Module 2
Module 2
of ME
WORK STUDY
Method study
Work measurement
1
Dept. of ME
Work study used for job evaluation, motion analysis, lost time analysis capacity
planning error analysis, Layout of physical facilities etc. and find application in
4. Material handling
5. Design
7. Transport
8. Hospital
9, Army
Module-II
2
Dept. of ME
METHOD STUDY
1. SELECT
Economic considerations
Module-II
Technical considerations
3
Dept. of ME
Human considerations.
2. RECORD
ii. Flow process chart; Man type, Material type and Equipment type
(b) Diagrams
i) Flow diagrams
3. EXAMINE
The purpose, place and sequence of every operation should be critically
examined. This help will reveal defects in existing methods
4. DEVELOP
The most practical, economic and effective method, drawing on the
Module-II
4
Dept. of ME
5. EVALUATE
Different alternatives to developing a new improved method comparing the cost
effectiveness of the selected new method with the current method with the
current method of performance.
6. DEFINE
The new method, as a result, in a clear manner and present it to those
concerned, i.e. management, supervisors and workers.
7. INSTALL
The new method as a standard practice and train the persons involved in
applying it.
8. MAINTAIN
The new method and introduce control procedures to prevent a drifting back
to the previous method of work.
1. Operation
5
Dept. of ME
2. lnspection
3. Transport
5. Permanent storage
An equilateral triangle standing on its vertex represents storage. Storage takes
place when an object is stored and protected against unauthorized removal.
Ex: Raw material in the store room.
6. Combined activity
When two activities take place at the same time or done by the same
operator or at the same place, the two symbols of activities are combined
Ex: Reading and recording a pressure gauge. Here a circle inside square
represents the combined activity of operation and inspection
OPERATION PROCESS CHART (OUTLINE PROCESS CFIART)
It is also called outline process chart. Operation process chart uses only two
symbols, i.e., operation and inspection. Operation, process chart is helpful to:
(a) Visualise the complete sequence of the operations and inspections in the
Module-II
process.
6
Dept. of ME
(a) Material type- which shows the events that occur to the materials.
Module-II
7
Dept. of ME
Summary
Module-II
8
Dept. of ME
Summary
are recorded. It shows whether the two hands of the operator are idle or
9
Dept. of ME
moving in relation to one another in a time scale.That is, we know from the
chart what the two hands are doing at any given moment of time. The two-
handed process chart is generally used for repetitive operations
Fig shows the example of assembling of nut and bolt
Summary
10
Dept. of ME
Summary
Module-II
11
Dept. of ME
FLOW DIAGRAM
Process charts indicate the sequence of activities. They do not Show the
frequent movements of men and material. If this movement is minimized, a lot
of savings can be achieved in cost and effort. If the path of movement of
material is not frequent and simple, a flow diagram is used for recording the
movement. A flow diagram is a diagram which is drawn to scale. The relative
position of machineries, gang ways, material handling equipment etc. are drawn
first. Then the path followed by men or material is marked on the diagram.
Different movements can be marked in different colours. Process symbols are
added to the diagram to identify the different activities at different work
centres.
12
Dept. of ME
STRING DIAGRAM
We make use of flow diagram for recording the movement of men or material
when the movement is simple and the path is almost fixed. But when the
paths are many and are repetitive, it may not be possible to record them in
a flow diagram. Here a string diagram is used.
Applications
Module-II
13
Dept. of ME
Macroscopic motion
Macroscopic Motion
Ex:
Module-II
14
Dept. of ME
The first step or phase in micromotion study involves taking the motion
pictures of the activity on film while the activity is being performed by the
operator. The equipment required to take a film or video tape consists of
1. 16 mm movie camera
2. 16 mm film
This step of micromotion study involves film analysis is of the film of motion
pictures. The film run at normal speed using a projector, entire film is viewed
and typical work cycle is selected. The THERBLIGS after they have been
identified are entered in film analysis sheet. This frame by frame analysis of
the film permits the discernment of even very short delays and discovery of
undesirable movements.
Therbligs:
15
Dept. of ME
This is the third phase or step of micromotion study. Film analysis is made
in the second phase is entered in the film analysis sheet. Based on this
sheet SIMO chart (Simultaneous motions Cycle Chart) developed by Gilberth is
prepared.
