Tutorial 4
Tutorial 4
Resource Leveling
Q1
In the following table, task durations are
given in weeks. The estimates were made
at the 95% level.
a. Find the expected time and variance
for each task
b. Draw the network (either AOA orAON)
and find the critical path and time.
c. Find the probability that the critical
path will be completed in 23 weeks.
d. What is the probability that the entire
network will be completed in 23 weeks.
Q2
Using the network below and resource tables that follow, schedule
the project based on resource constraint. A B
1 4
Activity Resource Rate/Day
A 10
B 7
C 5 C E
3 6
D 4
E 8
Maximum Available 12
Resource D
2
All relationships between the activities are finish-to-start and the lags are zero.
You are asked to
1. Update the schedule based on the resource constraint (a bar chart schedule). 3