Fuad Schedule ST

The document outlines a construction schedule for a project named 'Fuad Schedule ST' spanning from April 14, 2025, to November 18, 2025. It details various tasks involved in the structural and superstructure works, including excavation, concrete pouring, and rebar installation, along with their respective durations and timelines. The schedule includes a total of 40 tasks, with specific start and finish dates for each phase of construction.

Uploaded by

Surafel Wondu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
21 views2 pages

Fuad Schedule ST

The document outlines a construction schedule for a project named 'Fuad Schedule ST' spanning from April 14, 2025, to November 18, 2025. It details various tasks involved in the structural and superstructure works, including excavation, concrete pouring, and rebar installation, along with their respective durations and timelines. The schedule includes a total of 40 tasks, with specific start and finish dates for each phase of construction.

Uploaded by

Surafel Wondu
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

ID Task Task Name Duration Start Finish Apr '25 May '25 Jun '25 Jul '25 Aug

Finish Apr '25 May '25 Jun '25 Jul '25 Aug '25 Sep '25 Oct '25 Nov '25
Mode 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
1 Structural Skeleton Works 219 days Mon 4/14/25 Tue 11/18/25
2 Sub-Structure 70 days Mon 4/14/25 Sun 6/22/25
3 Excavation and earth work 1 mon Mon 4/14/25 Sat 5/3/25
4 Lean concrete for pads 2 days Sun 5/4/25 Mon 5/5/25
5 Formwork for pads 1 day Sun 5/4/25 Sun 5/4/25
6 Rebar for pad and column 1 day Mon 5/5/25 Mon 5/5/25
7 Concrete for pad 1 day Tue 5/6/25 Tue 5/6/25
8 Formwork for foundation 4 days Wed 5/7/25 Sat 5/10/25
columns
9 concrete for foundation column 1 day Sun 5/11/25 Sun 5/11/25
10 Backfill around foundation 1 wk Mon 5/12/25 Fri 5/16/25
11 Masonry work along the 10 days Sat 5/17/25 Mon 5/26/25
periphery
12 Backfill under slab 5 days Thu 5/22/25 Mon 5/26/25
13 Lean concrete for grade beam 1 day Tue 5/27/25 Tue 5/27/25
14 Rebar for grade beam 10 days Wed 5/28/25 Fri 6/6/25
15 Formwork for grade beam 10 days Wed 5/28/25 Fri 6/6/25
16 Concrete for grade beam 2 days Sat 6/7/25 Sun 6/8/25
17 Hardcore and ground floor mesh 12 days Mon 6/9/25 Fri 6/20/25
18 Concrete for Ground floor slab 2 days Sat 6/21/25 Sun 6/22/25
19
20 Super Structure 149 days Mon 6/23/25 Tue 11/18/25
21 Rebar for ground floor columns 10 days Mon 6/23/25 Wed 7/2/25

22 Formwork for ground floor 4 days Sun 6/29/25 Wed 7/2/25


columns
23 Concrete for ground floor 3 days Mon 7/7/25 Wed 7/9/25
columns
24 Formwork for first floor slab and 20 days Thu 7/10/25 Tue 7/29/25
beam
25 Rebar for first floor slab and 10 days Wed 7/30/25 Fri 8/8/25
beam
26 Concrete for first floor slab and 2 days Sat 8/9/25 Sun 8/10/25
beam
27 Rebar for first floor columns 10 days Mon 8/11/25 Wed 8/20/25
28 formwork for first floor columns 4 days Sun 8/17/25 Wed 8/20/25

29 Concrete for first floor columns 3 days Thu 8/21/25 Sat 8/23/25

30 Formwork for second floor slab 20 days Sun 8/24/25 Fri 9/12/25
and beam
31 Rebar for second floor slab and 10 days Sat 9/13/25 Mon 9/22/25
beam

Task Project Summary Manual Task Start-only Deadline

Project: Fuad Schedule ST Split Inactive Task Duration-only Finish-only Progress


Date: Tue 5/13/25 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone

Page 1
ID Task Task Name Duration Start Finish Apr '25 May '25 Jun '25 Jul '25 Aug '25 Sep '25 Oct '25 Nov '25
Mode 31 7 14 21 28 5 12 19 26 2 9 16 23 30 7 14 21 28 4 11 18 25 1 8 15 22 29 6 13 20 27 3 10 17 24
32 Concrete for second floor slab 2 days Tue 9/23/25 Wed 9/24/25
and beam
33 Rebar for second floor columns 10 days Thu 9/25/25 Sat 10/4/25

34 Formwork for second floor 4 days Wed 10/1/25 Sat 10/4/25


columns
35 Concrete for second floor slab 3 days Sun 10/5/25 Tue 10/7/25
and columns
36 Formwork for Top-beam and 12 days Wed 10/8/25 Sun 10/19/25
gutter
37 Rebar work for top-beam 7 days Mon 10/13/25 Sun 10/19/25
38 concrete for top beam 3 days Mon 10/20/25 Wed 10/22/25
39 Roof truss joinery works 15 days Thu 10/23/25 Thu 11/6/25
40 Roof sheeting and gutter and 12 days Fri 11/7/25 Tue 11/18/25
downpipe installations

Task Project Summary Manual Task Start-only Deadline

Project: Fuad Schedule ST Split Inactive Task Duration-only Finish-only Progress


Date: Tue 5/13/25 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone