kp ...(2.25)
PD
Kp KG Kt
1
R
Let KG KG 1
Kp
f stat PD
Kp
1
R
1
Kp , PD M
B
PD Increase in load
1
PD
B M M
f stat
1
1
B
1
BR R
Real Power - Frequency Control 2.17
1
Where B B
R
Area frequency response coefficient (AFRC) in p.u MW/Hz
1
In Practice B , neglecting B
R
f stat R PD Hz
f stat ...(2.26)
R Hz/MW
PD
Where,
R = Speed regulation
f stat = Change in steady state frequency
f stat R PD Hz
If several generators with governor speed regulations R1, R2 Rn are connected
to the system, the steady state deviation in frequency is given by
PD
f stat
B 1 1 1
R1 R2 Rn
Fig. 2.14
Fig. 2.15
KG Kt Kp
F s Pc s
KG Kt Kp
1 sTG 1 sTt 1 sTP
R
KG Kt 1, Tt TG 0
Pc
Pc s
s
Real Power - Frequency Control 2.19
Kp Pc
F s
Kp s
1 sTG 1 sTt 1 sTp
R
f stat Lt s F s
s0
Kp
f stat Pc
Kp
1
R
1
B
f stat Pc
1
1
BR
1
Pc
1
B
R
f stat 1 ...(2.27)
Hz/MW
Pc 1
B
R
If the controlling force Pc is applied to the speed changer and the load demand
changes by Pc, the static frequency change is obtained by superposition theorem.
Kp ...(2.28)
f stat Pc PD
Kp
1
R
f stat 0, we get Pc PD
1. The system can be made faster by reducing ‘R’ i.e., by increasing the static
loop gain.
2.20 Power System Operation and Control
PD M
2. f stat
1
B
R
By reducing R, f stat can be reduced.
3. If Tt and TG are neglected, the transient frequency dip is more.
Fig. 2.16
Kp ...(2.29)
1 sTP
F s [ PD s]
Kp KG Kt
1
R 1 sTG 1 sTt 1 sTP
Where,
TP = 20 sec
TG = 0.4 sec
Tt = 0.5 sec
Real Power - Frequency Control 2.21
Approximate Analysis
Let Tt TG 0
KG Kt 1
Fig. 2.17
Kp
F s [ PD s]
Kp
1 sTP
R
PD
For a step change PD s
s
Kp PD
F s
1 Kp s
TP s
TP RTP
PD Kp
F s
R Kp
TP s s
RTP
PD Kp A B
F s s
TP R K
s
p
RTP
R Kp
As A Bs 1
RTP
2.22 Power System Operation and Control
AB0
RTP RTP
A ,B
R Kp R Kp
PD Kp RTP 1 1
F s
TP R Kp s R Kp
s
RTP
f t Inverse Laplace transform [ F s]
R Kp
PD Kp R
f t 1 e RTP
t
R Kp
R Kp
RKp t ...(2.30)
f t M 1 e RTP
R Kp
Let KG Kt 1, TG Tt 0
Fig. 2.19
Kp
F s Pc s
Kp
1 sTP
R
Pc
For a step change Pc s
s
Kp Pc
F s
R Kp
TPs s
RTP
R Kp ...(2.31)
Pc KpR t
F t 1 e RTp
R Kp
The single area control technique discussed above can result in considerable
steady state frequency drop from no load to full load. The steady state frequency can
be adjusted to the desired value by adjusting the speed changer setting of the governor.
A better control technique has been developed to improve the dynamic response of
the system. In this control known as integral control, the speed changer setting is
adjusted automatically by a signal obtained by amplifying and integrating the
frequency error. In load frequency control application the frequency change in an area
2.24 Power System Operation and Control
is known as Area Control Error (ACE). Thus in integral control the speed changer
setting is adjusted automatically by a signal of the type ACE dt. The integral
control gives zero steady state error.
If the frequency decreases, the integrator calls for an increase in power. The
gain kI control the response. The polarity of the integral controller must be chosen
so that a positive frequency error gives a negative or decrease generation command
and a negative frequency error gives a positive or increase generation command.
Generally electronic integrators of the type used in analog computers are used.
...(2.32)
Pc kI f dt
Fig. 2.21
PD
For a step change PD s
s
Kp PD
F s
KI 1 Kp s
1 sTp
s R 1 sTG 1 sTt
f stat Lt s F s 0
s0
By addition of the integral controller, we find the frequency error has been
reduced to zero. But we cannot eliminate the transient frequency error. Hence we
have to minimize ACE dt.
...(2.33)
Time error A CE dt
0
Fig. 2.22
Assume TG Tt 0
KG Kt 1
Fig. 2.23
The response is not correct since the device is electromechanical and will
therefore have a non-zero response time. The error in our analysis affect only the
transient, not the static response.
Kp
1 sTp
F s [ PD s]
Kp KI 1
1
1 sT s R
p
PD
For step change, PD s
s
Real Power - Frequency Control 2.27
Kp PD
F s
KI 1 s
1 sTp Kp
s R
Kp Rs PD
sR s2 TpR Kp KI R Kps s
Kp R PD
Tp Rs2 s [R Kp] Kp KIR
Kp PD ...(2.34)
R Kp Kp KI
TP s2 s T
RTp p
R Kp Kp KI
s2 s T 0
RTp p
2
R Kp R Kp Kp KI
RT 4 T
RTp p p
s
2
For the critical case, the two roots are equal and we find K1 critical
2
R Kp 4Kp KI
T R T 0
p p
2
4 Kp KI critical R Kp
Tp TpR
Tp R Kp2
KI critical
4Kp T2p R2
R2 2KpR K2p
KI critical
4Kp TpR2
2
2Kp Kp
1
1
4Kp Tp R R
2
1 Kp
4Kp Tp 1 R
2
1 Kp
KI critical 1
4Tp Kp R
1 2H
Substitute Kp and Tp in equ. (2.35)
B Bf0
2
1 1 1
KI critical
2H 1 BR
4
Bf0 B
1 B2R2 2BR 1
2H 1 B2 R2
4
Bf0 B
R2 B2 2B 1
2H R R2
4 BR2
Bf0
2
1B 1
2H R
B4
Bf0
f0 2 ...(2.36)
1
KI critical B
8H R
Clearly, the nature of poles depends upon the magnitude of kI. If KI KI critical
R Kp Kp KI
Roots of s2 s T 0
RTp p
Real Power - Frequency Control 2.29
RKps 1 1 Kp KI
s2 0
RTp R Kp Tp
2
1 Kp 1 KI KP 1 Kp 1
s j
2 RTp Tp Tp 4 RTp Tp
j
Thus we can write the denominator polynomial in the form.
s 2 2
When , are positive and real, this is the Super Critical Case.
The time response f t contains damped oscillatory terms of the type.
e t sin t and e t cos t
If KI KI critical (subcritical case), we can write the polynomial in the form.
s 1 s 2 where 1 and 2 are both positive.
f t will contain terms of the type
e 1 t and e 2 t
In either of the above case, f t will approach zero and the system will be stable.
Fig. 2.24 shows two large power systems A and B interconnected through a tie
line. The tie line transfers power from system A to B and Vice-Versa. The aim of
the control is to regulate the frequency in both the areas as also to regulate the power
flow over the tie line as per the agreement between the utilities of system A and
B.
The control areas intertied by transmission lines can take advantage of the
spinning mass of large number of generators and differences in incremental costs
between units. Power flow over the tie lines can be on short term basis (if a control
area suffers a decrease in generation due to forced outage of equipment) or on long
term basis if there is a mutually beneficial sale of energy between the utilities of the
two area.
A small system can suffer extensive transient power swings due to load changes.
If the system capacity is 1000 MW and a 200 MW load change occurs, this 20%
change in load may make the system unstable and a complete blackout may result.
However if this system were a part of a bigger system, say 50000 MW, a 200 MW
change in load means only a 0.4% change. The drop in frequency would be very
small and the flow of power over the tie line would save the system from collapse.
Fig. 2.25
|V1| |V2|
Ptie, 1 sin 01 02
X12
Where ,
01, 02 Power angles of equivalent machines of the two areas.
For incremental changes in 1 and 2, the incremental tie line power can be
expressed as,
Real Power - Frequency Control 2.31
|V1| |V2|
P tie.1 p.u cos 01 02 1 2
X12 Pr1
T12 1 2
1 d
2ff
2 2 dt
1 d
f
2 dt
2 f dt
Similarly,
P tie.2 2 T21 f2 dt f1 dt
2.32 Power System Operation and Control
Where,
|V2| |V1| Pr1
T21 cos 02 01
Pr2X12 Pr1
Pr1
T21 T a12 T12
Pr2 12
T21 a12 T12
Pr1 ...(2.39)
Where, a12
Pr2
The incremental power balance equation for area 1 can be written as
2H1 d ...(2.40)
PG1 PD1 f1 B1 f1 P tie.1
f0 dt
2H1s
PG1 s PD1 s P tie.1 s f1 s B1
f0
PG1 s PD1 s P tie.1 s
f1 s
2H1s
B1 0
f
1
B1
[ PG1 s PD1 s P tie.1 s]
2H1s
1 0
f B1
Kps1 ...(2.41)
f1 s [ PG1 s PD1 s P tie.1 s]
1 sTps1
Where,
1
Kps1 =
B1
2H1
Tps1 =
f 0B1
Real Power - Frequency Control 2.33
Fig. 2.26
Fig. 2.27
2.34 Power System Operation and Control
1 ...(2.44)
PG2 stat f
R2 stat
From block diagram shown in Fig. 2.18
Kp1
[ PG1 stat PD1 Ptie 1 stat] fstat
1 sTp1
1
B
[ PG1 stat PD1 Ptie 1 stat] fstat
2Hs
1 0
f B
2Hs
PG1 stat PD1 Ptie 1 stat B 0 fstat
f
2H d
B fstat 0 fstat
f dt
d
Put f 0 for area 1, we get,
dt stat
PG1 stat PD1 P tie 1 stat B1 fstat
Ptie 1 stat PG1 stat PD1 B fstat ...(2.45)
Similarly for area 2
PG2 stat PD2 B2 fstat Ptie 2 stat
1 a12
fstat PD2 B2 fstat fstat a12 PD1 a12 B1 fstat
R1 R1
1 a12
fstat B2 a12 B1 a12 PD1 PD2
R2 R1
[ PD2 a12 PD1] ...(2.47)
fstat
B 1 a B 1
2 R2 12 1 R
1
1
f PD1 B1 fstat
R1 stat
1
fstat B1 PD1 ...(2.48)
R1
Substitute equation (2.47) in equation (2.48)
1
PD2 a12 PD1 B1
R1
Ptie 1 stat PD1
B 1 a B 1
2 R2 12 1 R
1
1 1 1
PD2 a12 PD1 B1 PD1 B2 a12 PD1 B1
R1 R2 R1
B 1 a B 1
2 R2 12 1 R1
1 1
PD2 B1 PD1 B2
R1 R2
B 1 a B 1
2 R2 12 1 R
1
1 1
Let 1 B1 and 2 B2
R1 R2
Real Power - Frequency Control 2.37
1 PD2 2 PD1
Ptie 1 stat
2 a12 1
R1 R2 R
B1 B2 B
PD1 PD2
fstat
2
PD2 PD1
Ptie 1 stat Ptie 2 stat
2
Suppose a step load change occurs at area (1)
PD2 0
PD1
fstat Hz
2
PD1
Ptie 1 stat
2
For inter connected power system, the steady state fr equency er r or is r educed by
50% and the change in tie line power is also r educed by 50%
Pc1 Pc2 0
a12 1
R1 R2 R
KP1 KP2 KP
Kp Kp
f1 s 1 [ PD1 s Ptie 1 s]
R 1 sTp 1 sTp
R sRTp Kp Kp
f1 s [ PD1 s Ptie 1 s]
R 1 sTp 1 sTp
KpR
f1 s [ PD1 s Ptie 1 s]
sRTp R Kp
KpR
[ PD2 s Ptie 1 s]
sRTp R Kp
2 T12 KpR
Ptie 1 s [ PD1 s PD2 s 2 Ptie 1 s]
s
sRTp R Kp
4 T12 KpR 2 T12 KpR
Ptie 1 s 1 [ PD1 s PD2 s]
sTpR R Kp s sTpR R Kp
2 T12 KpR
s [ PD1 s PD2 s]
TpRs R Kp
2 T12 Kp
Ptie 1 s [ PD1 s PD2 s]
2 R Kp 4 T12 Kp
Tp s s
TpR Tp
1
We know Kp Hz/p.u MW
B
2 T12 [ PD1 s PD2 s]
Ptie 1 s
1
2 RB 4 T12
TPB s s
TPR BTp
2H
Power system time constant TP sec
Bf0
s2 2 s 2 s 2 2 2
2.40 Power System Operation and Control
Where,
f0
B 1
=
4H R
2 T12 f0
2 =
H
2
Since and are positive the system is stable and damped. The roots of the
characteristics equation are
2 2 4
2
2
s1, 2
2
2
2
s1, 2 j
2
2
jd
Damping factor
d Damping angular frequency
2
d
2
2 f0 T12 f0 1
BR
H 4H
f0
Let, B 0,
4R
Damping mainly depends on Parameter f0 and H are constant.
1. Low valve of R will give strong damping.
2. High valve of R will give weak damping.
3. If R , d . Where d Natural angular frequency.
Real Power - Frequency Control 2.41
!( C84 ;8=4 F8C7 5A4@D4=2H 180B 2>=CA>; >5 CF> 0A40 BHBC4<
The persistent static frequency error is intolerable in the single control area case.
A persistent static error in tie-line power flow called “inadvertent exchange” would
mean that one area would have to support the other as a steady state basis.
The basic principle is good operations of pool must be that each area absorbs
its own load in normal steady state. In two area system, we could conceive of the
2.42 Power System Operation and Control
arrangement that are ‘1’ be responsible for frequency reset and area ‘2’ take care of
the tie line power.
ACE1 f1
ACE2 Ptie2
The ACE’s would be fed via slow integrators or to the respective speed changers.
But this arrangement is not so good. The block diagram of two area LFC with tie
line bias control is shown in Fig. 2.20.
The control strategy is termed as tie line bias control and is based upon the
principle that all operating.
Fig. 2.30 Block diagram of two area load frequency control with tie line bias control
2.44 Power System Operation and Control
The minus sign must be included; since each area should increase its generation
if either its frequency error or its tie line power increment is negative.
When steady state condition are reached, the output signals of all integrating
blocks become constant and their input signals must become zero.
Ptie 1 b1 f1 0
Ptie 2 b2 f2 0 ...(2.56)
f1 f2 0 ...(2.57)
Ptie 1 ...(2.58)
a12 constant
Ptie 2
and f1 f2 0
Depending on whether one (or) all the system has been assigned the job of
maintaining the frequency constant and extent of tie line load required, three methods
are available for LFC of interconnected systems. The equipment used is the same as
in the case of single area systems. In addition a tie line load recorder controller is
also necessary. The load on tie line is measured by a thermal converter which operates
the tie line load recorder controller. A knob on this controller sets the scheduled
amount of power transfer. Whenever the interchange is above or below the set valve,
a set of contacts in the load controller come in to service. These contacts are in
series with load frequency controller circuit. These contacts open and block all those
impulses which would make the tie line lead to further deviate from the set valve.
However all impulses which aid in keeping scheduled interchange are allowed to go
to the governor motor. Generally the same equipment can be used for all the following
types of control by putting the selector switch in the proper position.
equipment consists of the frequency controller only at the larger system and tie line
power controller recorder at the smaller system.
The design of ALFC has to fulfill many objectives like fast response, stability
etc. The optimum linear regulator (OLR) design meets those objectives satisfactorily.
The design of OLR requires the ALFC equations to be expressed in state variable
form. Fig. 2.31 shows the model of LFC for single area system.
Assume KG KT 1
Laplace transform equations are
1 P s 1 F s ...(2.60)
Pv s
1 sTG c R
1 ...(2.61)
PT s Pv s
1 sTT
Kp ...(2.62)
F s [ PT s PD s]
1 sTp
d Pv Pv F u
In the domain form,
dt TG RTG TG
d PT Pv PT
dt TT TT
d F Kp F Kp
PT P
dt Tp TP Tp
X1 Pv
State vector X X2 PT
X3
F
Write the equations in state variable form as
1 1 1
T 0 0
RTG TG
X 1
G X1
1 1
X 2 T 0 X2 0 G 0
X T TT
X3
3 Kp 1 Kp
0
0 Tp Tp T
p
In compact form, X AX BU P
2.48 Power System Operation and Control
Consider two area system, we have two control and disturbance forces.
Let u be the control force.
Let P be the disturbances force vector.
u PC1 P1 PD1
u 1 ; P
P P
u
2 PC2 2 D2
Real Power - Frequency Control 2.49
By using internal controller to the governor mechanism, the control loop must
be characterised by a sufficient degree of stability.
The individual gener ator s of the contr ol ar ea should divide the total load for
optimum economy can be met only by optimal dispatch equation.
The secondary ALFC loop takes over the fine adjustment of the frequency by
using internal control action. The frequency error should be zero. This loop operates
after the primary loop has done its job.
The output of the comparator is given to the computer which generates the raise
/ lower pulses which are sent to the individual speed governing mechanism, to read
just the megawatt generation accordingly.
2.50 Power System Operation and Control
WORKED EXAMPLE
4G0<?;4 2.1
Two synchronous generators operating in parallel. Their capacities are 300 MW and
400 MW. The droop characteristics of their governor are 4% and 5% from no load to
full load. Assuming that the generators are operating at 50 Hz at no load. How would
be a load of 600 MW shared between them. What will be the system frequency at this
load. Assume free governor action. (Dec 2007, May 2008, Dec. 2013)
Fig. 2.34
Solution
No load speed is indicated by OA. For alternator 1, OD is the full load speed
and for alternator 2, OF is the full load speed.
1.04 OD 50
OD 48.076 Hz
Real Power - Frequency Control 2.51
1.05 OF 50
OF 47.619 Hz
x 50 f 50 f
300 50 48.076 1.924
300
x 50 f
1.924
x 7796.258 155.925 f ...(1)
323.922 f 15596.09
f 48.148 Hz ...(3)
288.781 MW
311.219 MW
4G0<?;4 2.2
Two synchronous machines with the following data are operating in parallel to feed
a common load of 300 MW.
