The document contains a series of certification questions related to the SAP Activate Project Manager certification, specifically for the C_ACT_2403 exam. It includes a total of 410 questions covering various topics such as implementation phases, Scrum methodologies, project management, and SAP tools. Each question is followed by the correct answer and an explanation, providing a comprehensive overview of the knowledge required for the certification.

Uploaded by

ak545
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
100% found this document useful (1 vote)
802 views263 pages

C Act 2403

The document contains a series of certification questions related to the SAP Activate Project Manager certification, specifically for the C_ACT_2403 exam. It includes a total of 410 questions covering various topics such as implementation phases, Scrum methodologies, project management, and SAP tools. Each question is followed by the correct answer and an explanation, providing a comprehensive overview of the knowledge required for the certification.

Uploaded by

ak545
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 263

Certification Questions

C_ACT_2403
SAP Activate Project Manager Questions

Total Questions - 410


Question: 1

During which phase of a new implementation of SAP S/4HANA on Premise is the


Development system installed and technically configured, as well as Scope Items activated
based on results form Fit-Gap workshops?

1.) Explore
2.) Realize
3.) Prepare
4.) Deploy
5.) Discover

Correct Answer: 1

Explaination:

Question: 2

Which of the following statements are true for Scrum of Scrums meetings? (3 Correct)

1.) They do not need to be time boxed to 15 minutes.


2.) They allow teams to discuss their work, focusing especially on areas of overlap and
integration.
3.) They are problem-solving meetings
4.) They need to be held daily.

Correct Answer: 1,2,3


Explaination:

Question: 3

The duration of a Building Sprint should be between 2 and 4 weeks

1.) TRUE
2.) FALSE

Correct Answer: 1

Explaination:

Question: 4

Which of these are Workstreams of the SAP Activate Methodology? (4 Correct)


1.) Development
2.) Customer Team Enablement
3.) Testing
4.) Project Management
5.) Migration
6.) Design and Configuration

Correct Answer: 2,3,4,6

Explaination:

Question: 5

During a new implementation of SAP S/4HANA on Premise sizing exercises are important to
estimate hardware budget.

1.) FALSE
2.) TRUE

Correct Answer: 2
Explaination:

Question: 6

The SAP Solution Implementation Methodology includes a sequence of actions based on


methodological elements, PMBOK content, and open-source tools.

1.) FALSE
2.) TRUE

Correct Answer: 1
Explaination:

Question: 7

In a new implementation of S/4HANA Cloud Multi-Tenant Edition during the Realize phase
the Starter System shutdown is automatically initiated after requesting a P-System.

1.) FALSE
2.) TRUE

Correct Answer: 2
Explaination:

Question: 8

What is a correct statement for the product owner?

1.) The product owner is the project customer, and defines the requirements and priorities
of the project.
2.) The product owner has the authority to to terminate any development sprint in cases
where non resolvable issues arise or the workload proves to be inadequate.
3.) The product owner is responsible for making sure that everyone follow the Scrum rules.
4.) The product owner is the team leader, who is responsible for moderating meetings,
producing documentation, and resolving any isssues during the project.

Correct Answer: 1
Explaination:

Question: 9

What are outputs of the SAP Transformation Navigator? (3 Correct)

1.) Transformation Guide


2.) Software Guide
3.) Extension Guide
4.) Implementation Guide
5.) Technical Guide
6.) Business Guide

Correct Answer: 1,5,6


Explaination:

Question: 10

The Sprint Review meetings purpose is to continously improve the Scrum process using
lessens learned from the sprint execution.

1.) FALSE
2.) TRUE

Correct Answer: 1
Explaination:

Question: 11

In the System conversion to SAP S/4HANA Deploy phase, which of the following tasks are
included?

1.) Scheduling project plan


2.) Interface setup
3.) Final Testing
4.) Hyper Care support

Correct Answer: 3
Explaination:

Question: 12

Via which media does SAP provide Ready-to-run system for SAP S/4HANA deployment? (2
Correct)

1.) Blu-ray disks


2.) SAP App Center
3.) SAP Cloud Appliance Library
4.) SAP Solution Builder tool

Correct Answer: 1,3


Explaination:

Question: 13

Which end to end turn-key Application Lifecycle Management (ALM) solution can support
you in managing requirements and software development for large, Agile projects?

1.) Focused Build


2.) Solution Manager Test Suite
3.) Change Request Management
4.) Requirement Management

Correct Answer: 1
Explaination:

Question: 14

What is an Epic in the product backlog?

1.) A description of desired functionality told from the perspective of the user or customer.
2.) A large user story, typically a process or Scenario
3.) A collection of related user stories

Correct Answer: 2

Explaination:
Question: 15

Which of these are SAP Solution Manager 7.2 Value Chains? (4 Correct)

1.) Invoice to Pay


2.) Detect to correct
3.) Request to Fulfill
4.) Requirement to Deploy
5.) Order to Cash
6.) Portfolio to Project

Correct Answer: 2,3,4,6


Explaination:
Question: 16

Which Artifacts belong to the Requirement to Deploy value chain of SAP Solution Manager
7.2? (2 Correct)

1.) Work Package


2.) Project
3.) Test Case
4.) Service Request
5.) Incident

Correct Answer: 1,3

Explaination:

Question: 17

What's the Release cycle of S/4HANA Cloud Single-Tenant Edition?

1.) 2 Releases in 3 years


2.) Bi-Yearly Releases
3.) Quarterly Releases
4.) Monthly Releases
5.) Yearly Releases

Correct Answer: 1
Explaination:

Question: 18

What is the correct order of project lifecycle steps for a new implementation of S/4HANA
Cloud Multi-Tenant Edition?

1.) 1. Experience Trial 2. Setup and Enablement 3. Solution Validation and Delta Design 4.
Configure, develop 5. Migrate, Integrate, Extend, Test 5. Onboard and Deploy 6. Operate,
Monitor, Support
2.) 1. Setup and Enablement 2. Experience Trial 3. Fit-to-Standard 4. Configure 5. Migrate,
Integrate, Extend, Test 5. Onboard and Deploy 6. Operate, Monitor, Support
3.) 1. Experience Trial 2. Setup and Enablement 3. Fit-to-Standard 4. Configure 5. Migrate,
Integrate, Extend, Test 5. Onboard and Deploy 6. Operate, Monitor, Support

Correct Answer: 3

Explaination:
Question: 19

What’s the deciding factor for priorisation?

1.) Business Value


2.) Resource Availability
3.) Development Effort
4.) Time Effort

Correct Answer: 1

Explaination:

Question: 20

When does the Scrum Team receive formal confirmation that the User Stories are
completed to the satisfaction of the Product Owner?

1.) During the Sprint Review


2.) During the Sprint Retrospective
3.) During the User Acceptance Test
4.) During the daily Scrum meeting

Correct Answer: 1
Explaination:

Question: 21

Which of the following regarding elements of the SAP Activate Implementation Framework
is true? (2 Correct)

1.) Tools are part of a project infrastructure. They provide the team with an interface to
access and manage information (migrate data, interact with global SAP Communities,
access ready-to-use content, configure the SAP S/4HANA system, and so on).
2.) The SAP Solution Implementation Methodology combines: - Core and supporting
methodological elements - A sequence of actions based on methodological elements, SAP
content, and SAP Tools - Foundation for Quality Assurance services - Foundation for SAP
Associate Project Manager certification
3.) Regarding the content SAP Best Practices provide projects with a full configuration and
Ready-to-run systems provide projects with a productive system.

Correct Answer: 1,2


Explaination:

Question: 22

What are available target solutions for the transition path Selective Data Transition? (2
Correct)

1.) SAP S/4HANA On Premise


2.) SAP S/4HANA Cloud Single-Tenant Edition
3.) SAP S/4HANA Cloud Multi-Tenant Edition

Correct Answer: 1,2


Explaination:

Question: 23

For On Premise deployments SAP provides Ready-to-run systems on the following media: (2
Correct)

1.) Through Dropbox


2.) Through SAP Cloud Appliance Library
3.) Blu-ray Disks
4.) USB-Drive
5.) Floppy Disk

Correct Answer: 2,3


Explaination:

Question: 24

In a new implementation of S/4HANA Cloud Multi-Tenant Edition the Q-System includes


configuration and master data for selected cloud solutions for targeted enablement of the
project team on SAP standard processes and to be the host environment of the Fit-to-
Standard Workshops

1.) TRUE
2.) FALSE

Correct Answer: 2
Explaination:

Question: 25

What is the first step in writing a user story?

1.) Answering the question of how.


2.) Answering the question of what.
3.) Answering the question of who.

Correct Answer: 3

Explaination:

Question: 26

What are key measures of the Data Volume Management? (4 Correct)


1.) Data Deletion
2.) Data Cleansing
3.) Data Avoidance
4.) Data Archiving
5.) Data Summarization

Correct Answer: 1,3,4,5

Explaination:

Question: 27

New backlog items can be added to the sprint during the execution of the sprint.

1.) FALSE
2.) TRUE

Correct Answer: 1
Explaination:

Question: 28

What are major accelerators for the Integration Workstream in the Realize Phase?

1.) Interface register template


2.) Interface Functional Specification Template
3.) Technical Specification - Enhancements Template
4.) Interface Documentation in SAP Solution Manager 7.2

Correct Answer: 3

Explaination:
Question: 29

What's used to customize / configure during a new implementation of S/4HANA Cloud


Single-Tenant Edition?

1.) IMG
2.) SSCUI's

Correct Answer: 1

Explaination:

Question: 30

What is the difference between the “New implementation of SAP S/4HANA Cloud” and the
“New Implementation of SAP S/4HANA” transition path? Note: There are 2 correct answers
to this question. (2 Correct)

1.) Different sets of workstream are used for these transition paths.
2.) There are different roles in the Application Design and Configuration workstream.
3.) Upgrade of SAP S/4HANA Cloud are managed by SAP, and upgrades of SAP S/4HANA
are managed by the customer.
4.) SAP S/4HANA uses the implementation Guide(IMG) and the in-App Extensibility Option
for configuration and development, and SAP S/4HANA Cloud uses SSCUIs and the Side-by-
Side Extensibility Option.

Correct Answer: 3,4


Explaination:

Question: 31

What tool is used for the SAP Activate Transition Path Selective Data Transition?

1.) Software Update Manager


2.) SAP S/4HANA Migration Cockpit
3.) SAP Landscape Transformation

Correct Answer: 3

Explaination:
Question: 32

What is the correct description for the Prepare Phase?

1.) During the Prepare phase the project team will use an agile approach to iteratively and
incrementally build the functionality from the backlog. This build follows the prioritization
given by the product owner that continues to be involved with the project during the
sprints.
2.) In the Prepare phase, we define project governance, start teh project, define/identify the
resources, define the roles and responsibilities for the project team, and detail the
management plans for running the project.
3.) In the Prepare phase, we run the Fit/Gap analysis on the working system with the best
practices content up and running. The objective of the Prepare phase is to identify the fit of
the best practices based solution, capture delta configuration requirements, identify gaps,
and configuration values. All these are captured by the project team in the backlog and
later, in Realize phase the backlog items are implemented in the system. The best practices
content is used as a jump-start for the project.

Correct Answer: 2

Explaination:

Question: 33

Solution Validation and Delta Design Workshops are part of a new implementation of
S/4HANA Cloud Multi-Tenant Edition

1.) FALSE
2.) TRUE

Correct Answer: 1
Explaination:

Question: 34

How do you achieve frequent checkpoint with the End User in an Agile Delivery Approach?
(2 Correct)

1.) Demo the Model Company


2.) Solution Review for Waves
3.) Solution Demo for Sprints
4.) User Acceptance Test

Correct Answer: 3,4


Explaination:

Question: 35

The Fit-to-Standard and Solution Definiton Workshop are part of the Prepare Phase

1.) FALSE
2.) TRUE

Correct Answer: 1
Explaination:
Question: 36

What is the product backlog NOT? (3 Correct)

1.) Design documentation


2.) List of activities how to transform requirements into product
3.) Dynamic prioritized requirements list
4.) Requirements specification with loads of details

Correct Answer: 1,2,4

Explaination:

Question: 37

What are Scrum Master Tasks during Project Preparation? (3 Correct)

1.) Ensures development environment is available


2.) Ensures project set-up is done correctly and completely
3.) Ensures management or others do not influence team for sprint / project work
4.) Ensures team enters remaining effort daily
5.) Ensures rough architecture and high-level requirements are available

Correct Answer: 1,2,5


Explaination:

Question: 38

Product Backlog is simply a list of all all things that needs to be done within the project. It
replaces the traditional requirements specification artifacts.

1.) FALSE
2.) TRUE

Correct Answer: 2

Explaination:

Question: 39
What's true regarding the characteristics of S/4HANA Cloud Single-Tenant Edition? (4
Correct)

1.) On Premise Edition Scope


2.) Full support for On Premise integration scenarios?
3.) Full IMG configuration possibilities
4.) Modifications of SAP Standard Coding is available
5.) Full SAP S/4HANA extension possibilities

Correct Answer: 1,2,3,5

Explaination:

Question: 40

Which of the following tools are specific to the Data Management Workstream? (3 Correct)

1.) SAP Data Services


2.) SAP Landscape Transformation
3.) SAP S/4HANA Migration Cockpit ( for both SAP S/4HANA Cloud and SAP S/4HANA edition)
4.) SAP Solution Manager
5.) SAP Roadmap Viewer

Correct Answer: 1,3,4


Explaination:
Question: 41

In a new implementation of S/4HANA Cloud Multi-Tenant Edition during the Explore phase
which kind of workshops is conducted?