SIMO chart is the graphical presentation of the limbs of the workman under
Module-II
study. lt is two handed chart which records the motions (Therbligs) of both
16
Dept. of ME
the hands on a common scale. A few motions of other limbs such as of eye
and body are also on this Chart. Fig. shows a typical SIMO chart
Advantages
1. lt is useful technique for very short cycle job
2. lt is a permanent record of motions performed by a worker which can be
made without disturbing the worker
3. lt can be used for training purpose
Limitations
1. lt is expensive
2. lt is not well suited for long cycle jobs
which have been developed as a result of experience and which forms the
17
Dept. of ME
basis for the development of improved methods at the workplace. These are
first used by Frank Gilbreth, the founder of motion study and further
rearranged and amplified by Barnes, Maynard and others.
The principles are grouped into three headings:
Arrangement of workplace.
When possible:
1. Both hands should begin and complete their movements at the same time.
2. The two hands should not be idle at the same time except during periods
of rest.
3. Motions of the arms should be made simultaneously.
4. Hand and body motions should be made at the lowest classification at
which it is possible to do the work satisfactorily.
5. Utilize momentum to assist the worker, wherever is possible
6. Continuous curved movements are to be preferred to straight line motions
involving sudden and changes in directions.
7. ‘Ballistic’ (i.e., free swinging) movements are faster, easier accurate than
restricted or controlled movements.
8. The work should be arranged to permit easy and natural rhythm wherever
possible
9. Work should be arranged so that eye movements are confined to
comfortable area, without the need for frequent changes of focus.
18
Dept. of ME
3. Gravity fed, bins and containers should be used to deliver the materials as
close to the point of use as possible.
4. Illuminate the workplace properly for adequate seeing and visual perception
5. Materials and tools should be arranged to permit the best sequence of
motions.
6. The height of the workplace and chair etc. should be such that worker
can either sit or stand comfortably
19
Dept. of ME
1. Stop watch
2. Time study sheets
3. Time study boards
4. Measurement instrument like steel rule, measuring type, pencil, calculator etc.
5. Time recording machine
6. Motion picture camera
Stop Watch
Stop watch is one of the important timing devices used for measuring the
time taken by a worker to complete a job. Stop watch used for time study
purpose should be very accurate and preferably graduated in decimals so that
it can record even upto 0.01 minute. It has two hands. Large hand revolves
at a speed of one revolution per minute and its dial is divided into 100
divisions. The small hand revolves at a speed of one revolutions in 30
minutes. Dial for this small hand is graduated in such a way that it enables
to read up to one minute.
20
Dept. of ME
Module-II
21
Dept. of ME
In addition to the above equipment, a time study expert should keep a pencil,
steel tape, a calculator etc.
Module-II
By using this machine, some errors of the stop-watch method are eliminated.
22
Dept. of ME
Observed time
This is the actual time observed by using a stop watch. The observed time
of an operation is the total of the elemental times. The time study for the
same job is conducted for a number of times. The average of the observed
times is calculated.
Basic time is the time taken by a worker with standard performance. Basic
time is calculated from the observed time by applying the rating factor.
Standard Time
Allowances
It is not possible for a worker to do his job continuously without any break.
There are many interruptions (stoppage of work) taking place. Extra time is
added to the basic time to compensate this interruption. This extra time given
is known as allowance.
Relaxation Allowance
Module-II
23
Dept. of ME
It depends on nature of the job. This includes personal needs allowances and
fatigue allowances of worker.
Process Allowance
24
Dept. of ME
In a shop, there may be small delays due to waiting for the inspector,
consulting the supervisor, Obtaining special tools etc. These delays are of very
short duration. The allowance given to compensate these delays is called
contingency allowance. Generally 5% of basic time is given as contingency
allowance.
When one worker is attending more than one machine, one or more machine
units remain idle while attendant is occupied with the work on other machine.
Interference allowance provided to compensate this idleness due to interference
Policy allowance
Problems:
Q-1
Allowances = 10%
Solution:
= 6 + (4x1.1)
=6+4.4=10.4min
Module-II
25
Dept. of ME
=10.4 + (10.4x10/100)
=10.4(1+0.1) = 11.44min
Q-2
The elemental times (in minutes) for cycles of an operation using a stop
watch are presented below
Calculate the standard time for the operation if
1. Elements 2, 4 are machine elements
2. For other elements the operator is rated at 110%
3. Total allowances are 15% of normal time
Solution:
26
Dept. of ME
Time study (Stop watch Techniques) - Stop watch time study is one of the
techniques of work measurement commonly used. Here we make use of a
stop watch for measuring the time.
27
Dept. of ME
Elements are also examined whether they are done in the correct method.
28
Dept. of ME
29
Dept. of ME
This study is done to find the time delay due to occasional elements. These
elements may occur at irregular intervals. Example: Tool grinding, setting tools
etc. There are chances of missing these elements in the stop watch time
study. Production study is conducted for a longer period-at least for half a
day or one shift. Production study is conducted just like ordinary stop watch
time study. But here the time for occasional elements alone is observed. The
timings for occasional elements are compared with the allowance already
included
Uses of Production study
1. To check the accuracy of time standards.
2. To make sure that all the ineffective elements are included in the time
study.
3. To observe the waiting time and other delays of operator.
4. To get the data for working out the contingency allowance.
5. When the output goes down, this study is conducted to find out the
reasons for it.
SYNTHESIS FROM STANDARD DATA
Synthesis is a work measurement technique to build up normal time for a
new job (at a defined level of performance) by adding element times collected
from previously held time studies on similar jobs having same elements as
possessed by new job. Time for all constant elements and variable elements
are collected from the time studies previously made. These are stored in a
file. This is called time standard data bank. So, the time for any operation
can be worked out without actually making the time study.
Steps to develop standard data
1. Collect all the possible details about the job. For example, material,
dimensions, method, conditions etc. The collected details should be reliable
2. Break the job into constituent into elements.
The operations are broken into a number of elements. Many operators in an
industry have several common elements. Example: starting the machine,
stopping the machine etc. Whenever these activities occur, they take the same
Module-II
duration of time. These elements are called constant elements. Time for some
30
Dept. of ME
elements vary proportionately with the speed, feed, length of out etc. in
machining operation. These elements are known as variable elements. Variable
elements and constant elements are separated.
2. Collect the elemental time for constant elements from the standard data
bank.
3. For variable elements, the elemental time can be found out by using the
charts and graphs.
4. As far as possible, select the approximate normal times for all the
elements involved in the operation, from the synthetic data or the standard
data
5. Estimate the various allowances like, personal and rest allowances, process
allowances and special allowances for each element
6. Verify the analysis of elements for selected job method and other
conditions
7. Add various allowances to the normal time for each element and sum up
all such times for fix the standard time for new job .
Advantages
1. The time calculated using standard data is more accurate than the stop
watch time study.
2. The process is very quick.
3. It possesses greater accuracy and scope of coverage
4. It is used for estimating the cost of production before actually producing. It
is used to offer quotation.
5. Standard data finds universal applications
Limitations
1. Collection of data bank is a costly affair.
2. It is applied only in larger industries.
3. The data bank should be updated periodically
31
Dept. of ME
This study is also known as work sampling or activity sampling. Here the
ratio of the delay time and working time to the total time of an activity is
found out. This is done by random (irregular) observations.
For example:
Number of observations made -150
Number of times m/c found working -120
Number of times m/c found idle-30
% utilization of machine = (120 /150) x 100 = 80%
% idle time of machine (30 / 150) x 100 = 20%
Procedure
1. Define the problem- state the main objectives or purpose of problem,
describe the details of each element to be measured
2. Obtain the approval of the in charge of the department in which study is
to be made. Obtain the co-operation of the operators to be studied and they
should also understand the purpose of study _
3. Determine the desired accuracy of the final results in the form of standard
error or percentage
4. Sate the confidence level
5. Make a preliminary estimate of the percentage occurrence of the activity or
delay to be measured for one day or two days. This may be estimated on
the basis of past experience
6. Design the study. Determine the number of Observation to be made, days
or shifts needed for the study, Route to be followed by observer, design the
observation form etc.
7. Make the observation and record the data
8. Check the accuracy or precision of the data at the end of the study
9. Prepare the report and state results. If required make recommendations
Applications
1. Long cycle operations.
2. Activities where time study is not possible.
3. Estimate the percentage utilization of machine tools, cranes, trucks etc.
Module-II
32
Dept. of ME
Advantages
1. Activities which cannot be studied by stop watch time study can be
observed.
2. Cost of the study is less.
3. A single study man can observe several machines and operations.
4. This study is not a continuous study. So lesser time is spend on the
study.
