Iom 9
Iom 9
350/54
Introduction 350/66
Pump sets supplied are mounted on a substantial fabricated The pump should be located as near the liquid source as
baseplate; the complete assembly is of a rigid construction, practical, with adequate accessibility for inspection and
being intended for mounting on suitable foundations. repair and sufficient headroom for lifting tackle if
necessary.
These pump sets are supplied fitted with a high efficiency
electric motor adequately sized for the duty specified. Where pumps are electric motor driven, power source
electrical characteristics should match those shown on
The proprietary flexible coupling has been selected to meet motor data plate. A qualified electrical contractor should be
the power transmission and other operating requirements used to make the electrical connection.
for the pump set
4.4 Foundations
X Foundation Plinth
ensure a flow velocity of 2.5 to 3 m/s is not exceeded. This
is usually one size larger than the discharge branch.
Pipework should be as short and straight as possible to
reduce friction head loss.
Foundation Plinth The suction and discharge pipe work must be independently
supported and positioned such that no excessive forces and
moments are exerted on the pump flanges.
4. Adjustment
Failure to support suction and delivery pipework may result
in distortion of the pump casing, with the possibility of For horizontal lateral adjustment move the motor using the
early pump failure. motor jacking screws provided and for vertical and angular
adjustment fit shims between the motor feet and the
4.8 Guards baseplate.
If guards have been removed to install packing or to check
mechanical seal connections, they MUST be replaced to Note: Poor alignment is a major factor contributing to
maintain safe operation of the pump. shortening of pump bearing and seal life. It is
recommended that alignment is checked frequently and
4.9 Coupling Alignment maintained at below 10% of the manufacturer's specified
To minimise the bearing loading and to achieve full figure or 0.1mm.
coupling and bearing life, it is recommended that the shafts
(1800001) are aligned as accurately as possible i.e. well As the pump and motor feet are accurately machined, any
below the allowable misalignment of the coupling. discrepancy may be due to foreign matter between any of
the mating faces. These should be checked for cleanliness
Refer to the coupling manufacturer's instructions or proceed before assembly and before resorting to using shims under
generally thus: the motor feet.
Hazardous Materials
b) Noise:
Wear a suitable mask or respirator when
Listen for any unusual noise or an increase in normal sound
working with packing or gasket components that
level.
contain fibrous material, as these can be
hazardous when the fibrous dust is inhaled. Be
This may result from:
cautious if other supplier's components have been substituted
i) Loose fasteners for guards and other equipment.
for genuine KBL parts as these may then contain hazardous
ii) Air trapped in the pump i.e. the pump was not fully materials.
primed.
iii) Cavitation. Hazardous Gases, Mists, Sprays and Leaks
iv) Small solids in the liquid. Be aware of the hazards relating to the pumped
fluid, especially the danger from inhalation of
c) Suction Gauge Reading: toxic gases, skin and eye contact or penetration.
If this is lower than normal, investigate and check that Obtain and understand the hazardous substance (COSHH)
valves in the suction pipework are fully open or that the data sheets relating to the pumped fluid and note the
suction lift may have increased. recommended emergency and first aid procedures.
Check rotating element for wear. Where a soft packed gland seal is fitted, it will be necessary
Checks wear ring clearances. to replace the packing rings periodically when the gland can
EVERY
no longer be tightened to reduce leakage to the normal level,
YEAR Clean and regrease bearings.
or if the gland is overheating.
Measure total suction and discharge
Head as a test of pipe connection
Packing Removal Procedure
Packing Preparation 9. Cut each ring from the spiral at an angle of 45° diagonally
across the guidelines.
Champion Style (3116 or EQ.), Graphite cotton greasy packing
is used in the standard supply. However packing suitable for Repacking Procedure
liquid handled is also supplied against specific requirement.