1.) Fit Gap Workshop


2.) Fit-to-Standard Workshop

Correct Answer: 2

Explaination:

Question: 42

What are the responsibilities of the Product Owner in Release and Sprint Planning? (2 Correct)

1.) Analyze the functional and technical dependencies between User Stories
2.) Eliminate the backlog User Stories
3.) Prioritize backlog User Stories by business priority
4.) Define objective for each Release

Correct Answer: 3,4


Explaination:
Question: 43

Which of the following are part of the 10 SAP Quality Principals? (2 Correct)

1.) Start scoping early


2.) Achieve production readiness
3.) Plan one phase at a time
4.) Use standard functionality optionally

Correct Answer: 1,2

Explaination:

Question: 44

What is part of the SAP Activate Project Library content for SAP S/4HANA? (2 Correct)

1.) Ready-to-run systems


2.) Project Plan
3.) SAP Best Practices
4.) Accelerators
5.) System Content
6.) Guidance

Correct Answer: 2,4


Explaination:

Question: 45

What are the supported approaches for SAP Landscape Transformation? (3 Correct)

1.) System consolidation


2.) Selected Business Unit migration
3.) Selected Applications migration
4.) Hardware migration

Correct Answer: 1,2,3


Explaination:

Question: 46

What are IT responsibilities during Release Planning? (2 Correct)

1.) Prioritize Product Backlog


2.) Estimate Product Backlog
3.) Analysis of Technical Dependencies
4.) Define Product Backlog

Correct Answer: 2,3


Explaination:

Question: 47

What does the Content element of SAP Activate provide? (3 Correct)

1.) End-User guides


2.) Integration Content
3.) Business Processes Content
4.) Migration Content
5.) Functional Specification for WRICEF development

Correct Answer: 2,3,4


Explaination:

Question: 48

What are main categories in regards to security tasks and responsibilities? (4 Correct)

1.) Secure Setup


2.) Secure Code
3.) Secure Operation
4.) System Architecture
5.) Security Compliance

Correct Answer: 1,2,3,5

Explaination:
Question: 49

Which of these are SAP Project Roles of the Implementation Partner in the Project
Management Workstream? (4 Correct)

1.) Quality Manager


2.) Project Manager
3.) Development Lead
4.) Project Administrator
5.) Project Sponsor

Correct Answer: 1,2,4,5

Explaination:

Question: 50

The recommended landscape for a new implementation of SAP S/4HANA On Premise is


three tiered (DEV, QAS, PRD)

1.) FALSE
2.) TRUE
Correct Answer: 2

Explaination:

Question: 51

The Daily Stand-up Meeting purpose is to solve problems.

1.) TRUE
2.) FALSE

Correct Answer: 2
Explaination:

Question: 52

The goal of the firm-up sprint is to ensure integration of the Product Increments delivered
within previous Build Sprints

1.) FALSE
2.) TRUE

Correct Answer: 2
Explaination:

Question: 53

In a system conversion Simplification Item Checks (SI-Check) are based on Simplification


Item Catalog provided through SAP Support Portal. Custom Code analsyis tools in SAP
Netweaver 7.5 compare custom code in SAP ERP with Simplification Catalog Items and
provide guidance on custom code adoption, technical and functional implications and check
consistency of configuration and data.

1.) TRUE
2.) FALSE

Correct Answer: 1

Explaination:
Question: 54

Which of the following are Analytics and Reporting options? (4 Correct)

1.) SAP IDM


2.) SAP GRC
3.) SAP ACR
4.) Digital Boardoom
5.) SAP S/4HANA Embedded Analytics
6.) SAP BW/4HANA

Correct Answer: 3,4,5,6

Explaination:
Question: 55

Sprint Execution is the period during which the task-level work is performed by the
development team to complete the features committed to during sprint planning.

1.) TRUE
2.) FALSE

Correct Answer: 1

Explaination:

Question: 56

What's the recommended choice for On Premise-to-On Premise Integrations scenarios?

1.) SAP Process Orchestration


2.) SAP Cloud Platform Integration

Correct Answer: 1
Explaination:

Question: 57

Which test confirms that new functionalit is not causing defects in existing functionality?

1.) Unit Test


2.) Integration Test
3.) User Acceptance Test
4.) Regression Test
5.) String Test

Correct Answer: 4
Explaination:

Question: 58

What are correct statements regarding the Transition Path Selective Data Transition? (2
Correct)

1.) Migrate a selection of data


2.) Avoid full redesign SAP ERP processes and reuse SAP ERP processes, but rather re-use
some parts and redesign some other parts
3.) Reengineering and process simplification based on latest innovations
4.) Performing initial data load
5.) Implementing innovative business processes with pre-configured content on a new
platform

Correct Answer: 1,2

Explaination:
Question: 59

The backlog represents the list of requirements that have not been built during the baseline
build but need to be delivered to business. The Scrum team will prioritize the list once it ist
completed. It is important to capture all requirements before focusing on prioritization.

1.) TRUE
2.) FALSE

Correct Answer: 2

Explaination:

Question: 60

SSCUI's provide customers with access to SAP S/4HANA On Premise configuration.

1.) FALSE
2.) TRUE

Correct Answer: 1
Explaination:

Question: 61

What is the most granular level of the methodology you can view in SAP Roadmap Viewer?

1.) Deliverables
2.) Task
3.) Scenario
4.) Phase

Correct Answer: 2
Explaination:

Question: 62

Which kinds of extensibility are available on-premise? (2 Correct)

1.) Managed Extensibility


2.) Classic Extensibility
3.) Key User Extensibility

Correct Answer: 2,3


Explaination:

Question: 63

In which step during the selective data transitioning is the transformation assessment
happening?

1.) Prepare
2.) Realize
3.) Deploy
4.) Discover
5.) Explore

Correct Answer: 1
Explaination:

Question: 64

Which of the following are SAP DevOps Tools? (3 Correct)

1.) Jira
2.) CSOL
3.) ChaRM
4.) TDMS
5.) SAP Code Inspector

Correct Answer: 2,3,4


Explaination:

Question: 65

In which phase are the most important activities in the Customer Team Enablement
Workstream performed?
1.) Deploy
2.) Realize
3.) Explore
4.) Discover
5.) Prepare
6.) Run

Correct Answer: 5

Explaination:

Question: 66

What’s the Scrum of Scrums?

1.) Problem Solving Meeting


2.) Integration Meeting
3.) Planning Meeting
4.) Review Meeting

Correct Answer: 2
Explaination:

Question: 67

Who decides on the content of a sprint?

1.) Scrum Master


2.) Project Manager
3.) Scrum Team
4.) Product Owner

Correct Answer: 4
Explaination:

Question: 68

What are the benefits of the Ready-to-use Content? (3 Correct)

1.) Simple on-boarding to cloud


2.) Predictable results
3.) Fixed organizational structure
4.) Reduced functional scope
5.) Fast time to value

Correct Answer: 1,2,5


Explaination:

Question: 69

ALM Processes and tools shall be implemented as part of the Project Infrastructure before
which phase?

1.) Run
2.) Realize
3.) Explore
4.) Discover
5.) Deploy
6.) Prepare

Correct Answer: 3
Explaination:

Question: 70

Ready to use Content in SAP Activate includes which of the following? (2 Correct)

1.) SAP Best Practices


2.) Project Accelerators
3.) Courses delivered by SAP Education
4.) Business models from leading companies in each industry sector

Correct Answer: 1,2

Explaination:
Question: 71

SAP Solution Manager Focused Build is a powerful solution for Service Providers and larger
customers who want to manage all their systems in a central, scalable, and automated
environment.

1.) TRUE
2.) FALSE

Correct Answer: 2

Explaination:

Question: 72

What are the responsibilities and tasks of the Scrum Master? (4 Correct)

1.) Though leadershop in technical excellence of delivery of the functionality


2.) Accepts or rejects work results.
3.) Act as a guide in helping the team to adhere to Scrum principles and practices
4.) Protects the team from bureaucracy and non-value added activities
5.) Help team develop and adopt practices facilitating agile project execution

Correct Answer: 1,3,4,5


Explaination:
Question: 73

What are substreams of the Solution Adoption Workstream? (3 Correct)

1.) Value Management


2.) Quality Assurance
3.) Organization Change Management
4.) End User Training
5.) Project Management Office

Correct Answer: 1,3,4

Explaination:

Question: 74

What is the purpose of the Solution Validation activity on the Explore phase? (3 Correct)

1.) Challenges changes to standard


2.) Identify gaps
3.) Verify technical installation
4.) Log additional scope items
5.) Educate project participants.

Correct Answer: 1,2,4


Explaination:

Question: 75

Which of these are content provisioning tools? (5 Correct)

1.) openSAP
2.) KPI Catalog
3.) SAP Best Practice Explorer
4.) SAP Fiori App Reference Library
5.) SAP Solution Manager
6.) SAP Roadmap Viewer

Correct Answer: 1,2,3,4,6

Explaination:
Question: 76

For solutions with limited in-App extensibility Solution Validation (Workshop A) is named
Fit-to-Standard Workshop and Delta Design (Workshop B) is called Solution Definition.

1.) FALSE
2.) TRUE

Correct Answer: 2

Explaination:
Question: 77

During the Discover phase of a new implementation of SAP S/4HANA on Premise to


Customer Team shall be trained in business Processes, which are part of the pre-configured
solution selected for Fit-Gap Analysis.

1.) FALSE
2.) TRUE

Correct Answer: 1
Explaination:
Question: 78

What are approaches for System Conversion to SAP S/4HANA? (3 Correct)

1.) Near-Zero Downtime Technology (NZDT) approach for further reduction of downtime
based on a consulting service project
2.) Downtime-optimized conversion approach using SUM and reduced downtime by moving
data conversion partly to uptime
3.) Standard approach using Software Update Manager (SUM) with several optimizations

Correct Answer: 1,2,3

Explaination:

Question: 79

Which of the following are levels in the structure of an SAP Best Practices Solution
Package? (2 Correct)

1.) Business Process Scenarios


2.) Scope Items
3.) Configuration Guides
4.) Building Blocks

Correct Answer: 2,4


Explaination:

Question: 80

Which workstreams are part of the SAP Activate Methodology? (5 Correct)

1.) Data Management


2.) Customer Team Enablement
3.) Extensibility
4.) Solution Adoption
5.) Workers Council
6.) Design and Configuration

Correct Answer: 1,2,3,4,6


Explaination:

Question: 81

What is part of the SAP Activate Business Processes content for SAP S/4HANA? (2 Correct)

1.) Guidance
2.) System Content
3.) Accelerators
4.) Ready-to-run systems
5.) SAP Best Practices
6.) Project Plan

Correct Answer: 4,5


Explaination:

Question: 82

In which phase do you execute the User Acceptance Test?

1.) Deploy
2.) Realize
3.) Build and Test
4.) Final Preparation

Correct Answer: 2
Explaination:

Question: 83

What information does the Project Team need before they can correctly estimate the
relative size of backlog User Stories

1.) Test Strategy


2.) Overall project schedule
3.) Definition of Done
4.) Available Project Resources

Correct Answer: 3
Explaination:

Question: 84

The duration of a sprint is variable.

1.) FALSE
2.) TRUE

Correct Answer: 1
Explaination:

Question: 85

Which of these are included in the Project Governance according to SAP Activate? (3
Correct)

1.) Ensuring aherence to policies, standards and guidelines


2.) Establishing a communication plan
3.) Monitoring performance
4.) Ensuring appropriate stakeholder engagement

Correct Answer: 1,3,4


Explaination:

Question: 86

What are tools or content used in the Customer Team Enablement Workstream? (4 Correct)

1.) SAP Cloud Platform


2.) SAP Roadmap Viewer
3.) openSAP
4.) SAP Learning Hub
5.) SAP Best Practice Explorer
6.) SAP IAS

Correct Answer: 2,3,4,5


Explaination:

Question: 87
What's the correct description for the Workstream State Preparation

1.) Setup tools, establish frameworks


2.) Tools, procedures, roles for operations
3.) Create results, deliverables, and artifacts
4.) Preliminary strategy and tools selection

Correct Answer: 1

Explaination:

Question: 88

During which phase of a new implementation of SAP S/4HANA on Premise is the Solution
Documentation imported from SAP Best Practices Explorer into SAP Solution Manager
updated with description of gaps, WRICEF, custom developments and more?

1.) Explore
2.) Discover
3.) Discover
4.) Deploy
5.) Realize

Correct Answer: 1
Explaination:

Question: 89

The Product Owner facilitates the Daily Stand-up Meeting.

1.) TRUE
2.) FALSE

Correct Answer: 2
Explaination:

Question: 90

What's the preferred ALM solution for SAP S/4HANA Cloud STE?

1.) SAP Solution Manager


2.) SAP S/4HANA Cloud implementation portal

Correct Answer: 1
Explaination:

Question: 91

Solution Validation and Delta Design is part of the Explore phase of a system conversion

1.) FALSE
2.) TRUE

Correct Answer: 1

Explaination:
Question: 92

What is the best target deployment option of SAP S/4HANA for the “System Conversion”
transition path?

1.) SAP S/4HANA


2.) SAP C/4HANA
3.) Hybrid of SAP S/4HANA Cloud and SAP S/4HANA
4.) SAP S/4HANA Cloud

Correct Answer: 1

Explaination:

Question: 93
What's the default ALM solution for SAP S/4HANA on Premise?

1.) SAP S/4HANA Cloud implementation portal


2.) SAP Solution Manager
3.) SAP Transformation Navigator
4.) SAP Cloud Appliance Library

Correct Answer: 2

Explaination:

Question: 94

Validate and verify the system components against Solution Documentation is the correct
description for which testing type?

1.) Regression Test


2.) Integration Test
3.) String Test
4.) User Acceptance Test
5.) Unit Test
Correct Answer: 3

Explaination:

Question: 95

Where can you find the Integration Content? (3 Correct)

1.) SAP Best Practices Explorer


2.) Cloud Integration Automation Service
3.) SAP API Business Hub
4.) SAP Cloud Appliance Library
5.) SAP Solution Manager

Correct Answer: 1,2,3


Explaination:

Question: 96

What's the correct description for the detect to correct value chain of SAP Solution
Manager 7.2?

1.) Service Catalogue > Service Request > Service Fulfillment


2.) Portfolio Management > Project Management
3.) Monitor > Incident > Problem > Optimize
4.) Demand > Design > Development > Test > Deploy

Correct Answer: 3

Explaination:
Question: 97

Software product, content reuse across scenarios, In-application help and performance
support, Training simulation and test-script creation is the correct purpose for which tool or
content?

1.) Value Lifecycle Management


2.) KPI Catalog
3.) SAP Transformation Navigator
4.) SuccessFactors Learning Management System
5.) Enable Now

Correct Answer: 5

Explaination:

Question: 98

Which of these are Sprint Types of the SAP Activate Methodology? (3 Correct)

1.) Development Sprint


2.) Foundation Sprint
3.) Firm-up Sprint
4.) Building Sprint
5.) Design Sprint

Correct Answer: 2,3,4


Explaination:

Question: 99

What are major accelerators for the Integration Workstream in the Prepare Phase? (3
Correct)

1.) Technical Specification - Enhancements Template


2.) Interface Functional Specification Template
3.) Interface register template
4.) Interface Documentation in SAP Solution Manager 7.2

Correct Answer: 2,3,4


Explaination:

Question: 100

What are Business responsibilities during Release Planning? (2 Correct)

1.) Prioritize Product Backlog


2.) Define Product Backlog
3.) Estimate Product Backlog
4.) Analysis of Technical Dependencies

Correct Answer: 1,2


Explaination:

Question: 101

Which of the following are benefits of using Ready to Use Content? (2 Correct)

1.) Faster time-to-value


2.) Predictable results
3.) Minimized Total Cost of Ownership
4.) Run SAP Like a Factory

Correct Answer: 1,2


Explaination:

Question: 102

What are two important approaches, based on the Control Center Concept, that SAP
proposes to use for streamlines implementation and operation within Premium
Engagement. (2 Correct)

1.) Always Connected.