Machine 1: Governor speed droop: 4% speed changer set to give 75% rated
load at rated speed.
Machine 2: Governor speed droop: 3% speed changer set to give 50% rated
load at rated speed. The nominal frequency of operation of the set
is 50 Hz.
(i) Determine the load taken by each machine and the frequency of operation.
(ii) What adjustment should be made for the machine to share the loads as in
(i) but with a frequency of 50 Hz? (May 2008)
Solution
Pr1 75% of rated load
75
300
100
225 MW
50
300
100
In Fig. 2.35 no load speed is indicated by OA. For machine 1, OD is the full
load speed and for machine 2, OF is the full load speed.
50 OD
For Machine 1, 0.04
OD
50 OD 0.04 OD
1.04 OD 50
50
OD 48.077 Hz
1.04
50 OF
For Machine 2, 0.03
OF
1.03OF 50
OF 48.54 Hz
From Fig. 2.35 ABC and ADE are similar
CB AB
ED A D
x 50 f 50 f
225 OA OD 50 48.077
50 f
1.923
225
x 50 f
1.925
5850.2 117f ...(1)
From Fig. 2.35 ABH and AFG are similar
BH AR
FG AF
300 X 50 f 50 f
150 50 OF 50 48.544
50 f
1.456
150
300 x 50 f
1.456
5151.1 103.02f ...(2)
2.54 Power System Operation and Control
220.02f 10701.3
f 48.64 Hz
Load shared by Machine 1, x 5850.2 117 48.64
159.32 MW
4G0<?;4 2.3
Fig. 2.36
PD1
PD1, p.u
Pr1
5
PD1 p.u 0.33 p.u.
15
We know that, for two area system, change in tie line power transferred from
area A to B.
1 PD2 PD1 2
Ptie, 1 stat
a12 1 2
1
1 B1
R1
2.56 Power System Operation and Control
3 50
R1 0.1 Hz/MW
100 15
4 50
R2 0.5 Hz/MW
100 4
B1 B2 0
1 1
1 0.667
R1 1.5
1 1
2 0.5
R2 2
Pr1 15
a12 3.75
Pr2 4
0.055 p.u MW
f stat 0.412 Hz
49.588 Hz
Real Power - Frequency Control 2.57
4G0<?;4 2.4
A single area consists of two generating units, rated at 400 MW and 800 MW,
with speed regulation of 4% and 5% on their ratings. The units are operating in
parallel sharing 700 MW. Unit 1 supplied 200 MW and Unit 2 supplies 500 MW
at 1 p.u (50 Hz) frequency. The load is increased by 130 MW.
(i) Assume there is no frequency dependent load. Find the steady state frequency
deviation and the new generation on each unit.
(ii) The load varies 0.84% for every 1% change in frequency. Find the steady state
frequency deviation and the new generation on each unit. (June 2009)
Solution
Assume base MVA 1000
Power factor 1
1000
R1 0.4 0.1 p.u
400
1000
R2 0.05 0.0625 p.u
800
130
Per unit load change PL 0.13 p.u
1000
(i) Per unit steady state frequency deviation
PL
fp.u p.u
1 1
R1 R2
0.13
1 1
0.1 0.0625
0.005 p.u
Steady state fr equency deviation in Hz is
0.005 50 0.25 Hz
50 0.25 49.75 Hz
2.58 Power System Operation and Control
0.05 p.u
fp.u 0.005
P2 p.u
R2 0.0625
0.08 p.u
0.00484 p.u
f in Hz 0.00484 50 0.242
New frequency f f0 f
50 0.242
49.758 Hz
Change in generation for each unit is
f p.u 0.00484
P1 p.u
R1 0.1
0.0484 p.u
Real Power - Frequency Control 2.59
48.4 MW
f p.u 0.00484
P2 p.u
R2 0.0625
0.0774 p.u
P2 MW 0.0774 1000 77.4 MW
4.06 MW
4G0<?;4 2.5
Solution
Total load 1200 kW
Unit I 3% drop
Unit II 5% drop
Let x be the power generation of unit I.
From similar triangle BCD and BEF
CD BD
EF BF
2.60 Power System Operation and Control
Fig. 2.37
x 3h
1000 3
3000 1000h
x
3
1000 333.33 h ...(1)
From similar triangle ADH and A FG
DH AD
FG A F
1200 x 5 h
1000 5
1200 x 1000 200 h
x 200 200 h ...(2)
Equating equations (1) and (2) we get
200 200 h 1000 333.33 h
533.33 h 800
h 1.5
Substitute ‘h’ in equ. (1)
Real Power - Frequency Control 2.61
700 kW
Machine 1 cease to supply any load when the line DH is shifted to point B.
At this point.
Machine 2 will supply load equal to BK.
From A BK and A FG
Fig. 2.38
BK AB
FG AF
105 103
BK 1000
5
2
1000
5
400 kW
2.62 Power System Operation and Control
4G0<?;4 2.6
Two generators rated at 200 MW and 400 MW are operating in parallel. The
governor settings on the machine are such that they have 4% and 5% droops.
Determine the load taken by each machine for a total load of 600 MW and its
system frequency. assume free governor operation. Repeat the problem if both
governors have a droop of 4%. (May 2011, Dec 2014)
Fig. 2.39
Solution
Let X be the load shared by unit - I.
2 Hz
Fig. 2.40
BF AF h
DG AG AG
X h ...(1)
; 4x 200 h
200 4
600 x h
600 4
4x 200 h
x 50 h
4 600 50 h 600 h
2400 800 h
Real Power - Frequency Control 2.65
h3
PG1 150 MW
4G0<?;4 2.7
Fig. 2.41
BC AC
DE A E
x 4h
60 4
2.66 Power System Operation and Control
x 60 15 h ...(1)
Similarly
HCG and HEF
CG HC
EF HE
100 x 3 h
60 3
100 x 60 20 h
x 40 20 h ...(2)
Equating (1) and (2)
60 15 h 40 20 h
4
h
7
substitute ‘h’ in equation (1)
x 60 15 h
4
60 15 51.42 MW
7
Machine 1 delivers 51.42 MW
Machine 2 delivers 100 51.42 48.58 MW
50 y1
60 4
y1 3.33%
Real Power - Frequency Control 2.67
Fig. 2.42
CG HC 3 CE
EF HE HE
50 3 CE
60 HE
50
3 CE 3
60
50 3
CE 3 0.5
60
y1 y2 3.33 100.5
103.83%
4G0<?;4 2.8
Two thermal generating units are operating in parallel at 60 Hz. To supply a total
load of 700 MW unit I with a rated output of 600 MW and 4% speed droop
characteristics and unit II. Which has a rated output of 500 MW and 5% speed
droop. If total load increases to 800 MW determine loading of each unit and the
common frequency change before any supplementary control action occurs. Neglect
losses.
Solution
BCD and BEF
CD BD
EF BF
x 4h
600 4
x 600 150 h ...(1)
x PG1 420 MW
100
0.125 p.u MW
800
3.2 Hz/p.u.MW
4 60
R1 800 3.2 Hz/p.u. MW
100 600
5 60
R2 800
100 500
4.8 Hz/p.u MW
Pp.u
Change in frequency f Hz
1 1
R1 R2
0.125
0.24 Hz
1 1
3.2 4.8
System frequency f0 f
60 0.24
f 59.76 Hz
2.70 Power System Operation and Control
4G0<?;4 2.9
Solution
60
PD 0.2 p.u
300
1 1
KP 62.5
B 0.016
2H 25
TP 0
12.5 sec
Bf 0.016 50
Kp
F s PD s
KI 1 Kp
1 sTp
s R 1 sTG 1 sTt
PD 0.2
For a step response PD s
s s
Real Power - Frequency Control 2.71
62.5 0.2
F s
6 1 62.5 s
1 12.5s
s 2.5 1 0.2s 1 0.5s
f stat Lt s F s
s0
62.5 0.2
Lt
s 0 1 12.5s 15 s 62.5
2.5s 1 0.5s 1 0.2s
12.5 2.5s 1 0.2s 1 0.5s
2.5s 1 12.5s 1 0.2s 1 0.5s 982.5 62.5s
0
Steady state frequency deviation = 0
4G0<?;4 2.10
For the p-f control of a single area system have the following data
Kp 120 Hz/P.u
Tp 10 sec
Tg Tt 0
R 2.5 Hz/p.u MW
KI 0.1
PD 0.1 p.u MW
Compute the time error and the steady state frequency caused by a step disturbance
of magnitude given in the data. Express the error in second and cycles if the system
frequency is 50 Hz.
Solution
Kp PD
F s
R Kp Kp KI
Tp s2 s T
RTp p
120 0.1
2.5 120 120 0.1
10 s2 s
2.5 10
10
2.72 Power System Operation and Control
1.2
F s 2
s 4.9s 1.2
4.9
2
4.9 4 1.2
s
2
1.2
F s
s 0.258 s 4.641
4 B
F s
s 0.258 s 4.641
A 0.274
B 0.274
0.274 0.274
F s
s 0.258 s 4.641
Time error f t dt
0
0.274 e 4.641 t e 0.258 t
0
Real Power - Frequency Control 2.73
e 4.641 t e 0.258 t
0.274
4.641 0.258 0
1 1
0.274
4.641 0.258
Time error 1.002 cycles
1.002
Time error 0.02 sec
50
We lose 0.02 sec
f stat Lt s F s
s0
0.274 0.274
Lt s
s0 s 0.258 s 4.64
0
4G0<?;4 2.11
Solution
Fig. 2.44
2.74 Power System Operation and Control
R KP
PD Kp R t
f t 1e
RTp
R Kp
4 150
0.01 150 4 t
1e 4 18
4 150
0.0389 [1 e 2.138 t]
4G0<?;4 2.12
Two generating stations 1 and 2 have full load capacities of 200 and 100 MW
respectively, at a frequency of 50 Hz. The two stations are interconnected by an
induction motor and synchronous generator set with a full load capacity of 25 MW
as shown in fig. The speed regulation of station 1, station 2 and induction motor
and synchronous generator set are 4%, 3.5% and 2.5% respectively. The loads on
respective busbar are 75 and 50 MW. Find the load taken by the motor generator
set.
Solution
Let a power of A MW flow from station 1 to station 2.
4
% drop in speed at station-1 75 A
200
3.5
% drop in speed at station - 2 50 A
100
The reduction in frequency will result due to the power flow from station - 1
through the interconnector of M-G set.
2.5 2.5A
% drop is speed at M-G set A
25 25
(reduction in frequency at station-1 reduction in frequency at M-G set)
reduction in frequency at station-2)
Real Power - Frequency Control 2.75
4 2.5A 3.5
75 A 50 A
200 25 100
0.02 75 A 0.1A 0.035 50 A
1.5 0.02A 0.1A 1.75 0.03A
0.02A 0.1A 0.03A 175 1.5 0.25
0.15A 0.25
A 1.666 MW
i.e., a power of A 1.666 MW flow from station-1 to station-2.
Total load at station 1 75 A
75 1.666
76.666 MW
Total load at station-2 50 A
50 1.666
48.334 MW
Fig. 2.45
2.76 Power System Operation and Control
4G0<?;4 2.13
A 125 MVA turbo - attemator operate on full load operates at 50 Hz. A load of
50 MW is suddenly reduced on the machine. The steam valves to the turbine
commence to close after 0.5s due to the time lag in the governor system. Assuming
the inertia to be constant, H 6 kW s per kVA of generator capacity. Calculate
the change in frequency that occurs in this time.
Solution
Stored energy
By definition, H
Capacity of the machine
Energy stored at no load 6 125 1000
750 MJ
Excessive energy input to rotating parts in 0.5s 50 0.5 1000 25 MJ
As a result of this, there is a increase in the speed of the motor and hence an
increase in frequency.
2
f0 f
WKE W0KE 0
f
750 25
fnew 750
50 Hz
50.83 Hz
4G0<?;4 2.14
PD 250
B MW/Hz
f 50
PD 250
expressed in p.u.,, B
f 50 500
25
PD in p.u 0.05
500
1 1
B 0.01 0.06
n 2
PD
The static frequency drop f
AFRC
0.05
0.06
0.098 Hz
f 0.098
PG 4.9 10 2 p.u. MW
R 2
24.5 MW
While the sudden increase in load is 25 MW, the increase in generation is 24.5
MW and 0.5 MW is the loss of load due to the droop in frequency.
2.78 Power System Operation and Control
4G0<?;4 2.15
Given a single area with three generating units as shown in Fig. 2.46.
Speed droop R
Unit Rating (MVA)
(Per unit on unit base)
1 100 0.010
2 500 0.015
3 500 0.015
The units are loaded as P1 80 MW, P2 300 MW, P3 400 MW. Assume B 0.
What is the new generation on each unit for a 50 MW load increase? Repeat with
B 1.0 p.u (i.e 1.0 p.u as load base)
Solution
P P
(a) f
3 1 1 1
1 B
Ri
B R1 R2 R3
i1
1,000
R1 0.01 0.1 p.u
100
1000
R2 0.015 0.03 p.u
500
1000
R3 0.015 0.03 p.u
500
50
P 0.05 p.u
1000
0.05
f
1 1 1
0.1 0.03 0.03
f f0 f
49.96 Hz
Changes in unit generation
f
P1 0.00652 p.u 6.52 MW
R1
f
P2 21.739 10 3 p.u
R2
21.74 MW
f
P3 21.739 10 3 p.u
R3
21.74 MW
0.05
f 643.78 10 6
1 1 1
1
0.1 0.03 0.03
49.9614 Hz
f 643.78 10 6
P1 6.4 MW
R1 0.1
f 643.78 10 6
P2 21.459 MW
R2 0.03
f 643.78 10 6
P3 21.459 MW
R3 0.03
New generation
Even if the frequency is kept within tolerances, it does not provide for the
accuracy of synchronous clock. Since clocks measure the integral of the frequency.
Speed changer setting can be adjusted automatically by monitoring the dynamic
frequency changes with changes in load and the synchronous clocks run on time, but
not without error during transient period.
For this purpose a signal from f is fed through an integrator to the speed
changer. The integral controller actuates the load reference point until the frequency
deviation becomes zero. Integral controller gives zero steady state error.
7. Compare the functions of speed governor and speed changer in a speed
governing system of a turbine generator set. (May 2008)
characteristics of units of various types are recognized. Also unnecessary power output
changes should be kept at a minimum in order to reduce wear of control valves.
16. What are the types of automatic load frequency control for interconnected
power system? (Nov/Dec 2012)
1. Flat frequency control
2. Flat tie-line control
3. Frequency bias tie-line control
17. State whether changes in AVR loop will be reflected in LFC loop.
(April/May 2011)
Control actions in the AVR loop affect the magnitude of the generator e.m.f.
‘E’. As the internal e.m.f determines the magnitude of the ideal power, changes in
the AVR loop must be felt in the ALFC loop.
Fig. 2.48
19. What are the assumption made in dynamic response of uncontrolled case?
(AU/May 2004)
1. Neglect the turbine dynamics.
2. The speed changer action is instantaneous.
Real Power - Frequency Control 2.85
20. State the control objective of two area load frequency control?
(Dec/Nov 2004)
1. Under normal operating condition, each control area should have the capacity
to meet its own load from its own spinning generator, plus the scheduled
interchange between the neighbouring area.
2. Under emergency condition the energy can be drawn from the spinning
reserve of all the neighbouring areas immediately due to the sudden loss of
generating unit.
|V01| |V02|
T0 cos 01 02 MW/rad
X
26. Brief the application of secondary ALFC loop in power system network.
(May 2015)
The ALFC loop involves a frequency sensor that senses the frequency of the
busbar and compares it with tie line power frequencies in the signal mixer. The output
of this is an Area control error (ACE) which is sent to the speed changer through
integrator. The speed changer gives the reference speed to the governor. Integral
control is used to reduce the steady state frequency change to zero. The secondary
loop is biased to control the speed which intern controls the frequency. Since
NF
27. Find the open loop gain of an Automatic voltage regulator loop if the static
error does not exceed 1%. (May 2015)
If e0 is less than 1%, K must exceed 99%.
PART - B - QUESTIONS
1. What are the components of speed governor system of an alternator? Derive its
transfer function with an aid of a block diagram.
Machine 1: Governor speed droop: 4% Speed changer set to give 75% rated
load at rated speed.
Machine 2: Governor speed droop: 3% Speed changer set to give 50% rated
load at rated speed. Frequency of operation of the set is 50 Hz.
(i) Determine the load taken by each machine and the frequency of operation.
(ii) What adjustment should be made for the machine to share the loads as in
(i) but with a frequency of 50 Hz?
(16) (April/May 2008)
7. Two 1000 KW alternators operate in parallel. The speed regulation of first
alternator is 100% to 103% from full load to no load and that of other 100%
to 105%. How will the two alternators share a load of 1200 KW and at what
load will one machine cease to supply any portion of the load?
The following are the reactive power supplier (or) absorber in power system.
Synchronous generator
Synchronous generators can generate (or) absorb reactive power. Reactive power
Q is supplied by synchronous generators depending upon the short circuit ratio
(SCR).
1
SCR ; Xs synchronous reactance
Xs
An over excited synchronous machine operating on no load condition
(synchronous condenser), generates reactive power. Under excited synchronous machine
absorbs reactive power. It is undesirable to transmit large amount of reactive power
over transmission lines as this produces excessive voltage drop.
Shunt capacitor
It offers the cheapest means of reactive power supply.
Shunt reactors
It offers the cheapest means of reactive power absorption and these are connected
in the transmission line during light load condition.
Transformers
Transformers always absorb reactive power regardless of their loading.
At no load – Shunt magnetizing reactance effect is predominant.
At full load – Series leakage inductance effect is predominant.
Actual reactance
Per unit reactance, XT
Base value
Actual X
V
I
3.2 Power System Operation and Control
V kV
Actual reactance, X XT XT 1000
I I
kVA
Iph
3 kV
XT
X 3 kV2 1000
kVA
XT
3 |I2| 3 kV2 1000
kVA
3 kVA2 XT
3 kV2 1000
3 kV 2 kVA
Cables
Cables generate more reactive power than transmission lines because the cables
have high capacitance.
