Question 1 of 21
Kumar adds a "finish no later than" date constraint to his schedule. Two activities now show that they will finish later than the
project complete milestone. How can he address this negative slack?
Change the critical threshold setting to the lowest total slack value in the schedule.
Rework the dates for all the activities on the critical path in the schedule.
Redefine which tasks in the schedule are on the critical path and which ones are not.
Question 2 of 21
Maurice creates a baseline for his project schedule in order to _____ .
Question 3 of 21
What does it mean if an activity's total float is greater than zero?
The activity is on the critical path, and its delay will delay the project finish.
Question 4 of 21
Rajesh notices that the developer on his project has worked 25 fewer hours than planned. What should he do?
https://www.linkedin.com/learning/exams/summative/courses/project-management-foundations-schedules-2/results 1/6
07/01/2025, 14:50 Summative Exam: Results | LinkedIn Learning
Question 5 of 21
If the predecessor in a start-to-start dependency ends very late, what problem arises?
The successor finish date is delayed based on the predecessor's finish date.
The successor and the rest of the critical path are delayed, which delays the project finish date.
Question 6 of 21
What is the advantage of applying contours to activities in project schedules?
Question 7 of 21
If you're willing to accept some additional risk, _____ is an easy way to shorten the project schedule.
crashing
over-allocating resources
fast-tracking
reducing scope
Question 8 of 21
As Kat works on her project schedule, she asks colleagues to provide optimistic, pessimistic, and most likely estimates for some
of the activities. Which estimating method is she using?
https://www.linkedin.com/learning/exams/summative/courses/project-management-foundations-schedules-2/results 2/6
07/01/2025, 14:50 Summative Exam: Results | LinkedIn Learning
PERT
Delphi
Historical
Question 9 of 21
When Hal is estimating timing for his project activities, which approach would he begin with?
detailed
iterative
mid-range
Question 10 of 21
Which variables will Annika use when assigning resources to activities on her project schedule?
Question 11 of 21
Alex needs to break down his project into work packages. What do these represent in a work breakdown structure?
lowest-level deliverables
high-level deliverables
smallest activities
Question 12 of 21
In the project Brook is managing, a short and very important activity is scheduled to occur midway through a long activity. The
same resource is assigned to both. Which type of adjustment works best to resolve the overallocation in this situation?
https://www.linkedin.com/learning/exams/summative/courses/project-management-foundations-schedules-2/results 3/6
07/01/2025, 14:50 Summative Exam: Results | LinkedIn Learning
delaying
replacing resources
splitting
fast-tracking
Question 13 of 21
Haley determines that when the course outline is complete, the online template can be created. How should she define the
dependency type between these two activities for her project schedule?
finish-to-start
start-to-start
finish-to-finish
Question 14 of 21
Fiona's project team includes a part-time programmer who works mornings. Due to others' availability, she has a status
meeting for the entire team scheduled in the afternoon. What should she do?
Take notes so the programmer knows what was covered during the meeting.
Ask the part-time programmer whether they can work when the meeting is scheduled.
Question 15 of 21
Jamal's project team is not yet in place, but he is working on his project schedule. How can he show the project's resource
requirements?
Question 16 of 21
Why might Maria decide to add milestones to each reporting period in her project?
https://www.linkedin.com/learning/exams/summative/courses/project-management-foundations-schedules-2/results 4/6
07/01/2025, 14:50 Summative Exam: Results | LinkedIn Learning
to see progress
to save time
to stay on schedule
Question 17 of 21
Sylvia is developing several schedules for a large, complicated project. Which type of schedule would she share with
stakeholders to provide them an overview of the work?
a detailed schedule
a hybrid schedule
a summary schedule
Question 18 of 21
Nyala has several tasks for project meetings in her schedule. Which resource assignment variable should she specify as fixed?
resource allocation
assigned resources
work
duration
Question 19 of 21
Jiaying's stakeholders indicate that their project must finish one week earlier than scheduled. Which tasks should she focus on
crashing in order to shorten the schedule?
Question 20 of 21
Geoffrey is told to bring down the cost of the project, even if it takes longer to complete. What is one way he can do this?
https://www.linkedin.com/learning/exams/summative/courses/project-management-foundations-schedules-2/results 5/6
07/01/2025, 14:50 Summative Exam: Results | LinkedIn Learning
Eliminate overtime.
Question 21 of 21
What is the benefit to Jorge when he defines activities for his project schedule?
English (English)
Return to course
About
Become an Instructor
Help
Privacy & Terms
Accessibility
Apps
https://www.linkedin.com/learning/exams/summative/courses/project-management-foundations-schedules-2/results 6/6