2.) Build SAP Like a Factory
3.) Intelligent Enterprise
4.) Run SAP Like a Factory

Correct Answer: 2,4


Explaination:

Question: 103

Who’s doing the estimations?

1.) Product Owner


2.) Scrum Team
3.) Project Manager
4.) Scrum Master

Correct Answer: 2
Explaination:

Question: 104

What is SAP Activate?

1.) Step-by-step instruction on how to move from SAP Best Practices to your custom solution
2.) A Solution Adoption Framework
3.) A methodology for each of the deployment modes (cloud, on premise, hybrid)
4.) A bundle of ASAP, SAP Launch, and Rapid Deployment Solution

Correct Answer: 3
Explaination:
Question: 105

Key questions in the Sprint Review meeting are: (3 Correct)

1.) What obstacles are in your way?


2.) What went well during the sprint?
3.) What will you do until next meeting?
4.) What do we want to preserve?
5.) What can be improved for the next sprint and how?

Correct Answer: 2,4,5

Explaination:
Question: 106

What Activities and Artifacts are part of the Explore Phase of a system conversion? (4
Correct)

1.) Database migration


2.) SAP Readiness Check for SAP S/4HANA
3.) Custom Code Worklist
4.) Custom Code cleanup preparation
5.) Data structure conversion
6.) Application Conversion

Correct Answer: 1,3,5,6

Explaination:

Question: 107

The Project Manager organizes and facilitates the Sprint Review Meeting

1.) TRUE
2.) FALSE

Correct Answer: 2
Explaination:

Question: 108

Meeting purpose of the daily stand-up meeting is to ensure that everyone on the team is
informed about work in progress and any obstacles. It is meant to identify problems, but not
solve them.

1.) TRUE
2.) FALSE

Correct Answer: 1
Explaination:

Question: 109

A sprint usually lasts for two to three months.

1.) FALSE
2.) TRUE

Correct Answer: 1

Explaination:
Question: 110

What is part of the SAP Activate Integration content for SAP S/4HANA? (2 Correct)

1.) Accelerators
2.) Ready-to-run systems
3.) Project Plan
4.) Guidance
5.) System Content
6.) SAP Best Practices

Correct Answer: 4,5

Explaination:

Question: 111

"Readiness" Quality Gate verifies that Project is well-prepared to start a new phase

1.) FALSE
2.) TRUE

Correct Answer: 2
Explaination:

Question: 112

In a new implementation of S/4HANA Cloud Multi-Tenant Edition the Q-System is a


configurable system during implementation. After S4HC system is live, the Q-system will
act as a test environment for further configurations, and a quality assurance check during
the quarterly updates during which the Q-system will be updated two weeks ahead of the P-
system to give ample time for testing.

1.) TRUE
2.) FALSE

Correct Answer: 1

Explaination:
Question: 113

During a Lean or Agile approach what is fixed? (2 Correct)

1.) Resources
2.) Date
3.) Requirements

Correct Answer: 1,2

Explaination:

Question: 114

Which kinds of extensibility are available on SAP S/4HANA Cloud? (2 Correct)

1.) Managed Extensibility


2.) Key User Extensibility
3.) Classic Extensibility

Correct Answer: 1,2


Explaination:

Question: 115

What's the major difference between Selective Data Transition and System Conversion?

1.) Test Activities


2.) Data Migration Activities
3.) Onboarding and deploy activities
4.) Adjustment of Custom Code
5.) Custom Code Impact Analysis

Correct Answer: 2
Explaination:

Question: 116

Which of these are SAP Project Roles of the Implementation Partner in the Customer Team
Enablement Workstream?

1.) Business Solution Architect


2.) Education Services Consultant
3.) Developer
4.) Quality Manager
5.) Application Consultant

Correct Answer: 2
Explaination:

Question: 117

What are Golden Rules to help customers to adopt to Cloud with SAP S/4HANA Cloud
Single-Tenant Edition? (4 Correct)

1.) Ensure obscurity on deviations


2.) Foster cloud mindset by adhering to Fit-to-Standard and Agile Deployment detailed in
SAP Activate
3.) Use modern integration technologies
4.) Use pre-configured solutions with predefined processes
5.) Use modern extensibility technologies

Correct Answer: 2,3,4,5


Explaination:

Question: 118

Which of the following are components of SAP Model Company? (3 Correct)

1.) Quality Gate Check List


2.) Preconfigured Solution Business-Driven Configuration Questionnaire
3.) Business Process Content for SAP Solution Manager
4.) Accelerators

Correct Answer: 2,3,4


Explaination:

Question: 119

In a new implementation of S/4HANA Cloud Multi-Tenant Edition you need to perform


sizing during the Discover phase.

1.) FALSE
2.) TRUE

Correct Answer: 1
Explaination:

Question: 120

What's the preferred integration option for SAP S/4HANA Cloud STE?

1.) SAP Process Orchestration


2.) SAP Cloud Platform Workflow Management
3.) SAP Cloud Platform Integration

Correct Answer: 3
Explaination:

Question: 121

What is the correct description for the Realize Phase?

1.) In the Realize phase, we define project governance, start teh project, define/identify the
resources, define the roles and responsibilities for the project team, and detail the
management plans for running the project.
2.) In the Realize phase, we run the Fit/Gap analysis on the working system with the best
practices content up and running. The objective of the Realize phase is to identify the fit of
the best practices based solution, capture delta configuration requirements, identify gaps,
and configuration values. All these are captured by the project team in the backlog and
later, in Realize phase the backlog items are implemented in the system. The best practices
content is used as a jump-start for the project.
3.) During the Realize phase the project team will use an agile approach to iteratively and
incrementally build the functionality from the backlog. This build follows the prioritization
given by the product owner that continues to be involved with the project during the
sprints.

Correct Answer: 3
Explaination:

Question: 122

Which Artifacts belong to the Detect to correct value chain of SAP Solution Manager 7.2? (2
Correct)

1.) Request for Change


2.) Defect
3.) Incident
4.) Service Request
5.) Test Case

Correct Answer: 1,3


Explaination:

Question: 123

For S/4HANA Cloud Multi-Tenant Edition content corrections are generally scheduled in
which time period?

1.) Weekly
2.) Bi-Weekly
3.) Monthly
4.) Quarterly

Correct Answer: 2
Explaination:

Question: 124

What are SAP Landscape Transformation enabled scenarios?

1.) Migration of Business Units


2.) Migration of selected applications
3.) Consolidation

Correct Answer: 3
Explaination:

Question: 125

What is a User Story in the product backlog?

1.) A large user story, typically a process or Scenario


2.) A description of desired functionality told from the perspective of the user or customer.
3.) A collection of related user stories

Correct Answer: 2

Explaination:
Question: 126

SAP Best Practice Explorer is the central location for SAP Activate Methodology. It provides
detailed information on project activities and Project Library Accelerators.

1.) TRUE
2.) FALSE

Correct Answer: 2

Explaination:

Question: 127

Fit-to-Standard workshops are conducted during the Explore Phase of a SAP S/4HANA On
Premise implementation.

1.) TRUE
2.) FALSE

Correct Answer: 2
Explaination:

Question: 128

What are substreams of the Data Management Workstream? (3 Correct)

1.) Data Volume Management


2.) Data Transformation
3.) Data Cleansing
4.) Data Migration
5.) Master Data Management

Correct Answer: 1,4,5


Explaination:
Question: 129

For S/4HANA Cloud Multi-Tenant Edition upgrades are generally scheduled in which time
period?

1.) Monthly
2.) Weekly
3.) Quarterly
4.) Bi-Weekly

Correct Answer: 3

Explaination:

Question: 130

Which artifacts are part of the Solution Adoption workstream? (3 Correct)

1.) Project Plan


2.) System Go live Announcement (order)
3.) Detailed Design-Business Process
4.) Project Business Case
5.) Business Transformation Review (Point of View)

Correct Answer: 1,2,5


Explaination:

Question: 131

What term is used for a Ready to run SAP S/4HANA system with pre-built Solution
Documentation, which supports End-to End Processes for a specific industry so that the
Project Team can focus on differentiation and innovation?
1.) SAP Model Company
2.) Best Practice System
3.) SAP Cloud Appliance Library
4.) Fully Activated Appliance

Correct Answer: 1

Explaination:

Question: 132

In a new implementation of S/4HANA Cloud Multi-Tenant Edition the Starter System


includes configuration and master data for selected cloud solutions for targeted enablement
of the project team on SAP standard processes and to be the host environment of the Fit-to-
Standard Workshops

1.) FALSE
2.) TRUE

Correct Answer: 2
Explaination:

Question: 133

What’s a method to work on a flat backlog?

1.) User Story Mapping


2.) Planning Poker

Correct Answer: 1

Explaination:
Question: 134

What are the most important questions in the daily stand-up meeting? (3 Correct)

1.) What will you do until next meeting?


2.) What do you want to improve?
3.) How do you solve issues?
4.) What did you do since last meeting?
5.) What obstacles are in your way?

Correct Answer: 1,4,5

Explaination:

Question: 135

What is the primary purpose of the SAP Activate Methodology?

1.) To provide the sequence of actions in the Project


2.) To manage Solution documentation
3.) To provide end-to-end Application Lifecycle Management
4.) To enable access to the SAP ecosystem

Correct Answer: 1
Explaination:

Question: 136

Which new project roles are introduced with SAP Activate Methodology for the Agile
delivery approach? (2 Correct)

1.) Scrum Master


2.) Integration Lead
3.) Design Thinking Coach
4.) Product Owner

Correct Answer: 1,4

Explaination:

Question: 137
The Sprint Review meetings focus is on what has been delivered during the sprint,
identification and prioritization of any new requirements and an update or review of the
Product Backlog.

1.) TRUE
2.) FALSE

Correct Answer: 1

Explaination:

Question: 138

What are responsibilities and tasks of the product owner? (4 Correct)

1.) Defines the features of the product, devides on release date and content.
2.) Protects the team from bureaucracy and non-value added activities.
3.) Prioritizes features according to business value.
4.) Accepts or rejects work results.
5.) Can change features and priority as needed, potentially for every iteration.

Correct Answer: 1,3,4,5


Explaination:

Question: 139

What are Scrum Master Tasks during Sprint Review? (2 Correct)

1.) Ensures team enters remaining effort daily


2.) Ensures Product Owner prepares well for the next sprint
3.) Ensures development environment is available
4.) Ensures agenda of Sprint Review and facilitates discussion on product
5.) Ensures top 3 learnings will be decided and improved in next sprint

Correct Answer: 4,5


Explaination:

Question: 140

What are Outputs relating to the Business Process Workshop? (3 Correct)

1.) SAP Best Practices


2.) Initial Backlog
3.) Process Value Determination
4.) Issue List
5.) Business Requirements

Correct Answer: 2,4,5


Explaination:

Question: 141

In a new implementation of S/4HANA Cloud Multi-Tenant Edition during the Discover phase
the ALM roadmap shall define which ALM tool is used for S/4HANA Cloud Implementation.
For pure Cloud installations Solution Manager is a default choice.

1.) FALSE
2.) TRUE

Correct Answer: 1
Explaination:

Question: 142

For S/4HANA Cloud Multi-Tenant Edition all customers are on the same release and hotfix
package

1.) FALSE
2.) TRUE

Correct Answer: 2
Explaination:

Question: 143

The main activities during a Foundation Sprint are the definition of organizational structure
and master data

1.) TRUE
2.) FALSE

Correct Answer: 1

Explaination:

Question: 144

The Simplification and Custom Code Impact Analysis with Test Conversion is part of the
Realize Phase during a system conversion
1.) TRUE
2.) FALSE

Correct Answer: 2

Explaination:

Question: 145

What is the available target solution for the transition path System conversion?

1.) SAP S/4HANA Cloud Multi-Tenant Edition


2.) SAP S/4HANA On Premise
3.) SAP S/4HANA Cloud Single-Tenant Edition

Correct Answer: 2
Explaination:

Question: 146

What are correct statements for the Scrum master? (3 Correct)

1.) The product owner is the project customer, and defines the requirements and priorities
of the project.
2.) The Scrum master has the authority to terminate any development sprint in cases where
non resolvable issues arise or the workload proves to be inadequate.
3.) The Scrum master is the team leader, who is responsible for moderating meetings,
producing documentation, and resolving any issues during the project.
4.) The Scrum Master is responsible for making sure that everyone follow the Scrum rules.

Correct Answer: 2,3,4


Explaination:

Question: 147

What is the correct description for the Project Manager Role?

1.) Assist Customer Business Project Manager in large projects. Perform cost accounting,
expedite logistics topics, obtain statuses, prepare reports.
2.) Act as a visible champion. Legitimizes the project's goals and objectives. Informed of
major project activities and is a decision-maker for the project.
3.) Ensure clear goals for the project and that every team member understands these goals.
Ensures that each team member has a clear role and that their resources have been agreed.

Correct Answer: 3
Explaination:

Question: 148

Run SAP like a factory (for example, OCC) provides? (3 Correct)

1.) Higher degree of automation


2.) Better business performance
3.) Increased total cost of operations
4.) Improved business continuity

Correct Answer: 1,2,4


Explaination:

Question: 149

What's the recommended choice for Cloud-to-Cloud Integrations scenarios?

1.) SAP Process Orchestration


2.) SAP Cloud Platform Integration

Correct Answer: 2
Explaination:

Question: 150

What accelerator can help you document the Configuration Definition in the Explore phase?

1.) Data Definition


2.) Backlog template
3.) Change Request template
4.) Test Strategy

Correct Answer: 2
Explaination:
Question: 151

Which collaboration features can SAP Jam user access in the SAP Methodologies Jam
group? (2 Correct)

1.) Tweet questions


2.) Ask Questions
3.) Update Key Deliverable wikis
4.) Comment on Key Deliverables

Correct Answer: 2,4

Explaination:
Question: 152

Who determines the tasks that are required to complete the committed Backlog items in a
Sprint.

1.) Project Team


2.) Product Owner
3.) Scrum Master
4.) Project Manager

Correct Answer: 1

Explaination:

Question: 153

How do you set up Scrum teams? (2 Correct)

1.) As a cross functional team covering multiple functions, like configuration, data loads,
and testing.
2.) Based on End-to-End Processes like Order to Cash
3.) By type of work, like configuration Scrum, documentation Scrum, and testing Scrum.
4.) Based on group size, but a minimum of 12 people

Correct Answer: 1,2


Explaination:

Question: 154

Which of the following are example of Ready-to run SAP S/4HANA system? (2 Correct)
1.) SAP Mission Control Center
2.) SAP Best Practices Explorer
3.) Fully Activated Application
4.) SAP Model Company

Correct Answer: 3,4

Explaination:

Question: 155

In a new implementation of S/4HANA Cloud Multi-Tenant Edition during the Prepare phase
the SAP ALM trainings are replaced with Cloud Implementation Portal on-boarding.
Customer Team uses build-in Web Assistant in Starter System for SAP S4HC functionality
discovery.