Overhead lines
Transmission lines are considered as generating kVAR in their shunt capacitance
and consuming kVAR in their series inductance. The inductive kVAR vary with the
line current, whereas, the capacitive kVAR vary with the system potential.
Consider transmission line be loaded such that load current be ‘I’ amperes and
load voltage ‘V’ volts as shown in Fig. 3.1.
If we assume the transmission line to be lossless, the reactive power absorbed
by the transmission line will be,
QL |I|2 XL
|I|2 L
Due to capacitance of the transmission line, the reactive power generated at the
transmission line
|V|2
QC |V|2 C
XC
Suppose
QL QC
|I2| L |V|2 C
2
V L L
I C C
V
C
L
Zn
I
Case (i): QL QC
|I|2 L |v|2 C
The voltage sags if the voltage at the two ends are maintained constant. The
variations of voltage along the line is as shown in Fig. 3.2
Here the line is loaded below Zn i.e., light load condition. The net effect of
the line will be absorbed reactive power.
QC QL
|V|2 C |I|2 L
The variation of along the line is as shown in Fig. 3.2 and it is observed that
the voltage rises and maintains constant voltage at the ends. Under light load
conditions, the effect of shunt capacitors is predominating and the line will generate
reactive power.
Loads
Loads absorb reactive power, Load change occurs depending on the day, season
and weather conditions. Both real and reactive power of the composite loads vary as
a function of voltage magnitudes. Loads operating at lagging power factor give voltage
drop in the line and is uneconomical. Industrial consumers improve the power factor
using shunt capacitors.
Reactive Power - Voltage Control 3.5
v Vm sin t ...(3.1)
X
where is the power factor angle and equals tan 1
R
q iVL i L
di
dt
[Im sin t ] [L Im cos t ]
I2m L
q sin 2 t
2
The average of over one cycle is zero. During certain part of cycle energy
is supplied by the source to the inductance (an stored in the magnetic field). During
the remaining part of the cycle this energy returned to the source. The amplitude of
this double frequency sine wave of equ (3.3) is I2 L (or) I2 XL. It is known as
reactive power (symbol Q) and has the units of VAR (volt-ampere reactive). Bigger
units for Q are kVAR and MVAR. Thus.
The reactive power does not contribute anything as far as work done or energy
transferred from source to the device is concerned. Yet it contribute to the loading
of the equipment the loading of equipment is proportional to ‘I’ and hence proportional
to apparent power VI. The reactive power is a component of apparent power.
or S P jQ VI
3.6 Power System Operation and Control
Q Im [S] VI sin
In a 3 phase circuit
Real power, P 3Vphase Iphase cos
3 VL IL cos ...(3.8)
3 VL IL sin ...(3.9)
When power factor is 0.5, the current (for the same real power p) becomes
double and losses become 4 times. When power factor is 0.25 the current is four
times and losses are 16 times. In actual practice the power factor is around 0.8 and
losses are about 56% higher then the losses at UPF.
The system has to transmit reactive power due to the fact that most loads operate
at lagging power factor.
The voltage of the generator is proportional to the speed and excitation (flux)
of the generator. The speed being constant, the excitation is used to control generator
voltage. Therefore the voltage control system is also called as excitation control system
or automatic voltage regulator (AVR).
The excitation system provides the necessary filed current to the rotor winding
of the synchronous machine. The amount of excitation depends on the power factor,
speed of the machine and load current. For large currents, lower speeds and lagging
power factors, the excitation requirements is more.
3.3.1 Requirements
An excitation system may be a centralised excitation system or individual
excitation system. In centralised system two or more exciters feed a bus bar to which
the field systems of all alternators of the plant are connected. In individual excitation
system each alternator has its separate exciter. A centralised system is a cheaper
arrangement. However a fault in a centralised excitation system affects all alternators.
As such all modern alternators have individual exciters.
The main requirement of an excitation system are reliability under all conditions of
service, simplicity of control, ease of maintenance, stability and high transient response.
The initial cost of excitation equipment should only be a secondary consideration
in the selection of the system. An outage in the excitation system means the same
loss as the outage of the generator unit. In view of this an excitation system with
better reliability is preferable, even if the initial cost is more.
3.3.2 Classification
The excitation systems can be broadly classified into following types based on
the way DC supply given to the field winding of the alternator.
1. DC excitation system
2. AC excitation system
3. Static excitation system
1. DC excitation system
The DC excitation system consists of DC generators for supplying field current
to the synchronous machine. The system has two exciters – the main exciter and the
pilot exciter. The main exciter is a separately excited DC generator and provides the
field current to the alternator. The pilot exciter is generally a compound would self
3.10 Power System Operation and Control
excited DC generator and supplies the field current to the main exciter. Fig. 3.5 shows
a DC excitation system.
The main and pilot exciter can be either driven by the main shaft (or) separately
driven by a motor. Exciters drawn from the main shaft pressure the unit system of
operation and the excitation is not affected by external disturbances. In view of this
direct driven exciters are preferred.
Exciters for small size turbo alternators are usually directly coupled to the shaft.
For medium and large size turbo alternators, the exciters are coupled to the main
shaft through gears and are usually driven at 1000 rpm.
The voltage rating of the main exciter, for both hydrogenerators and turbo
alternators is around 400 V. The exciter capacity is around 0.5% of alternator capacity.
The main drawbacks of DC excitation system are large time constant and
commutation difficulties. In view of this DC excitation systems have been superseded
by AC excitation systems and static systems.
Reactive Power - Voltage Control 3.11
2. AC Excitation System
An AC excitation system consists of an AC generator and thyristor rectifier
bridge directly connected to the alternator shaft. This approach eliminates the
commutator, the main alternator field collector rings and some other connections. The
main exciter can either be self excited or separately excited. A rotating SCR excitatory
system uses a self excited main excitor. The brush less excitation system is a typical
example of AC excitation system using a separately excited main exciter.
The main alternator field rectifier generally consists of four parallel thyristors
each having a fuse in its circuits so that if the thyristor fails, the fuse opens thereby
allowing the system to continue operation. The thyristor assembly is so rated that
with loss of one thyristor unit, the alternator field requirements are met with sufficient
margin. The exciter rotor provides attachment and support for the rotating thyristor
assembly which overhangs the rotor diameter.
The power supply and rectifier control, included as a part of the rotating portion,
produce the necessary phase controlled triggering signals in response to a DC control
level supplied by the voltage regulator.
reliability. The thyristors are forced cooled with main and reserve fans. The thyristor
bridges are controlled by a set of dual firing circuits operating in parallel.
The base excitation is controlled by an input setting to the thyristor gating
circuits. This control signals is derived from the permanent magnet generator via a
regulated DC supply which also serves the regulator logic circuitry. The regulator
controls excitation by supplying a buck boost control signal which adds algebraically
to the basic setting. The regulator elements also comprise of solid state circuits.
The brushless, excitation system eliminates the use of commutator, collector and
brushes. It has a short time constant and a response time of less than 0.1 second. The
short time constant affords advantage in improved small signal dynamic performance and
facilitates the application of supplementary power system stabilizing signals.
The start up is accomplished using the station battery to provide the initial
alternator field current. The crow bar circuit is to protect the rectifiers and alternator
against the effect of an excessive negative voltage which can occur if alternators loses
synchronism. Protections are provided to shut down the alternator unit in the event
of a short circuit in rectifier circuit fault in step down transformer, excessive current
in crow bar circuit and excessive alternating current being drawn by the excitation circuit.
Reactive Power - Voltage Control 3.15
The static excitation system has a very small response time and provides excellent
dynamic performance. However the circuitry is rather complex and specialised
maintenance is needed.
Silicon controlled rectifiers are ideally suited for a static excitation system because
they have high speed of response, have high power gain and can be easily protected.
Assume that for some reason generator terminal voltage |V| has been decreased.
This results in a increased error voltage e which in turn causes increased values of
VR, ie, Vf and if. The direct axis generator flux increases as a result of increase in
if thus, raising the magnitude of the terminal voltage to the required level.
Comparator
The comparator compares the measured signal |V| against the reference DC signal
Vref. The difference between these two signals produce an error voltage ‘ve’ called
error signal
The error signal e |vref| |v| ...(3.11)
Amplifier
The amplifier amplifies the input error signal depending on the amplification
factor. There are various types of amplifiers used in the excitation system. They are
tuned generator, amplidyne and electronic amplifier.
VR e
VR KA e ...(3.12)
GA KA
VR s KA ...(3.13)
GA
e s 1 sTA
KA 10 to 400
Exciter
The purpose of the exciter is to supply field current to the rotor field of the
synchronous generator.
Let Re be the exciter field resistor
Le be the exciter field inductance
k1
Re
Ge
Le
1 s
R
e
Ke
Ge
1 sTe
K1
where, Ke
Re
Le
Te
Re
Synchronous Generator
Synchronous generator generates three phase AC power at its terminals. It may
be driven by steam turbine at a very high speed or by low speed water turbine
depending on the energy available at that particular place.
The terminal voltage of the generator is maintained constant during its varying
load conditions, with the help of excitation system.
The terminal voltage of the generator equals to difference between induced emf
E and drop across the armature Vdrop
V E Vdrop
Fig. 3.13 Circuit diagram of a synchronous Fig. 3.14 Equivalent circuit for field winding
generator of a synchronous generator
V E (neglect drop)
d ...(3.16)
Vf Rf if Lf if
dt
Emax If XL If Lfa
If
Erms L
2 fa
2 2 E
If Erms
Lfa Lfa
2
Rf E Lf E
d
Vf
Lfa dt
Taking lapalce transform
2
Vf s [R sLf] E s
Lfa f
Lfa kf
Lfs 1 sTd0
2 Rf 1
Rf
Lfa
Kf
2 Rf
The performance of the automatic voltage regulator (AVR) can be carried out
in two ways. They are
(i) Static analysis
(ii) Dynamic Analysis
kA ke kf
Open loop transfer function G s
1 sTA 1 sTe 1 sTd0
At initial condition
G s ...(3.18)
|V|0 |Vref|0
1 G s
3.22 Power System Operation and Control
P ...(3.19)
e0 |Vref|0
100
For a constant input, the transfer function is obtained by setting s 0
Substitute (3.18) in (3.19) we get
G s
e0 |Vref|0 |Vref|0
1 G s
|Vref|0
1
1 G s
Put s0
e0 |Vref|0
1 Vref 0
1K
1 Lt G s p
s0
Position error constant Kp Lt G s
s0
KA Ke Kf
Kp Lt G s Lt
s0 s 0 1 sTA 1 sTe 1 sTd0
Kp KA Ke Kf
Kp K KA Ke Kf
|Vref|0 ...(3.20)
e0
1K
p |Vref|0
e0 |Vref|0 e0 from equation 3.20
100 1K
Reactive Power - Voltage Control 3.23
|Vref|0 P
|Vref|0
1K 100
1 P
1K 100
100
1K
P
100 ...(3.21)
K 1
P
KA Ke Kf
1 sTA 1 sTe 1 sTd0 KA Ke Kf
1
For a step input Vref s
s
Vstat Lt s V s
s0
1
s KA Ke Kf
s
Lt
s 0 1 sTA 1 sTe 1 sTd0 KA Ke Kf
KA Ke Kf
1 KA Ke Kf
K
Vstat
1K
3.24 Power System Operation and Control
KA Ke Kf
Open loop transfer function G s
1 sTA 1 sTe 1 sTd0
G s
Closed transfer function
1 G s H s
G s
V s Vref s
1 G s
Taking inverse laplace transform,
V t L 1 [ V s]
The response depends upon the eigen values or closed loop poles, which are
obtained from the characteristics equation 1 G s 0
Find roots of characteristics equation [Eigen values] s1, s2, s3.
K1 K2 K3
V t L 1
s s1 s s2 s s3
Transient response K1 es1 t K2 es2 t Ks es3 t
Case II: Two roots (Eigen values) are complex conjugate j
The transient response is Ae t sin t For AVR loop to be stable, the
transient components must vanish with time.
Reactive Power - Voltage Control 3.25
All the eigen values are located in left half of s-plane. Then the loop possesses
good tracking ability i.e., the system is stable. For high speed response, the loop
posses eigen values located far away to the left from origin in s-plane. The closer
the eigen value is located to the j axis, the more dominant it becomes.
KA Ke Kf
Open loop transfer function 1 sTC
1 sTA 1 sTe 1 sTd0
Series compensator network will not affect the static loop gain k and thus
maintains the static accuracy.
i.e., K KA Ke Kf
If we tune Tc Te
3.26 Power System Operation and Control
K 1 sTc
Open loop transfer function becomes
1 sTA 1 sTd0 1 sTc
K
G s
1 sTA 1 sTd0
Root loci
Number of zeros, z 0
Number of poles, p 2
1 1
s1 and s2
TA Td0
1 1
Td0 TA
Td0 TA
N2
2q 1
Asymptode angle,
pz
where q 0, 1, , p z 1
Here pz12011
3
1 , 2
2 2
Low loop gain (a) Still results in negative eigen values, the dominant poles
s2 yields sluggish response.
Increasing loop gain (b) results in oscillatory response. The damping of the
oscillatory response. The damping of the oscillatory term will however, not decrease with
increasing gains as was the case in uncompensated system. So the system is stable.
Almost all the transformers are provided with taps on the winding for adjusting
the ratio of transformation. Taps are usually provided on the high voltage winding
to enable a fine control of voltage. Generally the tap changing can be done only
when the transformer is in de-energised state. However in some cases tap changing
is also possible when the transformer is energised and such transformers are known
as tap changing under load (TCUL) transformers. These transformers make it possible
to maintain a constant voltage level on important busses in the system.
Fig. 3.23 shows a line, with impedance R jX having tap changing transformer
at its two ends. Let ts and tr be the fractions of the nominal transformation i.e., tap
3.28 Power System Operation and Control
ratio/nominal ratio e.g. a transformer with nominal ratio 11/33 kV when tapped to
convert 11 kV to 36 kV has ts 36/33 1.09.
V1 and V2 are the nominal voltages at the sending end and receiving end
respectively. When taps are used, the actual sending end and receiving end voltages
would be ts v1 and tr v2. The product ts tr is generally made unity, so that overall
voltage level remains in the same order and the minimum range of taps is used. The
tap ratio ts and tr can be determined as under.
RP XQ ...(3.23)
ts V1 tr V2
tr V2 tr V2
1
Substitute tr in equ.(3.23)
ts
1 V2 ts RP X Q
ts
V1 ts V2
2
2 V2 ts RP XQ
(or) ts
V1 V1 V2
RP XQ V2 ...(3.24)
(or) t2s 1
V1 V2 V1
For complete compensation V1 V2 and ts can be found from Eq.(3.24),
1
tr in Eq.(3.24) all quantities are in per phase.
ts
Reactive Power - Voltage Control 3.29
Static Var Compensator (SVC) are placed in receiving substations and distribution
systems for smooth and stepless variation of compensation of reactive power injected
into line, by shunt capacitors and shunt reactors.
SVC – Static VAR compensator
TCR TSC – Thyristor controlled reactor Thyristor switched capacitor.
Fig. 3.24 Thyristor controlled reactor (TCR) and Thyristor switched capacitor (TSC)
and lower losses. However this scheme is about 15-20% more costly as compared to
TCR FC scheme. In addition to the switched capacitors, a small number of fixed
capacitors, serving as tuned filters are also included in this scheme as shown in Fig. 3.24.
where
BC susceptance of capacitor, BL Susceptance of reator at firing angle
Advantages of SVC
1. Less maintenance
2. Possibility to regulate the phases individually
3. Used in HVDC converter stations (fast control of Q)
4. Mid point voltage will vary with the load.
The function of STATCOM is similar to that of SVC. It can inject lagging (or)
leading vars into the power system as a four quadrant. In four quadrant it can inject
(or) absorb real and reactive powers.
A STATCOM is similar to a synchronous condenser. In a synchronous condenser
the reactive power is generated by controlling the field current. However in a
STATCOM the same result is obtained by using voltage source converter.
Reactive Power - Voltage Control 3.31
2. STATCOM does not add to the short circuit current of the system.
WORKED EXAMPLES
4G0<?;4 3.1
P 20 MW ;
66
Eph kV
3
60 60
Vph kV 103 V
3
3
20
Single phase power, Pph MW 6.66 106 W
3
PX QR
V
V
6
PX 6.66 10 30
Since R 0 ; V
V 60
103
3
5767.73
V 1 5767.33
sin 1 sin 66
E
103
3
8.7
66 kV bus bar must have an advance of 8.7 over the 60 kV bus bar.
PR QX QX
V
V V
Reactive Power - Voltage Control 3.33
66 60
V Eph Vph 103
3 3
3464.1 V
Q 30
3464.1
60 103
3
Q 4 MVAR/ph
From power triangle
Q
tan
P
4
0.6
6.66
4G0<?;4 3.2
A load of 18 j12 MVA is supplied with power from the bus bars of a power
plant via a 3, 110 kV line, 100 km long. The transmission line is represented by
-model and has the following parameters. R 20 , X 40 , C 0.697 F
Vs 115 kV. Find the power consumed from the power plant bus bars.
Solution
S2 18 j12
P2 jQ2 6 j4 MVA
ph 3
Vr 110
103 V 63.5 kV
ph 3
C
QC |Vr|2
2
1
63.52 106 2 f 0.697 10 6
2
0.441 106 0.441 MVAR
3.34 Power System Operation and Control
S P2 jQ2 jQC
6 j4 j0.441
6 j3.559 MVA
|S|2 62 3.5592
PL R 20
|Vr|2 63.52
0.241 MW
|S|2 62 3.5592
QL X 40
|Vr|2 63.52
0.483 MVAR
S S PL j QL
4G0<?;4 3.3
A single circuit 3, 220 kV, line runs at no load, voltage at the receiving end of
the line is 205 kV. Find the sending end voltage, if the line has resistance of
20 reactance of 87 and the susceptance as 5 10 4 . The transmission line
is to be represented by -model.
Fig. 3.29
Solution
205
V2 118.35 kV
3
B
QC |V2|2
2
118.352 5 10 4
3.5 MVAR Fig. 3.30
2
|V1| |V2| | V|
P2 R Q2 X
|V2|
V2
QC X 3.5 87
V1 V2 118.35
V2 118.35
V1 115.78 kV
3.36 Power System Operation and Control
V1L 200.53 kV
4G0<?;4 3.4
A 3 Induction motor delivers 400 HP at an efficiency of 0.9. The p.f being 0.8
lagging. A loaded synchronous motor with the power consumption of 100 kW is
connected in parallel to the induction motor. Calculate the necessary of kVA and
operating power factor of synchronous motor, if the overall power factor is to be
unity.
Solution
Power delivered 400 0.746 kW
Output power
Input power
400 0.746
Input power
0.9
331.55 kW Fig. 3.31
cos 2 0.8
2 36.87
Q2
tan 2
P2
Q2 P2 tan 36.87
Q Q2 248.66 kVAR
Q
tan 2.486
P
68.09
Reactive Power - Voltage Control 3.37
P
kVA supplied by synchronous motor
Power factor
100
0.3731
268.02 kVA
S 2
P Q
2
2
2
100 248.66
S 268.02 kVA
4G0<?;4 3.5
The load at receiving end of a 3 overhead line is 25 MW, 0.8 pf lags at the line
voltage of 33 kV. A synchronous compensator is situated at receiving end and the
voltage at both ends of the lines is maintained at 33 kV. Calculate the MVAR of
compensator. The line has a resistance and reactance of 5/ph, 20 /ph respectively.
(Dec 2009)
Fig. 3.32
Solution
33 33
V2ph 19.05 kV ; V1 ph 19.05 kV
3
3
25
P 106 8.333 MW
3
3.38 Power System Operation and Control
R 5/ph
X 20/ph
Power factor 0.8
Q2 P2 tan 2
cos 2 0.8
2 cos 1 0.8
Fig. 3.33
36.86
Q2 8.333 0.75 6.25 MVAR
2P2 R Q2 QC X P2 X2 [Q2 QC R]2 2P2 RX [Q2 QC] 0
P22 [R2 X2] [Q2 QC]2 R2 X2 2V22 [RP2 Q2 QC X] 0
46.47 24.41
QC 35.44 or 11.03
2
We can consider, QC 11.03 MVAR
4G0<?;4 3.6
Fig. 3.34
415
|V1|ph |V2|ph 239.6 kV
3
239.6 103 V
3.40 Power System Operation and Control
t1 t2 1
P2 200 MW
200 106 W
cos 2 0.8
2 36.86
150 MVAR
1
S2ph P jQ2
3 2
1
[200 j150] MVA
3
|V2|
t1
|V1| |V2| P2 R Q2 X
239.6 103
3 2 6 6
239.6 10 66.67 10 40 50 10 80
239.6 103
1.06
225258
1
t2 0.94
t1
These settings are within the limit. Therefore it would not be necessary to inject
additional VARs at the load end.
Reactive Power - Voltage Control 3.41
4G0<?;4 3.7
Fig. 3.36
Solution
t 1.1
66
|V1| kV 38.105 kV
3
|V1| 66 1
|Vn| 34.64 kV
t 3 1.1
60
P2 ph MW 20 MW
3
Q2 ph P2 ph tan 2
60
0.75 15 MVAR
3
Xp 18 , Xt 0.12
2 2
2 Q2 QC p P2 Xp
|V1| |Vn| |V |
|Vn| n
2 2
15 QC 20 18
38.1052 34.64 18
34.64 34.64
163.717
2
167.717 4 1696.36
QC
2
QC 11 MVAR/ph
[In practical significance]
QC 3 11 33 MVAR
QC 33 MVAR
Reactive Power - Voltage Control 3.43
4G0<?;4 3.8
A three phase oversheet line has resistance and reactance of 5 and 20 ohms
respectively. The load at the receiving end is 30 MW, 0.85 p.f lagging at 33 kV.
Find the voltage at the sending end. What will be the kVAR rating of the
compensating equipment inserted at the receiving end so as to maintain a voltage
of 33 kV at each end? Find also the maximum load that can be transmitted.
(May 2008)
Fig. 3.37
Solution
33
V2 ph 19.05 kV
3
33
V1 ph 19.05 kV
2
30
Pph 106 10 MW
3
cos 2 0.85
Q2 10 tan 31.79
6.197 MVAR
Fig. 3.38
3.44 Power System Operation and Control
2P2 R Q2 QC X P2 X2 P2 X2 [Q2 QC R]2 2P2 RX Q2 QC 0
P22 [R2 X2] [Q2 QC]2 R2 X2 2V22 [P2 R Q2 QC X] 0
R2 X2 [P22 Q22 2Q2 QC Q2C] 2V22 [P2 R Q2 QC X] 0
46.55
2
46.55 4 435.45
QC
2
23.275 10.309
33.584 or 12.966
We can consider 12.966 MVAR
Reactive Power - Voltage Control 3.45
Maximum load that can be transmitted Total reactive power for three phase
3 12,966
QC 38,898 MVAR
4G0<?;4 3.9
Solution
Fig. 3.39
132
|V1|ph |V2|ph 76.210 kV 76210 V
3
t1 t2 1
Fig. 3.40
3.46 Power System Operation and Control
48.432 MVAR
76210
1.00000131
76209.19
t1 1.00000131
1 1
t2 0.9999
t1 1.00000131
t2 0.9999
4G0<?;4 3.10
A three winding transformer is rated at 132/33/11 kV. The MVA ratings of the
three windings are 75,50 and 25 MVA respectively. The reactance of primary is
0.12 p.u on 132 kV, 75 MVA base. A static var compensating equipment is connected
to the tertiary winding. Neglecting losses find the tap settings to give satisfactory
operation under the following two conditions (a) Load of 60 MW, 50 MVar with
primary and secondary voltage limits of 125 and 33 kV. The static var system is
disconnected. (b) No load condition, SVS absorbing 25 MVAR and primary and
secondary voltage limits 140 kV and 33 kV.
Solution
Xp is given in p.u, Base kV = 132 kV
50
Q 0.667 p.u
75
XPQ
V1 Vn IXp sin Vn
Vn
0.12 0.667
0.947 Vn
Vn
140
V1 1.06 p.u
132
25
Q 0.333 p.u
75
0.12 0.333
1.06 Vn
Vn
112.6
Transformation ratio under load condition
33
3.413
134.77
Transformation ratio under no load condition
33
4.084
The actual ratio can be taken as mean of the above two values i.e., 3.748 varying
by 0.336 (or) 3.748 8.96%. Hence tap setting required is 8.96%.
3.48 Power System Operation and Control
4G0<?;4 3.11
145
Sending end voltage, Vs V
3
132
Receiving end voltage, Vr V
3
145 132
Ir 25 j90
3
3
B 93.4 74.47
Pr Vr Ir cos r 50 MW given
1,200.92 106 3755.98 106 1.50 Q2r 106 2500.7 106 179.98 Qr
Qr 44.87 MVAR
Qr Vr Ir sin r 44.87
pr Vr Ir cos r 50
tan r 0.8974
r 41.9
4G0<?;4 3.12
Solution
500 746 10 3
The power delivered, P
0.91
409.9 kW
409.9 0.855
Q 350.53 kVAR
350.5
tan 3.505
100
82.31
100
kVA of synchronous motor
0.274
4G0<?;4 3.13
Three supply points A, B and C are connected to a common bus bar M. Supply
point A is maintained at a nominal 275 kV and is connected to M through a
275/132 kV transformer (0.1 p.u reactance) and a 132 kV line of reactance 50 .
Supply point B is nominally at 132 kV line of 50 reactance. Supply point C is
nominally at 275 kV and is connected to M by a 275/132 kV transformer (0.1 p.u
reactance) and a 132 kV line of 50 reactance. If at a particular system load the
line voltage at M falls below it nominal value by 5 kV. Calculate the magnitude
of the reactive voltage ampere injection required at M to re-establish the original
voltage. The p.u values are expressed on a 500 MVA and resistance may be neglected
throughout.
Solution
Base MVA 500
Base kV 132
Reactive Power - Voltage Control 3.51
500
Hence fault MVA at M 1000 MVA
0.5
1000 106
Fault current 4.38 kA
3 132 103
Qm
three phase short circuit current
3 Vm
where Qm and Vm are 3-phase line values
Qm
3 4.38 7.6 MVAR/kVA
Vm
Natural voltage drop at M 5 kV
Therefore the reactive power to be injected to offset this drop 5 7.6 38 MVAR
4G0<?;4 3.14
A 220 kV line has tap changing transformer at both ends. The transformer at the
sending end has nominal ratio 11/220 kV and that at the receiving end 220/11 kV.
The line impedance is 20 j60 and the load at the receiving end is 100 MVA,
0.8 p.f lagging. If the product of the two off-nominal top setting is 1, find the tap
settings to give 11 kV at load bus.
Solution
100 0.8 106
P 26.67 106 W
3
4G0<?;4 3.15
A 220 kV bus supplies a load of 0.8 j0.2 p.u through a short line and a
transformer. The p.u reactance of line and transformer are 0.2 and 0.05 p.u. If
the voltage at load terminals is 1 p.u, find voltage and power factor at 220 kV
bus. Base MVA 100, Base kV 220.
Solution
V 1 0, X 0.25
P2 Q2 0.82 0.22
|I| 0.8246 p.u
V2 1
I 0.8246
14 p.u
10.78 p.u
1.069
0.980 lagging
4G0<?;4 3.16
In the system of Example 3.15, shunt capacitors are provided at the receiving end
to supply the total reactive power requirement of 0.2 p.u. Find the voltage and
power factor at 220 kV bus.
Solution
V 1 0, X 0.25
I 0.8 0 p.u
1.02 11.31
p.u 224.4 kV
4G0<?;4 3.17
Find the constants of nominal circuit for the uncompensated and compensated
perphase
line of A 350 km long line has a total series impedance of 180 75
3
and a total shunt admittance to neutral perphase of 1 10 90
Siemens (a)
Find ABCD parameter of the line (b) The line is provided with 60% series
compensation. Find ABCD parameters of the compensated line.
Solution
For the uncompensated line
B Z 180 75
B 83.71 56.18
ZY 1 10 3 90
AD1 ]
1 [83.71 56.18 0.965
1.38
2 2
1.38
A D 0.965
It is seen that both for the uncompensated and compensated lines, the constants
of equivalent and nominal circuit are nearly equal.
Reactive Power - Voltage Control 3.55
4. Show that the shunt compensation improves critical voltage as well as the
power factor. (May 2015)
Once the voltage is improved the power factor will also be improved.
E V2 QX
P
R R R
Fig. 3.43
Fig. 3.44
21. Distinguish between rotor angle stability and short term voltage stability.
(May 2015)
Fig. 3.45
Reactive Power - Voltage Control 3.61
PART - B QUESTIONS
10. Draw the circuit diagram for a typical excitation system and derive the transfer
function model and draw the block diagram. Discuss the stability aspects of the
AVR. (16) (April/May 2008) (April/May 2008)
11. Discuss the static and dynamic analysis of AVR. (Dec 2009)
12. Explain the methods of voltage control in a transmission system.
19. The load at receiving end of a 3 overhead line is 225 MW, 0.8 pf lag at the
line voltage of 33 kV. A synchronous compensator is situated at sending end
and the voltage at both ends of the line is maintained at 33 kV. Calculate the
MVAR of compensator. The line has a resistance and reactance of
5 /ph, 20 /ph, r espectively. (16) (Nov/Dec 2009) (May, 2014)
20. Discuss at length, the effect of tr ansfor mer on load tap changing on voltage
stability. (16) (May 2015)
21. A thr ee phase over head line has r esistance and r eactance of 5 and 20 ohms
r espectively. The load at the r eceiving end is 30 MW, 0.85 power factor lagging
at 33 kV. Find the voltage at the sending end. What will be the kVAR r ating
of the compensating equipment inser ted at the r eceiving end so as to maintain
a voltage of 33 kV at each end? Find also the maximum load that can be
tr ansmitted. (16) (April/May 2008)
UNIT - 4
# 42>=><82 38B?0C27
A power system has several power plants. Each power plant has several
generating units. At any point of time, the total load in the system is met by the
generating units in different power plants. Economic dispatch control determines the
power output of each power plant, and power output of each generating unit within
a power plant, which will minimize the overall cost of fuel needed to serve the system
load.
The economic dispatch problem involves the solution of two different problems
i.e., unit commitment and online dispatch.
Unit commitment
Optimum allocation of generators at each generating station at various station
load levels.,
q1
n ...(4.2)
fp eq Gpq fq Bpq ep fq Gpq eq Bpq
Reactive power, QP
q1
Where, ep and fp are the real and imaginary components of voltage at the pth
bus and Gpq and Bpq are the transmission line conductancy and susceptances
betweenthe pth and qth buses.
i.e., Vp ep jfp
Ypq Gpq j Bpq
p min p p max
Unit Commitment and Economic Dispatch 4.3
Most of the system would not operate satisfactorily and require stabilizer.
Where |Vp| Voltage and
p Load angle
Where,
Cp max Maximum loading capacity of the pth line.
Let,
FT F1 F2 FN
FT Total Fuel cost
F1 Fuel cost for generator 1
F2 Fuel cost for generator 2
Fn Fuel cost for generator ‘n’
N
Equality constraint PGi PD 0
i1
The necessary condition for the existence of a minimum cost operating condition
is that the incremental cost rates of all the units be equal to some undetermined value
.
d Fi (N-equations)
d PGi
N
(1-constraints)
Power balance equation is PGi PD
i1
There are two inequalities that must be satisfied for each of the units i.e., the
power output of each unit must be greater than or equal to the minimum power
permitted and must also be less than (or) equal to the maximum power permitted on
that particular unit.
dFi
for PGi, min PGi PGi, max
dPGi
Unit Commitment and Economic Dispatch 4.5
dFi
for PGi PGi max
dPGi
dFi
for PGi PGi min
dPGi
Net saving of cost:
Net saving Ft F1 F2
Where,
F1 Increase in cost for unit 1 (or) the input to source 1 will be
increased by a small amount.
F2 Decrease in cost for unit 2 or the input to source 2 will be
decreased by a small amount.
Fi can be calculated using the following formula.
dFi
Fi dP
dPGi Gi
It specifies the input energy rate, Fi PGi Mkcal/hr or cost of fuel used per
hour Ci PGi Rs/hr as a function of the generator power output PGi.
The curve drawn between the output power and incremental fuel cost is called
incremental cost curve.
Let the cost of the fuel be K Rs/Mkcal. Then the input fuel cost Ci PGi is
Ci ...(4.4)
Hi PGi bi ai PGi
PGi
Because the initial portion of curve decreases, reaches minimum point and then
increases.
Unit Commitment and Economic Dispatch 4.7
Ci
PGi bi ai PGi
PGi
Ci bi PGi ai P2Gi (Mkcal/hr)
The incremental cost curve for a thermal power plant is shown in Fig. 4.3.
The input output curve and incremental cost curve for a hydro power plant is
shown in Fig. 4.4.
The incremental fuel cost of all the generating units must be the same. The
common value of incremental fuel cost is called the system incremental cost. In
some cases, some of the units operate at their upper (or) lower limits, the IC of all
other machines which have not hit their limit must be equal to . is called as
system (or) incremental cost of received power.
The fuel cost curve and the incremental cost curve may have a number of
discontinuities as shown in Fig. 4.5(a).
The discontinuities occur when the output power has to be extended by using
additional boilers, steam condensers or other equipments. Discontinuities also appear
4.10 Power System Operation and Control
if the cost represents the operation of an entire power station, so that cost has
discontinuities on paralleling of generators. We can write real power generation as,
The generated real power PGi accounts for the major influence on Ci. The
individual real power generations are raised by increasing the prime mover torques
and this requires an increased expenditure of fuel. The reactive power generations
QGi do not have any measurable influence on Ci because they are controlled by varying
the field current.
For a plant with N generators.
The cost function or objective function,
N ...(4.7)
C Ci PGi C1 PG1 C2 PG2 CN PGN Rs/hr
i1
Where
Ci Fuel cost to unit i, Rs/hr
C Total fuel cost, Rs/hr.
(ii) Constraints
A set of real power generation variables PGi must be selected that will minimize
the cost function.
Equality constraint
Let PD Tot be the total system real power demand.
Let PD be the real power demand that must be supplied from the generator
units under control.
PD PD Tot PG base
consider, the real power balance require that the controlled generation variables
PGi obey the constraint equation.
N ...(4.8)
PD PG1 PG2 PGN PGi
i1
Where,
PGi Real power generation of unit i, MW
4.12 Power System Operation and Control
PD Total power received by the plant bus and transferred to the load.
Since our system is a compact one, the losses can be neglected in the
transmission line. Equation (4.8) can be rewrite as follows,
N
H PG1, PG2 PGN PD PGi 0
i1
Inequality constraints
Since each generator must not be operated above its rating or below some
minimum value.
PGi, min PGi PGi, max for i 1, 2, 3 N
Where,
C Operating cost
i Number of generators on the bus
N
subject to H PG1, PG2, PGN PD PGi
i1
Lagrangian function C C H
N N ...(4.9)
PGi
LC Ci PGi PD
i1 i1
For minimum objective function, differentiate equation (4.9) with respect to
PGi and equate to zero.
C
0, i 1, 2, N
PGi
C L Ci
00; i 1, 2, N
PGi PGi PGi
Ci
; i 1, 2, N
PGi
C1 C2 CN ...(4.10)
For N units,
PG1 PG2 PGN
Where,
Ci
Incremental cost of the unit i
PGi
The optimal loading of generators corresponds to the equal incremental cost of
all the generators.
Equation (4.10) is called as coordination equation neglecting losses. The
incremental cost curve is shown in Fig. 4.6.
4.14 Power System Operation and Control
Where i, i, i are adjusted to give best possible curve fit. The graphical
representation of economic dispatch of ‘N’ units is shown in Fig. 4.8.
N
Power demand PD PGi
i1
Unit Commitment and Economic Dispatch 4.15
Because of above specified limits, some units will be unable to operate at the
same incremental fuel cost as other units. Therefore, if some units reach their limit
values the economic dispatch strategy calls for the remaining units to operate so as
to satisfy the equal incremental cost criterion.
