Psa - 2
Psa - 2
Power System
Analysis – 2
(21EE62)
The connection of a network topology shown by replacing all physical element by lines is called
a graph. A graph in which a direction is assigned to each branch is called an oriented graph.
ii. Basic loops
when link is added to a tree it forms a loop. A loop containing only one link and remaining twigs
is called a basic loop or fundamental loop.
iii. Tree
Tree is a connected sub graph containing all the nodes of the graph G. but without any closed
loops. The number of tree-branches is given by t = n - 1
iv. Co-tree
The set of branches of the original graph G. not included in the tree is called co-tree.
Power System Analysis - 2 3
v. Basic cut-sets.
Cut set which contain only one twig and remaining links are called basic cut set or fundamental
cut set or f-cut sets. They are defined for a particular tree and are equal in numbers to the number
of twigs.
2. Define primitive network and explain its two forms with neat representation circuit. Also derive
their respective performance equations.
A primitive network is a fundamental element which in not connected to any other element. A set of
such unconnected elements is defined as a primitive network.
General primitive element
Can be written as
3. With usual notations, prove that YBUS = AT [Y] A using singular transformation.
…(1)
5. A power system consists of four buses. The generators are connected at buses 1 and 3. The
transmission lines are connected between buses 1-2, 1-4, 2-3 and 3-4 which have reactances of
j0.25, j0.5, j0.4 and j0.1 respectively. Develop a bus admittance matrix by direct inspection
method. Choose bus 1 as reference.
7. Consider an oriented graph of the power system shown below in Fig Q2(c). Choose branches 1, 3
and 5 as twigs to form a tree. Build a basic loop incidence matrix C for the given oriented graph.
Select node 2 as reference.
2) The mechanical power input and the rating of the generator pose a limitation on active power
generation.
3) Limitation of the generator field excitation constrains the reactive power generation.
……(1)
……(2)
Separating real and imaginary parts in (2), we obtain
5. What are the different types of buses considered during load flow analysis? Explain briefly
Ɛ = tolerance value
6) Compute slack bus power.
9) Go to step 4 and iterate till the power mismatches are less than tolerance value.
3. Stating all assumptions, deduce fast Decoupled load flow (FDLF) model. Explain the step-by-step
procedure for load flow solution using FDLF method.
From decoupled load flow we got
where, Bij’ and Bij’’ are negative of the susceptance’s of respective elements of the bus admittance
matrix. Divide by |Vi| and assume |Vj| ~_ 1pu, we get
7) Update δi and Vi
8) Go to step 4 and iterate power residue is less than tolerance value.
4. Draw a flow chart for Fast Decoupled Load Flow (FDLF) method.
Elements of J1
Diagonal element
Elements of J3
Diagonal element
Elements of J2
Diagonal element
Elements of J4
Diagonal element
6. Derive the expressions for diagonal elements of Jacobian matrices in NR method of load flow
analysis.
Refer q no. 5
7. Compare Gauss - Seidal, Newton Raphson and Fast decoupled load flow method of load flow
solution with respect to various parameters.
Sl.no G.S method N.R method FDLF method
1. Require large number of Require a smaller number of Require a greater number of
iterations to reach iterations to reach iterations than N.R method
convergence convergence.
2. Computation time per Computation time per iteration Computation time per
iteration is less is more iteration is less
3. It has linear convergence It has quadratic convergence It has geometric convergence
characteristics characteristics characteristic
4. It has quadratic convergence The number of iterations is The number of iterations is
characteristics independent of the size of the does not dependent of the size
system of the system
5. Less memory requirements More memory requirements. Less memory requirements
than N.R.method.
6. Works well with rectangular Polar co-ordinates are Polar co-ordinates.
co-ordinates preferred
7. Less accurate More accurate Moderate
This is the fundamental curve for a thermal plant and it is a plot of the input in British thermal units/hr
v/s power output plant in MW.
ii) Hear rate curve
Incremental cost is the produced of incremental fuel rate and fuel cost Rs/Rtu. Unit of the incremental
fuel cost is Rs/Mwh.
iv) Incremental cost curve.
Generation of G3 may be more than G1 and G3. The transfer of power from G1 and G2 to load is
limited by the transmission network. Hence G3 even it is more expensive is committed.
Where,
Fcost (K,I) = least total cost to arrive at state (K,I)
Pcost (K,I) = Production cost for state (K,I)
Scost (K-1, L : K,I) = Transition cost from state (K-1,L) to state (K,I)
State (K,I) is the Cth combination in hour k. For the forward DP approach, we define a strategy as the
transition or path, from one state at a given hour to a state at the next hour.
For flow chart q no. 2
7. Derive an expression for transmission loss as a function of plant generation for a two-plant
system.
(or)
Deduce the condition for optimal load dispatch considering transmission losses in a system.
When transmission distances are large, the transmission losses are a significant part of the generation
and have to be considered in the generation schedule for economic operation. The mathematical
formulation is now stated as
Assume that the total load is supplied by only generator 1. As shown below.
Let current through Kth branch in the network be Ik1. Let us define current distribution factor
By principle of superposition
Step 1: obtain prefault voltage at all buses and current in all lines through a load flow study.
Let prefault bus voltage vector be
Assume that rth bus is faulted through a fault impedance zth. The post fault bus voltage vector will be
given by
A fictitious node ‘լ’ is introduced the source eլ is between buses լ and q. eլ is so chosen that the current
ipq = 0, so that the element P – լ can be treated as a branch. The performance equation given by.
Case 1: If there is no mutual coupling between the added element and elements of the partial network.
Case 2: If there is no mutual coupling and P is the reference node Zpi = Zpl = 0.
3. Build an algorithm for numerical solution of swing equation by Runge - Kutta method.
In Runge-Kutta method, the changes in dependent variables are calculated from a given s formulae,
derived by using an approximation, to replace a truncated Taylor's series expansion formulae for the
Runge-Kutta fourth order approximation, for solution of two simultaneous d ential equations are given
below:
The solution of δ(t) is obtained in discrete intervals of time, with a uniform interval of At. Discretization
is done as follows:
1) The acceleration calculated at the beginning of an interval is assumed to remain constant from the
middle of the preceding interval to the middle of the interval being considered. This assumption
also implies that the accelerating power Pa computed at the beginning of an interval is assumed
constant from the middle of the preceding interval to the middle of the interval being considered.
2) The speed derivation Ꙍ=dδ/dt is assumed constant over the entire interval computed at the middle
of the interval. Note that here w is the speed above the synchronous speed, Ꙍs.
Where,
From our assumption, the speed is constant throughout the nth interval. The change in angular
position during the nth interval is,
The process is repeated to obtain Pa(n), δn-1 and δn+1. Greater accuracy can be obtained by
considering smaller time intervals.
5. A 20MVA, 50Hz generator delivers 18MW over a double circuit line to an infinite bus. The
generator has kinetic energy of 2.52MJ/MVA at rated speed. The generator has a transient
reactance of 0.35pu. Each transmission line has a reactance of 0.2pu on a 20MVA base. The
generator excitation voltage |E'| = 1.1pu and infinite bus voltage V = 1∟0° pu. A three-phase
short circuit occurs at the midpoint of one of the lines. Plot the swing curve with the fault cleared
by simultaneous opening of breakers at both ends of the line at 2.5 cycles after the occurrence of
fault. Take a step size of time as 0.05sec. Also, calculate the critical clearing angle. Use point by
point method.