1.) TRUE
2.) FALSE

Correct Answer: 1
Explaination:

Question: 156

Who determines the priority of user stories in the backlog of an Agile project?

1.) Product Owner


2.) Project Team
3.) Project Manager
4.) SCRUM Master

Correct Answer: 1
Explaination:

Question: 157

SAP Best Practices Explorer is the central place for Solution Documentation. It hosts
information on Business Process flows and SAP S/4HANA configuration guidelines.

1.) FALSE
2.) TRUE
Correct Answer: 2

Explaination:

Question: 158

What tool is used for the SAP Activate Transition Path New implementation?

1.) SAP Landscape Transformation


2.) SAP S/4HANA Migration Cockpit
3.) Software Update Manager

Correct Answer: 2

Explaination:

Question: 159
Which of the following will help you avoid modification of standard functionality in SAP
S/4HANA Cloud, Single Tenant Edition? (2 Correct)

1.) The Side-by-Side Extensibility Option (such as SAP Cloud Platform)


2.) SAP Code Inspector
3.) The 5 Golden Rules
4.) Contract restrictions in SAP S/4HANA Enterprise Cloud and SAP S/4HANA Cloud Single
Tenant Edition.
5.) A developer key

Correct Answer: 3,4

Explaination:

Question: 160

Which of these are Workstream States in the SAP Activate Methodology? (4 Correct)
1.) Delivery
2.) Preparation
3.) Execution
4.) Discovery
5.) Operations Preparation
6.) Planning

Correct Answer: 2,3,5,6

Explaination:

Question: 161

What does the Side-by-Side Extensibility Option mean?

1.) Transfer reporting to BW/4HANA


2.) Have two SAP S/4HANA instance – one for standard code, and another for custom
developments
3.) Context-aware SAP S/4HANA extensions, focused on tight integration
4.) Extensibility based on the SAP Cloud Platform and published APIs
Correct Answer: 4

Explaination:

Question: 162

What tool provides guidance on replacing custom code development for SAP ERP with SAP
S/4HANA functionality for the “System Conversion” transition path?

1.) Software Provisioning Manager


2.) Software Update Manager with Database Migration Option
3.) SAP Code Inspector
4.) Simplification Item Check (SI-Check)

Correct Answer: 4
Explaination:

Question: 163

What's the correct description for the End-to-End Processes? (2 Correct)

1.) Building blocks required for all processes.


2.) Do not stop at organizational borders.
3.) Span across the company, for example, Order to Cash.
4.) Run within one Process Area / LoB, for example, Accounts receivable.

Correct Answer: 2,3

Explaination:
Question: 164

What is the order of artifacts within the technical Architecture and infrastructure
workstream in the Prepare phase?

1.) Technical Strategy -> Parameter Hardware Sizing calculation -> Hardware Sizing
Results -> Hardware Specification from Hardware Vendor
2.) Parameter Hardware Sizing calculation -> Hardware Sizing Results -> Hardware
Specification from Hardware Vendor -> Technical Strategy
3.) Technical Strategy -> Hardware specification from Hardware Vendor -> Parameter
Hardware Sizing calculation -> Hardware Sizing result
4.) Parameter Hardware Sizing calculation -> Technical Strategy -> Hardware Sizing
Results -> Hardware Specification from Hardware Vendor

Correct Answer: 1

Explaination:

Question: 165

What is the term used for workshops, which are intended to set value targets, validate SAP
Standard functionality against customer requirements and collect delta requirements in the “New
Implementation of SAP S/4 HANA” Transition path?

1.) Delta Design


2.) Design Thinking
3.) Solution Validation
4.) Fit-to-Standard
Correct Answer: 3

Explaination:
Question: 166

Which artifacts in the Testing workstream are created within the Realize phase for the
“New implantation of SAP S.4HANA Cloud” transition path? Note: There are 2 correct
answers to this question? (2 Correct)

1.) Reporting Functional Specifications


2.) Functional Test Scenarios
3.) Functional Specifications
4.) User Acceptance Test- Plan

Correct Answer: 2,4


Explaination:

Question: 167

Which accelerates support the Fit-to-Standard workshop in the Explore phase? (2 Correct)

1.) Test Strategy


2.) Backlog template
3.) Quality Gate Checklist
4.) Business-Driven Configuration Questionnaire

Correct Answer: 2,4


Explaination:
Question: 168

Which governance bodies are recommended by SAP Activate? (3 Correct)

1.) Steering Committee


2.) Integrating Committee
3.) Workers Council
4.) Operating Committee

Correct Answer: 1,2,4

Explaination:

Question: 169

In which phase should you create a Data Migration Strategy (L0) during a Selective Data
Transition?

1.) Explore
2.) Deploy
3.) Realize
4.) Discover

Correct Answer: 4
Explaination:

Question: 170

What is the purpose of the Scrum Board?

1.) To show the functional breakdown of the solution scope


2.) To document the results of the integration Test
3.) To visualize team progress
4.) To manage the resource load

Correct Answer: 3
Explaination:

Question: 171

A definition of Ready signifies that a User Story has been completed.

1.) FALSE
2.) TRUE

Correct Answer: 1

Explaination:
Question: 172

What is the Sprint Retrospective used for?

1.) Present Sprint results to the customer


2.) Improve Scrum process
3.) Replan based on the results of the sprint

Correct Answer: 2

Explaination:

Question: 173

Which activity helps the Project Team add User Stories to the Product Backlog?

1.) Conducting the Solution Validation workshop


2.) Planning the User Acceptance Test
3.) Assessing project risks
4.) Preparing a project schedule

Correct Answer: 1
Explaination:

Question: 174

A user story map arranges user stories into a usefol model to help understand the
functionality of the system, identify holes and omissions in your backlog and effectively plan
holistic releases that deliver value to users and business with each release.

1.) FALSE
2.) TRUE

Correct Answer: 2

Explaination:
Question: 175

What tool is used to authorize changes between SAP ERP and SAP S/4HANA maintenance
tracks?

1.) SAP Code Vulnerability Analyzer


2.) SAP Code Inspector
3.) Business Process Change Analyzer
4.) Retrofit

Correct Answer: 4

Explaination:

Question: 176

What tool provides sizing estimations for the “System Conversion” transition path?
1.) Scope and Effort Analyzer
2.) SAP Best Practices Explorer
3.) SAP Transformation Navigator
4.) SAP Readiness Check

Correct Answer: 4

Explaination:

Question: 177

What's the correct description for a Task?

1.) Structured collection of activities with dependencies, used to plan and monitor project
team work.
2.) Work to be performed by a project team to create one or more deliverables
3.) Measurable result of the project team work showing project progress. It can be tangible
or intangible. It may, or may not require formal approval from stakholders. It may be
assigned to one or more Workstreams

Correct Answer: 2
Explaination:

Question: 178

"Readiness" Quality Gate verifies that Project meets Acceptance Criteria for Phase Closure

1.) TRUE
2.) FALSE

Correct Answer: 2

Explaination:

Question: 179

Working in an agile approach, what should your planning look like at the beginning of
realize phase?
1.) Project scope and planning are complete and final
2.) Go-Live scope is fixed on the first of January the following year.
3.) Timeline of the Sprint may differ due to the workload
4.) User Stories are in a Ready state for NO more than the first three Sprint

Correct Answer: 4

Explaination:
Project scope and planning cannot be said complete and final since question talks
about agile approach. Which means requirement may keep changing and hence
project scope and planning keep changing
Go-live scope fixed on 1st of Jan is not a feasible option. Go-live can happen any
time of year as agreed with customer
Timeline of sprint cannot differ due to workload because sprint duration is always
fixed in agile
Hence the only option left is: user stories are in a ready state for no more than
first 3 sprint

Question: 180

What is the minimum number of quality gates mandated by the SAP Activate methodology?

1.) 0
2.) 4
3.) 5
4.) 3

Correct Answer: 2

Explaination:

Question: 181
Which of the following scenarios are enables for the "Selective Data Transition" transition
path with the SAP Landscape Transition tool? (3 Correct)

1.) Security Migration


2.) Extraction of Business Units
3.) System Consolidation
4.) Consolidation through online data replication
5.) System Update

Correct Answer: 2,3,4

Explaination:

Question: 182

Which of these are part of the SAP Quality Principles? (4 Correct)

1.) Anchor business value in the project


2.) Ensure timely delivery and effective tracking
3.) Avoid standard functionality and best practices
4.) Staff project with sufficient, competent, and motivated people
5.) Start scoping late
6.) Cooperate with stakeholders and use a proper governance model
Correct Answer: 1,2,4,6

Explaination:

Question: 183

In which phase do you verify that the SAP Best Practices content meets the customer’s
business needs, and then capture gaps?

1.) Explore
2.) Realize
3.) Deploy

Correct Answer: 1
Explaination:

Question: 184

Which statements are part of 5 Golden Rules for SAP S/4HANA Cloud, Single Tenant
Edition? (2 Correct)

1.) Document deviation from Golden Rule for transparency and future use in upgrade
2.) Use SAP Solution Manager 7.2 with Focused Build
3.) Stick to the security standards of the customer organization.
4.) Foster a cloud mindset and adherence to the Fit-to-Standard approac

Correct Answer: 1,4


Explaination:

Question: 185

What criterion does the Product Owner use to Sequence the Product Backlog?
1.) Business Priority
2.) Complexity
3.) Resource Availability
4.) Relative Effort

Correct Answer: 1

Explaination:

Question: 186

What techniques helps a Scrum Team to prioritize a large flat Backlog?

1.) Fit/Gap Analysis


2.) Planning Poker
3.) Retrospective
4.) User Story Mapping

Correct Answer: 4
Explaination:

Question: 187

A Workstream is a grouping attribute for? (5 Correct)

1.) Deliverables
2.) Activities
3.) Projects
4.) Artifacts
5.) Roles
6.) System

Correct Answer: 1,2,3,4,5


Explaination:

Question: 188

What Solution Operation Framework can customers use to create a joint Business and IT -
organization, that will secure transparency and efficiency of SAP implementation,
innovation, operation and quality of business processes and system?

1.) Business Transformation Management Methodology


2.) SAP Operations Control Center
3.) Customer Center of Expertise
4.) SAP Activate

Correct Answer: 3
Explaination:

Question: 189

Where can you find Data Migration templates?

1.) SAP Cloud Appliance Library


2.) SAP Best Practices Explorer
3.) SAP S/4HANA Migration Cockpit
4.) SAP Roadmap Viewer

Correct Answer: 3
Explaination:

Question: 190

With SAP Solution Manager Focused Insights you can build and distribute powerful
customer-specific dashboards in minutes.

1.) TRUE
2.) FALSE

Correct Answer: 1
Explaination:

Question: 191

What is the basis for approving work results (signing Act of Acceptance) on a Project phase
level?

1.) Scrum of Scrum meeting decision


2.) Agreed and met Acceptance Criteria within Quality Gate
3.) Definition of Done for User Story
4.) Definition of Ready for Sprint

Correct Answer: 2
Explaination:

Question: 192
Which artifacts are created within Application Design and Configuration workstream in the
Explore Phase of the “New implementation of SAP S/4HANA” transition path? (3 Correct)

1.) Roles and Authorization Management Concept


2.) Detailed Design – Business Process
3.) Organization Structure Specification
4.) Project Procedure – Mock-up Modeling
5.) Delta Requirement List – Register

Correct Answer: 2,3,5

Explaination:

Question: 193

What are correct statements regarding the Transition Path New Implementation? (3
Correct)

1.) Performing initial data load


2.) Reengineering and process simplification based on latest innovations
3.) Migrate a selection of data
4.) Save investments into SAP ERP projects
5.) Implementing innovative business processes with pre-configured content on a new
platform

Correct Answer: 1,2,5


Explaination:

Question: 194

What Sprint types are part of the SAP Activate Methodology? (3 Correct)

1.) Initial
2.) Build
3.) Firm-up
4.) Foundational
5.) Daily

Correct Answer: 2,3,4


Explaination:

Question: 195

In which phase do you create “an ordered list of everything that is known to be need in the
product”?
1.) Deploy
2.) Explore
3.) Realize
4.) Prepare

Correct Answer: 2

Explaination:

Question: 196

Expert configuration allows implementation of customer specific requirements with


restrictions. Expert Configurations are implemented in the Q-System by SAP Service
Center. Expert configuration allows? (3 Correct)

1.) Change of non-editable fields in SAP Best Practice content.


2.) Creation of new processes in customer owned area
3.) Consideration of namespaces for customer owned processes
4.) Deletion of SAP Best Practice content
5.) Adaption of editable fields within SAP Best Practice content

Correct Answer: 2,3,5


Explaination:

Question: 197

Which activities are critical for delivering Agile projects? (2 Correct)

1.) Retrospective agenda creation


2.) Blueprint scheduling
3.) Sprint planning
4.) Release planning

Correct Answer: 3,4


Explaination:

Question: 198
In which phase should you first run the SAP Readiness Check for SAP S/4HANA Selective
Data Transition” transition path, in a System Consolidation scenario that includes
conversion from SAP ERP?

1.) Prepare
2.) Discover
3.) Explore
4.) Realize

Correct Answer: 2

Explaination:

Question: 199

Build SAP like a Factory offers? (3 Correct)

1.) Accelerated time-to-value


2.) Increased total cost of implementation
3.) Smooth transition to operations
4.) Support for New Business Models
Correct Answer: 1,3,4

Explaination:

Question: 200

Which Value Chains does SAP Solution Manger 7.2 deliver? (3 Correct)

1.) Detect-to-Correct
2.) Request-to-Fulfill
3.) Cash-to-Order
4.) Hire to Retire
5.) Requirements-to-Deploy

Correct Answer: 1,2,5


Explaination:
Question: 201

What is the Key characteristics of the Agile project approach?

1.) Iterative build with frequent inspections


2.) Frequent Quality Gates
3.) Formal and detailed documentation
4.) Frequent and detailed project scheduling

Correct Answer: 1
Explaination:

Question: 202

What does SAP Activate recommend to keep team members informed and aligned?
1.) Daily team stand-up meeting
2.) Daily status meeting with project manager
3.) Daily progress review meeting with sponsor
4.) Daily e-mail status updates to project manager

Correct Answer: 1

Explaination:

Question: 203

Which of the following dimensions need to be considered during prioritization? (3 Correct)

1.) Technological Preferences


2.) Integration
3.) Importance
4.) Scaling

Correct Answer: 2,3,4


Explaination:

Question: 204

What are some of the Key topics covered in the Customer Team Enablement workstream?
(3 Correct)

1.) Solution Expertise


2.) Project Sourcing Approach
3.) Planning skills
4.) Project Management
5.) Technical Expertise

Correct Answer: 1,4,5


Explaination:

Question: 205

Which of these are SAP Project Roles of the Implementation Partner in the Extensibility
Workstream? (2 Correct)

1.) Business Solution Architect


2.) Quality Manager
3.) Application Consultant
4.) Developer
5.) Development Lead

Correct Answer: 4,5


Explaination:

Question: 206

Which of the following is part of the Explore phase in the “New Implementation of SAP
S/4HANA Cloud” transition path?