In a system, where a number of stations are operating in parallel and are inter
connected, transmission loss must be taken into consideration in economic studies.
Incremental transmission loss characteristics and incremental plant characteristics must
be considered together to determine the optimum system economy.
N
Minimize C Ci PGi ; i 1, 2, N
i1
PDi PL PGi
i1 i1
N N ...(4.9)
PDi PL PGi 0
i1 i1
C
0
PGi
C Ci PL
0
PGi PGi PGi
Ci PL
1
PGi PGi
ICi [1 ITLi]
Where,
Ci (IC-Incremental fuel cost)
ICi
PGi
ICi ...(4.11)
Li ICi
1 ITLi
Where,
Li Penalty factor of plants
1
Penalty factor i
1 ITLi
The N optimum dispatch equations together with the power balance equation
for finding N 1 unknowns PG1, PG2, PGN plus .
From the expression of the penalty factor, it may be noted that for optimum
operation, plants causing lower incremental transmission losses may be allowed to
operate with higher incremental cost.
Unit Commitment and Economic Dispatch 4.17
N
Equating constraints PGi PD 0
i1
Inequality constraints: Since each generator most not be operated above its rating
or below some minimum value, PGi min PGi PGi max for i 1, 2, , N.
If a particular generator loading PGi reaches the limit PGi, max or PGi, min its
loading from now on is held fixed at this value and the balance load is then shared
between the remaining generators on equal incremental cost basis. The real generation
must not be set so as to cause overloads on certain lines.
Case (i): Operating limits for power generation are not specified
Step 1: Assign initial trial value of ‘’(or) Calculate ‘’ using
N
bi
PD 2ai
i1
N
1
2ai
i1
(i.e.,) PGI i i i 2
N
Step 3: Compute PGi
i1
N
Step 4: Check the power balance equation PGi PD
i1
bi
The economic schedules, PGi , i 1, 2, N
2ai
Step 3: If the computed PGi satisfy the operating limits.
PGi, min PGi PGi, max i 1, 2, N then the optimum solution is obtained.
Otherwise, go to the next step.
Step 4: If PGi violates the operating limits then fix the generation at the respective limit.
new bi
PGi
2ai
dC
ICi 2ai PGi bi
dPGi
N N
PL PGi Bij PGj
i1 j1
N
PL
PGi
2 Bij PGj
j1
ICi [1 ITLi]
N
2ai PGi bi 1 2Bij PGj
j1
N
2ai PGi bi 2Bii PGi 2Bij PGj
j1
ji
N
PGi [2ai 2 bii] bi 2Bij PGj
j1
ji
N
bi ...(4.12)
1
2 Bij PGj
j1
ji
PGi
2ai
2Bii
4.22 Power System Operation and Control
N
Power balance equation PD PL PGi 0
i1
N
bi
PD 2ai
i1
Compute 0 using N
1
2ai
i1
N
bi
1
2 Bij PGj
j1
j1
PGi
2ai
2Bii
Where,
C ai P2Gi bi PGi Ci
Step 4: Check if any PGi is beyond (or) below the inequality constraint.
The total load in any power system varies from instant to instant. During certain
time of the day the load is at peak value, during certain other times it is very low and
during certain other times it is at some intermediate value. The load division between the
generating units in operation is determined from the principle of equal incremental costs.
The topic of unit commitment deals with specifying the units which should be operated
for a given load i.e., which units should be committed to supply a given load.
It is possible that it may be economical to decommit certain units when load is
low. To commit a unit means to bring the boiler to the required temperature, bring the
turbine and generator to synchronous speed and synchronise the generator to the system.
4.9.1 Need for unit commitment
1. Enough units will be committed to supply the system load.
2. To reduce the loss or fuel cost.
3. By running the most economic unit, the load can be supplied by that unit
operating closer to its best efficiency.
Unit Commitment and Economic Dispatch 4.25
unequal temperature distribution in turbine casing. This also involves energy consumption.
All these costs are termed as transition cost.
When the load is very low, the unit with the lowest heat rate supplies the entire
load. As he load increases the units having heat rates in ascending order are
successively added to the system.
The heat rate curve of unit B shows the input in kcal/MWhr hour for different
values of outputs in MW for the unit B. The combined heat rate curve of units B
and D shows the total input in k-cal per MW hour for different values of outputs in
MW. If the two units B and D are in operation and share the load as per the principle
of equal incremental costs. The combined heat rate of units B, D and A shows the
total input for all these three units in operation at the same incremental cost and
sharing the load and so on. The loads at which the units are to be added are given
by the points of intersection as shown in Fig. 4.11.
Let us consider a load of 600 MW and four generating units each of 210 MW
capacity. If all the four units are to be operated, the operating cost will be minimum
when the loads are allocated as per the equal incremental cost criterion. However it
is possible that only if unit 1,2 and 3 are operated and load allocated to these three
units as per equal incremental cost criterion, the operating cost is lesser than that
when all the four are operated.
One possible method for determining optimal unit commitment is to try all
possible combinations of units for supplying the load. In the above case of four units
each of 210 MW to meet 600 MW load demand, the possibilities are
1. All units 1 to 4 operated.
2. Units 1, 2, 3 operated and unit 4 shut down
3. Units 1, 3, 4 operated and unit 2 shut down
4. Units 1, 2, 4 operated and unit 3 shut down
5. Units 2, 3, 4 operated and unit 1 shut down
If operating costs is calculated for all the above five combinations, the scheme
giving the minimum operating cost can be implemented. When the number of units
is very large, this simple method becomes very lengthy and a better technique is
necessary.
For a system having a large number of units. it is preferable to use a method
which can be used in a digital computer. Dynamic programming is one such technique.
The problem of unit commitment is also governed by the consideration of
auxiliary power consumption, reserve requirement, starting losses, stability
consideration of voltage instability. Many of these considerations cannot be expressed
in economic terms. The technical aspects of the problem of unit commitment are as
important as the economic aspects. As such, the decision on plant capacity to be
operated and unit commitment must be based as both technical and economic aspects.
The algorithm for unit commitment as per priority list method can be summerised
as under:
1. When the load is decreasing, examine whether shutting down a generating
unit would still leave enough generation to supply the load plus axillary
power consumption plus spinning reserve requirement. If this condition is
not satisfied, continue running the already operating units and go to step 2.
2. Find out the time when the unit being shut down will be needed again. Let
this time be T.
Unit Commitment and Economic Dispatch 4.29
3. If T is less than minimum shut down time, keep the unit on and go to step
5. If not go to step 4.
4. Calculate and compare the costs. Include shut down and start-up costs. If
the total cost for that unit shut and operating are the same and there is not
substantial saving keep that unit on. If sufficient saving exists, shut down
the unit.
5. Repeat the above sequence for the next generation unit on priority list. If
this unit requires to be shut down, go to next and continue.
Fig. 4.12
4.30 Power System Operation and Control
Table 4.1
Unit x1 x2 x3 x4 x5 x6 x7
1 ON ON ON OFF ON OFF OFF
2 ON ON OFF ON OFF ON OFF
3 ON OFF ON ON OFF OFF ON
It has to be remembered that all the above combinations may not be feasible
for a certain time interval. This is evidently, due to the simple fact that a combination
of total capacity less than system load is not feasible and can be disregarded for that
time interval.
The cost Cn i denotes minimum operating cost of nth combination for ith
interval. Then Cm i 1 will denote minimum operating cost of Xm i 1 and so on.
The operating cost is not the only cost which has to be considered in optimising
unit commitment. Some cost is incurred in changing the state. This cost is usually
referred to as startup or shut down cost. Another terminology is transition cost. Let
this cost be denoted by symbol ‘S’. Then
Since the number of generating units in any system is pretty large (may be 20
or even more) the combination of units can be 220 1 which is a very large number.
Combining it with the number of time intervals (say N) in which the day is divided
makes the solution all the more complex. Therefore the unit commitment problem is
solved for each time interval separately by a subprogram and then the results for all
these N intervals are combined.
Unit Commitment and Economic Dispatch 4.31
The total cost tnm i for any time interval can be written as
where Cn i is the minimum operating cost of nth combination for ith interval and
Snm i is the cost of transition from combination xm i 1 to combination xn i.
[Least total cost to reach state i, n operating cost for state i, n transition
cost from state i 1, m to state i, n]
...(4.13)
The operating cost for any stage needs the method of economic dispatch. This
is evidently due to the fact that for any give combination of units, the operating cost
is minimum if all the units in this combination are operating at equal incremental
cost.
Two other variables enter the strategy for unit commitment by forward dynamic
programming. This is because a number of possible combinations exist for every state.
Let this be denoted by K.
Another variable is the number of paths (or) strategies to save at every step.
Let this variable be denoted by L. Fig. 4.13 shows a simple flow chart for unit
commitment through forward dynamic programming.
4.32 Power System Operation and Control
Fig 4.13 Flow chart for unit commitment using forward dynamic programming.
Unit Commitment and Economic Dispatch 4.33
WORKED EXAMPLES
4G0<?;4 4.1
A power plant consists of two 200 MW units, whose input cost data given by
F1 0.004 P21 2.OP1 80 Rs/hr
F2 0.006P22 1.5P2 100 Rs/hr.
For the total load of 250 MW, what should be the division of load between two
units for most economic operation. (Dec 2007, Dec 2012)
Solution
dF1
1 2 0.004P1 2
dP1
0.008P1 2
dF2
2 2 0.006P2 1.5
dP2
0.012P2 1.5
P1 P2 250 ...(2)
0.02 P1 2.5
P1 125 MW
P2 250 P1
250 125
P2 125 MW
4G0<?;4 4.2
The fuel cost functions for three thermal plants in $/h are given by
F1 0.004 P2g1 5.3 Pg1 500
F2 0.006 Pg2 5.5 Pg2 400
F3 0.009 P2g3 5.8 Pg3 200
Where Pg1, Pg2 and Pg3 are in MW
Find the optimal dispatch and the total cost when the total load is 925 MW with
the following generator limits.
100 MW Pg1 450 MW
100 MW Pg2 350 MW
100 MW Pg3 225 MW
(May 2008) (June 2009)
Solution
(i) Find initial value of
Unit Commitment and Economic Dispatch 4.35
N
bi
PD 2ai
i1
N
1
2ai
i1
dF1 Pg1
1 2 0.004 Pg1 5.3
dPg1
dF2 Pg2
2 2 0.006 Pg2 5.5
dPg2
dF3 Pg3
3 2 0.009 Pg3 5.8
dPg3
5.3
Pg1 459.21 MW
2 0.004
5.5
Pg2 289.47 MW
2 0.006
5.8
Pg3 176.31 MW
2 0.009
N
The solution satisfies PGi 925 MW
i1
But generation schedules of unit 1 is not within the limit. Set unit 1 to its
maximum output.
4.36 Power System Operation and Control
8.9
PD new PD Pg1 925 450 475 MW
Now shar e the load
Pg2 Pg3 475 MW between units 2 and 3 using equal incr ements cost r ule.
2 3
Pg2 295 MW
Sub in equation (2), we get
Pg3 475 Pg2 475 295 180 MW
Pg2 295 MW
Pg3 180 MW
1535.6
Total cost F1 F2 F3
4G0<?;4 4.3
Solution
0.0015 0.0006 B11 B12
Bmn
0.0006 0.0024 B21 B22
dPL
ITL2 2 B12 PG1 2 B22 PG2
dPG2
For 20
0.08 PG1 20
20
1 0.003 PG1 0.0012 PG2
0.02
PG2 P 0.833 PG1
0.024 G1
0.09 PG1 16
20
1 0.0012 PG1 0.0048 PG2
1.628 MW
For 25
0.08 PG1 20
25
1 0.003 PG1 0.0012 PG2
0.09 PG1 16
25
1 0.0012 PG1 0.0048 PG2
PG1 42.647 MW
6.44
PG2 53.6 MW
0.12
6.894
Change in transmission loss 6.894 1.628
Change in transmission loss 5.266 MW
4.40 Power System Operation and Control
4G0<?;4 4.4
Obtain the priority list of unit commitment using full load average production cost
for the given data
Heat rate for unit 1, H1 510 7.2 PG1 0.0014 P2G1 MW/hr
Heat rate for unit 2, H2 310 7.85 PG2 0.00194 P2G2 MW/hr
Heat rate for unit 3, H3 78 7.97 PG3 0.00482 P2G3 MW/hr
Solution
Step 1: Full load average production cost (FLAPC)
K1 H1 PG1 max
FLAPC1
PG1 max
4G0<?;4 4.5
Solution
IC1 0.1 P1 17 ITL1 0.05
IC2 0.12 P2 14.4 ITL2 0.1
IC3 0.16 P3 9 ITL3 0.15
PD 100
4.42 Power System Operation and Control
17.89 16 10.59
100
0.105 0.133 0.19
1 1 1
0.105 0.133 0.19
446.418
20.0134
22.306
new b1 20.0134 17.89
P1 20.22 MW
2a1 0.105
new b2 20.0134 16
P2 30.18 MW
2a2 0.133
4G0<?;4 4.6
25 PG 100
PD 180 MW
2
bi
PD 2ai 180
40 30
i1 0.4 0.5
75.56
2 1 1
1
2ai
0.4 0.5
i1
b1 75.56 40
PG1 88.9 MW
2a1 0.4
b2 75.56 30
PG2 91.1MW
2a2 0.5
PG1, PG2 are within the limits cost of generation for unit 1.
F1 5256.64 Rs/hr
4957.80 Rs/hr
180
If the load on each unit is 90 MW, the cost of generation will be
2
5340 Rs/hr
4875 Rs/hr
F1 F2 10,215 Rs/hr
4G0<?;4 4.7
There are 3 thermal generating units which can be committed to take the system
load of 800 MW. The fuel cost data and generation operating limit data are given
below. Obtain an optimum unit commitment using brute force enumeration
technique.
F1 0.006 P2G1 7PG1 600
F2 0.01 P2G2 8PG2 400
F3 0.008 P2G3 6PG3 500 operating limits are
100 PG1 400 MW
50 PG2 300 MW
150 PG3 500 MW
Power demand 800 MW.
Solution
Brute force technique Number of combinations 23 1 8 1 7
Sl.No. Unit I Unit II Unit III PG1 PG2 PG3 Max min Solution cost (Rs.)
1. Off Off Off – – Infeasible –
PD 800 MW
bi 8 6
PD 800
2ai 2 0.01 2 0.008
1 1 1
2ai 2 0.01 2 0.008
14
b2 14 8
PG2 300 MW
2a2 2 0.01
b3 14 6
PG3 500 MW
2a3 2 0.008
F2 a2 P2G2 b2 PG2 C2
F3 a3 P2G3 b3 PG3 C3
3700 5500
Rs.9200
Consider 6th case (feasible): Units 1 and 3 are operating
bi 7 6
PD 800
2ai 2 0.006 2 0.008
1 1 1
2ai 2 0.006 2 0.008
12.057
b1 12.057 7
PG1
2a1 2 0.006
F1 a1P2G1 b1PG1 C1
F3 a3 P2G3 b3 PG3 C3
11.02
b1 11.02 7
PG1 335 MW
2a1 2 0.006
b2 11.02 8
PG2 151 MW
2b2 2 0.01
b3 11.02 6
PG3 314 MW
2b3 2 0.008
FT F1 F2 F3
FT Rs.8627.04
4.48 Power System Operation and Control
Total fuel cost for the 6th case is less than that of the other cases of feasible
solution.
when the system load level is 800 MW, it is preferable to keep unit 1 and
3 running.
4G0<?;4 4.8
A plant has two generators supplying the plant bus and neither is to operate below
20 MW (or) above 135 MW. Incremental costs with PG1 and PG2 in MW are:
dF1
0.14 PG1 21 Rs/MWhr
dPG1
dF2
0.225 PG2 16.5 Rs/MWhr
dPG2
For economic dispatch, find the plant when the demand equals (a) 45 MW
(b) 125 MW (c) 250 MW.
Solution
(a) PD 45 MW
N
bi
PD 2ai 45
21
16.5
i1 0.14 0.225
23.15
N 1 1
1 0.14 0.225
2ai
i1
b1 23.15 21
PG1 15.41 MW
2a1 0.14
PG1 PG min
1 0.14PG1 21
23.8
Optimality condition is satisfied therefore PG1 20 MW
PG2 PD PG1 45 20 25 MW
Unit Commitment and Economic Dispatch 4.49
PG2 25 MW
(b) PD 125 MW
21 16.5
125
0.14 0.225
1 1
0.14 0.225
30.061
b1 30.06 21
PG1
2a1 0.14
64.726 MW
b2 30.0616 16.5
PG2
2a2 0.225
60.275 MW
PG1 64.726 MW
PG2 60.274 MW
(c) PD 250 MW
250
21
16.5
0.14 0.225
40.849
1 1
0.14 0.225
b1 40.849 21
PG1 141.78
2a1 0.14
b2 40.849 16.5
PG2 108.22
2a2 0.225
4.50 Power System Operation and Control
1 0.14 PG1 21
39.9
The optimality condition satisfied
Therefore PG1 135 MW
PG2 PD PG1 250 135 115 MW
The optimum schedule is
PG1 135 MW
PG2 115 MW
4G0<?;4 4.9
PG2 120
Unit Commitment and Economic Dispatch 4.51
377.5 Rs./hr
125
dF2
Increase in cost for unit 2 dP dPG2
120
G2
125
40 0.3 PG2 dPG2
120
125
P2G2
40 PG2 0.3
2 120
383.75 Rs/hr
Total yearly saving 6.25 8760
Rs.54750
4.52 Power System Operation and Control
4G0<?;4 4.10
H1 PG1
FLAPC1 K1
PG1
PG1 PG1, max
Unit commitment
All the three units would be held on until the load reached 900 MW. Units 1
and 3 would be held on until the load reached 500 MW, then unit 1 would be dropped.
