Mth601 Solution
Mth601 Solution
Assignment no #1 solution
Question no 1
Solution:
Stepl: List Activities with Duration
Activity Duration
1
1—2
2—3 4
2—4 5
3—5 3
4—5 1 .5
5—7 2.5
3—6 1 .5
6—7 1
4—6
35
7--8 4
Step 2:
Forward pass (Earliest times)
Earliest finish at node 8 = 14.5
Step3:
Backward pass(Latest times )
Latest finish at node 8 =14.5
Critical path:
Solution:
Network Diagram:
Variance(c2)
STEM: Calculate Expected for each activity
Activity Expected Variance Standard
time Deviation
A 3 0 0
B 6 1 1
C 4 0.44 0.67
D 6 0 44 0_67
E 6 0.44 0_67
F 0 0 0
G 4 0.11 0.33
H 5 1 1
Path3: 2
Question 3:
Solution:
Given
Demand Rate(D)=25 unit/month
Setup cost (SF Rs 15 per order
Production cost =Rs1 per item
HGlding cost = Rs 0.30 per unit per month
q• 45.63
1.83 months
3 Optimum shortage (S) The maximum
inventory level (l*) is :