1.) Solution Validation and Delta Design


2.) Fit-to-standard
3.) Simplification and Custom Code Impact Analysis
4.) Setup and Enablement

Correct Answer: 2
Explaination:

Question: 207

Which new role is introduced in the SAP Activate Methodology in a Full Scrum Team

1.) Product Owner


2.) Application Consultant
3.) Project Manager
4.) System Administrator

Correct Answer: 1
Explaination:

Question: 208

What is the objective of a Sprint Retrospective meeting?

1.) Define the stakeholder management approach


2.) Review and prioritize the Backlog
3.) Improve the Scrum process
4.) Provide formal feedback to the Project Manager

Correct Answer: 3
Explaination:

Question: 209

How does the provisioning of SAP S/4HANA Cloud differ from the setup of SAP S/4HANA? (2 Correct)

1.) To start a Solution Validation workshop, a DEV system is available for SAP S/4HANA, while a Starter
system is required for Fit-to-standard for SAP S/4HANA Cloud
2.) In SAP S/4HANA Cloud, decommissioning/shutdown of the Starter system is initiated automatically after
the P-system is required through the Manage Your Solution app. Whereas in an SAP S/4HANA system, the DEV
system persists.
3.) SAP S/4HANA system takes less time to provision than SAP S/4HANA Cloud system
4.) There is a Preset phase for Q-system which is unique for SAP S/4HANA Cloud

Correct Answer: 1,2


Explaination:
Question: 210

What is Strategy Level 0 (L0) artifact?

1.) Approach document that is developed by a united Project Team (partner + customer)
2.) Project result that is developed solely by the partner
3.) Optional information that is NOT important for project activities
4.) Preliminary strategy developed by the customer to approach the Project in a specific
workstream.

Correct Answer: 1

Explaination:

Question: 211

What is the purpose of a Firm-up Sprint?


1.) To perform String test
2.) To run an end-to-end integration Test
3.) To revise the Release Plan and Sprint Plan
4.) To demonstrate functionality from previous Sprints

Correct Answer: 1

Explaination:

Question: 212

In which phase will the customer develop a preliminary strategy for building a target
Operations and Support organizational model?

1.) Discover Phase


2.) Run Phase
3.) Prepare phase
4.) Explore Phase

Correct Answer: 3
Explaination:

Question: 213

What are phases of the SAP Activate methodology? (3 Correct)

1.) Hand-Over
2.) Prepare
3.) Close
4.) Deploy
5.) Initialize
6.) Run

Correct Answer: 2,4,6

Explaination:
Question: 214

For "Solution Replacement" and "Business Transformation" implementation types build


requirements based on a new software and not on an existing one. Otherwise, there's a risk
of costly replication of inefficient approaches and suboptimal data structures into new
solution.

1.) FALSE
2.) TRUE

Correct Answer: 2
Explaination:
Question: 215

What are some of the key characteristics of the implementation approach in SAP Activate
Methodology? (3 Correct)

1.) Based on Ready-to-use Content


2.) On Premise only
3.) Cloud Ready
4.) Fixed scope
5.) Delta-based

Correct Answer: 1,3,5

Explaination:

Question: 216

Which of the following provides the highest level of detail with regards to the SAP Best
Practice Explorer?

1.) Scope Item Groups


2.) Solution Package
3.) Scope Items
4.) Building Blocks
5.) Business Area

Correct Answer: 4
Explaination:

Question: 217

What's the correct description for the Process Step Library?

1.) Building blocks required for all processes.


2.) Run within one Process Area / LoB, for example, Accounts receivable.
3.) Do not stop at organizational borders.
4.) Span across the company, for example, Order to Cash.

Correct Answer: 1
Explaination:

Question: 218

What is the difference between the “System Conversion” and the “ New Implementation of
SAP S/4HANA” transition path? Note: There are 2 correct answers to this question? (2
Correct)

1.) SSCUIs are used in System Conversion for configuring SAP S/4HANA through the
Manage Your Solution app.
2.) There are different upgrade cycles.
3.) In the Realize phase, data is converted and NOT migrated for System Conversion
4.) In the Realize phase, custom codes is adjusted rather than developed for System
Conversion.

Correct Answer: 3,4


Explaination:

Question: 219

What are key characteristics of SAP Activate Framework? (5 Correct)

1.) Cloud ready


2.) Based on ready-to-use content
3.) Quality Built-Out
4.) Delta-based
5.) Scalable, Modular and Agile
6.) SAP Engagement Ready

Correct Answer: 1,2,4,5,6


Explaination:

Question: 220

Which of the following content best outlines the sequence of testing within the Application
Design and Configuration workstream in the Realize Phase?

1.) 1. String test 2. User Acceptance Test 3. Integration Test


2.) 1. Data Migration 2. String test 3. User Acceptance Test
3.) 1. String test 2. Integration Test 3. User Acceptance Test
4.) 1. Integration Test 2. User Acceptance Test 3. String test

Correct Answer: 3
Explaination:

Question: 221

What tool would you use for managing project tasks and Solution Documentation when
implementing SAP S/4HANA Cloud?

1.) SAP Support Marketplace


2.) SAP Transformation Navigator
3.) SAP Roadmap Viewer
4.) Implementation portal for SAP S/4HANA Cloud

Correct Answer: 4
Explaination:
Question: 222

How would you describe the Realize Phase in the “New Implementation of SAP S/4HANA”

1.) Configure and Develop


2.) Configuration Copy
3.) Transition Path
4.) Configure
5.) Configure and adjust custom code

Correct Answer: 1

Explaination:

Question: 223

In SAP Activate, what tool is used in the Agile Delivery Approach during the Realize phase
to make forecasts based on actual data

1.) Burndown Chart


2.) Product Increment
3.) Project Plan
4.) Release Plan

Correct Answer: 1
Explaination:

Question: 224

Which roles are new with SAP activate? (2 Correct)

1.) Project Team


2.) Project Manager
3.) Scrum Master
4.) Product Owner

Correct Answer: 3,4

Explaination:
Question: 225

Which estimation technique can be used in Agile Delivery Approach to size the User Stories
during Sprint Planning?

1.) Product Owner’s relative estimates of the effort that will be needed to implement the
User Story
2.) Detailed bottom-up effort estimate by the Scrum Master in Story point based on the
User Story complexity.
3.) Detailed bottom-up effort estimate that break each User Story up into hours or shorter
tasks
4.) Relative estimate in ideal Person Days that reflects the best estimated provided by the
project team

Correct Answer: 4

Explaination:

Question: 226

How would you describe the Explore phase in the "New Implementation of SAP S/4HANA
Cloud” transition path?

1.) Fit-to-Standard
2.) Setup and Enablement
3.) Solution Validation and Delta Design.
4.) Simplification and Custom Code Impact Analysis
Correct Answer: 1

Explaination:

Question: 227

What's the correct order of steps to create delta requirements based on SAP S/4HANA
capabilities?

1.) 1. Set Reference Value 2. Validate Solution 3. Collect delta Requirements 4. Create
Initial Backlog 5. Enhance Solution Documentation 6. Verify and Accept 7. Enhance
Solution Documentation
2.) 1. Validate Solution 2. Set Reference Value 3. Create Initial Backlog 4. Collect delta
Requirements 5. Enhance Solution Documentation 6. Verify and Accept 7. Enhance Solution
Documentation
3.) 1. Collect delta Requirements 2. Validate Solution 3. Set Reference Value 4. Create
Initial Backlog 5. Enhance Solution Documentation 6. Verify and Accept 7. Enhance
Solution Documentation

Correct Answer: 1
Explaination:

Question: 228

Which is true for the Business Process Content Solution Configuration?

1.) It is a function of the SAP S/4HANA System which contains system objects.
2.) It is provided through SAP Best Practices Explorer online tool.

Correct Answer: 1
Explaination:

Question: 229

The Sprint Retrospective Meetings purpose is to continuosly improve the Scrum process
using lessons learned from the Sprint Execution

1.) TRUE
2.) FALSE

Correct Answer: 1
Explaination:

Question: 230

With SAP Activate Guided configuration which features are users taking advantage of? (3
Correct)

1.) A simple possibility to evaluate activated business processes and country versions
2.) Initial configuration of the solution and recording of updates for continuous innovation
3.) A competence based approach for testing your configured business processes
4.) An embedded migration engine for simple data migration

Correct Answer: 1,2,4

Explaination:
Question: 231

Which of the following belong to the Application Design and Configuration workstream for
SAP S/4HANA Cloud in the Explore phase? Note: There are 2 correct answers to this
question? (2 Correct)

1.) Integration prerequisite confirmation


2.) Kick-off workshop
3.) Fit-to-standard workshop
4.) Configuration definition.

Correct Answer: 3,4

Explaination:

Question: 232

According to the Definition of Done, which activity must be completed for each Sprint?

1.) The Team knows how to demo this story to the product owner.
2.) The software is deployed on the 'TST' environment.
3.) The organization is ready to use the new software.
4.) The software has been accepted by QA.
Correct Answer: 2

Explaination:

Question: 233

SAP Activate uses concepts, ceremonies and roles introduces by which methodology and
expands them with Solution Implementation specifics?

1.) ICB
2.) PRINCE2
3.) SCRUM
4.) ITIL

Correct Answer: 3
Explaination:

Question: 234

Why is there NO Sandbox system in the “New Implementation of SAP S/4HANA Cloud,
Single Tenant Edition” transition path?

1.) Because the Fit-to-Standard workshop is conducted using Q-system


2.) Because the customer may use the SAP Model Company.
3.) Because the project team uses the DEV system to confirm solution fit and define delta
requirements.
4.) Because SAP S/4HANA Cloud, Single Tenant Edition, contains predefined business
processes which should NOT be changed.

Correct Answer: 3
Explaination:

Question: 235

How often will an upgrade be performed on an SAP S/4HANA Cloud, Single Tenant Edition
environment?

1.) One Upgrade and Two Feature Packs per year


2.) Every Year
3.) Every Quarter
4.) Schedule is defined by Service Level Agreement for SAP HANA Enterprise Cloud and
SAP S/4HANA Cloud, Single Tenant Edition Service

Correct Answer: 4
Explaination:

Question: 236

In the “New Implementation of SAP S/4HANA” transition path, which systems are part of
the project system landscape? (2 Correct)

1.) QAS
2.) DEV
3.) P-system
4.) Starter system

Correct Answer: 1,2


Explaination:

Question: 237

Which tool can you use to collaborate with other SAP Activate Methodology Practitioners?

1.) SAP Jam


2.) SAP Implementation Assistant
3.) SAP Roadmap Viewer
4.) SAP Solution Manager

Correct Answer: 1

Explaination:
Question: 238

Which tools does SAP Activate provide to support Guided Configuration? (3 Correct)

1.) Solution Builder


2.) Expert Configuration
3.) Self Service Configuration
4.) SAP Solution Composer
5.) Model Company

Correct Answer: 1,2,3

Question: 239

What must you do when you implement SAP Business Suite On-Premise with SAP Best
Practices?

1.) Activate and apply SAP Best Practices content with the self-service configuration UI
2.) Activate and apply SAP Best Practices with SAP Solution Manager
3.) Apply SAP Best Practices with the Configure your Solution application
4.) Assemble and apply SAP Best Practices to the system

Correct Answer: 2

Question: 240

What capabilities does SAP API Business Hub provide to help you select integration
options for your project? (3 Correct)

1.) Advice on selecting scope items in SAP Best Practices Explorer


2.) Pre-packaged integrations
3.) Integration with Ide and code generation
4.) Recommendations on using integration bus (SAP Process Orchestration or SAP
Integration Suite)
5.) Sandbox for testing APIs

Correct Answer: 2,4,5

Question: 241
Which activities are part of the Application: Solution Adaption work stream of SAP
Activate for new implementations? (3 Correct)

1.) Value Audits


2.) Production Support Plan
3.) Value Determination
4.) Change Management Plan
5.) Scope Validation

Correct Answer: 1,3,4

Question: 242

What tool provides guidance on replacing custom code developed for SAP ERP with SAP
S/4HANA functionality for the "System Conversion" transition path?

1.) Software Update Manager with Database Migration Option


2.) Simplification Item Check (SI-Check)
3.) Software Provisioning Manager
4.) SAP Code Inspector

Correct Answer: 2

Question: 243

How do you gain access to the SAP Activate Methodology Jam site?

1.) Register on SAP Service Marketplace


2.) Send e-mail to SAP contact address
3.) Submit e-mail address via on-line form
4.) Join SAP S/4HANA group on SAP Community Network

Correct Answer: 3

Question: 244

What is the final activity in the Realize phase of a new implementation of SAP S/4HANA
cloud edition?

1.) Data migration


2.) End-to-End walkthrough
3.) Readiness check
4.) Solution validation
Correct Answer: 2

Question: 245

In which phase of the SAP Activate methodology does the team complete the
Transformation Planning?

1.) Deploy
2.) Explore
3.) Prepare
4.) Realize

Correct Answer: 3

Question: 246

In which of the following project phases is it important to plan and schedule data loads
followed by load validation activities?

1.) Explore
2.) Deploy
3.) Prepare
4.) Realize

Correct Answer: 1

Question: 247

Which of the following statements about Scrum is correct?

1.) In Scrum, the team is Self-organized, define all task necessary for all project life cycle.
2.) The three ceremonies are sprint planning, daily scrum, sprint review (retrospective).
3.) Scrum Master defines and prioritizes features and gathers requirements.
4.) In Scrum, as best practices, we have three main roles, and three artifacts or three
ceremonies.

Correct Answer: 2

Question: 248

Which of the following are not phases of the SAP Activate methodology? (2 Correct)
1.) Realize
2.) Preparation
3.) Go-Live & Support
4.) Prepare

Correct Answer: 2,3

Question: 249

What activities do you perform during the fit-to-standard workshops milestone in the SAP
Activate methodology within SAP Cloud ALM? (3 Correct)

1.) Create SAP Fiori screen mock-ups in SAP Cloud ALM.


2.) View details of high-level process flows in SAP Cloud ALM.
3.) Create notes and/or requirements in SAP Cloud ALM.
4.) Create wireframes for user interfaces in SAP Cloud ALM.
5.) View details of business process diagrams and descriptions in SAP Cloud ALM.

Correct Answer: 2,3,5

Question: 250

Which collaboration features can SAP Activate Jam users access? (2 Correct)

1.) Ask questions


2.) Update Key Deliverable wikis
3.) Tweet questions
4.) Comment on documents

Correct Answer: 1,4

Question: 251

In which SAP Activate methodology phase does the team complete the Transformation
Strategy?