4G0<?;4 4.11
Solution
dF1
1 25 2 0.1PG1
dPG1
dF2
2 32 2 0.1 PG2
dPG2
4.54 Power System Operation and Control
25 0.2PG1 32 0.2PG2
285
2PG1 285 ; PG1
2
142.5 MW
PG2 107.5 MW
Alter:
N
bi
PD 2ai 250
25 32
i1 0.2 0.2
N 1 1
1
2ai
0.2 0.2
i1
53.5
b1 53.5 25
PG1 142.5 MW
2a1 0.2
b2 53.5 32
PG2 107.5 MW
2a2 0.2
PGi 250 MW
i1
Unit Commitment and Economic Dispatch 4.55
4G0<?;4 4.12
A power plant has three units with the following cost characteristics:
C1 0.05 P2G1 23.5 PG1 700 Rs/hr
C2 0.2 P2G2 20 PG2 850 Rs/hr
C3 0.09 P2G3 18 PG3 960 Rs/hr
Where PGi’s are in MW.
Maximum and minimum loading allowable on each unit are: 150 MW and 40 MW.
Find the optimal scheduling for a load of 275 MW.) (May 2010)
Solution
(i) Find
N
bi
PD 2ai
i1
N
1
2ai
i1
23.5 20 18
275
2 0.05 2 0.2 2 0.09 36.55
1 1 1
2 0.05 2 0.2 2 0.09
(ii) Find PGi using 36.55
b1 36.55 23.5
PG1 130.5 MW
2a1 2 0.05
b2 36.55 29
PG2 41.375 MW
2a2 2 0.2
b3 36.55 18
PG3 103.055 MW
2a3 2 0.09
4.56 Power System Operation and Control
40 PG1 150
40 PG2 150
40 PG3 150
The optimum schedule is
PG1 130.5 MW
PG2 41.375 MW
PG3 103.055 MW
4G0<?;4 4.13
Two areas are interconnected as shown in fig. Total generating capacity in each
is 600 MW. The cost characteristics are
C1 2000 20P1 0.05P21 Rs/hr
C2 2750 26P2 0.03091P22 Rs/hr
Find the cost of generation if (a) each area supplies its own load. (b) Units are
loaded as per economic scheduling. Assume that line has unlimited capacity and
transmission losses are negligible. Also find the saving and tie line loading.
Solution
P1 350 MW
P2 550 MW
dC1
(b) 20 0.1 P1
dP1
dC2
26 0.06182 P2
dP2
P1 380.9 MW
P2 519.1 MW
Rs.77.275 per hr
4G0<?;4 4.14
Solution
IC1 IC2
1 ITL1 1 ITL2
1 1
L2 1.25 PL
1 ITL2 1 0.2 ITL
PG
From equ (1)
IC1, L1 IC2 L2
L1 1.5625
Unit Commitment and Economic Dispatch 4.59
4G0<?;4 4.15
Solution
1 dPL
Penalty factor where ITL1
1 ITL1 dP1
dF1
IC1
dP1
dF2
IC2
dP2
IC1 IC2
1 ITL1 1 ITL2
dF1 dF2
dP1 dP2
dPL dPL
1 dP 1 dP
1 2
0.16 P1 32 0.24P2 36
dPL 1 0.2
1 dP
1
48
75
dPL
1
dP1
4.60 Power System Operation and Control
1
Penalty factor for unit I,
dPL
1
dP1
75
48
1
i.e., 1.5625
1 ITL1
4G0<?;4 4.16
Solution
Energy input Fi PGi PGi Hi PGi Ci bi PGi ai P2Gi
Ci
Heat rate Hi PGi bi ai PGi
PGi
Ci ...(1)
H1 PG1 H1 25 bi ai 25 10
25
Ci ...(2)
H2 PG2 H2 40 bi ai 40 9
40
Ci ...(3)
H3 PG3 H3 100 bi ai 100 8
100
Solving equations (1), (2), (3) find the values of a1, b1, c1
Unit Commitment and Economic Dispatch 4.61
0.04 1 25 ci 10
0.025 1 40 bi 9
0.01 1 100 a 8
i
0.675
10 1 25
1 9 1 40 45
8 1 100
1 45
Ci 66.666
0.675
0.04 10 25
2 0.025 9 40 4.95
0.01 8 100
2
bi 7.33
0.04 1 10
3 0.025 1 9 0
0.01 1 8
ai 0
1614 Rs/hr
Inequality Constraints
Since each generator must not be operated above its rating or below some
minimum value.
1 2 N
The incremental cost curve is obtained by considering the change in the cost
of generation to the change in real-power generation at various points on the
input-output curves, i.e., slope of the input-output curve as shown in Fig.
dCi
Where,
dPGi
Ci Operating cost
dP
Incremental
dF
Unit Commitment and Economic Dispatch 4.65
Where,
ai, bi, ci are constants
PGi Power generation.
11. List few constraints that are accounted in unit commitment problem.
(April/May 2010) (Nov/Dec 2010) (Nov/Dec 2007 (Dec 2014)
1. Spinning reserve
2. Thermal constraints
(i) Minimum up constraints
(ii) Minimum down constraints
(iii) Crew constraints
3. Other constraints
(i) Hydro constraints
18. Mention the assumption made in the formation of loss formula matrix, B.
(April/May 2008)
1. Assume generators are identical.
1
PGi Fi
Participation factor for each unit N
PD
1
Fi
i1
22. Write the condition for the optimal power dispatch in a lossless system.
(Nov/Dec 2013)
The necessary condition for the existence of a minimum cost operating condition is
that the incremental cost rates of all the units be equal to some undetermined value .
dCi [N equations]
dPGi
N
Power balance equation is PGi PD
i1
1
Li
1 ITLi
26. Find the incremental transmission losses for a two area power system, where
the bus voltages are kept fired and the line power flow is a function of line
angle. Power loss is a function of area B only.
(May 2015)
dPL
ITL1 2 B11 PG1 B12 PG2
dPG1
dPL
ITL2 2 B22 PG2 B12 PG1
dPG2
PART - B: QUESTIONS
1. Derive coordination equation for economic dispatch including losses, in the power
system. Give steps for economic dispatch calculation. Neglecting losses.
(16) (April/May 2011) (Dec 14)
2. (i) Explain the iteration method for finding the solution of economic
dispatch including transmission losses with a neat flow chart.
(10) (Nov/Dec 2012)
(ii) A generating unit has two 200 MW units whose input cost data is as follows:
F1 0.004P21 2.0 P1 80 Rs/hr
F2 0.006P22 1.5 P2 100 Rs/hr
For a total load of 250 MW, find the load dispatch between the two units for
economic operation. (6) (Nov/Dec 2012)
3. (i) Derive the coordination equation with losses neglected.
(8) (April/May 2011)
(ii) The cost characteristics of three plants of a plant are:
C1 0.05 P21 17.0 P1 160 Rs/hr
C2 0.06 P22 14.4 P2 200 Rs/hr
C3 0.08 P23 9.0 P3 240 Rs/hr
where P1, P2, P3 are in MW
10. A power plant consists of two 200 MW units, whose input cost data given by,
F1 0.004 P21 2.0 P1 80 Rs/hr
F2 0.006 P32 1.5 P2 100 Rs/hr
For the total load of 250 MW, what should be the division of load between two
units for most economic operation? (16) (Nov/Dec 2007)
11. A heat rate of 100 MW fuel fired generator is
10 Mkcal/MWhr at 25% rating
9 Mkcal/MWhr at 40% rating
8 Mkcal/MWhr at 100% rating.
Find
(i) Fuel cost of 25%, 40%, 100% loading.
(ii) Incremental cost
(iii) Fuel input rate using quadratic approximation to deliver 101 MW.
(AU/May 11)
12. Determine the economic operation point for the three thermal units delivering a
total load of 600 MW without considering generate limit as well as with
considering generator limit. (AU/May 2015)
16. (i) Explain the priority list method using suitable numerical example.
(10) (Nov/Dec 2012) (April/May 2010) (April/May 2008) (Nov/Dec 2008) (May 2015)
(ii) Define 1. Minimum up time 2. Minimum down time 3. Spinning reserve.
(6) (Nov/Dec 2012)
17. Explain in detail about forward dynamic programming method with suitable
diagram. (8) (Nov/Dec 2007) (Dec 14)
18. (i) Explain the unit commitment problem using priority ordering load dispatch.
(8) (April/May 2008)
19. Construct the priority list for the units given below: (Nov/Dec 2009)
20. Determine the priority list using full load average production cost for the data
given below. (May 11)
Also obtain optimum unit commitment solution for the power demand of 800
MW.
21. Create a unit commitment using the priority list method for the following three
units (Dec 2014)
The fuel cost equations are as follows:
Today’s power systems are essentially very huge interms of energy generated,
transmitted and utilised, number of customers and total investment. The installed
capacity in USA excess 1000 GW with annual energy generated exceeding 5000 TWhr.
The installed capacity in India exceeds 140 GW with annual energy generated
exceeding 700 TWhr. Moreover the system is growing continuously with more
generating plants, transmission lines and distribution lines being added every month.
The power system feeds a very large number of domestic, commercial, industrial,
agriculture, electric traction and other customers.
Generation, transmission and distribution of electrical energy has to face the
following challenges
5.2 Power System Operation and Control
1. No method for large scale storage of electrical energy has been devised so
far. Electrical energy must be generated and supplied instantaneously.
2. The real and reactive power demand changes from instant to instant, day
to day and season to season. Power system has to meet this varying demand
all the time.
3. The overall cost in generation, transmission and distribution must be kept
to its minimum so that electricity tariff is not abnormally high. Moreover
the decision regarding increase in tariff lies with Government departments
and regularity bodies. The power utility has no right to increase the tariff
by itself.
4. Many environmental factors have to be kept in view. It is essential that
generation, transmission and distribution of electrical energy should have
minimum impact on environment.
5. The quality of electric supply must be maintained. This includes proper
voltage, proper frequency and adequate reliability. However an average
customer has no means to judge quality unless it becomes very bad.
Power system engineers employ large number of controls and many complex
devices to satisfy the above challenges. Moreover the above considerations require
the power systems to be operated as interconnected systems. An isolated power system
can hardly meet the above challenges.
The operation and control of an interconnected power system cannot be done
manually. A manually operated system is too slow and is subject to human errors.
Therefore all power systems, throught out the world, are controlled through computers
installed in a centre called Energy control centre. The various functions of an energy
control centre (ECC) can be enumerated as under:
1. Load forecasting: Long term, medium term and short term.
2. Planning of increase in generation capacity, transmission capacity and
distribution capacity.
3. System monitoring.
4. Planning of scheduled maintenance and repair.
5. State estimation.
6. Unit commitment and economic dispatch.
7. Automatic generation control.
Computer Control of Power Systems 5.3
1. Load forecasting
Long term and medium term forecasts are needed for deciding about system
expansion strategies. Pretty long time is needed to setup new generation and
transmission projects. A hydroelectric power plant may needed about 8-10 years for
setting up. A thermal power plant may take 3-4 years for installation. If medium
term forecasts indicate a big increase in demand, the utility may have to go in for
gas turbine power plant. The electric utility has always to be ready to meet the demand
and load forecasts help in long term planning, fuel budgeting, operations planning,
preparation of weekly generation schedules, allocation of pool savings etc. Proper and
accurate long term, medium term and short term load forecasting has lot of bearing
on reliability of electric supply in future.
3. System monitoring
System monitoring makes available the upto date information on the conditions
in the power system. The important and critical quantities have to be measured and
the data sent to the energy control centre so that a continuous watch may be kept
on the system. System monitoring also includes collecting important information about
voltage profiles, frequency, generator loadings, transformer tap positions etc. For proper
system monitoring digital computers are installed in energy control centres to collect
and process the critical informations. Moreover the computer can also check the
incoming information match it with prestored values and limits and alarm the operators
in the event of an overload, an out of limit voltage, a forced outage etc. System
monitoring also helps in making arrangements for emergency supplies from a
neighbouring utility.
5.4 Power System Operation and Control
5. State estimation
State estimation refers to the process of estimating the unknown system state
variables. These estimates arc made on the basis of measurements. The state estimator
operates on real time inputs which are of two types i.e., data and status information.
The on/off status of circuit breakers disconnect switches etc. determines the network
configuration which changes everytime these devices operator. Remote terminal units
(RTU)s installed at different places in the system send information about power system
status. Measurements are made to estimate the system performance in real time from
the points of view of system security control and constraints on economic dispatch.
The estimator has to eliminate these in accurate measurements and produce the best
estimates. The output of state estimation is used for security, reliability, economic
dispatch and control.
emergency conditions. It is possible that the whole area served by the utility may so
completely dark. The ECC has to be equipped and be ready to face such situations
and take suitable automatic and manual actions to bring back the system to normal
state as early as possible.
Proper and efficient management system requires lot of data about operating
conditions. Many operations have to be carried out at unattended locations from
operating centre. In many situation operations such as opening or closing a circuit
breaker etc. have to be carried out but the cost of providing operating personnel may
be prohibitive. If an operator has to go from the control centre to the site to perform
such operations there would be considerable delay. Such delays result in long outage
durations and poor reliability. SCADA systems have been developed to overcome such
problems. The need to control remote operations and monitor them led to development
of SCADA.
5.3.4 Configurations
SCADA system may have different configurations depending on the system and
its requirements. Each configuration consists of a master unit M and remote unit R.
Fig. 5.1 (a) shows a one to one SCADA configuration. It has a master unit for
each remote unit. Fig. 5.2 (b) shows star configuration with master unit at a central
location and remote units branched out. The number of remote units may be any
depending on the power system. However each communication channel has one remote.
It is also called hub configuration. Fig. 5.3 (c) shows a configuration there may be
many remote units on a communication channel. Fig. 5.4 (d) shows a network
5.8 Power System Operation and Control
configuration. It has one master unit M, several communication channels and many
remotes on each channel. It is a combination of star and party line configurations
Fig. 5.1 SCADA configuration (a) One to one (b) Star (c) Party-line (d) Network
Computer Control of Power Systems 5.9
The master unit is the heart of SCADA system. All operations of different RTUs
are made from the master unit and reported bank by RTUs to the master unit. The
master unit has a digital computer and other auxiliary equipment to permit
communications between master unit and RTUs. One such equipment is a modem
(modulator - demodulator). The computer uses digital pulses. Modem converts these
digital pulses to analog signal so that it can be transmitted to RTU. The messages
from master unit to RTUs are in the form of tones of audio frequency and are sent
by frequency shift techniques. Frequency shift signaling is pretty immune from noise.
The other equipments include line printer, operators console, CRT, graphic instruments
board etc. as shown in fig. 5.2. The printer enables the messages received from RTUs
to be converted to hard copy. Sometimes a single line diagram of the power system
controlled through SCADA also exists in the master station. Digital/analog (D/A)
converters are also provided in master unit so that informations like line currents, bus
voltages, frequency, real and reactive power flows as received in digital from is
converted to analog form and read by various indicating instruments. Some recording
instruments are also provided so that visuals representation of the condition is
displayed. Colour CRT screens enable different colours to indicate changes in voltage
levels, positions of circuit breakers etc.
Some flashing indicators and alarm signals are used to draw the attention of
operator.
For remote operations the operator at the master station follows ‘Select before
operate’ procedure which is as follows:
1. The operator selects the RTU
5.10 Power System Operation and Control
The installed generation capacity in India has increased from about 1710 MW
in 1950 to about 140000 MW in 2009. The electrical energy generated annually has
increased from about 5 109 kwh in 1950 to about 700 109 kwh in 2009. The
percapita consumption has increased from 15.6 kwh in 1950 to about 700 kwh in
2009. Yet every state is facing shortage of electrical energy. The peak time power
shortage is about 13% and energy shortage is about 8%. Only about 50% of population
has access to electrical energy. The reason for shortages can be attributed to the fact
that generation, transmission, distribution and utilisation of electrical energy is not
being managed properly.
Energy management system is an interactive energy management tool that helps
track energy usage and reduce wastage. It can be described in terms of its application
to electric utilities, who manage generation, transmission and distribution of electric
energy and users industries, commercial hours etc. SCADA is used for both these
categories.
Demand side management involves all activities which involve actions by the
user. The scope of DSM includes load management, increased electrification,
developing DSM programs, peak clipping, vally filling, load shedding, strategic energy
conservation, strategic load growth etc.
EMS for industries also uses tools like SCADA and many other softwares.
Network topology means the different ways in which the active and passive
devices are connected in a network. In a power system the main active devices are
the synchronous generators. Each power system has a number of power plants and
each power plant has more than one generator. Each generator has a step up
transformer to setup the voltage from generation voltage (generally 11 kV in India)
to 132, 220, 480 kV. Each power plant feeds one (or) more transmission lines. Power
plants exist in different areas and are thus spread over the entire area. The total system
consisting of all the lines etc is called grid. Circuit breakers are installed at each end
of line and other buses etc. for disconnecting the faulty equipments and cirants in
the event of fault.
The power system all over the world have expanded considerably during the
past few decades. In general a power system may have about 6 generating plants
with a total of about 25 generates about 50 buses and an equal number of HV and
EHV lines. The operation and control of such a system is a complex task. The
requirements of reliability, economic operation and security even under the most
difficult situations makes the job of power system engineers really cumbersome.
SCADA systems are used extensively by every utility to monitor the performance
of the system. The data as obtained by SCADA system is used to take decisions in
emergency state. To ensure correct decision it is necessary to know the existing state
of the system. The state variables are the voltage magnitudes and phase angles at the
buses. The inputs to the load flows analysis are the P and |V| at generator buses (Pu
buses) and P and Q at load buses. If this complete information is not available, the
load flow analysis cannot be made. Moreover it is possible that there may be errors
in these in put quantities.
The state estimation process is meant to determine the best possible estimate
of voltage magnitude and phase angles recognising the fact that some of the inputs
(obtained from measurements by SCADA instruments) may be erroneous and
they may also be redundant measurements.
The error ‘e’ is a random number. The probability density function of ‘e’ is a
normal distribution with mean value zero. The probability density function is
Computer Control of Power Systems 5.15
1 e
2 ...(5.2)
PDF e
2 22
2 Variance
Fig. 5.4 shows the normal distribution curve.
Fig. 5.3 shows a simple DC circuit having two resistance in parallel fed by a
voltage source.