If the packing is to be cut from a coil or long length the size, 10. Insert the first ring and tap it to the bottom of the stuffing box.
number of rings and length is thus: Each following ring should be installed in the same manner
and positioned in the stuffing box so that the 'split' is advanced
Gland packings are fitted with Impeller side 2 + L + 4 Gland 120°.
side (arrangement for 1E, 2E & 3E module pumps) & With
Impeller side 2+L+2+L+1 Gland side (Arrangement for 2-Stage 11. Install the lantern ring(s) in the proper position(s) to align with
module pumps) L = Lantern Ring. the seal lubrication connection(s), allowing for movement of
the ring deeper into the box as the packing is compressed.
Stuffing Box Data
PACKING SIZE NO. OF
SLEEVE SIZE of 12. When all the rings have been inserted, the last packing ring
PUMP SHAFT SQUARE LENGTH RINGS
DIA. RING ID/OD should not protrude from the stuffing box face.
MODULE SECTION of ONE PER
mm mm / mm
mm RING mm BOX
1E 100 12 355 100/125 6 13. Slide the gland into the stuffing box and ensure that it sits
2E 120 12 415 120/144 6
squarely against the last packing ring. Fit the gland plate and
3E 140 15 490 140/170 6
1 50/48-2 85 12 310 85/109 5 the gland retaining nuts on the studs and tighten evenly to
200/58-2 120 12 415 120/144 5 finger pressure.
14. Start the pump as per point 5.2, allow pressure to increase to
7. Wrap the packing around a dummy shaft, of the same normal level and ensure that air is not trapped in the pump
diameter as the sleeve casing.
15. A soft packed gland must have slight steady leakage, and this
should start soon after the pump reaches its normal operating
pressure.
16. If gland leakage stops, the pump will overheat leading to seal
damage or premature pump failure. If overheating is detected,
8. To assist in cutting rings, two guide lines parallel to the shaft the pump must be stopped and allowed to cool and when
axis and separated by a distance equal to the packing section restarted, gland leakage should start.
may be drawn on the spiral.
17. If the pump overheats again, stop the pump restart it again, do
not slacken the gland retaining nuts.
7. DO NOT SPIN A CLEAN DRY BEARING. 20. Secure bearing housing (2400001) to the upper half casing
(1220001) & lower half casing (1230001) & insert
8. Inspect the bearing for wear, fractures, cracks, corrosion or (9790001).
other damage, which may necessitate replacement.
21. Fit the new v-ring on the shaft (1800001) to abut against the
9. Lightly oil the bearing and wrap in greaseproof paper to bearing housing (2400001).
prevent contamination before reassembly.
22. Where applicable refit and set the mechanical seal.
10. Check that the shaft (1800001), bearing cover and housing are
clean and undamaged.
Non-Drive End Bearing Replacement Procedure
11. It is recommended that new v-rings are fitted when bearings are
replaced to ensure that contamination is prevented. 1. Proceed as per the drive end bearing replacement procedure,
paragraphs 1and 2.
12. Slide the v-ring onto the shaft (1800001) wipe the seal recess in
the bearing cover with grease and set in position on the shaft 2. Remove the bearing cover (2700001) from the non-drive end
(1800001) against the bearing cover (2710001). bearing housing (2400001) and using a suitable puller,
withdraw the bearing housing (2400001) from the shaft
13. Heat the bearing (2600001) to approximately 100 °C (230 °F) (1800001).
using bearing hotplate, induction heater or oven. NOTE - Do
not exceed 120 °C (248 °F). 3. Using a suitable punch, flatten the lock washer and remove
the bearing locknut (3360001) and the lock washer.
14. Slide the heated bearing onto the shaft (1800001) to abut the
shoulder. Ensure that the bearing sits fully and squarely against 4. Replace the non-drive end bearing and as per the drive end
the shoulder. bearing replacement procedure, paragraphs 4 to 16.
15. Cool the bearing to room temperature and pack both sides with 5. Place the locking washer onto the shaft (1800001) and screw
two/three ounces of recommended grease. on the bearing lock nut (3360001).
16. Coat the inside of the bearing housing (2400001) with grease 6. Fit and tighten the bearing locknut to 300 Nm and lift the tab
and slide into place over the bearings. of the lock washer.
17. If necessary use two screwed rods to pull the bearing housing 7. Fit the bearing housing (2400001) as per the drive end
(2400001) towards the bearing cover then fit four of the screws bearing replacement procedure, paragraphs 17 to 20.