1.) Deploy
2.) Realize
3.) Explore
4.) Prepare

Correct Answer: 3
Question: 252

What are the core capabilities in SAP Cloud ALM for implementation? (3 Correct)

1.) Portfolio management


2.) Custom code management
3.) Test management
4.) Task management
5.) Process management

Correct Answer: 3,4,5

Question: 253

What does a project jump-start include for a new implementation of SAP S/4HANA on-
premise edition?

1.) SAP Best Practices


2.) Rapid prototyping
3.) Project team training
4.) Full project SCRUM

Correct Answer: 1

Question: 254

What are the three elements of SAP Activate? (3 Correct)

1.) Content
2.) Methodology
3.) Focused Build
4.) Tools
5.) SAP Solution Manager

Correct Answer: 1,2,4

Question: 255

In which tools can the project team across the SAP Activate Methodology content
including accelerators? (2 Correct)
1.) SAP Community Network
2.) Roadmap Viewer
3.) SAP Jam
4.) SAP Service Marketplace

Correct Answer: 2,3

Question: 256

Which of the following activities support the Realize Phase of a System Conversion
journey to SAP S/4HANA On-Premise Edition? (2 Correct)

1.) Custom code Adjustment planning


2.) Data aging configuration
3.) Non-production systems migration
4.) Value determination

Correct Answer: 2,3

Question: 257

How can a customer get access to SAP Cloud ALM?

1.) SAP Cloud ALM fair usage rights are included in SAP Preferred Success and SAP
Preferred Care at NO additional cost.
2.) SAP Cloud ALM fair usage rights are included in SAP Enterprise Support, cloud
editions at NO additional cost.
3.) SAP Cloud ALM can be bought on the SAP Store.
4.) SAP Cloud ALM fair usage rights are included in SAP MA Attention and SAP Active
Attention at NO additional cost.

Correct Answer: 2

Question: 258

Which content packages are available in the SAP Package Library? (2 Correct)

1.) SAP Activate Methodology


2.) SAP Best Practices
3.) Solution Builder
4.) Rapid Deployment Solutions

Correct Answer: 2,4


Question: 259

What tool do you use to configure an SAP Business Suite on-premise solution?

1.) ABAP Workbench


2.) SAP Implementation Guide
3.) Configuration Composer
4.) Expert Configuration

Correct Answer: 2

Question: 260

How can the project manager help to keep momentum in the project and help to keep the
customer involved? (2 Correct)

1.) Increase the number of Q-Gates


2.) Add customer resources to the project to reduce the need for formal training
3.) Leverage agile cycles to build and test the solution
4.) Walk through the solution processes with the stakeholders

Correct Answer: 2,3

Question: 261

Which of the following is a Key Deliverable of the Prepare phase?

1.) Solution Scope and Value Determination


2.) Change Impact Analysis and Communication Plan
3.) Baseline Build
4.) Release and Sprint Plan

Correct Answer: 1

Question: 262

What are some of the values of SAP Cloud ALM for operations? (3 Correct)
1.) It provides end-to-end transparency.
2.) It provides a solution readiness check.
3.) It provides improved efficiency and automation.
4.) It provides license management capabilities.
5.) It provides reduced cost of operations.

Correct Answer: 1,3,5

Question: 263

How can SRCUM teams be organized?

1.) By job title


2.) By work stream
3.) By project phase
4.) By project governance level

Correct Answer: 2

Question: 264

What is a benefit of using Guided Configuration instead of the Implementation Guide?

1.) It ensures configuration is done using SAP Solution Manager


2.) It eliminates the need for Content Lifecycle Management
3.) It eliminates the need to generate transport requests for configuration settings
4.) It ensures SAP updates do NOT conflict with customer configurations

Correct Answer: 4

Question: 265

Which key activities does the Guided Configuration support you with? (3 Correct)

1.) Manage roles of configuration users


2.) Train new users
3.) Create test data
4.) Test configured processes
5.) View solution scope

Correct Answer: 2,4,5


Question: 266

What are some core objectives of business process monitoring? (2 Correct)

1.) To provide transparency over end-to-end processes


2.) To increase business process execution quality
3.) To provide process update and change feedback
4.) To provide reverse business process analysis

Correct Answer: 1,2

Question: 267

Which of the following activities are part of the Realize Phase of a System Conversion
journey to SAP S/4HANA On-Premise Edition? (3 Correct)

1.) Operations impact analysis


2.) Custom code adjustment
3.) Delta configuration
4.) Development system migration
5.) Sandbox system migration

Correct Answer: 2,3,4

Question: 268

Which of the following activities are performed in the Explore phase of SAP Activate in
SAP S/4HANA Implementation? (3 Correct)

1.) Adjusting custom code objects


2.) Implementing best practices
3.) Creating transactional data
4.) Organizational structure
5.) Changing master data

Correct Answer: 3,4,5

Question: 269

Which of the following are key aspects of business process monitoring? (3 Correct)
1.) Predefined KPIs with process content
2.) Root cause analysis
3.) Automated problem resolution
4.) Process change analysis
5.) Process mining reports

Correct Answer: 1,2,3

Question: 270

In which phase do you verify that the SAP Best Practice solution scenarios meet the
business needs of the customer?

1.) Explore
2.) Deploy
3.) Realize
4.) Prepare

Correct Answer: 1

Question: 271

What is the best target environment for a System Conversion journey is as described in
the SAP Activate methodology?

1.) SAP Hybris


2.) SAP S/4HANA Cloud Edition
3.) SAP S/4HANA On-Premise Edition
4.) Hybrid of SAP S/4HANA Cloud Edition and SAP S/4HANA On-Premise Edition

Correct Answer: 3

Question: 272

Which activity is part of the SAP Activate Methodology for a new implementation of SAP
S/4HANA on-premise edition but NOT of the cloud edition?

1.) End-to-End Integration Test


2.) User Acceptance Test
3.) Unit Test
4.) Technical System Test

Correct Answer: 4
Question: 273

In which phase of the SAP Activate methodology does the team complete the Cut-over
Rehearsal?

1.) Prepare
2.) Explore
3.) Realize
4.) Deploy

Correct Answer: 4

Question: 274

What can users do in the Roadmap Viewer tool?

1.) Display and navigate detailed SAP Activate methodology WBS


2.) Upload SAP Activate WBS into SAP Solution Manager7.1
3.) Download full SAP Activate methodology content for use off-line
4.) Create a customer-specific version of SAP Activate Methodology

Correct Answer: 1

Question: 275

The tasks associated with Landscape transportation are in which workstream?

1.) System & Data Migration


2.) Transition to Operations
3.) Technical Architecture and Infrastructure
4.) Application Solution Adoption

Correct Answer: 3

Question: 276

You are defining the testing strategy for your project. What would you include in a Scope
of Integration test?
1.) The functionality of end-to-end business processes
2.) The functionality of modular processes
3.) The connectivity between database and application servers
4.) The network communication

Correct Answer: 1

Question: 277

Which of the following is not correct about the REALIZE phase? (2 Correct)

1.) The beginning of the Realize phase the team prepares a list of all the requirements in a
backlog.
2.) The project team ensures that the build is meeting the business requirements.
3.) The team prepares for operations so that the functionality can be brought live.
4.) Detailed design workshops are held.

Correct Answer: 1,4

Question: 278

Which of the following SAP S/4HANA Landscape Transformation options are enabled? (3
Correct)

1.) System Upgrade


2.) System Consolidation
3.) Migration of Business Units
4.) Migration of Selected Applications
5.) Security Migration

Correct Answer: 2,3,4

Question: 279

Which of the following building blocks are part of the SAP S/4HANA platform? (2 Correct)

1.) SAP Fiori UX


2.) SAP HANA in-memory database
3.) SAP Solution Manager
4.) LOB Cloud Solution

Correct Answer: 1,2


Question: 280

Which of the following are examples of Ready-to-run SAP S/4HANA systems? (2 Correct)

1.) Fully Activated Appliance


2.) SAP Best Practices Explorer
3.) SAP Mission ControlCenter
4.) SAP Model Company

Correct Answer: 1,4

Question: 281

What is the key characteristic of Agile project delivery?

1.) Frequent and detailed project scheduling


2.) Formal and detailed documentation
3.) Iterative build with frequent inspections
4.) Frequent Quality Gates

Correct Answer: 3

Question: 282

How many deliverables are a part of the Key Deliverable 'Project Initiation'?

1.) Three
2.) Two
3.) One
4.) Four

Correct Answer: 4

Question: 283
What are the responsibilities of the Project Team on level 4 in the picture below? (2
Correct)

1.) Set Project policy, standards and oversight


2.) Set business priorities, goals and objectives
3.) Identify and resolve issues and risks
4.) Perform status reporting and communication

Correct Answer: 3,4

Question: 284

Which of the following is true about a cloud implementation project? (2 Correct)

1.) In the prepare phase of a cloud implementation project the project team provide the
customer with materials to review as self-enablement.
2.) The entire transport system is kept intact and up and running.
3.) The Starter System is specific to SAP S/4HANA Cloud.
4.) Starter Systems are not required to be in place for the 'Fit to Standard' workshops.

Correct Answer: 1,3

Question: 285

What are some of the values of SAP Cloud ALM for implementation? (3 Correct)
1.) NO additional cost of product
2.) Pre-loaded SAP Activate tasks
3.) Accelerated time to market
4.) Central cost and effort management
5.) Comprehensive document repository

Correct Answer: 1,2,3

Question: 286

What do you do during post cutover?

1.) Setup Operational Support


2.) Perform the Verification Session of the SAP Going Live Check
3.) Perform Technical System Test
4.) Conduct Organizational Readiness Check

Correct Answer: 2

Question: 287

When do you perform User Acceptance Testing during the Agile Build?

1.) Before Integration Testing


2.) During each Firm-up Sprint
3.) After each Sprint
4.) After Integration Testing

Correct Answer: 4

Question: 288

Which of the following are part of the 10 SAP Quality Principles? (2 Correct)

1.) Start scoping early.


2.) Plan one phase at a time.
3.) Use standard functionality optionally.
4.) Achieve production readiness.

Correct Answer: 1,4


Question: 289

What is the minimum number of Quality Gates mandated for SAP S/4HANA transition
projects?

1.) 2
2.) 3
3.) 4
4.) 5

Correct Answer: 3

Question: 290

Which of the following can be used to navigate through the roadmap? (2 Correct)

1.) Tasks
2.) Phases
3.) Workstreams
4.) Deliverables

Correct Answer: 2,3

Question: 291

SAP now offers the ability to deploy and manage solutions in which of the following
environments?

1.) Cloud and On-premise


2.) On-premise
3.) Cloud
4.) Cloud, On-premise and Hybrid

Correct Answer: 4

Question: 292

Which content is made available after you activate SAP Best Practices for a new financial
implementation? (2 Correct)

1.) Implementation Guide


2.) Online help
3.) Pre-configured business processes
4.) Standard chart of accounts
Correct Answer: 3,4

Question: 293

In which phase of the SAP Activate Methodology does the team complete the System
Assessment?

1.) Deploy
2.) Explore
3.) Prepare
4.) Realize

Correct Answer: 3

Question: 294

What is the correct order of the SAP Activate Methodology phases?

1.) Plan -> Design -> Build -> Operate


2.) Discover -> Prepare -> Explore -> Realize -> Deploy -> Run
3.) Plan -> Build -> Run -> Sustain
4.) Prepare -> Discover -> Explore -> Realize -> Deploy -> Run

Correct Answer: 2

Question: 295

Which key deliverable includes the development of RICEFW objects?

1.) Development Build


2.) Enhancement Delivery
3.) Sprint Execution
4.) Custom Extensions Management

Correct Answer: 2

Question: 296

How are the build and test tasks planned and executed in the Realize phase?
1.) By using the sprint backlog list as input for each iteration.
2.) By executing regression tests after each iteration
3.) With Q-Gates for sign off after each iteration
4.) By using incremental build in fixed-scope iteration

Correct Answer: 4

Question: 297

Which of the following tools is used to install SAP S/4HANA?

1.) SAP Solution Manager


2.) SWPM (Software Provisioning Manager)
3.) Cloud Application Library
4.) Data Migration server

Correct Answer: 2

Question: 298

Which of the following Key Deliverables do you complete in the Solution Design work
stream in the Explore phase? (3 Correct)

1.) Design for the Gaps and Deltas


2.) Baseline Build
3.) Data Migration Approach
4.) Validation Workshops
5.) Solution Scope and Value Determination

Correct Answer: 1,4,5

Question: 299

In which phase do you run the user acceptance test?

1.) Deploy
2.) Realize
3.) Build and Test
4.) Final Preparation

Correct Answer: 2
Question: 300

What is the purpose of the Solution Builder tool in the SAP Activate Guided Configuration?

1.) To activate the Best Practices content


2.) To create delta building blocks for complementary content
3.) To personalize activated, ready-to run business processes
4.) To create customer-specific scope items

Correct Answer: 1

Question: 301

Which activities are part of the Design and Configuration application of the SAP Activate
methodology? (2 Correct)

1.) Perform Fit/Gap Analysis


2.) Schedule kick-off workshop
3.) Conduct Scope Validation
4.) Confirm Integration prerequisites

Correct Answer: 1,3

Question: 302

Your project is preparing for the Fit/Gap analysis workshops. If you use the Agile
approach, what sequence of activities do you perform in the Explore Phase?

1.) a. Conduct Solution Validation workshops b. Set reference value c. Prioritize initial
backlog d. Conduct Delta Design workshops
2.) a. Set reference value b. Prioritize initial backlog c. Conduct Delta Design workshops
d. Conduct Solution Validation workshops
3.) a. Conduct Solution Validation workshops b. Conduct Delta Design workshops c. Set
reference value d. Prioritize initial backlog
4.) a. Set reference value b. Conduct Solution Validation workshops c. Prioritize initial
backlog d. Conduct Delta Design workshops

Correct Answer: 4

Question: 303

Which of the following are the benefits of SAP JAM? (2 Correct)


1.) Easy to use
2.) Reduced Recovery Time
3.) Highly available
4.) User collaboration

Correct Answer: 1,4

Question: 304

Which of the following is not a characteristic that the quality principles are based on?

1.) Experience of Typical Pitfalls


2.) Best Practices
3.) SAP Quality Award example winners
4.) International standard

Correct Answer: 4

Question: 305

Identify the two landscape transformation specific tasks in the explore phase. (2 Correct)

1.) Setup Landscape Transformation Software


2.) Define the Data Migration Architecture
3.) Perform Client transfer
4.) Run a Landscape Transformation Assessment

Correct Answer: 1,4

Question: 306

What is the purpose of the SAP Activate Methodology?

1.) To enable access to the SAP ecosystem


2.) To accelerate the initial implementation of SAP S/4HANA
3.) To provide end-to-end integrated application lifecycle management
4.) To manage project and solution documentation

Correct Answer: 2

Question: 307
What is a difference between the SAP Activate methodology for a new implementation of
SAP S/4HANA cloud edition and a new implementation of SAP S/4HANA on-premise?