Thus
zmeas
1 ztrue
1 e1 ...(5.3)
zmeas
2 ztrue
2 e2 ...(5.4)
Both errors are randomly distirbuted with zero mean. The PDF for e1 and e2
are
1 e21 ...(5.5)
PDF e1 exp 2
1
2
21
1 e22 ...(5.6)
PDF e2 exp 2
2
2
22
Since true current through R1 is x/R1 and true current R2 is x/R2 we can write
PDF for zme
1
as
and zme
2
as
as
2 ...(5.7)
meas x
z1
meas 1 R1
PDF z1 exp
1
2
2
21
2 ...(5.8)
meas x
z2
meas 1 R2
PDF z2 exp 2
2
2
2
2
Now we have to find the probability that measured value is the true value.
meas meas
z1 dz1
as
Prob zme
1 PDF zmeas
1 dzmeas
1 as dzme
1
as
meas
z1
as
PDF zmeas
1 dzme
1
Computer Control of Power Systems 5.17
Then
2
zmeas x
1 R1
meas ...(5.9)
1
Prob zmea
1
s
exp dz1
2
1 221
2
zmeas x
2 R2
meas ...(5.10)
1
Prob zmea
2
s
exp dz2
2
2 222
The probability of two events happening together is the product of the two
probabilities.
Thus
s
Prob zmeas
1 and zmeas
2 PDF zmea
1 PDF zmeas
2 dzmeas
1 dzmeas
2
2 2
meas x meas x
z1 R z2 R
1 2
1 1 meas meas
exp exp dz1 dz2 ...(5.11)
1
2
2
21 2
2
2
22
2 2
zmeas x zmeas x
1 R1 2 R2
...(5.14)
max ln 1
2 ln 2
2
221 222
5.18 Power System Operation and Control
The term 1 2 and 2 2 are constant. The remaining two terms are
appearing with negative sign. Therefore we have to minimize these two terms to get
as
maximum probability of zmeas
1 and zme
2
Thus
2 2
1meas x zmeas x
z 2
R1 R2 ...(5.15)
meas meas
Max prob z1 and z2 min
221 222
To minimize the function on right hand side of (Eq.5.15) we take the differential
and equate to zero. Thus
2 2
zmeas x zmeas x
1 R1 2 R2
d
0
dz 221 222
zm eas x zmeas x
1 R1 1 R2
or 0 ...(5.16)
R1 21 R2 22
The solution is
zm
1
eas
zm
2
eas
R1 21 R2 22
x ...(5.17)
1 1
2 2
R21 21 R2 2
If one of the ammeters is of higher accuracy, its variance will be lower than
that of other
x zmeas
1 R1 ...(5.18)
It is seen from the above analysis that in the method of maximum likelihood
the estimate of unknown quantity is expressed as the value of the quantity which
Computer Control of Power Systems 5.19
gives the minimum of sum of squares of difference between each measured value
and true value (being measured) and each squared difference divided (or weighted)
by the variance of the meter error. Thus the method is basically weighted least square
estimation.
If we are making N measurements to estimate the value of a parameter x, we
can write
N
[zmeas
i fi x]2
min J x
x
21 ...(5.19)
i1
zmeas
i Value of ith measured quantity
21 Variance of ith measurement
J x measurement residual
fi function which is used to find the value being measured by the ith
measurement.
If we have M unknown parameters for which we are estimating the values using
N measurements we can write
N ...(5.20)
[z1 f1 x1, x2 xm]2
min J x1 x2 xm
x1, x2 xm
21
i1
Whenever any equipment is not available for service, the equipment is said to
have suffered an outage. An outage may be a forced outage or scheduled maintenance
outage. The forced outage may be due to fault or defect in the equipment. Whenever
a forced outage occurs the equipment (generator, transformer, line) has to be
disconnected from service and sent for repairs. At the same time an attempt is made
to ensure continuity of supply to consumers as for as possible. Scheduled maintenance
is also necessary for different equipments to restore them to good working condition.
Every utility has elaborate maintenance schedules for different equipments.
Forced outages of generators, lines etc. May cause emergency conditions, the
possible effect of outages are analysed using contingency analysis program.
Fig. 5.5 shows a simple flow chart to illustrate to the principles of contingency
analysis. The program reads data, sets up system model, estimates initial conditions
and simulates faults an generators one by one. For each fault condition of possibility
of lines being loaded, bus voltages going outside limits etc. are found. Similarly faults
on lines are also simulated one by one and possibility of over-loading (or) voltage
limit violation are found.
The flow chart of Fig. 5.5 is for single contingency. However there is always
a possibility of more than one forced outage simultaneously. All utilities have programs
for testing their systems for two outages occurring together. Moreover outages can
also occur in sequence i.e one outage followed by another. This condition has also
to be tested.
Computer Control of Power Systems 5.21
Fig. 5.6 shows the different states in which a power system may exist at different
times. For over 98% of time it exists in normal state. For over 98% of time it exists
in normal state. However sometimes the system may go to alert and other states. The
transition diagram depicts the transition of the system from normal to other states
and back.
When the system is in normal state the generation matches the load. This equality
is shown by alphabet E in transition diagram. Another symbol used in this diagram
is 1. This symbol denotes that none of the equipments (generators, lines, transformers
are met with and therefore
etc.) is over loaded. In normal state both these conditions
E and I are mentioned in the diagram for normal state. E denotes that equality between
generation and load is disturbed. Similarly I denotes that some equipment is
overloaded.
When in normal state the system is secure and some amount of spinning reserve
also exists. When a small decrease in generation occurs or some other disturbance
takes place, the system may go to Alert State. However, the system is synchronised
but the security level is reduced below the specified limit. But generation and load
are matching and none of the equipments is over loaded. Some corrective action is
initiated and system may go back to normal state. However if preventive action is
not successful or if disturbance is severe, the system may go to emergency state. If
Computer Control of Power Systems 5.23
the disturbance is severe the system may transition directly from normal to emergency
system is synchronised but some equipments may
state. For emergency state also the
be overloaded (symbols E and I denote these condition). Some emergency control
action are needed if the system laters emergency state. If these emergency control
action fail, the system may transition to in Extremis state. When in this state the
synchronisation is upset and the system gets disintegrated into islands. The generation
and load matching so longer exists and overloding
of equipment may also occur. This
state is characterised by symbols E and I. This state may witness tripping of one or
more generators (due to over loading) and some lines may also get tripped. Some
parts of the country (or province) may also face block out if the system is in Extremis.
The conditions which force the power system to go from Normal to In Extremis may
last for a few seconds or a few minutes. The power system engineers have to take
some very important corrective actions to take the system to ‘Restorative’ and then
to ‘Normal’ state. This process may take or any hours or even days. Turbines have
to be restored and generators have to be synchronised again. The islands, in which
the system has disintegrated, have to be connected again and lost loads have to be
picked up. The control strategies which are adopted when the system is not in ‘Normal’
state can be summarised as under.
Alert state: Preventive control to restore adequate reserve generating margin,
generation shifting, tie line rescheduling, voltage reduction.
Emergency state: Immediate control to clear equipment overloads, fault clearing,
fast valuing dynamic braking, exciter control, load control, capacitor switching and
all controls mentioned in ‘Alert’ state.
In Extremes
Heroic action to control disruption of entire system, Load shedding, controlled
islanding and all controls mentioned in ‘Emergency state’.
Restorative: Corrective control to re-establish viable system, generating units
restarting and synchronisation load restoration, re-synchronisation of different islands
and areas.
The main equipment is a computer with enough storage capability. Many years
ago main frame computers were used for this purpose but new desktop computers
have also huge storage capability and are sufficient for most power systems. In an
energy control centre computers are connected in ring formation. All computers have
5.24 Power System Operation and Control
back up computers too. The main computer is used for on line program execution.
The other computers are for duties like data acquisition etc. The stand by computers
are meant for emergency duty. Some CROs, printers are also there. The stand by
computer is kept updated so that there is no loss of data or control. The change over
from main computer to stand by computer can be manual, or automatic but is generally
automatic. Operator’s console, modems, graphic instruments board also exist. The
communication channels go out from the station to remote terminal units. Computer
based telementry and data processing facilities have been provided.
Modern trend is to use computers for relaying also. The advantages of using
computers for relaying are logging capability and application expansion possibility.
Accuracy, fast response and overall economy are the other advantages.
Numerical relays sample the valves of current, voltage etc. many times each
second A/D converters convert these sample to digital form and feed then to the
computer. Whenever a fault occurs the computer calculates the fault current and issues
necessary commands to RTU for circuit breaker operation and isolation of faulty
section. Computer relays can locate faults also. Moreover self checking features can
also be incorporated. However the computer relays have relatively short life span on
the other hand conventional relay have long life.
3. Real time monitoring end control (ie., LFC, Economic dispatch, load
shedding and restoration, transformer tap changing, control of static var
systems etc.
4. Operating systems.
Computer Control of Power Systems 5.25
2. Alarm
3. Control and indication of AGC
4. Data logging
5. Data acquisition
6. ON/OFF Control
8. List the applications of SCADA. (Dec/2014)
1. Automatic generation control
2. Interchange scheduling
3. Optimal power flow
4. Short circuit analysis
9. Define the EMS system. (Nov/Dec 2011) (April/May 2009)
Energy management system is the process of monitoring, coordinating and
controlling the generation, transmission and distribution of electrical. It is performed
at centres called “system control centres”, by a computer system called EMS.
10. What are the EMS function? (Nov/Dec 2009)
1. Network Configuration/Topology Processor
2. State Estimation
3. Contingency Analysis
4. Three Phase Balanced Operator Flow
5. Optimal Power Flow
6. Dispatcher Training Simulator
11. What are the objectives of Automatic generation control?
(May/June 2014))
1. To hold frequency at or very close to a specified nominal value.
2. To maintain the correct value of interchange power between control areas.
3. To maintain each units generation at the most economic value.
12. Denote the hierarchical levels used in EMS.
1. System control centre
2. Area control centre
3. Remote terminal unit
Computer Control of Power Systems 5.27
2. Short term
3. Medium term
4. Long term
25. What are the important types of relays used for protection?
1. Over-current relay
2. Impedance relay
26. Distinguish between reliability and security of power system. (May 2008)
Reliability is a probabilities index defined as the long term average number of
days on which daily peak load exceeds the available generating capacity.
PART - B: QUESTIONS
1. Explain need of computer control of power system. (6) (Nov/Dec 2011)
2. Briefly discuss the various functions of energy control centre.
(8) (Nov/Dec 2010)
3. (i) Illustrate SCADA with typical schematic. (8) (April/May 2008)
(ii) What are the functions of a modern power system control centre?
(8) (April/May 2008)
4. Discuss the functions of ‘SCADA’ in power system operation.
(16) (Nov/Dec 2012) (Dec 2014)
5. Briefly explain various functions of SCADA with a neat diagram.
(10) (Nov/Dec 2011)
6. Write short notes on:
(i) SCADA systems. (8)
(ii) Security analysis and control. (8) (April/May 2011)
7. Draw a block diagram to show the hardware configuration of a SCADA system for
a power system and explain the application of SCADA in monitoring and control
of power system. (10) (Nov/Dec 2013) (Nov/Dec 2009) (April/May 2008)
8. Explain the hardware components and functional aspects of SCADA system using
a functional block diagram. Also discuss the functions of SCADA.
(16) (April/May 2010)
9. What is EMS? What are its major functions in power system operation and
control? (6) (Nov/Dec 2013) (April/May 2008)
10. Explain the security monitoring using state estimation with necessary diagrams.
(16) (Nov/Dec 2013) (Nov/Dec 2009) (May 2015)
11. Enumerate the various operating states and the control strategies of a power
system. (16) (Nov/Dec 2012)
12. Explain briefly how the system states are continuously monitored and controlled.
(8) (April/May 2010)
13. Write short note on security control. (4) (Nov/Dec 2008)
14. Draw the state transition diagram and explain the various operating state of a
power system and the associated control actions. (16) (Nov/Dec 2008)
5.30 Power System Operation and Control
15. Explain the operating state of a power system in the security perspective with
an example (16) (Nov/Dec 2007) (Dec 2014) (May 2015)
16. Explain various state transition and control strategies using state transition
diagrams. (16) (Nov/Dec 2011) (April/May 2008)
17. Explain the various operating states of a power system with transition diagram.
(16) (April/May 2011) (Nov/Dec 2010)
18. Draw a state transition of a power system showing different sets of operating
states classified according to security level. Mark on the diagram and explain
the state transition that may occur due to system disturbances and also the
different control actions that can be taken to improve the security level of the
system. (16) (April/May 2008)
19. Explain the various controls for secure operation. (June 2014)
Question Paper 1
M 2151
B.E/B.Tech DEGREE EXAMINATION, APRIL/MAY 2008
Seventh Semester
Electrical and Electronics Engineering
EE 431 — POWER SYSTEM CONTROL
Time: Three hours Maximum: 100 Marks
15. (a) Develop an iterative algorithm for solving the optimum dispatch equation
of an ‘n’ bus power system taking into account the effects of system losses.
(16)
Refer Page No: 4.8.1
Or
(b) A power plant consists of two 100 MW units, whose input cost data
given by,
F1 0.05 P21 20P1 800 Rs/hr
F2 0.06 P21 16P1 1000 Rs/hr.
For the total load of 150 MW, what should be the division of load between
two units for most economic operation? (16)
Refer Example: 4.1
4 Power System Operation and Control
M 3279
B.E/B.Tech DEGREE EXAMINATION, NOVEMBER/DECEMBER 2008
Seventh Semester
Electrical and Electronics Engineering
EE 1401 — POWER SYSTEM OPERATION AND CONTROL
(Regulation 2004)
Time: Three hours Maximum: 100 Marks
8. Write the condition for the optimal power dispatch in a lossless system.
Refer Page No: 4.67
Part B – (5 16 80 Marks)
11. (a) (i) Discuss the various reserve requirements in power system operation.
(6)
Refer Page No: 1.9
(ii) The maximum demand on a power station is 100 MW. If the annual
load factor is 40%, calculate the total energy generated in a year. (4)
Refer Page No: 1.16
(iii) A diesel station supplies the following loads to various consumers: (6)
Industrial consumer 1500 kW, Commercial establishment 750 kW,
Domestic power 100 kW, Domestic light 450 kW. If the maximum
demand on the station is 2500 kW and the number of kWh generated per
year is 45 106, determine (1) Diversity factors (2) Annual load factor.
Refer Example: 1.7
Or
(b) (i) What are system level and plant level controls? (6)
Refer Section: 1.12
(ii) Define diversity factor. Discuss the practical ways to improve the
diversity factor. (6)
Refer Section: 1.8
(iii) Write short note on Load Forecasting. (4)
Refer Section: 1.10.1
12. (a) What are the components of speed governor system of an alternator?
Derive its transfer function with an aid of a block diagram. (16)
Refer Section: 2.2
Or
(b) Two 50 Hz power stations are connected by means of an interconnected
cable of negligible impedance, so that the stations work in parallel. Station
A has a full load capacity of 15 MW and uniform speed regulation of 3%.
Station B has a capacity of 4 MW and uniform speed regulation of 4%.
The load on the busbars of station B is 4 MW and of station A is 10 MW.
Calculate the generated output of each station, power transmitted by
interconnected cable and operating frequency assuming free governor action
6 Power System Operation and Control
and that the speed changers of generators were set to have frequency of 50
Hz at no-load.
Refer Example: 2.3
13. (a) Draw the diagram of a typical automatic voltage regulator and develop
its block diagram representation. (16)
Refer Section: 3.4
Or
(b) (i) Explain how the OLTC can be used for voltage control. (6)
Refer Section: 3.8
14. (a) In a power system having two units, the loss co-efficient are
B11 0.0015 MW 1, B12 0.0006 MW 1
B21 0.006 MW 1, B22 0.0024 MW 1
The incremental production costs of the units are
dF1
0.08 PG1 20 Rs/MWhr
dPG1
dF2
0.08 PG2 16 Rs/MWhr .
dPG2
Find the generation schedule for 20 and 25. Find also the change in
transmission losses between the two schedules. (16)
Refer Example: 4.3
Or
Question Paper 7
(b) (i) What is unit commitment problem? Discuss the constraints that are
to be accounted in unit commitment problem. (8)
Refer Section: 4.9
(ii) Explain the priority ordering method of committing units. State merits
and limitations of this method. (8)
Refer Section: 4.26
15. (a) (i) Briefly discuss the various functions of energy control center. (12)
Refer Section: 5.2
(ii) Write short note on security control. (4)
Refer Section: 5.20
Or
(b) Draw a state transition diagram and explain the various operating state
of a power system and the associated control actions.
Refer Section: 5.22
8 Power System Operation and Control
4. Draw the dynamic response of change in frequency for a step load change.
Refer Page No: 2.85
Part B – (5 16 80 Marks)
11. (a) (i) Discuss the main functions of security control. (8)
Refer Section: 1.1.2
(ii) Differentiate cold reserve from hot reserve. (4)
Refer Section: 1.9
(iii) Explain the term economic dispatch control (EDC) (4)
Refer Section: 1.1.2
Or
(b) A generating station supplies the following loads: 15000 KW, 12000 KW,
8500 KW, 6000 KW and 450 KW.
The station has a maximum demand of 22000 KW. The annual load factor
of the station is 48%. Calculate
(i) the number of units supplied
(ii) the diversity factor
(iii) the demand factor. (16)
Refer Example: 1.10
12. Two 1000 KW alternators operate in parallel. The speed regulation of first
alternator is 100% to 103% from full load to no load and that of other 100%
to 105%. How will the two alternators share a load of 1200 KW and at what
load will one machine cease to supply any portion of the load? (16)
Refer Example: 2.9
Or
(b) Draw the block diagram of two area load frequency control system and
explain the uncontrolled static analysis. (16)
Refer Section: 2.7
13. (a) (i) Explain the transfer function of modeling of exciter system with
neat diagram. (8)
Refer Section: 3.4
(ii) Discuss the static and dynamic analysis of AVR. (8)
Refer Section: 3.5
Or
(b) (i) What are the methods of voltage control? Explain any two methods
in detail.