& tighten evenly to pull the bearing housings (2400001) into
place, fit and tighten the remaining screws. 8. Refit the bearing cover (2700001).
2 Remove the seal lubrication pipes from the inserts for soft For pumps fitted with mechanical seals, refer to the seal
packed pumps or from the mechanical seal. manufacturer's instructions and lock the seal before
removing the retaining screws and sliding the seals back
3 Remove the screws that retain the bearing housings (2400001) from the face of the insert (9790001).
to the lower half casing (1230001).
Provide a suitable lifting strap and support the weight of the
4 Remove the nuts from the casing studs securing the upper half rotating assembly thus:
casing (1220001) to the lower half casing (1230001).
1. Remove the remaining screws that retain the bearing housings 7. Release the screws and remove the liquid deflectors from
(2400001) to the lower half casing (1230001). the shaft (1800001).
2. Tap the inserts with a soft-faced hammer to break the seal 8. For pumps fitted with mechanical seals: Slide the
between the insert and the lower half casing (1230001). mechanical seal assemblies off the shaft (1800001), remove
the inserts and set aside for inspection.
3. Lift the rotating assembly clear of the lower half casing
(1230001) and support the shaft (1800001) on suitable V 9. For pumps fitted with soft packed glands: Remove the
blocks. glands from the shaft (1800001) and remove the inserts
complete with packing rings and lantern rings and set aside
4. If necessary, remove the casing wear ring dowels from the for inspection.
lower half casing (1230001).
10. If not already removed, remove the casing wear rings and
5. With feeler gauges, check the clearance between the casing set aside for inspection and measurement.
wear rings and the impeller (1590001). The Diametrical
clearances between Impeller (1590001) and casing rings For Clockwise pump construction:
(1900001) should be
11. Using a suitable 'C' spanner, unscrew and remove the
Minimum: 0.690 mm and maximum 0.939 mm (for special non-drive end sleeve and go to step 13.
material)
For Counter Clockwise pump construction:
Minimum: 0.440 mm and maximum 0.689 mm (for C.I/non
ferrous material) 12. Using a suitable 'C' spanner, unscrew and remove the drive
end sleeve.
Note: Increase in the wear ring clearance allows increased
internal leakage with resultant loss of pump performance, Note: Light tapping with a soft faced mallet may be needed to
head and efficiency. When the clearance is double the free the impeller (1590001) from the shaft (1800001), do not
original clearance, it is recommended that new wear rings are damage the impeller (1590001) if it is to be reused.
fitted. It is permissible to run the pump with increased
clearance due to wear but the loss of pump efficiency will
significantly increase the pump running costs.
1. Remove the screws and slide the bearing cover along the shaft
(1800001) towards the liquid deflector.
2. Dry the bearings with dry compressed air or with a clean soft 12. If the shaft (1800001) runs true within tolerance, remount
cloth by hand and by spinning by hand. Confirm that the the shaft (1800001) as in step 10 but with the sleeve fitted
bearings rotate smoothly without slackness. in position, and check the sleeves run-out at the packing
contact positions. Indicator readings must not vary more
3. DO NOT OVERSPIN A CLEAN DRY BEARING.
than 0.07 mm (0.003").
7. Remove all grease and other deposits from all other parts using
16. If the unit is not to be reassembled immediately, brush all
suitable cleaning fluid and a clean dry cloth.
bright iron and steel surfaces with Texaco Rust Proof
Compound L or Rust Proof Compound Spray or a suitable
8. Coat all unpainted carbon steel parts with a light smear of oil to
equivalent rust preventive fluid.
prevent rust.
17. Protect all parts (especially mechanical seal parts and faces)
9. Measure the inside diameter of the wear rings (1900001) and
against loss, weather or mechanical damage.
the outside diameter of the wear ring surfaces on the impeller
(1590001), calculate the clearance and compare these with
dimensions in Section 6.7.
3 Examine 'O' and 'V' rings and renew if showing wear, damage
or deterioration.