1.) For the cloud edition, there is an additional work stream for integration with on-
premise systems
2.) For the cloud edition, there is an additional Q-Gate for integration with on-premise
systems
3.) For on-premise, there is an additional Q-Gate for system installation
4.) For on-premise, there are additional deliverables for the system setup

Correct Answer: 4

Question: 308

Which accelerations can you use during the Scope Validation/Fit-Gap Analysis activity in
the Explore Phase? (2 Correct)

1.) Sprint Backlog Template


2.) RICEF Specification Template
3.) Solution Validation Workshop
4.) Quality Gate Checklist

Correct Answer: 2,3

Question: 309

Which artifacts in the Testing work stream are created within the Realize phase for the
New Implementation of SAP S/4HANA Cloud" transition path? (2 Correct)

1.) Functional Test Scenarios


2.) Functional Specifications
3.) Reporting Functional Specifications
4.) User Acceptance Test – Plan

Correct Answer: 1,4

Question: 310

How do you achieve frequent checkpoints with the end user in an Agile delivery
approach? (2 Correct)
1.) Solution Demo for Sprints
2.) Demo the SAP Model Company
3.) User Acceptance Test
4.) Solution Review for Waves

Correct Answer: 1,3

Question: 311

Which of the following are available in the initial SAP Methodologies JAM Page? (2
Correct)

1.) Roadmaps
2.) Accelerators
3.) Task description
4.) Summary

Correct Answer: 1,2

Question: 312

Which of the following are included in ready-to-use content in SAP Activate? (2 Correct)

1.) Business models from leading companies in each industry sector


2.) Project accelerators
3.) SAP Best Practices
4.) Courses delivered by SAP Education

Correct Answer: 2,3

Question: 313

What is the key difference between Notes and Requirements in the Change and Deploy
capability of SAP Cloud ALM?

1.) Notes are created from tasks.


2.) Requirements are created from tasks.
3.) Users can create a follow-up task that is actionable for Requirements.
4.) Users can create a follow-up task that is actionable for Notes.

Correct Answer: 3
Question: 314

In which SAP Activate methodology phase does the team identify and design functional
quick wins in scope of the conversion project?

1.) Realize
2.) Deploy
3.) Prepare
4.) Explore

Correct Answer: 4

Question: 315

In what respect is SAP Activate Methodology different from the ASAP Methodology?

1.) Supports cloud deployments


2.) Supports only new implementations
3.) Leverages iterative incremental build
4.) Includes Fit/Gap analysis instead of Blueprint

Correct Answer: 4

Question: 316

What are the three pillars of SAP Activate? (3 Correct)

1.) SAP Activate Methodology


2.) SAP Best Practices
3.) SAP S/4HANA in-memory database
4.) SAP Solution Manager
5.) Guided Configuration

Correct Answer: 1,2,5

Question: 317

Which component of SAP Activate offers customers a reference solution in the cloud for a
quick start?

1.) SAP Implementation Assistant


2.) SAP Activate Methodology
3.) Guided Configuration
4.) SAP Best Practices
Correct Answer: 4

Question: 318

In SAP Activate, what replaces the detailed Blueprint from ASAP?

1.) Business Process Mapping


2.) Value Determination
3.) Custom Extension management
4.) Fit/Gap Workshops

Correct Answer: 4

Question: 319

Which of the following tasks are required in the Prepare Phase? (3 Correct)

1.) Train the project team


2.) Set up the infrastructure to support the project
3.) Define the communication plan
4.) Approve the test strategy
5.) Identify relevant SAP Best Practices

Correct Answer: 1,2,5

Question: 320

Which of the following is a key characteristic of the Agile project approach?

1.) Formal and detailed documentation


2.) Frequent and detailed project scheduling
3.) Frequent quality gates
4.) Iterative build with frequent inspections

Correct Answer: 4

Question: 321

In which SAP Activate methodology phase does the team complete the Integration
Validation?
1.) Explore
2.) Realize
3.) Deploy
4.) Prepare

Correct Answer: 2

Question: 322

Which of the following is not correct about workstreams? (2 Correct)

1.) It can span phases


2.) It is assigned as an attribute to phases, deliverables and tasks
3.) It is a collection of related deliverables
4.) Workstreams are dependent on phase start and end

Correct Answer: 2,4

Question: 323

What is the hierarchy level under Phase in the SAP Jam space for SAP Activate on-
premise?

1.) Key Deliverable


2.) Scenario
3.) Work Stream
4.) Task

Correct Answer: 1

Question: 324

What do you do during an iterative approach to build a solution?

1.) Build the solution module by module


2.) Deliver a prototype of the solution
3.) Provide a working solution only at the end of the release
4.) Include frequent inspection check-points

Correct Answer: 4
Question: 325

What are the core capabilities in SAP Cloud ALM for operations? (3 Correct)

1.) Upgrade analysis


2.) Operation automation
3.) Monitoring
4.) Event and alert management
5.) License management

Correct Answer: 2,3,4

Question: 326

In Which phase does the Transition to Operations work stream start?

1.) Explore
2.) Realize
3.) Deploy
4.) Prepare

Correct Answer: 3

Question: 327

Which pre-loaded content is available in SAP Cloud ALM for implementation? (2 Correct)

1.) Activate methodology tasks


2.) Business process best practice content
3.) Software configurations
4.) Roles and authorizations

Correct Answer: 1,2

Question: 328

Which deliverable is specific to on-premise and NOT for the cloud?

1.) Technical Design Solution


2.) Knowledge Transfer
3.) Adaptation Specification
4.) Learning Needs Analysis

Correct Answer: 2
Question: 329

What is a deliverable of the Application. Customer Team Enablement work stream in the
Prepare phase of SAP Activate?

1.) Project Charter


2.) Project Documentation
3.) Knowledge transfer to end users
4.) Learning plan

Correct Answer: 4

Question: 330

Which new project roles are introduced with the SAP Activate methodology for the Agile
delivery approach, compared to waterfall? (2 Correct)

1.) SCRUM Master


2.) Product Owner
3.) Integration Lead
4.) Design Thinking Coach

Correct Answer: 1,2

Question: 331

What is a key characteristic of SAP Activate for new implementations of S/4HANA cloud
edition?

1.) Start with executable content


2.) Limited involvement of business stakeholders
3.) Waterfall approach
4.) Design-based

Correct Answer: 1

Question: 332

Which of the following activities are part of the Deploy Phase of a Landscape
Transformation journey to SAP S/4HANA On-Premise Edition? (2 Correct)
1.) Solution Activation
2.) Optimize software Change Control Management
3.) Training delivery
4.) Access organizational and production readiness

Correct Answer: 3,4

Question: 333

Which of the following content best outlines the scope of the Integration Test?

1.) a. Prototype b. Delta/gap solutions c. Data flows with non-SAP application


2.) a. Prototype b. Delta configuration c. Data flows between SAP solutions
3.) a. Solution baseline b. Delta/gap solutions c. Data flows with non-SAP application
4.) a. Solution baseline b. Delta configuration c. Data flows between SAP solutions

Correct Answer: 3

Question: 334

In which phase do you create a prioritized list of user requirements?

1.) Realize
2.) Explore
3.) Prepare
4.) Deploy

Correct Answer: 2

Question: 335

The hyper care period is part of which phase?

1.) Realize
2.) Explore
3.) Deploy
4.) Go-Live

Correct Answer: 3

Question: 336
Where can you find Project Library Accelerators?

1.) SAP Best Practices Explorer


2.) SAP Cloud Appliance Library
3.) Fully Activated Appliance
4.) SAP Roadmap Viewer

Correct Answer: 4

Question: 337

Which of the following are the key responsibilities of the Scrum Master? (3 Correct)

1.) Task initiator


2.) Responsible for the project delivery
3.) Team protection
4.) Leadership skill
5.) Team support

Correct Answer: 3,4,5

Question: 338

Which accelerator can help you document the detailed design of solution extensions?

1.) Sprint Backlog Template


2.) RICEF Specification Template
3.) Change Request Template
4.) Product Backlog Template

Correct Answer: 2

Question: 339

Which of the following scenarios are enabled for the "Selective Data Transition" transition
path with the SAP Landscape Transformation tool? (3 Correct)

1.) Security Migration


2.) System Upgrade
3.) Extraction of Business Units
4.) System Consolidation
5.) Consolidation through online data replication

Correct Answer: 3,4,5


Question: 340

Which of the following tasks are part of the Production support after the Go Live key
deliverable? (2 Correct)

1.) Resolve issues identified during the Hyper Care period


2.) Provide further training to customer end users
3.) Set up the Operations Control Center
4.) Perform a Technical systems test

Correct Answer: 1,2

Question: 341

Which artifacts are created within Application Design and Configuration work stream in
the Explore phase of the "New Implementation of SAP S/4HANA" transition path? (3
Correct)

1.) Delta Requirements List - Register


2.) Roles and Authorizations Management Concept
3.) Project Procedure - Mock-up Modeling
4.) Detailed Design - Business Process
5.) Organization Structure Specification

Correct Answer: 1,4,5

Question: 342

Which navigation option do you use in the Roadmap Viewer to access the SAP Activate
Methodology content?

1.) Navigate by assigned Delivery Mode


2.) Navigate by RACI matrix accountability
3.) Navigate by work stream
4.) Navigate by Project Team Member Role

Correct Answer: 3

Question: 343

Which of the following is not correct about Fit/Gap Analysis? (2 Correct)


1.) Minimize the needs for rework during realization.
2.) Validate pre-activate and pre-assembled solution in the development system.
3.) Prioritize delta requirement and gaps.
4.) Drive towards adopting customers processes.

Correct Answer: 2,4

Question: 344

Which of the following tools are used for rapid database migration? (2 Correct)

1.) Software Update Manager (SUM)


2.) Database Migration Option (DMO)
3.) SWPM (software provisioning manager)
4.) SAP Solution Manager

Correct Answer: 1,2

Question: 345

What are deliverables of the Application: Integration work stream in the prepare phase?
(3 Correct)

1.) Fit/Gap Analysis


2.) Data Cleansing
3.) Security Checks
4.) Adaptation Specifications
5.) Network Connectivity Checks

Correct Answer: 3,4,5

Question: 346

What can you do in the SAP Roadmap Viewer tool?

1.) Create a customer-specific version of a roadmap.


2.) Navigate detailed Solution Implementation Roadmaps.
3.) Download full roadmap content for offline navigation.
4.) Comment on Deliverables and Tasks within Roadmaps.

Correct Answer: 2
Question: 347

Your project is performing some high-level planning for a System Conversion journey from
SAP Business Suite to SAP S/4HANA on-premise edition. What is the correct sequence of
selected key deliverables across the project phases?

1.) a. Code adjustment b. Detailed System Assessment c. Production Readiness Check d.


Validation of Migration
2.) a. Production Readiness Check b. Detailed system Assessment c. Code Adjustment d.
Validation of Migration
3.) a. Detailed system Assessment b. Code Adjustment c. Validation of Migration d.
Production Readiness Check
4.) a. Detailed system Assessment b. Production Readiness Check c. Code Adjustment d.
Validation of Migration

Correct Answer: 3

Question: 348

What structure level do you see when you access the Roadmap Viewer and chose work
stream navigation?

1.) Deliverable
2.) Scenario
3.) Task
4.) Scope Item

Correct Answer: 1

Question: 349

Which statements are part of the 5 Golden Rules for SAP S/4HANA Cloud, Single Tenant
Edition? (2 Correct)

1.) Foster a cloud mindset and adherence to the Fit-to-Standard approach.


2.) Document deviations from Golden Rules for transparency and future use in upgrades.
3.) Stick to the security standards of the customer organization.
4.) Use SAP Solution Manager 7.2 with Focused Build.

Correct Answer: 1,2

Question: 350

Which of the following are the pillars of SAP Activate? (3 Correct)


1.) SAP Launch Methodology
2.) SAP Activate Methodology
3.) SAP ASAP Methodology
4.) Guided Configuration
5.) SAP Best Practices

Correct Answer: 2,4,5

Question: 351

What are two important approaches, based on the Control Center concept that SAP
proposes to use for streamlined implementation and operations within Premium
Engagements? (2 Correct)

1.) Build SAP Like a Factory


2.) Always Connected
3.) Intelligent Enterprise
4.) Run SAP Like a Factory

Correct Answer: 1,4

Question: 352

What does a cutover involve?

1.) Closing quality gate


2.) Transport ng new product increment in the development system
3.) Presenting completed User Story to key users
4.) Switching productive business operations from one system to another

Correct Answer: 4

Question: 353

Arrange the following in the correct sequence of steps followed for a 'Fit to Standard'
workshop.
1.) Discuss how the process fit with customer requirements, Review Best Practice Process
Flow, Demonstrate Business Scenarios and Concepts, Identify required configuration,
Enable customer on execution of scenarios, Identify gaps
2.) Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts,
Identify required configuration, Discuss how the process fit with customer requirements,
Enable customer on execution of scenarios, Identify gaps
3.) Demonstrate Business Scenarios and Concepts, Review Best Practice Process Flow,
Identify required configuration, Discuss how the process fit with customer requirements,
Enable customer on execution of scenarios, Identify gaps
4.) Review Best Practice Process Flow, Demonstrate Business Scenarios and Concepts,
Discuss how the process fit with customer requirements, Identify gaps, Identify required
configuration, Enable customer on execution of scenarios

Correct Answer: 4

Question: 354

Which Value Chains does SAP Solution Manager 7.2 deliver? (3 Correct)

1.) Detect-to-Correct
2.) Request-to-Fulfill
3.) Hire-to-Retire
4.) Requirements-to-Deploy
5.) Cash-to-Order

Correct Answer: 1,2,4

Question: 355

What is the purpose of the Solution Validation activity in the Explore phase? (3 Correct)

1.) To verify technical installation


2.) To identify gaps
3.) To log additional scope items
4.) To challenge changes to standard
5.) To educate project participants

Correct Answer: 2,3,4

Question: 356

What are the benefits of the SAP best practices? (3 Correct)


1.) Fast time to value
2.) Predictable results
3.) Simple on-boarding to cloud
4.) Fixed organizational structure
5.) Reduced functional scope

Correct Answer: 1,2,3

Question: 357

When applying a cloud mindset in a greenfield Implementation, which of the following


should you consider? (2 correct)

1.) Apply SAP quality principles


2.) Use supported extensibility technologies
3.) Use quality gates
4.) Ensure transparency on deviations

Correct Answer: 2,4

Question: 358

Which of the following is the customer's responsibility in both on-premise and private
cloud scenarios?