Refer Section: 3.7
10 Power System Operation and Control
(ii) The load at the receiving end of a three phase, overhead line is 225
MW, 0.8 lagging PF, at a line voltage of 33 KV. A synchronous compensator
is situated at the receiving end and the voltage at both ends of the line is
maintained at 33 KV. Calculate the MVAR of the compensator. The line has
5 ohm resistance per phase and 20 ohm inductive reactance per phase. (8)
Refer Example 3.5
14. (a) State the unit commitment problem. With the help of a flowchart
explain forward dynamic programming solution method of unit commitment
problem. (16)
Refer Section: 4.10.2
Or
(b) (i) Develop an iterative algorithm for solving the optimum dispatch
equation of an ‘n’ bus power system taking into account the effects of system
losses. (8)
Refer Section: 4.8.1
(ii) Construct the priority list for the units given below: (8)
5. Write the relation between voltage, power and reactive power at a node.
Refer Page No: 3.56
7. List the few constraints that are accounted in unit commitment problem.
Refer Page No: 4.65
Part B – (5 16 80 Marks)
11. (a) (i) Explain the need for voltage and frequency regulation in power
system. (8)
Refer Section: 1.11
(ii) A generating station has a Maximum demand of 400 MW. The annual
load factor is 65% and capacity factor is 50% find the reserve capacity of
the plant. (8)
Refer Example: 1.1
Or
(b) (i) Explain the system voltage control and security control. (8)
Refer Section: 1.1.2
(ii) Consider an inductive load of type Z R jX. By how many percent
will the real load drop if the voltage is reduced by 1%? (8)
Refer Example: 1.15
12. (a) (i) Obtain the state variable model of a Single Area LFC. (8)
Refer Section: 2.9.3
(ii) Explain the tie-line bias control of two area system. (8)
Refer Section: 2.8
Or
(b) For a system of regulation 4 Hz/p.u MW, Kp 150 Tp 18 sec,
P0 0.01 P.U. Find the dynamic response for uncontrolled case. Also derive
the equation used. (16)
Refer Example: 2.11
13. (a) (i) Draw the circuit diagram of a typical excitation system and explain
the components. (8)
Refer Section: 3.3
(ii) Discuss generation and absorption of reactive power. (8)
Refer Section: 3.1
Or
(b) (i) How to minimize transmission loss using reactive power control?
(6)
Refer Section: 3.2.3
Question Paper 13
4. Write down the equation for area control error of two area system.
Refer Page No: 2.83
Part B – (5 16 80 Marks)
11. (a) Explain the following: (16)
(i) Hot reserve and cold reserve.
(ii) Load curve and load duration curve.
(iii) Governor control
(iv) Security control.
Refer Page No: 1.9
Refer Page No: 1.4
Or
(b) A generating station has the following daily load cycle:
12. (a) Develop the model of single control area and obtain its block diagram
representation. Explain the salient features under static and dynamic
conditions.
(16)
Refer Section: 2.5
Or
(b) Two synchronous generators operating in parallel. Their capacities are
700 MW and 600 MW. The droop characteristics of their governor are 4%
and 5% from no load to full load. Assuming that the generators are operating
at 60 Hz at no load, how would be a load of 800 MW shared between them.
What will be the system frequency at this load? Assume free governor action.
(16)
Refer Example: 2.1
13. (a) (i) Discuss generation and absorption of reactive power. (8)
Refer Section: 3.1
16 Power System Operation and Control
15. (a) Discuss the various functions of energy control centre. (16)
Refer Section: 5.2
Or
(b) Explain the operating states of a power system in the security
perspective with an example. (16)
Refer Section: 5.22
Question Paper 17
Part B – (5 16 80 Marks)
11. (a) A generating station has a maximum demand of 20 MW, a load factor of
60% a plant capacity factor of 48% and a plant use factor of 80%. Find the
(i) Daily energy produced.
(ii) Reserve capacity of the plant.
(iii) Maximum energy that could be produced daily if the plant were
running all the time and
(iv) Maximum energy that could be produced if the plant when running
(acc. to operating schedule) were fully loaded.
Refer Example: 1.11
Or
(b) (i) A generating station has a maximum demand of 50,000 kW.
Calculate the cost per unit generated from the following data.
Capital cost Rs.95 106
Annual load vector 40%
Annual cost of fuel and oil Rs.9 106
Taxes, wages and salaries etc. Rs.7.5 106
Interest and depreciation 12%. (12)
Refer Example: 1.12
(ii) 1. Define “diversity factor”. (2)
Refer Section: 1.8
2. Define “Planed use factor”. (2)
Refer Section: 1.6 (h)
12. (a) Draw the block diagram of uncontrolled two area load frequency control
system and explain the salient features under static conditions. (16)
Refer Section: 2.7
Or
(b) How is speed governor mechanism modeled? Explain its operations with
the speed load characteristics? (16)
Refer Section: 2.2
13. (a) (i) Develop a typical excitation arrangement to control the voltage of
an alternator and explain. (8)
Refer Section: 3.4
Question Paper 19
(ii) Briefly explain the role of tap changing transformer in voltage control?
(8)
Refer Section: 3.8
Or
(b) What is static VAR compensator? Where it is used? Explain its
operation. Also state the merits of static VAR compensator over the other
methods of voltage control. (16)
Refer Section: 3.9
14. (a) (i) Explain the unit commitment problem using priority ordering load
dispatch. (8)
Refer Section: 4.10.1
(ii) Explain the term ‘Incremental Operating cost’ of power system related
with economic dispatch. (8)
Refer Section: 4.3
Or
(b) The fuel inputs pre hour of plants 1 and 2 are given as
F1 0.2 P21 40 P1 120 Rs /hr
F2 0.25 P22 | 30 P2 150 Rs /hr
Determine the economic operating schedule and the corresponding cost of
generation if the maximum and minimum loading on each unit is 100 MW
and 25 MW. Assume the transmission losses are ignored and the total
demand is 180 MW. Also determine the saving obtained if the load is equally
shared by both the units. (16)
Refer Example: 4.6
15. (a) (i) Explain need of computer control of power system. (6)
Refer Section: 5.23
(ii) Briefly explain various functions of SCADA with a neat diagram. (10)
Refer Section: 5.6
Or
(b) Explain various state transitions and control strategies using state
transition diagram.
Refer Section: 5.22
20 Power System Operation and Control
Part B – (5 16 80 Marks)
11. (a) (i) A generating station has the following daily load cycle.
Time (hrs) 0-6 6-10 10-12 12-16 16-20 20-24
Load (MW) 40 50 60 50 70 40
Draw the load curve and find. (10)
1. Max. demand
2. Units generated/day
3. Average load
4. Load factor.
Refer Example: 1.5
(ii) Explain the types of load forecasting. (6)
Refer Section: 1.10
Or
(b) Explain the important objectives of power system and various control
strategies during its operation. (16)
Refer Section: 1.1
12. (a) With a neat block diagram, explain the single area load frequency
control system. (16)
Refer Section: 2.5
Or
(b) (i) Discuss the integration of economic dispatch control with automatic
generation control. (8)
Refer Section: 2.11
(ii) Derive an expression for load sharing between two alternators. What
are the effects of fuel supply and change of excitation? (8)
Refer Section: 2.3
13. (a) (i) Discuss the relation between voltage and reactive power at a node.
(9)
Refer Section: 3.1
(ii) Explain briefly the reactive power requirement for control of voltage
in long radial lines. (7)
Refer Section: 3.1
22 Power System Operation and Control
Or
(b) Explain the methods of voltage control in a transmission system.
14. (a) (i) Explain the iteration method for finding the solution of
economic dispatch including transmission losses with a neat flowchart. (10)
Refer Section: 4.7
(ii) A generating unit has two 200 MW units whose input cost data is as
follows:
F1 0.004 P21 2.0P1 80 Rs/hr
F2 0.006 P22 1.5 P2 100 Rs/hr,
For a total load of 250 MW, find the load dispatch between the two units
for economic operation. (6)
Refer Example: 4.1
Or
(b) (i) Explain the priority list method for unit commitment problem.(10)
Refer Section: 4.10.1
15. (a) Discuss the functions of ‘SCADA’ in power system operation. (16)
Refer Section: 5.6
Or
(b) Enumerate the various operating states and the control strategies of a
power system. (16)
Refer Section: 5.22
Question Paper 23
Part B – (5 16 80 Marks)
11. (a) (i) A generating station has a maximum demand of 50,000 kW.
Calculate the cost per unit generated from the following data.
Capital cost Rs.95 106
Annual load factor 40%
Annual cost of fuel and oil Rs.9 106
Taxes, wages and salaries, etc Rs.7.5 106
Interest and depreciation 12% (12)
Refer Page No: 1.12
(ii) 1. Define ‘Diversity factor’. (4)
2. Define ‘Plant use factor’.
Refer Section: 1.8
Refer Section: 1.6 (h)
Or
(b) (i) Define the following: (6)
1. Hot reserve
2. Cold reserve
3. Spinning reserve.
(ii) A generating station has the following daily load cycle:
Or
(b) What are the components of speed governor system of an alternator?
Derive its transfer function with an aid of a block diagram. (16)
Refer Section: 2.2
13. (a) Describe various methods of voltage control and explain any three in
detail. (16)
Refer Section: 3.7
Or
(b) Draw the diagram of a typical automatic voltage regulator and develop
its block diagram representation. (16)
Refer Section: 3.4
14. (a) State the unit commitment problem. With the help a flow chart, explain forward
dynamic programming solution method of unit commitment problem. (16)
Refer Section: 4.10.2
Or
(b) The fuel inputs per hour of plants 1 and 2 are given as
F1 0.2 P21 40 P1 120 Rs/hr
F2 0.25 P22 30 P2 150 Rs/hr. Determine the economic operating schedule
and the corresponding cost of generation. The maximum and minimum
loading on each unit is 100 MW and 25 MW. Assume the transmission losses
are ignored and the total demand is 180 MW. Also determine the saving
obtained if the load is equally shared by both the units. (16)
Refer Example: 4.6
15. (a) (i) What is EMS? What are its major functions in power system
operation and control? (6)
Refer Section: 5.11
(ii) Draw a block diagram to show the hardware configuration of a SCADA
system for a power system and explain the application of SCADA in
monitoring and control of power system. (10)
Refer Section: 5.3
Or
(b) Explain the security monitoring using state estimation with necessary
diagrams. (16)
Refer Section: 5.6
26 Power System Operation and Control
Part B – (5 16 80 Marks)
11. (a) A power supply is having the following loads.
12. (a) Develop the state variable model of a two area system and State the
advantages of the mode.
Refer Section: 2.9.3
Or
(b) An isolated power system has the following parameters: Turbine rated
output 300 MW, Nominal frequency 500 Hz, Governor speed regulation
0.05 p.u, Inertia constant 5, Turbine time constant 0.5 sec. Governor
time constant 0.2 sec, Load change 60 MW. The load varies by 0.8% for
a 1% change in frequency. Determine the steady stat frequency deviation in
Hz.
Refer Example: 2.9
28 Power System Operation and Control
13. (a) The load at receiving end of a 3 phase overhead transmission line is
20 MW, 0.8 p.f lags at the line voltage of 33 KV. A synchronous compensator
is situated at receiving end and voltage at both ends of the lines is maintained
at 33 KV. Calculate the MVAR of the compensator. The line has resistance
and reactance of 5 /ph, 20 /ph
Refer Section: 3.5
Or
(b) Explain the Injection of reactive power by switched capacitors to
maintain the acceptable voltage profile and to minimize the transmission loss
in a power system.
Refer Section: 3.2
14. (a) A heat rate of 100 MW fuel fired generator is 10 Mkcal / MWhr at 25% rating
9 Mkcal / MWhr at 40% rating
8 Mkcal / MWhr at 100% rating.
Find (i) Fuel cost at 25, 40,100% loading
(ii) Incremental cost
(iii) Fuel input rate using quadratic approximation to deliver 101 M.W.
Refer Example: 4.16
Or
(b) Determine the priority list using full load average production cost for
the data given below.
Part B – (5 16 80 Marks)
Or
(b) Explain an overview of power system operation and control and the
role of computer in the implementation with the help of block diagram.
12. (a) Explain the load frequency control of a single area system.
Refer Section: 2.5
Or
(b) (i) Explain the speed load characteristics of speed governor system.
(ii) Two generators rated 200 MW and 400 MW are operating in parallel.
The droop characteristics of their governors are 4% and 5% respectively
from no load to full load. Assuming that the generators are operating at 50
Hz at no load how would a load of 600 MW be shared between them? What
will be the system frequency at this load? Assume free governor operation.
Also find the load sharing if both governors have a droop of 4%.
13. (a) With the help of a block diagram explain modelling of an excitation
system. Derive the transfer function of each block.
Refer Section: 3.4
Or
(b) Explain the different methods of voltage control.
14. (a) Derive the coordination equations for economic dispatch with and
without loss.
Refer Section: 4.10
Or
(b) (i) Create a unit commitment using the priority list method for the
following three units.
The fuel cost equations are as follows:
Unit 1: F1 P1 561 7.92 P1 0.001562 P21 150 P1 600
Unit 2: F2 P2 310 7.85 P2 0.00194 P222 100 P2 400
Unit 3: F3 P3 93.6 9.56 P3 0.005784 P23 50 P3 200.
Refer Example: 4.7
(ii) Explain forward dynamic programming approach for solving Unit
Commitment problem with a neat flow - chart.
Refer Section: 4.10.2
15. Explain the concept of energy control centre (or) load dispatch centre. Also
discuss its function.
Refer Section: 5.2
Or
(b) Explain the various operating states of power system. Also discuss the
state transitions and control strategies.
Refer Section: 5.22
32 Power System Operation and Control
2. What are the advantages of computer control in power system? What are
the types of computer control?
Refer Page No: 1.50
3. Find the open loop gain of an Automatic voltage regulator loop if the static
error does not exceed 2%.
Refer Page No: 2.86
5. Show that the shunt compensation improves critical voltage as well as the
power factor.
Refer Page No: 3.56
7. Find the incremental transmission losses for a two area power system, where
the bus voltages are kept fixed and the line power flow is a function of line
angle. Power loss is a function of generation of area B only.
Refer Page No: 4.68
Question Paper 33
Part B – (5 16 80 Marks)
11. (a) Compare various stochastical methods of load fore casting.
Refer Section: 1.10
Or
(b) Give a detailed account of online techniques for non-stationary load
prediction.
Refer Section: 1.10
12. (a) With the block diagram of speed governing system, explain the
Automatic Load Frequency Control. Also derive necessary equations.
Refer Section: 2.2
Or
(b) A sub-grid has total rated capacity 2500 MW. It encounters a load
increase of 50 MW if the normal operating load is 1000 MW. Assume inertia
constant (H) to be 5 sec and regulation of the generators in the system as
2 Hz/p.u. MW. Find (i) ALFC loop parameters (ii) Static frequency drop,
(iii) Transient response of the ALFC loop. Assume load frequency
dependency to be linear.
Refer Example: 2.10
13. (a) Derive the relation between voltage and real and reactive powers in a
transmission line. Explain the voltage profile variation along the line as the
reactive power varies.
Refer Section: 3.1
Or
(b) Discuss at length, the effect of transformer on load tap changing on
voltage stability.
Refer Section: 3.8
34 Power System Operation and Control
14. (a) Determine the economic operation point for the three thermal units
delivering a total load of 600 MW without considering generator limit as
well as with considering generator limit
Given:
Unit 1: maximum output 600 MW, minimum output 150 MW. The fuel
cost function is F1 P1 550 7.7 P1 0.00165 P21 Rs/hr
Unit 2: coal fired: maximum output 500 MW, minimum output 125 MW.
The fuel cost function is F2 P2 300 7.88 P2 0.002 P22 Rs/hr
Unit 3: coal fired: maximum output 600 MW, Minimum output 150
MW
The fuel cost function is F3 P3 80 7.99 P3 0.005 P23 Rs/hr .
Or
(b) What is priority list method of unit commitment? Explain it with an
example.
Refer Section: 4.10.1
15. (a) What is state estimation with respect to power system? Explain briefly
the method of maximum likelihood weighted least squares estimation.
Refer Section: 5.6
Or
(b) What is normal operating state of a power system? Describe in detail
the various states that a power system takes, with their operating conditions.
Refer Section: 5.22
Question Paper 35
PART - B 5 16 80 Marks
11. (a) Consider an inductive load of type Z R jX
Refer Example 1.15
11. (a) (i) By how much percentage the real load drop, if the voltage is
reduced by 5%?
11. (a) (ii) How would 2% drop in frequency affect the real load, if the load
power factor is 0.8. Derive the relations used. (16)
(Or)
11. (b) A power station has to meet the following load demands:
Load A:50 kW between 10 AM and 6 PM
Load B:30 kW between 6 PM and 10 PM
Load C:20 kW between 4 PM and 10 AM
Plot the daily load curve and determine (i) diversity factor, (ii) units
generated per day, (iii) load factor. (16)
50 30 20
70
Diversity factor 1.42
(ii) Units generated per day Area under the load curve
20 10 50 6 70 2 50 4 100 2
Average load
(iii) Load factor
Maximum deyand
Units generated per day
Average load
Hours in a day
1040
43.33
24
43.33
Load factor
70
12. (a) Draw the block diagram of uncontrolled two area ALFC system and
explain the salient features under static and dynamic conditions.
Refer Section. 2.8 (16)
(Or)
12. (b) (i) Determine the steady frequency in Hz for an isolated control area(8)
having the following data. Total rated area capacity, Pr 300 MW frequency,
f 50 Hz, inertia constant, H 5 s, regulation, R 0.05 pu, turbine time
constant 0.5 sec, governor time constant 0.2 sec, load change 60 MW.
The load varies by 0.8 percent for a 1 percent in frequency.
Refer Section 2.9
12. (b) (ii) Obtain the state variable model of single area ALFC system. (8)
Refer Section. 2.6
13. (a) Develop the block diagram of AVR and obtain its transfer function
and explain the static and dynamic response. (16)
Refer Section 3.4
(Or)
13. (b) Explain the role of tap changing transformer in voltage control. (16)
Refer Section 3.8
14. (a) Write the algorithm for interactive solution of economic dispatch
without and with losses co-ordinated (16)
Refer Section 4.4
(Or)
38 Power System Operation and Control
14. (b) (ii) Explain dynamic programming solution for unit commitment with
flowchart. (8)
Refer Section 4.10.2
15. (a) Briefly explain various functions of SCADA with a neat diagram. (16)
(Or)
15. (b) Draw a state transition diagram of a power system and explain the
different control actions. (16)
Refer Section 5.8