5. The study will not interrupt the production.
6. The operators do not feel that they are closely watched by study man. So
they work freely.
7. Trained study man is not required.
8. Calculation is easy.
9. No equipment-Stop watch or other devices are not needed.
Limitations
1. This is economical only when the study is made in a wide area. i.e,
group of machines or group of operators.
2. This is not suitable for short cycle repetitive operations.
3. This is not a detailed study.
33
Dept. of ME
Table preparation
A table is provided for each motion. Depending upon different characteristics
of a motion, the time can be read from the table.
Groups of average workmen (by age, physical attributes, temperament) were
selected and placed under laboratory conditions (average heat, light atmospheric
conditions etc.). These work men were made to perform a wide variety of
motions which were filmed with a cine camera at 16 frames per sec. These
films were Later exhibited using a constant speed projector to a group of
highly qualified industrial engineers who rated the films. The net result of
these experiments were the development of MTM tables for the time values
for all the basic motions performed by a human body. There are 10 MTM
tables, 9 of which provide the time for various types of motions. The
originators of MTM used the smallest or basic time measurement unit as
0.0006 minute. This basic time unit is called time measurement unit (TMU)
1TMU=0.0006 minute
Advantages of MTM
1. Time standard for a job can be arrived at without going to the place of
work.
Module-II
34
Dept. of ME
Limitations
MTM can deal only with manual motions of an operation.
ANALYTICAL ESTIMATING
Setting the time standards for long and non-repetitive operations by stop watch
method are uneconomical. Analytical estimating technique determines the time
values for such jobs either by using the synthetic data or on the basic of
the past experience of the estimator when no synthetic or standard data is
available. In order to produce accurate results the estimator must have
sufficient experience of estimating, motion study, time study and the use of
synthesized time standards.
Procedure
The various procedural steps involved in analytical estimating are:
1. Select the estimator
2. Find out job details which include job dimensions, standard procedure and
especially the job conditions, i.e., poor illumination, high temperatures,
hazardous environments, availability of special jigs, fixtures or tooling,
condition of materials, etc.
3. Break the job into constituent elements.
4. Select the time values for as many elements possible from the data bank
(i.e., synthetic data).
5. To the remaining elements for which no synthetic data is available, usually
the estimator gives suitable time values from his past knowledge and
experience.
6. Add up all time values to get total basic time at 100% rating
7. In analytical estimating, relaxation allowance is not added to individual
elements. Add relaxation allowances (10 to 20%) to basic time.
8. Any other allowance is added above to get standard time
Module-II
Advantages
35
Dept. of ME
Limitations
The estimate will not be accurate.
Application
Analytical estimating is used for non-repetitive Jobs, jobs involved times and
the jobs having elements of variable nature.
(April-2018)
1. What is therbligs
2. Explain Flow diagram
3. Explain the advantages of work study
4. Explain the procedure for conduct of method study
5. Explain the work sampling and its needs
6. Explain work measurement and its objectives
7. Explain the terms MTM, Synthesis using the standard data and analytical
estimating
(Oct-2017)
36
Dept. of ME
(Oct-2016)
(March-2015)
1. Define work sampling
2. Explain two handed process chart with the help of example
3. Define method study. Explain the procedure for Method study
4. List the principles of motion economy concerning human body
5. Explain the different types of sampling techniques used
6. An Industrial job involves 4 operations. Related data is given below. Rest
and personal allowances are 10% and contingencies are 2% of the basic
time. Find the standard time for completing the job Module-II
37
Dept. of ME
(March-2014)
1. Expand the letters in SIMO chart
2. Illustrate and explain String diagram
3. Name and show the process charts Symbols. Define and illustrate a two
handed process chart for any simple job
4. Explain the principle of motion economy
5. Explain the procedure for stop watch time study ‘. Explain the applications
of work sampling
(March-2013)
1. Draw the symbols used in process chart for Transportation, Operation,
Delay and storage
2. State the basic procedure of method study
3 What is flow process chart? Briefly explain three types of flow process
chart
4. State the applications of work sampling.
5. Explain SIMO chart with an example
6. The mean observed time and rating factor for the five elements of a job
are as follows
(Oct-2012)
38
Dept. of ME
4. Explain about flow process chart for material type and operator type with
illustration
5. Explain the construction of SIMO chart with a simple example
6. What is work measurement? Explain the systematic method of work
measurement
7. Explain the procedure for work sampling
Module-II
39