1.) Middleware
2.) Operating system
3.) Database
4.) Servers

Correct Answer: 4

Question: 359

Which of the following are SAP Activate workstreams? (2 correct)

1.) Data Migration


2.) Change Management
3.) Extensibility
4.) Project Management

Correct Answer: 3,4


Question: 360

Which tool do you use to configure SAP S/4HANA Cloud, public edition?

1.) IMG (Implementation Guide)


2.) SAP Cloud ALM
3.) SAP Solution Manager
4.) SAP Central Business Configuration

Correct Answer: 4

Question: 361

In which workshop do you validate SAP standard functionality and collect delta
requirements?

1.) Fit-to-standard
2.) Fit-to-gap
3.) Solution validation
4.) Design thinking

Correct Answer: 1

Question: 362

When working with an Agile approach, what is the minimum planning requirement
expected at the beginning of the Realize phase?

1.) Sprint planning and sprint durations should be defined for the first 2 to 3 sprints.
2.) Realize phase scope, planning, and budget should be completed and final.
3.) Release plan and sprint ceremony guidelines should be finalized.
4.) User stories on product backlog should be in ready state for the first 2 to 3 sprints.

Correct Answer: 4

Question: 363

What is preferred when a customer wants to keep most of their original processes and
migrate to SAP S/4HANA Cloud, private edition?
1.) System Conversion
2.) Selective Data Transition
3.) Mix and Match
4.) Shell Conversion

Correct Answer: 1

Question: 364

When performing an SAP Readiness Check in system conversion, what areas are covered
within the result? (3 correct)

1.) Recommended SAP Fiori apps


2.) Sizing for SAP S/4HANA
3.) Simplification database
4.) SAP and third party interfaces
5.) Active business functions

Correct Answer: 1,2,5

Question: 365

Which of the following are workshop design principles/guidelines? (2 correct)

1.) Fit-to-standard
2.) Expert configuration definitions
3.) Best Practices enablement
4.) Active participation

Correct Answer: 1,2

Question: 366

Which additional scope option does the strategic advisory service for cloud analytics
offer? (2 correct)

1.) SAP Activate methodology for the Intelligent Enterprise


2.) Baseline package
3.) SAP S/4HANA for central finance
4.) Extended package

Correct Answer: 1,2


Question: 367

What can you find in the SAP Fiori apps reference library? (3 correct).

1.) Related app recommendations based on your usage profile


2.) Shortcut to the Quicksizer tool to estimate hardware requirements
3.) Shortcut to the Maintenance Planner tool to establish the technical update path
4.) Installation and configuration requirements for selected apps
5.) Related app-specific SAP Fiori design guidelines

Correct Answer: 1,3,4

Question: 368

Which systems are part of the private cloud edition landscape? (2 correct)

1.) Sandbox
2.) Evaluation
3.) Production
4.) Starter

Correct Answer: 2,3

Question: 369

Which collaboration features are available in the SAP Community? (2 correct)

1.) Tweet questions


2.) Comment on Key Deliverables
3.) Ask questions
4.) Update Key Deliverable wikis

Correct Answer: 2,3

Question: 370

Which of the following are cornerstones of SAP's security strategy? (3 correct)

1.) Secure Infrastructure


2.) Secure Company
3.) Secure Products
4.) Secure Operations
5.) Secure Projects
Correct Answer: 2,3,4

Question: 371

What is the objective of using scaling Scrum techniques when coordinating large teams in
complex projects?

1.) To bring all specialists, such as the company legal advisors, into the scrum team
2.) To manage the flow of information between the project and stakeholders
3.) To reallocate staff to skill-based teams such as developers in one single team
4.) To ensure alignment in architecture, configuration, and integration

Correct Answer: 4

Question: 372

Which estimation technique can you use in an Agile delivery approach to size the user
stories during sprint planning?

1.) Detailed top-down effort estimate by the Scrum Master in story points, based on the
user story complexity
2.) Detailed bottom-up effort estimate by the product owner that breaks up each story into
short tasks
3.) Relative effort estimate in Ideal Person Days that reflects the best estimate by the
project team
4.) Project Manager's relative effort estimate that will be needed to implement and test
the user story

Correct Answer: 1

Question: 373

In which of the following do you use a work item in Focused Build?

1.) Epics
2.) Waves
3.) Sprints
4.) Releases

Correct Answer: 3
Question: 374

What findings do you document in the Explore Phase workshops? (3 correct).

1.) Detailed design of extensions


2.) Key business decisions
3.) Business role mapping
4.) Process models
5.) Confirmation of scope

Correct Answer: 2,4,5

Question: 375

Which of the following tools are considered enablers for digital transformation? (3
correct).

1.) SAP Product Availability Matrix


2.) Software Logistics Toolset
3.) SAP Roadmap Viewer
4.) SAP Best Practices Explorer
5.) SAP Activate Community

Correct Answer: 3,4,5

Question: 376

In which phase do you collect the main attributes of the product as per the Agile
definition?

1.) Deploy
2.) Realize
3.) Prepare
4.) Explore

Correct Answer: 4

Question: 377

What is the difference between the System Conversion and New Implementation
transition paths to SAP S/4HANA? (2 correct)
1.) Custom code is developed in System Conversion and adjusted in New Implementation
of SAP S/4HANA in the Realize phase.
2.) Data is converted in System Conversion and migrated in New Implementation of SAP
S/4HANA in the Realize phase.
3.) Custom code is adjusted in System Conversion and developed in New Implementation
of SAP S/4HANA in the Realize phase.
4.) Data is migrated in System Conversion and converted in New Implementation of SAP
S/4HANA in the Realize phase.

Correct Answer: 2,3

Question: 378

What is the difference between the System Conversion and New Implementation
transition paths to SAP S/4HANA? (2 correct)

1.) Custom code is developed in System Conversion and adjusted in New Implementation
of SAP S/4HANA in the Realize phase.
2.) Data is converted in System Conversion and migrated in New Implementation of SAP
S/4HANA in the Realize phase.
3.) Custom code is adjusted in System Conversion and developed in New Implementation
of SAP S/4HANA in the Realize phase.
4.) Data is migrated in System Conversion and converted in New Implementation of SAP
S/4HANA in the Realize phase.

Correct Answer: 2,3

Question: 379

Which of the following are used to perform configuration in SAP S/4HANA Cloud, private
edition?

1.) Self Service Configuration Uls (SSCUIs)


2.) SAP Solution Manager
3.) SAP Central Business Configuration
4.) IMG (Implementation Guide)

Correct Answer: 4

Question: 380

Your customer is using a non-SAP ERP system and decides to implement SAP S/4HANA.
Which of the following options are available to your customer? (3 correct).
1.) New Implementation SAP S/4HANA Cloud, public edition
2.) System Conversion SAP S/4HANA
3.) New Implementation SAP S/4HANA Cloud, private edition
4.) System Conversion SAP S/4HANA Cloud, private edition
5.) New Implementation SAP S/4HANA

Correct Answer: 1,3,5

Question: 381

Which accelerators support the fit-to-standard workshop in the Explore phase? (2 correct)

1.) Quality gate checklist and quality gate guide


2.) Requirements feature in SAP Cloud ALM
3.) Test strategy document
4.) Business-Driven Configuration questionnaire

Correct Answer: 1,4

Question: 382

In which workstream do you execute an organizational change impact analysis?

1.) Solution Adoption


2.) Analytics
3.) Application Design and Configuration
4.) Data Management

Correct Answer: 1

Question: 383

Which task should you include in your procedure while preparing for a fit-to-standard
analysis in an SAP Data Warehouse Cloud project? (2 correct)

1.) Review all the necessary Implementation Design Principles (IDPs).


2.) Review all the necessary leading practice process diagrams.
3.) Review available SAP S/4HANA accelerators for the Data Management workstream.
4.) Review SAP S/4HANA best practices availability for your country.

Correct Answer: 2,4


Question: 384

You are implementing SAP S/4HANA Cloud, public edition for your customer. How are
your customer systems activated?

1.) Via the SAP Contact Center


2.) Via the Central Business Configuration System
3.) Via the SAP Business Technology Platform
4.) Via the SAP Cloud ALM

Correct Answer: 2

Question: 385

Which of the following steps are part of the fit-to-standard process? (2 correct)

1.) Design to-be business process models


2.) Enable customers on standard business processes
3.) Document integration requirements
4.) Review Best Practices process flow

Correct Answer: 2,4

Question: 386

Which products are addressed in the SAP Activate methodology for the Intelligent
Enterprise roadmap? (2 correct)

1.) SAP Ariba


2.) SAP Fieldglass
3.) SAP S/4HANA
4.) SAP Concur

Correct Answer: 2,4

Question: 387

What transition scenarios are possible when adopting RISE with SAP? (3 correct).

1.) New Implementation


2.) Shell Conversion
3.) Lift and Shift
4.) Mix and Match
5.) System Conversion
Correct Answer: 1,3,5

Question: 388

You are transitioning to SAP S/4HANA.In which phase do you adjust custom code?

1.) Deploy
2.) Discover
3.) Explore
4.) Realize

Correct Answer: 4

Question: 389

Which of the following best outlines the sequence of testing in the Realize phase?

1.) 1. String test 2. User Acceptance Test 3. Integration Test


2.) 1. Data Migration 2. String test 3. User Acceptance Test
3.) 1. String test 2. Integration Test 3. User Acceptance Test
4.) 1. Integration Test 2. User Acceptance Test 3. String test

Correct Answer: 3

Question: 390

Which of the following characteristics relate to the Focused Build for SAP Solution
Manager functionality? (2 correct)

1.) SAP delivers a standard solution without any additional coding required
2.) SAP delivers all knowledge required with the solution.
3.) SAP delivers a standard solution with its own separate license
4.) SAP delivers all configuration activities within your project

Correct Answer: 1,2

Question: 391

Which activity helps the project team identify and add user stories to the backlog?
1.) Preparing a project schedule and budget
2.) Planning the User Acceptance Testing
3.) Conducting the fit-to-standard workshop
4.) Assessing project risks and issues

Correct Answer: 3

Question: 392

Which functionality is available in Focused Build?

1.) Integration Monitoring


2.) Test Management
3.) User Experience Monitoring
4.) Custom Code Management

Correct Answer: 2

Question: 393

A customer with an existing SAP S/4HANA solution is exploring the best approach to move
their landscape into the cloud. Which is the most suitable option for the customer?

1.) System Conversion


2.) Mix and Match
3.) Selective Data Transition
4.) Lift and Shift

Correct Answer: 4

Question: 394

When deploying a new implementation on-premise, which of the following is


recommended when performing custom development?

1.) SAP ABAP Workbench


2.) SAP Business Technology Platform
3.) SAP Best Practices
4.) SAP API Business Hub

Correct Answer: 1
Question: 395

Which of the following activities take place during the Discover phase in an SAP
BW/4HANA implementation? (2 correct)

1.) Discuss the Benefits of SAP Data Warehouse Cloud.


2.) Create, review, and sign off the Create Project Management Plan.
3.) Discuss the Benefits and Functionality of SAP Analytics Cloud.
4.) Create, review, and sign off the Project Charter.

Correct Answer: 1,4

Question: 396

Which of the following characteristics are unique to SAP S/4HANA Cloud, public edition?
(3 correct).

1.) Optional 3-system landscape


2.) Mandatory upgrades
3.) Software upgrades performed by SAP
4.) Customer data center deployment
5.) Choice of hardware vendor

Correct Answer: 1,2,3

Question: 397

Which of the following Accelerators can you find in the SAP Best Practices Explorer? (2
correct)

1.) Process Diagram


2.) Stakeholder Identification Guide
3.) Test Case
4.) Test Strategy

Correct Answer: 1,3

Question: 398

Which of the following are levels in the structure of an SAP Best Practices for SAP
S/4HANA Solution Package? (2 correct)
1.) Configuration Guides
2.) Building Blocks
3.) Business Process Scenarios
4.) Scope Items

Correct Answer: 2,4

Question: 399

When doing a new implementation on premise or private cloud, which system is


recommended to demonstrate standard functionality in the Explore phase?

1.) Trial
2.) Starter
3.) Sandbox
4.) Development

Correct Answer: 3

Question: 400

Which of the following tools can support you in managing requirements and software
development for implementation projects? (2 correct)

1.) Focused Build for SAP Solution Manager


2.) Focused Insights for SAP Solution Manager
3.) SAP Focused Run
4.) SAP Cloud ALM

Correct Answer: 1,4

Question: 401

Which of the following capabilities does SAP Solution Manager Test Suite support? (2
correct)

1.) Load and volume testing


2.) Multi-technology change impact analysis
3.) Tests for SAP and non-SAP solutions
4.) Manual and automated functional tests

Correct Answer: 2,4


Question: 402

Which of the following are capabilities of the test automation tool for SAP S/4HANA
Cloud, public edition? (2 correct)

1.) Captures test results with screenshots


2.) Supports the creation of custom test automates
3.) Supports recording of transaction-based processes
4.) Raises test defects automatically

Correct Answer: 2,3

Question: 403

From which platform are you able to deploy a trial system within a short timeframe?

1.) SAP Business Technology Platform


2.) SAP Learning Hub
3.) SAP Support Portal
4.) SAP Cloud Appliance Library

Correct Answer: 4

Question: 404

Which system tenants are the first to be provisioned when implementing SAP S/4HANA
Cloud, public edition?

1.) SAP S/4HANA sandbox system


2.) SAP S/4HANA starter system
3.) Central Business Configuration System
4.) SAP Cloud Identity Services

Correct Answer: 3

Question: 405

When conducting an upgrade of an SAP S/4HANA Cloud, public edition three system
landscape, in which phase are the Business Roles updated?
1.) Discover
2.) Deploy
3.) Realize
4.) Explore

Correct Answer: 2

Question: 406

Which of the following tools facilitate secure communication between SAP cloud solutions
and protected on-premise networks that CANNOT be accessed directly from the Internet?

1.) Cloud Integration Automation service


2.) Identity Authentication service
3.) SAP Connectivity service
4.) SAP Business Technology Platform

Correct Answer: 3

Question: 407

Which of the following considerations apply when determining the project methodology?
(3 correct).

1.) Solution fit


2.) Organizational fit
3.) Project fit
4.) Implementation fit
5.) Project Manager fit

Correct Answer: 2,3,5

Question: 408

For which of the following products do you find a specific set of best practices for the
public sector?

1.) SAP SuccessFactors Employee Central


2.) SAP S/4HANA Cloud, public edition
3.) SAP Marketing Cloud
4.) SAP S/4HANA

Correct Answer: 1
Question: 409

Which of the following are Selective Data Transition scenarios? (3 correct)

1.) Migration of business units


2.) Migration of open items
3.) Migration of transactional data
4.) Consolidation
5.) Migration of selected applications

Correct Answer: 1,4,5

Question: 410

What activity do you perform during the daily stand-up meeting?

1.) Negotiate acceptance criteria.


2.) Report showstoppers.
3.) Re-baseline the release plan.
4.) Provide end users with a demo of the new features.

Correct Answer: 2