Pump Reassembly
For counter-clockwise rotation: 9. For soft packed pumps: Fit the packing, lantern rings and
SHAFT SLEEVE (NDE) IMPELLER KEY
glands as per instructions in section 6.2.
(LOCKING SLEEVE)
(NDE) (DE)
10. Fit the liquid deflectors on the shaft (1800001) and secure
with screws.
DIM. B
Note: The position of the impeller key (3200001) and the shaft
sleeve (Locking Sleeve) is governed by the direction of rotation
of the pump. For clockwise pumps they are fitted at the drive
end of the shaft (1800001) slot and for counter-clockwise
pumps they are at the non-drive end.
Where the location was not marked, please refer to the pump
section drawing supplied or to KBL for dimensions A or B.
2 Screw the shaft sleeve onto the shaft (1800001) to the marked
position. Turn the sleeve to the nearest slot to align with the
keyway.
16. Place the locking washer onto the shaft (1800001) and screw
on the bearing lock nut (3360001).
17. Fit and tighten the bearing locknut to 300 Nm and lift the tab
of the lock washer.
18. Cool the bearings to room temperature and pack both sides
with two/three ounces of recommended grease.
19. Coat the inside of the bearing housings (2400001) with grease
and slide into place over the bearings. If necessary use two
a) Tighten the four 'corner' screws marked 1, 2, 3 and 4.
screwed rods to pull the bearing housing towards the bearing
cover. b) Work outward along shaft (1800001) axis toward the
stuffing boxes in opposite quarters tightening screws in
20. Secure the bearing housings (2400001) to the insert
regions 5, 6, 7 and 8.
(9790001) with hex screws.
c) Work outward along the branch and in opposite quarters
21. Check and install the dowel pins in the lower half casing
tightening screws in regions 9, 10, 11 and 12.
(1230001) to locate the casing wear rings.
d) Repeat the whole sequence (a to d).
22. Place the rotating assembly into the pump casing lower half.
Correct any excessive 'O' ring twisting or buckling. Check 28. Check that the shaft (1800001) turns freely by hand.
that the impeller (1590001) is centralised in the casing and
that there are no rubs. 29. Top up the bearing lubrication by applying several strokes
with a grease gun.
23. Install casing gasket with a light coat of commercial cup
grease on both gasket surfaces. Carefully align the inner edge 30. The pump is now ready for re-coupling to the motor and
of the gasket with the insert 'O' rings. re-commissioning.
24. Lower the upper half casing into place and install casing joint
Procedure for Dismantling of rotating assembly of Two Stage
nuts. Pump
25. NOTE: When installing upper half casing, make sure that the
'O' rings are not cut or pinched and that the casing gasket is
hard against the 'O' rings.
The difference relates to the disassembly of the two 4. Slide the casing wear rings onto the impeller.
impellers and the interstage plate. Proceed to disassemble
the rotating assembly as for single stage pumps to step 10 of 5. Check that the dowels that retain the interstage plate are
'Procedure to dismantle the rotating assembly'. correctly fitted.
For Clockwise pump construction: Continue with pump re-assembly from paragraph 7.
5 Tap and pull the other impeller off the shaft (1800001) with
the impeller spacer (2010001).
1. Select the first impeller for assembly, check the impeller for
correct direction of rotation and slide onto shaft (1800001)
to abut the locked shaft sleeve.
Note: Pump construction may vary slightly between the different pump sizes within each type, it is important to refer to the specific pump
section drawing and to quote the pump serial number when ordering parts to ensure that the correct part is supplied in the original
material of construction.
Note: Pump construction may vary slightly between the different pump sizes within each type, it is important to refer to the specific pump
section drawing and to quote the pump serial number when ordering parts to ensure that the correct part is supplied in the original
material of construction.
Note: These torque figures are approximate, and for un-plated fasteners only. No allowance has been made for special finishes or lubricants, washers or
mating surfaces.
Grade Identification
*IMPORTANT: PUMP MUST BE OPERATED WITHIN THE WORKING RANGE AS SPECIFIED ON THE PERFORMANCE
CURVE.