Final Project
Final Project
PROJECT MANAGEMENT
A project is an interrelated set of activities that has a definite starting and ending
point and that result in a unique product or service. Project Management Project
management is a scientific way of planning, implementing, monitoring
&controlling the various aspects of a project such as time, money, materials,
manpower, other resources.
Activity
Event Event
CPM is akin to PERT as both techniques use similar network models and
methods are having the same general purpose.
But CPM is primarily concerned with the trade-off between cost and time.
It has been applied mostly to projects that employ fairly stable technology
and are relatively risk free.
Hence its orientation is 'deterministic'
Forward pass:-
Earliest start time (ES):-Earliest time an activity can start where ES=
maximum EF of immediate predecessors.
Earliest finish time (EF):- Earliest time an activity can finish and earliest
start time plus activity time EF-ES +t.
Backward pass: -
Latest start time (LS):- Latest time is an activity can start without delaying
critical path time.
Latest finish time (LF):- Latest time is an activity can be completed without
delaying critical path time.
LS= minimum LS of immediate predecessors
Slack time: - slack time for an activity is the difference between its earliest
and latest start time or between the earliest and the latest finish time.
Critical path is the path of activities having zero slack time.
T = (a+4m+b)/6
Why PERT/CPM
CPM PERT
1. It is an activity oriented 1. It is an event oriented technique.
technique. 2. It uses three times an estimate that
2. It its only one time estimate. is optimistic time, most likely time
3. It uses network diagram and pessimistic time.
4. It is deterministic 3. It uses network diagram
5. It takes cost parameters into 4. It is probabilistic
account 5. It does not take cost parameters
6. The concept of 'crashing' is into account
applied 6. There is no 'crashing' in PERT
7. It is normally used where the 7. It is normally used when high
emphasis is on tradeoff precision is required in time
between cost and completion estimates without considering the
date for large projects. cost implications.
8. E.g. plant maintenance, civil
construction
Advantages of PERT/CPM
Disadvantages of PERT/CPM
Crashing of project
Crashing a project implies reducing the duration of the project by
employing more resources to it.
procedure for crashing:-
1. Construct the network diagram and find critical path.
2. Examine cost time slop of different activities on the critical
path which is calculated as cost slop
Floats
Total float is the amount of time by which an activity may be delayed
without delaying the project completion
Caution: interpret total floats of activities carefully - all cannot be used
independently
Free float is that part of total float which can be used without affecting
floats of the succeeding activities
Independent float is the amount of time which can be used without
affecting the head and the tail events Total Float ≥ Free Float ≥
Independent Float
Calculation of Floats
Total float = Latest start time of the activity - Earliest start time of the
activity
Free float = Earliest start time of the next activity - Earliest finish time of the
activity
Interfering float = Total float - Free float
Independent float = Earliest start time of the next activity - Latest finish
time of the preceding activity - Duration of the activity
= Free float - Tail event slack, or zero, whichever is higher