Fuad Schedule ST
Fuad Schedule ST
Finish Apr '25 May '25 Jun '25 Jul '25 Aug '25 Sep '25 Oct '25 Nov '25
Mode 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
1 Structural Skeleton Works 219 days Mon 4/14/25 Tue 11/18/25
2 Sub-Structure 70 days Mon 4/14/25 Sun 6/22/25
3 Excavation and earth work 1 mon Mon 4/14/25 Sat 5/3/25
4 Lean concrete for pads 2 days Sun 5/4/25 Mon 5/5/25
5 Formwork for pads 1 day Sun 5/4/25 Sun 5/4/25
6 Rebar for pad and column 1 day Mon 5/5/25 Mon 5/5/25
7 Concrete for pad 1 day Tue 5/6/25 Tue 5/6/25
8 Formwork for foundation 4 days Wed 5/7/25 Sat 5/10/25
columns
9 concrete for foundation column 1 day Sun 5/11/25 Sun 5/11/25
10 Backfill around foundation 1 wk Mon 5/12/25 Fri 5/16/25
11 Masonry work along the 10 days Sat 5/17/25 Mon 5/26/25
periphery
12 Backfill under slab 5 days Thu 5/22/25 Mon 5/26/25
13 Lean concrete for grade beam 1 day Tue 5/27/25 Tue 5/27/25
14 Rebar for grade beam 10 days Wed 5/28/25 Fri 6/6/25
15 Formwork for grade beam 10 days Wed 5/28/25 Fri 6/6/25
16 Concrete for grade beam 2 days Sat 6/7/25 Sun 6/8/25
17 Hardcore and ground floor mesh 12 days Mon 6/9/25 Fri 6/20/25
18 Concrete for Ground floor slab 2 days Sat 6/21/25 Sun 6/22/25
19
20 Super Structure 149 days Mon 6/23/25 Tue 11/18/25
21 Rebar for ground floor columns 10 days Mon 6/23/25 Wed 7/2/25
29 Concrete for first floor columns 3 days Thu 8/21/25 Sat 8/23/25
30 Formwork for second floor slab 20 days Sun 8/24/25 Fri 9/12/25
and beam
31 Rebar for second floor slab and 10 days Sat 9/13/25 Mon 9/22/25
beam
Page 1
ID Task Task Name Duration Start Finish Apr '25 May '25 Jun '25 Jul '25 Aug '25 Sep '25 Oct '25 Nov '25
Mode 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
32 Concrete for second floor slab 2 days Tue 9/23/25 Wed 9/24/25
and beam
33 Rebar for second floor columns 10 days Thu 9/25/25 Sat 10/4/25
Page 2